OVERVIEW SCOPE OF WORK (SOW)

Size: px
Start display at page:

Download "OVERVIEW SCOPE OF WORK (SOW)"

Transcription

1 Site Description The subject property is occupied by the former Parker Service Station, which contained a former Service Garage (now called Former Garage) and Filling Station Store (now called Storage Building) (SMS # ) operated from the 1920 s to The property is located at 1 South Street, within the Village of Middletown Springs (Figures 1 & 2, Attachment 3 CAP CD), in a mixed residential/commercial area of the village. The former Service Garage was located west of the former Storage Building. The former Storage Building is located adjacent to the eastern border of the property (Figure 3, Attachment 3 - CAP CD). The Site encompasses approximately 0.5 ± acres, on the corner of VT Route 133/140 and South Street, within the village. Prior to the construction of the former Storage Building and Service Garage, the site contained a brick house and store constructed in the 1830 s. The house and store were destroyed by fire in the 1920 s. Following the fire, the store s basement was filled with debris, presumably the brick building material and soil fill. After the basement backfilling, a concrete slab was poured over top and the former Filling Station Store (Storage Building) was built on the slab. In 2014, the Storage Buildings stick-built building was removed, leaving the slab in-place. The slab was recently removed and staged onsite allowing for full access to the filled-in basement. An asbestos inspector has confirmed the widespread presence of loose, friable asbestos in the soils in the northern half of the basement. Additionally, chemical contaminants such as poly-chlorinated biphenyls (PCBs) and total petroleum hydrocarbons (TPH) are present in the soils in the northern half of the basement. Disposal sampling for chemical contaminants has been completed and laboratory analysis results are included. The asbestos inspector completed a site walk through with three asbestos abatement contractors. Included in this bid are the names of the three abatement contractors as well as a copy of the asbestos abatement plan. Please select one of the three abatement contractors. The choice of three was done in the interest of time, as the funding has a sunset date. Additionally, the asbestos inspector is requiring six test pits be completed in the southern half of the basement. The inspector will be onsite to observe the soils for signs of asbestos during the test pitting. If it is deemed asbestos contaminated then it can be disposed of at the same facility as the known asbestos contaminated soils in the northern half of the basement. During the test pitting, Ross Environmental Associates, Inc. (R.E.A.) will collect chemical contaminant disposal samples from the soils. The Village would like to salvage the Storage Building s field stone and granite block foundation, if possible after they are properly washed. The Former Garage is located immediately west of the former Storage Building. In 2013, approximately five cubic yards of PCB and PAH contaminated soil was removed from an area formerly containing a hydraulic lift at the Former Garage. The lift extended to approximately six feet below ground surface (bgs). Confirmatory sampling, completed after the contaminant removal, indicated the presence of PCBs on the west sidewall location, as seen on the attached CD containing the 2013 PCB soil removal report completed by Ross Environmental Associates, Inc. (R.E.A.). This RFP requires the removal of additional PCB and PAH contaminated soil from area of the former hydraulic lift with the completion of confirmatory sampling after soil removal. All contaminated soils removed from the excavation will have to be disposed of at a TSCA approved disposal facility, such as Model City in New York, per Kim Tisa, the Regional EPA PCB Coordinator. The excavation should not be backfilled until the confirmatory sampling results indicate the removal of all contaminants, rush sample analysis will be completed by R.E.A.. The project has been presented as two separate phases of work. One phase is associated with the removal, transport, disposal and confirmatory sampling of PCB and PAH contaminated soils from the area of the hydraulic lift at the Former Garage (Item #4) and the second phase consists of the removal, transport and disposal of asbestos contaminated soil and ACM which includes an asbestos contaminated boiler, safe, brake pads and gaskets at the former Storage Building (Item #5). Additional chemical contamination is present in the soil including PCBs below the TSCA Hazardous Designation of 50 ppm and TPH above the VT DEC SSV for industrial soils. CONTRACTOR can submit bids on either or both of

2 the phases. The OWNER will decide on the best fit scenarios based on responses to the Request for Proposal (RFP). Due to the close proximity of the two phases, CONTRACTORS will need to coordinate the work to be completed. All plans and scope of work (SOW) should be completed to the level requested in the approved Leggett, Brashears and Graham, Inc. (LBG) CAP in conjunction with the R.E.A. PCB removal report, which are included on a CD. The CAP requirements take precedent over the requirements included in this RFP, if different. Project Overview The funding for the proposed work is through EPA grants and requires adherence to Federal Law, which includes Davis-Bacon prevailing wages, which must be included in the bid costs. A Phase I Environmental Site Assessment (ESA) for the site was completed by LBG in July The ESA identified evidence of Recognized Environmental Conditions (RECs) at the site. The RECs included: Past use of the service garage and filling station from the 1920 s to 2004, including floor drains, use of used oil onsite and a 1920 s gasoline pump north of the Former Garage. The ESA also identified Historical RECs (HRECs), including a 1974 spill of more than 5,000-gallons of gasoline, which affected two downgradient supply wells; a 1991 underground storage tank (UST) removal, which resulted in subsurface groundwater monitoring well installation; a hydraulic lift installed in 1955 and located in the Service Garage building and two out of service 6,000-gallon USTs. The Phase I ESA then recommended a Phase II ESA to further investigate the RECs. Details of the Phase I ESA are included in Appendix 1 on the CD. A Phase II ESA was completed by LBG in April The Phase II ESA included the completion of soil borings and the installation of additional groundwater monitoring wells. Additionally, on-site building materials were analyzed for the possible presence of lead and asbestos. Subsurface conditions at the site consisted of sand and gravel layers with building rubble (brick, slate, concrete) overlaying clayey silt and glacial till. The contents of the hydraulic cylinder were found to not contain PCBs or PAHs above laboratory method detection limits, but soils in the immediate vicinity were found to contain PAHs and PCBs above the EPA Regional Screening Levels (RSLs), with one soil sample exceeding the Toxic Substance Control Act (TSCA) of 50 parts-per-million (ppm). Additionally, sediment was sampled from the floor drain system and exhibited metals and PAH concentrations above the RSL. Groundwater was sampled in the vicinity of the floor drain and hydraulic cylinder and showed metals contamination exceeding the Vermont Groundwater Enforcement Standard (VGES). Bulk sampling of potential asbestos containing material (ACM) indicated the presence of chrysotile asbestos within the former Storage Building in window glazing as well as ACM brake pads and gaskets. Composite lead samples were collected from the former Storage Building paint, which failed the toxicity characteristic leaching potential (TCLP) analysis. A copy of the Phase II ESA is included in Appendix 1 on the CD. A supplemental site investigation (SSI) was complete by LBG in the Fall 2011, based on the findings of the Phase II ESA. Grid sampling was completed in the vicinity of the former hydraulic lift to determine the degree and extent of PAH and PCB contamination. PAH and PCB contamination was identified at the bottom of the cylinder excavation from five to six feet bgs, which extended to the north and east. Additionally, lead contamination in groundwater was confirmed. A copy of the SSI is included in Appendix 1 on the CD. In August 2013, R.E.A. completed the removal of PAH and PCB contaminated soils from the immediate vicinity of the former hydraulic lift as required by and in accordance with the CAP. The soil was to have been removed from the former cylinder hole from four to six feet bgs, which amounted to approximately 2.5 cubic yards (yds 3 ) of soil. As a precaution the excavation was completed to nine feet bgs and was over excavated horizontally by one foot in all directions. Following the removal of the soil, confirmatory sampling was completed. Soil was analyzed for the possible presence of PAHs and PCBs. Soil at approximately 5.5 feet bgs on the western wall of the excavation was found to contain PCBs at 9,300 ug/kg, which is above the corresponding VT DEC SSVs, but below the TSCA hazardous designation;

3 however, the soil is still under the TSCA non-dilution, non-contact clause and needs disposal at a TSCA approved facility, as the source was 75 ppm, which is above the TSCA Hazardous designation of 50 ppm. Additionally, the laboratory method detection limit was above the SSV for the PAH benzo(a)pyrene; therefore, the results for benzo(a)pyrene were inconclusive at that time. A copy of the LBG CAP and the R.E.A. PAH and PCB removal report have been provided on the CD and are referenced within this Request for Proposals (RFP). The CAP and R.E.A. report outline several Recognized Environmental Concerns (REC s) to be addressed. Residual PCB and PAH contaminated soils exist on-site in the vicinity of the former hydraulic lift, above the VT DEC SSV industrial cleanup criteria. Asbestos contaminated soil and asbestos containing material (furnace, safe, brake pads, gaskets) are present in the basement of the former Storage Building. Additional contaminants, such as PCBs and TPH are also present in the backfilled soils contained within the Service Garage basement. General & Site Work Requirements CONTRACTOR will adhere to all General Requirements, which includes submittals, Health & Safety Plan (HASP) and Soil Management Plans (Attachment 1, CAP) and the included asbestos abatement plan. CONTRACTOR will adhere to all Site Work requirements, which includes Proper Handling, Transportation and Off-site Disposal of asbestos contaminated soil and ACM; Proper Handling, Transportation and Off-Site Disposal of Excavated Material. The contaminated soil, ACM and debris services to be performed by the CONTRACTOR shall be as follows: 1. Mobilization / Demobilization CONTRACTOR shall mobilize and demobilize all equipment, materials, and personnel necessary to perform the SOW to the Site. All workers must have OSHA 40-hour HAZWOPER training/or be a licensed asbestos abatement contractor, and updated 8-hour refresher certification. CONTRACTOR shall ensure that only certified and licensed personnel complete asbestos related work (Attachment 3, CAP). R.E.A. will inform CONTRACTOR of environmental conditions at the Site, where known, and provide available chemical data for informational purposes (Appendix 1 & 2, CAP), but CONTRACTOR is responsible for preparing their own Health and Safety Plan (HASP) for use at the Site. Prior to commencing work, CONTRACTOR shall furnish R.E.A. with appropriate HAZWOPER and asbestos certification documentation for their employees, and provide a copy of their HASP. CONTRACTOR should assume at least one representative from R.E.A. will be on-site to independently document soil, debris and furnace removal procedures. CONTRACTOR will mark out subsurface utilities prior to commencing work, and will coordinate with DIGSAFE. 2. Dust, Erosion Prevention & Sediment Control CONTRACTOR will be responsible for temporary erosion control measures for the full construction period, to ensure that nearby contaminant free solids and waters are not affected by the completion of the work. Prior to the start of each section of the work, the CONTRACTOR shall ensure that appropriate silt fences and erosion controls are installed in the vicinity. Erosion control requirements are set forth in Figures C-1, C-2 & C-3 in the CAP and must be adhered to. Additionally, all asbestos contaminated soils shall be wetted prior to removal to ensure that asbestos fibers do not become airborne and pose a risk to nearby persons. 3. Disposal & Confirmatory Sampling & Analysis R.E.A. will be responsible for the collection and analysis of appropriate disposal and confirmatory samples from PCB and PAH contaminated soils from the area of the former Service Garage, and

4 PCB, PAH, TPH and VOC contaminated soil and debris from the former Storage Building. A town provided asbestos inspector will complete confirmatory sampling in accordance with regulations related to asbestos containing material. All excavations are to remain open until the results of the confirmatory sampling are received. Additional soil removal may be necessary, based on the confirmatory sampling analysis results. R.E.A. will complete all confirmatory sampling on a rush analysis basis, to ensure the project is completed in time. 4. Former Garage (Exhibit A) PCB and PAH contaminated soils exists in the immediate vicinity of a former hydraulic lift located beneath the former Service Station (Figure 3, Attachment 3, CAP). Prior to the commencement of the soil removal work, CONTRACTOR shall install appropriate erosion control measures, such as silt fences and sediment controls, to safeguard nearby clean surface soils and vegetation. CONTRACTOR can use PCB and PAH laboratory analysis results from the LB&G CAP for disposal. The CONTRACTOR shall dispose of the soils as a hazardous PCB (greater than 50 ppm), based on the original source (former hydraulic cylinder) at an approved TSCA facility, such as Model City in New York. The CONTRACTOR shall over excavate the area of the previous (29 August 2013) PCB and PAH contaminated soil removal at the former hydraulic lift location (R.E.A. Report, CD). The R.E.A. excavation was 5 x5 x9. Residual PCB contamination was detected in the western sidewall at approximately 5.5 feet bgs during confirmatory sampling completed by LGB after soil removal. Based on the Phase II ESA, the Supplemental Site Investigation and the CAP, all completed by LBG, the CONTRACTOR shall further excavate soils by a minimum of three feet horizontally on the western sidewall from five feet bgs to ten feet bgs, and the CONTRACTOR shall further excavate soils on the north, south and eastern sidewalls by a minimum of one foot from five feet bgs to ten feet bgs. Soils from the 2013 backfilling, within two feet eastward of the western sidewall, shall be removed and disposed of as hazardous PCB soils. The sum total of soil is expected to be removed is approximately 10 cubic yards. Following soil removal, R.E.A. shall collect one PCB and one benzo(a)pyrene sample from the western sidewall at approximately 5.5 feet bgs, and PAH samples for benzo(a)pyrene from the excavation bottom at ten feet bgs and from the three remaining sidewalls at approximately 5.5 feet bgs. The CONTRACTOR shall leave the excavation open until receipt of the laboratory analysis, which must show that contaminant concentrations are below the industrial concentration for PCBs and benzo(a)pyrene in the VT DEC SSV table. The contractor shall build a temporary OSHA approved fence around the open excavation during the wait for laboratory analysis results. Following confirmation of SSV requirements the CONTRACTOR shall backfill the excavation with clean fill and remove the fence. 5. Former Storage Building (Exhibit B) The basement of the former Storage Building was backfilled in the 1920 s, after the former store and house above burnt down. Based on available information, the store s basement was backfilled with debris from the buildings (bricks, wood, etc.) and fill. It is unknown the size of the basement that was backfilled. After the backfilling, a concrete pad was constructed over top (and may have extended beyond the basement) and a service garage was built on the slab. Based on available information, the building was used to repair vehicles and eventually for storage. The northern half of the area beneath the removed slab, contains obvious debris and asbestos. However, the southern half of the area beneath the slab contains no visible surface debris and may have had minimal fill placed over to create and even grade. The original stacked stone and granite block basement walls were part of the footer walls, which the Town of Middletown Springs would like to retain for future use, if possible. The CONTRACTOR shall stockpile field stone and granite blocks onsite after they have been washed for asbestos fibers. Based on a recent asbestos inspector site visit, the northern half of the basement contains loose friable asbestos contaminated soil and ACM including an old furnace, safe, brake pads and gaskets.

5 Additionally, the northern basement soils contain PCB Aroclors (1254 and 1260) above the VT DEC SSV for industrial soil, but below the TSCA hazardous designation of 50 ppm, and total petroleum hydrocarbons (TPH) in excess of the VT DEC industrial SSV of 1,000 mg/kg. The CONTRACTOR will dispose of the soils at a facility approved for both asbestos and chemical contaminant disposal. A copy of the laboratory analysis report is attached. The contractor shall wash debris for asbestos fibers in the excavation and separate out for landfill disposal. All chemical disposal and confirmatory sampling will be completed by R.E.A. The disposal samples will be analyzed on a normal time frame and confirmatory samples will be analyzed on a rush basis. The CONTRACTOR will leave the excavation open until the confirmatory sampling results are received and approval for backfilling is given by R.E.A. If the confirmatory sampling results indicate residual contamination remains, then the CONTRACTOR will be required to remove additional soils for transport and disposal. If a concrete slab is present at the bottom of the northern half of the basement then the slab will be tested for asbestos and chemical contamination. The outcome of the sampling will determine the fate of the concrete. If clean it may remain in the ground, but the town will make this decision. The CONTRACTOR shall excavate six test pits in the southern half of the former basement to eight feet bgs. An asbestos inspector will be onsite to determine if asbestos or ACM are present in the soils. R.E.A. will collect chemical disposal soil samples from the test pits to determine if the soil will require removal and off-site disposal or if it is clean and can stay in place. A limited portion of surface soils in the southwestern portion of the southern half of the former basement has TPH contamination above the VT DEC Industrial SSV. It is recommended that this soil be disposed of along with soils from the northern half of the basement. If the asbestos contractor or test pit disposal sampling determines that contamination exists, then the CONTRACTOR shall arrange for excavation, transport and disposal of the soils at the appropriate disposal facility. The CONTRACTOR shall complete the additional excavation, transport and disposal at the same cost presented on Exhibit B (2.0). Based on the dimensions of the basement, up to 463 cubic yards (yds 3 ) of contaminated soil/debris may need disposal by the CONTRACTOR. It is assumed that the excavation depth will be eight feet bgs, which is the likely basement depth below grade. The CONTRACTOR shall arrange to have the asbestos contaminated soil, ACMs including an old furnace, safe, brake pads and gaskets and PCB and TPH contaminated soils removed and disposed of by a qualified and certified asbestos contractor at an approved facility. The asbestos contractor shall comply with all State and Federal asbestos requirements included in abatement plan. Following soil and debris removal, the owner representative will collect confirmatory sampling from the sidewalls and bottom of the excavation. The CONTRACTOR shall to leave the excavation open until the sample results are received and approval is given by R.E.A. for backfilling.

Remediation Approach. W-3839 July 6, 2009

Remediation Approach. W-3839 July 6, 2009 W-3839 July 6, 2009 Scott Alfonse City of New Bedford Department of Environmental Stewardship 133 William Street, Room 304 New Bedford, MA 02740 Re: Opinion of Probable Remediation Costs Former Polymerine

More information

Memorandum. Rian Amiton; City of Brockton Planning Department. John McRobbie and Thomas Biolsi; TRC Environmental Corporation

Memorandum. Rian Amiton; City of Brockton Planning Department. John McRobbie and Thomas Biolsi; TRC Environmental Corporation TRC Wannalancit Mills 650 Suffolk Street Lowell, Massachusetts 01854 Main 978.970.5600 Fax 978.453.1995 Memorandum To: From: Subject: Rian Amiton; City of Brockton Planning Department John McRobbie and

More information

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location Maryland Department of the Environment Site Location FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) This 2.4581-acres site (Site) consists of four parcels of

More information

EXECUTIVE SUMMARY. The following is our conclusions of the environmental issues at the Site based on our investigations:

EXECUTIVE SUMMARY. The following is our conclusions of the environmental issues at the Site based on our investigations: EXECUTIVE SUMMARY Engineers, Inc. (), on behalf of the Town of East Lyme, Connecticut performed a Phase II Environmental Site Assessment (Phase II ESA) on the property located at 224 Main Street (the Site

More information

FOR THE HARPER-THIEL SITE 3201 MILLER ROAD WILMINGTON, DELAWARE

FOR THE HARPER-THIEL SITE 3201 MILLER ROAD WILMINGTON, DELAWARE DRAFT ANALYSIS OF BROWNFIELDS CLEANUP ALTERNATIVES FOR THE HARPER-THIEL SITE 3201 MILLER ROAD WILMINGTON, DELAWARE The objective of performing a remedial action is to reduce risk associated with contaminants

More information

New York State Department of Environmental Conservation August Receive Site Fact Sheets by . See "For More Information" to Learn How.

New York State Department of Environmental Conservation August Receive Site Fact Sheets by  . See For More Information to Learn How. New York State Department of Environmental Conservation August 2013 FACT SHEET Environmental Restoration Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: 1201

More information

Mill Street Corridor Assessment/Cleanup Overview

Mill Street Corridor Assessment/Cleanup Overview Mill Street Corridor Assessment/Cleanup Overview Former S. Bent Mill Site Site History Overview Circa 1867 to 1992 - S. Bent Mill Company (furniture manufacturing) Circa early 1900s - expansion of the

More information

Updated/Draft Analysis of Brownfields Cleanup Alternatives Former Birdseye

Updated/Draft Analysis of Brownfields Cleanup Alternatives Former Birdseye November 2, 2017 Mr. Dennis Marker City of Caribou 25 High Street Caribou, Maine 04736 RE: Plant Updated/Draft Analysis of Brownfields Cleanup Alternatives Former Birdseye 27 Birdseye Avenue, Caribou,

More information

SOIL MANAGEMENT PLAN

SOIL MANAGEMENT PLAN SOIL MANAGEMENT PLAN BELFAST BOATYARD 39 & 41 FRONT STREET BELFAST, MAINE Prepared by: Ransom Consulting, Inc. 400 Commercial Street, Suite 404 Portland, Maine 04101 (207) 772-2891 March 22, 2013 1.0 INTRODUCTION

More information

Phase II/III Environmental Site Assessments

Phase II/III Environmental Site Assessments Draft Analysis of Brownfields Cleanup Alternatives Remediation of Contaminated Former Drycleaning and Dye Works 69 East Main Street, Meriden, CT 06450 Prepared by the City of Meriden I. Introduction &

More information

REQUEST FOR PROPOSAL DEMOLITION & REMOVAL OF THE OLD TOWN HALL 2278 US ROUTE 4 EAST

REQUEST FOR PROPOSAL DEMOLITION & REMOVAL OF THE OLD TOWN HALL 2278 US ROUTE 4 EAST REQUEST FOR PROPOSAL DEMOLITION & REMOVAL OF THE OLD TOWN HALL 2278 US ROUTE 4 EAST MENDON, VT 05701 TOWN OF MENDON, VERMONT August, 2018 1 1. SUMMARY AND BACKGROUND The Town of Mendon s original Town

More information

5.14 CONTAMINATED MATERIALS

5.14 CONTAMINATED MATERIALS 5.14 CONTAMINATED MATERIALS 5.14.1 Introduction Contaminated materials are toxic or potentially harmful substances that may be present in soil, groundwater, and building materials. Contaminated materials

More information

DECISION DOCUMENT. Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013

DECISION DOCUMENT. Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013 DECISION DOCUMENT Kent Avenue Station Site Voluntary Cleanup Program Brooklyn, Kings County Site No. V00732 October 2013 Prepared by Division of Environmental Remediation New York State Department of Environmental

More information

CUMBERLAND COUNTY IMPROVEMENT AUTHORITY CUMBERLAND COUNTY SOLID WASTE COMPLEX SOIL ACCEPTANCE PROTOCOL

CUMBERLAND COUNTY IMPROVEMENT AUTHORITY CUMBERLAND COUNTY SOLID WASTE COMPLEX SOIL ACCEPTANCE PROTOCOL CUMBERLAND COUNTY IMPROVEMENT AUTHORITY CUMBERLAND COUNTY SOLID WASTE COMPLEX SOIL ACCEPTANCE PROTOCOL This protocol establishes procedures to be followed by waste generators petitioning the Cumberland

More information

CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY

CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY File No. 0506-013-07 Contaminated Media Management Plan Midland

More information

PHASE II ENVIRONMENTAL ASSESSMENT REPORT. Burlington International Airport House Removals AIP 78

PHASE II ENVIRONMENTAL ASSESSMENT REPORT. Burlington International Airport House Removals AIP 78 PHASE II ENVIRONMENTAL ASSESSMENT REPORT Burlington International Airport House Removals AIP 78 110 & 120 Airport Parkway 31 Dumont Avenue 396 White Street 1375 & 1379 Airport Drive South Burlington, Vermont

More information

Silver Line Phase III Hazardous Materials Technical Appendix

Silver Line Phase III Hazardous Materials Technical Appendix Silver Line Phase III Hazardous Materials Technical Appendix Introduction This Technical Appendix contains a description of hazardous materials release locations occurring within the limits of construction

More information

D2 Project Environmental Remediation Briefing August 21, 2018

D2 Project Environmental Remediation Briefing August 21, 2018 D2 Project Environmental Remediation Briefing August 21, 2018 The Union Square Revitalization Project (USQ) is a 2.4 million square foot transit-oriented, mixed use project that is transforming Union Square,

More information

ECSI Number: Responsible Party: Klamath County. QTime Number: Entry Date: 9/22/04 (VCP)

ECSI Number: Responsible Party: Klamath County. QTime Number: Entry Date: 9/22/04 (VCP) ECSI Number: 1213 Responsible Party: Klamath County QTime Number: 37941 Entry Date: 9/22/04 (VCP) Proposed Remedial Action Staff Report - Addendum Chiloquin Forest Products Chiloquin, Klamath County, Oregon

More information

SOIL AND GROUNDWATER MANAGEMENT PLAN MAINE ENERGY RECOVERY COMPANY SITE BIDDEFORD, MAINE

SOIL AND GROUNDWATER MANAGEMENT PLAN MAINE ENERGY RECOVERY COMPANY SITE BIDDEFORD, MAINE SOIL AND GROUNDWATER MANAGEMENT PLAN MAINE ENERGY RECOVERY COMPANY SITE BIDDEFORD, MAINE MARCH 19, 2015 JN: 12-3259.1 Report Prepared by: Summit Environmental Consultants 640 Main Street Lewiston, Maine

More information

SECTION MONITORING WELL ABANDONMENT

SECTION MONITORING WELL ABANDONMENT SECTION 027300 MONITORING WELL ABANDONMENT PART I GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 1 - GENERAL REQUIREMENTS,

More information

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon Rock Fill Layer Management and Maintenance Plan 13 Highway 99 Prepared for: Half Moon LLC P.O. Box 25112 97402 PBS Project No. 51833.000 Rock Fill Layer Management and Maintenance Plan TABLE OF CONTENTS

More information

Spill Prevention Control and Countermeasures Plan Former Raytheon Facility 430 Boston Post Road Wayland, Massachusetts

Spill Prevention Control and Countermeasures Plan Former Raytheon Facility 430 Boston Post Road Wayland, Massachusetts SPCC PLAN Raytheon Company Spill Prevention Control and Countermeasures Plan Former Raytheon Facility 430 Boston Post Road Wayland, Massachusetts 6 November 2002 143.65 Environmental Resources Management

More information

COUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY NEVADA COUNTY CDA GUIDELINES FOR ASH AND BURN DEBRIS CLEAN UP AND REMOVAL AFTER A FIRE

COUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY NEVADA COUNTY CDA GUIDELINES FOR ASH AND BURN DEBRIS CLEAN UP AND REMOVAL AFTER A FIRE COUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY Environmental Health Department 950 MAIDU AVENUE, SUITE 170 NEVADA CITY, CA 95959-8617 (530) 265-1222 FAX (530) 265-9853 http://mynevadacounty.com Amy Irani,

More information

CENTENNIAL MILLS EXISTING ENVIRONMENTAL CONDITIONS Prepared by PDC 7/28/06

CENTENNIAL MILLS EXISTING ENVIRONMENTAL CONDITIONS Prepared by PDC 7/28/06 CENTENNIAL MILLS EXISTING ENVIRONMENTAL CONDITIONS Prepared by PDC 7/28/06 Background The following is a building by building (area) description of remaining or suspect environmental conditions at. Full

More information

A. Project will be constructed under a general construction contract.

A. Project will be constructed under a general construction contract. SECTION 01100 SUMMARY AND PAYMENT ITEMS 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections,

More information

Remediation Plan. for. Creek County Landfill Site. E/2 SE NW 28-18N-12E Creek County, OK

Remediation Plan. for. Creek County Landfill Site. E/2 SE NW 28-18N-12E Creek County, OK Remediation Plan for Creek County Landfill Site in E/2 SE NW 28-18N-12E Creek County, OK Draft Remediation Plan Table of Contents 1.0 GENERAL... 3 1.1 Location... 3 1.2 Site Boundaries... 3 1.3 Background...

More information

PHASE II ENVIRONMENTAL ASSESSMENT REPORT. Burlington International Airport House Removals AIP 74

PHASE II ENVIRONMENTAL ASSESSMENT REPORT. Burlington International Airport House Removals AIP 74 PHASE II ENVIRONMENTAL ASSESSMENT REPORT Burlington International Airport House Removals AIP 74 200-202 Airport Parkway 4, 6, 8, 10, 12 Picard Circle 61, 76 Dumont Avenue 400 White Street 7 Shamrock Road

More information

Project Photo Tour Updated July 15, Tom Blackman Project Lead. Gary Cambre Senior Communications Manager 1

Project Photo Tour Updated July 15, Tom Blackman Project Lead. Gary Cambre Senior Communications Manager 1 Soil Remedial Actions Planned at Middle River Complex - 2015 Project Photo Tour Updated July 15, 2015 Tom Blackman Project Lead Gary Cambre Senior Communications Manager 1 This Project is composed of:

More information

George s Used Equipment Removal Action Report Laboratory analytical results were compared to the cleanup objectives outlined in the previously approve

George s Used Equipment Removal Action Report Laboratory analytical results were compared to the cleanup objectives outlined in the previously approve July 10, 2015 Ed Olson MPCA 520 Lafayette Avenue North St. Paul, MN 55115 RE: George s Used Equipment Response Action Report UMore Park OU2 and OU3 Rosemount, MN Bay West Proposal J140651 Dear Mr. Olson:

More information

I. Introduction and Background

I. Introduction and Background M-0817 February 18, 2014 Kathy Castagna EPA New England - Region 1 5 Post Office Square, Suite 100 Mail Code (OSRR07-3) Boston, MA 02109-3912 Re: Analysis of Brownfield Cleanup Alternatives 116 Cook Avenue,

More information

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA)

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA) DRAFT Analysis of Brownfields Cleanup Alternatives (ABCA) Preliminary Evaluation Ball Square Station Site Boston Avenue and Broadway Somerville and Medford, Massachusetts Massachusetts DEP Release Tracking

More information

FINAL PLAN OF REMEDIAL ACTION

FINAL PLAN OF REMEDIAL ACTION FINAL PLAN OF REMEDIAL ACTION DELAWARE CAR COMPANY Second and Lombard Streets Wilmington, Delaware DNREC Project No. DE-1059 October 2000 Department of Natural Resources and Environmental Control Division

More information

Greene County Demolition and Clean-Up Plan for FEMA Flood Buy Out Properties NYCDEP Properties

Greene County Demolition and Clean-Up Plan for FEMA Flood Buy Out Properties NYCDEP Properties Greene County Demolition and Clean-Up Plan for FEMA Flood Buy Out Properties NYCDEP Properties This Demolition and Clean-up Plan describes the demolition and cleanup measures to be taken by the County

More information

INTRODUCTION. A. Overview. A. Scope of Work. B. Additional Requirements

INTRODUCTION. A. Overview. A. Scope of Work. B. Additional Requirements RFP 2019-01 Reeta s Building Demolition City of Morgantown REQUEST FOR PROPOSALS Demolition Contractors INTRODUCTION A. Overview This Request for Proposals ( RFP ) is being issued by the City of Morgantown

More information

FINAL PLAN OF REMEDIAL ACTION FOR THE NVF-NEWARK COMPANY SITE NEWARK, DELAWARE

FINAL PLAN OF REMEDIAL ACTION FOR THE NVF-NEWARK COMPANY SITE NEWARK, DELAWARE FINAL PLAN OF REMEDIAL ACTION FOR THE NVF-NEWARK COMPANY SITE NEWARK, DELAWARE May, 1999 DNREC Project DE-199 Prepared by: Delaware Department of Natural Resources and Environmental Control Division of

More information

Introduction to Brownfields: Site Assessment and Cleanup

Introduction to Brownfields: Site Assessment and Cleanup consulting engineers and scientists Introduction to Brownfields: Site Assessment and Cleanup Presented by: Barry Giroux, P.E., LEP, Senior Project Manager TAB Technical Assistance for Brownfields Team

More information

New York State Department of Environmental Conservation. Receive Site Fact Sheets by . See "For More Information" to Learn How.

New York State Department of Environmental Conservation. Receive Site Fact Sheets by  . See For More Information to Learn How. New York State Department of Environmental Conservation November 2013 FACT SHEET Brownfield Cleanup Program Receive Site Fact Sheets by Email. See "For More Information" to Learn How. Site Name: West 28th

More information

Demolition Information Packet

Demolition Information Packet Table of Contents I. Demolition Process Checklist II. III. IV. Approval for Demolition Demolition Permit Utility Disconnections V. Other Important Issues Asbestos and Lead VI. VII. Demolition Standards,

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

Environmental Site Assessment for Lenders April EPA All Appropriate Inquiry and. ASTM Phase I Environmental Site Assessment

Environmental Site Assessment for Lenders April EPA All Appropriate Inquiry and. ASTM Phase I Environmental Site Assessment Environmental Site Assessment for Lenders April 2017 EPA All Appropriate Inquiry and ASTM Phase I Environmental Site Assessment 1 CONTENT 1. CERCLA Liability & AAI 2. Typical Contaminants Encountered 3.

More information

Introduction to Brownfields: Site Assessment and Cleanup

Introduction to Brownfields: Site Assessment and Cleanup consulting engineers and scientists Introduction to Brownfields: Site Assessment and Cleanup Presented by: Ileen S. Gladstone, P.E., LSP, LEED AP Vice President & Senior Practice Leader TAB Technical Assistance

More information

COMMON WORK RESULTS FOR EXISTING CONDITIONS SCHEDULES FOR EXISTING CONDITIONS

COMMON WORK RESULTS FOR EXISTING CONDITIONS SCHEDULES FOR EXISTING CONDITIONS DIVISION 02 EXISTING CONDITIONS 02 01 00 MAINTENANCE OF EXISTING CONDITIONS 1. Maintenance of site remediation, underground storage tank removal, facility remediation, and hazardous waste drum handling

More information

5. Partially filled fuel tanks within the building shall be pumped empty. The oil and tanks shall be removed and deposed of in a legal manner.

5. Partially filled fuel tanks within the building shall be pumped empty. The oil and tanks shall be removed and deposed of in a legal manner. Page 1 of 1. A pre bid site walk though was held at the site, 200 West Street, Ware MA, at 2:00pm August 24, 2011. The following attended: a. Chief Thomas Coulombe Ware Fire Department b. Mr. Thomas Martens

More information

February 8, Mr. Jeff Vanderdasson, P.E. PACLAND 6400 SE Lake Road, Suite 300 Portland, Oregon 97222

February 8, Mr. Jeff Vanderdasson, P.E. PACLAND 6400 SE Lake Road, Suite 300 Portland, Oregon 97222 Mr. Jeff Vanderdasson, P.E. PACLAND 6400 SE Lake Road, Suite 300 Portland, Oregon 97222 Re: Phase I Environmental Site Assessment Recommendations Letter NW 9th Street and NW Spruce Avenue Corvallis, Benton

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

CITY OF TACOMA Department of Neighborhood and Community Services

CITY OF TACOMA Department of Neighborhood and Community Services CITY OF TACOMA Department of Neighborhood and Community Services ADDENDUM NO. 3 DATE: January 31, 2017 REVISIONS TO: Request for Bids Specification No. NC16-0353F On-Call Building Demolition NOTICE TO

More information

General Motors (Central Foundry Division) Cleanup Progress Update Massena, St. Lawrence County, NY

General Motors (Central Foundry Division) Cleanup Progress Update Massena, St. Lawrence County, NY General Motors (Central Foundry Division) Cleanup Progress Update Massena, St. Lawrence County, NY U.S. Environmental Protection Agency Spring 2016 Cleanup of GM Site Continues The cleanup of the GM site

More information

REPORT. Hendee St. Incinerator Demolition Site Plan. Prepared for Louisiana Land Trust

REPORT. Hendee St. Incinerator Demolition Site Plan. Prepared for Louisiana Land Trust REPORT Hendee St. Incinerator Demolition Site Plan Prepared for Louisiana Land Trust June 2014 Section 1 Introduction The Hendee Court Incinerator is located at 2301 Hendee Court and is owned by the City

More information

Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program

Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program www.pca.state.mn.us Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program This document describes the requirements for excavating petroleum-contaminated soil

More information

FINAL PLAN OF REMEDIAL ACTION. Deemer Steel Site - Operable Unit-I New Castle, DE

FINAL PLAN OF REMEDIAL ACTION. Deemer Steel Site - Operable Unit-I New Castle, DE FINAL PLAN OF REMEDIAL ACTION Deemer Steel Site - Operable Unit-I New Castle, DE DNREC Project No. DE 1243 March 2002 Delaware Department of Natural Resources and Environmental Control Division of Air

More information

Project Background. Project Purpose

Project Background. Project Purpose August 21, 2015 Ms. Suzanne Wynn Project Manager Gainesville Community Redevelopment Agency 802 NW 5th Avenue, Suite 200 Gainesville, Florida 32601 Re: Order of Magnitude Estimates for Environmental Assessment/Remediation

More information

ANALYSIS OF BROWNFIELD CLEANUP ALTERNATIVES

ANALYSIS OF BROWNFIELD CLEANUP ALTERNATIVES ANALYSIS OF BROWNFIELD CLEANUP ALTERNATIVES Preliminary Evaluation for Wells & Son Metal Recycling aka Cardinal Grain Property 607 South Chauncey Street Columbia City, Indiana 46725 1.0 INTRODUCTION This

More information

DRAFT. Introduction and Background. June 20, 2013 Project

DRAFT. Introduction and Background. June 20, 2013 Project Geotechnical Environmental and Water Resources Engineering June 20, 2013 Project 116320 Mr. Nick Hodgkins Maine Department of Environmental Protection 17 State House Station Augusta, ME 04333 Dear Nick:

More information

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 Issued 6/1/95 Revised 11/08/2004; 3/6/06 Please direct any questions or comments about the applicability of this document to Luigi

More information

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995.

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995. April 2012, rev. 00 02 8213 Asbestos Abatement 1. General 1.01 Summary of Work A. Contractor 1.02 Definitions 1. The Contractor shall provide removal and proper disposal of asbestos containing materials.

More information

Foundation/Site Work Code Requirements

Foundation/Site Work Code Requirements Q: What is a Foundation Only permit and why did I receive one when I filed for a full Building Permit? All Building Permits for new construction and additions are reviewed for zoning compliance. This review

More information

Technical Memorandum. Blum Junk Yard Properties. Assessment of Environmental Risk Related to Demolition of Properties at 411 and 501 E.

Technical Memorandum. Blum Junk Yard Properties. Assessment of Environmental Risk Related to Demolition of Properties at 411 and 501 E. Technical Memorandum Blum Junk Yard Properties Assessment of Environmental Risk Related to Demolition of Properties at 411 and 501 E. 15 th Street 9/16/15 40140060.13 Prepared For: Steven Sampson Brown

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS

IV. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS IV. ENVIRONMENTAL IMPACT ANALYSIS F. HAZARDS AND HAZARDOUS MATERIALS INTRODUCTION This section summarizes the results of four Phase I Environmental Site Assessments (ESAs) prepared for the various properties

More information

de-construction of Old City Hall

de-construction of Old City Hall de-construction of Old City Hall for the CITY OF GREEN COVE SPRINGS, FL 229 Walnut Street Green Cove Springs, Florida LOCATION MAP Sheet List Table T-1 COVER SHEET TEMPORARY FENCE PLAN LEGEND: GRAPHIC

More information

Tighe&Bond. Hazardous Building Materials Assessment. Ramage Paper Mill Monroe, Massachusetts. Prepared For:

Tighe&Bond. Hazardous Building Materials Assessment. Ramage Paper Mill Monroe, Massachusetts. Prepared For: Tighe&Bond Ramage Paper Mill Monroe, Massachusetts Hazardous Building Materials Assessment Prepared For: Franklin Regional Council of Governments Greenfield, Massachusetts May 25, 2016 F01372-12 May 25,

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

Introduction. Remedial Action Objectives. In This Guide

Introduction. Remedial Action Objectives. In This Guide Addendum to Citizens Guide Proposed soil cleanup plans for additional Tax Blocks for Lockheed Martin s Middle River Complex Winter 2013-2014 Lockheed Martin Would Like to Invite the Community to a Public

More information

COUNTY: MUNICIPALITY: DPW LOCATION: STREET ADDRESS: PROPERTY OWNER: MAILING ADDRESS:

COUNTY: MUNICIPALITY: DPW LOCATION: STREET ADDRESS: PROPERTY OWNER: MAILING ADDRESS: NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION COMPLIANCE ASSISTANCE INSPECTION FORM MUNICIPAL DEPARTMENT OF PUBLIC WORKS (DPW) SITES COUNTY: MUNICIPALITY: DPW LOCATION: STREET ADDRESS: PROPERTY OWNER:

More information

Building Demolition - 46 Main St. (St. Andrews United Church)

Building Demolition - 46 Main St. (St. Andrews United Church) Request for Proposals Building Demolition - 46 Main St. (St. Andrews United Church) Stewiacke, N.S. Building Demolition Stew2018-06 1. INTRODUCTION: The Town of Stewiacke is inviting interested and qualified

More information

RE: Public Comment Period regarding proposed closure of the following four Leaking Underground Fuel Tank (LUFT) Cases:

RE: Public Comment Period regarding proposed closure of the following four Leaking Underground Fuel Tank (LUFT) Cases: 2646 Palma Drive, #450 Ventura, CA 93003 P 805-654-9611 F 805-654-9613 October 17, 2014 UCSB Environmental Health & Safety Attn: Ms. Jodi Woods 565 Mesa Road Santa Barbara, California 93106-5132 RE: Public

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

IXPER 70C Calcium Peroxide CASE STUDY

IXPER 70C Calcium Peroxide CASE STUDY IXPER 70C INTRODUCTION TO ENHANCED AEROBIC BIOREMEDIATION Enhanced aerobic bioremediation is a well-established and viable remediation technology for in situ degradation of a variety of petroleum hydrocarbon

More information

3.7 GROUNDWATER AND SOILS Introduction Environmental Setting Applicable Regulations Impacts and Mitigation Measures

3.7 GROUNDWATER AND SOILS Introduction Environmental Setting Applicable Regulations Impacts and Mitigation Measures . GROUNDWATER AND SOILS 0.. Introduction.. Environmental Setting.. Applicable Regulations.. Impacts and Mitigation Measures... Project Impacts and Mitigation... Proposed Project... Construction Impacts

More information

Engineers and. Limited Asbestos and Lead Containing Materials Evaluation 273 D Street & 244 Athens Street Boston, Massachusetts

Engineers and. Limited Asbestos and Lead Containing Materials Evaluation 273 D Street & 244 Athens Street Boston, Massachusetts GZA GeoEnvironmental, Inc. Engineers and Scientists April 4, 2013 File No. 01.0171487.10 Mr. Jonathan Wright Caritas Communities Inc. 25 Braintree Hill Office Park, Suite 206 Braintree, MA 02184 249 Vanderbilt

More information

Type of information required. 1) AF/BLM experience. 2) Cleanup/ closure documentation and TBD requirements; ICs not acceptable

Type of information required. 1) AF/BLM experience. 2) Cleanup/ closure documentation and TBD requirements; ICs not acceptable UNCERTAINTIES FOR WHICH SAMPLING IS NOT REQUIRED Recommended No. Uncertainty Resolution Type of information required 1. Does legal definition of Resolve survey withdrawn property information. match actual

More information

Guidance Document Risk-Based Corrective Action (RBCA) For Residential and Commercial Heating Oil Systems. National Oilheat Research Alliance (NORA)

Guidance Document Risk-Based Corrective Action (RBCA) For Residential and Commercial Heating Oil Systems. National Oilheat Research Alliance (NORA) Guidance Document Risk-Based Corrective Action (RBCA) For Residential and Commercial National Oilheat Research Alliance (NORA) Forward Heating oil is used to heat many private homes as well as small commercial

More information

FINAL PLAN OF REMEDIAL ACTION

FINAL PLAN OF REMEDIAL ACTION FINAL PLAN OF REMEDIAL ACTION DRAVO SHIPYARD Operable Unit II RDC/Harbor Associates Properties Wilmington, Delaware DNREC Projects No. DE-1092 & DE-1096 February 2001 Department of Natural Resources and

More information

CENTRAL VERMONT REGIONAL PLANNING COMMISSION Brownfields Advisory Committee Draft Minutes May 21, 2018

CENTRAL VERMONT REGIONAL PLANNING COMMISSION Brownfields Advisory Committee Draft Minutes May 21, 2018 Committee Members: CENTRAL VERMONT REGIONAL PLANNING COMMISSION Brownfields Advisory Committee Draft Minutes May 21, 2018 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

More information

Phase I and Phase II Environmental Site Assessments

Phase I and Phase II Environmental Site Assessments Phase I and Phase II Environmental Site Assessments Society of Women Environmental Professionals Capital Chapter Ira Walton Environmental Director United Environmental Services, Inc. May 1, 2018 Who Needs

More information

7.0 EVALUATION OF REMEDIAL ALTERNATIVES

7.0 EVALUATION OF REMEDIAL ALTERNATIVES 7.0 EVALUATION OF REMEDIAL ALTERNATIVES This section provides a description of the developed remedial alternatives based on viable remedial technologies and process options, as identified in Section 4.0,

More information

KABA DEMOLITION INFORMATION PACKET

KABA DEMOLITION INFORMATION PACKET I. Demolition Process Checklist Structures Requiring No Permit Residential Structures 200 Square Feet or Less Commercial Structures 120 Square Feet or Less Structures Requiring No Bond 1 and 2 Family Residential

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

Asbestos Dust Mitigation Plan (ADMP) Application

Asbestos Dust Mitigation Plan (ADMP) Application El Dorado County Air Quality Management District (AQMD) 330 Fair Lane, Placerville, CA 95667 Phone: 530-621-7501 / Fax: 530-295-2774 www.edcgov.us/airqualitymanagement Asbestos Dust Mitigation Plan (ADMP)

More information

ENVIRONMENTAL SUMMARY OF CATALYST AREA 1

ENVIRONMENTAL SUMMARY OF CATALYST AREA 1 ENVIRONMENTAL SUMMARY OF CATALYST AREA 1 Phase I Environmental Site Assessment and Phase II Environmental Site Assessment for 55 South River Street. Environmental Response Program WDNR File Review for,

More information

Fill Material and Soil Management

Fill Material and Soil Management Fill Material and Soil Management What You Need to Know The purpose of this fact sheet is to describe how fill material and excess soil can be reused properly during the cleanup and redevelopment of properties

More information

City of Waukegan, Illinois

City of Waukegan, Illinois City of Waukegan, Illinois NPDES Phase II Stormwater Program Stormwater Pollution Prevention Plan Public Works Facility July 2011 City of Waukegan, Illinois Stormwater Pollution Prevention Plan for the

More information

Solicitation Number: FA B-A001 Project Numbers: RKMF Demo Base Gymnasium & RKMF Demo Pool Facilities.

Solicitation Number: FA B-A001 Project Numbers: RKMF Demo Base Gymnasium & RKMF Demo Pool Facilities. Solicitation Number: FA4861-14-B-A001 Project Numbers: RKMF 13-0134 Demo Base Gymnasium & RKMF 130135 Demo Pool Facilities Responses to RFIs 1. Does all the building material get hauled off base? Response:

More information

ASH MANAGEMENT PLAN. U.S. Environmental Protection Agency Region 4, Atlanta, GA. Mr. Joe Alfano, Remedial Project Manager

ASH MANAGEMENT PLAN. U.S. Environmental Protection Agency Region 4, Atlanta, GA. Mr. Joe Alfano, Remedial Project Manager ASH MANAGEMENT PLAN U.S. Environmental Protection Agency Region 4, Atlanta, GA Mr. Joe Alfano, Remedial Project Manager 404-562-8933 City of Jacksonville Environmental and Compliance Department Site Investigation

More information

CLEANUP ACTION PLAN COOK INLET HOUSING AUTHORITY 3607 & 3609 SPENARD ROAD ANCHORAGE, ALASKA OCTOBER 7, Prepared By:

CLEANUP ACTION PLAN COOK INLET HOUSING AUTHORITY 3607 & 3609 SPENARD ROAD ANCHORAGE, ALASKA OCTOBER 7, Prepared By: CLEANUP ACTION PLAN COOK INLET HOUSING AUTHORITY 3607 & 3609 SPENARD ROAD ANCHORAGE, ALASKA OCTOBER 7, 2016 Prepared By: SHANNON & WILSON, INC. 5430 Fairbanks Street, Suite 3 Anchorage, Alaska 99507 (907)

More information

ASH AND BURN DEBRIS CLEAN UP AND REMOVAL PROCESS

ASH AND BURN DEBRIS CLEAN UP AND REMOVAL PROCESS COUNTY OF LAKE HEALTH SERVICES DEPARTMENT Division of Environmental Health 922 Bevins Court, Lakeport 95453-9739 Telephone 707-263-1164 Denise Pomeroy Interim Health Services Director Raymond Ruminski

More information

Material Characterization Report

Material Characterization Report SSI-Metro12 Facility Carteret, NJ Page 1 of 3 Please complete all sections of the form, sign where indicated and return completed form to: Soil Safe, Inc. 6700 Alexander Bell Dr., Suite 300, Columbia MD

More information

SOIL INVESTIGATION McLAREN BIKE SKILLS PARK SAN FRANCISCO, CALIFORNIA

SOIL INVESTIGATION McLAREN BIKE SKILLS PARK SAN FRANCISCO, CALIFORNIA FUGRO CONSULTANTS, INC. SOIL INVESTIGATION McLAREN BIKE SKILLS PARK SAN FRANCISCO, CALIFORNIA Prepared for: CITY OF SAN FRANCISCO RECREATION AND PARKS DEPARTMENT JUNE 2013 Fugro Project No. 04.72130038

More information

April 16, Dear Mr. Beedie:

April 16, Dear Mr. Beedie: April 16, 2012 Mr. Michael Beedie, P.E. City of Ft. Walton Beach Engineering Services Department 105 Miracle Strip Parkway SW Ft. Walton Beach, FL 32548 Re: Proposal for a Supplemental Site Assessment

More information

REQUEST FOR CONSTRUCTION BIDS May 23, 2017

REQUEST FOR CONSTRUCTION BIDS May 23, 2017 REQUEST FOR CONSTRUCTION BIDS May 23, 2017 Cambridge Greenway Trail / Railroad Bridge Replacement Flood Mitigation Project 1.0 Project Background A former railroad bridge that currently carries the Cambridge

More information

Appendix F Asbestos Emission Control Plan (on CD-ROM)

Appendix F Asbestos Emission Control Plan (on CD-ROM) Appendix F Asbestos Emission Control Plan (on CD-ROM) rjmmmrmpv Asbestos Emission Control Plan MPCA VIC Project No. VP22480 Dakota County, Minnesota Prepared for the University of Minnesota November 14,

More information

15A NCAC 02T.1501 is proposed for readoption without substantive changes as follows:

15A NCAC 02T.1501 is proposed for readoption without substantive changes as follows: 1 1 1 1 1 1 1 1 0 1 SECTION.0 SOIL REMEDIATION 1A NCAC 0T.1 is proposed for readoption without substantive changes as follows: 1A NCAC 0T.1 SCOPE The rules in this Section apply to the Disposal or Treatment

More information

Johanna Heywood, PE, PG

Johanna Heywood, PE, PG Johanna Heywood, PE, PG MEMPHIS BROWNFIELD WORKSHOP, SEPTEMBER 10, 2014 Past use of the site Chemicals used on-site Surrounding property usage Does not generally confirm or delineate contaminated areas

More information

REQUEST FOR BIDS BUILDING DEMOLITION 102 W. Main St.

REQUEST FOR BIDS BUILDING DEMOLITION 102 W. Main St. 531 N. Nash Street Hortonville, WI 54944-0099 Phone: 920-779-6011 Fax: 920-779-6552 www.hortonvillewi.org REQUEST FOR BIDS BUILDING DEMOLITION 102 W. Main St. Date Issued: February 5, 2016 Date Due: March

More information

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering) Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating

More information

MISSOURI DEPARTMENT OF NATURAL RESOURCES. Requirements for Asbestos and Lead Paint Abatement at Voluntary Cleanup Program Sites Technical Bulletin

MISSOURI DEPARTMENT OF NATURAL RESOURCES. Requirements for Asbestos and Lead Paint Abatement at Voluntary Cleanup Program Sites Technical Bulletin MISSOURI DEPARTMENT OF NATURAL RESOURCES Requirements for Asbestos and Lead Paint Abatement at Voluntary Cleanup Program Sites Technical Bulletin 7/2001 Division of Environmental Quality Hazardous Waste

More information

FINAL PLAN OF REMEDIAL ACTION. Burns and McBride. South Market and A Streets August 19, 2008

FINAL PLAN OF REMEDIAL ACTION. Burns and McBride. South Market and A Streets August 19, 2008 FINAL PLAN OF REMEDIAL ACTION Burns and McBride South Market and A Streets August 19, 2008 Wilmington, Delaware DNREC Project No. DE-0325 This Revised Final Plan of Remedial Action (Final Plan) presents

More information

NYSDEC GUIDANCE FOR THE MANAGEMENT OF ASBESTOS CONTAINING MATERIALS (ACM) GENERATED DURING SEVERE STORM EVENTS

NYSDEC GUIDANCE FOR THE MANAGEMENT OF ASBESTOS CONTAINING MATERIALS (ACM) GENERATED DURING SEVERE STORM EVENTS NYSDEC GUIDANCE FOR THE MANAGEMENT OF ASBESTOS CONTAINING MATERIALS (ACM) GENERATED DURING SEVERE STORM EVENTS This document provides New York State Department of Environmental Conservation (Department)

More information