Overcoming Transmission Line Siting Challenges. Case Study Middletown-Norwalk Project

Size: px
Start display at page:

Download "Overcoming Transmission Line Siting Challenges. Case Study Middletown-Norwalk Project"

Transcription

1 Overcoming Transmission Line Siting Challenges Case Study Middletown-Norwalk Project NARUC Transmission Workshop April 21, 2011 Albert W. Cretella, III

2 Presentation Overview Project Description Need, Route Options, Steps to ID Best Solution Siting Challenges Overhead Lines Underground Lines Techniques & Technologies Used Route Variations & Bypasses Low Magnetic Field Designs Underground Cable River & Rail Crossing Methods Summary & Closing Thoughts 2

3 Connecticut Energy Situation NY 0 MA Daily total imports are approximately 1,500 MW RI Most of the time Connecticut uses more power than it generates. 0 Long Island Most of Connecticut s imported power moves on a 345-kV system. SWCT consumes half the state s electricity. But the 115-kV system in SWCT limits the movement of power to where it s needed 50% 345-kV 115-kV Power Plant 3

4 Determining a Solution What needs to be done?* What are the components of the solution? What is the best combination of solution components? 1.Strengthen power source to a point in Wallingford Overhead Point-to-Point Options Connect that source to substations in Milford, Bridgeport, and Norwalk Underground Point-to-Point Options * Per regional planning led by ISO-New England. Evaluate each option based on these criteria Evaluate each combination based on these criteria SYSTEM BENEFIT Operability, Reliability TECHNICAL FEASIBILITY Can it be engineered? Can it be built? PROPERTY IMPACT Impact on homes & property; Visual impact ENVIRONMENTAL IMPACT Impact on wildlife, vernal pools, aquifers COST to CUSTOMERS Engineering and Construction Costs Per national and regional reliability standards. 4

5 Step 1: What needs to be done? To meet national and regional reliability standards 1 Middletown S/S 1 2 Norwalk S/S 2 S/S 2 S/S 5

6 Step 2: What are the options? 6

7 Scovill Rock Beseck East Devon? I-91, I-95 Wilbur Cross Amtrak Railroad Conrail Railroad Transmission ROW Secondary Roads 7

8 Step 3: What are the best options? What are the components of the solution? What is the best combination of solution components? 1 Overhead Point-to-Point Options Underground Point-to-Point Options SYSTEM BENEFIT Operability, Reliability Evaluate each option based on these criteria PROPERTY IMPACT Impact on homes & property; Visual impact Evaluate each combination based on these criteria COST to CUSTOMERS Engineering and construction costs TECHNICAL FEASIBILITY Can it be engineered? Can it be built? ENVIRONMENTAL IMPACT Impact on wildlife, vernal pools, aquifers Per national and regional reliability standards. 8

9 Choosing a Route / Design was an Iterative Process System Studies General Electric ISO-NE NU HVDC Black & Veatch Singer Substation Site Routing & Criteria Burns & McDonnell m n Decision Circle Transmission & Substation Design Burns & McDonnell Underground Technology Underground Construction PDC JD Hair Property Impact Black & Veatch CB Ellis Noise Cavanough & Tocci Environmental Review EMF/ Best Practice Exponent Phenix Environmental, Inc. Historical Raber Associates Environmental Topology Water Resources Coastal Area Cultural SSES Marine Options ESS 9

10 M-N Project and Alternatives M-N Project (Budget $1.400 B) Alternative A (Budget $1.350 B) Alternative B (Budget $1.272 B) OH 345-kV (circuit miles) OH 115-kV (circuit miles) UG 345-kV XLPE (circuit miles) UG 115-kV XLPE (circuit miles) Greenfield S/S Sites Upgrade S/S Sites Acquisition Acres Land / # Homes

11 Middletown-Norwalk Summary 69 miles of 345-kV line 24 miles of XLPE underground 45 miles of overhead 57 miles of 115-kV line 1 mile of XLPE underground 56 miles of overhead 3 new substations 2 existing substation upgrades Construction in 18 towns Middletown Haddam Durham Middlefield Wallingford Meriden Cheshire Hamden Bethany Woodbridge Orange West Haven Milford Stratford Bridgeport Fairfield Westport Norwalk In-Service Date: December 2008

12 Why This Solution Why underground from Milford to Norwalk? Going underground is 50% shorter The underground option avoids the environmental and social impacts of having to acquire over 100 acres and up to 29 homes The reduced length, avoided real estate costs, and construction difficulty make going underground virtually cost-neutral to going overhead Why overhead from Middletown to Milford? No ROW expansion is needed except for 2.5 miles in an unpopulated area of Haddam/Middletown Nine of the 13 towns would see a net reduction in the number of poles in the ROW Most towns would experience no discernible increase in pole heights from what exists today 12

13 Design & Construction Challenges Overhead EMF ROW acquisition (condemnation of residential homes) Viewscape Permitting (wetland) Existing ROW rights Constructability 13

14 Magnetic Field Mitigation Connecticut Public Act No New Applicant Requirements: Mapping requirement to identify Statutory Facilities (i.e., residential areas, private or public schools, licensed child day care facilities, licensed youth camps and public playgrounds) in the vicinity of the proposed OH route. Assessment of the impact of electromagnetic fields. 14

15 Protection from Magnetic Fields Electric fields are a function of voltage higher voltage causes higher electric fields Magnetic fields are a function of current (Amps) higher current causes higher magnetic fields Power is a function of Volts times Amps For the same amount of power, higher voltage means less current therefore lower magnetic fields There is no practical way to shield magnetic fields, but there are ways to reduce them 15

16 Strategies to Reduce Magnetic Fields 1. Add Distance Widen the ROW Relocate the Line Increase Pole Height 2. Optimize phasing to maximize field cancellation 3. Optimize combination of the structures A B C C B A 16

17 Split Phase Construction Structure Type B 345 kv Split Phase Structure Type C Combination 345/115kV Split Phase Structure Type E Horizontal Split Phase 17

18 Cross Section 1 Scovill Rock S/S to Chestnut Junction (2.6 miles; 335 ROW) Middletown Existing Proposed Option 1 Option 3 ($2.1M/mile) ($2.1M/mile) ($3.1M/mile) mg on North/West Edge of ROW 33.8 mg on South/East Edge of ROW (15 GW Case) (15 GW Case) Existing Proposed Option 1 Option 3 Existing Proposed Option 1 Option 3 18

19 Cross Section 2 Oxbow Junction to Beseck S/S (7.0 miles; 125 ROW) Haddam, Durham, Middletown, Middlefield, Wallingford kV 115-kV Existing Proposed Option 2 Option ($2.8M/mile) ($6.7M/mile) ($7.5M/mile) Bypass Royal Oak by placing 345-kV on new ROW. Existing 115-kV remains. Option 6 ($TBD M/mile) mg on North/West Edge of ROW mg on South/East Edge of ROW (15 GW Case) (15 GW Case) * * Existing Proposed Existing Proposed * EMF value for 115-kV only 19

20 Royal Oak Neighborhood Bypass Property Condemnation Significant Tree Clearing Significant Wetland Impacts Bypasses may not be Least Environmentally Damaging Practical Alternative 20

21 Cross Section 7B Cheshire Town Line to Cook Hill Junction (0.4 miles; 200 ROW) Cheshire kV 130 Existing Proposed Option 1 Option 2 ($8.4M/mile) ($9.0M/mile) ($12.5M/mile) mg on North/West Edge of ROW 115-kV 150 mg on South/East Edge of ROW (15 GW Case) (15 GW Case) kV Existing Proposed Option 1 Option 2 Existing Proposed Option 1 Option 2 21

22 Cross Section 8-South Pease Road Junction to East Devon S/S (12.0 miles; 165 ROW) Woodbridge, Orange, Milford Existing Proposed Option 4 Option 5 ($3.8M/mile) ($5.0M/mile) ($5.5M/mile) mg on North/West Edge of ROW mg on South/East Edge of ROW (15 GW Case) (15 GW Case) Existing Proposed Option 4 Option 5 Existing Proposed Option 4 Option 5 22

23 Jewish Community Center Bypass 23

24 Design & Construction Considerations Underground System Limitations Operation & Maintenance Concerns Traffic/Public & Worker Safety DOT/Local Constraints Cost Railroad/Bridge/ River Crossing Methods Soil/Water Handling Conflicts w/other Utilities Residential & Business Disruption 24

25 Underground Challenges How much underground cable can system handle What are O&M implications of UG lines Shortest route is always better can it be built? CT Siting Council approved route along 14 miles of State roadways (shortest and straightest route) DOT resisted use of State roadways due to potential traffic impacts and safety concerns DOT originally wanted the duct bank 8 feet deep which would be too deep for the heat to dissipate and would reduce the capacity of the line DOT wanted all vaults to be located outside of the travel roadway needed to find off street locations How to cross rivers and railroads 25

26 Cable Types Cable Type Maximum Voltage High-pressure Fluid-filled (HPFF) 345kV + Electrical Advantages Most Common at >230kV High-pressure Gas-filled (HPGF) 138kV Lower Capacitance Extruded-dielectric (XLPE) 345kV + Extruded-dielectric (EPR) 138kV Higher Rating than HPFF, Lower VAR Consumption, Low Maintenance More Flexible than XLPE Self-contained Fluid-filled (SCFF) 345kV + High Voltages Electrical Disadvantages Higher VAR Consumption, Leaking oil Higher VAR Consumption, Uncommon New to the United States at 345kV+ Higher Electrical Losses than XLPE Dielectric Fluid, Higher VAR Consumption than XLPE, Uncommon 26

27 Factors Impacting Vault Locations Maximizing system reliability minimize splices Cable length that can be loaded on reels maximum 1800 feet Electrical requirement to space each set of 4 vaults about equally Maximum cable pulling tensions Location of water and railroad crossings - fixed or hard coded vault locations due to river crossings Maximizing the number of off-street vault locations Minimizing impacts to existing businesses (condemnation and business disruption claims) Location of off road wetlands Avoidance of existing utilities Avoidance of intersections 27

28 Water / Rail Crossing Methods Horizontal Directional Drill (HDD) Horizontal Auger (Jack and Bore) Self-Supporting Utility Bridge Open Cut (Trenching with Cofferdams) In-Street Trenching Attachment to DOT Bridges Evaluation Criteria Conformance with Siting Council Decision and Order Minimize Impact to the Environment Minimize Social Impact Minimize Construction Risk Minimize Construction Schedule 28

29 UG Route Change Very busy commercial area No feasible crossing method 29

30 Options to Cross Ash Creek ConnDOT Bridge Attachment Structurally Infeasible HDD Unacceptable Risks Unfavorable Subsurface Conditions Mixed Face Soil Conditions / Shallow Drill Path - Risk of Construction Failure Release of drilling mud (Frac-Out) Staging Area - Unsatisfactory Demolition of business at 58 Post Road in Fairfield Eliminates Entire business parking Lot in Bridgeport for 2-3 months Jack & Bore Not Constructible Open Cut Environmentally Devastating 30

31 Ash Creek Crossing Original Proposal Self-Supporting Utility Bridge 160 Foot Clear Span 4-5 Month Construction Duration Bridge Located Outside of Town Public Access Easement Design Provides Shoreline Access Around Bridge Abutments and Under Bridge Minor Impacts to Intertidal Area 31

32 Proposed Utility Bridge at Ash Creek Building Demolition Elimination of Parking for 2-3 months 32

33 Mock-up of Utility Bridge at Ash Creek This attempt to provide residents a visual representation did not go well and resulted in a petition to DEP due to proposed crossing method 33

34 Ash Creek Permitting Background Extensive feasibility / design completed to determine the least environmentally damaging practical alternative DEP hearings conducted due to petition associated with the construction method After DEP hearings and extensive discussion the Town of Fairfield, City of Bridgeport, ConnDOT and DEP eventually agreed to permit an HDD within the State roadway under the existing bridge Town of Fairfield, City of Bridgeport and ConnDOT signed Memorandum of Understanding to ensure that all understood the impacts of an HDD within the roadway 34

35 Ash Creek Horizontal Directional Drill One circuit on each side of road Each circuit bundle of 5 conduits Drill path was steep and deep to get under bridge abutments Circuits separated and spaced far apart to address cable overheating concerns Construction mostly night work in 12- hour shifts 6 days per week 35

36 Ash Creek-Northwest Corner 36

37 Ash Creek-Northeast Corner 37

38 Construction Duration for Each HDD Each HDD took over 5 months to complete 30 days to install traffic control and Mobilize HDD equipment 8 days to drill pilot hole 30 days to ream pilot hole to proper diameter 45 days to fuse conduits for pull back 2 days conduit pull back 12 days to clean/test conduits 30 days to remove traffic control, restore road and demobilize NOTE: Blue items occur in expanded work zone. Typical Horizontal Directional Drill Setup 38

39 Saugatuck River Crossing 39

40 Saugatuck River Crossing Horizontal Directional Drill 1563 feet in length Max 40 deep 2 3 month construction duration Subsurface conditions Marginal Drill side staging area Adequate Conduit side staging area somewhat constrained residential street Result Hit target exit point Frac-outs cleaned up with no impacts to coastal / environmental resources 40

41 Managing Stakeholder Conflicting Priorities State Siting Authority Federal Agencies - ACOE, NPS, USF&W, OLISP (Office of Long Island Sound), etc. Municipal Leaders State Dept. of Transportation State Dept. of Environmental Protection State Dept. of Health Residents Businesses Other Utilities Communication, engagement and compromise for the greater good are essential 41

42 M-N Project Cost Summary Configuration Circuit Miles $ M/Circuit Mile Range / Ave Influencing Factors 345-kV OH 52 $ / $ kV UG 46 $ / $13.2 Single / Double Circuit Low EMF Designs Double Circuit Duct Bank River / RR Crossings 115-kV OH 63 $ / $2.1 Single / Double Circuit 115-kV UG 1 $7.5 / $7.5 Single Circuit Duct Bank Underground transmission lines can cost 4 to 6 times more than overhead transmission lines on an adequately sized existing ROW 42

43 Closing Thoughts Every projects use of various technologies must be evaluated on its own merits Cost/mile comparisons of OH and UG can be deceiving State Siting Regulators should strive to streamline / shorten the siting approval process 2 plus years is too long State Siting Regulators should be cautious about delegating decisions to municipalities Legislators can provide leadership roles in coordinating stakeholders State and Federal agencies, municipal leaders, businesses and residents 43

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

Sudbury to Hudson Transmission Reliability Project Frequently Asked Questions (FAQs)

Sudbury to Hudson Transmission Reliability Project Frequently Asked Questions (FAQs) Sudbury to Hudson Transmission Reliability Project Frequently Asked Questions (FAQs) June 2, 2016 revised Project Overview Eversource is proposing to construct a new 115-kilovolt (kv) transmission line

More information

SOUTHWEST CONNECTICUT RELIABILITY PROJECT

SOUTHWEST CONNECTICUT RELIABILITY PROJECT SOUTHWEST CONNECTICUT RELIABILITY PROJECT BY THE CONNECTICUT LIGHT AND POWER COMPANY DOING BUSINESS AS EVERSOURCE ENERGY VOLUME 1: DESCRIPTION OF THE PROPOSED PROJECT AND ALTERNATIVES ANALYSIS APRIL 2016

More information

SUPPLEMENTAL MUNICIPAL CONSULTATION FILING FOR THE CONNECTICUT PORTION OF THE INTERSTATE RELIABILITY PROJECT THE CONNECTICUT LIGHT AND POWER COMPANY

SUPPLEMENTAL MUNICIPAL CONSULTATION FILING FOR THE CONNECTICUT PORTION OF THE INTERSTATE RELIABILITY PROJECT THE CONNECTICUT LIGHT AND POWER COMPANY SUPPLEMENTAL MUNICIPAL CONSULTATION FILING FOR THE CONNECTICUT PORTION OF THE INTERSTATE RELIABILITY PROJECT BY THE CONNECTICUT LIGHT AND POWER COMPANY VOLUME 1A of 11 JULY 2011 Supplemental Municipal

More information

Scheduled Outages and Service Interruptions in Connecticut. Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015

Scheduled Outages and Service Interruptions in Connecticut. Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015 Scheduled Outages and Service Interruptions in Connecticut Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015 1 Topics Profiles of Connecticut EDCs SAIDI and SAIFI Interruptions

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

Sudbury to Hudson Transmission Reliability Project

Sudbury to Hudson Transmission Reliability Project Hudson, Massachusetts Board of Selectmen Presentation February 22, 2016 Revised 3-24-16 Page 4 revised last bullet on Route Analysis Process. Page 9 revised preferred route (overhead) visual simulation

More information

This Overview contains information about electric transmission lines which are installed

This Overview contains information about electric transmission lines which are installed Underground Electric Transmission Lines This Overview contains information about electric transmission lines which are installed underground, rather than overhead on poles or towers.1 Underground lines

More information

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Purpose of this Public Information Centre Provide you with an update on Hydro One s infrastructure

More information

I. ELECTRIC AND MAGNETIC FIELDS

I. ELECTRIC AND MAGNETIC FIELDS I. ELECTRIC AND MAGNETIC FIELDS This section provides EMF information for the Project, presenting projections for future EMF levels associated with the proposed transmission line in each segment of the

More information

Sudbury to Hudson Transmission Reliability Project. Town of Sudbury Board of Selectmen Lincoln-Sudbury Regional High School October 26, 2016

Sudbury to Hudson Transmission Reliability Project. Town of Sudbury Board of Selectmen Lincoln-Sudbury Regional High School October 26, 2016 Sudbury to Hudson Transmission Reliability Project Town of Sudbury Board of Selectmen Lincoln-Sudbury Regional High School October 26, 2016 Agenda Project Need and Benefits Summary of Community Outreach

More information

Underground Cost Analysis; Option 10 and 11 - TRTP Project. Project Segment 8A Corridor October 21, 2012

Underground Cost Analysis; Option 10 and 11 - TRTP Project. Project Segment 8A Corridor October 21, 2012 Underground Cost Analysis; Option 10 and 11 - TRTP Project Project Segment 8A Corridor October 21, 2012 SCE Cost Overview on Option 10 (Single Circuit XLPE 3 Cables per Phase) and Option 11 (Single Circuit

More information

Underground System Design TADP 547

Underground System Design TADP 547 Underground System Design TADP 547 Transmission Cable Installation Presentation 5.4 Instructor: Frank Frentzas Transmission Design and Installation When planning an underground power cables system the

More information

Seacoast Reliability Project Need and Proposed Solution. Madbury Planning Board Meeting February 4, 2015

Seacoast Reliability Project Need and Proposed Solution. Madbury Planning Board Meeting February 4, 2015 Seacoast Reliability Project Need and Proposed Solution Madbury Planning Board Meeting February 4, 2015 Agenda Reliability in the NH Seacoast Project Need and Overview Selecting a Transmission Route Proposed

More information

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No.

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No. d/b/a National Grid and Clear River Energy LLC (Burrillville Interconnection Project) RIPUC Dkt. No. Testimony of David J. Beron, P.E., P.M.P. November, 0 0-v R.I.P.U.C. Dkt. No. 0 0 INTRODUCTION Q. Please

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

Quintillion Subsea Project Applicant Proposed Mitigation Statement

Quintillion Subsea Project Applicant Proposed Mitigation Statement 1. Avoidance of impacts to waters of the U.S., including wetlands: Please describe how, in your project planning process, you avoided impacts to waters of the U.S., including wetlands, to the maximum extent

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

PUBLIC WORKS DEPARTMENT Council Meeting Date: November 15, 2011 Staff Report #:

PUBLIC WORKS DEPARTMENT Council Meeting Date: November 15, 2011 Staff Report #: PUBLIC WORKS DEPARTMENT Council Meeting Date: November 15, 2011 Agenda Item #: F3 REGULAR BUSINESS: Authorize the City Manager to Amend the Agreement with Infrastructure Engineering Corporation to Complete

More information

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE Conference Center at the Maritime Institute Anne Arundel County, Maryland Thursday, April 28, 2016 Two bridges in Two Months - Accelerated

More information

Glebe Potomac River 230 kv Transmission Line Project. May 2018

Glebe Potomac River 230 kv Transmission Line Project. May 2018 Glebe Potomac River 230 kv Transmission Line Project May 2018 What Has Changed Since May 2016, And What Has Not Just as in May 2016: PJM Forecasted Violations of Federal (NERC) Reliability Standards Remain

More information

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 4 11.07.18.. Agenda Welcome and Introductions Outreach Materials Update Work Plan Update Community Conversations Alternative Review Charleston/Meadow Exhibits and 3D

More information

Underground Conduit Systems

Underground Conduit Systems Section 32 Underground Conduit Systems Note 1 under the title of Sec. 32 defines how the NESC uses the following terms: Duct Conduit Conduit system The common trade use of these terms is slightly different

More information

SECTION 10 UTILITIES

SECTION 10 UTILITIES SECTION 10 UTILITIES Virtually every highway construction project in the State of New Jersey impacts utility facilities. The Designer shall examine and seek alternatives to minimize or eliminate the impact

More information

Woburn to Wakefield Line Project Questions and Answers (Q&A)

Woburn to Wakefield Line Project Questions and Answers (Q&A) Woburn to Wakefield Line Project Questions and Answers (Q&A) May 27, 2016 Ownership and Regulation Q: Who owns and operates the transmission lines? A: For the Woburn to Wakefield Line Project, Eversource

More information

SECTION 10 TRANSMISSION LINE DESIGN AND RIGHT-OF-WAY CONFIGURATION OPTIONS IN MANSFIELD HOLLOW

SECTION 10 TRANSMISSION LINE DESIGN AND RIGHT-OF-WAY CONFIGURATION OPTIONS IN MANSFIELD HOLLOW SECTION 10 TRANSMISSION LINE DESIGN AND RIGHT-OF-WAY CONFIGURATION OPTIONS IN MANSFIELD HOLLOW Supplemental Municipal Consultation Filing The Interstate Reliability Project 10. TRANSMISSION LINE DESIGN

More information

Significant Unavoidable Adverse Impacts

Significant Unavoidable Adverse Impacts 6 Significant Unavoidable Adverse Impacts CHAPTER 6. SIGNIFICANT UNAVOIDABLE ADVERSE IMPACTS 6.1 LAND USE AND HOUSING Construction of the project would not require significant excavation, inhibit access

More information

Appendix C Presentation Slides with Script

Appendix C Presentation Slides with Script Appendix C Presentation Slides with Script 32 Grand Crossing Rail Project 10 S. Riverside Plaza, Suite 400 Chicago, IL 60606 www.grandcrossingrail.com info@grandcrossingrail.com [title slide no narration]

More information

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact

More information

Sudbury to Hudson Transmission Reliability Project Briefing. William Wrigley, Town Administrator Stow, Massachusetts August 16, 2016

Sudbury to Hudson Transmission Reliability Project Briefing. William Wrigley, Town Administrator Stow, Massachusetts August 16, 2016 Sudbury to Hudson Transmission Reliability Project Briefing William Wrigley, Town Administrator Stow, Massachusetts August 16, 216 Agenda Project Need and Benefits Summary of Community Outreach Activities

More information

Lloydminster to Spruce Lake 138kV Transmission Line Projects

Lloydminster to Spruce Lake 138kV Transmission Line Projects Lloydminster to Spruce Lake 138kV Transmission Line Projects Preferred Corridor Presentation June 2017 SaskPower continues to invest in the province s electricity system to ensure we have the infrastructure

More information

E kv Transmission Line Underground Relocation Project. Evaluation of National Grid s 2014 Underground Estimate

E kv Transmission Line Underground Relocation Project. Evaluation of National Grid s 2014 Underground Estimate E-183 115 kv Transmission Line Underground Relocation Project Evaluation of National Grid s 2014 Underground Estimate April 10, 2015 Introduction Ferrucci Russo P.C. contacted Power Delivery Consultants,

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date June 19, 2018 Project Northern Natural Gas Company (Northern) Cedar Station Upgrade Project Dakota County, Minnesota Authority: Section 7(c) Personnel FERC Staff: Company Staff:

More information

Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street

Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street 1600 SW Western Blvd, Suite 100 Corvallis, OR 97333 (541) 766-4601(desk) GOrmsby@TriAxisEng.com August 30, 2013 Robert White Power Services Manager Tillamook People s Utility District 1115 Pacific Avenue

More information

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0 SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605/SR-60 EA# 3101U0 October 9, 2017 Contents 1 Purpose of ICE Memo... 1 2 Background... 1 3 Existing Interchange Deficiencies... 1 4 Context Sensitive

More information

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services

More information

July 26, Revised Electric and Magnetic Fields (EMF) Design Guidelines of Southern California Edison Company

July 26, Revised Electric and Magnetic Fields (EMF) Design Guidelines of Southern California Edison Company Akbar Jazayeri Vice President, Revenue and Tariffs July 26, 2006 ADVICE 2018-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revised Electric and Magnetic Fields

More information

Harlem Avenue Interchange Design Discussion. August 24, 2015

Harlem Avenue Interchange Design Discussion. August 24, 2015 Harlem Avenue Interchange Design Discussion August 24, 2015 1 Expressway Construction Pre-dates Modern Design Standards Expressway designed and constructed in 1950 s No past experience to base design standards

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date May 22, 2018 Project Northern Natural Gas Company Cedar Station Upgrade Project Dakota County, Minnesota Authority: Sections 7(c) Personnel FERC Staff: Company Staff: S. Xiah

More information

APPENDIX J. Dry Utilities Master Plan

APPENDIX J. Dry Utilities Master Plan APPENDIX J Dry Utilities Master Plan Sutter Pointe Specific Plan Dry Utilities Master Plan Prepared by MacKay & Somps Civil Engineers, Inc. 1771 Tribute Road, Suite E Sacramento, California 95818 (916)

More information

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY Bryan Thompson, Town of Westport Abhinav Huli, Haley & Aldrich, Inc Lori Carriero, P.E., Tighe & Bond PRESENTATION OUTLINE

More information

Mystic to Woburn Line Project. Grant of Location Hearing Town of Winchester

Mystic to Woburn Line Project. Grant of Location Hearing Town of Winchester Grant of Location Hearing Town of Winchester Purpose and Need A strong electrical transmission grid is vital to the safety, security and economic prosperity of the region. The transmission system serves

More information

THE CONNECTICUT PORTION OF THE INTERSTATE RELIABILITY PROJECT

THE CONNECTICUT PORTION OF THE INTERSTATE RELIABILITY PROJECT THE CONNECTICUT PORTION OF THE INTERSTATE RELIABILITY PROJECT BY THE CONNECTICUT LIGHT AND POWER COMPANY VOLUM ME 3: ENVIRONMENTAL CULTURAL RESOURCES DECEMBER 2011 Connecticutt Siting Council Application

More information

400 watt, high pressure sodium. Type C watt, high pressure sodium Collector Street Light Units

400 watt, high pressure sodium. Type C watt, high pressure sodium Collector Street Light Units CITY OF MEDFORD PUBLIC WORKS DEPARTMENT ENGINEERING & DEVELOPMENT DIVISION TRAFFIC ENGINEERING SECTION April 15, 2010 Street Lighting Standards and Specifications Luminaire Types Type R-100 100 watt, high

More information

Environme ntal Assessment Addendum

Environme ntal Assessment Addendum FI Improved Interchange at I-71 and Routes 36/37 and Proposed Sunbury Parkway Environme ntal Assessment Addendum DEL-71-7.91 PID 90200 September 20, 2017 The environmental review, consultation, and other

More information

WELCOME The Walk Bridge Project CTDOT Project No

WELCOME The Walk Bridge Project CTDOT Project No 1 WELCOME The Walk Bridge Project CTDOT Project No. 0301-0176 Walk Bridge Public Scoping/Public Information Meeting 1. Project description 2. Study process 3. Findings 4. Potential solutions 5. Next steps

More information

COMMERCIAL CONDUIT RULES AND REGULATIONS

COMMERCIAL CONDUIT RULES AND REGULATIONS Electric Engineering Division COMMERCIAL CONDUIT RULES AND REGULATIONS S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies B - 1 1805 NE 30th Ave., Bldg. 400 Ocala, FL 34470-4875

More information

Final Air Quality Report

Final Air Quality Report Florida Department of TRANSPORTATION Final Air Quality Report PD&E Study From East of Babcock Street (SR 507) to US 1 Brevard County, Florida Financial Project ID: 430136-1-22-01 ETDM Project Number: 13026

More information

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project Welcome Metro North Transmission Project Burnaby Community Information Open House March 8, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.

More information

BL ENGLAND & RELIABILITY PIPELINE PROJECT. September 27, 2013

BL ENGLAND & RELIABILITY PIPELINE PROJECT. September 27, 2013 BL ENGLAND & RELIABILITY PIPELINE PROJECT September 27, 2013 PRESENTATION OUTLINE Utility Service in New Jersey South Jersey Gas overview Project background Existing system infrastructure Reliability considerations

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2007 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

More information

Electric Service Handbook

Electric Service Handbook Electric Service Handbook Revised August 2017 Contact Information Telephone (253): Electrical Inspection Office 502-8277 7:30 am - 4:30 pm Electrical Inspectors Area Map on Website 7:30 am - 8:30 am Automated

More information

Subsurface Utility Engineering & Asset Management. American Council of Engineering Companies/Maryland

Subsurface Utility Engineering & Asset Management. American Council of Engineering Companies/Maryland PHI s Underground Use of SUE in Transmission Design Process Subsurface Utility Engineering & Asset Management American Council of Engineering Companies/Maryland Presented by: Pepco Underground Transmission

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

November 16, 2017 Via Electronic Filing

November 16, 2017 Via Electronic Filing 414 Nicollet Mall Minneapolis, MN 55401 November 16, 2017 Via Electronic Filing Daniel P. Wolf Executive Secretary Minnesota Public Utilities Commission 121 7 th Place East, Suite 350 St. Paul, MN 55101

More information

Underground Conversions

Underground Conversions Underground Conversions Things to consider Thomas Drive in Panama City Beach after its underground conversion. Contents Introduction...1 Why go underground?...2 What is involved?...3 Conversion and scope...3

More information

About the Team. Black Forest Partners, L.P. Southline Transmission, L.L.C. Additional Consultants

About the Team. Black Forest Partners, L.P. Southline Transmission, L.L.C. Additional Consultants About the Team Black Forest Partners, L.P. Project manager for Southline Transmission Project Led by Southwest natives Bill Kipp and Doug Patterson Originally focused on investment opportunities in renewable

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re: The Narragansett Electric Company : (E-183 115 kv Transmission Line : Docket No. SB-2003-01 Relocation Project A/C I-195

More information

Muskrat Falls Project - Exhibit 37 Page 1 of 22 SOBI Decision Recommendation

Muskrat Falls Project - Exhibit 37 Page 1 of 22 SOBI Decision Recommendation Page 1 of 22 SOBI Decision Recommendation 12 October 2010 Page 2 of 22 Background Two options for crossing of the SOBI have been diligently pursued. Option 1 Seabed Crossing Option 2 Tunnel / Conduit Crossing

More information

Horizontal Directional Drilling

Horizontal Directional Drilling Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social

More information

Duwamish Waterway Self Guided Tour: Turning Basin Number Three and Terminal 105 Aquatic Habitat Restoration Sites

Duwamish Waterway Self Guided Tour: Turning Basin Number Three and Terminal 105 Aquatic Habitat Restoration Sites Duwamish Waterway Self Guided Tour: Turning Basin Number Three and Terminal 105 Aquatic Habitat Restoration Sites Text and illustrations in the following pages include: (1) summary information describing

More information

Application for a Certificate of Environmental Compatibility

Application for a Certificate of Environmental Compatibility Application for a Certificate of Environmental Compatibility Irvington to Kino 138 kilovolt Transmission Line Project Prepared for: Arizona Power Plant and Transmission Line Siting Committee Submitted

More information

530,300 SF Divisible to 65,000 SF For Sale or Lease MOOSUP DISTRIBUTION CENTER 85 MOOSUP POND ROAD PLAINFIELD, CT

530,300 SF Divisible to 65,000 SF For Sale or Lease MOOSUP DISTRIBUTION CENTER 85 MOOSUP POND ROAD PLAINFIELD, CT 530,300 SF Divisible to 65,000 SF For Sale or Lease Dominant Market Presence A 530,300-square foot manufacturing/ warehouse facility in Plainfield, Connecticut, the Moosup Distribution Center boasts the

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

Electric Engineering Division RESIDENTIAL CONDUIT RULES AND REGULATION. S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies

Electric Engineering Division RESIDENTIAL CONDUIT RULES AND REGULATION. S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies Electric Engineering Division RESIDENTIAL CONDUIT RULES AND REGULATION S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies 1805 NE 30TH AVE., BLDG. 400 Ocala, FL 34470-4875 Phone:

More information

Peninsula Corridor Electrification Project. Draft Environmental Impact Report

Peninsula Corridor Electrification Project. Draft Environmental Impact Report Peninsula Corridor Electrification Project Draft Environmental Impact Report Public Meeting Purpose of Tonight s Meeting Provide an overview of Draft Environmental Impact Report (Draft EIR) Receive comments,

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

Equipment Guide shorten restoration times underground

Equipment Guide shorten restoration times underground Dominion Energy Virginia s Strategic Underground Program is a system-wide initiative to shorten restoration times following major storms by placing certain outage-prone overhead electric distribution lines

More information

5-1 Street Lights Required Street Lights on Private Roadways Developer s Responsibility...5-1

5-1 Street Lights Required Street Lights on Private Roadways Developer s Responsibility...5-1 SECTION 5 STREET LIGHTING CONTENTS Page 5-1 Street Lights Required...5-1 5-2 Street Lights on Private Roadways...5-1 5-3 Developer s Responsibility...5-1 5-4 Utility Company Authorization...5-1 5-5 General

More information

Presented by: Enoch Lenge, Northeast Utilities. Zero Net Energy: Moving from Homes to Community

Presented by: Enoch Lenge, Northeast Utilities. Zero Net Energy: Moving from Homes to Community Presented by: Enoch Lenge, Northeast Utilities Zero Net Energy: Moving from Homes to Community Moving from homes to communities! 2 What is a Zero Energy Community? Energy efficiency Renewables energy Sustainability

More information

STATE OF NEW HAMPSHIRE Inter-Department Communication. Tf~ Tom Frantz - Director, Electric Division

STATE OF NEW HAMPSHIRE Inter-Department Communication. Tf~ Tom Frantz - Director, Electric Division STATE OF NEW HAMPSHIRE Inter-Department Communication FROM: \"""' Tf~ Tom Frantz - Director, Electric Division DATE: 15 October 2010 AT (OFFICE): NHPUC SUBJECT: DE 10-224: Petition by PSNH for a License

More information

4.8 ENVIRONMENTAL HEALTH - ELECTRIC AND MAGNETIC FIELDS

4.8 ENVIRONMENTAL HEALTH - ELECTRIC AND MAGNETIC FIELDS 4.8 ENVIRONMENTAL HEALTH - ELECTRIC AND MAGNETIC FIELDS This section provides project-level discussion and analysis of potential health and safety impacts related to power frequency electric and magnetic

More information

Environmental Effects of Underground & Overhead Transmission Line Construction & Maintenance in the United States

Environmental Effects of Underground & Overhead Transmission Line Construction & Maintenance in the United States Environmental Effects of Underground & Overhead Transmission Line Construction & Maintenance in the United States Ryan A. Brockbank Halifax, Nova Scotia September 20 23, 2015 Environmental Concerns on

More information

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017 VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

ELECTRICITY, NATURAL GAS, AND TELECOMMUNICATION SERVICES

ELECTRICITY, NATURAL GAS, AND TELECOMMUNICATION SERVICES 4.12.5 ELECTRICITY, NATURAL GAS, AND TELECOMMUNICATION SERVICES 4.12.5.1 INTRODUCTION The electricity, natural gas and telecommunications analysis is based on information within the following documents:

More information

Powering Sydney s Future. TransGrid 330kV Cable Route Selection Process Summary

Powering Sydney s Future. TransGrid 330kV Cable Route Selection Process Summary Powering Sydney s Future TransGrid 330kV Cable Route Selection Process Summary Contents Contents... 2 1. Executive summary... 3 2. Drivers for the project... 3 3. Options considered... 3 4. 330kV cable

More information

Project Alignment Appendix A

Project Alignment Appendix A Project Alignment Appendix A Fargo Moorhead Metropolitan Area Flood Risk Management Project EA Document This page is intentionally left blank Project Alignment Appendix A Table of Contents 1 BACKGROUND...

More information

Electrical Network Design, Engineering & Construction

Electrical Network Design, Engineering & Construction Electrical Network Design, Engineering & Construction www.uea.com.au UEA know how. Because we know the network. UEA Electrical is an A Grade Accredited Service Provider specialising in the design, engineering

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

South Sounder Capital Improvements Program

South Sounder Capital Improvements Program Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Date Last Modified July 1, 2016 PROJECT AREA AND REP RESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION

More information

345 kv Underground Report

345 kv Underground Report POWER ENGINEERS, INC. February 24, 2010 345 kv Underground Report PROJECT NUMBER: 117910 PROJECT CONTACT: Mike Mueller Richard C. Mues, PE EMAIL: mike.mueller@powereng.com rmues@powereng.com PHONE: 314-851-4050

More information

1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project

1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project 1.0 INTRODUCTION 1.1 Environmental Assessment/Environmental Impact Evaluation for the New Haven, Hartford and Springfield High-Speed Intercity Rail Project Connecticut is centrally located in a part of

More information

PUBLIC HEARING LOOP 9

PUBLIC HEARING LOOP 9 PUBLIC HEARING LOOP 9 From Interstate (I)-35E to I-45 Dallas and Ellis Counties, Texas CSJ: Loop 2964-10-005 9: I-35E to I-45 Tuesday, June 20, 20, 2017 2017 Public Hearing Introductions ELECTED & PUBLIC

More information

Board Policy on Construction of Transmission and Distribution Projects

Board Policy on Construction of Transmission and Distribution Projects Board Policy: Policy Type: Monitored by: Construction of Transmission and Distribution Projects Operating Policies Oversight and REV Committee Board Resolution: Resolution #1383, approved September 27,

More information

Community Benefits of Land Restoration

Community Benefits of Land Restoration Community Benefits of Land Restoration Introducing Green Infrastructure for Coastal Resilience Matt Fulda, Acting Director Monroe May 23 rd, 2017 Avery Point Campus, University of Connecticut Easton Trumbull

More information

Environmental Assessment May 2007

Environmental Assessment May 2007 jurisdictional waters. It is assumed that, at a minimum, a USACE Section 404 Nationwide Permit would be necessary to construct these features. The impacts of the fill into the floodplain cannot be fully

More information

THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION

THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION PETITION OF PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE FOR A LICENSE TO CONSTRUCT AND MAINTAIN ELECTRIC LINES, STATIC WIRES AND FIBER OPTIC

More information

VII. WATER SUPPLY AND SEWAGE TREATMENT

VII. WATER SUPPLY AND SEWAGE TREATMENT VII. WATER SUPPLY AND SEWAGE TREATMENT Water supply and sewage treatment are essential services accompanying the development of land for housing, non-profit and community institutions, commerce and industry.

More information

DESIGN STANDARDS SECTION DS 7 STREET LIGHTING

DESIGN STANDARDS SECTION DS 7 STREET LIGHTING DESIGN STANDARDS SECTION DS 7 STREET LIGHTING DS 7-01 GENERAL: A. INTENT: The intent of these Design Standards is to provide minimum standards for the design of street lighting to serve the ultimate level

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions. March 28, 2016

House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions. March 28, 2016 House Select Committee on Strategic Transportation Planning and Long Term Funding Solutions March 28, 2016 US Highway 70 Main highway route from I-40 & I-95 to the Global TransPark and the Port of Morehead

More information

Takatz Lake Project - Alaska

Takatz Lake Project - Alaska BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT SUBMITTED BY: City and Borough of Sitka Electric Department 105 Jarvis Street Sitka, Alaska 99835 June, 2008 Initial Statement

More information

Chapter 2. Alternatives

Chapter 2. Alternatives Chapter 2. Alternatives This chapter presents an overview of the process used to develop the reasonable alternatives considered for the 75 th Street Corridor Improvement Project (CIP), presents details

More information

EXHIBIT A DESCRIPTION OF PROJECT

EXHIBIT A DESCRIPTION OF PROJECT EXHIBIT A DESCRIPTION OF PROJECT Exhibit A 1 SUMMARY DESCRIPTION OF PROJECT Public Utility District No. 1 of Snohomish County, Washington (Snohomish), is applying to the Federal Energy Regulatory Commission

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

CTLCV Candidate Survey

CTLCV Candidate Survey CTLCV Candidate Survey Please complete this survey by July 30, 2016. First Name: * Philip Last Name: * Dwyer Running For: * House Senate District Number: * 28 Party: * Democrat Republican Working Families

More information

Quick guide to living and working near electric transmission lines

Quick guide to living and working near electric transmission lines Quick guide to living and working near electric transmission lines October 2015 about atc American Transmission Co. has approximately 50,000 easement agreements with property owners in our service area.

More information