Subsurface Utility Engineering & Asset Management. American Council of Engineering Companies/Maryland

Size: px
Start display at page:

Download "Subsurface Utility Engineering & Asset Management. American Council of Engineering Companies/Maryland"

Transcription

1 PHI s Underground Use of SUE in Transmission Design Process Subsurface Utility Engineering & Asset Management American Council of Engineering Companies/Maryland Presented by: Pepco Underground Transmission March 28,

2 Agenda Background About Pepco Holdings Pepco holdings Quick Facts PHI UG Transmission Design Process (Civil) UG Transmission Design Engineering Cost SUE Benefits / Challenges UG Electric Lines UG Electric Lines Construct Working In Close Proximity To Pepco Underground Facilities PHI UG Transmission Engineering Contact Q & A 2

3 About Pepco Holdings Approximately 2 million customers in Delaware, the District of Columbia, Maryland and New Jersey Atlantic City Electric, Delmarva Power and Pepco provide regulated electricity service Delmarva Power also provides natural gas service 3

4 Pepco Holdings Quick Facts Service territory: 8,340 square miles Customers served Atlantic City Electric: 547,000 electric Delmarva Power: 515,000 electric 130,000 natural gas Pepco: 842,000 electric Total population served: 5.4 million PHI Service Territory As of 2/19/16 4

5 PHI UG Transmission Design Process (Civil) Underground Transmission Design Guide Formally Issued in June 2016 Project Steps: Initiate Based on system need a concept is created Route Analysis o Level D survey for all possible routes o Level B survey in and around substations to ensure feasibility of approaching subs o Preferred route selected based on Route Matrix 30% Design Conduct Site Topography and Level B Survey Design Horizontal Alignment 60% Design Conduct Level A survey Complete Soil Borings & Geotech report Design Vertical Alignment 90% Design Complete Design details Obtain Applicable Permits Finalize design Issue for Construction Complete SOW for bid and award Example of PHI Design Checklist Checklists created to verify all information is provided during the each step of the design Complete Design Review at 30%, 60%, 90% and IFC stages In-field Constructability Review completed at 30%, 60% and as needed 5

6 PHI UG Transmission Design Process (Civil) 30% Design Topographic survey completed Level B Survey completed Horizontal alignment designed Constructability and Design reviews completed Example of 30% Design Submittal from Civil Design Consultant 6

7 PHI UG Transmission Design Process (Civil) 60% Design Example of 60% Design Submittal from Civil Design Consultant Level A Survey Completed Soil Borings completed and reviewed Design Review and Constructability Review completed 7

8 UG Transmission Design Engineering Cost Total Engineering costs is about 6% of the total project construction cost (excluding cost of materials) Subsurface Utility Engineering (SUE) cost is 50% of the total Engineering cost ( 3% of the total construction cost) 8

9 SUE Benefits Previous Projects Change Order Comparison Due To Utility Conflicts Level of SUE Performed Change Orders Received (Percentage of the Project Construction Cost) Project Construction Cost None 10% $66M MISS Utility Marking and test Pitting Utility Designation and Test Pitting 3% $32M 1.4% $22M 9

10 SUE Benefits (Continued) More accurate design More realistic budget and schedule Less risk for the contractor More contractor participation in the bid Proposals are within tolerance of the cost estimate. Less change orders Less design changes Less risk of dig-ins SUE Challenges Added engineering/design cost (upfront cost) Longer design phase Not all SUE services are equal 10

11 UG Electric Lines Hi Voltage Cables High pressure Pipe Type (HPPT) Self Contained Fluid Filled Gas Oil Dry Cables EPR (Ethylene propylene rubber) XLPE (Cros)s-linked polyethylene Pipe type SCFF XLPE EPR 11

12 UG Electric Lines Construct Pipe Type Duct Banks Direct buried Submarine Manholes (Vaults) Trenchless installations Pipe type Direct Buried 12 Concrete Encased Duct Bank

13 Working In Close Proximity To Pepco Underground Facilities See PROCESS AND PROCEDURES FOR WORKING IN CLOSE PROXIMITY TO PEPCO UNDERGROUND FACILITIES Transmission vs. Distribution Functions Standards Management Records In addition to submitting utility request through Pepco regular channel, please contact PHI Transmission Engineering directly. (Contact info provided at the end of this presentation) Test Holes General Pipe Type Feeders Only PHI approved contractors are qualified to do test holes on PHI transmission lines 13

14 PHI UG Transmission Engineering Contact For UG Transmission utility requests contact: AaRae Alexander Associate Engineer and copy Afshin Avvali, P.E. Sr Engineer or Mousa Hejazi, P.E. Manager Engineering

15 Q & A 15

TECHNICAL PROCEDURE TABLE OF CONTENTS

TECHNICAL PROCEDURE TABLE OF CONTENTS TECHNICAL PROCEDURE No. Page DATE: 07/3/5 CATEGORY UNDERGROUND STRUCTURES SUBJECT OF SMUD s UNDERGROUND TRANSMISSION TABLE OF CONTENTS PURPOSE... 2 2 REFERENCES... 2 3 MINIMUM REQUIREMENTS... 2 4 RELATED

More information

SUBSURFACE UTILITY ENGINEERING

SUBSURFACE UTILITY ENGINEERING SUBSURFACE UTILITY ENGINEERING Standard of Care for Subsurface Utility Engineering Bill Pickering, P.E. District Engineer Dave Cole, P.S. Senior Vice President SUBSURFACE UTILITY ENGINEERING Standard of

More information

Underground System Design TADP 547

Underground System Design TADP 547 Underground System Design TADP 547 Transmission Cable Installation Presentation 5.4 Instructor: Frank Frentzas Transmission Design and Installation When planning an underground power cables system the

More information

Underground Conduit Systems

Underground Conduit Systems Section 32 Underground Conduit Systems Note 1 under the title of Sec. 32 defines how the NESC uses the following terms: Duct Conduit Conduit system The common trade use of these terms is slightly different

More information

Goals of today s presentation

Goals of today s presentation Fast-tracked Fircrest Pipe Bursting Project Leads to Success Darrel Frame, P.E. - Civil Engineer - Murray, Smith and Associates, Inc. Goals of today s presentation Review of City of Fircrest Pipe Bursting

More information

EIC Climate Change Technology Conference 2015

EIC Climate Change Technology Conference 2015 CSA S250-11 and CI/ASCE 38-02 How to effectively utilize these Utility Standards for the 3 R s Reduce Reuse Recycle during Infrastructure projects. CCTC 2015 Paper Number #1570110557 Lawrence Arcand 1,

More information

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger

More information

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

345 kv Underground Report

345 kv Underground Report POWER ENGINEERS, INC. February 24, 2010 345 kv Underground Report PROJECT NUMBER: 117910 PROJECT CONTACT: Mike Mueller Richard C. Mues, PE EMAIL: mike.mueller@powereng.com rmues@powereng.com PHONE: 314-851-4050

More information

Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street

Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street 1600 SW Western Blvd, Suite 100 Corvallis, OR 97333 (541) 766-4601(desk) GOrmsby@TriAxisEng.com August 30, 2013 Robert White Power Services Manager Tillamook People s Utility District 1115 Pacific Avenue

More information

MEMORANDUM TO THE INDUSTRY

MEMORANDUM TO THE INDUSTRY MEMORANDUM TO THE INDUSTRY TO: FROM: All Builders, Developers, Engineers, Site Contractors, and Distributors Engaging in the Installation of Loudoun Water s Systems Huy Tran P.E., LEED AP, Manager of Land

More information

SECTION GS10300 UNDERGROUND TRENCHING AND EXCAVATION CONSIDERATIONS

SECTION GS10300 UNDERGROUND TRENCHING AND EXCAVATION CONSIDERATIONS SECTION GS10300 UNDERGROUND TRENCHING AND EXCAVATION CONSIDERATIONS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings, general provisions of the contract, including General and Supplementary Conditions

More information

Sealing solutions against constant water pressure CABLE AND PIPE SEALS FOR UNDERGROUND APPLICATIONS

Sealing solutions against constant water pressure CABLE AND PIPE SEALS FOR UNDERGROUND APPLICATIONS Sealing solutions against constant water pressure CABLE AND PIPE SEALS FOR UNDERGROUND APPLICATIONS Do you have problems with water ingress? Effective cable and pipe sealing is essential when you provide

More information

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control

More information

September 30, Re: Formal Case No. 1116

September 30, Re: Formal Case No. 1116 ^pepco A PHI Comparnj Andrea H. Harper Associate General Counsel EP1132 701 Ninth Street, NW Suite 1100. 10*^ Floor Washington. DC 20068 202 331-6649 202 331-6767 Fax ahharper'

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD) ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

SECTION 10 UTILITIES

SECTION 10 UTILITIES SECTION 10 UTILITIES Virtually every highway construction project in the State of New Jersey impacts utility facilities. The Designer shall examine and seek alternatives to minimize or eliminate the impact

More information

To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations. From: Juan M. Ulloa, P.E.

To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations. From: Juan M. Ulloa, P.E. AGENDA ITEM NO.: 5.C.1 ADMINISTRATIVE REPORT NO.: 2014-47 To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations From: Juan M. Ulloa, P.E. Approved by:

More information

Designated Entity Pre-qualification Submittal. Pepco Holdings, Inc. or PHI

Designated Entity Pre-qualification Submittal. Pepco Holdings, Inc. or PHI Designated Entity Pre-qualification Submittal By Pepco Holdings, Inc. or PHI On behalf of its affiliates Potomac Electric Power Company (Pepco), Delmarva Power & Light Company (Delmarva), and Atlantic

More information

DESIGNER EFFECTIVE GUIDELINES

DESIGNER EFFECTIVE GUIDELINES DESIGNER EFFECTIVE GUIDELINES Adopted by the Pennsylvania One Call System, Inc. Board of Directors January 30, 2008 Disclaimer of Liability Copyright 2008 This Guide has been prepared as an educational

More information

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 www.norcalpug.com Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 Kathryn Wallin Bennett Trenchless Bo Botteicher Underground Solutions Project Area Existing Sewers 66-inch

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 4/14/2015 Project 150249 Addendum No. 2 PID No. 81747 FRA IR 270

More information

TECHNICAL NOTE HDPE Pipe and Utility Crossings

TECHNICAL NOTE HDPE Pipe and Utility Crossings TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are

More information

APPENDIX D DIRECTIONAL BORING GUIDELINES

APPENDIX D DIRECTIONAL BORING GUIDELINES The City of Winnipeg Appendix D Bid Opportunity No. 180 163-2016 Page 1 of 1 Template Version: C420150806 - RW APPENDIX D DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional Boring

More information

APPENDIX D C DIRECTIONAL BORING GUIDELINES

APPENDIX D C DIRECTIONAL BORING GUIDELINES The City of Winnipeg Appendix C D Bid Opportunity No. 19-2015 18 2015 Page 1 of 1 Template Version: C420150116 - RW APPENDIX D C DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional

More information

Excavations and Blind Penetrations into Walls & Floors

Excavations and Blind Penetrations into Walls & Floors Excavations and Blind Penetrations into Walls & Floors (Instructions for using JLab DIGGING, EXCAVATING, FLOOR/WALL PENETRATION PERMIT REQUEST) Permits are required on JLAB property for any penetrations

More information

Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure

Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure 1 Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure General Meeting of the IEEE Power Engineering Society Panel Discussion Predictive Reliability

More information

3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES

3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.2 Underground Lines [below sections will be renumbered at a later date] 5.0 GENERAL REQUIREMENTS 5.1 Underground transmission lines 69 kv and

More information

SECTION MEDIUM-VOLTAGE CABLES PART 1 GENERAL

SECTION MEDIUM-VOLTAGE CABLES PART 1 GENERAL SECTION 260513 - MEDIUM-VOLTAGE CABLES PART 1 GENERAL 1.1 SECTION INCLUDES A. Medium voltage cable. B. Cable terminations. C. This specification describes single conductor EPR (Ethylene-propylene-rubber)

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Digital Transformation and Operational Intelligence in Utilities. Agendra Kumar President, Esri India

Digital Transformation and Operational Intelligence in Utilities. Agendra Kumar President, Esri India Digital Transformation and Operational Intelligence in Utilities Agendra Kumar President, Esri India Agenda Market Observations and Trends Role of GIS Vision and Road Map for Smart Utilities Summary and

More information

Transmission Owner Asset Management

Transmission Owner Asset Management Transmission Owner Asset Management Pieces of Asset Management New customers, load growth, repairs, maintenance, operational issues, etc. All the pieces make up the asset management plan for repair or

More information

Geotechnical Investigations Water Main Construction

Geotechnical Investigations Water Main Construction Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine

More information

Fair Oaks Water District

Fair Oaks Water District Fair Oaks Water District Request for Proposal To develop a set of construction drawings, construction specifications and bid documents for a Skyway Well in Fair Oaks. (FOWD Job #C19WTSTSTHD) Prepared by:

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

ECS INSTALLATION OF POWER CABLES AND JOINTS IN AIR

ECS INSTALLATION OF POWER CABLES AND JOINTS IN AIR Document Number: ECS 02-0031 Network(s): Summary: ENGINEERING CONSTRUCTION STANDARD ECS 02-0031 INSTALLATION OF POWER CABLES AND JOINTS IN AIR EPN, LPN, SPN This standard describes the decision making

More information

Professional Surveying and Engineering Services

Professional Surveying and Engineering Services Professional Surveying and Engineering Services Survey, Site Design, Right-of-Way, Permitting, Project Management The Best Choice! Right-of-Way and Permitting Right-of-Way Acquisition Team Fishel is proficient

More information

CHAPTER 13. New January 1, 2013 SUE. Subsurface Utility Engineering. Designation and Location. Chapter Contents

CHAPTER 13. New January 1, 2013 SUE. Subsurface Utility Engineering. Designation and Location. Chapter Contents CHAPTER 13 New January 1, 2013 SUE Subsurface Utility Engineering Designation and Location Chapter Contents Sec. 13.01 Sec. 13.02 Sec. 13.03 Sec. 13.04 Sec. 13.05 Sec. 13.06 Introduction Standards and

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

Replacement of the Broadcast Tower for KJZZ and KBAQ

Replacement of the Broadcast Tower for KJZZ and KBAQ Replacement of the Broadcast Tower for KJZZ and KBAQ ADDENDUM NO. 2 RFP #3280-9 12/24/2014 The following clarifications, changes, additions or deletions for this project shall be made to the Contract Documents;

More information

For the 6/15/2017 meeting review

For the 6/15/2017 meeting review For the 6/15/2017 meeting review PJM DESIGNATED ENTITY DESIGN STANDARDS UNDERGROUND LINES 1.0 PURPOSE These standards represent the minimum criteria by which a competitively solicited facility must be

More information

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E. How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study Jessica M. W. Hou, P.E., BCEE Agenda What is a jack and bore? What is does the Underground

More information

Sustainable Utility Construction: Methods and Techniques

Sustainable Utility Construction: Methods and Techniques Sustainable Utility Construction: Methods and Techniques September 19, 2011 APWA Congress Denver, Colorado Murv Morehead ROW Coordinator Overland Park, Kansas Monty Zimmerman Row Manager Lenexa, Kansas

More information

16300 HIGH VOLTAGE DISTRIBUTION

16300 HIGH VOLTAGE DISTRIBUTION 16300 HIGH VOLTAGE DISTRIBUTION PART 1: GENERAL 1.01 WORK INCLUDED A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served

More information

Improving ROI by Leveraging ArcGIS Server for Data Analytics. Subrahmanyam(Subbu) Pendyala Anil Jayavarapu

Improving ROI by Leveraging ArcGIS Server for Data Analytics. Subrahmanyam(Subbu) Pendyala Anil Jayavarapu Improving ROI by Leveraging Server for Data Analytics Subrahmanyam(Subbu) Pendyala Anil Jayavarapu June 29, 2016 Agenda About Pepco Holdings GIS at Pepco Holdings Analytics Business Needs Current Approach:

More information

System-wide Sewer Rehabilitation: Efficiency in Design. May 5, 2011 OWEA Collection Systems Specialty Workshop Eric Dunn, PE Brown and Caldwell

System-wide Sewer Rehabilitation: Efficiency in Design. May 5, 2011 OWEA Collection Systems Specialty Workshop Eric Dunn, PE Brown and Caldwell System-wide Sewer Rehabilitation: Efficiency in Design May 5, 2011 OWEA Collection Systems Specialty Workshop Eric Dunn, PE Brown and Caldwell 1 Introduction Large, system-wide sewer system rehabilitation

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

Preventing Cross Bores. Solutions & Progress

Preventing Cross Bores. Solutions & Progress Preventing Cross Bores Solutions & Progress February, 2012 Mark H. Bruce President Cross Bore Safety Association www.crossboresafety.org Copyright 2012 Cross Bore Safety Association All rights reserved.

More information

How PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works

How PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works How PGW Manages Pipeline Installation in a Congested Underground Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works Summary Philadelphia by the numbers Philadelphia Gas

More information

Uniform Color Code and Marking Guidelines

Uniform Color Code and Marking Guidelines APPENDIX B Uniform Color Code and Marking Guidelines The information contained in this appendix is intended to supplement information for existing practices found within CGA Best Practices. 8/ BEST PRACTICES

More information

TERRADYN CONSULTANTS, LLC

TERRADYN CONSULTANTS, LLC TERRADYN CONSULTANTS, LLC 10/30/17 Civil Engineering - Land Planning - Stormwater Design - Environmental Permitting 1644 Justin Brown, Code Enforcement Officer Town of Falmouth 271 Falmouth Road Falmouth,

More information

SUBSURFACE UTILITY ENGINEERING: Designation/Location Techniques Used in Utility Conflict Management

SUBSURFACE UTILITY ENGINEERING: Designation/Location Techniques Used in Utility Conflict Management SUBSURFACE UTILITY ENGINEERING: Designation/Location Techniques Used in Utility Conflict Management Presented to: 2018 LADOTD TRANSPORTATION CONFERENCE Andrew McLaughlin, PLS Craig Polifrone Dennis Hymel

More information

STATEMENT QUALIFICATIONS FOR UTILITY SERVICES

STATEMENT QUALIFICATIONS FOR UTILITY SERVICES STATEMENT OF QUALIFICATIONS FOR UTILITY SERVICES Included in this Statement of Qualifications... Introducing Ourselves Key Personnel Joel R. Colwell, P.E. Ramon A. Herrera, P.E. Terry L. McDaniel, P.E.

More information

ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION

ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION ML&P ELECTRICAL FACILITY CLEARANCE REQUIREMENTS FOR CONSTRUCTION OR MAINTENANCE NEAR ELECTRICAL FACILITIES July 31, 2014 MUNICIPAL LIGHT & POWER ELECTRICAL

More information

7/20/2017 MEETING--- POST MEETING MARKUP

7/20/2017 MEETING--- POST MEETING MARKUP 7/20/2017 MEETING--- POST MEETING MARKUP 3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.2 Underground Lines [below sections will be renumbered at a later date] 5.0 GENERAL REQUIREMENTS 5.1

More information

Underground Cost Analysis; Option 10 and 11 - TRTP Project. Project Segment 8A Corridor October 21, 2012

Underground Cost Analysis; Option 10 and 11 - TRTP Project. Project Segment 8A Corridor October 21, 2012 Underground Cost Analysis; Option 10 and 11 - TRTP Project Project Segment 8A Corridor October 21, 2012 SCE Cost Overview on Option 10 (Single Circuit XLPE 3 Cables per Phase) and Option 11 (Single Circuit

More information

APPLICATION FOR RIGHT OF WAY PERMIT

APPLICATION FOR RIGHT OF WAY PERMIT City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER

More information

A Trenchless Approach to Lift Station Elimination

A Trenchless Approach to Lift Station Elimination A Trenchless Approach to Lift Station Elimination PRESENTED BY: SCOTT MAUGHN, P.E. DANIEL HUFFINES, P.E. FSAWWA Fall Conference November 27, 2018 1 AGENDA Project Background Preliminary Investigations

More information

PJM S UNDERGROUND & SUBMARINE TRANSMISSION CABLE RATING METHODOLOGY GUIDELINES

PJM S UNDERGROUND & SUBMARINE TRANSMISSION CABLE RATING METHODOLOGY GUIDELINES PJM S UNDERGROUND & SUBMARINE TRANSMISSION CABLE RATING METHODOLOGY GUIDELINES PARTICIPATING COMPANIES: Baltimore Gas and Electric Company (BGE), Pepco Holdings Inc. (PHI), PECO Energy (PECO), PPL, Public

More information

10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS

10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS 10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS Engineering, Procurement and Construction Management (EPCM) costs for Balance of Plant (BOP) installations seriously

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements. SECTION 31 20 00 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating soil and other material for surface improvements. B. Excavating soil and other material for drainage basins. C. Placing fill. D. Compaction

More information

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project Welcome Metro North Transmission Project Burnaby Community Information Open House March 8, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.

More information

Chapter 5. Utilities

Chapter 5. Utilities Chapter 5 Utilities 5.1 General...5-1 5.2 Utility Accommodation Manual...5-2 5.3 Location of Existing Utilities...5-3 5.3.1 Quality Levels of Utility Locates...5-3 5.4 Subsurface Utility Engineering...5-5

More information

Overcoming Transmission Line Siting Challenges. Case Study Middletown-Norwalk Project

Overcoming Transmission Line Siting Challenges. Case Study Middletown-Norwalk Project Overcoming Transmission Line Siting Challenges Case Study Middletown-Norwalk Project NARUC Transmission Workshop April 21, 2011 Albert W. Cretella, III Presentation Overview Project Description Need, Route

More information

ADMINISTRATIVE DIRECTIVE #CS-04

ADMINISTRATIVE DIRECTIVE #CS-04 HILLSBOROUGH COUNTY Office of the County Administrator ADMINISTRATIVE DIRECTIVE #CS-04 SUBJECT: EFFECTIVE DATE: UTILITY COORDINATION PROCEDURES FOR HILLSBOROUGH COUNTY CONSTRUCTION PROJECTS WITHIN COUNTY

More information

FLEXWELL FHK. Flexible district heating pipe

FLEXWELL FHK. Flexible district heating pipe FLEXWELL FHK Flexible district heating pipe The intelligent alternative: safe and economical through simplified planning and minimal civil construction costs Safety furnished by the corrugated steel casing

More information

SAFETY ORIENTATION FOR EXCAVATION WORKERS

SAFETY ORIENTATION FOR EXCAVATION WORKERS SAFETY ORIENTATION FOR EXCAVATION WORKERS Every excavation job is different: soil, work zone characteristics, near by structures, utilities, nothing is ever the same. Because of this, an effective worker

More information

FLORIDA ARMY NATIONAL GUARD, CBJTC CACTF FIBER OPTIC CABLE INSTALLATION, PN SCOPE OF WORK, 28 MARCH 2012

FLORIDA ARMY NATIONAL GUARD, CBJTC CACTF FIBER OPTIC CABLE INSTALLATION, PN SCOPE OF WORK, 28 MARCH 2012 1. General. 1.1 The project will require the provisioning and installation of conduits, hand holes, pull boxes and fiber optic cable extending several miles from a point of beginning to the Combined Arms

More information

RFP Questions and Answers 1 (Pre-Bid Meeting)

RFP Questions and Answers 1 (Pre-Bid Meeting) RFP 40860 Questions and Answers 1 (Pre-Bid Meeting) Amendment to Page 8 of 99 of the Proposal for RFQ 40860 to change from 120 days stated to 270 days for completion of project. Clarifications of drawings:

More information

Task Order Authorization

Task Order Authorization Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement

More information

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 WM-T5-01 Problems Realized with Contractor-Proposed Pilot Tube Auger Boring Rebecca

More information

FORM 1 S Design Certification List - Wastewater Agreements

FORM 1 S Design Certification List - Wastewater Agreements FORM 1 S Design Certification List - Wastewater Agreements Job Description Location Developer / Owner Developer / Owner Contact Details Consultant Gippsland Water Drawing Numbers Notes: 1 Where the word

More information

1 of 5. University of Leicester, University Road, Leicester, LE1 7RH T W.

1 of 5. University of Leicester, University Road, Leicester, LE1 7RH T W. Document Control Rev Date By Comments A Jun 16 L. Davies Technical Review Update B Jun 17 L. Davies Technical Review Update C Dec 17 UoL Sign off for release Design Guidance 1. Any underground jointing

More information

E kv Transmission Line Underground Relocation Project. Evaluation of National Grid s 2014 Underground Estimate

E kv Transmission Line Underground Relocation Project. Evaluation of National Grid s 2014 Underground Estimate E-183 115 kv Transmission Line Underground Relocation Project Evaluation of National Grid s 2014 Underground Estimate April 10, 2015 Introduction Ferrucci Russo P.C. contacted Power Delivery Consultants,

More information

What is the motivation/goal of Senate Bill ?

What is the motivation/goal of Senate Bill ? This document is disseminated by the American Council of Engineering Companies of Colorado (ACEC Colorado) in the interest of information exchange. ACEC Colorado assumes no liability for the use of the

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 1C-5 Issue date: July 2012 SUBSURFACE (GEOTECHNICAL) INVESTIGATION PROCEDURE 1. General: Provide project specific foundation and soils (geotechnical) investigation as required to comply with

More information

leinfelder Fauna Spotter Catcher Architects. Engineers. Scientists

leinfelder Fauna Spotter Catcher Architects. Engineers. Scientists Horizons leinfelder Fauna Spotter Catcher Kleinfelder has a large team of accredited, highly competent, and experienced personnel trained to meet construction milestones and manage animal welfare. Architects.

More information

FUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC

FUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC Fusible C-900 Fusible C-905 FPVC Installations Trenchless Horizontal directional drilling Sliplining Pipe bursting Jack-and-bore carrier pipe Open-Cut Applications Features and Benefits Gasketless, leak-free,

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

WORK IN THE VICINITY OF UNDERGROUND ASSETS

WORK IN THE VICINITY OF UNDERGROUND ASSETS CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF UNDERGROUND ASSETS EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD

More information

Information Bulletin:

Information Bulletin: Equipment Advisory Adv. No. 2015012 R1 Supersedes: Adv. No. 2015012 R0 Issue Date: April 21, 2015 File: 1649.10 Information Bulletin: Backfill Revision Note Revised text since R0 edition is shown with

More information

PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE

PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE SUGGESTED STANDARD SPECIFICATION January, 2012 Prepared by International Pipe Bursting Association Thanks to the following participants for the development

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

The New You Inventory It, Map It and Manage It. SUE, GIS and EAM Combine into a Powerful Result

The New You Inventory It, Map It and Manage It. SUE, GIS and EAM Combine into a Powerful Result The New You Inventory It, Map It and Manage It SUE, GIS and EAM Combine into a Powerful Result January 12, 2006 Issues Emergency Preparedness Emergency Response Security Facilities Maintenance Regulatory

More information

7/17/2017 Page 1 of 5

7/17/2017 Page 1 of 5 HORIZONTAL DIRECTIONAL DRILLING AND BORING PART 1.0 GENERAL 1.1 DESCRIPTION This section covers the work necessary for the installation of conduit duct banks by directionally controlled horizontal drilling

More information

1 Revised: 2019 Edition

1 Revised: 2019 Edition STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with

More information

Horizontal Directional Drilling

Horizontal Directional Drilling Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social

More information

Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation

Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation 1. Scope of Work 1.1. Provide civil and electrical engineering services for the Nocatee 230/26kV Substation.

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 60502-2 Second edition 2005-03 Power cables with extruded insulation and their accessories for rated voltages from 1 kv (U m = 1,2 kv) up to 30 kv (U m = 36 kv) Part 2: Cables

More information

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with

More information

Course name : Outside Plant - Fibre Optics Civil Works Professional Knowledge and Skills for Certification

Course name : Outside Plant - Fibre Optics Civil Works Professional Knowledge and Skills for Certification Course name : Outside Plant - Fibre Optics Civil Works Professional Knowledge and Skills for Certification Course Detail: DURATION: 5 days TARGET GROUP: Any person who needs to do trenching, duct installation,

More information

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV Network(s): Summary: ENGINEERING INSTRUCTION EI 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV EPN, LPN, SPN This engineering instruction details the minimum requirements acceptable for the installation

More information

YOUR GROUND DRILLING PARTNERS.

YOUR GROUND DRILLING PARTNERS. YOUR GROUND DRILLING PARTNERS INDEX 2. ABOUT US 3. OUR SERVICES 4. OUR LOCATION 5. HORIZONTAL DRILLING 6. DIRECTIONAL BORING PROCESS 9. HDD DRILLING METHOD 12. MACHINE DETAILS 13. POLYETHYLENE PIPE CONDUIT

More information

Canadian Guidelines for Safe Excavation in the Vicinity of the Bell Network

Canadian Guidelines for Safe Excavation in the Vicinity of the Bell Network Canadian Guidelines for Safe Excavation in the Vicinity of the Bell Network 2018 Introduction Table of Contents Page Canada s largest telecommunications company, Bell Canada, provides its customers with

More information

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE General Provisions Western Municipal Water District (WMWD) requests a qualified Design Consultant

More information