1 PHI s Underground Use of SUE in Transmission Design Process Subsurface Utility Engineering & Asset Management American Council of Engineering Companies/Maryland Presented by: Pepco Underground Transmission March 28,
2 Agenda Background About Pepco Holdings Pepco holdings Quick Facts PHI UG Transmission Design Process (Civil) UG Transmission Design Engineering Cost SUE Benefits / Challenges UG Electric Lines UG Electric Lines Construct Working In Close Proximity To Pepco Underground Facilities PHI UG Transmission Engineering Contact Q & A 2
3 About Pepco Holdings Approximately 2 million customers in Delaware, the District of Columbia, Maryland and New Jersey Atlantic City Electric, Delmarva Power and Pepco provide regulated electricity service Delmarva Power also provides natural gas service 3
4 Pepco Holdings Quick Facts Service territory: 8,340 square miles Customers served Atlantic City Electric: 547,000 electric Delmarva Power: 515,000 electric 130,000 natural gas Pepco: 842,000 electric Total population served: 5.4 million PHI Service Territory As of 2/19/16 4
5 PHI UG Transmission Design Process (Civil) Underground Transmission Design Guide Formally Issued in June 2016 Project Steps: Initiate Based on system need a concept is created Route Analysis o Level D survey for all possible routes o Level B survey in and around substations to ensure feasibility of approaching subs o Preferred route selected based on Route Matrix 30% Design Conduct Site Topography and Level B Survey Design Horizontal Alignment 60% Design Conduct Level A survey Complete Soil Borings & Geotech report Design Vertical Alignment 90% Design Complete Design details Obtain Applicable Permits Finalize design Issue for Construction Complete SOW for bid and award Example of PHI Design Checklist Checklists created to verify all information is provided during the each step of the design Complete Design Review at 30%, 60%, 90% and IFC stages In-field Constructability Review completed at 30%, 60% and as needed 5
6 PHI UG Transmission Design Process (Civil) 30% Design Topographic survey completed Level B Survey completed Horizontal alignment designed Constructability and Design reviews completed Example of 30% Design Submittal from Civil Design Consultant 6
7 PHI UG Transmission Design Process (Civil) 60% Design Example of 60% Design Submittal from Civil Design Consultant Level A Survey Completed Soil Borings completed and reviewed Design Review and Constructability Review completed 7
8 UG Transmission Design Engineering Cost Total Engineering costs is about 6% of the total project construction cost (excluding cost of materials) Subsurface Utility Engineering (SUE) cost is 50% of the total Engineering cost ( 3% of the total construction cost) 8
9 SUE Benefits Previous Projects Change Order Comparison Due To Utility Conflicts Level of SUE Performed Change Orders Received (Percentage of the Project Construction Cost) Project Construction Cost None 10% $66M MISS Utility Marking and test Pitting Utility Designation and Test Pitting 3% $32M 1.4% $22M 9
10 SUE Benefits (Continued) More accurate design More realistic budget and schedule Less risk for the contractor More contractor participation in the bid Proposals are within tolerance of the cost estimate. Less change orders Less design changes Less risk of dig-ins SUE Challenges Added engineering/design cost (upfront cost) Longer design phase Not all SUE services are equal 10
11 UG Electric Lines Hi Voltage Cables High pressure Pipe Type (HPPT) Self Contained Fluid Filled Gas Oil Dry Cables EPR (Ethylene propylene rubber) XLPE (Cros)s-linked polyethylene Pipe type SCFF XLPE EPR 11
12 UG Electric Lines Construct Pipe Type Duct Banks Direct buried Submarine Manholes (Vaults) Trenchless installations Pipe type Direct Buried 12 Concrete Encased Duct Bank
13 Working In Close Proximity To Pepco Underground Facilities See PROCESS AND PROCEDURES FOR WORKING IN CLOSE PROXIMITY TO PEPCO UNDERGROUND FACILITIES Transmission vs. Distribution Functions Standards Management Records In addition to submitting utility request through Pepco regular channel, please contact PHI Transmission Engineering directly. (Contact info provided at the end of this presentation) Test Holes General Pipe Type Feeders Only PHI approved contractors are qualified to do test holes on PHI transmission lines 13
14 PHI UG Transmission Engineering Contact For UG Transmission utility requests contact: AaRae Alexander Associate Engineer and copy Afshin Avvali, P.E. Sr Engineer or Mousa Hejazi, P.E. Manager Engineering
15 Q & A 15
TECHNICAL PROCEDURE TABLE OF CONTENTS
TECHNICAL PROCEDURE No. Page DATE: 07/3/5 CATEGORY UNDERGROUND STRUCTURES SUBJECT OF SMUD s UNDERGROUND TRANSMISSION TABLE OF CONTENTS PURPOSE... 2 2 REFERENCES... 2 3 MINIMUM REQUIREMENTS... 2 4 RELATED
More informationSUBSURFACE UTILITY ENGINEERING
SUBSURFACE UTILITY ENGINEERING Standard of Care for Subsurface Utility Engineering Bill Pickering, P.E. District Engineer Dave Cole, P.S. Senior Vice President SUBSURFACE UTILITY ENGINEERING Standard of
More informationUnderground System Design TADP 547
Underground System Design TADP 547 Transmission Cable Installation Presentation 5.4 Instructor: Frank Frentzas Transmission Design and Installation When planning an underground power cables system the
More informationUnderground Conduit Systems
Section 32 Underground Conduit Systems Note 1 under the title of Sec. 32 defines how the NESC uses the following terms: Duct Conduit Conduit system The common trade use of these terms is slightly different
More informationGoals of today s presentation
Fast-tracked Fircrest Pipe Bursting Project Leads to Success Darrel Frame, P.E. - Civil Engineer - Murray, Smith and Associates, Inc. Goals of today s presentation Review of City of Fircrest Pipe Bursting
More informationEIC Climate Change Technology Conference 2015
CSA S250-11 and CI/ASCE 38-02 How to effectively utilize these Utility Standards for the 3 R s Reduce Reuse Recycle during Infrastructure projects. CCTC 2015 Paper Number #1570110557 Lawrence Arcand 1,
More informationCS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS
TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger
More informationH. Underground Transmission System Design
H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,
More information345 kv Underground Report
POWER ENGINEERS, INC. February 24, 2010 345 kv Underground Report PROJECT NUMBER: 117910 PROJECT CONTACT: Mike Mueller Richard C. Mues, PE EMAIL: mike.mueller@powereng.com rmues@powereng.com PHONE: 314-851-4050
More informationSubject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street
1600 SW Western Blvd, Suite 100 Corvallis, OR 97333 (541) 766-4601(desk) GOrmsby@TriAxisEng.com August 30, 2013 Robert White Power Services Manager Tillamook People s Utility District 1115 Pacific Avenue
More informationMEMORANDUM TO THE INDUSTRY
MEMORANDUM TO THE INDUSTRY TO: FROM: All Builders, Developers, Engineers, Site Contractors, and Distributors Engaging in the Installation of Loudoun Water s Systems Huy Tran P.E., LEED AP, Manager of Land
More informationSECTION GS10300 UNDERGROUND TRENCHING AND EXCAVATION CONSIDERATIONS
SECTION GS10300 UNDERGROUND TRENCHING AND EXCAVATION CONSIDERATIONS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings, general provisions of the contract, including General and Supplementary Conditions
More informationSealing solutions against constant water pressure CABLE AND PIPE SEALS FOR UNDERGROUND APPLICATIONS
Sealing solutions against constant water pressure CABLE AND PIPE SEALS FOR UNDERGROUND APPLICATIONS Do you have problems with water ingress? Effective cable and pipe sealing is essential when you provide
More informationSliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control
More informationSeptember 30, Re: Formal Case No. 1116
^pepco A PHI Comparnj Andrea H. Harper Associate General Counsel EP1132 701 Ninth Street, NW Suite 1100. 10*^ Floor Washington. DC 20068 202 331-6649 202 331-6767 Fax ahharper'
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)
ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationSECTION 10 UTILITIES
SECTION 10 UTILITIES Virtually every highway construction project in the State of New Jersey impacts utility facilities. The Designer shall examine and seek alternatives to minimize or eliminate the impact
More informationTo: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations. From: Juan M. Ulloa, P.E.
AGENDA ITEM NO.: 5.C.1 ADMINISTRATIVE REPORT NO.: 2014-47 To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations From: Juan M. Ulloa, P.E. Approved by:
More informationDesignated Entity Pre-qualification Submittal. Pepco Holdings, Inc. or PHI
Designated Entity Pre-qualification Submittal By Pepco Holdings, Inc. or PHI On behalf of its affiliates Potomac Electric Power Company (Pepco), Delmarva Power & Light Company (Delmarva), and Atlantic
More informationDESIGNER EFFECTIVE GUIDELINES
DESIGNER EFFECTIVE GUIDELINES Adopted by the Pennsylvania One Call System, Inc. Board of Directors January 30, 2008 Disclaimer of Liability Copyright 2008 This Guide has been prepared as an educational
More informationKathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016
www.norcalpug.com Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 Kathryn Wallin Bennett Trenchless Bo Botteicher Underground Solutions Project Area Existing Sewers 66-inch
More informationOhio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director
Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 4/14/2015 Project 150249 Addendum No. 2 PID No. 81747 FRA IR 270
More informationTECHNICAL NOTE HDPE Pipe and Utility Crossings
TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are
More informationAPPENDIX D DIRECTIONAL BORING GUIDELINES
The City of Winnipeg Appendix D Bid Opportunity No. 180 163-2016 Page 1 of 1 Template Version: C420150806 - RW APPENDIX D DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional Boring
More informationAPPENDIX D C DIRECTIONAL BORING GUIDELINES
The City of Winnipeg Appendix C D Bid Opportunity No. 19-2015 18 2015 Page 1 of 1 Template Version: C420150116 - RW APPENDIX D C DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional
More informationExcavations and Blind Penetrations into Walls & Floors
Excavations and Blind Penetrations into Walls & Floors (Instructions for using JLab DIGGING, EXCAVATING, FLOOR/WALL PENETRATION PERMIT REQUEST) Permits are required on JLAB property for any penetrations
More informationPepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure
1 Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure General Meeting of the IEEE Power Engineering Society Panel Discussion Predictive Reliability
More information3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES
3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.2 Underground Lines [below sections will be renumbered at a later date] 5.0 GENERAL REQUIREMENTS 5.1 Underground transmission lines 69 kv and
More informationSECTION MEDIUM-VOLTAGE CABLES PART 1 GENERAL
SECTION 260513 - MEDIUM-VOLTAGE CABLES PART 1 GENERAL 1.1 SECTION INCLUDES A. Medium voltage cable. B. Cable terminations. C. This specification describes single conductor EPR (Ethylene-propylene-rubber)
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationDigital Transformation and Operational Intelligence in Utilities. Agendra Kumar President, Esri India
Digital Transformation and Operational Intelligence in Utilities Agendra Kumar President, Esri India Agenda Market Observations and Trends Role of GIS Vision and Road Map for Smart Utilities Summary and
More informationTransmission Owner Asset Management
Transmission Owner Asset Management Pieces of Asset Management New customers, load growth, repairs, maintenance, operational issues, etc. All the pieces make up the asset management plan for repair or
More informationGeotechnical Investigations Water Main Construction
Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine
More informationFair Oaks Water District
Fair Oaks Water District Request for Proposal To develop a set of construction drawings, construction specifications and bid documents for a Skyway Well in Fair Oaks. (FOWD Job #C19WTSTSTHD) Prepared by:
More informationSECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.
PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record
More informationECS INSTALLATION OF POWER CABLES AND JOINTS IN AIR
Document Number: ECS 02-0031 Network(s): Summary: ENGINEERING CONSTRUCTION STANDARD ECS 02-0031 INSTALLATION OF POWER CABLES AND JOINTS IN AIR EPN, LPN, SPN This standard describes the decision making
More informationProfessional Surveying and Engineering Services
Professional Surveying and Engineering Services Survey, Site Design, Right-of-Way, Permitting, Project Management The Best Choice! Right-of-Way and Permitting Right-of-Way Acquisition Team Fishel is proficient
More informationCHAPTER 13. New January 1, 2013 SUE. Subsurface Utility Engineering. Designation and Location. Chapter Contents
CHAPTER 13 New January 1, 2013 SUE Subsurface Utility Engineering Designation and Location Chapter Contents Sec. 13.01 Sec. 13.02 Sec. 13.03 Sec. 13.04 Sec. 13.05 Sec. 13.06 Introduction Standards and
More informationE. CONSTRUCTION PROCEDURES
E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications
More informationReplacement of the Broadcast Tower for KJZZ and KBAQ
Replacement of the Broadcast Tower for KJZZ and KBAQ ADDENDUM NO. 2 RFP #3280-9 12/24/2014 The following clarifications, changes, additions or deletions for this project shall be made to the Contract Documents;
More informationFor the 6/15/2017 meeting review
For the 6/15/2017 meeting review PJM DESIGNATED ENTITY DESIGN STANDARDS UNDERGROUND LINES 1.0 PURPOSE These standards represent the minimum criteria by which a competitively solicited facility must be
More informationTS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE
TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION
More informationHow to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.
How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study Jessica M. W. Hou, P.E., BCEE Agenda What is a jack and bore? What is does the Underground
More informationSustainable Utility Construction: Methods and Techniques
Sustainable Utility Construction: Methods and Techniques September 19, 2011 APWA Congress Denver, Colorado Murv Morehead ROW Coordinator Overland Park, Kansas Monty Zimmerman Row Manager Lenexa, Kansas
More information16300 HIGH VOLTAGE DISTRIBUTION
16300 HIGH VOLTAGE DISTRIBUTION PART 1: GENERAL 1.01 WORK INCLUDED A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served
More informationImproving ROI by Leveraging ArcGIS Server for Data Analytics. Subrahmanyam(Subbu) Pendyala Anil Jayavarapu
Improving ROI by Leveraging Server for Data Analytics Subrahmanyam(Subbu) Pendyala Anil Jayavarapu June 29, 2016 Agenda About Pepco Holdings GIS at Pepco Holdings Analytics Business Needs Current Approach:
More informationSystem-wide Sewer Rehabilitation: Efficiency in Design. May 5, 2011 OWEA Collection Systems Specialty Workshop Eric Dunn, PE Brown and Caldwell
System-wide Sewer Rehabilitation: Efficiency in Design May 5, 2011 OWEA Collection Systems Specialty Workshop Eric Dunn, PE Brown and Caldwell 1 Introduction Large, system-wide sewer system rehabilitation
More informationUNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1
GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe
More informationPreventing Cross Bores. Solutions & Progress
Preventing Cross Bores Solutions & Progress February, 2012 Mark H. Bruce President Cross Bore Safety Association www.crossboresafety.org Copyright 2012 Cross Bore Safety Association All rights reserved.
More informationHow PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works
How PGW Manages Pipeline Installation in a Congested Underground Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works Summary Philadelphia by the numbers Philadelphia Gas
More informationUniform Color Code and Marking Guidelines
APPENDIX B Uniform Color Code and Marking Guidelines The information contained in this appendix is intended to supplement information for existing practices found within CGA Best Practices. 8/ BEST PRACTICES
More informationTERRADYN CONSULTANTS, LLC
TERRADYN CONSULTANTS, LLC 10/30/17 Civil Engineering - Land Planning - Stormwater Design - Environmental Permitting 1644 Justin Brown, Code Enforcement Officer Town of Falmouth 271 Falmouth Road Falmouth,
More informationSUBSURFACE UTILITY ENGINEERING: Designation/Location Techniques Used in Utility Conflict Management
SUBSURFACE UTILITY ENGINEERING: Designation/Location Techniques Used in Utility Conflict Management Presented to: 2018 LADOTD TRANSPORTATION CONFERENCE Andrew McLaughlin, PLS Craig Polifrone Dennis Hymel
More informationSTATEMENT QUALIFICATIONS FOR UTILITY SERVICES
STATEMENT OF QUALIFICATIONS FOR UTILITY SERVICES Included in this Statement of Qualifications... Introducing Ourselves Key Personnel Joel R. Colwell, P.E. Ramon A. Herrera, P.E. Terry L. McDaniel, P.E.
More informationANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION
ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION ML&P ELECTRICAL FACILITY CLEARANCE REQUIREMENTS FOR CONSTRUCTION OR MAINTENANCE NEAR ELECTRICAL FACILITIES July 31, 2014 MUNICIPAL LIGHT & POWER ELECTRICAL
More information7/20/2017 MEETING--- POST MEETING MARKUP
7/20/2017 MEETING--- POST MEETING MARKUP 3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.2 Underground Lines [below sections will be renumbered at a later date] 5.0 GENERAL REQUIREMENTS 5.1
More informationUnderground Cost Analysis; Option 10 and 11 - TRTP Project. Project Segment 8A Corridor October 21, 2012
Underground Cost Analysis; Option 10 and 11 - TRTP Project Project Segment 8A Corridor October 21, 2012 SCE Cost Overview on Option 10 (Single Circuit XLPE 3 Cables per Phase) and Option 11 (Single Circuit
More informationAPPLICATION FOR RIGHT OF WAY PERMIT
City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER
More informationA Trenchless Approach to Lift Station Elimination
A Trenchless Approach to Lift Station Elimination PRESENTED BY: SCOTT MAUGHN, P.E. DANIEL HUFFINES, P.E. FSAWWA Fall Conference November 27, 2018 1 AGENDA Project Background Preliminary Investigations
More informationPJM S UNDERGROUND & SUBMARINE TRANSMISSION CABLE RATING METHODOLOGY GUIDELINES
PJM S UNDERGROUND & SUBMARINE TRANSMISSION CABLE RATING METHODOLOGY GUIDELINES PARTICIPATING COMPANIES: Baltimore Gas and Electric Company (BGE), Pepco Holdings Inc. (PHI), PECO Energy (PECO), PPL, Public
More information10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS
10 CRITICAL STEPS REQUIRED FOR EFFECTIVE EPC BOP COST MANAGEMENT RENEWABLE ENERGY PROJECTS Engineering, Procurement and Construction Management (EPCM) costs for Balance of Plant (BOP) installations seriously
More informationSPECIAL SPECIFICATION 6666 Charter Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,
More informationSECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.
SECTION 31 20 00 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating soil and other material for surface improvements. B. Excavating soil and other material for drainage basins. C. Placing fill. D. Compaction
More informationWelcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project
Welcome Metro North Transmission Project Burnaby Community Information Open House March 8, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.
More informationChapter 5. Utilities
Chapter 5 Utilities 5.1 General...5-1 5.2 Utility Accommodation Manual...5-2 5.3 Location of Existing Utilities...5-3 5.3.1 Quality Levels of Utility Locates...5-3 5.4 Subsurface Utility Engineering...5-5
More informationOvercoming Transmission Line Siting Challenges. Case Study Middletown-Norwalk Project
Overcoming Transmission Line Siting Challenges Case Study Middletown-Norwalk Project NARUC Transmission Workshop April 21, 2011 Albert W. Cretella, III Presentation Overview Project Description Need, Route
More informationADMINISTRATIVE DIRECTIVE #CS-04
HILLSBOROUGH COUNTY Office of the County Administrator ADMINISTRATIVE DIRECTIVE #CS-04 SUBJECT: EFFECTIVE DATE: UTILITY COORDINATION PROCEDURES FOR HILLSBOROUGH COUNTY CONSTRUCTION PROJECTS WITHIN COUNTY
More informationFLEXWELL FHK. Flexible district heating pipe
FLEXWELL FHK Flexible district heating pipe The intelligent alternative: safe and economical through simplified planning and minimal civil construction costs Safety furnished by the corrugated steel casing
More informationSAFETY ORIENTATION FOR EXCAVATION WORKERS
SAFETY ORIENTATION FOR EXCAVATION WORKERS Every excavation job is different: soil, work zone characteristics, near by structures, utilities, nothing is ever the same. Because of this, an effective worker
More informationFLORIDA ARMY NATIONAL GUARD, CBJTC CACTF FIBER OPTIC CABLE INSTALLATION, PN SCOPE OF WORK, 28 MARCH 2012
1. General. 1.1 The project will require the provisioning and installation of conduits, hand holes, pull boxes and fiber optic cable extending several miles from a point of beginning to the Combined Arms
More informationRFP Questions and Answers 1 (Pre-Bid Meeting)
RFP 40860 Questions and Answers 1 (Pre-Bid Meeting) Amendment to Page 8 of 99 of the Proposal for RFQ 40860 to change from 120 days stated to 270 days for completion of project. Clarifications of drawings:
More informationTask Order Authorization
Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement
More informationProblems Realized with Contractor-Proposed Pilot Tube Auger Boring
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 WM-T5-01 Problems Realized with Contractor-Proposed Pilot Tube Auger Boring Rebecca
More informationFORM 1 S Design Certification List - Wastewater Agreements
FORM 1 S Design Certification List - Wastewater Agreements Job Description Location Developer / Owner Developer / Owner Contact Details Consultant Gippsland Water Drawing Numbers Notes: 1 Where the word
More information1 of 5. University of Leicester, University Road, Leicester, LE1 7RH T W.
Document Control Rev Date By Comments A Jun 16 L. Davies Technical Review Update B Jun 17 L. Davies Technical Review Update C Dec 17 UoL Sign off for release Design Guidance 1. Any underground jointing
More informationE kv Transmission Line Underground Relocation Project. Evaluation of National Grid s 2014 Underground Estimate
E-183 115 kv Transmission Line Underground Relocation Project Evaluation of National Grid s 2014 Underground Estimate April 10, 2015 Introduction Ferrucci Russo P.C. contacted Power Delivery Consultants,
More informationWhat is the motivation/goal of Senate Bill ?
This document is disseminated by the American Council of Engineering Companies of Colorado (ACEC Colorado) in the interest of information exchange. ACEC Colorado assumes no liability for the use of the
More informationSTATE UNIVERSITY CONSTRUCTION FUND
DIRECTIVE 1C-5 Issue date: July 2012 SUBSURFACE (GEOTECHNICAL) INVESTIGATION PROCEDURE 1. General: Provide project specific foundation and soils (geotechnical) investigation as required to comply with
More informationleinfelder Fauna Spotter Catcher Architects. Engineers. Scientists
Horizons leinfelder Fauna Spotter Catcher Kleinfelder has a large team of accredited, highly competent, and experienced personnel trained to meet construction milestones and manage animal welfare. Architects.
More informationFUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC
Fusible C-900 Fusible C-905 FPVC Installations Trenchless Horizontal directional drilling Sliplining Pipe bursting Jack-and-bore carrier pipe Open-Cut Applications Features and Benefits Gasketless, leak-free,
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01
More informationWORK IN THE VICINITY OF UNDERGROUND ASSETS
CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF UNDERGROUND ASSETS EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD
More informationInformation Bulletin:
Equipment Advisory Adv. No. 2015012 R1 Supersedes: Adv. No. 2015012 R0 Issue Date: April 21, 2015 File: 1649.10 Information Bulletin: Backfill Revision Note Revised text since R0 edition is shown with
More informationPIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE
PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE SUGGESTED STANDARD SPECIFICATION January, 2012 Prepared by International Pipe Bursting Association Thanks to the following participants for the development
More informationSPECIAL SPECIFICATION 6664 Level (3) Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,
More informationThe New You Inventory It, Map It and Manage It. SUE, GIS and EAM Combine into a Powerful Result
The New You Inventory It, Map It and Manage It SUE, GIS and EAM Combine into a Powerful Result January 12, 2006 Issues Emergency Preparedness Emergency Response Security Facilities Maintenance Regulatory
More information7/17/2017 Page 1 of 5
HORIZONTAL DIRECTIONAL DRILLING AND BORING PART 1.0 GENERAL 1.1 DESCRIPTION This section covers the work necessary for the installation of conduit duct banks by directionally controlled horizontal drilling
More information1 Revised: 2019 Edition
STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with
More informationHorizontal Directional Drilling
Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social
More informationAppendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation
Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation 1. Scope of Work 1.1. Provide civil and electrical engineering services for the Nocatee 230/26kV Substation.
More informationINTERNATIONAL STANDARD
INTERNATIONAL STANDARD IEC 60502-2 Second edition 2005-03 Power cables with extruded insulation and their accessories for rated voltages from 1 kv (U m = 1,2 kv) up to 30 kv (U m = 36 kv) Part 2: Cables
More informationGUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES
State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water
More informationSPECIAL SPECIFICATION 6658 Time Warner Communications System
2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable
More informationSection Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers
STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with
More informationCourse name : Outside Plant - Fibre Optics Civil Works Professional Knowledge and Skills for Certification
Course name : Outside Plant - Fibre Optics Civil Works Professional Knowledge and Skills for Certification Course Detail: DURATION: 5 days TARGET GROUP: Any person who needs to do trenching, duct installation,
More informationEI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV
Network(s): Summary: ENGINEERING INSTRUCTION EI 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV EPN, LPN, SPN This engineering instruction details the minimum requirements acceptable for the installation
More informationYOUR GROUND DRILLING PARTNERS.
YOUR GROUND DRILLING PARTNERS INDEX 2. ABOUT US 3. OUR SERVICES 4. OUR LOCATION 5. HORIZONTAL DRILLING 6. DIRECTIONAL BORING PROCESS 9. HDD DRILLING METHOD 12. MACHINE DETAILS 13. POLYETHYLENE PIPE CONDUIT
More informationCanadian Guidelines for Safe Excavation in the Vicinity of the Bell Network
Canadian Guidelines for Safe Excavation in the Vicinity of the Bell Network 2018 Introduction Table of Contents Page Canada s largest telecommunications company, Bell Canada, provides its customers with
More informationREQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE
REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE General Provisions Western Municipal Water District (WMWD) requests a qualified Design Consultant
More information