1 Photograph Ministry of Defence Environmental Statement Volume 3: Non-Technical Summary Prepared for: +City Deal, Plymouth City Council Economic Development Department Marine Industries Production Campus Proposed Redevelopment of South Yard, Devonport, Plymouth November 2014 UNITED KINGDOM & IRELAND

2 REVISION SCHEDULE Rev Date Details Prepared by Reviewed by Approved by 0 November 2014 Final for submission to local planning authority Charlotte Cook Technical Director And Steffan Shageer Ian Roach Associate Director Environment and Planning Ian Roach Associate Director Environment and Planning Senior Assistant Environmental Consultant URS Infrastructure & Environment UK Limited Mayflower House Armada Way Plymouth Devon PL1 1LD (T)

3 Preface This document is Volume 3: Non-Technical Summary of the Environmental Statement that accompanies the outline planning application for the proposed redevelopment at South Yard, Devonport. The Environmental Statement also comprises the following separate volumes: Volume 1: Main Text and Figures Volume 2: Appendices

4 Limitations URS Infrastructure & Environment UK Limited ( URS ) has prepared this report for the use of +City Deal, Plymouth City Council Economic Development Department ( Client ) in accordance with the Agreement under which our services were performed. No other warranty, expressed or implied, is made as to the professional advice included in this Report or any other services provided by URS. Where the conclusions and recommendations contained in this report are based upon information provided by others it is upon the assumption that all relevant information has been provided by those parties from whom it has been requested and that such information is accurate. Information obtained by URS has not been independently verified by URS, unless otherwise stated in the Report. The methodology adopted and the sources of information used by URS in providing its services are outlined in this Report. The work described in this Report was undertaken between September 2014 and November 2014 and is based on the conditions encountered and the information available during the said period of time. The scope of this Report and the services are accordingly factually limited by these circumstances. Where assessments of works or costs identified in this Report are made, such assessments are based upon the information available at the time and where appropriate are subject to further investigations or information which may become available. Certain statements made in the Report that are not historical facts may constitute estimates, projections or other forward-looking statements and even though they are based on reasonable assumptions as of the date of the Report, such forward-looking statements by their nature involve risks and uncertainties. Copyright This Report is the copyright of URS Infrastructure & Environment UK Limited. Any unauthorised reproduction or usage by any person other than the addressee is strictly prohibited.

5 Introduction The Proposed Development forms part of the Plymouth and South West Peninsula City Deal which was announced in January The City Deal is a ground breaking agreement with government that aims to deliver economic growth in the south west. The deal area covers Plymouth, Cornwall, Devon, Torbay and Somerset. The City Deal will tackle low rates of productivity by investing in three key areas: Marine Development, Business Support and a Deal for Young People. The proposed development comprises a Marine Industries Production Campus located within South Yard, Devonport, Plymouth. The south west peninsula, despite its coastlines and marine centres, still lacks accessible employment sites close to major marine companies and deep water berths. This has a continuing impact on the ability of supply chain companies to grow and develop. The aim of the Proposed Development is to grow the marine and advanced manufacturing sectors across the peninsula by providing additional facilities for the relocation and development of supply chain companies. It is anticipated that these new facilities will link marine centres and assets across the peninsula. Public sector funding worth 21m will be invested to facilitate the development, and it is hoped to lever in a further 59m of private sector investment to develop the Marine Industries Production Campus, creating over 1,200 new jobs.

6 Environmental Impact Assessment The Proposed Development is subject to an Environmental Impact Assessment (EIA). The EIA procedure requires the developer to undertake certain environmental studies and compile an Environmental Statement describing the likely significant effects of the Proposed Development on the environment and proposed measures to mitigate these effects. This document is a non-technical summary of the Environmental Statement. The Environmental Statement and non-technical summary have been prepared by the Plymouth office of environmental consultants, URS Environment & Infrastructure UK Limited (URS). URS has considerable experience of EIA in Plymouth and across the UK. URS is a registrant to the industry-standard EIA Quality Mark scheme of the Institute of Environmental Management and Assessment and is entitled to bear the following logo. Outline Planning Application An application for outline planning permission has been made for the Proposed Development by +City Deal, Plymouth City Council Economic Development, as the developer for this project. Local Planning Authority The Local Planning Authority that will determine the outline planning application is Plymouth City Council. There is a clear organisational distinction between Plymouth City Council s two roles as developer and Local Planning Authority. Ministry of Defence and Other Parties The land is currently part of the Devonport Dockyard, however as part of a joint venture between the Ministry of Defence, Defence Infrastructure Organisation, Homes and Communities Agency and Plymouth City Council Economic Development, the land has been identified as available for release to the market for development. The proposals have been developed in full consultation and agreement with these parties, as well as existing businesses within the site and in the surroundings. Public Consultation Two public consultation events were carried out on 7 October and 11 October The feedback from these events has informed the proposals.

7 Site and Surroundings The Site is located at the western edge of Devonport, within the historic dockyard adjacent to Granby Way and Gun Wharf / Morice Town. The Site has been used as a Royal Naval Dockyard, and for associated military activity, since the late 17th Century. The whole of South Yard covers an area of approximately 35 hectares (86 acres). The site of the proposed development comprises land known as Area 1 and Area 5 of South Yard, whose areas are approximately 2.04 hectares and 3.84 hectares respectively, making a total site area of approximately 5.88 hectares. The extents of Area 1 and Area 5 comprising the site, as well as the surrounding context, are shown in the aerial photograph over the page. Historically Area 1 and Area 5 were amongst the earliest parts of the dockyard to be developed; they have been used by the Royal Navy for at least 300 years. The Site continues to be used for various dockyard activities. Within the Site there are a number of existing land uses and buildings including: Area 1 Former car park; and Naval museum spread across several buildings (one of which, the former Pay Office, is shown below). Area 5 Land between three docks (known as Number 2 Dock, Number 3 Dock and Number 4 Dock); Numerous buildings with various dockyard-related uses; Access road linking South Yard and Morice Yard (and North Yard beyond); and External storage areas. There is a large retaining wall which separates Area 1 from Area 5. There are several Listed Buildings within the site.

8

9 Proposed Development The proposed development comprises a total of 25,854 square metres (278,290 square feet) of employment space, achieved partly by converting some existing buildings into employment use and partly by constructing new buildings. The most important of the existing historic buildings will be retained and refurbished. There will also be parking (including street level parking and a multi-storey car park), landscaping and a café provided. The Proposed Development will create an improved sense of arrival to South Yard, benefitting existing businesses such as Princess Yachts as well as new employers. The Proposed master plan is illustrated over the page. Naval Heritage Collection The Naval Heritage Collection is currently housed in four existing buildings within the site. There is an agreement which will provide for the Naval Heritage Collection to be consolidated but retained on the site until an alternative arrangement has been agreed as part of Plymouth s History Centre project. While not a planning matter, there is assurance that the part of the site that will continue to house the heritage collection and will not be redeveloped until the future of the heritage collection has been appropriately secured.

10

11 Ecology Survey and assessment scope Surveys and a desk study were undertaken between June 2011 and October 2014 including: Ecological desk-study Ecological walkover survey Bat surveys Existing conditions The following designated ecological sites, and habitats and species on Site, were considered: Impact assessment The construction of the Proposed Development would not lead to significant effects on designated sites, either alone or in combination with other projects and plans. Temporary noise disturbance from the construction activities has the potential to impact upon migratory fish using the Tamar estuary. There will not be any piling in the river, and the type of piling that is proposed on the Site is drilled auger piling, which causes less noise and vibration than driven piling. The effects on fish are not expected to be significant. Type European Sites within 5km Statutory and Non-statutory Sites within 2 km Habitats on Site Species on Site Name Plymouth Sound and Estuaries Special Area of Conservation Tamar Estuaries Complex Special Protection Area Tamar Estuaries Complex Site of Special Scientific Interest (SSSI) Mount Wise SSSI Richmond Walk SSSI St John s Lake SSSI Western King SSSI Railway Biodiversity Network Feature Devonport Park Biodiversity Network Feature Improved grassland, scrub and scattered trees Buildings and hard standing Bats potentially roosting in buildings, foraging and commuting Breeding and wintering birds There are records of a number of bat species present within the Site and our surveys have recorded bats flying through the site. No evidence of bats was found during the building inspections, although this does not entirely rule out their presence and the Proposed Development therefore has the potential to have a significant effect on bats. Broad-leaved trees, buildings and flat-roofed buildings on the Site are suitable roosting and nesting sites for breeding, wintering and migrant birds. Significant effects could occur as a result of habitat loss and noise disturbance during construction. Mitigation and monitoring Strict environmental management controls will be in place during construction works. Night time lighting within the Site will need to be minimised and directed into the Site, away from the designated ecological sites. It is recommended that during test piling some underwater noise monitoring is undertaken to verify that there are no significant effects on migratory fish, or to change working practices or propose further mitigation measures if required. There are five buildings that have been identified that should, as a precautionary measure, be checked for hibernating bats during the winter months (December February 2014/15). A precautionary wintering bird survey should also be undertaken during the winter months. An update to this Environmental Statement will be submitted in February 2015 to further assess impacts on bats

12 and birds and, if necessary, specify mitigation measures. Any vegetation removal and demolition works should ideally be timed to avoid the breeding bird season (generally taken to be March to August inclusive) to prevent disturbance to nesting birds. If this is not possible then standard mitigation will be implemented, involving a suitably experienced Ecologist checking for any nesting birds no more than 24 hours prior to any works being undertaken and if a nest is found then it should remain undisturbed until the young have fledged. Conclusion The majority of the effects associated with the construction stage of the Proposed Development are assessed as not significant, except for the potential effects on roosting bats and wintering birds which could be significant if protected bat or bird species are identified in forthcoming surveys. Further survey and assessment during winter 2014/15 is required. Small areas of low quality habitat on Site will be lost during construction, which will lead to an initial, short term loss in biodiversity. However this will be compensated for by additional habitat creation that forms part of the Proposed Development. Once the proposed habitats have established, the overall effect upon biodiversity will be positive.

13 Heritage Survey and assessment scope An assessment of the impact of the proposed redevelopment on various heritage assets on Site was carried out. In addition, to ensure that all impacts have been fully considered, the study was expanded to assess features of heritage value 250m from the boundary of the Site. The Proposed Development was considered in terms of its impact upon the heritage assets and this was weighted according to the value assigned to that asset. lower level were more industrial and operational in form. The complex arrangement of the heritage assets within the study area is highlighted by the identification of some 36 designated (i.e. the most important) assets, although only 9 of these are within the application Site. A further 13 nondesignated assets fall within the Site. Impact assessment Considerable care was taken during the design process to ensure that the Proposed Development was mindful of the value of the heritage features within the site. This is demonstrated in the results of the assessment, which show how limited the impact of the Proposed Development would be upon the identified heritage assets within the Site. With the exception of the removal of a section of parapet walling to the terrace wall, removal of one capstan at the head of the dock, and demolition of several non-designated buildings (including Building SO28 The Surgery ), few of the heritage assets will be affected. These effects are considered to have a modest impact upon the overall heritage value of the Site. Mitigation and monitoring Existing conditions A fully documented Heritage Baseline Assessment was undertaken to understand the development of the dockyard as a whole, and its national role as one of three key historic royal dockyards. This detailed study drew on a wide range of historic data to build up a clear picture of the historic evolution of South Yard and the buildings within it, complemented by detailed site visits. The heritage significance of the Site was described in terms of its potential for archeological deposits, and a full description of the individual buildings and structures, and their significance, has been prepared. Detailed building recording will take place prior to demolition. Whilst this recording would not mitigate the effects, given their low significance this is considered to be an appropriate monitoring measure. Conclusion The Proposed Development would involve minor impacts upon assets within the Site, with the exception of the proposed works to The Surgery, an unlisted building for which a moderate effect is identified. However, taken as a whole, none of the impacts are determined to be significant in terms of their effect on the heritage assets of the Site overall. Given the historic nature of Devonport Dockyard, the assessment needed to consider not only the significance of the existing heritage assets within the site, but also the form and function of the original building groupings. It was apparent that the upper level of the dockyard had a much more formal arrangement, whilst structures on the dockside,

14 Ground Conditions Survey and assessment scope An assessment has been undertaken of the potential impacts of ground contamination on humans, land and water. For harm to occur as a result of potential land contamination, three conditions need to be met: there needs to be a source of contamination; there needs to be a human or environmental feature that can be harmed by the contamination; and there needs to be a pathway between the two. Existing conditions Information on the Site and surrounding area is provided within a Phase 1 Land Quality Assessment report included in the Environmental Statement. The Site and the remainder of South Yard (extending to the south) have had an industrial land use since the pre 1800 s and the surrounding land use (to the north, and east) is mixed residential and commercial use. The majority of the contemporary industries in the immediate vicinity of the Site are now inactive, such as the scrapyard which was adjacent to the north in Holman Buildings Road, but this area has since been redeveloped and it is assumed that any associated contamination would have been dealt with at this time. The Dockyard operations (current and historic) represent the most potentially contaminative industry in the locality. Impact assessment It is possible that soil and groundwater beneath the site is contaminated; there may also be ground gas present. These could all, in various ways, potentially affect construction workers, underlying groundwater, the nearby river, and the new buildings that are proposed. Mitigation and monitoring The most significant design measure is the incorporation of significant areas of hardstanding across the majority of the Site, preventing rain water from getting into Site soils, which in turn could then transfer any contaminants present into groundwater. Strict environmental management controls will be in place during construction works. There are also various standard practices that can be relied upon to mitigate contamination impacts, such as the incorporation of gas protection measures within new buildings; the utilisation of appropriate personal protective equipment by construction workers, and a procedure for dealing with unforeseen contamination. Further site investigations will allow these mitigation measures to be specified in detail, including if necessary Site clean-up works..

15 Conclusion Contaminated soils: Following the implementation of mitigation measures, the effects on ground and surface water, construction / maintenance workers, and the new built environment from contaminated soil are not considered significant. Further site investigations may also further reduce the risk to groundwater and surface water. Contaminated groundwater: Similarly the effects from groundwater contamination are not considered to be significant once mitigation measures are put in place. Again, further site investigations may also further reduce the risk to groundwater and surface water. Ground Gas: With the implementation of the mitigation measures the risk of an effect from ground gas on construction workers is not considered to be significant. Overall therefore, it is considered that provided appropriate mitigation, monitoring and control measures are employed during each phase of the development, the Proposed Development will not pose an increased risk to human health or the environment in relation to ground conditions.

16 Noise Survey assessment and scope An assessment of construction noise impacts has been undertaken based on likely construction activities and their associated noise and vibration impacts at residential properties close to the Site. The noise assessment for the completed development focuses on setting noise design criteria for future businesses plant and activities and assesses the site s suitability for office use. An assessment is also made of the impacts of road traffic noise. Existing conditions The Site is currently commercial / industrial in nature, with further commercial / industrial to the south, and residential to the north and east. All residential properties are of high sensitivity to noise, but commercial / industrial activities are of medium or low sensitivity. Noise monitoring was undertaken at three residential locations surrounding the Site in November This provided representative noise levels for daytime, evening and night. Impact assessment Demolition and Construction Demolition and excavation / earthworks using heavy plant are likely to be the main source of noise impacts at nearby properties. The construction and fitting out of the new buildings, and internal refurbishment of existing buildings, and associated landscaping works, are likely to result in lower noise levels. The potential for significant vibration impacts is likely to be limited just to piling works. However, the site benefits from an existing and substantial solid stone wall between the Site and residential properties to the north, which will provide significant screening, particularly at ground level. Construction noise would be audible. However, based on the likely nature of the construction works and the proximity of residential properties, the phased and temporary nature of the works, and the strict control of site activities including limited working hours noise minimisation measures, construction noise effects are not assessed as being significant. Operation Road Traffic: The largest traffic flow increases are anticipated on Granby Way (east and westbound); this being the key access route to the site. Increases of up to 17% are anticipated in 2017, but this would only equate to a traffic noise increase of less than 1 decibel, which is negligible and not significant. In the longer term, traffic flow increases on Granby Way could rise by 39% in 2027, which equates to a noise increase of 3 decibels. The effect is this is considered minor and not significant. For all other local roads assessed the traffic increases would be lower, negligible and not significant. Noise from Industrial Sources: Details of the new businesses and the exact uses of the buildings are not yet known. However, once the development is complete and fully operational the level of overall activity at the site will increase from current levels. Mitigation and monitoring Noise and vibration will be managed during construction, with mitigation measures to be prescribed and enforced through a Construction Environmental Management Plan. On-site, good practice procedure will be followed, such as use of hoarding. The assessment presents design parameters in the form of noise limits, that have been derived from the background noise measurements. Conclusion Through implementation of mitigation measures and industry best practice it is considered that construction noise and vibration effects can be controlled such that they would not be significant. Once the buildings start to be occupied, the predicted changes in road traffic noise on Granby Way indicate a minor adverse but not significant effect in the longer term. On all other local roads the traffic noise would be negligible. The buildings will have to be designed to certain noise standards such that significant effects will not occur.

17 Air Quality Survey assessment and scope The air quality assessment includes a study of the following: the impact of emissions of dust (including fine particulates) from construction activities on neighbouring residential properties; as well as the potential track out of material on vehicle tyres that could potentially affect roads leading from the site access; the impact of road traffic exhaust emissions (nitrogen dioxide and fine particles) to occur as a result of predicted changes in road traffic movements on the local road network as a result of the Proposed Development; and the impact of emissions generated by the proposed commercial and industrial activities on the Site. Existing conditions The closest residential properties are located adjacent to the northern boundary of the site, including on Cornwall Street, Albany Street, Cornwall Beach and Holmans Buildings. The precise uses of the proposed buildings are not yet known but emissions from Site activities could potentially include welding fumes, grinding emissions, and paint and coating fumes. These activities are expected to be small in scale, and any emissions are likely to be correspondingly small. Similar emissions from the existing dockyard are similar in type and scale. Once the new buildings start to become occupied there will be some increases to traffic flows on roads in the vicinity. These changes in traffic flows have been assessed against projected future traffic baseline flows for two future years: 2017 and These years represent the indicative opening year of the Proposed Development (2017), and the indicative completion year (2027). The Government sets air quality objective values for the protection of human health. In 2017 the traffic emissions are not predicted to exceed the air quality limit values at any location for any pollutant assessed. The largest predicted increase in nitrogen dioxide concentration is just 0.2 microgrammes per cubic metre at Chapel Street, with the Proposed Development increasing nitrogen dioxide levels from 31.3 to 31.5 microgrammes. The Government s objective value is This increase is negligible and not significant. To undertake the assessment of road traffic emissions a computer model has been used to quantify future pollution levels. Inputs into this model include local air quality background data obtained from Plymouth City Council, recent weather data, and existing and predicted future traffic flows. URS is currently conducting a nitrogen dioxide survey along several roads in the vicinity of the Site in order provide verification of the road traffic emissions model and an assessment of current conditions on and in the immediate vicinity of the Site. An update to the air quality assessment will be issued upon completion of this survey in February Impact assessment level without development 2017 level with development 40.0 National objective for protection of health During the construction phase, there is the potential for construction activities to increase dust concentrations at locations up to 350m from the Site boundary, and 50m from roads extending to 500m from the site access due to track out. Predicted annual average nitrogen dioxide concentrations at Chapel Street in 2017 (microgrammes per cubic metre)

18 For comparison, existing nitrogen dioxide levels in Royal Parade in the city centre already exceed the objective value by some way recent measurements have recorded levels of 75.0 microgrammes. In 2027 the assessment predicts even smaller changes as a result of the Proposed Development. Mitigation and monitoring Strict environmental management controls will be in place during construction works, which would include measures to minimise dust and mud on the roads. No other mitigation measures are considered to be necessary. Conclusion The effects of the construction and operation Proposed Development on air quality would not be significant.

19 Flood Risk Survey assessment and scope A Flood Risk Assessment (FRA) has been undertaken. The FRA seeks to identify and assess the risk of flooding to and from the development, and to outline how flood risk will be managed so that the development will remain safe throughout its lifetime. The FRA took into account the tidal flood risk posed by the Tamar Estuary, including considering the anticipated effects of climate change on sea level rise and wave action. The FRA also assessed the risk posed by all flood sources including surface water management at the site, to ensure flood risk to third parties is not increased. The assessment included a review of flood risk data from the Environment Agency and other data sources. In addition a site survey was undertaken. Existing conditions The majority of the Site is identified by the Environment Agency as falling within Flood Zone 1, where there is a low risk of flooding. The jetties fall within Flood Zone 2 where there is because of their location and level a medium risk from river or sea flooding. Impact assessment Drawing on guidance published in the National Planning Policy Framework the proposed light industrial and office uses in the new buildings are defined as Less Vulnerable. The new warehouse style buildings proposed around the jetties are defined as Water Compatible ; these uses are considered appropriate in all Flood Zones. The risk of the development flooding from a combined water level and wave action event was found to be the most likely within Area 5 closest to the river. The risk posed by other sources of flooding was considered low. An outline drainage strategy within the FRA proposes measures for the management of surface water on Site that would further reduce the existing risk posed by surface water and sewer flooding. With regard to the risk of flooding from the development, as the existing site is predominantly hardstanding and the proposals include some areas of open space / soft landscaping, the total hardstanding area, and therefore rate at which water runs off the Site, was not found to increase as a result of the Proposed Development. Mitigation and monitoring Recommendations have been made for flood resilient design measures including appropriate finished floor levels for the proposed buildings, whilst having regard to the need to provide level access for forklift trucks, etc into the structures. A Flood Management Plan is also recommended to manage the risk posed to the site during an extreme water level and wave event. The use of sustainable drainage systems will further reduce run-off from the development. As part of this development the possibility of providing a dedicated surface water sewer along the route of the proposed Vivid Approach Road could be explored. Conclusion The FRA found that the proposed uses as indicated in the masterplan are appropriate for the relevant parts of the site in which they would be located. The risk of flooding of the new development is low, other than for the warehouse buildings on the jetties in Area 5, which are considered capable of management and mitigation. No additional adverse effects are anticipated with regard to surface water runoff, given the existing state of the site, although a sustainable drainage system should be implemented where practical and reasonable.

20 Conclusions The redevelopment of approximately 5.88 hectares of the South Yard, Devonport, Plymouth as a Marine Industries and Production Campus has the potential to create over 1,200 jobs. An Environmental Impact Assessment has considered the effects of the Proposed Development during both its construction and its subsequent operation. Most of the effects of the Proposed Development have been assessed as not significant There are some exceptions in relation to ecology, where there are potentially significant effects on roosting bats and wintering birds during construction. They are classified as potentially significant as wintering bird and bat hibernation surveys have yet to be undertaken. Further surveys will take place over the winter of 2014/2015 and an Addendum to the Environmental Statement will be submitted in February 2015 to further assess impacts on bats and birds and, if necessary, specify mitigation measures. In conclusion the Proposed Development will deliver redevelopment and employment benefits for Plymouth, with minimal environmental effects.

21

Sustainability Statement

Sustainability Statement Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Sustainability Statement Doc Ref: 7.07 Appendix B.21 Greenwich Pumping Station

More information

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009 Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted

More information

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary Environmental Impact Assessment Report prepared by: Ecus Ltd. Brook Holt 3 Blackburn Road Sheffield S61 2DW 0114 266 9292 September 2013 Page Left Intentionally Blank 2 INTRODUCTION This Non Technical

More information

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices Crossrail Environmental Statement Volume 9c Appendices Westbourne Park Bus Garage Extension Environmental Statement Volume 2 Appendices 9c If you would like information about Crossrail in your language,

More information

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands Environmental Statement Non Technical Summary Anthony s Way Frindsbury June 2010 www.wyg.com creative minds safe hands Contents Section A Introduction Part 1 Background Part 2 Environmental Assessment

More information

Ravenhead Quarry. Environment Act Application for Determination of Conditions (ROMP) Environmental Statement Non Technical Summary

Ravenhead Quarry. Environment Act Application for Determination of Conditions (ROMP) Environmental Statement Non Technical Summary Ravenhead Quarry I Environment Act 1995 Application for Determination of Conditions (ROMP) Environmental Statement Non Technical Summary November 2013 Prepared for: Ibstock Bricks (1996) Limited UNITED

More information

2 ENVIRONMENTAL IMPACT ASSESSMENT

2 ENVIRONMENTAL IMPACT ASSESSMENT 2 ENVIRONMENTAL IMPACT ASSESSMENT Introduction 2.1 Environmental Impact Assessment (EIA) is required for certain categories of projects and involves a process of drawing together, in a systematic way,

More information

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement Wellington Dock Planning Application, Liverpool Non-Technical Summary for Environmental Statement INTRODUCTION United Utilities PLC (UU) has applied for planning permission for an extension to Liverpool

More information

West Calf. Close. Water Point. Hazelbank Farm. Moss End Cottage. Oughtershaw C/13/187. Stone

West Calf. Close. Water Point. Hazelbank Farm. Moss End Cottage. Oughtershaw C/13/187. Stone Beck Yorkshire Dales National Park Authority Application Code: Committee Date: 13/03/2018 Location: Barn, Oughtershaw Low Bull Ing West Calf Little Calf FB Oughtershaw Cattle Grid fall Stone West Calf

More information

Longbridge Town Centre Planning Application

Longbridge Town Centre Planning Application Longbridge Town Centre Planning Application Non-Technical Summary of the Environmental Statement January 2011 Introduction An application for Planning Permission has been submitted to Birmingham City Council

More information

Arcow Quarry, North Yorkshire

Arcow Quarry, North Yorkshire Arcow Quarry, North Yorkshire Non Technical Summary Planning applications for a railhead and associated development REVISION SCHEDULE Rev Date Details Prepared by Reviewed by Approved by 0 December 2013

More information

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement Non Technical Summary Business and Environmental Services A responsive County Council providing excellent and efficient local services

More information

CONCLUSIONS 14 CONTENTS

CONCLUSIONS 14 CONTENTS CONTENTS Introduction... 14-1 Traffic... 14-1 Air Quality... 14-1 Noise and Vibration... 14-2 Geology and Hydrology... 14-2 Landscape and Visual... 14-3 Ecology... 14-4 Cultural Heritage... 14-4 Population

More information

VIRIDOR WASTE MANAGEMENT LTD

VIRIDOR WASTE MANAGEMENT LTD VIRIDOR WASTE MANAGEMENT LTD Proposed re-phasing of landfilling operations; amended restoration levels and aftercare scheme; and provision of a new waste reception building with associated site infrastructure

More information

Seaham North Pier Environmental Impact Assessment Volume 1: Non-Technical Summary January 2014

Seaham North Pier Environmental Impact Assessment Volume 1: Non-Technical Summary January 2014 Seaham North Pier Environmental Impact Assessment Volume 1: Non-Technical Summary January 2014 CONTENTS INTRODUCTION SEAHAM NORTH PIER THE ENVIRONMENTAL IMPACT ASSESSMENT ENVIRONMENTAL EFFECTS INTRODUCTION

More information

ROYAL ARSENAL Buildings 10, 11 and Royal Carriage Square Foul Sewage & Utilities Report

ROYAL ARSENAL Buildings 10, 11 and Royal Carriage Square Foul Sewage & Utilities Report ROYAL ARSENAL Buildings 10, 11 and Royal Carriage Square Foul Sewage & Utilities Report Submitted to Berkeley Homes (East Thames) Limited Submitted by AECOM Scott House Alençon Link Basingstoke Hampshire

More information

In-combination and Cumulative Effects Assessment

In-combination and Cumulative Effects Assessment P O R T I S H E A D B R A N C H L I N E P R E L I M I N A R Y ENV I R O N M E N T A L I N F O R M A T I O N R E P O R T V O L U M E 2 C H A P T E R 18 In-combination and Cumulative Effects Assessment Table

More information

Central Park Mixed Use Development

Central Park Mixed Use Development Central Park Mixed Use Development Environmental Statement Non Technical Summary June 2012 Contents Section A Introduction Part 1 Part 2 Part 3 Background Environmental Assessment Site Description Section

More information

West Calf. Close. Water Point. Hazelbank Farm. Moss End Cottage. Oughtershaw C/13/187. Stone

West Calf. Close. Water Point. Hazelbank Farm. Moss End Cottage. Oughtershaw C/13/187. Stone Beck Yorkshire Dales National Park Authority Application Code: Committee Date: 10/04/2018 Location: Barn, Oughtershaw Low Bull Ing West Calf Little Calf FB Oughtershaw Cattle Grid Waterfall Stone West

More information

Ponds Farm, Environmental Statement Non-Technical Summary

Ponds Farm, Environmental Statement Non-Technical Summary Ponds Farm, Cogent Land LLP QUALITY MANAGEMENT Issue/revision Issue 1 Revision 1 Final Date 03/05/2012 04/05/2012 09/05/2012 Prepared by Matthew Shepherd Caroline Burn Caroline Burn Signature Checked by

More information

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary Sizewell B Dry Fuel Store Environmental Statement Non-Technical Summary NON TECHNICAL SUMMARY 1 INTRODUCTION This Non Technical Summary (NTS) is submitted as part of the application to extend the existing

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH DRD ROADS SERVICE, SOUTHERN DIVISION Environmental Statement, Volume 1 November 2005 Non Technical Summary i Introduction The Department for Regional

More information

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary Norfolk Minerals and Waste Local Plan Minerals Site Specific Allocations Development Plan Document (DPD) Single Issue Silica Sand Review Sustainability Appraisal Report Non-technical summary March 2016

More information

Preface. Gaia Power Ltd 71A High Street Yarm TS15 9BG. Tel: Web:

Preface. Gaia Power Ltd 71A High Street Yarm TS15 9BG. Tel: Web: Preface This document comprises the Environmental Statement and its Non- Technical Summary, which have been prepared in support of an application for planning consent for the construction of a biomass

More information

RMB Chivenor Flood Defence Scheme. Non-Technical Summary FINAL. Version 3.0

RMB Chivenor Flood Defence Scheme. Non-Technical Summary FINAL. Version 3.0 RMB Chivenor Flood Defence Scheme Non-Technical Summary FINAL Version 3.0 RMB CHIVENOR FLOOD DEFENCE SCHEME ENVIRONMENTAL STATEMENT CONTENTS 1 INTRODUCTION AND BACKGROUND II 2 THE PROPOSED PROJECT III

More information

5. Environmental issues and methodology

5. Environmental issues and methodology 5. Environmental issues and methodology 5 Environmental issues and methodology Introduction 5.1 The methodology used to carry out the environmental impact assessment (EIA) is set out in this chapter. This

More information

Ironstone Quarry Wind Energy Project Environmental Statement

Ironstone Quarry Wind Energy Project Environmental Statement Ironstone Quarry Wind Energy Project Environmental Statement Non Technical Summary April 2011 Introduction Waste Recycling Group (WRG) Ltd is seeking permission to construct and operate a four turbine

More information

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref: Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by

More information

IROPI: National politics v environmental decisions

IROPI: National politics v environmental decisions Bruce Munro National Environmental Assessment Service Environment Agency Abstract IROPI: National politics v environmental decisions As a public body responsible for flood risk management in England and

More information

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4.1 INTRODUCTION This section describes the broad principles of the methodology adopted for the EIA of the Proposed Development. EIA is a procedure required

More information

DELEGATED REPORT. Reason To ensure that any impermeable areas created during the filming process does not have a permanent impact on the site runoff.

DELEGATED REPORT. Reason To ensure that any impermeable areas created during the filming process does not have a permanent impact on the site runoff. DELEGATED REPORT APPLICATION NO. 16/03324/PRIOR LOCATION Hartland Park Bramshot Lane Fleet Hampshire PROPOSAL Notification for Prior Approval for the Temporary Use of Building or Land for the Purpose of

More information

GC001: Lambert s Transport/Europa Tyres, Station Road, Gosberton Risegate

GC001: Lambert s Transport/Europa Tyres, Station Road, Gosberton Risegate GC001: Lambert s Transport/Europa Tyres, Station Road, Gosberton Risegate Sustainability Objective 1. To provide a mix of sustainably designed new housing to provide everybody in South East Lincolnshire

More information

Napier Gateway Environmental Statement Non-technical Summary

Napier Gateway Environmental Statement Non-technical Summary Napier Gateway Environmental Statement Non-technical Summary ENVIRONMENT J2 Global Corporation Ltd Napier NON-TECHNICAL SUMMARY www.bwbconsulting.com ENVIRONMENT J2 Global Corporation Ltd Napier NON-TECHNICAL

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories: 5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION The scope of the EIA falls under three broad categories: technical scope; spatial scope; and temporal scope. The scoping process for the

More information

PROPOSED MIXED USE DEVELOPMENT

PROPOSED MIXED USE DEVELOPMENT J Routledge & Sons PROPOSED MIXED USE DEVELOPMENT Land at Tanhouse Lane, Widnes Environmental Statement: Non-Technical Summary Planning Application: 05/00057/OUTEIA Tanhouse Lane Environmental Statement

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

Table of Contents. O Devaney Gardens. Page i. Page Number. Section. 1 Introduction

Table of Contents. O Devaney Gardens. Page i. Page Number. Section. 1 Introduction Section 1 Introduction Page Number 1.1 Introduction 2 1.2 Screening - Requirement for an EIA 5 1.3 Purpose of this EIA 6 1.4 Objectives of this EIA 6 1.5 Scoping 10 1.6 Format and Structure of this EIS

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Thorn Turn Winter Maintenance and Highways Depot

Thorn Turn Winter Maintenance and Highways Depot Thorn Turn Winter Maintenance and Highways Depot Non-Technical Summary Central Bedfordshire Council 12 May 2015 1 Notice This document and its contents have been prepared and are intended solely for Central

More information

Environment Agency Guidance on Requirements for Land Contamination Reports. July 2005

Environment Agency Guidance on Requirements for Land Contamination Reports. July 2005 Environment Agency Guidance on Requirements for Land Contamination Reports July 2005 ENVIRONMENT AGENCY GUIDANCE ON REQUIREMENTS FOR LAND CONTAMINATION REPORTS Context Who is this guidance aimed at? Developers,

More information

Preston Road, Brighton

Preston Road, Brighton Sensible Ecological Survey Solutions 137-147 Preston Road, Brighton For: Urban Splash Prepared by: Dr David Bell Sensible Ecological Survey Solutions Ltd. Registered Address: 1 Red Gables Pepper Street

More information

an Inspector appointed by the Secretary of State for Communities and Local Government

an Inspector appointed by the Secretary of State for Communities and Local Government Appeal Decision Site visit made on 20 September 2016 by John Dowsett MA DipURP DipUD MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government Decision date: 7 th November

More information

Rising Sun. Scaffold Hill. Flood Risk Assessment

Rising Sun. Scaffold Hill. Flood Risk Assessment Rising Sun Scaffold Hill Flood Risk Assessment August 2010 Contents 1.0 Introduction... 4 2.0 Site Description... 5 3.0 Legislative Framework... 6 4.0 Flood Risk... 10 5.0 Surface Water Drainage... 11

More information

Siemens Plc & London Development Agency Urban Sustainability Centre Environmental Statement

Siemens Plc & London Development Agency Urban Sustainability Centre Environmental Statement Siemens Plc & London Development Agency Urban Sustainability Centre Siemens Plc & London Development Agency Urban Sustainability Centre Non-Technical Summary July 2010 This report takes into account the

More information

Environmental Statement Non-Technical Summary Rectory Farm, Hounslow

Environmental Statement Non-Technical Summary Rectory Farm, Hounslow Environmental Statement Non-Technical Summary Rectory Farm, Hounslow Introduction This document is the Non-Technical Summary (NTS) of the Environmental Statement (ES) for a proposed development at the

More information

Working on flood embankments: Essential environmental considerations

Working on flood embankments: Essential environmental considerations Working on flood embankments: Essential environmental considerations Information for project managers, engineers and contractors When undertaking any work on or adjacent to coastal and estuarine flood

More information

New U.S. Embassy, Nine Elms Lane ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY

New U.S. Embassy, Nine Elms Lane ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY 1. Introduction The Government of the United States of America (specifically the Unites States Department of State - hereafter referred to as the Applicant ) is seeking to build a new Embassy in London

More information

Southshore residential red zone: Summary of Technical Information as at September Area ID: 1. Purpose of this document

Southshore residential red zone: Summary of Technical Information as at September Area ID: 1. Purpose of this document Southshore residential red zone: Summary of Technical Information as at September 2016 Area ID: 1 Purpose of this document The following information is a summary of the local environmental values, conditions

More information

Harewood Whin Waste Transfer Station Environmental Statement

Harewood Whin Waste Transfer Station Environmental Statement Harewood Whin Waste Transfer Station Environmental Statement This document is the Environmental Statement for the proposed Waste Transfer Station at the site of the Harewood Whin Resource Recovery Facility,

More information

Environmental Statement Non Technical Summary. Liverpool Waters September 2010

Environmental Statement Non Technical Summary. Liverpool Waters September 2010 Environmental Statement Non Technical Summary Liverpool Waters September 2010 Contents Section A Introduction Part 1 Background Part 2 Environmental Assessment Part 3 Site Description Section B The Proposals

More information

Berth 9 Quay Extension Environmental Statement Non-Technical Summary

Berth 9 Quay Extension Environmental Statement Non-Technical Summary Berth 9 Quay Extension Hutchison Ports UK Ltd July 2013 Final Report 9Y0150 CONTENTS Page 1 PROJECT BACKGROUND 1 2 NEED FOR THE PROPOSED SCHEME 4 3 DESCRIPTION OF THE CONSTRUCTION PHASE 4 4 DESCRIPTION

More information

Sustainability Statement. Gainsford Road. For Pocket Living. XCO2 energy. April 2016

Sustainability Statement. Gainsford Road. For Pocket Living. XCO2 energy. April 2016 For Pocket Living April 2016 XCO2 energy w: www.xco2energy.com :: e: mail@xco2energy.com t: +44 (0) 20 7700 1000 :: f: +44 (0) 20 7183 6620 17-18 Hayward s Place :: Clerkenwell :: London :: EC1R 0EQ Contents

More information

Chapter 8 Natural Resources

Chapter 8 Natural Resources Chapter 8 Natural Resources 127-134 8.1 Introduction 8.2 Extractives Industry 8.3 Forestry 8.4 Fishing / Aquaculture 8.1 Introduction Kerry has a number of naturally occurring resources that contribute

More information

Resource Consent Application - Removal/Remediation of Flare/Blowdown Pit at Kapuni Well site KA2 for Shell Todd Oil Services Ltd

Resource Consent Application - Removal/Remediation of Flare/Blowdown Pit at Kapuni Well site KA2 for Shell Todd Oil Services Ltd 27 March 2012 Project No. 42780930 South Taranaki District Council Private Bag 902 Hawera, 4640 Attention: Blair Sutherland Dear Blair Subject: Resource Consent Application - Removal/Remediation of Flare/Blowdown

More information

E9: CLIMATE CHANGE: ADAPTATION AND RESILIENCE

E9: CLIMATE CHANGE: ADAPTATION AND RESILIENCE HIGH SPEED TWO INFORMATION PAPER E9: CLIMATE CHANGE: ADAPTATION AND RESILIENCE This paper outlines how the combined impact of Phase One of the HS2 project and potential climate change, on the receiving

More information

Port of Hull Local Development Order

Port of Hull Local Development Order Port of Hull Local Development Order Integrated Environmental Assessment Non Technical Summary March 2012 Final Prepared for: Hull City Council UNITED KINGDOM & IRELAND REVISION SCHEDULE Rev Date Details

More information

Network Rail Romford Rail Operating Centre and Maintenance Delivery Unit Volume I: Environmental Statement Non-Technical Summary

Network Rail Romford Rail Operating Centre and Maintenance Delivery Unit Volume I: Environmental Statement Non-Technical Summary Romford Rail Operating Centre and Maintenance Delivery Unit Volume I: Environmental Statement Non-Technical Summary Issue 22 August 2012 This report takes into account the particular instructions and requirements

More information

Southshore residential red zone: Summary of Technical Information as at October Area ID: 1. Purpose of this document

Southshore residential red zone: Summary of Technical Information as at October Area ID: 1. Purpose of this document Southshore residential red zone: Summary of Technical Information as at October 2016 Area ID: 1 Purpose of this document The following information is a summary of the local environmental values, conditions

More information

BARRASFORD QUARRY PERIODIC REVIEW. Environmental Statement - Non Technical Summary. October 2014

BARRASFORD QUARRY PERIODIC REVIEW. Environmental Statement - Non Technical Summary. October 2014 BARRASFORD QUARRY PERIODIC REVIEW Environmental Statement - Non Technical Summary October 2014 Environmental Statement - Non Technical Summary. October 2014 1 LAFARGETARMAC.COM Introduction This is a Non

More information

BSkyB Site Levelling and Remediation Works. Environmental Statement Volume 3. Planning Application June 2013 Non-Technical Summary

BSkyB Site Levelling and Remediation Works. Environmental Statement Volume 3. Planning Application June 2013 Non-Technical Summary BSkyB Site Levelling and Remediation Works Environmental Statement Volume 3 Planning Application June 2013 Non-Technical Summary BSkyB Site Levelling and Remediation Works Environmental Statement Volume

More information

Royal Edinburgh Hospital Masterplan

Royal Edinburgh Hospital Masterplan Royal Edinburgh Hospital Masterplan ENVIRONMENTAL STATEMENT VOLUME 1 (OF 4): NON TECHNICAL SUMMARY October 2013 ENVIRONMENTAL STATEMENT VOLUME 1 (OF 4): NON TECHNICAL SUMMARY October 2013 Sinclair Knight

More information

1.0. Introduction. Environmental Impact Assessment Prepared for Egnedol Wales Limited

1.0. Introduction. Environmental Impact Assessment Prepared for Egnedol Wales Limited 3 1.0 Introduction 4 1.0 Introduction 1.1 Overview 1.2 The Environmental Impact Assessment and the Environmental Statement 1.3 Environmental Permit 1.4 Availability of the Environmental Statement 04 07

More information

SUBURBAN RESIDENTIAL. QLDC PROPOSED DISTRICT PLAN [PART THREE] DECISIONS VERSION 7 lower density SUBURBAN residential

SUBURBAN RESIDENTIAL. QLDC PROPOSED DISTRICT PLAN [PART THREE] DECISIONS VERSION 7 lower density SUBURBAN residential 7 LOWER DENSITY SUBURBAN RESIDENTIAL 7.1 Zone Purpose The Lower Density Suburban Residential Zone is the largest residential zone in the District. The District Plan includes such zoning that is within

More information

8 AIR AND CLIMATE Introduction

8 AIR AND CLIMATE Introduction Table of contents 8 AIR AND CLIMATE... 8-1 8.1 Introduction... 8-1 8.1.1 Scope of the Assessment... 8-1 8.1.2 Methodology... 8-1 8.1.3 Assessment Criteria for Air Quality... 8-2 8.1.4 National Legislation

More information

an Inspector appointed by the Secretary of State for Communities and Local Government

an Inspector appointed by the Secretary of State for Communities and Local Government Appeal Decision Site visit made on 15 December 2017 by S M Holden BSc MSc CEng MICE TPP FCIHT MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government Decision date:

More information

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT PLANNING APPLICATION TO REMOVE CONDITION 2 OF PLANNING PERMISSION REFERENCE TDC/94/065 TO EXTEND THE OPERATIONAL LIFE OF THE NON-HAZARDOUS AND HAZARDOUS

More information

Non-Technical Summary

Non-Technical Summary Non-Technical Summary i. Introduction and background Introduction The Environment Agency (generally referred to in this non-technical summary as we or us ) has prepared an Environmental Statement (ES)

More information

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS TERMS OF REFERENCE ELECTRICAL TRANSMISSION LINES & SUBSTATIONS Notes for NEPA for Generic Terms of Reference This generic Terms of Reference (TOR) is applicable to development projects involving the construction

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

Construction Method Statement

Construction Method Statement Construction Method Statement Introduction. The project involves the construction of the new Apartment Extra Car Home for Grwp Cynefin in Pothmadog, Gwynedd, Wales. The programme and construction methodology

More information

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions.

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions. 18. Air The Project Air quality team prepared an Air Quality Assessment Report for the Project, which is included in Volume 3 (Part 1). The Report provides an assessment of air quality effects associated

More information

GIS data classes used within the November 2013 Environmental Statement Environmental Maps

GIS data classes used within the November 2013 Environmental Statement Environmental Maps LWM-HS2-EV-DAT-000-000006 P01 22 January 2014 GIS data classes used within the November 2013 Environmental Statement Environmental Maps Document No.:LWM-HS2-EV-DAT-000-000006 Revision Author Checked by

More information

To develop the new facility, the following site preparation and construction activities are planned.

To develop the new facility, the following site preparation and construction activities are planned. Project Description To develop the new facility, the following site preparation and construction activities are planned. Site Preparation: Remove existing structures and asphalt within building footprints.

More information

For inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:33:57

For inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:33:57 EPA Export 11-02-2014:23:33:57 P03/3343 CORRIB GAS FIELD DEVELOPMENT Prepared in respect of the proposed Bellanaboy Bridge Gas Terminal and associated Srahmore Peat Deposition Site RESPONSE TO REQUEST

More information

FRINGE COMMERCIAL ZONE RULES

FRINGE COMMERCIAL ZONE RULES Chapter 17 FRINGE COMMERCIAL ZONE RULES INTRODUCTION This chapter contains rules managing land uses in the. This zone surrounds the CBD area of the City and contains much of the commercial service activity

More information

Decision Document Penpound Poultry Unit

Decision Document Penpound Poultry Unit Natural Resources Wales permitting decisions Natural Resources Wales permitting decisions Decision Document Penpound Poultry Unit www.naturalresourceswales.gov.uk Issued 27 September 2017 Page 1 of 15

More information

NON TECHNICAL SUMMARY

NON TECHNICAL SUMMARY NON TECHNICAL SUMMARY CONTENTS Introduction... 1 The Proposed Development... 1 Planning Policy and Need... 2 Landscape and Visual Impact... 3 Noise... 4 Ecology... 4 Hydrogeology... 5 Land Quality... 6

More information

APPENDIX A: AT: CRICKLEWOOD SIDINGS, LAND REAR OF BRENT TERRACE (SOUTH) CRICKLEWOOD LONDON NW2 1BX DRAFT PLANNING CONDITIONS

APPENDIX A: AT: CRICKLEWOOD SIDINGS, LAND REAR OF BRENT TERRACE (SOUTH) CRICKLEWOOD LONDON NW2 1BX DRAFT PLANNING CONDITIONS APPENDIX A: THE CONSTRUCTION OF A COMPOUND FOR USE BY RAILWAY STAFF AND TRAIN DRIVERS, INCLUDING THE ERECTION OF A TWO STOREY OFFICE AND WELFARE BLOCK WITH ASSOCIATED YARDS, SITE LEVELLING, EXTERNAL LIGHTING,

More information

Renewable and Low Carbon Energy Facility. Environmental Statement Non Technical Summary

Renewable and Low Carbon Energy Facility. Environmental Statement Non Technical Summary Renewable and Low Carbon Energy Facility Environmental Statement Non Technical Summary February 2010 Ltd Renewable and Low Carbon Energy Facility, Dorset Green Technology Park, Winfrith, Dorset Environmental

More information

FLOOD RESPONSE PLAN PROPOSED WASTE MANAGEMENT FACILITY AT UNIT C, MAERDY INDUSTRIAL ESTATE, RHYMNEY, TREDEGAR, NP22 5PY. On behalf of Mekatek Ltd

FLOOD RESPONSE PLAN PROPOSED WASTE MANAGEMENT FACILITY AT UNIT C, MAERDY INDUSTRIAL ESTATE, RHYMNEY, TREDEGAR, NP22 5PY. On behalf of Mekatek Ltd FLOOD RESPONSE PLAN PROPOSED WASTE MANAGEMENT FACILITY AT UNIT C, MAERDY INDUSTRIAL ESTATE, RHYMNEY, TREDEGAR, NP22 5PY On behalf of Mekatek Ltd Our Ref: 0097.b Date: December 2016 Prepared by: JDE Unit

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment Practice Update and the New Directive Gareth Wilson, Partner Barton Willmore LLP What is EIA? US: the formal process used to predict the environmental consequences (positive

More information

EIA Screening. Proposed Mixed Use Development at Jacobs Island, Cork. Montip Horizon Limited

EIA Screening. Proposed Mixed Use Development at Jacobs Island, Cork. Montip Horizon Limited EIA Screening Proposed Mixed Use Development at Jacobs Island, Cork Montip Horizon Limited June 2018 1. Introduction This Environmental Impact Assessment Screening has been prepared to determine whether

More information

Public Information Centre

Public Information Centre Vineland West Private Water System Municipal Class Environmental Assessment Public Information Centre Tuesday, July 12, 2016, 6 to 8 p.m. Vineland Research and Innovation Centre, Rittenhouse Hall Welcome!

More information

Non-Technical Summary

Non-Technical Summary Non-Technical Summary Introduction and Background The Environment Agency owns Rye Harbour Farm in East Sussex and has developed a scheme to enhance the nature conservation value of the Farm, which lies

More information

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Construction Management Plan (CMP) 227 Princess Highway, Dandenong Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale

More information

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby.

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. The site comprises the employment element of the South West Rugby allocation

More information

MAIN INDUSTRIAL ZONE RULES

MAIN INDUSTRIAL ZONE RULES Chapter 23 MAIN INDUSTRIAL ZONE RULES Introduction This chapter contains rules managing land uses in the. The boundaries of this zone are shown on the planning maps. All rules apply throughout the unless

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

Decree of the Ministry of the Environment

Decree of the Ministry of the Environment (NB: Unofficial translation from Finnish) Decree of the Ministry of the Environment on plans and reports concerning construction Issued in Helsinki on 12 March 2015 In accordance with a decision by the

More information

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary Viridor Energy from Waste Facility Environmental Statement Non-Technical Summary September 2012 Viridor Energy from Waste Facility Environmental Statement Non-Technical Summary Introduction Viridor has

More information

S e c t i o n S u b d i vision

S e c t i o n S u b d i vision S e c t i o n 2. 6 - S u b d i vision Subdivision is a process of defining and redefining land parcel boundaries and can provide a framework for future land use and development. Integrated, well planned

More information

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment.

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment. 8. NOISE AND VIBRATION 8.1 Introduction This report has been prepared by AWN to form part of an EIAR for the proposed residential development at Wonderful Barn, Barnhall, Leixlip. The chapter assesses

More information

MOU001: Land to the west of Eaugate Road, Moulton Chapel Sustainability Objective

MOU001: Land to the west of Eaugate Road, Moulton Chapel Sustainability Objective MOU001: Land to the west of Eaugate Road, Moulton Chapel Sustainability Objective Indicative development scenario: Total site area: 0.24ha Potential open space: 0.03ha Development area: 0.21ha Potential

More information

SITE C FIELD WORK FOR 2019

SITE C FIELD WORK FOR 2019 January 2019 SITE C FIELD WORK FOR 2019 During the construction of Site C, BC Hydro will conduct environmental and engineering field work along the Peace River between the Williston Reservoir and the Alberta

More information

Wytch Farm Pipeline Refurbishment Project. Environmental Statement. Non-Technical Summary. November 2007

Wytch Farm Pipeline Refurbishment Project. Environmental Statement. Non-Technical Summary. November 2007 Wytch Farm Pipeline Refurbishment Project Environmental Statement Non-Technical Summary November 2007 Location map 0 1 2 3 4 5 kilometres Development area Introduction BP Exploration Operating Company

More information

SUBURBAN COMMERCIAL ZONE - RULES

SUBURBAN COMMERCIAL ZONE - RULES Suburban Commercial Zone Chapter 18 SUBURBAN COMMERCIAL ZONE - RULES INTRODUCTION This chapter contains rules managing land uses that take place within the suburban shopping centres of the City. This includes

More information

Squire and Partners. Homebase Site 195 Warwick Road, London W14. Non Technical Summary WSP Environment and Energy. On Behalf of St Edward Homes Ltd

Squire and Partners. Homebase Site 195 Warwick Road, London W14. Non Technical Summary WSP Environment and Energy. On Behalf of St Edward Homes Ltd Squire and Partners Homebase Site 195 Warwick Road, London W14 Non Technical Summary WSP Environment and Energy On Behalf of Ltd July 2010 QM Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks

More information

Seven Sisters Road

Seven Sisters Road April 2013 Environmental Statement Volume 3 Non-Technical Summary National Grid Substation with Residential and Commercial Development Contents Page 1 Introduction 1 2 The Environmental Impact Assessment

More information