NORTH DIVERSION MASTER TRANSPORTATION PLAN

Size: px
Start display at page:

Download "NORTH DIVERSION MASTER TRANSPORTATION PLAN"

Transcription

1 NORTH DIVERSION MASTER TRANSPORTATION PLAN Fargo Moorhead Metropolitan Area March 2012 FINAL REPORT

2

3 TABLE OF CONTENTS EXECUTIVE SUMMARY... I SUMMARY OF KEY FINDINGS... I BACKGROUND... 1 PURPOSE... 1 PLANNING PROCESS... 3 ROADWAY CONNECTIVITY... 4 BRIDGE CROSSINGS... 7 LAND ACCESSIBILITY MOBILITY TOWNSHIP IMPROVEMENTS EMERGENCY RESPONSE IMPROVEMENTS POSTAL SERVICE IMPROVEMENTS SCHOOL IMPROVEMENTS CONSTRUCTION IMPROVEMENTS FURTHER DISCUSSION COST ESTIMATES CONCLUSION APPENDIX A - COST ESTIMATES FIGURES FIGURE I PROPOSED IMPROVEMENT PLAN... III FIGURE 2 STUDY AREA FIGURE... 2 FIGURE 3 PLANNING PROCESS... 3 FIGURE 4 EXISTING CONNECTIVITY... 5 FIGURE 5 CR 31 AND 4 CROSSING ALIGNMENT... 8 FIGURE 6 CR 32 CROSSING ALIGNMENTS... 9 FIGURE 7 CR 20, 22 AND 81 CROSSINGS FIGURE 8 ROADWAY ACCESSIBILITY IMPROVEMENTS FIGURE 9 ROADWAY SURFACES FIGURE 10 MOBILITY IMPROVEMENTS FIGURE 11 PROPOSED BYPASS ROUTES FIGURE 12 OVERALL PROJECT RECOMMENDATIONS TABLES TABLE 1 COST ESTIMATES 20 Kadrmas, Lee & Jackson Final Report

4

5 EXECUTIVE SUMMARY The purpose of this study is to analyze the disruptions to roadway system continuity for the north section of the Red River diversion alignment (Maple River to the outfall), analyze the resulting impacts these disruptions have on roadway users and formulate recommendations intended to mitigate these impacts. This study employed a public input-centric approach that focused on consensus and relationship building. Input solicited from the following groups guided the development of study goals, deliverables and recommendations: Cass County Engineering and Planning Berlin Township Board Hardwood Township Board Raymond Township Board Wiser Township Board Red River Regional Dispatch Center Cass County Sheriff s Office Harwood Fire Station Mapleton Fire Station Gardner Fire Station Northern Cass School District West Fargo District Harwood Post Office Argusville Fire Station, Mapleton School District and Central Cass School District were solicited for input but did not attend their respective meetings. SUMMARY OF KEY FINDINGS Connectivity: Bridges are required to maintain connectivity across the diversion channel. Based upon the relationship of the proposed diversion alignment with the existing infrastructure, traffic volumes and barriers on the roadway network, bridges are proposed on the following roadways: Combination of County Road 4 and County Road 31 County Road 20 County Road 22 County Road 32 County Road 81 Accessibility: To maintain accessibility to all property adjacent to the proposed diversion channel, a connection between 27 th Street and CR 81 south of the channel is proposed. This section of 27 th Street, located between Interstate 29 and the Sheyenne River, would be inaccessible upon Diversion Channel construction without this connection. It is also recommended that gravel roadway connections are constructed to maintain accessibility to areas land locked due to the proposed diversion channel. This scenario occurs at two (2) parcels in the study area. Additionally a box culvert is recommended where drain 13 crosses 170 th Avenue Southeast to provide access to the area south of Drain 30 between 170 th Avenue Southeast and the diversion channel. Kadrmas, Lee & Jackson Final Report P age i

6 To maintain farming accessibility it is recommended that all of the existing roadways that have not been identified as proposed crossing locations dead-end at the diversion with the exception of the two sections of roadway that were less than one-fifth of a mile. It is recommended that these sections of roadways less than one-fifth mile in length be removed. Finally, it is recommended that that existing low flow crossing areas be studied during project development to determine structural integrity. Mobility: To account for the increased traffic volumes on ancillary roadways between dead-end township roads and county roads furnished with diversion crossings, 167 th Avenue Southeast was proposed for roadway improvements to operate as a collector adjacent to the diversion channel alignment. These upgrades include upgrading approximately five miles of minimum maintenance earth roadways to gravel and installing two new box culverts. Construction Accommodations: To accommodate traffic during bridge construction on county roadways, it is recommended that temporary construction bypass routes are established. This scenario requires that roadway and bridge construction occur prior to diversion channel construction as planned. At lower volume county roads, circuitous bypass routes are proposed on the surrounding roadways. This type of bypass route is proposed at CR 32 and CR 22. At higher volume locations and where surrounding infrastructure is incomplete or would require unsatisfactorily long detours, new bypass roads offset 200 feet from the existing roadway are proposed. This type of bypass route is proposed at CR 20 and 81. The proposed combination bridge for CR 4 and CR 31 will not be located on the existing roadways. As a result, this bridge does not require a temporary bypass route. It is also recommended that contractors be prohibited from impacting traffic on consecutive county roadway crossings locations to limit roadway user inconvenience. In other words, the contractor shall maintain normal traffic flow on the upstream and downstream diversion channel county road crossings during bridge construction. This does not apply to bridges that are not constructed on the existing roadway alignment. Communication with Stakeholders: To maintain the relationship established during this study, it is recommended that the outlets of communication be maintained as this project transitions from planning into development. All parties involved in this study are affected by the proposed roadway closures to varying degrees, whether it be during a daily commute to work or during an emergency response call. Timely notification of roadway construction, detours and closures allows roadways users to adapt to the changing roadway network landscape prior to facing these impacts in the field. Kadrmas, Lee & Jackson Final Report P age ii

7 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 22ND ST SE 23RD ST SE 25TH ST SE Drain TH AVE N E 19 AVE N 19TH AVE N D M 81 Red River Tributary Drain 24C Drain 13 I29 Proposed CR 4/CR 31 Roadway Realignment M 34 W I S E R T O W N S H I P CO RD TH AVE SE G A R D N E R T O W N S H I P 22ND ST SE 23RD ST SE Drain TH AVE I29 SE M 4 -Install Box Culvert ARGUSVILLE Proposed CR 81 Bypass Route: -Constructed as New Gravel Roadway M 4 29 Drain 30 New Gravel Roadway CO RD 81 Sheyenne River Proposed CR 32 Bypass Route: -Use of Exsiting Roadways -Resurface Earth Roadways With Gravel -Box Culvert Installation at Rush River and 167th Ave SE Improvements Established as Part of Mobility Enhancements -New Gravel Roadway M 32 -New Gravel Roadway -Improve Roadway Surface to Gravel -Install Box Culvert at Rush River Crossing 28TH ST SE M 32 H A R W O O D T O W N S H I P 25TH ST SE Proposed CR 32 Roadway Realignment 167TH AVE SE 27TH ST SE Rush River B E R L I N T O W N S H I P M 81 HARWOOD Lower Branch Rush River 30TH ST SE Drain 9 64TH AVE N 25 ST N 81ST ST N Proposed CR 22 Bypass Route: -Use of Existing Roadways M 13 31ST ST SE 52ND AVE N 37TH ST N 45TH ST N 57TH ST N 29 -Improve Roadway Surface to Gravel -Install New Box Culvert at River Crossing M 20 Drain TH ST N OLD US HWY 81 N 32ND AVE N 32ND AVE NW 45TH ST N R E E D T O W N S H I P M 17 57TH ST N Drain 21 14TH ST NW 26TH ST NW 19TH AVE NW Drain 10 Proposed CR 20 Bypass Route: -Constructed as New Gravel Roadway Sheyenne Diversion Drain 45 WEST FARGO Sheyenne River Tributary FARGO 94 15TH ST W 93RD ST N 26TH ST W 34TH ST SE 38TH ST NW R A Y M O N D T O W N S H I P 35TH ST SE 12TH AVE NW 36TH ST SE SHEYENNE DIVERSION RD 37TH ST SE M 28 13TH AVE W 38TH ST SE 21ST AVE W 39TH ST SE 15TH S M 15 M 11 Figure I Proposed Improvement Plan North Red River Diversion Master Transportation Plan Miles 26TH ST SE 4 28TH ST SE 32ND ST SE M 11 M 20 Legend Cutoff Roads Proposed Diversion Crossings Proposed Box Culverts Existing Low Flow Crossings Existing Bridges Construction Bypass Routes Mobility Improvement (Earth Surface to Gravel Surface) 163RD AVE SE Accessibility Improvement Proposed Roadway Realignment Roadway Removal Drains Rivers Interstate Highway Proposed Diversion Alignment Roadway Centerlines Parcels Without Access* Parcel Lines *Does not include property that can be accessed by adjoining parcels with matching owner M 11 37TH ST SE

8 BACKGROUND To reduce flood risk and flood damages in the Fargo-Moorhead metropolitan area, a feasibility study was conducted by the US Army Corps of Engineers (USACE) to identify flood risk management measures that could be implemented and developed into a federal project. The results of this feasibility study identified a 36-mile diversion alignment that would start approximately four miles south of the confluence of the Red and Wild Rice Rivers, extend west and north around the cities of Horace, Fargo, West Fargo and Harwood and ultimately re-enter the Red River north of the confluence of the Red River and Sheyenne Rivers near the City of Georgetown, Minnesota. The depth of the proposed diversion channel is approximately 20 feet, with a maximum depth of 35 feet. The channel bottom width varies from 100 to 250 feet. The total footprint of the diversion channel has a maximum width of 2,200 feet including areas for soil disposal piles, leaving an affected acreage of 8,054 acres. PURPOSE Although the diversion channel alignment has been refined since the USACE study, the overall impact to the existing transportation network has remained constant. The limits of this study include all of the roadways within four miles of the proposed diversion channel alignment between the Maple River and the outfall into the Red River (refer to FIGURE 2). This alignment cuts through the existing grid of township, county and state roads in a primarily non-perpendicular fashion. This scenario results in gaps in connectivity to roadways aligned both north and south and east and west. The purpose of this study is to analyze the disruptions to roadway system continuity for this particular section of the diversion alignment, analyze the resulting impacts these disruptions have on roadway users and formulate recommendations intended to mitigate these impacts. Kadrmas, Lee & Jackson Final Report P age 1

9 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 22ND ST SE 23RD ST SE Drain 65 40TH AVE N 19 AVE N 19TH AVE N 25 ST N Drain 10 FARGO Drain 9 Red River Tributary Drain 24C Drain 13 M 34 W I S E R T O W N S H I P CO RD TH AVE SE Drain 29 ARGUSVILLE M 81 25TH ST SE M 4 25TH ST SE 29 Drain 30 I29 26TH ST SE I29 CO RD 81 Sheyenne River 27TH ST SE H A R W O O D T O W N S H I P 167TH AVE SE 28TH ST SE 28TH ST SE Rush River B E R L I N T O W N S H I P HARWOOD Lower Branch Rush River M 13 M 81 M 17 64TH AVE N 31ST ST SE 105TH ST N 81ST ST N 52ND AVE N 37TH ST N Drain 67 M 20 OLD US HWY 81 N 32ND AVE N 32ND AVE NW 29 R E E D T O W N S H I P 45TH ST N 57TH ST N 45TH ST N 57TH ST N Drain 21 14TH ST NW 26TH ST NW 38TH ST NW 19TH AVE NW M 10 R A Y M O N D T O W N S H I P 34TH ST SE 36TH ST SE 12TH AVE NW Sheyenne Diversion Drain 45 SHEYENNE DIVERSION RD 37TH ST SE 94 WEST FARGO M 28 Sheyenne River Tributary 13TH AVE W 38TH ST SE 15TH ST W 26TH ST W 21ST AVE W 39TH ST SE M 15 32ND AVE W 38TH ST W 40TH ST SE 2 G A R D N E R T O W N S H I P 22ND ST SE 23RD ST SE M RD AVE SE M 32 30TH ST SE 163RD AVE SE 35TH ST SE M 11 37TH ST SE Figure 2 Study Area North Red River Diversion Transportation Master Plan 4 Legend Rivers Drains Existing Low Flow Crossings Existing Bridges Proposed Diversion Alignment County Roads Other Roads Miles Interstate Highway

10 PLANNING PROCESS Roadway networks can be highly complex and serve a variety of user groups, trip purposes and levels of facilities. This study looks at the network as the sum of its parts and understands the relationship between those parts and the capabilities, impacts and effectiveness of the system as a whole. To study this collaboration of parts, a threephase planning approach was employed. This process included the following steps: data collection, technical analysis and recommendation formulation. The primary outlet for reliable data was from the people who lived and worked in the communities closest to the proposed diversion alignment. As a result, public involvement guided the technical analysis of the project which in turn led to project goals, deliverables and recommendations (refer to FIGURE 3). Public Input Technical Analysis Recommendations Connectivity Accessability Mobility FIGURE 3 Planning Process The primary objective of the public involvement program was to communicate the proposed project and gain feedback on particular needs and concerns of the community. The consensus-building approach was developed to Kadrmas, Lee & Jackson Final Report P age 3

11 minimize potential controversy and negative public opinion on the project. This approach also aimed to develop relationships that will offer benefits throughout the entire FM diversion project from development to construction. The project team met with various key stakeholders and decision makers to solicit feedback regarding perceived transportation deficiencies resulting from diversion implementation and desired plan deliverables. Meetings were held prior to conducting detailed technical analysis. Individual meetings were held with the following groups: Cass County Engineering and Planning Berlin Township Board Harwood Township Board Raymond Township Board Wiser Township Board Red River Regional Dispatch Center Cass County Sheriff s Office Harwood Fire Station Mapleton Fire Station Gardner Fire Station Northern Cass School District West Fargo District Harwood Post Office Argusville Fire Station, Mapleton School District and Central Cass School District were solicited for input but did not attend their respective meetings. These meetings not only helped to identify network deficiencies and improvement opportunities but these meetings led to insight regarding the values of the communities in the study area. This insight allowed the study team to develop goals and objectives that met the functional transportation needs of the area without significantly disrupting the existing culture. This community-centric process resulted in recommendations that are formulated based upon the needs of the community as identified by the community. ROADWAY CONNECTIVITY The study area consists of the approximately 13.5-mile section of diversion that stretches from the Maple River to the Red River outfall. This section of diversion channel effectively disconnects 8 east-west and 7 north-south county and township roadways. This section of the diversion also disconnects Interstate-29 and two railway lines. It is important to note that all state maintained roads and railroad lines will remain connected across the proposed diversion channel. As a result, these roadways were not analyzed as part of this report. Bridges are required at specific locations across the diversion channel to maintain an acceptable level of connectivity between the two sides. Financial constraints require that bridge locations be judiciously selected. As a result, bridge locations were selected based upon the traffic needs of the individual townships and the region as a whole. Intuitively, roadways that serve the needs of the region carry more vehicles per day as they are not restricted by existing barriers. Existing barriers within the study limits included rivers, drains and Interstate 29. Barrier crossings were used to identify roadway priority. For example, a roadway with a bridge over a drain holds a higher priority than a roadway with a low flow crossing or no crossing at all. Figure 4 depicts the roadways that are restricted by barriers and the roadways that are unimpeded by barriers within the study area. Kadrmas, Lee & Jackson Final Report P age 4

12 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 23RD ST SE 22ND ST SE Drain 65 40TH AVE N T SE 19 AVE N 19TH AVE N 37TH ST SE 25 ST N Drain 10 FARGO M 81 Red River Tributary Drain 24C Drain 13 M 34 W I S E R T O W N S H I P CO RD TH AVE SE G A R D N E R T O W N S H I P I29 I29 22ND ST SE 23RD ST SE ") Drain 29 M 4 ") ARGUSVILLE 29 Drain 30 ") ") I29 ") Sheyenne River CO RD 81 27TH ST SE ") ") 167TH AVE SE M 32 28TH ST SE H A R W O O D T O W N S H I P 25TH ST SE I29 Rush River ") B E R L I N T O W N S H I P 28TH ST SE ") ") HARWOOD Lower Branch Rush River ") ") Drain 9 64TH AVE N 31ST ST SE 105TH ST N M 13 81ST ST N 52ND AVE N ") ") 37TH ST N Drain 67 M 20 OLD US HWY 81 N I29 32ND AVE N 32ND AVE NW ") ") 29 R E E D T O W N S H I P I29 I29 45TH ST N 57TH ST N 45TH ST N 57TH ST N Drain 21 14TH ST NW 26TH ST NW 38TH ST NW 19TH AVE NW R A Y M O N D T O W N S H I P I29 34TH ST SE 35TH ST SE 36TH ST SE 12TH AVE NW Sheyenne Diversion Drain 45 SHEYENNE DIVERSION RD WEST FARGO M 28 Sheyenne River Tributary 13TH AVE W 15TH ST W 26TH ST W 21ST AVE W M 1 30TH ST SE M 20 37TH ST SE 38TH ST SE 94 39TH ST SE 25TH ST SE 26TH ST SE Figure 4 Existing Connectivity M RD AVE SE 4North Red River Diversion Transportation Master Plan 163RD AVE SE Legend M 11 Roadway With Connectivity Not Limited By Existing Barrier Roadway With Connectivity Limited By Existing Barriers ") Proposed Travel Barriers (Diversion Channel) Existing Travel Barriers Existing Low Flow Crossings Existing Bridges Drains Rivers Interstate Highway Miles Roads Outside Study Area Proposed Diversion Alignment

13 Using a buffer of three (3) miles from the center of the diversion channel, the only study roadways that cross the diversion that are not currently impeded by barriers are the county roads (refer to FIGURE 4): County Road 4 County Road 20 County Road 22 County Road 31 County Road th Street Southeast Based upon the analysis of existing roadway barrier restrictions, these six (6) roadways make appropriate diversion crossing candidate locations. It may be impractical to construct bridges on both CR 22 and 30 th Street Southeast due to the proximity of the two roadways (one mile separation). Input indicated that CR 22 currently experiences higher traffic volumes and further analysis indicated that 30 th Street Southeast currently has multiple stretches of earth roadway compared to the constant gravel cross-section on CR 22. As a result, 30 th Street Southeast was eliminated from further analysis. If bridges were built exclusively at the locations denoted above, a large gap in connectivity would be developed between CR 22 and CR 4. At the center of this gap in connectivity is CR 32. The second iteration for the selection of bridge locations was convenience-based. The following data was used to develop a cost-benefit analysis to gauge convenience: Based upon preliminary cost estimates produced by Houston Engineering in Appendix E of the Fargo- Moorhead Metro Feasibility Study, the estimated mean cost of the bridges within the study area is approximately $3 million. Based upon median perceived vehicle type distribution, corresponding mean miles per gallon from the US Department of Energy's publication Fuel Economy Guide 2011 and a $3.50 per gallon price of fuel, the average price of fuel for every mile a vehicle is detoured equates to approximately $0.21 per mile per vehicle. Based upon the median income for Cass County residents and the time required to drive one mile at 55 mph, the equivalent cost of loss productivity for every mile a vehicle is detoured equates to approximately $0.40 per mile per vehicle. Based upon a 2010 NDDOT Average Annual Daily Traffic (AADT) count, 100 vehicles use CR 32 adjacent to the proposed diversion crossing location. Based upon the data provided above, it would cost these 100 vehicles approximately $131,400 to detour three miles to CR 22 and three miles back. Within 23 years, the cost experienced by the residents would outweigh the cost of the bridge. This does not account for the number of vehicles that will be detoured at the roadways between CR 32, CR 22 and CR 4 that will also be detoured. If a bridge is established at each county road, the maximum detour distance would be one mile (to and from) any roadway without a crossing. This minor detour compounded by the fact that the majority of these remaining roadways experience minimal travel, resulted in cost-benefit numbers that did not favor a new bridge crossing at any township roadway. As a result, it is recommended that a diversion crossing is established at each county road. Kadrmas, Lee & Jackson Final Report P age 6

14 BRIDGE CROSSINGS Due to the proposed diversion channel alignment, many of the proposed county road bridge crossings would not cross the channel perpendicularly. This is significant because each degree of skew at the bridge location requires additional bridge deck to compensate for the longer crossing. For example, a bridge crossing location that would be 600 feet if perpendicular to the diversion channel would be extended by nearly 250 feet if the bridge was skewed by 45 degrees. It is important to note that this is not a constant rate. For example, a 10 degree skew requires 10 feet of additional bridge length. Using cost estimates derived from Cass County standards, nearly 100 feet of gravel roadway can be built for every foot of bridge deck. As such, all bridges were first designed to perpendicularly cross the diversion. Once roadways have been selected as diversion crossing locations it is necessary to layout the horizontal alignments of the roadways based upon environmental constraints (drains, adjacent roadways, houses, etc.). Preliminary analysis indicated that fitting a bridge across the diversion perpendicularly at both CR 4 and CR 31 would result in crossing locations approximately one mile apart. Based upon input from the County and Townships, the construction of one bridge, shared and located between the two county roads, was selected as the optimal decision in terms of bridge cost and practicability. Refer to FIGURE 5 for an illustration of the proposed crossing and horizontal curvature of the roadways. According to the County and Townships, the primary traffic movements at the current CR4/CR31 intersection corresponds to eastbound motorists on CR 4 turning northbound onto CR 31 toward the Red River Crossing on CR 34 and vice versa. As such, the proposed alignment should save the majority of drivers approximately one mile of commute time and distance. The remaining movements, however, will experience an increase in motorist delay and miles travelled. Due to the skewed crossing angle at CR 32, five crossing alternatives were developed for public and agency review. The options ranged from 55 mph design speed alignment with significant right-of-way (ROW) requirements to a 40 mph design speed alignment with minimal ROW requirements. The input received was varied. Three of the four townships preferred the option with the smallest ROW impacts whereas one of the townships and the Emergency Response and Sherriff s Office representatives preferred the 55 MPH design speed configuration for safety. In order to provide an increased degree of safety without requiring substantial ROW acquisition, a bridge alternative with a minor skew of 15 degrees was developed that utilized the higher design speed but limited ROW impacts. The skew would increase the bridge length by 22 feet or approximately $99,000 equating to a 3.5 percent increase in overall bridge cost. Refer to FIGURE 6 for illustration of the proposed bridge alignment. The final diversion crossings are located on roads that naturally intersect the diversion perpendicularly. As a result, these roadways required zero horizontal curvature considerations. Illustrations of the bridges can be found on FIGURE 7. Kadrmas, Lee & Jackson Final Report P age 7

15 COUNTY COUNTY COUNTY Insert 23RD STSE 50 Radius All Approaches 55 MPH Curve 2810 Radius 4% Superelevation 580 Bridge 50 Radius All Approaches 25 MPH Curve 511 Radius 4% Superelevation 24TH STSE Install Box Culvert Drain 29 GRAPHIC SCALE (in feet) " = MPH Curve 511 Radius 4% Superelevation (See Insert) 35 MPH Curve 654 Radius 5% Superelevation Proposed Roadway Alignment Typical Cross Section 50 Radius All Approaches 55 MPH Curve 2810 Radius 4% Superelevation 200 ROW CASS 4 CASS 4 55 MPH Curve 2810 Radius 4% Superelevation CASS 31 Figure 5 CR 31 and 4 Crossing Alignments 0 GRAPHIC SCALE (in feet) LEGEND Top of Levee Diversion Earth Side Slope North Red River Diversion Master Transportation Plan 1" = 2000 N Diversion Bench Diversion Channel Bottom Diversion Low Flow Channel Diversion Centerline W ND E Required Roadway ROW Roadway Removal S Drain

16 COUNTY 167TH AVE SE COUNTY Insert Typical Cross Section 27TH STSE 27TH STSE 650 Bridge (Outer Bench to Outer Bench) GRAPHIC SCALE (in feet) " = MPH Curve 1890 Radius 5% Superelevation Proposed Roadway Alignment 55 MPH Curve 2810 Radius 4% Superelevation 200 ROW CASS 32 CASS MPH Curve 2810 Radius 4% Superelevation (See Insert) 55 MPH Curve 1890 Radius 5% Superelevation Figure 6 CR 32 Crossing Alignment 0 GRAPHIC SCALE (in feet) LEGEND Top of Levee Diversion Earth Side Slope North Red River Diversion Master Transportation Plan 1" = 1000 N Diversion Bench Diversion Channel Bottom Diversion Low Flow Channel Diversion Centerline W ND E Required Roadway ROW Roadway Removal S

17 COUNTY COUNTY COUNTY County Road 81 County Road 22 County Road Bridge 580 Bridge CASS Bridge CASS 20 CASS 81 Maple River Figure 7 CR 20, 22 and 81 Crossings 0 GRAPHIC SCALE (in feet) LEGEND Top of Levee Diversion Earth Side Slope 1" = 1000 Diversion Bench North Red River Diversion Master Transportation Plan N Diversion Channel Bottom Diversion Low Flow Channel Diversion Centerline W ND E BNSF Railway S

18 LAND ACCESSIBILITY Where access is already limited, the diversion channel may completely restrict access to a particular section of land. Currently, 27 th Street Southeast between CR 81 and the Sheyenne River is accessed via CR 81 or 170 th Avenue Southeast. The proposed diversion channel alignment would eliminate both connections to this section of 27 th Street Southeast. As a result, a connection between the 27 th Street and CR 81 south of the diversion is recommended to maintain accessibility to the property north of 27 th Street. Additionally a box culvert is recommended where drain 13 crosses 170 th Avenue Southeast to provide access to the area south of Drain 30 between 170 th Avenue Southeast and the diversion channel (refer to FIGURE 7). Two parcels of land remain inaccessible with the proposed improvement plan. All other parcels of land are either directly accessible from existing or proposed roadways or from adjoining property maintained by the same property owner. The first such parcel is owned by William Henry Larson and is located between the diversion channel and the Sheyenne River west of 172 nd Avenue Southeast. A section of gravel roadway connecting this parcel of land to CR 4 is recommended along the diversion channel ROW footprint. The second parcel of land is located between the diversion channel and Interstate I-29 north of CR 32. Similarly, A section of gravel roadway connecting this parcel of land to 169 th Avenue Southeast is recommended along the diversion channel ROW footprint. It is important to note that leasing agreements were not studied as part of this study. Leasing agreements offer the potential for one party to maintain adjoining parcels of land eliminating accessibility restrictions. If it is determined that an existing leasing agreement is in place at either of these locations or a land exchange can be completed, the proposed gravel roadways should be removed from further analysis. It is important to note that the structural integrity of existing low flow crossings vary by location. However, traffic volume increases are anticipated to be minimal at each crossing location. As a result, improvements were not recommended at locations where low flow crossings currently exist. If during final design it is determined that the low flow crossings in the study area require improvements, an additional $250,000 per improved crossing (box culvert) should be allocated for overall project development. The diversion channel will split the township roads at varying points. Based upon input received from county and township officials, maintaining roadways is recommended to maintain farming accessibility on split properties. The roadways would terminate as dead-ends similar to how township roadways currently terminate at I-29. There are, however, two locations that may benefit from roadway removal. The first is 169 th Avenue Southeast between 27 th Street Southeast and the diversion. Removing this one-fifth mile section would allow the 24-acre section of land between the diversion and 169 th Avenue Southeast to be joined with the adjacent 320-acre section of land to the west. The second section of roadway proposed for removal is between the diversion and CR 4 on 172 nd Avenue Southeast. This section of roadway is slightly over one-tenth of a mile and serves minimal access benefits. Refer to FIGURE 8 for an illustration of the proposed roadway removal sections. Kadrmas, Lee & Jackson Final Report P age 11

19 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 22ND ST SE 23RD ST SE 25TH ST SE Drain TH AVE N SE 19 AVE N 19TH AVE N D M 81 Red River Tributary Drain 24C Drain 13 I29 M 34 W I S E R T O W N S H I P CO RD 81 -New Gravel Roadway 167TH AVE SE G A R D N E R T O W N S H I P 22ND ST SE -Install Box Culvert -Remove Roadway Section as Part of Accessibility Improvements 23RD ST SE Drain TH AVE I29 SE M 4 ARGUSVILLE M 4 29 Drain 30 26TH ST SE -Remove Roadway Section as Part of Accessibility Improvements Sheyenne River CO RD 81 28TH ST SE M 32 28TH ST SE M 32 H A R W O O D T O W N S H I P 25TH ST SE 27TH ST SE 167TH AVE SE -New Gravel Roadway HARWOOD -New Gravel Roadway Rush River B E R L I N T O W N S H I P M 81 Lower Branch Rush River 30TH ST SE Drain 9 105TH ST N 64TH AVE N 31ST ST SE M ST N 81ST ST N 52ND AVE N Drain 67 37TH ST N 45TH ST N 57TH ST N M OLD US HWY 81 N 32ND AVE N 45TH ST N R E E D T O W N S H I P M 17 57TH ST N Drain 21 14TH ST NW 26TH ST NW 19TH AVE NW Drain 10 Sheyenne Diversion Drain 45 WEST FARGO 94 Sheyenne River Tributary FARGO 15TH ST W 93RD ST N 26TH ST W 34TH ST SE 38TH ST NW R A Y M O N D T O W N S H I P 35TH ST SE 12TH AVE NW 36TH ST SE SHEYENNE DIVERSION RD 37TH ST SE M 28 13TH AVE W 38TH ST SE 21ST AVE W 39TH ST SE 15TH S M 15 1 M 11 Figure 8 Roadway Accessibility Improvements 32ND ST SE M 11 M 20 Legend Dead Ends at Diversion Proposed Box Culverts 163RD AVE SE Accessibility Improvement Proposed Roadway Realignment Roadway Removal M 11 37TH ST SE Existing Low Flow Crossings Existing Bridges Proposed Diversion Crossings Drains Rivers Interstate Highway Proposed Diversion Alignment Roadway Centerlines Miles 4North Red River Diversion Master Transportation Plan Parcels Without Access* Parcel Lines *Does not include property that can be accessed by adjoining parcels with matching owner

20 MOBILITY The county and township roads in the study area are predominantly gravel or minimum maintenance earth roads with intermittent sections of paved roadway at higher volume locations (refer to FIGURE 9). The diversion channel will sever township road connections which will result in a funnel effect of all ancillary roadways onto the county roads to cross the diversion. The scenario will result in earth roadways that typically experience minimal vehicular and farm equipment activity to see increased traffic volumes. Some of these roadways may not be suitable for increased traffic volumes and will require roadway resurfacing to withstand the new loadings. Due to the varying degree of uses and corresponding needs of the existing roadway network, mobility issues are categorized by trip purpose below. TOWNSHIP IMPROVEMENTS During township meetings, three separate sections of 167 th Avenue Southeast were requested for improvement due to anticipated traffic volume growth caused by diversion implementation. 167 th Avenue Southeast represents the north-south roadway directly adjacent to the diversion channel on the west side. These segments included all but one mile of the earth sections of 167 th Avenue Southeast within the study limits. Instead of fragmenting the sections of gravel and earth roadway it may be appropriate to provide a continuous gravel roadway between CR 20 where the roadway terminates before the Maple River and just south of the Leonard s Way addition where the roadway is paved (refer to FIGURE 10). This improvement will address the anticipated increase in traffic volumes on the roadway and also offer a roadway parallel to the diversion that would increase mobility between the township and the county roads adjacent to the diversion channel. A parallel roadway on the east side of the diversion channel does not appear to be necessary due to the presence of existing parallel roadways (CR 17, CR 81 and CR31). It is important to note that there were additional improvement requests from township board members. However, analysis conducted by the study team and approved by County Highway Department staff indicated that these other roadways are not anticipated to experience an increase in traffic due to implementation of the diversion. As such, these requests were noted but not recommended as part of this study. EMERGENCY RESPONSE IMPROVEMENTS Based upon input received from the Cass County Sherriff s Office, Red River Regional Dispatch Center and Harwood, Mapleton and Gardner fire departments, the primary transportation response outlets are county roads. These agencies indicated that as long as bridges were provided at each county road and one combined bridge for CR 4 and CR 31, there would be minimal to no impacts to response routes and times. Kadrmas, Lee & Jackson Final Report P age 13

21 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 22ND ST SE 23RD ST SE 25TH ST SE Drain 65 40TH AVE N 19 AVE N 19TH AVE N M 1 Red River Tributary Drain 24C Drain 13 I29 M 34 W I S E R T O W N S H I P CO RD TH AVE SE G A R D N E R T O W N S H I P 22ND ST SE 23RD ST SE Drain TH AVE I29 SE M 4 ARGUSVILLE M 4 29 Drain 30 26TH ST SE CO RD 81 Sheyenne River 28TH ST SE M 32 28TH ST SE M 32 H A R W O O D T O W N S H I P 25TH ST SE 167TH AVE SE 27TH ST SE Rush River B E R L I N T O W N S H I P M 81 HARWOOD Lower Branch Rush River 30TH ST SE Drain 9 64TH AVE N 31ST ST SE M TH ST N 81ST ST N 52ND AVE N Drain 67 37TH ST N 45TH ST N 57TH ST N M 20 32ND AVE NW 29 OLD US HWY 81 N 32ND AVE N 45TH ST N R E E D T O W N S H I P M 17 57TH ST N Drain 21 14TH ST NW 26TH ST NW 19TH AVE NW Drain 10 Sheyenne Diversion Drain 45 WEST FARGO Sheyenne River Tributary FARGO 15TH ST W 93RD ST N 26TH ST W 38TH ST NW R A Y M O N D T O W N S H I P 34TH ST SE 35TH ST SE 12TH AVE NW 36TH ST SE SHEYENNE DIVERSION RD 37TH ST SE 94 M 28 13TH AVE W 38TH ST SE 21ST AVE W 39TH ST SE M 15 15TH ST W 32ND AVE W 38TH 166TH 40TH ST SE M 11 32ND ST SE M 11 M 20 3RD ST SE 163RD AVE SE M 11 37TH ST SE Figure 9 Roadway Surfaces North Red River Diversion Master Transportation Plan 4 Legend Existing Low Flow Crossings Existing Bridges Drains Rivers Proposed Diversion Alignment Roads Outside Study Area Primitive Roads Earth Road Gravel Road Miles Asphalt Road Interstate Highway

22 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 22ND ST SE 23RD ST SE 25TH ST SE Drain 65 40TH AVE N 19 AVE N 19TH AVE N I94 M 81 Red River Tributary Drain 24C Drain 13 I29 M 34 W I S E R T O W N S H I P CO RD TH AVE SE G A R D N E R T O W N S H I P 22ND ST SE 23RD ST SE Drain TH AVE I29 SE M 4 ARGUSVILLE M 4 29 Drain 30 -Improve Roadway Surface to Gravel -Install Box Culvert at River Crossing 26TH ST SE Sheyenne River CO RD 81 28TH ST SE M 32 28TH ST SE M 32 H A R W O O D T O W N S H I P 25TH ST SE 167TH AVE SE 27TH ST SE Rush River B E R L I N T O W N S H I P M 81 HARWOOD Lower Branch Rush River 30TH ST SE Drain 9 105TH ST N 64TH AVE N 31ST ST SE M ST N 81ST ST N 52ND AVE N Drain 67 37TH ST N 45TH ST N 57TH ST N M OLD US HWY 81 N Drain 21 26TH ST NW -Improve Roadway Surface to Gravel -Install New Box Culvert at River Crossing 32ND AVE N 32ND AVE NW 45TH ST N R E E D T O W N S H I P M 17 57TH ST N 14TH ST NW 19TH AVE NW Drain 10 Sheyenne Diversion Drain 45 WEST FARGO Sheyenne River Tributary FARGO 94 15TH ST W 93RD ST N 26TH ST W 38TH ST NW R A Y M O N D T O W N S H I P 35TH ST SE 12TH AVE NW 36TH ST SE SHEYENNE DIVERSION RD 37TH ST SE M 28 13TH AVE W 38TH ST SE 21ST AVE W 39TH ST SE 15TH S M 15 M 11 Figure 10 Mobility Improvements North Red River Diversion Master Transportation Plan 4 32ND ST SE M 11 M 20 Legend Mobility Improvements Proposed Box Culverts D ST SE 163RD AVE SE Proposed Diversion Crossings Existing Low Flow Crossings Existing Bridges Drains M 11 37TH ST SE Rivers Proposed Diversion Alignment Miles Roadway Centerlines Interstate Highway

23 POSTAL SERVICE IMPROVEMENTS The Harwood Post office currently serves all homes within the study area with the exception of the one-mile section south of CR 20. Based upon input received from the Harwood Post Office, the proposed configuration of diversion crossings would not significantly impact service within the area. The major concern of the post office was construction phasing and timing. Currently the post office receives mail sequenced based upon delivery routes. As roads are closed for bridge construction, mail carriers may be forced to alter routes. Refer to the section titled Construction Needs for further details regarding constructing phasing. SCHOOL IMPROVEMENTS Based upon input received from the West Fargo and Northern Cass school districts, the proposed configuration of diversion crossings would not significantly impact school bussing routes within the area. Northern Cass officials supported the recommendation of improving 167 th Avenue Southeast along the diversion channel. They anticipated that this roadway would improve bussing operations in the area. CONSTRUCTION IMPROVEMENTS Preliminary analysis indicates that due to the presence of existing roadway barriers and connectivity to Interstate- 29 that the anticipated construction haul routes will be predominantly, if not exclusively, on the county road network. Furthermore, these roadways currently carry the highest traffic volumes. As a result, there are no construction route roadway improvements recommended on the township network. Bridge construction is anticipated to restrict traffic at crossing locations in excess of one calendar year. Due to the length of construction, temporary construction bypass routes are recommended to accommodate traffic. At the lower volume crossing locations, it may be cost effective to utilize the available existing infrastructure for the bypass route by detouring traffic to the next section line. Adjacent section lines that are not designed for increased traffic loading will require roadway upgrades. For example, the one-mile section of 29 th Street Southeast between 167 th and 168 th Avenues Southeast will need to be upgraded from a minimum maintenance earth roadway to a gravel roadway to accommodate bypass traffic from CR 32. Utilizing the existing infrastructure may be impractical at specific county roads diversion crossings. At CR 20 and CR 81 in particular, no adjacent roadways exist to bypass the roadway without significant detour miles. These roadways experience the highest traffic volumes within the study area. As a result, it is recommended to construct an adjacent temporary bypass route offset approximately 200 feet from the roadway. The majority of this proposed bypass can be constructed within the ROW required for the Diversion Channel. Refer to FIGURE 11 for details regarding proposed bypass routes. Construction phasing was a topic of discussion at the majority of the meetings. The concept of constructing the bridges before the diversion was fully supported, however it was requested that traffic not be impacted on consecutive county roads. In particular, a major concern was that both CR 20 and CR 22 would be concurrently constructed causing significant inconvenience to roadway users. Based upon this input, it recommended that the contractor (or contractors in coordination) shall not be permitted to have consecutive county roads under construction at a single time. This rule would not apply to county road crossing locations that do not occur in the existing roadway right-of-way due to proposed alignment revisions (i.e. CR 4 and 31). Kadrmas, Lee & Jackson Final Report P age 16

24 Another topic of discussion at the majority of meetings was the maintenance of any roadway used as a construction route. The study team assured all invested parties that maintenance agreements would be established with all contractors prior to beginning any work. It is recommended, however, that the breadth of this agreement be extensive to ensure that each roadway is periodically maintained in a timely manner, specifically after periods of inclement weather. It is important to note that high volumes of heavy construction traffic may result in a scenario where maintenance cannot be conducted adequately or timely enough to provide acceptable riding conditions for motorists. This scenario may require that specific roadways be upgraded to pavement. At this stage in project development, the extent of construction travel each roadway will experience is unknown. Due to the cost associated with converting a gravel roadway to pavement and the added cost of maintaining a paved roadway, the final decision to upgrade a roadway should be decided once the extent of construction travel is determined. It is important to note that it is not anticipated that any roadways will require paving at this time. Additionally, all paving decisions must be approved by the proper roadway maintenance authority (county or township). FURTHER DISCUSSION The following discussion points were either received as input during one or more project meetings or arose during technical analysis. The points did not dictate the result of this study, however the comments should be considered during project development. Bridge Width: Bridge width was a major topic of discussion at the township meetings. The majority of township farmers preferred bridge deck widths exceeding 40 feet, which is beyond the Cass County standard for bridge decks for graveled or paved roadways. The general feeling was that a combine with an attached header would not be able to traverse a bridge with a smaller deck. Although the combine header should be able to clear the outside bridge barriers, the signs and hazard markers mounted on these barriers would create complications if they were fixed. Additionally, the crown of a 600-foot bridge may hide a combine occupying the entirety of the bridge from a motorist on the opposite end of the bridge. This scenario would create a potential conflict point on the bridge. There was a small group of farmers that mentioned pulling the header behind the combine whenever crossing a bridge as an acceptable alternative; however, the group was in the minority. If the bridge width is not expanded to prevent conflicts on the bridge it may be necessary to develop regulations that prohibit vehicles wider than a determined width on the diversion crossing bridges. Frontage Roads: There was a small minority of meeting attendees that felt that frontage roads along the outside or on top of the diversion embankments should be established for general public use. The study team and the majority of attendees believed that these frontage roads would experience minimal utilization, particularly once roadway users become accustomed to bridge crossing locations. Furthermore, establishing new roadways would add additional township maintenance costs from an already constrained funding source. The majority of township board members felt that the most cost effective improvements corresponded to improvements to existing roadways. New Bypass Routes versus Bypass Routes on Existing Infrastructure: As previously documented, the proposed plan is to develop new bypass routes at locations where traffic volumes are the greatest and where no adjacent infrastructure is within in a reasonable distance. This resulted in new bypass routes for CR 20 and CR 81. The proposed bypass routes for CR 32 and 22 would utilize adjacent infrastructure. Although impacts from these circuitous routes would be minimal, an increased sensitivity must be Kadrmas, Lee & Jackson Final Report P age 17

25 considered for emergency responders. The proposed bypass routes at CR 32 and 22 are anticipated to add an additional minutes of travel time on these roadways. Kadrmas, Lee & Jackson Final Report P age 18

26 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 22ND ST SE 23RD ST SE 25TH ST SE Drain 65 40TH AVE N 19 AVE N 19TH AVE N M 81 Red River Tributary Drain 24C Drain 13 I29 M 34 W I S E R T O W N S H I P CO RD TH AVE SE G A R D N E R T O W N S H I P 22ND ST SE 23RD ST SE Proposed CR 81 Bypass Route: -Constructed as New Gravel Roadway Drain TH AVE I29 SE M 4 ARGUSVILLE 29 Sheyenne River M 32 M 32 Proposed CR 32 Bypass Route: -Use of Exsiting Roadways -Resurface Earth Roadways With Gravel -Box Culvert Installation at Rush River and 167th Ave SE Improvements Established as Part of Mobility Enhancements M 4 Drain 30 26TH ST SE CO RD 81 28TH ST SE 28TH ST SE H A R W O O D T O W N S H I P 25TH ST SE Rush River B E R L I N T O W N S H I P 27TH ST SE M 81 HARWOOD Lower Branch Rush River 30TH ST SE Drain 9 64TH AVE N 25 ST N Drain 67 Proposed CR 22 Bypass Route: -Use of Existing Roadways M 13 31ST ST SE 81ST ST N 52ND AVE N 37TH ST N 45TH ST N 105TH ST N M OLD US HWY 81 N 32ND AVE N Drain 21 Proposed CR 20 Bypass Route: -Constructed as New Gravel Roadway 32ND AVE NW 45TH ST N R E E D T O W N S H I P M 17 57TH ST N 14TH ST NW 26TH ST NW 19TH AVE NW Drain 10 Sheyenne Diversion Drain 45 WEST FARGO Sheyenne River Tributary FARGO 15TH ST W 93RD ST N 26TH ST W 38TH ST NW R A Y M O N D T O W N S H I P 34TH ST SE 35TH ST SE 12TH AVE NW 36TH ST SE 37TH ST SE M 28 13TH AVE W 38TH ST SE 94 21ST AVE W 39TH ST SE 15TH S M 15 M 11 Figure 11 Proposed Bypass Routes 4North Red River Diversion Master Transportation Plan 32ND ST SE M 11 M 20 Legend D ST SE 163RD AVE SE Construction Bypass Routes Proposed Diversion Crossings Existing Low Flow Crossings Existing Bridges Drains M 11 37TH ST SE Rivers Proposed Diversion Alignment Miles Roadway Centerlines Interstate Highway

27 COST ESTIMATES Cost estimates are based upon average costs compiled from similar past KL&J, County and NDDOT projects. Input from the County indicated that the preferred bridge widths are 36 feet minimum and 40 feet preferred for this project. County standards utilize a 28-foot roadway surface width for two-lane rural gravel sections and 32 feet for two-lane rural paved sections. Based upon this information and input from the County, the 36-foot bridges widths were utilized for bridges on gravel roadways and 40-foot bridges on paved roadways. The only exception was CR 20. The county anticipates this roadway requiring an upgrade from gravel to pavement in the near to intermediate future. Cost estimates with quantities can be found in APPENDIX A COST ESTIMATES. TABLE I Cost Estimates Cost Roadway Bridge Bypass Total County Road 4/31 $3,004,100 $3,784,500 $0 $6,788,600 County Road 81 $717,000 $4,205,000 $1,010,900 $5,932,900 County Road 32 $694,600 $4,241,300 $329,200 $5,265,100 County Road 22 $95,900 $4,045,500 $329,200 $4,470,600 County Road 20 $81,700 $4,640,000 $1,010,900 $5,732, th Ave SE Improvements $2,370,800 $0 $0 $2,370,800 27th St SE Connection to CR 81 $502,400 $0 $0 $502,400 Roadway Terminations at Diversion $323,400 $0 $0 $323,400 Box Culvert at Drain 13 and 170th Ave SE $362,500 $0 $0 $362,500 CR 4 Roadway to Parcel Connection $88,800 $0 $0 $88, th Ave SE Roadway to Parcel Connection $71,100 $0 $0 $71,100 Total $8,312,300 $20,916,300 $2,680,200 $31,908,800 Note: Cost Includes 25% Contingency and 20% Engineering Fee CONCLUSION Through various meetings and discussion with the general public and local agencies directly affected by the proposed diversion channel, it was clear that the diversion offers several transportation obstacles corresponding to connectivity, accessibility and mobility. In response to these obstacles, the study team developed solutions to remedy or minimize project impacts. Not only are engineering solutions identified in this study, relationships and consensus was built with those directly affected. These relationships offer benefits throughout the entire FM diversion project from development into construction. It is recommended that the outlets of communication be maintained as this project transitions from planning into development. All parties are affected by the roadway closures to varying degrees, whether it be during a daily commute to work or during emergency response calls. Timely notification allows roadway users to adapt to the changing roadway network landscape. This will not only prevent motorist delay resulting from unnecessary detouring, but will also help improve relationships with those opposing the project. FIGURE 12 illustrates each study recommendation on one map. Kadrmas, Lee & Jackson Final Report P age 20

28 19TH ST SE Drain 23 Maple River Drain 25 20TH ST SE Drain 26 22ND ST SE 23RD ST SE 25TH ST SE Drain TH AVE N E 19 AVE N 19TH AVE N D M 81 Red River Tributary Drain 24C Drain 13 I29 Proposed CR 4/CR 31 Roadway Realignment M 34 W I S E R T O W N S H I P CO RD TH AVE SE G A R D N E R T O W N S H I P 22ND ST SE 23RD ST SE Drain TH AVE I29 SE M 4 -Install Box Culvert ARGUSVILLE Proposed CR 81 Bypass Route: -Constructed as New Gravel Roadway M 4 29 Drain 30 New Gravel Roadway CO RD 81 Sheyenne River Proposed CR 32 Bypass Route: -Use of Exsiting Roadways -Resurface Earth Roadways With Gravel -Box Culvert Installation at Rush River and 167th Ave SE Improvements Established as Part of Mobility Enhancements -New Gravel Roadway M 32 -New Gravel Roadway -Improve Roadway Surface to Gravel -Install Box Culvert at Rush River Crossing 28TH ST SE M 32 H A R W O O D T O W N S H I P 25TH ST SE Proposed CR 32 Roadway Realignment 167TH AVE SE 27TH ST SE Rush River B E R L I N T O W N S H I P M 81 HARWOOD Lower Branch Rush River 30TH ST SE Drain 9 64TH AVE N 25 ST N 81ST ST N Proposed CR 22 Bypass Route: -Use of Existing Roadways M 13 31ST ST SE 52ND AVE N 37TH ST N 45TH ST N 57TH ST N 29 -Improve Roadway Surface to Gravel -Install New Box Culvert at River Crossing M 20 Drain TH ST N OLD US HWY 81 N 32ND AVE N 32ND AVE NW 45TH ST N R E E D T O W N S H I P M 17 57TH ST N Drain 21 14TH ST NW 26TH ST NW 19TH AVE NW Drain 10 Proposed CR 20 Bypass Route: -Constructed as New Gravel Roadway Sheyenne Diversion Drain 45 WEST FARGO Sheyenne River Tributary FARGO 94 15TH ST W 93RD ST N 26TH ST W 34TH ST SE 38TH ST NW R A Y M O N D T O W N S H I P 35TH ST SE 12TH AVE NW 36TH ST SE SHEYENNE DIVERSION RD 37TH ST SE M 28 13TH AVE W 38TH ST SE 21ST AVE W 39TH ST SE 15TH S M 15 M 11 Figure 12 Overall Project Recommendations North Red River Diversion Master Transportation Plan Miles 26TH ST SE 4 28TH ST SE 32ND ST SE M 11 M 20 Legend Cutoff Roads Proposed Diversion Crossings Proposed Box Culverts Existing Low Flow Crossings Existing Bridges Construction Bypass Routes Mobility Improvement (Earth Surface to Gravel Surface) 163RD AVE SE Accessibility Improvement Proposed Roadway Realignment Roadway Removal Drains Rivers Interstate Highway Proposed Diversion Alignment Roadway Centerlines Parcels Without Access* Parcel Lines *Does not include property that can be accessed by adjoining parcels with matching owner M 11 37TH ST SE

29 APPENDIX A - COST ESTIMATES Kadrmas, Lee & Jackson Final Report P age 22

30 Kadrmas, Lee & Jackson Final Report P age 23

31 Kadrmas, Lee & Jackson Final Report P age 24

October. South Diversion Master Transportation Plan Final Report

October. South Diversion Master Transportation Plan Final Report October 2013 South Diversion Master Transportation Plan Final Report Table of Contents TABLE OF CONTENTS 1 Executive Summary... 1 1.1 Connectivity...1 1.2 Accessability...2 1.3 Mobility...2 1.4 Discarded

More information

Appendix K Civil Engineering

Appendix K Civil Engineering Appendix K Civil Engineering Fargo-Moorhead Metropolitan Area Flood Risk Management Final Feasibility Report and Environmental Impact Statement Prepared by: U.S. Army Corps of Engineers St. Paul District

More information

Project Alignment Appendix A

Project Alignment Appendix A Project Alignment Appendix A Fargo Moorhead Metropolitan Area Flood Risk Management Project EA Document This page is intentionally left blank Project Alignment Appendix A Table of Contents 1 BACKGROUND...

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects SEPTEMBER 1989 Arkansas State Highway and Transportation Department GEOMETRIC DESIGN CRITERIA for Non-freeway

More information

FEMA/USACE Coordination Plan

FEMA/USACE Coordination Plan FEMA/USACE Coordination Plan Project: Fargo-Moorhead Metropolitan Feasibility Study ND Diversion Channel with upstream staging Federal Plan (Authorized WRRDA 2014) Project Design: Project Reach: U.S. Army

More information

CHAPTER 3 SCOPE SUMMARY

CHAPTER 3 SCOPE SUMMARY CHAPTER 3 SCOPE SUMMARY GENERAL The SDDOT is an active member of AASHTO to share common national design standards for the state highway system. The AASHTO Task Force on Geometric Design has completed the

More information

DRAFT AIR QUALITY TECHNICAL MEMORANDUM

DRAFT AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM PROJECT DEVELOPMENT AND ENVIRONMENT STUDY STATE ROAD 60 GRADE SEPARATION OVER CSX RAILROAD Polk County, Florida Financial Project ID: 436559-1-22-01 Prepared for: Florida

More information

Fargo-Moorhead Flood Risk Management Project Supplement to Environmental Impact Statement (SEIS) Final Preparation Notice May 21, 2018

Fargo-Moorhead Flood Risk Management Project Supplement to Environmental Impact Statement (SEIS) Final Preparation Notice May 21, 2018 Fargo-Moorhead Flood Risk Management Project Supplement to Environmental Impact Statement (SEIS) Final Preparation Notice May 21, 2018 1. Title of EIS being supplemented and date of completion: Final Environmental

More information

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

Executive Summary. Overview

Executive Summary. Overview Executive Summary Overview The Genesee-Finger Lakes Diversion Route Initiative identifies the most suitable diversion routes for Principal Arterial roads in the nine-county Genesee-Finger Lakes Region.

More information

US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison

US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison T E C H N I C A L M E M O R A N D U M US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison PREPARED FOR: Mn/DOT District 7 PREPARED BY: CH2M HILL DATE: March 27, 2007 This technical

More information

APPENDIX D ACCESS MANAGEMENT GUIDELINES

APPENDIX D ACCESS MANAGEMENT GUIDELINES APPENDIX D ACCESS MANAGEMENT GUIDELINES Access management has become an important tool in transportation planning. Access management guidelines are intended to preserve the integrity of roadways by balancing

More information

SECTION 6. ROAD CONSTRUCTION STANDARDS

SECTION 6. ROAD CONSTRUCTION STANDARDS SECTION 6. ROAD CONSTRUCTION STANDARDS Construction of new roads or reconstruction of existing roads proposed for dedication to the County shall conform to the standards set forth in this section. Roads

More information

500 Interchange Design

500 Interchange Design 500 Interchange Design Table of Contents 501 Interchange Design... 5-1 July 2015 501.1 General... 5-1 501.2 Interchange Type... 5-1 501.2.1 General... 5-1 502 Interchange Design Considerations... 5-2 502.1

More information

Appendix B. Design. Page i. Design

Appendix B. Design. Page i. Design Page i Princeville, North Carolina Flood Risk Management Integrated Feasibility Report and Environmental Assessment Table of Contents 1.1. Introduction... 1 1.2. Existing Conditions... 1 1.3. Objectives...

More information

5/11/2016 SR 15 SECTION 088 CSVT SOUTHERN SECTION SR 15 SECTION 088 CSVT SOUTHERN SECTION AGENDA

5/11/2016 SR 15 SECTION 088 CSVT SOUTHERN SECTION SR 15 SECTION 088 CSVT SOUTHERN SECTION AGENDA PUBLIC OFFICIALS MEETING MAY 11, 2016 AGENDA I. INTRODUCTIONS V. CURRENT PROJECT STATUS VI. PROJECT SCHEDULE VII. UPCOMING ACTIVITIES VOPEN DISCUSSION & QUESTIONS IX. ACTION ITEMS 1 A. Bridge Lighting

More information

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares

More information

Design Documentation Report

Design Documentation Report 10/18/2013 Design Documentation Report Fargo-Moorhead Flood Risk Management Project Reaches 1, 3, 4, and 5 Bridge Channels Engineering and Design Phase Reaches 1, 3, 4, and 5 Post 90% SUBMITTAL Table of

More information

4.12 Public and Emergency Services

4.12 Public and Emergency Services 4.12 Public and Emergency Services Public services include schools, community centers, cemeteries, and social service providers. Emergency services include fire and police stations and services, hospitals,

More information

Mendocino Forest Products Grading For Industrial Land Improvements

Mendocino Forest Products Grading For Industrial Land Improvements Mendocino Forest Products Grading For Industrial Land Improvements Technical Memorandum #10 CEQA Evaluation of Environmental Impacts Prepared for: Mendocino Forest Products Company, LLC Consulting Engineers

More information

4.11 TRAFFIC AND CIRCULATION

4.11 TRAFFIC AND CIRCULATION 4.11 4.11.1 ENVIRONMENTAL SETTING EXISTING TRAFFIC CONDITIONS Hyampom Road is the only all-weather access to the community of Hyampom, thereby making it the only school bus and mail route. It is also a

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0 SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605/SR-60 EA# 3101U0 October 9, 2017 Contents 1 Purpose of ICE Memo... 1 2 Background... 1 3 Existing Interchange Deficiencies... 1 4 Context Sensitive

More information

500 Interchange Design

500 Interchange Design 500 Interchange Design Table of Contents 501 Interchange Design... 1 501.1 General... 1 501.2 Interchange Type... 1 501.2.1 General... 1 502 Interchange Design Considerations... 2 502.1 Determination of

More information

M D 355 [FR E D E R IC K R O A D] OVER

M D 355 [FR E D E R IC K R O A D] OVER M D 355 [FR E D E R IC K R O A D] OVER LITTLE BENNETT CREEK MAINTENANCE OF TRAFFIC ALTERNATIVE ANA LYSIS Prepared by: INTRODUCTION The purpose of this report is to present the results of traffic analyses

More information

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc. 2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction

More information

Information for File # RJH

Information for File # RJH Information for File #2011-01629-RJH Applicant: Matthew Ternes Corps Contact: Ryan Huber, U. S. Army Corps of Engineers, 211 North Broadway, Suite 221, Green Bay, Wisconsin 54303; ryan.j.huber@usace.army.mil;

More information

WOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011

WOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 CHAPTER 1: INTRODUCTION... 5 1.1 Study Purpose and background... 5 1.2 Study Approach... 6 1.3 Study Area... 6 CHAPTER 2: DESCRIPTIONS OF ALTERNATIVES... 7 2.1

More information

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 INTERCHANGE MODIFICATION REPORT FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 PREPARED BY: VIRGINIA DEPARTMENT OF TRANSPORTATION STAUNTON DISTRICT DECEMBER 13, 2006

More information

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project 06/2014 PROJECT STUDY REPORT (Cal Poly Pomona Senior Project) For Conceptual Approval of an Interchange Improvement And Cooperative Agreement with The City of Lake Elsinore for completion of Project Approval

More information

Kansas NG911 Addressing Guidelines

Kansas NG911 Addressing Guidelines Kansas NG911 Addressing Guidelines Version 1.0 Prepared by the GIS Committee on behalf of the Kansas 911 Coordinating Council Document Change Log Date Author Change Reason 25 Jan 18 GIS Committee Initial

More information

Common questions on project details

Common questions on project details Common questions on project details Alternatives Considered Project Benefits Page 2 Page 4 Litigation & Legal Issues Page 5 Rush River Lower Rush River Inlet Structure Lower Rush River Inlet Structure

More information

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South

More information

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination 4-65 Interstate 73 FEIS: I-95 to the Myrtle Beach Region 4-66 Comment noted. The use of existing roadways was considered during alternative development (refer to Chapter 2, Section 2.1, page 2-1 and the

More information

Interchange Workshop Report (August 2004)

Interchange Workshop Report (August 2004) U.S. Highway 14 Corridor Study New Ulm to North Mankato Table of Contents Section Interchange Workshop Report (August 2004) Page 1. Introduction and Next Steps 1 2. Interchange Workshop Participants &

More information

U.S. Army Corps of Engineers Permit Application Tips

U.S. Army Corps of Engineers Permit Application Tips U.S. Army Corps of Engineers Permit Application Tips MnDOT Environmental Conference Ben Orne and Sarah Wingert, USACE 4-29-2015 US Army Corps of Engineers BUILDING STRONG Outline Introduction to Corps

More information

SUBDIVISION SECTION STREET DESIGN MANUAL

SUBDIVISION SECTION STREET DESIGN MANUAL CITY OF ANAHEIM SUBDIVISION SECTION STREET DESIGN MANUAL A. INTRODUCTION : POLICY STATEMENT B. STREET CLASSIFICATION C. STREET STANDARDS REQUIREMENTS Requirements Approval of Street Improvement Plans Widening

More information

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002 TRANSPORTATION INTERSTATE 87 INTERCHANGE 11A TOWN OF MALTA SARATOGA COUNTY, NY DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002 PROJECT REPORT NEW YORK STATE DEPARTMENT OF TRANSPORTATION JOSEPH

More information

Willmar Wye Public Open House #4 and Public Hearing

Willmar Wye Public Open House #4 and Public Hearing Willmar Wye Public Open House #4 and Public Hearing February 23, 2017 www.dot.state.mn.us/d8/willmarwye Agenda Time Topic 5:00 pm Open House Opportunity for the public to ask questions of project staff

More information

Fargo-Moorhead Metro Flood Risk Management Project

Fargo-Moorhead Metro Flood Risk Management Project Fargo-Moorhead Metro Flood Risk Management Project MFR -011 FMM Project Alignment - Outlet Structure to Maple River Aqueduct Prepared by: U.S. Army Corps of Engineers, Saint Paul District 1 Table of Contents

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

Recommended Roadway Plan Section 3 Existing Facilities & System Performance

Recommended Roadway Plan Section 3 Existing Facilities & System Performance Recommended Roadway Plan Section 3 Existing Facilities & System Performance RECOMMENDED ROADWAY PLAN SECTION 3 Existing Facilities and System Performance 3.1 Introduction An important prerequisite to transportation

More information

CHAPTER 2 - TRAVEL DEMAND MODEL DEVELOPMENT

CHAPTER 2 - TRAVEL DEMAND MODEL DEVELOPMENT CHAPTER 2 - TRAVEL DEMAND MODEL DEVELOPMENT 2.1 EXISTING TRAVEL DEMAND MODEL In order to accurately project future year traffic volumes within this regional study area, it was first necessary to construct

More information

SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work

SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work 2004 Specifications CSJ: 0932-01-076 SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work 1.0 Description of Project 1.1. General. This project provides for the widening of

More information

Arterial Connector Study Adoption Considerations

Arterial Connector Study Adoption Considerations Arterial Connector Study Adoption Considerations 1. The Problem/Opportunity. Dakota County, MnDOT and the cities of Inver Grove Heights and Rosemount have conducted this study because Dakota County is

More information

Page 1D-1 Revised language to link from Project Management Manual to Project Management Online Guide.

Page 1D-1 Revised language to link from Project Management Manual to Project Management Online Guide. IMPERIAL ROAD DESIGN MANUAL REVISIONS July 2008 CHAPTER 1D Page 1D-1 Revised language to link from Project Management Manual to Project Management Online Guide. CHAPTER 2A Page 2A-3 Revised language to

More information

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.1 INTRODUCTION A preliminary environmental review was performed on the proposed freeway improvements that form Concept C, which encompasses the three freeway corridors

More information

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS CITY OF ALBANY DEPARTMENT OF PUBLIC WORKS DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS Prepared By PUBLIC WORKS DEPARTMENT ALBANY, OREGON 97321 Telephone: (541) 917-7676 TABLE OF CONTENTS

More information

January 16, Rhode Island Energy Facilities Siting Board 89 Jefferson Boulevard Warwick, Rhode Island 02888

January 16, Rhode Island Energy Facilities Siting Board 89 Jefferson Boulevard Warwick, Rhode Island 02888 INVENERGY 196 January 16, 2019 Rhode Island Energy Facilities Siting Board 89 Jefferson Boulevard Warwick, Rhode Island 02888 Re: Clear River Energy Center Invenergy Docket No. SB-2015-06 When Invenergy

More information

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199)) 11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

Between existing Interstate 70 in St. Louis, MO to west of the IL 203 Interchange on existing I-55/70 in Madison, IL

Between existing Interstate 70 in St. Louis, MO to west of the IL 203 Interchange on existing I-55/70 in Madison, IL American Association of State Highway and Transportation Officials An Application from the State Highway or Transportation Department of Illinois for: Elimination of a U.S. (Interstate) Route Establishment

More information

Rivers Edge Alternative Urban Areawide Review (AUAR) Traffic Study

Rivers Edge Alternative Urban Areawide Review (AUAR) Traffic Study Appendix F Rivers Edge Alternative Urban Areawide Review (AUAR) Traffic Study Prepared by Westwood Professional Services, Inc. for City of St. Paul Park Grey Cloud Island Township October 14, 2003 Introduction

More information

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR July 12, 2002 A Paper Submitted for the AREMA Annual Conference by: Paul B. Satterly, P.E. HNTB CORPORATION 111 Monument Circle, Suite 1200 Indianapolis,

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS SECTION PAGE NO. SECTION TITLE NO. EXECUTIVE SUMMARY -------------------------------------------------------------------- ES-1 1.0 INTRODUCTION

More information

Chapter 4: Transportation and Circulation

Chapter 4: Transportation and Circulation Chapter 4: Transportation and Circulation 4.1 Introduction Circulation improvements constructed for the West Valley Logistics Center will improve the functional efficiency of the circulation system in

More information

Appendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South

Appendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South Appendix Q Draft Location Hydraulic Study Report For the State Route 32 Widening Between Fir Street and Yosemite Drive at Dead Horse Slough and South Fork Dead Horse Slough in the, California Draft Location

More information

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

SOUTHWEST LRT (METRO GREEN LINE EXTENSION) 8 Evaluation of Alternatives This chapter evaluates the effectiveness of the No Build Alternative and the Southwest Light Rail Transit (LRT) Project (the Project) based on the information contained in

More information

Zoning Permits 11-1 ZONING PERMITS

Zoning Permits 11-1 ZONING PERMITS Zoning Permits 11-1 ZONING PERMITS (a) Building or structures shall be started, repaired, reconstructed, enlarged or altered only after a zoning permit has been obtained from the administrator and a building

More information

Mountain View County Local Road Management Plan

Mountain View County Local Road Management Plan Mountain View County Local Road Management Plan Joey Sherstabetoff, P.Eng. Amec Foster Wheeler Environment & Infrastructure 2015 RoaData Conference Red Deer, Alberta Thursday, January 22 nd, 2015 Introduction

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV Noise Technical Report 2015 Addendum NOISE TECHNICAL REPORT 2015 Addendum PREPARED FOR: Federal Highway Administration and Georgia Department of Transportation PREPARED BY: Parsons Brinckerhoff Project

More information

Appendix F: Noise Report

Appendix F: Noise Report Appendix F: Noise Report HIGHWAY 404 HIGHWAY 407 TO GREEN LANE (W.O. 03-20024) REGIONAL MUNICIPALITY OF YORK NOISE REPORT Preliminary Design and Class Environmental Assessment Study Class Environmental

More information

Chapter 6 Freight Plan

Chapter 6 Freight Plan Chapter 6 Freight Plan Overview This chapter presents a review and assessment of needs, deficiencies, policies and improvement options affecting the freight transportation system within the Medford Urban

More information

Information for: File # RQM

Information for: File # RQM Information for: File # 2013-04711-RQM Applicant: Todd County Highway Department Corps Contact: Robert Maroney Address: 10867 East Gull Lake Drive NW Brainerd, Minnesota 56401 E-Mail: robert.q.maroney@usace.army.mil

More information

South Dakota Department of Transportation. Interchange Modification Justification Report. Interstate 90 Exit 44 (Bethlehem Road - Piedmont)

South Dakota Department of Transportation. Interchange Modification Justification Report. Interstate 90 Exit 44 (Bethlehem Road - Piedmont) South Dakota Department of Transportation Interchange Modification Justification Report Interstate 90 Exit 44 (Bethlehem Road - Piedmont) February 28, 2014 Prepared By: SDDOT Office of Project Development

More information

Larimer County Land Use Code Section 5.8: Rural Land Use Process

Larimer County Land Use Code Section 5.8: Rural Land Use Process Larimer County Land Use Code Section 5.8: Rural Land Use Process 5.8.6 PRINCIPLES D. Development Standards 3. Engineering Standards and Guidelines for Roads and Drainage The following Standards and Guidelines

More information

I-69 Angelina and Nacogdoches Counties Scoping Study Executive Summary

I-69 Angelina and Nacogdoches Counties Scoping Study Executive Summary I-69 Angelina and Nacogdoches Counties Scoping Study Executive Summary November 2013 The Texas Department of Transportation (TxDOT) is working to find the most appropriate means to develop the Interstate

More information

CHAPTER 7 ROADWAY STANDARDS AND TECHNICAL CRITERIA

CHAPTER 7 ROADWAY STANDARDS AND TECHNICAL CRITERIA Table of Contents CHAPTER 7 ROADWAY STANDARDS AND TECHNICAL CRITERIA Table of Contents 7-01 ROADWAY DESIGN AND TECHNICAL CRITERIA...1 7-01-01 General...1 7-01-02 Required Design Submittals...2 7-01-03

More information

TRANSPORTATION RELATIONSHIP TO OTHER ELEMENTS OF THE PLAN AND COUNTY REGULATIONS VISION FOR TRANSPORTATION PLANNING ROAD NETWORK SECTION 7

TRANSPORTATION RELATIONSHIP TO OTHER ELEMENTS OF THE PLAN AND COUNTY REGULATIONS VISION FOR TRANSPORTATION PLANNING ROAD NETWORK SECTION 7 TRANSPORTATION Like many growing western counties, Douglas County focuses on one of the most integral elements in land-use planning: transportation. The primary purpose of a transportation network is to

More information

4.9 TRANSPORTATION AND CIRCULATION

4.9 TRANSPORTATION AND CIRCULATION 4.9 TRANSPORTATION AND CIRCULATION 4.9 TRANSPORTATION AND CIRCULATION This section describes the current transportation setting for and generally assesses the impacts of future dairy development on the

More information

Distributed Storage Alternative Screening Analysis February 17, 2015

Distributed Storage Alternative Screening Analysis February 17, 2015 Distributed Storage Alternative Screening Analysis February 17, 2015 Executive Summary The Distributed Storage Alternative (DSA) was conceptualized during the public comment and alternative screening process

More information

Public Notice ISSUED: 20-JAN-2016 EXPIRES: 19-FEB-2016

Public Notice ISSUED: 20-JAN-2016 EXPIRES: 19-FEB-2016 APPLICANT: Shakopee Mdewakanton Sioux Community Public Notice ISSUED: 20-JAN-2016 EXPIRES: 19-FEB-2016 REFER TO: MVP-2015-04726-RMM SECTION: 404 - Clean Water Act 1. APPLICATION FOR PERMIT TO discharge

More information

Appendix C. Wetland Impact Assessment and Two-Part Finding. I-94 St. Michael to Albertville Minnesota Department of Transportation

Appendix C. Wetland Impact Assessment and Two-Part Finding. I-94 St. Michael to Albertville Minnesota Department of Transportation Appendix C Wetland Impact Assessment and Two-Part Finding I-94 St. Michael to Albertville Minnesota Department of Transportation Office of Environmental Stewardship 395 John Ireland Blvd. St. Paul, MN

More information

Essex Junction Highway-Rail Grade Crossing Study

Essex Junction Highway-Rail Grade Crossing Study Communities working together to meet Chittenden County s transportation needs CHITTENDEN COUNTY METROPOLITAN PLANNING ORGANIZATION Essex Junction Highway-Rail Grade Crossing Study October 18, 2000 CCMPO

More information

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting.

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting. On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting. Located in the heart of South Carolina, the I-20/26/126 Corridor is the crossroads of the state

More information

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES 1 PURPOSE... 3 2 PROJECT DESCRIPTION... 5 3 PROJECT COMMON AND PROJECT GENERAL TASKS... 6 4 ROADWAY

More information

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS 603.1 DESCRIPTION Determine the smoothness of the pavement surface and correct the deficiencies as specified in the Contract Documents. For the purposes of this

More information

O Street Arterial Corridor Study

O Street Arterial Corridor Study Prepared for: Weld County Public Works Department P.O. Box 758 1111 H Street Greeley, Colorado 80631 Prepared by: Felsburg Holt & Ullevig 6300 South Syracuse Way, Suite 600 Centennial, CO 80111 303-721-1440

More information

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule

More information

WHETSTONE RIVER RESTORATION PROJECT - ADDENDUM

WHETSTONE RIVER RESTORATION PROJECT - ADDENDUM DRAFT WHETSTONE RIVER RESTORATION PROJECT - ADDENDUM Upper Minnesota Watershed District February 2, 2015 I hereby certify that this plan, specification, or report was prepared by me or under my direct

More information

KANSAS WORK ZONE SAFETY AND MOBILITY PROCESSES AND PROCEDURES

KANSAS WORK ZONE SAFETY AND MOBILITY PROCESSES AND PROCEDURES KANSAS WORK ZONE SAFETY AND MOBILITY PROCESSES AND PROCEDURES Bureau of Transportation Safety and Technology 700 SW Harrison, Topeka, KS 66603 July 30, 2008 Definitions Significant Project All Federal-aid

More information

Highway 12 SP , Willmar Wye Soils Borings, Soils Tests, and Reporting

Highway 12 SP , Willmar Wye Soils Borings, Soils Tests, and Reporting Highway 12 SP 3403-74, Willmar Wye Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003246 General Project Overview This work is located along Trunk Highway (TH) 12, on the west side of Willmar.

More information

ACTION TRANSMITTAL

ACTION TRANSMITTAL ACTION TRANSMITTAL 2016-07 DATE: December 4, 2015 TO: FROM: TAC Planning MTS Staff PREPARED BY: Rachel Wiken (651) 602-1572 SUBJECT: REQUESTED ACTION: RECOMMENDED MOTION: Functional Class Change #1330

More information

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail

More information

Jobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E.

Jobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E. Jobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E. Ohio DOT Work Zone Process Review Ohio DOT Work Zone Process Review This review was conducted by the Ohio Department of Transportation

More information

12 DRAINAGE General Administrative Requirements Standards

12 DRAINAGE General Administrative Requirements Standards 12 DRAINAGE 12.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with drainage, including culverts, bridge hydraulics, roadway ditches, and closed storm

More information

Section IMPLEMENTATION PLAN. 7. Implementation Plan

Section IMPLEMENTATION PLAN. 7. Implementation Plan Section 7 IMPLEMENTATION PLAN 7. Implementation Plan 7.0 Implementation Plan The Tier 1 Final EIS has presented several improvements along the Chicago to St. Louis corridor to meet the purpose and need

More information

Informational Brochure. Proposed Interchange. Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island

Informational Brochure. Proposed Interchange. Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island Informational Brochure Proposed Interchange OF Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island October 5, 2016 Department of Transportation Two Capitol

More information

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 State Project # 0064-965-264, P101, R201, C501, B616, B617, B618, B619, B620, B621, D601, D602 Federal # NHS-064-3(479),

More information

TRANSIT SERVICE GUIDELINES

TRANSIT SERVICE GUIDELINES CHATHAM AREA TRANSIT AUTHORITY FEBRUARY 2014 Table of Contents 1. PURPOSE... 3 2. CAT SERVICE GUIDELINES... 3 3. TRAVEL MARKETS... 4 4. TRANSIT COVERAGE... 4 5. TRANSIT ACCESS... 4 6. BUS STOP SPACING

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL No. 2014-17 DATE: February, 2014 TO: FROM: PREPARED BY: SUBJECT: REQUESTED ACTION: T Bob Paddock Roadway

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY THE COMMONWEALTH OF MASSACHUSETTS Number: P-92-010 Date: 10-08-92 - ) HIGHWAY DEPARTMENT FROM: NON-NHS BRIDGE R&R POLICY The purpose of this Engineering Directive is to formally notify Department Personnel

More information

4.0 Method of Measurement. Measurement for Optional Temporary Pavement Marking will be made to the nearest linear foot.

4.0 Method of Measurement. Measurement for Optional Temporary Pavement Marking will be made to the nearest linear foot. 4.0 Method of Measurement. Measurement for Optional Temporary Pavement Marking will be made to the nearest linear foot. 5.0 Basis of Payment. Payment for OPTIONAL TEMPORARY PAVEMENT MARKING as described

More information

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017 Chester Bridge Environmental Assessment (EA) CAG Meeting #2 October 12, 2017 Agenda Introductions Purpose & Need review and Merger Approval Review of the Conceptual Alternatives Recap of the Public Meeting

More information

TxDOT Houston District Permit Requirements (Information contained herein is subject to change)

TxDOT Houston District Permit Requirements (Information contained herein is subject to change) Houston District Permit Requirements (Information contained herein is subject to change) Access Driveway for Commercial / Industrial Developments; or Street Tie-In / Drainage-Only 1) Complete the three

More information