Alignment of CPM Scheduling and Short Interval Planning

Size: px
Start display at page:

Download "Alignment of CPM Scheduling and Short Interval Planning"

Transcription

1 Alignment of CPM Scheduling and Short Interval Planning Scott Kelly, Walt Disney Imagineering Jeff Betts, Whiting-Turner Contracting Co. Don Rote, Building Point Pacific Steven Solloway, Whiting-Turner Contracting Co. OCTOBER 18, 2017 C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E

2 Evolution of Planning Over a Career Elementary School Modernization- 2 Week Look Ahead 02/04/03 Mobilization Dur Start complete Move on Temp Const Office Trailers Temp Const Office - Furniture Temp Const Office - Equipment Temp Const Office - Phone Temp Const Office - Power Temp Const Office - DSL Fencing at Bld. C & Cov'd Walk Fencing at Onsite Laydown Area Subcontractor Safety Orientation / Planning Meeting Building C Phase 1 Safe / Disconnect Elec, Gas, HVAC, Plumbing, Alarm Electrical Demo Plumbing Demo & Cut-N-Cap HVAC Demo & Cut-N-Cap Phase 1 Soft Demo Phase 1 Hard Demo Layout Mech Roof Op.s to identify dimensions for ordering of pre-fab curb Pending Response to RFI Elec/HVAC/Plumbing/Framer Coord Mt Electrical Rough HVAC Rough Phase 3 Work Utility Markout for New HC Ramp Barricade Work Area at New HC Ramp Demo for New Ramp Layout & Ecavate Footings New Ramp Footing Templates Footing Reinforcing 2

3 Planning Successes and Lessons Learned Community College Theater and Art Center Four-building summer sprint ($8M) CPM required by Specifications (+) Pull planning new but rapidly embraced (+) Daily coordination accomplished by pull planning Five rows of planning boards (-) Difficulty developing TIA without CPM 3

4 Planning Successes and Lessons Learned Power Plant Multi Year Risk Project ($BBs) (+)Required robust Critical & Near Critical Path Analyses (+) Evaluation of Required Schedule Contingencies (+) Establishing In Field Need Dates for Long Lead Equipment (+) Resource analysis of critical craft labor (-) Limited insight into near term discrete activities and / or constraints (-) Limited communication & buy-in of near term plans & activities 4

5 Planning Successes and Lessons Learned Last Planner System Field-use look-ahead Simple spreadsheet The REAL schedule CPM Schedule Office use contractual tool CPM software The billing schedule 5

6 6

7 Important Questions and How to Answer Them What is the longest path to operation of the Gamma Ray? What constraints are there to getting the plasma vault dried in by net Friday? What is the late date to order the cyborg s holoprojector? What is the turnover date of Lieutenant Raffi s transport shuttle landing pad? What day will humanoid robot s chest plate be welded to his rib supports? Will we delay completion of the Space Sasquatch s village if we only mobilize one rope bridge crew? How many crews will be working in the Little Green Men s palace on second shift this weekend? Are there any impacts to the pour date of the Warlocks s hut foundation if we need to remove and replace the tree branch elements? 7

8 Important Questions and How to Answer Them What is the longest path to operation of the Gamma Ray? What constraints are there to getting the plasma vault dried in by net Friday? What is the late date to order the cyborg s holoprojector? What is the turnover date of Lieutenant Raffi s transport shuttle landing pad? What day will humanoid robot s chest plate be welded to his rib supports? Will we delay completion of the Space Sasquatch s village if we only mobilize one rope bridge crew? How many crews will be working in the Little Green Men s palace on second shift this weekend? Are there any impacts to the pour date of the Warlocks s hut foundation if we need to remove and replace the tree branch elements? Some questions are best answered by the short interval plan 8

9 Important Questions and How to Answer Them What is the longest path to operation of the Gamma Ray? What constraints are there to getting the plasma vault dried in by net Friday? What is the late date to order the cyborg s holoprojector? What is the turnover date of Lieutenant Raffi s transport shuttle landing pad? What day will humanoid robot s chest plate be welded to his rib supports? Will we delay completion of the Space Sasquatch s village if we only mobilize one rope bridge crew? How many crews will be working in the Little Green Men s palace on second shift this weekend? Are there any impacts to the pour date of the Warlocks s hut foundation if we need to remove and replace the tree branch elements? and some by the Critical Path Method schedule. 9

10 Strengths and Weaknesses of the Systems CRITICAL PATH METHOD SCHEDULING (CPM) LAST PLANNER SYSTEM (LPS) PROS CONS Logic Driven PROS CONS Logic Driven Lacks Details Big Picture Daily Detail Lacks Logic Big Picture Not Collaborative Critical Path Group Effort Micro View Critical Path Accountability Daily Detail Ownership Highly Detailed Group Effort Ownership 10

11 Creating the Integrated Process Big Hairy Audacious Goals Defining the ideal Setting ground rules Communicating to the larger team 11

12 The Integrated Process Defined Development using both tools First pass (CPM) Trade informed (CPM) Phase planned (short interval) CPM Pull planned (short interval) Actualized (both) Refinement and addition of detail LPS Stickies Sandbo schedule Active schedule Current published Schedule Development Over Time Initial Schedule Trade Partner Input Pull Planned 12

13 Weekly Meeting Cycle Monday Tuesday Wednesday Thursday Friday Daily Check-in Daily Check-in Phase Plan Daily Check-in Daily Check-in Weekly 6- week Plan Daily Check-in CPM & WWP Sync 13

14 Integration with Other Processes 14

15 Challenges Change! Integration of Varied Stakeholder Eperience Software limitations Compleity of Project 15

16 Successes Current Construction PPC: 82 Communication to a diverse audience Transparency and trust Early warning system Smaller project staff Integration of many disciplines in schedule Smooth integration of phase plans into CPM Happy customer! 16

17 Looking Forward 17

18 In the spirit of continuous improvement, we would like to remind you to complete this session s survey in the Congress app! We look forward to receiving your feedback.

Best Practices for Collaborative Pull Planning of Complex Renovation Work in Manufacturing

Best Practices for Collaborative Pull Planning of Complex Renovation Work in Manufacturing Best Practices for Collaborative Pull Planning of Complex Renovation Work in Manufacturing Samir Emdanat, Ghafari Associates Branden Brickles, General Motors Tim Buckley, Barton Malow Thursday Oct 19 th,

More information

MIS 2101/2901 EXAM 1 REVIEW SESSION. Michelle Purnama Diamond Peer

MIS 2101/2901 EXAM 1 REVIEW SESSION. Michelle Purnama Diamond Peer MIS 2101/2901 EXAM 1 REVIEW SESSION Michelle Purnama Diamond Peer michelle.purnama@temple.edu EXAM FORMAT 25 Multiple Choice Questions First 5 from assigned readings Next 10 from assigned videos & lectures

More information

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams GETTING STARTED WITH LEAN CONSTRUCTION A guide for project teams HOW TO USE THIS DOCUMENT Outlined in this guide are foundational steps for helping project teams improve the predictability and profitability

More information

Introduction to the Last Planner System

Introduction to the Last Planner System Introduction to the Last Planner System Dick Bayer October 3, 2016 1 Agenda: Welcome, overview and introductions Current Practice Last Planner System (LPS) as a series of countermeasures Establishing milestones

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

Course 1 Project Management and Planning in Facilities Connect

Course 1 Project Management and Planning in Facilities Connect Course 1 Project Management and Planning in Facilities Connect PM MODULE HOME SCREEN (COMPANY FOCUS) In today s course, we will explore the following: Facilities Connect Overview Project Management / Planning

More information

Effective Management of the Last Planner System Using vplanner

Effective Management of the Last Planner System Using vplanner Effective Management of the Last Planner System Using vplanner Effective Management of the Last Planner System Using vplanner 2018 LCI Congress Webinar Series Samir Emdanat Director of Product Development

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

Lessons Learned in Agile Enterprise Deployments

Lessons Learned in Agile Enterprise Deployments Lessons Learned in Agile Enterprise Deployments Michael Rudy Aras Managing Consultant Agenda Aras Consulting delivers a range of services for global enterprise customers This presentation will offer Lessons

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION

THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION Dr. Dan Patterson, PMP Chief Design Officer, PLANNING & SCHEDULING Introduction Twenty-five years ago, I was taught that project management was built

More information

Monday to Friday, 1:00 PM to 2:00 PM. Monday-Wednesday-Thursday 8:10 AM to 11:00 AM Tuesday 8:10 AM -12:00 PM

Monday to Friday, 1:00 PM to 2:00 PM. Monday-Wednesday-Thursday 8:10 AM to 11:00 AM Tuesday 8:10 AM -12:00 PM California Polytechnic State University, San Luis Obispo College of Architecture & Environmental Design Construction Management Department CM 214, Residential Construction Management Sections 01 & 02,

More information

THE LAST 100 FEET >> BIM IN THE FIELD TULALIP RESORT HOTEL 2009 AIA TAP BIM AWARDS

THE LAST 100 FEET >> BIM IN THE FIELD TULALIP RESORT HOTEL 2009 AIA TAP BIM AWARDS THE LAST 100 FEET >> BIM IN THE FIELD TULALIP RESORT HOTEL 2009 AIA TAP BIM AWARDS TULALIP RESORT HOTEL >> TABLE OF CONTENTS Architect Statement Descriptive Data Contractor Statement Owner Statement Introduction

More information

THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION

THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION A BASIS White Paper by Dr. Dan Patterson, PMP Introduction Twenty-five years ago, I was taught that project management was built upon the premise of

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

Project Controls for Optimal Execution

Project Controls for Optimal Execution Project Controls for Optimal Execution Scheduling Techniques to Optimize Execution Tony Bolstad, Senior Project Controls Manager, Scheduling & Information Services, Inc. www.1sis.com Agenda Scheduling

More information

Turner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project.

Turner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project. EXHIBIT N - Lean Production Planning System and Innovation Turner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project. Production Planning

More information

County of Santa Cruz

County of Santa Cruz County of Santa Cruz County Administrative Office 701 Ocean Street, Suite 520, Santa Cruz, CA 95060-4073 Phone:(831) 454-2100 Fax:(831) 454-3420 TDD/TTY: call 711 Carlos J. Palacios, County Administrative

More information

Lincoln Village Community Park Par Course Project Cordova Recreation & Park District Addendum #1 Issued on Friday January 12, 2018

Lincoln Village Community Park Par Course Project Cordova Recreation & Park District Addendum #1 Issued on Friday January 12, 2018 Lincoln Village Community Park Par Course Project Cordova Recreation & Park District Addendum #1 Issued on Friday January 12, 2018 1. CHANGE: The existing concrete mowbands at each entrance to the par

More information

Gas Operational Forum. 27 March :30AM Radisson Blu Hotel, 130 Tottenham Court Road, London

Gas Operational Forum. 27 March :30AM Radisson Blu Hotel, 130 Tottenham Court Road, London Gas Operational Forum 27 March 2018 09:30AM Radisson Blu Hotel, 130 Tottenham Court Road, London Health & Safety Brief No fire alarm testing is planned for today. In the case of an alarm, please follow

More information

Collaborative Design and Scoping. CH2M s practice of Target Value Design

Collaborative Design and Scoping. CH2M s practice of Target Value Design Collaborative Design and Scoping CH2M s practice of Target Value Design Agenda Purpose of the Collaborative Design and Scoping Process How does the CDS relate to Target Value Delivery? CDS outcome: the

More information

Civil Engineering and Architecture TEKS/LINKS Student Objectives One Credit

Civil Engineering and Architecture TEKS/LINKS Student Objectives One Credit First Six Weeks History of Civil Architect CEA 1.1(A) The student will connect modern structural and architectural designs to historical architectural and civil engineering achievements. CEA 1.1(B) The

More information

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 SECTION 01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 PART 1 GENERAL 1.1 DESCRIPTION The Contractor is responsible for scheduling all design, procurement and construction. A single

More information

Lessons Learned Impacting Bridget Malinowski and John Stevens

Lessons Learned Impacting Bridget Malinowski and John Stevens Lessons Learned Impacting 2015 Bridget Malinowski and John Stevens Agenda Review lessons learned Maintain the schedule Potential change orders Agency coordination Claims process Design and construction

More information

MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT Report Date: Prepared By: Prepared For: MONTHLY PROGRESS REPORT 04 SEPTEMBER REPORT LISTING Project Description 1 S OUTHBOROUGH, MASSACHUSETTS Project Information 1 Payment Status 2 Damages / Claims 2

More information

Full Time Job Title: Tile Setter Job Number: 3303 Hours/Days: Monday-Friday Salary: $20.00/hr Location:

Full Time Job Title: Tile Setter Job Number: 3303 Hours/Days: Monday-Friday Salary: $20.00/hr Location: Full Time Job Title: Tile Setter Job Number: 3303 Hours/Days: Monday-Friday Salary: $20.00/hr Los Angeles, CA Skills Be able to square a room for tile layout. Need to be able to tile shower walls, counter

More information

Mitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction

Mitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction STARTING UP AN ILPD PROJECT Mitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction As to Disney artwork/properties: Disney Lean

More information

CVEN 4087/4434. Construction Engineering Project Plan Assignment. Spring Context

CVEN 4087/4434. Construction Engineering Project Plan Assignment. Spring Context CVEN 4087/4434 Construction Engineering Project Plan Assignment Spring 2008 Context The preconstruction phase is arguably one of the most important phases of construction on any project. Pre-planning before

More information

CORNERCUBE. Lean Construction and Lean Project Delivery: Implications for Cost and Schedule CORNERCUBE. Optimizing Project Outcomes

CORNERCUBE. Lean Construction and Lean Project Delivery: Implications for Cost and Schedule CORNERCUBE. Optimizing Project Outcomes Optimizing Project Outcomes Lean Construction and Lean Project Delivery: Implications for Cost and Schedule What s Happening On LPD Projects Cost Improvement Opportunity Cost LPD Time Improvement Opportunity

More information

Construction Engineering: Reinvigorating the Discipline

Construction Engineering: Reinvigorating the Discipline Construction Engineering: Reinvigorating the Discipline Lean Construction Institute Gregory A. Howell, P.E. A brief history of project management An activity centered operating system develops based on

More information

NOTICE OF MEETING TUESDAY, MAY 9, 2017 Immediately following the 6:00 pm Special Meeting

NOTICE OF MEETING TUESDAY, MAY 9, 2017 Immediately following the 6:00 pm Special Meeting NOTICE OF MEETING TUESDAY, MAY 9, 2017 Immediately following the 6:00 pm Special Meeting I. CALL TO ORDER Park District of Highland Park Board of Park Commissioners West Ridge Center 636 Ridge Rd. Highland

More information

Value of Failure! Students Course! Module 4: Preventing Failure!

Value of Failure! Students Course! Module 4: Preventing Failure! Value of Failure Students Course Content 1. Project Management 2. Basics of risk management Project: The black box of project management Project Idea Project Management Completion / Operation Project management

More information

A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E.

A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E. A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E. Last Planners prepare assignments for people who do work. Last Planners can be found throughout construction

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

I-70 over SR 121 Bridge Slide Construction and Engineering

I-70 over SR 121 Bridge Slide Construction and Engineering I-70 over SR 121 Bridge Slide Construction and Engineering March 6, 2018 Kevin Gorak, American Structurepoint Pete Jerrell, Walsh Construction Project Overview Project Location I-70 in Richmond, IN Project

More information

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation

More information

The Faster Road to Innovation Why Workopolis Went Agile

The Faster Road to Innovation Why Workopolis Went Agile The Faster Road to Innovation Why Workopolis Went Agile What I m Covering Today Why did we transition to Agile? What we wanted to Achieve Highlights of How We Did It What we Achieved What we Learned Technology

More information

Learning Objectives In this class, you will:

Learning Objectives In this class, you will: CS11526 Production Planning and Lean Construction Explained: A Hands-on Simulation Michael Moran Autodesk Todd Elkins Autodesk Nathan Wood DPR Learning Objectives In this class, you will: 1. Learn the

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

College Action Project Worksheet for CAP Projects August 7, 2015 Update for CAP

College Action Project Worksheet for CAP Projects August 7, 2015 Update for CAP College Action Project Worksheet for CAP Projects August 7, 2015 Update for 2015-16 CAP CAP #2.1.2: Increase the use of labor market information (LMI) and forecasting in GRCC Planning Processes Tie current

More information

Sanitary Sewer Backup Prevention Procedures

Sanitary Sewer Backup Prevention Procedures Sanitary Sewer Backup Prevention Procedures Contractor Responsibilities: 1. Fill out daily sanitary sewer backup prevention forms that certify that the sewer system is watertight, free of debris and that

More information

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017 AECOM Field Office 3550 Water Street, NW Under the Key Bridge North Abutment REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.:

More information

A Framework for Schedule Design Planning for Schedule Development

A Framework for Schedule Design Planning for Schedule Development A Framework for Schedule Design Planning for Schedule Development Chris Carson, PSP Corporate Director of Project Controls Patrick Kelly, PSP Project Controls Manager Chris.Carson@alphacorporation.com

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.307 Construction Planning and Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304 호 Project

More information

Enhanced Resource Planning

Enhanced Resource Planning Enhanced Resource Planning With a few resource planning enhancements can get you better schedule models. Just some schedule adjustments you are to do manually when not available within your resource planning

More information

3/6/2014 HOSPITALITY AND RESTAURANT MANAGEMENT CHAPTER LEARNING OBJECTIVES CHAPTER LEARNING OBJECTIVES. Leaders Facilitate the Planning Process

3/6/2014 HOSPITALITY AND RESTAURANT MANAGEMENT CHAPTER LEARNING OBJECTIVES CHAPTER LEARNING OBJECTIVES. Leaders Facilitate the Planning Process HOSPITALITY AND RESTAURANT MANAGEMENT Leaders Facilitate the Planning Process OH 2-2 CHAPTER LEARNING OBJECTIVES Explain basic principles of planning, with an emphasis on how employees can assist, and

More information

Government with Microsoft

Government with Microsoft with Microsoft 1 Initiative Planning Conduct virtual town halls 6 Reach consensus in record time 8 Boost productivity in the field 10 Track files with ease 12 Government with Microsoft Site Scoping Execution

More information

CAMPUS LIFE RETREAT. Strategic Planning Student Health Services. Mary Knudtson, DNSc, NP, FAAN Executive Director

CAMPUS LIFE RETREAT. Strategic Planning Student Health Services. Mary Knudtson, DNSc, NP, FAAN Executive Director CAMPUS LIFE RETREAT Strategic Planning Student Health Services Mary Knudtson, DNSc, NP, FAAN Executive Director Strategic Planning Strategic planning is an organization s process of defining its strategy,

More information

http://www.myvplanner.com Effective Management of Production Planning Information Using vplanner LCI Congress Exhibit Hall Webinar Series Samir Emdanat Peter Ghafari Director of Product Development semdanat@ghafari.com

More information

Design-Build Surgical Center Program Management

Design-Build Surgical Center Program Management Design-Build Surgical Center Program Management Chris Carson, PSP Alpha Corporation Norfolk, Virginia Mission Provide Construction Managers and Owner Stakeholders with Real Time Information Relating to

More information

Toronto Centre-CGAP Regional Course on Supervision of Microfinance Institutions March 2013, Kigali Hosted by Central Bank of Rwanda

Toronto Centre-CGAP Regional Course on Supervision of Microfinance Institutions March 2013, Kigali Hosted by Central Bank of Rwanda Toronto Centre-CGAP Regional Course on Supervision of Microfinance Institutions 17-22 March 2013, Kigali Hosted by Central Bank of Rwanda 1 Toronto Centre-CGAP Regional Course on Supervision of Microfinance

More information

Contractor Safety Performance -

Contractor Safety Performance - Contractor Safety Performance - Maximizing Your Influence Insert then choose Picture select your picture. Right click your picture and Send to back. Copyright 2018 by ERM Worldwide Group Limited and/or

More information

TABLE OF CONTENTS. Student Handout 1: Career Pre-Assessment Student Handout 2: Volunteering, Internships, and Job Shadowing

TABLE OF CONTENTS. Student Handout 1: Career Pre-Assessment Student Handout 2: Volunteering, Internships, and Job Shadowing TABLE OF CONTENTS Lesson 1: The Path to Success (Career and Job Opportunities)... 3 Student Handout 1: Career Pre-Assessment Student Handout 2: Volunteering, Internships, and Job Shadowing Lesson 2: Bread

More information

THE EXPERIENCE MGMT SUMMIT MARKET RESEARCH

THE EXPERIENCE MGMT SUMMIT MARKET RESEARCH THE EXPERIENCE MGMT SUMMIT MARKET RESEARCH MARKET RESEARCH AT QUALTRICS X4 SUMMIT SLC UTAH MARCH 6-9 2018 WHAT IS THE X4 SUMMIT? The 5th annual Qualtrics X4 Summit is the largest gathering of Qualtrics

More information

Dilley ISD 2013 Bond Program Project Update Report June 14, 2016

Dilley ISD 2013 Bond Program Project Update Report June 14, 2016 Dilley ISD 2013 Bond Program Project Update Report June 14, 2016 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going construction phase o Architect BWA: Executed

More information

PLANNING. Ahmed Elyamany, PhD

PLANNING. Ahmed Elyamany, PhD PLANNING Ahmed Elyamany, PhD Lecture Topics Benefits of Planning Use of Project Plan Problems with Day-to-Day Planning Problems Caused By Not Planning Definition of Activity Activity durations Sequencing

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

INBOUND SALES PLAYBOOK. Your Comprehensive Plan for Turning Prospects Into Happy Customers

INBOUND SALES PLAYBOOK. Your Comprehensive Plan for Turning Prospects Into Happy Customers INBOUND SALES PLAYBOOK Your Comprehensive Plan for Turning Prospects Into Happy Customers SO, YOUR BUSINESS WANTS TO GO INBOUND WITH ITS SALES PROCESS? Way to go! You re already on the right track to getting

More information

Management / Supervision Full Time

Management / Supervision Full Time Full Time Job Title: Associate District Manager Job Number: 3599 (ADM) Hours/Days: Monday-Friday Salary: $DOE Approximate Location: Los Angeles, CA Requirements: Skills Requirements: Recent college graduate,

More information

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract The Effects of Comparative 4D Models on Schedule Development and Controls Kevin Coyne, P.E. Managing Engineer, Exponent, Inc. Abstract In this paper the argument is made that the use of comparative 4D

More information

The Essential Product Owner Partnering with the Team

The Essential Product Owner Partnering with the Team The Essential Product Owner Partnering with the Team Bob Galen President & Principal Consultant RGCG, LLC bob@rgalen.com Introduction Bob Galen Somewhere north of 30 years experience Various lifecycles

More information

Transforming Planning and Scheduling at BP Whiting

Transforming Planning and Scheduling at BP Whiting Transforming Planning and Scheduling at BP Whiting How NetPoint is Improving Schedule Quality and Engaging Stakeholders in New Ways Tuesday January 21, 2014 By Kaveh Dabiran, LEED AP 1 Case Study CLIENT

More information

Role Type Pay Band Location Duration Reports to: Seoul, Korea 1 year (renewable thereafter)

Role Type Pay Band Location Duration Reports to: Seoul, Korea 1 year (renewable thereafter) Role Title Customer Management Assistant (CMA) Role Information Role Type Pay Band Location Duration Reports to: Sales and Customer Management J Seoul, Korea 1 year (renewable thereafter) Branch Manager

More information

1.0 PART THREE: Work Plan and IV&V Methodology

1.0 PART THREE: Work Plan and IV&V Methodology 1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring

More information

2019 BUSINESS FORECASTING AND ANALYTICS FORUM MARCH 25-26, 2019 SAN FRANCISCO, CA

2019 BUSINESS FORECASTING AND ANALYTICS FORUM MARCH 25-26, 2019 SAN FRANCISCO, CA 2019 BUSINESS FORECASTING AND ANALYTICS FORUM MARCH 25-26, 2019 SAN FRANCISCO, CA DAY 1 - MONDAY, MARCH 25 TH, 2019 7:45am Registration and Breakfast 8:15am Welcome and Opening Comments 8:30am Opening

More information

AWP: The Silver Bullet for Solving Productivity Problems on Projects?

AWP: The Silver Bullet for Solving Productivity Problems on Projects? AWP: The Silver Bullet for Solving Productivity Problems on Projects? Jim Rammell, Wood Group Mustang Panel Discussion AWP Conference 2014 October 7-8 Houston, TX Introductions Wayne Crew, Director, CII

More information

Kaysville Parks and Recreation Department Request For Bids Pioneer Park Phase I RFB 10-17

Kaysville Parks and Recreation Department Request For Bids Pioneer Park Phase I RFB 10-17 The total construction s shall be broken down into the categories indicated below to provide the Owner with a comparable analysis of each proposal submitted and a method for determining value engineering

More information

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 8.4 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration Evacuation

More information

Managing Work Across the Enterprise

Managing Work Across the Enterprise Managing Work Across the Enterprise Leveraging ArcGIS Online for Service Ticket & Work Order Management A Case Study for How a City Has Enhanced Efficiency and Increased Productivity to Serve Citizens

More information

Emergency Management Maps

Emergency Management Maps ArcGIS for Emergency Management Emergency Management Maps JESS NEUNER ArcGIS for Emergency Management A solution to support the EM Mission Series of useful maps and apps focused on emergency management

More information

12/10/2012. Disney Marketing ROI Case Study DMA Conference. Defining A Marketing ROI Solution. Presentation Agenda

12/10/2012. Disney Marketing ROI Case Study DMA Conference. Defining A Marketing ROI Solution. Presentation Agenda Disney Marketing ROI Case Study DMA Conference Presented by Disney & SAS October 2012 Defining A Marketing ROI Solution Reach the right audience Maximize Return on investment for marketing spend Through

More information

Construction Update. April 2016

Construction Update. April 2016 Construction Update April 2016 Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor

More information

ACCENTURE & SAP SUCCESS FACTORS INVESTIGATE CAPABILITIES WORKBOOK. Imagine where we will go together...

ACCENTURE & SAP SUCCESS FACTORS INVESTIGATE CAPABILITIES WORKBOOK. Imagine where we will go together... ACCENTURE & SAP SUCCESS FACTORS INVESTIGATE CAPABILITIES WORKBOOK Imagine where we will go together... Imagine where we will go together... AGENDA TUESDAY APRIL 19TH 12:00 PM Lunch (outside Ali Conference

More information

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4. Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside

More information

Implementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood

Implementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Modern School Construction in the Pacific Northwest: Achieving Performance and

More information

MATERIAL VISIBILITY. for Owners/Operators: The Importance of A CASE STUDY

MATERIAL VISIBILITY. for Owners/Operators: The Importance of A CASE STUDY The Importance of MATERIAL VISIBILITY for Owners/Operators: A CASE STUDY Canadian Oil Sands Refinery project owner gains unprecedented material visibility across multiple contractors INTRODUCTION ABOUT

More information

THE ENTRELEADER S GUIDE TO DELEGATION

THE ENTRELEADER S GUIDE TO DELEGATION THE ENTRELEADER S GUIDE TO DELEGATION Your business can t grow unless you learn to trust others to help you win. And that starts with delegating to your team. The only problem? Most small-business owners

More information

Cycle Through the Success of Ortho NorthEast s Instant Access Clinic

Cycle Through the Success of Ortho NorthEast s Instant Access Clinic May 16-18, 2018 Caesar s Palace Las Vegas, Nevada Cycle Through the Success of Ortho NorthEast s Instant Access Clinic Kylie Mills, Manager of Scheduling and Phone Triage Krista Bennett, Manager of Clinical

More information

8 WAYS WORKFORCE PLANNING CAN INCREASE YOUR PROFITS

8 WAYS WORKFORCE PLANNING CAN INCREASE YOUR PROFITS 8 WAYS WORKFORCE PLANNING CAN INCREASE YOUR PROFITS TABLE OF CONTENTS Introduction...3 1. Determine Your Current Headcount...4 2. Forecast Attrition...5 3. Forecast Workforce Demand...6 4. Perform a Workforce

More information

Micro Service Architecture

Micro Service Architecture Micro Service Architecture A software developer s view on the Cloud Tobias Abarbanell CTO, Frontiers Media 16-Jun-2016 Micro Service Architecture - Tobias Abarbanell 1 What are Micro services? Micro service

More information

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 Date: March 1, 2010 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org More and more

More information

Long-term Memory Review PROFICIENCY PRACTICE: MONDAY REVIEW

Long-term Memory Review PROFICIENCY PRACTICE: MONDAY REVIEW PROFICIENCY PRACTICE: MONDAY REVIEW 1) When solving a word problem, the first thing to do is the known information 2) When a problem requires more than one step, one strategy is to organize the known information

More information

Product Planning Report. Product planning insights from the world s leading companies

Product Planning Report. Product planning insights from the world s leading companies 2017 Product Planning Report Product planning insights from the world s leading companies What s inside 1 Report Highlights...3 2 Planning & Prioritizing...7 3 Crafting the Plan...11 4 Communicating the

More information

QR Network System Rules

QR Network System Rules QR Network System Rules Capricornia Coal Chain Date: 31/08/2011 QR Network Capricornia System Rules - 1 - QR Network Capricornia System Rules - 2 - Contact Details For more information on this document,

More information

39 Years of Learning the Hard Way. Mark A Etrheim, Mastercraft Homes Inc

39 Years of Learning the Hard Way. Mark A Etrheim, Mastercraft Homes Inc 39 Years of Learning the Hard Way Mark A Etrheim, Mastercraft Homes Inc Clear and compelling marketing Finding good customers Well designed homes Accurate estimating system Best carpenters to frame Highly

More information

SAMPLE WORK PLAN. 2. Execute subcontractor agreements and gather forms and documentation required from each sub

SAMPLE WORK PLAN. 2. Execute subcontractor agreements and gather forms and documentation required from each sub SAMPLE WORK PLAN You have just been awarded a $500,000 construction contract as a prime bidder. You will perform 60% of the work in-house (including your suppliers) and 40% will be performed by 3 different

More information

Dilley ISD 2013 Bond Program Project Update Report March 11, 2015

Dilley ISD 2013 Bond Program Project Update Report March 11, 2015 Dilley ISD 2013 Bond Program Project Update Report March 11, 2015 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going o Architect BWA: Executed 2/20/13 Work on-going

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification

More information

Benny s Campus Store. CCNY Campus Spirit Store operates five days a week. The hours of operation are:

Benny s Campus Store. CCNY Campus Spirit Store operates five days a week. The hours of operation are: Benny s Campus Store 1.00 HOURS OF OPERATION CCNY Campus Spirit Store operates five days a week. The hours of operation are: Monday, Wednesday, Thursday 9:00 am - 5:00 pm When School is in Session Tuesday

More information

White Paper January Budgeting: Beyond spreadsheets

White Paper January Budgeting: Beyond spreadsheets White Paper January 2010 Budgeting: Beyond spreadsheets 2 Contents 3 Business problems 3 Business drivers 3 The solution Break the logjam Modeling built for business change Fewer process headaches, more

More information

Principles of Planning for IT Projects

Principles of Planning for IT Projects Principles of Planning for IT Projects Introduction Building Timings Exercises Meals & refreshments Mobile Phones Part 1 Setting the Scene 1. Course Objectives 2. Where projects come from 3. What is a

More information

A Guide To Your First 30 Days Leading A Business Turnaround

A Guide To Your First 30 Days Leading A Business Turnaround Nebes Consulting LLC William Nebes III, Founder & President bill@nebesconsulting.com (m) +1-603-305-7450 https://nebesconsulting.com @billnebes A Guide To Your First 30 Days Leading A Business Turnaround

More information

Survey of State Park Managers

Survey of State Park Managers Survey of State Park Managers In August 1999, the Legislative Auditor s Office conducted a survey of state park managers. We asked park managers about the use of volunteers, state park budget and capital

More information

Reading Utility Meters

Reading Utility Meters Reading Utility Meters Summary: Students observe and interpret daily and weekly patterns of energy consumption by reading utility meters. Objectives Students will be able to read and interpret information

More information

Reliable Decisions in Design

Reliable Decisions in Design Reliable Decisions in Design Paz Arroyo, Lean Project Andy Springer, Jones Lang LaSalle David Long, Lean Project Daniel Kim, Arup Thursday, October 19 th 2017 Presentation Contents Reliable Design Decisions

More information

Robertson Family Farm

Robertson Family Farm Robertson Family Farm Adventures in Blueberry Farming Who are we? James and Sandy purchased the property in February 2013. Matthew and Samantha moved to the farm in June of 2013, and we began our season

More information

Organizational Change Through Metrics

Organizational Change Through Metrics Organizational Change Through Metrics Speaker: Allen Hurst and Heather Rainey Company: Improving Enterprises Website: www.improvingenterprises.com Welcome to the PMI Houston Conference & Expo 2015 Please

More information

ArcGIS for Local Government: An Overview SCOTT OPPMANN

ArcGIS for Local Government: An Overview SCOTT OPPMANN ArcGIS for Local Government: An Overview SCOTT OPPMANN Agenda Introduction Why? Solution Offering What s Next Your Feedback Using ArcGIS to understand and mitigate challenges Housing Forecasting Urban

More information

the Field Company Describe basic Autodesk options analysis,

the Field Company Describe basic Autodesk options analysis, BIM for Contractors: Takin It to the Field David Epps Holder Construction Company Rachel Stalzer Holder Construction Company Class ID: CR2694-P Class Descriptio on Many builders who are implementing BIM

More information