Oconomowoc Area School District Facility Construction Update June 29, 2018
|
|
- Trevor Hudson
- 5 years ago
- Views:
Transcription
1 Oconomowoc Area School District Facility Construction Update June 29, 2018
2 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major work has shifted inside the original building. Demolition inside the original building is complete and framing of new openings and interior walls has begun. New plumbing and fire protection system rough-in is also underway. New exterior concrete work has begun, including the new main entrance ramp, and will continue through early July. The new bus loop will be paved at the end of July. New maker-space in the lower level Sliding walls inside the new addition New openings between classrooms on the main level EXTERIOR AND FINISHING WORK ON THE NEW ADDITION, MAIN BUILDING INTERIOR RENOVATIONS June - August 2018 August 2018 CELEBRATION OF COMPLETION September 23, 2018 Framing for new walls in the lower level New main entrance ramp in progress View time-lapse photos of the full construction progress at Ixonia Elementary by clicking here.
3 MEADOW VIEW ELEMENTARY The Ground Breaking Celebration for the new Meadow View Elementary was held on Friday, June 1. OASD staff, students, parents, and community members joined the festivities and shared their hopes and dreams for the new school. Crews have begun the exterior wall footings and structures are starting to be visible in the area that will be the new gym. Over the summer, work will continue on the footings, foundation, and exterior walls. View time-lapse photos of the full construction progress at Meadow View Elementary by clicking here. BEGAN April 2018 FOOTINGS, FOUNDATION & EXTERIOR WALLS June August 2018 EXTERIOR STRUCTURE, ROOFING, INTERIOR WALLS, ELECTRICAL, PLUMBING, FIRE PROTECTION, CONCRETE, LANDSCAPING & FINISHING WORK August 2018 August 2019 August 2019
4 OCONOMOWOC HIGH SCHOOL: MAIN CAMPUS OHS back hallway on June 8 Renovations inside OHS main campus began immediately after school ended and demolition is complete. The main campus project includes: Remodeling of the existing manufacturing classrooms Remodeling of the existing building trades classrooms Improvement of existing spaces to create a new transportation lab Relocation of robotics classroom space Opening between the construction & manufacturing classrooms, with new hallway window openings OHS back hallway on June 26 with new window openings cut DEMOLITION, PLUMBING IMPROVEMENTS, MASONRY WORK, ROOFTOP AIR UNIT REPLACEMENT June July 2018 NEW WINDOW & DOOR INSTALLATION, WALL FRAMING, DRYWALL, PAINTING, INTERIOR FINISHING July August 2018 August 2018 CELEBRATION OF COMPLETION September 30, 2018 Demolition inside future transportation lab space
5 OCONOMOWOC HIGH SCHOOL: EAST CAMPUS Upper level conference area with new windows Office hallway with drywall and windows installed Openings for skylights above the bridge walkway The interior of OHS East Campus is coming to life as drywall installation nears completion. 90% of the drywall is complete on the first floor and finishing work has begun. 50% of the drywall work is complete on the lower level. 90% of the exterior windows have been installed on the first floor and 50% have been installed on the lower level. Roofing work is 50% complete and will be finished in early July. New exterior metal paneling installation will begin this week and interior painting will begin in mid July. Excavation of the new walking path between Main and East Campus is complete and work continues until the path is paved in mid July. Upper level new windows installed EXTERIOR DEMOLITION & WINDOW REPLACEMENT, PLUBMING, STRUCTURAL STEEL INSTALLATION, METAL FRAMING, FIRE PROTECTION SYSTEM INSTALLATION, EXTERIOR GRADING, ROOF REPLACEMENT, WINDOW REPLACEMENT, WALKING PATH EXCAVATION, DRYWALL INSTALLATION January June 2018 DRYWALL COMPLETION, EXTERIOR & INTERIOR WINDOW INSTALLATION COMPLETION, FINAL PLUMBING & ELECTRICAL INSTALLATION, FINISHING WORK, FURNITURE & TECHNOLOGY INSTALLATION June July 2018 August 2018 CELEBRATION OF COMPLETION September 30, 2018 Café with new skylight
6 OCONOMOWOC HIGH SCHOOL: FAB LAB In spring, the OASD School Board approved bids for the renovation of existing classroom space to create the new Ocon Fab Lab, an engineering, robotics, and fabrication classroom and lab space. The Ocon Fab Lab project is not part of the facility referendum projects and is instead being funded by the OASD. Construction work for the Fab Lab is happening this summer so that the new space can be ready for the school year, consistent with the facility referendum projects. The new Fab Lab is located at the top of the main staircase, near the Field House. It will feature large windows where students and staff can see the innovative work happening inside. Window openings for the new Fab Lab Window openings from the Project Lead the Way Classroom into the new Fab Lab
Oconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationAuburn University Construction Project Update March 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish
More informationAuburn University Construction Project April
Small Animal Teaching Hospital Phase I: Construction Cost: $8.8 million. Phase I consists of (1) constructing an addition to the Overton-Rudd Auditorium to expand classroom and lecture hall capacity, (2)
More informationProject Status Update & Progress Report
UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationPRESENTATION JANUARY 24, 2017
4918 HOVENKAMP DRIVE DALLAS, TEXAS 75227 PRESENTATION JANUARY 24, 2017 RGM ARCHITECTS OCTOBER 25, 2016 1 2 COMMUNITY INPUT DESIGN DOCUMENT PROCUREMENT CONSTRUCTION PD SD DD CD BD CA PROJECT PROCESS 3 Construction
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationChino Valley Unified School District Monthly Construction Update
h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationLLANO ISD SCHOOL BOARD MEETING. January 2016
LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationMCER Study for Little Powder K-8
MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives
More informationFACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015
FACILITIES PROJECTS UPDATE BOARD OF EDUCATION August 11, 2015 AGENDA Measure R Bond Projects Fund 40 Capital Projects Maintenance Projects MEASURE R BOND PROJECTS KINDERGARTEN MODERNIZATIONS PROGRAM BUDGET:
More information2016 BOND INFORMATION
2016 BOND INFORMATION This publication is provided as a public service by the offices of Operations and Maintenance, Communications and Financial Services. www.svvsd.org @svvsd 395 South Pratt Parkway,
More informationAuburn University Construction Project Update June 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena achieved the Substantial Completion project milestone as of June 4 th, 2010. Punch list item work is ongoing. Work related to the project,
More informationPerimeter Site Improvements
Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff
More informationProgram Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement
Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:
More informationField House Proposal
Field House Proposal For Experienced Dependable Resourceful 5802 Akron Cleveland Rd. Hudson, OH 44236 Table Of Contents Cost Projection 3 Funding Summary 4 Site Plan 5 Field House Layout 6 Field House
More informationCoos Bay Best Bond Cost Breakdowns
Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of
More informationYardmen Arena Expansion & Renovation Project Update
For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville
More informationPhase IIA Apartment construction continues despite challenging weather.
Phase IIA Apartment construction continues despite challenging weather. THE BANKS PROJECT MONTHLY REPORT: FEBRUARY 2015 The Banks Monthly Report: February 2015 In February, Public Parties construction
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationCONSTRUCTION COST BREAKDOWN THIS IS FORM CCB
CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr
More informationBoard Report. Bond Program Update:
March 2014 Bond website: www.pcc.edu/bond Bond Program Update: Winter term is quickly coming to an end and as spring term approaches we have more buildings and areas opening for use for students and staff.
More informationBirmingham Public Schools
Birmingham Public Schools 2015 BOND ISSUE PROGRAM Project Status Update Tuesday June 5, 2018 Agenda Dashboard Update for Website Summer 2018 Construction Project Preview Summer 2018 Construction Progress
More information10 Year Plan. Facilities Planning Guide. December 15, 2014
10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016
FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements
More informationBLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS
BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS January 9, 2017 SUMMARY OF OCTOBER 17 TH PRESENTATION 1. Five-Year Capital Facilities Plans & 15-year History 2. 2016-2020
More informationAuxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.
Capital Projects Status Report October 1, 2018 Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah 84119 P 801.974.8365 F 801.974.8375 Current Projects 1. Edison construction update: In Area
More informationNew Hall High School Project Summary Report to the Board of Education June 3, 2015
New Hall High School Project Summary Report to the Board of Education June 3, 2015 Trade Procurement Status: Bid Package# Description Status Firm 1 Mass Excavation Awarded John Pohar & Sons 2 Concrete
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationBuilding & Grounds Committee Meeting Tuesday, 13 September Minutes
Building & Grounds Committee Meeting Tuesday, 13 September 2016 Minutes Present: Johnson, Laverghetta (joined at 8:00 am) and McCarthy. Also present: Kettrich, Koch, Prior, Crolius, Marsenison. Mrs. Johnson
More informationSafety Update Crossing study is in final review stages. Facilities Update Construction Progress
Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update.
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As
More informationSouthwest Health System Construction Newsletter October 7, 2017
Southwest Health System A Week in Review Patient Wing Interior sheetrock is 99% complete in the Patient Wing proper Taping and finishing is following behind sheetrock, and Nunn is preparing rooms for paint
More informationUpdate on FCPS Construction/Renovation Projects. September 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationPhotos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek
Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School
More informationNALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationInvitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:
RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:
More informationCupertino Union School District
Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK
More informationCONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.
CONSTRUCTION UPDATE JUNE THIS IS AUBURN. WOODFIELD DRIVE EXTENSION FACILITIES MANAGEMENT ARCHITECT: GOODWYN, MILLS, CAWOOD D&J ENTERPRISES $1.4 APRIL Woodfield Drive entrance from South Donahue Drive.
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationTOWN OF BELMONT, NH - TOWN CENTER FACILITIES - CONCEPTUAL PROJECT BUDGET December 20, 2018
POLICE DEPARTMENT OPTION A - Addition/Renovation to Existing Site 6,662 S.F. Interior demolition $ 12/SF $ 79,944 Foundation and structural frame $ 35/SF $ 233,170 Thermal and moisture protection $ 30/SF
More informationCONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS
CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS (August 28, 2018) PIERCE HALL IMPROVEMENTS PROJECT NO. 950511-950532 UNIVERSITY OF CALIFORNIA, RIVERSIDE PREQUALIFICATION PROCESS ALL
More informationCollins Middle School
Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0
More informationHIDDEN VALLEY ELEMENTARY SCHOOL
SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802
More informationDeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016
DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationCAPITAL PROJECTS UPDATE
JULY 15, 2004 CAPITAL PROJECTS UPDATE ISSAQUAH SCHOOL DISTRICT CAPITAL PROJECTS DEPARTMENT Director Steve Crawford Project Coordinators Mike Archer Tom Mullins Royce Nourigat Office Staff Debbie Massaro
More informationUpdate on FCPS Construction/Renovation Projects. August 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationNew Ringgold Middle School. Project Slideshow August 26, 2017
New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo
More informationSchool Assessment Report
School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School
More informationFacilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017
Facilities Maintenance & Operations Update Presidents Executive Cabinet March 6, 2017 1 Update Proposition 39 Year 4: March 6 March 31 Will complete all exterior lighting upgrades to LED Aquatic Center
More informationMONTHLY PROGRESS REPORT
MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report
More informationSubject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3
MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape
More informationJanuary 2017 Project Update
January 2017 Project Update Overall Referendum Project Status: ON SCHEDULE/ON BUDGET All elements of the project completed to date have been completed on or ahead of schedule and final costs were under
More informationLa Porte Independent School District 2014 Bond Program Status Report August 11, 2015
La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte ISD 2014 Bond Program ADMINISTRATION: Superintendent: Lloyd Graham Deputy Superintendent: Dr. Linda Wadleigh
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As
More informationShow how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality
Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationNEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING. Neidig Community Meeting July 2018
NEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING Neidig Community Meeting July 2018 PROPOSED NEIDIG ELEMENTARY SCHOOL Expanded parking Separate bus loop Gymnasium Addition 2 story classroom wing
More informationProp S Update. August 07, BIDS BEING REVIEWED o RFP #: PS Fencing at Beaumont and Gateway High Schools
August 07, 2012 Prop S Update BIDS BEING REVIEWED o RFP #: PS71-1112 Fencing at Beaumont and Gateway High Schools OUT FOR BID o RFP #: PS61-1213 IP Clock District Wide Schools 08/17/2012 o RFP #: PS75-1213
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationUpdate on FCPS Construction/Renovation Projects. August 2016
Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:
More informationSchool Assessment Report
School Assessment Report School: Carver High School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:23 AM FOR OFFICIAL USE ONLY Final School Assessment Report
More informationRepair & Replacement Study
Donald Lum Elementary School Repair & Replacement Study 23 January 2018 ALAMEDA UNIFIED SCHOOL DISTRICT 1495.05 1 PROJECT BACKGROUND Overview of Engineering Studies Miller Pacific Geotechnical Report -
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationFACILITIES Summer Projects. September 8, 2015 Board Meeting
FACILITIES 2015 Summer Projects September 8, 2015 Board Meeting On January 27, 2015 the Laguna Beach Unified School District Board of Education approved a 10-year facilities plan. The plan identified numerous
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As
More informationHartsville Area Schools - Building Evaluations
Darlington County School District Darlington, South Carolina August 8, 2012 Hartsville Area Schools - Building Evaluations School Name: West Hartsville Elementary Observed By: Cannon/Carter Principal:
More informationMCKINLEY INSTITUTE OF TECHNOLOGY BRAILSFORD & DUNLAVEY RGM AND ASSOCIATES MEASURE T BOND
MCKINLEY INSTITUTE OF TECHNOLOGY N E I G H B O R H O O D M E E T I N G A P R I L 2 4, 2 0 1 7 1 1 LPA MASTER PLAN 2 PHASE 1 SCOPE Blue Line 3 PHASE 1 SCOPE Blue Line 4 BOND T REVISED PROGRAM SCOPE 1 Modernize
More informationCrockett Elementary School Renovations
We are your future. We are EPISD. August 7, 07 August 9, 07 Existing Conditions August 9, 07 Existing Conditions SITE PLAN 7 7 7 EXISTING DROP-OFF AREA CREATES CONGESTION AND BUS DROP-OFF IS NOT DEFINED.
More informationSchool Assessment Report
School Assessment Report School: Morningside Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:29:07 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationReferendum Implementation
SPACE Net Gain (new) Classrooms Claremont = +47 Hillcrest & Elizabeth = +20 Utilization Gain SGS = +25 at 6-8 MS level SAFETY Annex Connection To Franklin Park Repair Parking Lots, Sidewalks & Outdoor
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More information2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:
MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.
More informationRR Program Summary: Complete renovation with addition and code upgrades for a historic academic building
Program Summary: Complete renovation with addition and code upgrades for a historic academic building Program Statement: Damaged in Hurricane Katrina, the circa-1929 former high school in historic Marigny
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationOwen County School District
Owen County School District Maintenance Board Report 02/20/2012 District Maintenance Projects or Requests: Working with the architects and engineers to develop a temporary support system for the main electrical
More informationManufacturing Facilities Proposal
Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationUpdate on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior
More informationSchool Assessment Report
School Assessment Report School: Morningside Elementary School Report: Dec 15, 2014 Condition Assessment: Suitability Assessment: Generated: 12/15/2014 12:11:31 PM FOR OFFICIAL USE ONLY Final School Assessment
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFacilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE
More informationImplementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood
Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Modern School Construction in the Pacific Northwest: Achieving Performance and
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior
More informationProject Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope
Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope
More informationCONSTRUCTION UPDATE. April 2017 THIS IS PROGRESS. THIS IS AUBURN.
CONSTRUCTION UPDATE April THIS IS AUBURN. RISK MANAGEMENT AND SAFETY ADMINISTRATIVE BUILDING RISK MANAGEMENT AND SAFETY SEAY SEAY & LITCHFIELD ARCHITECTS CAM BUILDERS Entrance to the Risk Management and
More informationProject Manual Index of Specifications Shenandoah Schools Concession Building
INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions
More informationRESIDENTIAL PROJECT INFORMATION
Community Development Building and Inspection Services 2100 Ridge Avenue Evanston, Illinois 60201-2798 T 847.448.4311 FAX 847.448.8020 www.cityofevanston.org RESIDENTIAL PROJECT INFORMATION The Community
More information