M50 RED COW INTERCHANGE LUAS LIGHT RAIL SYSTEM GRADE SEPARATION FEASIBILITY REPORT

Size: px
Start display at page:

Download "M50 RED COW INTERCHANGE LUAS LIGHT RAIL SYSTEM GRADE SEPARATION FEASIBILITY REPORT"

Transcription

1 M50 RED COW INTERCHANGE LUAS LIGHT RAIL SYSTEM GRADE SEPARATION FEASIBILITY REPORT PREPARED FOR: THE DEPARTMENT OF TRANSPORT KILDARE STREET DUBLIN 2. PROJECT T th AUGUST 2003 O CONNOR SUTTON CRONIN & ASSOCIATES CONSULTING CIVIL & STRUCTURAL ENGINEERS 9 PRUSSIA STREET DUBLIN 7 01)

2 O CONNOR SUTTON CRONIN & ASSOCIATES CONSULTING CIVIL & STRUCTURAL ENGINEERS REPORT ON OPTIONS FOR GRADE SEPARATION OF LUAS AT RED COW INTERCHANGE FOR DEPARTMENT OF TRANSPORT PROJECT T nd AUGUST 2003 INDEX PAGE 1. EXECUTIVE SUMMARY 1 2. INTRODUCTION 2 3. RED COW INTERCHANGE 3 4. CURRENT LUAS ALIGNMENT PROPOSALS 4 5. FUTURE ROAD PROPOSALS 5 6. LUAS ALIGNMENT GEOMETRIC CONSTRAINTS 6 7. LUAS GRADE SEPARATION OPTIONS 7 8. PREFERRED OPTION SUMMARY & RECOMMENDATIONS 11

3 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport O CONNOR SUTTON CRONIN & ASSOCIATES CONSULTING CIVIL & STRUCTURAL ENGINEERS REPORT ON OPTIONS FOR GRADE SEPARATION OF LUAS AT RED COW INTERCHANGE FOR DEPARTMENT OF TRANSPORT 1. EXECUTIVE SUMMARY PROJECT T nd AUGUST O Connor Sutton Cronin & Associates (OCSC) have been appointed by the Department of Transport (DoT) to carry out a review of the engineering feasibility of providing a grade separated crossing of the M50 Motorway and Red Cow interchange for the LUAS light rail system Line A Tallaght to Abbey Street Line. The OCSC brief is to review the present situation along with the various current infrastructural proposals for the immediate Red Cow area (LUAS at-grade, Park & Ride at-grade/grade separated access, National Roads Authority (NRA) interchange upgrade proposals) and to set out the feasibility of providing a separation between the LUAS line and the local road infrastructure. This separation may either be along the current LUAS alignment but be elevated or dropped relative to the road or alternatively, may involve a horizontal realignment away from the interchange to cross the M50 at a point removed from the roundabout where it would not interfere with traffic OCSC have consulted with a number of parties in the preparation of this report including the DoT, South Dublin County Council (SDCC), the Railway Procurement Agency (RPA), the National Roads Authority (NRA) and ARUP Consulting Engineers (ARUP). These consultations were undertaken for the following reasons: to advise the statutory bodies of the OCSC brief and to obtain all relevant background information necessary for a rigorous assessment of the issues; to better understand the means by which the present LUAS alignment was developed; to ascertain the geometric constraints to light rail alignment design; to garner all relevant information in relation to future road proposals in the area; 1.3. It is important that any proposals brought forward for LUAS alignment change take cognizance of and be compatible with the existing built environment, the current roads alignment and any future plans for road improvements in the area The report analyses the information received from the statutory bodies and considers a number of options for grade separation of the light rail system in the light of all current and known future constraints. These options are judged on engineering feasibility, effectiveness, impact on the built environment, land acquisition requirements, impact on current LUAS works and possible consequential delays to LUAS Line A opening which is currently planned for August The report concludes that the preferred grade separation option can be achieved by maintaining the bulk of the current horizontal alignment of the LUAS along the median of the R110 Regional Road (Naas Road) and elevating the vertical alignment to allow the rail line to cross the Red Cow interchange above current road levels The proposed alignment is compatible with NRA proposals for upgrading the Red Cow interchange and with the Ewbank Preece O heocha Mott McDonald proposals for a grade separated access to the LUAS depot at the south-western corner of the junction between the M50 and the N7 Naas Road. The cost of the proposed option is estimated to be in the order at 25 million. The adoption of the preferred option will mean a delay in the opening of the LUAS beyond August 2004 or alternatively an opening followed by a future closure to effect the necessary tie-in between the current and proposed alignment. Project No. T 79 1 Issue No. 1, 29 th August 2003

4 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 2. INTRODUCTION 2.1. O Connor Sutton Cronin & Associates (OCSC) have been appointed by the Department of Transport (DoT) to carry out a review of the feasibility of providing a grade separated crossing of the M50 Motorway and Red Cow interchange for the LUAS light rail system Line A Tallaght to Abbey Street Line The current alignment proposals for the light rail system ( see Section 3 following) shows the trams running along the central median of the R110 Naas Road through the Long Mile Road/Nangor Road hamburger junction, before crossing the Red Cow junction at-grade via a new M50 overbridge which has been constructed to the immediate south of the current rotary interchange layout The matter of LUAS and the Red Cow interchange has been topical for some time now and the Department of Transport is anxious to consider options to allow for a grade separation of the light rail trams from the road network local to the interchange In undertaking this review OCSC, as earlier noted have had discussions with the following statutory bodies and Consulting Engineers representatives: National Roads Authority (NRA), Mr. Tim Aherne; Railway Procurement Agency (RPA), Mr. Michael Sheedy; South Dublin County Council (SDCC), Mr. Frank Coffey; ARUP Consulting Engineers, Mr. Colin Salter The purpose of these meetings was to garner the necessary information to allow for a rigorous assessment of the issues and to consult as widely as possible in relation to previous alignment designs, design constraints and any future infrastructure proposals for the immediate area The Red Cow interchange is the junction of the M50 Motorway with the N7 National Primary Road and the R110 Regional Road. The junction is located between two exceptionally busy at-grade junctions at Newlands Cross and at the Nangor Road/Long Mile Road and is probably the busiest interchange in the country Traffic levels through the junction would be of the order of 70,000 vehicle per day with very strong tidal movements in the a.m. and p.m. peak hours. Indeed the junction tends to have extended peaks and to be congested throughout the day. The strongest movements in the a.m. peak is the left turn off the N7 inbound continuing northbound along the M50 and the straight eastbound movement along the R110, with the reverse movements being strongest in the p.m. peak There is a perception that the addition of the LUAS, as currently designed, to the currently heavily loaded junction will be the straw which breaks the camel s back and it is in this context that this review has been commissioned in order to protect the significant investment in both the light rail system and the local and national road infrastructure, and to ensure insofar as possible the most effective and efficient outcome to the benefit of all transport modes. Project No. T 79 2 Issue No. 1, 29 th August 2003

5 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 3. RED COW INTERCHANGE 3.1. The Red Cow interchange is a grade separated large diameter signalised rotary interchange located at the junction of the M50 Motorway, the N7 National Primary (Dublin Limerick) Road and the R110 Regional Road which is one of the main radial routes into the centre of Dublin see Site Location Map overleaf The interchange is as noted one of the busiest in the country with AADT 1 traffic volumes in the high tens of thousands and with a relatively high volume of heavy goods vehicles The area immediately surrounding the interchange is quite densely build out with the Fox & Geese industrial complex south east, the proposed LUAS depot and Park & Ride facility to the south west and the Clondalkin residential area to the north west see Figure 1 following In addition to the foregoing there are a number of live planning applications for further developments in the area all of which militate against the selection of alternative alignment options for either the light rail system or the local road infrastructure The NRA has already undertaken a measure of improvements to the junction. These include the construction of capacity enhancement measures to the on and off slips at the interchange. In particular new freeflow slips have been provided from the N7 northbound and from the R110 southbound onto the Motorway which allows this traffic to avoid some of the daily congestion at the interchange The eastbound off ramp from the southbound lane of the motorway onto the R110 has also been improved to allow for a further level of freeflow in the area The situation at the junction is not helped by the presence of the two at-grade junctions to the immediate east and west at Newlands Cross and at Nangor Road/Long Mile Road. The Nangor Road junction has recently been redesigned and is now a hamburger arrangement The NRA has already commissioned studies into further grade-separated and freeflow design options at a number of the M50 interchanges including the Red Cow. Early versions of these designs have been the subject of some public consultation and ongoing design work has continued in the interim The NRA has also brought forward proposals for an upgrade of the M50 to a 2*3 facility and the new West Link toll bridge has recently been opened immediately north of the M50/N4 interchange to the north of the Red Cow. These future road proposals are discussed further in Section 5 following and it is likely that some at least of the proposals will be implemented in the short to medium term. to the north east, the Ballymount Industrial complex to the 3.7. The above measures have helped the current situation but the ongoing rise in traffic levels over the 1990 s has meant that the situation continues to disimprove. This ongoing disimprovement will in all likelihood continue to be the pattern as traffic levels continue to rise at least until 2006, after which time the Dublin Transportation Office (DTO) traffic model shows a decline in traffic levels as public transport improvements take effect It is important in the context of this report, that cognizance is taken of all of these proposed road upgrades and that any options for realignment and grade-separation of the light rail system be compatible with NRA road proposals and other planned developments in the immediate area. 1 Annual Average Daily Traffic Project No. T 79 3 Issue No. 1, 29 th August 2003

6 Department of Transport PROJECT: LUAS - RED COW GRADE SEPARATION REPORT. DRAWING: SITE LOCATION MAP CLIENT: Department of Transport Kildare Street Dublin 2. Drawn By: Checked By: Designed By: Scale: P. Corrigan T. Horan N/A N.T.S. O'Connor Sutton Cronin & Associates Consulting Civil & Structural Engineers 9 Prussia Street Dublin 7 R.C.D. 023 ISSUE 1 R.C.D. 0 PROJECT NO. T 79 Ordnance Survey Ireland Licence No. EN Government of Ireland.

7

8 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 4. CURRENT LUAS DESIGN PROPOSALS 4.1. Current LUAS alignment design proposals for the area envisage outbound Luas trams crossing the R110/Nangor Road hamburger junction and travelling westbound along the central median of the R110 Naas Road as far as the Red Cow interchange The horizontal alignment consists of a straight or almost straight section along the central median followed by a series of reverse horizontal curves some quite close to design minimum standards in particular the turn adjacent the Alfa Romeo site at the R110 entry to the interchange. The vertical alignment is essentially at-grade but there is a separation of approximately a metre to the R110 close to the interchange The LUAS trams have free movement along the median as far as the Red Cow interchange but then cede priority to traffic at the interchange. They then wait until signalled before travelling across the Naas Road entry arm of the roundabout and the M50 southbound on-ramp before coming to rest on a newly provided overbridge to the immediate south of the interchange. The trams then await further signalling before crossing the northbound off-ramp of the M50 and continuing on into the Red Cow depot. The LUAS does not cross the R110 freeflow slip southbound onto the M50.The reverse procedure applies for inbound trams see Figure 2 overleaf The trams can cross the R110 entry to the interchange when signals are red both to this arm (R110 traffic heading southbound onto the M50 is unaffected by the trams) and to the N7 Naas Road inbound. During this window, the southbound on slip to the M50 is rarely used as traffic entering the interchange is coming off the M50 southbound and move predominantly eastbound to the R110 or westbound to the N As noted, the trams come to rest on the LUAS M50 overbridge before waiting to cross the northbound off slip into the new LUAS depot and Park & Ride site. This off ramp receives only 10 seconds of green time during any cycle and it is therefore relatively easy for the LUAS to cross the ramp in normal conditions The current signal cycle timings at the Red Cow vary between 60 and 70 seconds in the a.m. and p.m. peaks and it is envisaged that the trams will at worse effect the crossing within a single cycle and indeed in a shorter time in many instances. The current arrangement and phasing of signals at the interchange means that it will be possible for the LUAS trams to cross the interchange without interference to traffic and without taking signal green time from any traffic movement Traffic modelling of the junction by the DTO has shown that the LUAS trams can effect the crossing of the interchange without impact on traffic in normal conditions and in most cases will be able to effect the crossing within a single signal cycle Notwithstanding the above however it is evident that the imposition of extra movements and conflicts at the Red Cow interchange, which is currently heavily saturated and subject to frequent congestion events, has at least the potential for greater and more frequent problems. The potential is exacerbated by the fact that the interchange is not a freeflow junction but has a number of at-grade conflicts between very heavy traffic movements In particular there is the possibility that the trams may get caught up in at least some of these events and that rather than being a cause of conflict may become a victim of same. It is in this context that the DoT have requested this review to be carried out. Project No. T 79 4 Issue No. 1, 29 th August 2003

9

10 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 5. FUTURE ROAD PROPOSALS junction. The construction of the complete scheme will also involve significant local land acquisition The NRA through ARUP Consulting Engineers have prepared proposals for further grade separation of the Red Cow interchange. These proposals allow for the grade separation of a number of heavy traffic movements and will alleviate congestion at the interchange It is likely however that some measures will be implemented to facilitate the heaviest traffic movements at the junction. These would include in particular the northbound movement from the N7 onto the M50 and the westbound movement off the M50 onto the N Work on a number of design options has been ongoing for some time now and a number of different options have been developed The estimated cost for the complete scheme has been estimated at close to 100 million and it is uncertain as to whether the complete scheme will go ahead in the medium term. It is uncertain also what the overall benefits of the complete scheme would be in the context of the two atgrade junctions either side of the interchange at Newlands Cross and at the R110/Nangor Road/Long Mile Road 5.5. In addition to the above the NRA have also prepared proposals for an upgrade of the M50 to a 2*3 arrangement by the construction of a third lane in each direction in the space currently occupied by the central median. It is again uncertain as to when these proposals will be implemented but it is likely that priority would be given to that section of the motorway between the N7 and N4 interchanges The complete Red Cow grade separation scheme is shown in Figure 3 overleaf and the proposal can be seen in the context of the current LUAS alignment design at the interchange The scheme essentially involves the construction of a third tier at the interchange. The M50 mainline proper remains unaltered but the straight through movement from the N7 to the R110 is accommodated by a newly constructed overbridge across the motorway close to the east-west diameter of the current rotary The westbound movement off the M50 onto the N7 is accommodated by a third tier over the new east-west link and across the M50 close to and north of the current southern bridge of the rotary The existing southern bridge of the rotary is used in the design to accommodate westbound traffic exiting the Turnpike Road to the west of the Red Cow Hotel. The scheme is better presented graphically as shown in Figure 4 following It is likely that a reduced form of the scheme, to cater for the heaviest of movements at the junction, can be constructed with a cost in the region of million It is notable however that the design still incorporates the LUAS trams effecting some crossings atgrade. Project No. T 79 5 Issue No. 1, 29 th August 2003

11

12 RED COW LUAS GRADE SEPARATION FEASIBILITY REPORT FIGURE 4 GRAPHICAL REPRESENTATION OF PROPOSED RED COW INTERCHANGE UPGRADING BY ARUP CONSULTING ENGINEERS

13 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 6. LUAS ALIGNMENT GEOMETRIC CONSTRAINTS & VEHICLE CHARACTERISTICS In order to conceive of alternative alignment options for the light rail system it is necessary to have knowledge of the horizontal and vertical geometric alignment constraints under which the trams can safely and comfortably operate The geometric alignment constraints for the light rail system are set out in the RPA document Track Alignments Tramway Clearances Design Criteria and is based on the Alsom Citadis vehicle characteristics. A copy of this document has been provided to OCSC by the RPA At its proposed normal operating speed of 70 kilometres per hour, the light rail system requires a minimum design radius of 544 metres approximately As this horizontal radius decreases so to must the safe operating speed of the tram. The absolute minimum specified horizontal radius specified is 25 metres at which radius the trams can only travel at 15 kilometres per hour In the vertical plane the absolute minimum summit (crest) curve length is 700 metres and the absolute minimum sag curve specified is 350 metres The maximum vertical gradient at which the trams are permitted to travel is 6% In addition to the above there are particular horizontal and vertical alignment constraints at those locations where passenger stops are to be provided. In such instances the horizontal radius is limited to a minimum of 300 metres and the vertical gradient limited to 2% (rising to 4% in exceptional situations). SE 2.70 m DKE 2.40 m 6.2 m SCHEMATIC DIAGRAM OF LUAS ROLLING STOCK GUAGES 6.8. The length of a tram will be either 30 metres or 41 metres depending on the type of vehicle and the width of a tram is 2.40 metres The height of a vehicle is 3.35 metres but this is added to by the pantograph which links the tram to the overhead power transmission network The maximum loaded weight of the 30 metre and 41 metre trams is 590 and 774 kilonewtons respectively. The design specification also details the hypothesis of loads for structural design purposes In conjunction with the foregoing, cognisance needs to be taken of both the static and kinematic envelopes of the trams. The static envelope of a tram on a level straight track is 2.40 metres. The kinematic envelope of the vehicle takes account a number of dynamic elements which arise from the motion of the vehicle including lateral movement and is 2.70 metres on level straight track The swept path of two trams running side by side is as shown in the schematic diagram below. There is some widening of this envelope required with horizontal curvature but the diagram is offered as an indication of the width requirements of the system The design criteria also offers information in relation to minimum lateral clearances between the trams and other light rail infrastructure, continuous obstacles, footpaths, cycleways etc The above requirements have been borne in mind by OCSC in developing possible alternative alignment options for the light rail in the vicinity of the Red Cow interchange. Project No. T 79 6 Issue No. 1, 29 th August 2003

14 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 7. LUAS GRADE SEPARATION OPTIONS Option 2: Southwards Horizontal Displacement 7.1. OCSC have considered a number of options for grade separation of Luas at the Red Cow. There are two main options for separation as follows: a horizontal alignment displacement to the north or south of the Red Cow interchange; a vertical alignment displacement to take the light rail either under or over the interchange Horizontal Realignment Options Option 1: Northwards Horizontal Displacement 7.2. As noted earlier in the report, the area in and around the Red Cow interchange is heavily developed and the options for realignment off the R110 east of the interchange are limited A horizontal displacement of the alignment to the north side of the R110 seems impracticable from even a superficial consideration. The displacement would require the LUAS to cross the R110 to the east of the Red Cow and run along the northern edge of the Regional Road The realignment would allow for a grade separated crossing of the M50 north of the existing rotary to the south of Holly Road before crossing the N7 to the west of the interchange to enter the LUAS depot see Figure 5 overleaf There are significant drawbacks to a consideration of this alignment as follows: the alignment would bring the LUAS into conflict with a number of existing premises located on the north side of the R110 to the detriment of travel times; the alignment requires the LUAS to cross the R110 atgrade between the Nangor Road junction and the Red Cow; the alignment leaves significant elements of the current LUAS alignment redundant; this option may pose difficulties with the current layout of the LUAS depot and Park & Ride facility; the option would not be compatible with proposals for upgrading the Red Cow interchange Considering all of the foregoing this horizontal realignment is not considered to be a viable option The second horizontal realignment option is to move the LUAS to the south of the R110. However this option seems equally unattractive as Option 1 from a number of viewpoints This area is equally as developed if not more so than the north side of the R110. There are a number of significant road junctions and business accesses on this side of the road and the introduction of a tram line here would lead to significant conflicts between the light rail system and other road users These conflicts would be to the detriment of both modes of transport and be much less efficient than the current proposals In addition to the above, the south side of the R110 immediately adjacent the Red Cow interchange is much more significantly built out than the corresponding area to the south of the R110. This makes a realignment design of the LUAS particularly difficult In order to avoid the interchange and impact with the on and off ramps of the motorway it would be desirable to cross the M50 some distance south of the rotary where the down gradient of the ramps would allow the LUAS to overbridge both with sufficient vertical clearance see Figure 6 following. Project No. T 79 7 Issue No. 1, 29 th August 2003

15

16

17 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport This southwards movement of the alignment brings the LUAS into significant conflict with the built environment to the extent that land acquisition costs would be very significant This alignment would also require a significant redesign of the layout of the LUAS depot and Park & Ride facility Considering the foregoing, this realignment option is not recommended. Vertical Realignment Options Option 3: Vertical Realignment at Red Cow As an alternative to horizontal displacements of the current alignment, it would be possible to maintain the bulk of the current horizontal alignment and to vertically alter the light rail alignment in the vicinity of the Red Cow interchange There are a number of possible alternative alignment arrangements which could be provided in order to provide the requisite grade separation. Two possible alignments are shown in Figures 7 & 8 following. The designs will require the elevation of the line for approximately 200 metres east of the interchange along the R110 median in order to gain sufficient headroom at the interchange The deciding criteria between these alignments will be the degree to which they allow for the retention of existing LUAS civil works, including the depot and Park & Ride facility and the degree to which they are compatible with the NRA s proposals for further grade separation at the interchange The relative benefits of these vertical realignment options would be significant compared to the horizontal realignment options presented earlier These benefits would include, inter alia, the following: The current alignment along the R110 median could be retained with the undoubted benefits of segregation and travel time savings that it offers; There would be a minimal requirement if any for further land acquisition; There would be a minimum redundancy of LUAS civil engineering work undertaken to date; The overall cost of provision would be less than for other options particularly when land acquisition costs are taken into account; The alignment can be made compatible with current NRA proposals for an upgrade of the Red Cow road infrastructure and it may be possible to utilise the current LUAS bridge as part of that upgrade; The alignment design and construction could be fast tracked and constructed earlier than other realignment options given that land acquisition will be minimal if required There will be some disbenefits of the proposed alignment however. These will chiefly be related to further construction disruption to road traffic and possible disruption to LUAS operations It is currently expected that the LUAS Line A will be in operation and carrying passengers in August 2004 which is only 12 months away. It would be difficult to effect the necessary design, planning and construction work of a LUAS realignment within this relatively short period In this context there are then two options open to the Department of Transport and the RPA as follows: Project No. T 79 8 Issue No. 1, 29 th August 2003

18

19

20 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport Delay the opening of this line or at least that part of the line which would be affected by the realignment works until such time as the works have been completed; Open the line and then put a closure in place whilst the realignment work takes place Each of the above options is quite unpalatable but the former seems the most sensible if the design and planning of the scheme can be fast tracked. Project No. T 79 9 Issue No. 1, 29 th August 2003

21 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 8. PREFERRED OPTION 8.1. The Preferred Option for grade separation of the light rail system at the Red Cow interchange is to maintain insofar as possible the current horizontal alignment along the R110 central median and to vertically elevate the tram line in the vicinity of the interchange as noted in Figures 7 & 8 earlier The further design of these options needs to be more rigorously fleshed out with better topographical information and to be examined in the context of maximum compatibility with the already completed LUAS works and the NRA proposals for the interchange The vertical realignment option however does allow 8.4. Any at-grade horizontal alignment of the track along either side of the R110 or even further displaced away from this road, will serve only to increase the travel time of the LUAS due to tram-vehicle conflicts and will more than offset the potential time losses at the Red Cow The use of the R110 central median for the LUAS is considered to be the most efficient alignment option possible. Under this arrangement, the trams have unimpeded flow from the Nangor Road junction as far as the Red Cow roundabout without having to cede priority to or take priority from road traffic Any other alignment option will increase the number conflicts between the LUAS and road traffic to the detriment of both modes of transport It is difficult to be precise in relation to the potential cost of the recommended vertical realignment options set out above, at this early stage. However the cost is likely to be of the order of million These figures are however to be considered in the context of the overall project cost of 750 million, the projected cost of the Red Cow upgrade at 100 million and the potential for travel time savings which they carry. maximum use to be made of existing tracking, minimises or avoids the need for new land acquisition and is the most efficient in terms of tram travel times It is recommended that further work be carried out on the detailed design of the vertical realignment options set out herein in consultation with both the RPA and the NRA and that the compatibility of the preferred realignment option be analysed with respect to the requirements of each body. Project No. T Issue No. 1, 29 th August 2003

22 O Connor Sutton Cronin & Associates LUAS Red Cow Grade Separation Report Consulting Civil & Structural Engineers Department of Transport 9. SUMMARY & RECOMMENDATIONS 9.1. Current RPA proposals for the LUAS alignment at the Red Cow interchange involve at grade crossings of the R110, and the on and off ramps of the M Although traffic modelling has shown that the LUAS can, in normal circumstances, negotiate the interchange with minimal impact on traffic, given the current signalling arrangement at the junction, there is concern that this may not always be the case The authors of this report have consulted with the various interested bodies charged with both road and LUAS proposals for the area, including the NRA, the RPA and the local Roads Authority, South Dublin County Council The authors have examined the NRA proposals for further grade separation at the Red Cow and have also considered the LUAS alignment design manuals Options for a horizontal realignment of the light rail system away from the Red Cow (in order to achieve separation at the interchange) have been examined but have been dismissed on the basis that they will not lead to reduced LUAS travel time but rather to more conflict between the rail and road systems It is accepted that the current horizontal alignment for the LUAS along the central median of the R110 is the most efficient alignment possible up to the point at which it crosses the interchange at grade. separation across the Red Cow interchange, as shown in the two sample options put forward This vertical alignment is achievable within the current median width and will maintain full segregation between the light rail line and road traffic on the R It will be necessary to take up and relay a certain amount of rail track which has been laid and it may also be necessary to alter the layout of the depot and Park & Ride. However further detailed design may allow for a minimisation of impact particularly within the depot and Park & Ride If the realignment as set out in this report is to proceed, it will impact on the current proposed opening time for the LUAS or alternatively require a closure of the line following opening in order to execute the tie-in works between the current and proposed alignment There is particular concern also that rather than being the cause of further congestion at the interchange, the LUAS may become a victim of the ongoing congestion in the area given the less disciplined characteristics of road as opposed to rail vehicles and respective driver behaviours There is a significant body of civil engineering work already completed by the RPA s contractors in this area including track laying and depot/park & Ride construction. It is important in a cost context that as much as possible of this work should be maintained It is recommended that grade separation at the junction be provided by maintaining in as far as possible, the current horizontal alignment along the central median of the R110 and then elevating the alignment to provide a vertical Tony Horan Chief Civil Engineer O Connor Sutton Cronin & Associates Project No. T Issue No. 1, 29 th August 2003

Stage One Reference Design Enhancements. Date: 2 October Cabinet-in-Confidence

Stage One Reference Design Enhancements. Date: 2 October Cabinet-in-Confidence Stage One Reference Design Enhancements Date: 2 October 2013 Introduction This paper provides further information regarding the proposed enhancements to the Reference Design that have been identified since

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares

More information

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS SECTION PAGE NO. SECTION TITLE NO. EXECUTIVE SUMMARY -------------------------------------------------------------------- ES-1 1.0 INTRODUCTION

More information

Rolling Crown Construction Methods

Rolling Crown Construction Methods Rolling Crown Construction Methods CC-PAV-04009 January 2016 CC Construction & Commissioning Technical TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII)

More information

David King, Railway Procurement Agency 14 th November 2012

David King, Railway Procurement Agency 14 th November 2012 Bus Rapid Transit for Dublin Hugh Creegan, National Transport Authority David King, Railway Procurement Agency 14 th November 2012 Topics Core Dublin BRT Network System Concept BRT in the Transport System

More information

Interchange Workshop Report (August 2004)

Interchange Workshop Report (August 2004) U.S. Highway 14 Corridor Study New Ulm to North Mankato Table of Contents Section Interchange Workshop Report (August 2004) Page 1. Introduction and Next Steps 1 2. Interchange Workshop Participants &

More information

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report APPENDIX B Excerpts from the October 2002 Interstate 83 and PA Route 921 The objective for the SR 921 interchange site was to study alternatives for construction of a new interchange. There are no short-term

More information

Assessment of Compatibility of Rolling Stock and Infrastructure Gauging and Stepping Distances

Assessment of Compatibility of Rolling Stock and Infrastructure Gauging and Stepping Distances Uncontrolled When Printed Railway Group Standard Assessment of Compatibility of Rolling Stock and Infrastructure Gauging and Stepping Distances Synopsis This document mandates specific requirements and

More information

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 INTERCHANGE MODIFICATION REPORT FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310 PREPARED BY: VIRGINIA DEPARTMENT OF TRANSPORTATION STAUNTON DISTRICT DECEMBER 13, 2006

More information

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0 SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605/SR-60 EA# 3101U0 October 9, 2017 Contents 1 Purpose of ICE Memo... 1 2 Background... 1 3 Existing Interchange Deficiencies... 1 4 Context Sensitive

More information

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7 ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7 ENVIRONMENTAL IMPACT STATEMENT For ease of local identification this Environmental Impact Statement

More information

Road Safety Impact Assessment Guidelines

Road Safety Impact Assessment Guidelines Road Safety Impact Assessment Guidelines October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing and improving the

More information

Limerick Gasworks. Traffic Impact Assessment. Scoping Report. September St John's House Queen Street Manchester M2 5JB UK

Limerick Gasworks. Traffic Impact Assessment. Scoping Report. September St John's House Queen Street Manchester M2 5JB UK Limerick Gasworks Traffic Impact Assessment Scoping Report September 2010 St John's House Queen Street Manchester M2 5JB UK T 0161 8324542 F 0161 8352038 Document Control Sheet Project Title Report Title

More information

University Site: Land Between Madingley Road and Huntingdon Road (Parcel A); and

University Site: Land Between Madingley Road and Huntingdon Road (Parcel A); and Technical Note Project: North West Cambridge Transport Study To: Cambridgeshire County Council Subject: Additional Development Scenarios - University From: Atkins Date: 19/02/2009 cc: Executive Summary

More information

13. Traffic and Transport

13. Traffic and Transport 13. Traffic and Transport 13.1 Executive Summary The traffic impact of the Facility has been examined for both transport of materials and staff, and with regard to the latter, accessibility of the site

More information

Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018

Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018 Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018 Lead officer: Chris Tunstall Greater Cambridge Partnership Recommendations from the Ely to Cambridge A10 Transport Study and proposed

More information

Information supporting the traffic chapters

Information supporting the traffic chapters Annex I Metro North EIS Information supporting the traffic chapters - Baseline traffic report Information Note Project Title: MVA Project Number: Metro North EIA C8103900 Subject: Alterations to Baseline

More information

Hastings District Council. Whakatu Arterial Link Traffic Management Plan

Hastings District Council. Whakatu Arterial Link Traffic Management Plan Hastings District Council Whakatu Arterial Link Traffic Management Plan June 2014 Table of contents 1. Introduction... 2 1.1 Purpose of this report... 2 1.2 The Whakatu Arterial Link... 2 2. Traffic Management...

More information

MEMORANDUM: INITIAL CONCEPTS SUMMARY

MEMORANDUM: INITIAL CONCEPTS SUMMARY MEMORANDUM: INITIAL CONCEPTS SUMMARY INTRODUCTION This memo presents a summary of initial concepts that have been identified as development of the project study has progressed, along with a recommendations

More information

MEMORANDUM. Date: July 14, 2006 Project #: To: US 97 & US 20 Refinement Plan Steering Committee

MEMORANDUM. Date: July 14, 2006 Project #: To: US 97 & US 20 Refinement Plan Steering Committee MEMORANDUM Date: July 14, 2006 Project #: 6389 To: US 97 & US 20 Refinement Plan Steering Committee From: Sonia Hennum, P.E., Andrew Cibor, E.I.T., & Julia Kuhn, P.E. Project: US 97 & US 20 Refinement

More information

500 Interchange Design

500 Interchange Design 500 Interchange Design Table of Contents 501 Interchange Design... 5-1 July 2015 501.1 General... 5-1 501.2 Interchange Type... 5-1 501.2.1 General... 5-1 502 Interchange Design Considerations... 5-2 502.1

More information

Greater Cambridge City Deal Executive Board. A428/A1303 Better Bus Journeys Scheme Public Consultation Outcomes and Next Steps

Greater Cambridge City Deal Executive Board. A428/A1303 Better Bus Journeys Scheme Public Consultation Outcomes and Next Steps Report To: Greater Cambridge City Deal Executive Board 3 rd March 2016 Lead Officer: Graham Hughes, Executive Director of Economy, Transport and Environment, Cambridgeshire County Council A428/A1303 Better

More information

Technical Standard for the Design of Forest Entrances from Public Roads

Technical Standard for the Design of Forest Entrances from Public Roads Technical Standard for the Design of Forest Entrances from Public Roads Contents Acknowledgements... 3 1) Introduction... 4 2) Forest Entrances from National Primary and National Secondary Routes... 5

More information

Passenger service for the Dudding Hill line: brief for feasibility study

Passenger service for the Dudding Hill line: brief for feasibility study Appendix 1: Specification for a Study Passenger service for the Dudding Hill line: brief for feasibility study Introduction The West London Alliance is currently investigating ways of accommodating the

More information

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002 TRANSPORTATION INTERSTATE 87 INTERCHANGE 11A TOWN OF MALTA SARATOGA COUNTY, NY DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002 PROJECT REPORT NEW YORK STATE DEPARTMENT OF TRANSPORTATION JOSEPH

More information

DDI s Can Move More Than Cars. Alex Ariniello. Presentation for the ITE Western District Annual Meeting. July, 2016 in Albuquerque, New Mexico

DDI s Can Move More Than Cars. Alex Ariniello. Presentation for the ITE Western District Annual Meeting. July, 2016 in Albuquerque, New Mexico DDI s Can Move More Than Cars Alex Ariniello Presentation for the ITE Western District Annual Meeting July, 2016 in Albuquerque, New Mexico In January, 2016, a Diverging Diamond Interchange (DDI) opened

More information

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV Noise Technical Report 2015 Addendum NOISE TECHNICAL REPORT 2015 Addendum PREPARED FOR: Federal Highway Administration and Georgia Department of Transportation PREPARED BY: Parsons Brinckerhoff Project

More information

500 Interchange Design

500 Interchange Design 500 Interchange Design Table of Contents 501 Interchange Design... 1 501.1 General... 1 501.2 Interchange Type... 1 501.2.1 General... 1 502 Interchange Design Considerations... 2 502.1 Determination of

More information

PREFACE. The Environmental Impact Statement (EIS) for the M50 Motorway Upgrade Scheme consists of the following documents:

PREFACE. The Environmental Impact Statement (EIS) for the M50 Motorway Upgrade Scheme consists of the following documents: PREFACE The (EIS) for the M50 Motorway Upgrade Scheme consists of the following documents: Volume 1 Introduction and General Volume Volume 2 M1 Interchange to River Liffey Volume 3 River Liffey to River

More information

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project 06/2014 PROJECT STUDY REPORT (Cal Poly Pomona Senior Project) For Conceptual Approval of an Interchange Improvement And Cooperative Agreement with The City of Lake Elsinore for completion of Project Approval

More information

150Intr Transport and Strategic Regeneration Welsh Assembly Government New M4 Project Magor to Castleton WelTAG Appraisal Report Stage 1 DRAFT 3 WORKI

150Intr Transport and Strategic Regeneration Welsh Assembly Government New M4 Project Magor to Castleton WelTAG Appraisal Report Stage 1 DRAFT 3 WORKI 150Intr Transport and Strategic Regeneration Welsh Assembly Government WelTAG Appraisal Report Stage 1 DRAFT 3 WORKING DOCUMENT 1 Transport and Strategic Regeneration Welsh Assembly Government WelTAG Appraisal

More information

The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening;

The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening; 5 TRAFFIC AND TRANSPORT 5.1 SUMMARY OF RESIDUAL IMPACTS The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening; be outside of the

More information

9.0 I-26 & I-526 Interchange Improvements

9.0 I-26 & I-526 Interchange Improvements 9.0 I-26 & I-526 Interchange Improvements The I-26 & I-526 System-to-System interchange currently consists of a combination of directional and loop ramps providing for all movements from one Interstate

More information

SOUTH MEDFORD INTERCHANGE BRIDGES

SOUTH MEDFORD INTERCHANGE BRIDGES Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is

More information

Police Observation Platforms on Motorways

Police Observation Platforms on Motorways Police Observation Platforms on Motorways DN-GEO-03027 December 2002 DN Design Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible

More information

Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830

Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 Functional Planning Study :06 December 2016 E00311A Executive Summary Strathcona County, as requirement of the roadside development permit from Alberta Transportation for the intersection upgrade of

More information

Word Count 2832 (including abstract), No of Figures 13, No of tables -1, Equivalent Count of word Submission Date

Word Count 2832 (including abstract), No of Figures 13, No of tables -1, Equivalent Count of word Submission Date TITLE: DESIGN OF MULTI-LEVEL INTERCHANGE AT SEWRI, MUMBAI, INDIA Description Details Word Count 2832 (including abstract), No of Figures 13, No of tables -1, Equivalent Count of word - 6334 Submission

More information

Proposed Petone to Grenada Link Road Options

Proposed Petone to Grenada Link Road Options Report 15.41 Date 2 March 2015 File TP/03/29/02 Committee Author Regional Transport Committee Chris Upton, Chair Chief Executives Forum Proposed Petone to Grenada Link Road Options 1. Purpose This report

More information

Road Transport Upgrade through Kapiti. Transportation Review for Kapiti Coast District Council

Road Transport Upgrade through Kapiti. Transportation Review for Kapiti Coast District Council Transportation Review for Kapiti Coast District Council September 2009 Project: Title: Document Reference: Prepared by: Reviewed by: Revisions: Road Transport Upgrade through Kapiti Transportation Review

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

DRAFT Operational Traffic Management Plan

DRAFT Operational Traffic Management Plan A Development Consent Order Application by Ashfield Land Management Limited and Gazeley GLP Northampton s.à.r.l. In respect of February 2018 DOCUMENT SIGNATURE AND REVIEW SHEET Project Details Project

More information

A Rail Freight Interchange for Spalding

A Rail Freight Interchange for Spalding A Rail Freight Interchange for Spalding Consultation by South Holland District Council on a proposed development site option for a Rail Freight Interchange facility March 2010 About the proposals Introduction

More information

N4 Collooney to Castlebaldwin Road Scheme

N4 Collooney to Castlebaldwin Road Scheme Traffic Analysis Brief of Evidence N4 Collooney to Castlebaldwin Road Scheme Presented by: Declan Keenan and Shane Dunny of AECOM Designer AECOM Lower Ground Floor Grand Canal House Upper Grand Canal Street

More information

Placerville, a Unique Historical Past Forging into a Golden Future

Placerville, a Unique Historical Past Forging into a Golden Future Placerville, a Unique Historical Past Forging into a Golden Future City Manager s Report June 24, 2014 City Council Meeting Prepared by: Nathan Stong, City Engineer Item #: Subject: Adopt a Resolution:

More information

campaigning by the Railway Development Society Limited

campaigning by the Railway Development Society Limited campaigning by the Railway Development Society Limited Department for Transport A14 Challenge Team Roads Policy Great Minster House, 33 Horseferry Road, London SW1P 4DR Please Reply to: 24 Bure Close St.

More information

Active Traffic Management in Michigan. Patrick Johnson, P.E. HNTB Michigan Inc.

Active Traffic Management in Michigan. Patrick Johnson, P.E. HNTB Michigan Inc. Active Traffic Management in Michigan Patrick Johnson, P.E. HNTB Michigan Inc. Active Traffic Management (ATM) Active Traffic Management Strategies: Dynamic Lane Use Dynamic Shoulder Use Queue Warning

More information

10.0 AIR QUALITY AND CLIMATIC FACTORS

10.0 AIR QUALITY AND CLIMATIC FACTORS .0 AIR QUALITY AND CLIMATIC FACTORS.1 ASSESSMENT METHODOLOGY.1.1 General Section 39 (2) (b) (ii) of the Transport (Railway Infrastructure) Act 2001, requires that proposed developments are examined in

More information

IMPLEMENTATION GUIDELINE NO. 23

IMPLEMENTATION GUIDELINE NO. 23 IMPLEMENTATION GUIDELINE NO. 23 Refuse Arrangements and Management for Multiple Residential Development Date of Resolution These guidelines were adopted by Council on the 22 February 2011 and takes effect

More information

N40 Demand Management Study

N40 Demand Management Study N40 Demand Management Study Final Report June 2017 [BLANK] N40 Demand Management Study Final Report May 2017 [BLANK] Table of Contents Executive Summary... 1 1.0 Introduction... 4 1.1 Background... 4 1.2

More information

Land at Penny Pot Lane, Killinghall

Land at Penny Pot Lane, Killinghall NORTH YORKSHIRE COUNTY COUNCIL BUSINESS and ENVIRONMENTAL SERVICES LOCAL HIGHWAY AUTHORITY Proposed Development: Location: Applicant: Outline Application for erection of 600 dwellings, primary school,

More information

Appendix F: Noise Report

Appendix F: Noise Report Appendix F: Noise Report HIGHWAY 404 HIGHWAY 407 TO GREEN LANE (W.O. 03-20024) REGIONAL MUNICIPALITY OF YORK NOISE REPORT Preliminary Design and Class Environmental Assessment Study Class Environmental

More information

CE 452 Traffic Impact Assessment

CE 452 Traffic Impact Assessment CE 452 Traffic Impact Assessment 1 Why Required? New developments Produce/ attract new traffic Production: Residences Attraction: Shops, Offices, Schools, Hospitals etc. etc. Changes in traffic pattern

More information

INTERIM ADVICE NOTE 121/09. Advice Regarding the Application of Integrated Traffic Management

INTERIM ADVICE NOTE 121/09. Advice Regarding the Application of Integrated Traffic Management INTERIM ADVICE NOTE 121/09 Advice Regarding the Application of Integrated Traffic Management Summary This document provides advice on identifying motorway junctions which may be suitable for the application

More information

WestConnex Stage 3 EIS (M4/M5 Link) Submission by Alexandria Residents Action Group (ARAG)

WestConnex Stage 3 EIS (M4/M5 Link) Submission by Alexandria Residents Action Group (ARAG) WestConnex Stage 3 EIS (M4/M5 Link) Submission by Alexandria Residents Action Group (ARAG) Summary ARAG strongly objects to the WestConnex M4-M5 Link for the following reasons: There is a lack of strategic

More information

Hinksey Flood Alleviation Scheme Sink or Swim

Hinksey Flood Alleviation Scheme Sink or Swim Hinksey Flood Alleviation Scheme Sink or Swim Hinksey Flood Alleviation Scheme Sink or Swim; Enhancing asset resilience a case study in tackling flooding on the railway Presented by: Paul Armitage, Project

More information

Illawarra Business Chamber/Illawarra First. Submission on NSW Draft Freight and Ports Plan

Illawarra Business Chamber/Illawarra First. Submission on NSW Draft Freight and Ports Plan Illawarra Business Chamber/Illawarra First Submission on NSW Draft Freight and Ports Plan Illawarra Business Chamber A division of the NSW Business Chamber Level 1, 87-89 Market Street WOLLONGONG NSW 2500

More information

1. Introduction. 1.1 Project Background. ANTONY JOHNSTONE Transport Associate Aurecon

1. Introduction. 1.1 Project Background. ANTONY JOHNSTONE Transport Associate Aurecon ANTONY JOHNSTONE Transport Associate Aurecon Antony.johnstone@aurecongroup.com RAFAEL CARVAJAL Operational Modelling and Visualisation Coordinator Main Roads WA Rafael.CARVAJALCIFUENTES@mainroads.wa.gov.au

More information

Requirements for the Weekly Operating Notice, Periodical Operating Notice and Sectional Appendix

Requirements for the Weekly Operating Notice, Periodical Operating Notice and Sectional Appendix Requirements for the Weekly Operating Notice, Periodical Operating Notice and Synopsis This document mandates requirements for the production of information related to engineering work, alterations to

More information

DEVELOPMENT, ANALYSIS, AND DESIGN OF A NEW PARKWAY AT GRADE INTERSECTION (PAGI)

DEVELOPMENT, ANALYSIS, AND DESIGN OF A NEW PARKWAY AT GRADE INTERSECTION (PAGI) 2013 ITE Western District Annual Meeting COCEPT DEVELOPMET, AALYSIS, AD DESIG OF A EW PARKWAY AT GRADE ITERSECTIO (PAGI) Lead Author: James M. Witkowski, PhD Supporting Author: Darrell Truitt, PE The Pima

More information

Consideration of a Diverging Diamond Interchange in Saskatchewan. Paul H. A. Steel, Project Manager, M. Eng., P.Eng., Tetra Tech EBA Inc.

Consideration of a Diverging Diamond Interchange in Saskatchewan. Paul H. A. Steel, Project Manager, M. Eng., P.Eng., Tetra Tech EBA Inc. Consideration of a Diverging Diamond Interchange in Saskatchewan Paul H. A. Steel, Project Manager, M. Eng., P.Eng., Tetra Tech EBA Inc. Terry Schmidt, P.Eng., MBA, Senior Project Director, Tetra Tech

More information

CLA /10.54, PID Project Description:

CLA /10.54, PID Project Description: Project Description: The proposed project will consist of widening IR 70 to three lanes from Enon Road (SLM 06.75) to the US 68 interchange ramps (SLM 10.55). IR 70 is a component of the Strategic Highway

More information

The London to Fishguard Trunk Road (East of Magor to Castleton) Order 201-

The London to Fishguard Trunk Road (East of Magor to Castleton) Order 201- Proof of Evidence Construction Adran yr Economi a r Seilwaith Department for Economy and Infrastructure The M4 Motorway (Junction 23 (East of Magor) to West of Junction 29 (Castleton) and Connecting Roads)

More information

University Region FY 2023 Final Scoping Package

University Region FY 2023 Final Scoping Package September 30, 2016 University Region FY 2023 Final Scoping Package I-496/US-127 Scoping From I-96 to the I-496/US- 127 Interchange CS 33045 JN 126442 I-496/US-127 STUDY EXECUTIVE SUMMARY UNIVERSITY REGION

More information

CONTROL AND COMMUNICATIONS DEVICES AND SYSTEMS PART 1 TD 73/16 EMERGENCY ROADSIDE TELEPHONES (ERT) SUMMARY

CONTROL AND COMMUNICATIONS DEVICES AND SYSTEMS PART 1 TD 73/16 EMERGENCY ROADSIDE TELEPHONES (ERT) SUMMARY DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 9 SECTION 2 NETWORK - TRAFFIC CONTROL AND COMMUNICATIONS TRAFFIC TECHNOLOGY DEVICES AND SYSTEMS PART 1 TD 73/16 EMERGENCY ROADSIDE TELEPHONES (ERT) SUMMARY This

More information

US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison

US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison T E C H N I C A L M E M O R A N D U M US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison PREPARED FOR: Mn/DOT District 7 PREPARED BY: CH2M HILL DATE: March 27, 2007 This technical

More information

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement 2 Purpose and Need 2.1 Study Area Interstate 81 (I-81) is relied upon for local and regional travel and interstate travel in the eastern United States. It extends 855 miles from Tennessee to New York at

More information

Patrick Prescott, Community Development Director By: David L. Kriske, Assistant Community Development Director

Patrick Prescott, Community Development Director By: David L. Kriske, Assistant Community Development Director DATE: April 26, 2016 TO: FROM: Ron Davis, Interim City Manager Patrick Prescott, Community Development Director By: David L. Kriske, Assistant Community Development Director SUBJECT: Modification of two

More information

BRT Investigations Summary Report

BRT Investigations Summary Report Ngauranga to Airport / Let's Get Welly Moving BRT Investigations Summary Report Ngauranga to Airport / Let's Get Welly Moving BRT Investigations Summary Report Prepared By Sam Thornton Senior Transportation

More information

A three-stage process was implemented in order to develop and evaluate the project concepts and provide recommendations for the project.

A three-stage process was implemented in order to develop and evaluate the project concepts and provide recommendations for the project. MEMORANDUM TO: FROM: Highway 36/Rice Street PMT Mark Benson DATE: March 23, 2009 RE: Selection of a Preferred Alternative SEH No. 105803 The purpose of this memorandum is to document the process for selecting

More information

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane.

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane. 17. SERVICES 17.1 Introduction 17.1.1 WSP Development Limited has been appointed by CALA Homes to investigate and appraise the availability of services to serve a proposed mix-use development of approximately

More information

Design Report N60 BALLA TO CLAREMORRIS ROAD PROJECT AT HEATHLAWN

Design Report N60 BALLA TO CLAREMORRIS ROAD PROJECT AT HEATHLAWN COMHAIRLE CONTAE MHAIGH EO N60 BALLA TO CLAREMORRIS ROAD PROJECT AT HEATHLAWN Improvements to the N60 road in the townlands of Pollavaddy, Garhawnagh, Carrowgarve, Rathduff, Knocknamoghalaun, Heathlawn,

More information

Informational Brochure. Proposed Interchange. Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island

Informational Brochure. Proposed Interchange. Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island Informational Brochure Proposed Interchange OF Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island October 5, 2016 Department of Transportation Two Capitol

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM NY Susquehanna and Western Rail Line Bicycle/Pedestrian Path DBNUM: NS9803 / UPC: 058018 The 4.8 mile New York, Susquehanna, and Western Railway (NYS&W)

More information

SOUTH DUBLIN COUNTY COUNCIL Traffic Management Centre Roads (Traffic and Transportation) Department

SOUTH DUBLIN COUNTY COUNCIL Traffic Management Centre Roads (Traffic and Transportation) Department SOUTH DUBLIN COUNTY COUNCIL Roads (Traffic and Transportation) Department TECHNICAL SPECIFICATION 5 SDCC-TS-05 DESIGN AND INSTALLATION PROCEDURES REQUIREMENTS FOR THE DESIGN AND INSTALLATION OF TRAFFIC

More information

6.0 CONGESTION HOT SPOT PROBLEM AND IMPROVEMENT TRAVEL DEMAND MODEL ANALYSIS

6.0 CONGESTION HOT SPOT PROBLEM AND IMPROVEMENT TRAVEL DEMAND MODEL ANALYSIS 6.0 CONGESTION HOT SPOT PROBLEM AND IMPROVEMENT TRAVEL DEMAND MODEL ANALYSIS 6.1 MODEL RUN SUMMARY NOTEBOOK The Model Run Summary Notebook (under separate cover) provides documentation of the multiple

More information

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting

More information

Macroscopic and Microscopic Simulation for the Evaluation of People Mover Systems. Dr.-Ing. Peter Mott Sven Beller PTV AG, Karlsruhe, Germany

Macroscopic and Microscopic Simulation for the Evaluation of People Mover Systems. Dr.-Ing. Peter Mott Sven Beller PTV AG, Karlsruhe, Germany Macroscopic and Microscopic Simulation for the Evaluation of People Mover Systems Dr.-Ing. Peter Mott Sven Beller PTV AG, Karlsruhe, Germany 1. Introduction This paper is intended to show how a comprehensive

More information

Safety Review. Proposed Revised Loading Arrangements at St. Michan's Street, Dublin 1

Safety Review. Proposed Revised Loading Arrangements at St. Michan's Street, Dublin 1 PMCE Independent Specialists Engineering Solutions of Proposed Revised Loading Arrangements at St. Michan's Street, Dublin 1 On Behalf of: Dublin City Council September 2014 of Proposed Revised Loading

More information

I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge

I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge Client: AJR or IJR? This is a TO-MAY-TO This is a TO-MAH-TO Practical Design PRACTICAL

More information

Traffic Impact Study Requirements

Traffic Impact Study Requirements [TYPE THE COMPANY NAME] Traffic Impact Study Requirements County of San Mateo Department of Public Works Roadway Services 9/1/2013 I. Introduction The County of San Mateo (County), Department of Public

More information

OFFICIAL COMMUNITY PLAN. PART B.9 Fleet Street Business Park Secondary Plan

OFFICIAL COMMUNITY PLAN. PART B.9 Fleet Street Business Park Secondary Plan OFFICIAL COMMUNITY PLAN PART B.9 Fleet Street Business Park Secondary Plan 1. INTRODUCTION 1.1. Background This secondary plan provides policy direction for the development of a new industrial park in

More information

CHAPTER 8: I-71 ACCESS IMPROVEMNETS

CHAPTER 8: I-71 ACCESS IMPROVEMNETS CHAPTER 8: I-71 ACCESS IMPROVEMNETS I-71 Access Improvements were a separate and distinct part of the overall Uptown Transportation Study. This Part B work is fully documented in the Planning Study Report

More information

Appendix B Highway 407 Interchange Review - Cochrane Street Area

Appendix B Highway 407 Interchange Review - Cochrane Street Area Appendix B Highway 407 Interchange Review - Cochrane Street Area AECOM 300 ater Street hitby, ON, Canada L1N 9J2 www.aecom.com Memorandum To Michael May, P.Eng., Town of hitby Page 1 CC Subject Greg Hardy,

More information

Community Advisory Committee Meeting No. 2. June 22, 2006

Community Advisory Committee Meeting No. 2. June 22, 2006 Community Advisory Committee Meeting No. 2 June 22, 2006 Introductions The Study Team KDOT Wichita Partners Consultants CAC members Overview Today s Agenda Opinion Survey Study Status Starting Concept

More information

Chapter 6 Freight Plan

Chapter 6 Freight Plan Chapter 6 Freight Plan Overview This chapter presents a review and assessment of needs, deficiencies, policies and improvement options affecting the freight transportation system within the Medford Urban

More information

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH DRD ROADS SERVICE, SOUTHERN DIVISION Environmental Statement, Volume 1 November 2005 Non Technical Summary i Introduction The Department for Regional

More information

VII. FREIGHT MANAGEMENT

VII. FREIGHT MANAGEMENT VII. FREIGHT MANAGEMENT The regional transportation network must not only move people safely and efficiently, but must also facilitate the safe and efficient transportation of goods as well. Local freight

More information

DIVISION 9 TRAM TECHNICAL

DIVISION 9 TRAM TECHNICAL Revision 0 Specification: Division 9 DIVISION 9 TRAM TECHNICAL Contents: Part 910 Tramway Provisions Part 920 Tram Track Part 930 Overhead Catenary Part 940 Tram Platforms DTEI XXCxxx Page 1 PART 910 TRAMWAY

More information

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION HIGH SPEED TWO INFORMATION PAPER E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION This paper outlines the framework for the control and management of traffic associated with the construction of the Proposed

More information

PARAPET STANDARD & SPECIFICATION UPDATES

PARAPET STANDARD & SPECIFICATION UPDATES PARAPET STANDARD & SPECIFICATION UPDATES Richard Bowen Engineering Inspector National Roads Authority National Roads Authority Standards Section Training for New Developments April 2013 Context Presentation

More information

Code of Engineering Practice for Works on, Near or Adjacent to the Luas Light Rail System

Code of Engineering Practice for Works on, Near or Adjacent to the Luas Light Rail System Railway Procurement Agency Page 1 of 21 Code of Engineering Practice for Works on, Near or Adjacent to the Luas Light Rail System Railway Procurement Agency Page 2 of 21 Table of Contents Clause Page No

More information

St. Francis Drive through the City of Santa Fe Corridor Study

St. Francis Drive through the City of Santa Fe Corridor Study VIII. ENGINEERING AND ENVIRONMENTAL EVALUATION INTERSECTION IMPROVEMENTS SOUTHERN For the southern end of the corridor, traffic volumes are expected to increase over existing levels. The Phase A Report

More information

LANDSIDE FACILITIES AIRLINE TERMINAL FACILITIES INVENTORY 5.0 INTRODUCTION C H A P T E R 1 CHAPTER 5

LANDSIDE FACILITIES AIRLINE TERMINAL FACILITIES INVENTORY 5.0 INTRODUCTION C H A P T E R 1 CHAPTER 5 C H A P T E R 1 INVENTORY AIRLINE TERMINAL FACILITIES INVENTORY CHAPTER 5 LANDSIDE FACILITIES 5.0 INTRODUCTION This chapter focuses on the landside circulation and access system at the Spokane International

More information

Essex Junction Highway-Rail Grade Crossing Study

Essex Junction Highway-Rail Grade Crossing Study Communities working together to meet Chittenden County s transportation needs CHITTENDEN COUNTY METROPOLITAN PLANNING ORGANIZATION Essex Junction Highway-Rail Grade Crossing Study October 18, 2000 CCMPO

More information

FINAL PROJECT PRIORITIZATION PLAN FOR THE NM 599 CORRIDOR

FINAL PROJECT PRIORITIZATION PLAN FOR THE NM 599 CORRIDOR FINAL PROJECT PRIORITIZATION PLAN FOR THE NM 599 CORRIDOR PROJECT NO. WIP-599-1(102) CONTROL NO. D5SF2 APRIL 2010 Prepared for: New Mexico Department of Transportation Northern Design Bureau P.O. Box 1149

More information

REPORT Condition D19 Permanent Noise Barriers

REPORT Condition D19 Permanent Noise Barriers REPORT Condition D19 Permanent Noise Barriers Project Name: WestConnex New M5 Project number: 15.7020.2597 Revision date: 19/08/2016 Revision: 1 Document Approval Rev. Prepared by Reviewed by Recommended

More information

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE Paul Gauvreau University of Toronto, Canada (formerly J. Muller International) Thomas E. Kelly, Jr. Earth Tech/J.

More information

BARNSLEY METROPOLITAN BOROUGH COUNCIL

BARNSLEY METROPOLITAN BOROUGH COUNCIL BARNSLEY METROPOLITAN BOROUGH COUNCIL This matter is a Key Decision within the Council s definition and has been included in the relevant Forward Plan REPORT OF THE EXECUTIVE DIRECTOR PLACE A628 Dodworth

More information

VIII. LAND USE ISSUES

VIII. LAND USE ISSUES VIII. LAND USE ISSUES The & Route 57 Land Use and Circulation Study (Land Use Study, Figure 6) was completed for the Town of Clay in November 1999 (Clough, Harbour & Associates). This study investigated

More information