Hinksey Flood Alleviation Scheme Sink or Swim

Size: px
Start display at page:

Download "Hinksey Flood Alleviation Scheme Sink or Swim"

Transcription

1 Hinksey Flood Alleviation Scheme Sink or Swim Hinksey Flood Alleviation Scheme Sink or Swim; Enhancing asset resilience a case study in tackling flooding on the railway Presented by: Paul Armitage, Project Manager Network Rail November November

2 Agenda 1. Hinksey geography 2. The problem of flooding and the impact on the railway 3. The reason to improve flood resilience 4. Option selection using flood modelling 5. The Hinksey flood alleviation scheme scope of works 6. Planning the possession 7. The 16 day blockade

3 Introduction Hinksey Flood Alleviation Scheme Sink or Swim 3

4 Geography Area of consideration To Didcot Parkway and London 4

5 The Network 1. Key strategic passenger and freight line from Didcot to north 2. Used by 7.5m passengers annually 3. Freight line supports high value automotive traffic for export 4. 2 track railway, signal controlled with track circuits, 90mph line speed 5

6 The problem The whole area floods 6

7 The whole area floods all the time Telegraph 11 times in the last 14 years 7

8 The business case Train delays in the area are roughly 400 per minute. In the last 3 years Hinksey has flooded causing in excess of 16 Million per year Politically VERY sensitive This job was a top 10 urgent requirement from David Cameron Network Rail was funded to deal with flooding at 10 key sites in the Western region. Hinksey is number 1 So what did we do 8

9 Hinksey Flood Alleviation Scheme Project Aim: 1. To increase the resilience of the railway in the Hinksey area to flood events 2. Works shall minimise the impact on the flood risk to third party properties and businesses 3. Implement the works as soon as possible The Telegraph

10 Area of consideration Residential Residential A34 NSC Depot & Sidings Fowles Bridge Abingdon Road Bridge Cold Harbour Campsite Dairy Depot Strouds Bridge Southern By Pass (A423) Residential

11 Network of watercourses Hinksey Lake Hinksey Stream Hinksey Brook Redbridge Stream Weirs Mill Stream River Thames Hinksey Ditch Abingdon Road Bridge Hinksey Drain

12 Why does the railway corridor flood at Hinksey? Hinksey Drain Indicative Cross-Section Looking Towards Oxford Hinksey Stream Oxford Abingdon Road Overbridge South-West By- Pass Overbridge Fowles Underbridge Indicative Longitudinal Track Profile Stroud s Underbridge Peak Flood Level

13 Typical flooding extents

14 Project options March 2008 Feasibility Report: Looked at various flood mitigating measures including: Do nothing Sheet piling along the embankment Raise the track levels above the flood line Widen and enlarge existing culverts Holding reservoir High capacity pumping Report concluded that the preferred solution was to raise the existing track levels

15 Preferred solution Oxford Abingdon Road Overbridge South-West By- Pass Overbridge Fowles Underbridge 400mm MIN Stroud s Underbridge Peak Flood Level Indicative Longitudinal Track Profile

16 Impact of the proposed solution A significant track lift required to raise the existing tracks above peak flood levels - Effectively building a dam across an existing flood plain The existing flood plain will be reduced on one side - how will this affect lineside neighbours? - There is a need to understand the flood dynamics both prior to and after the implementation of the proposed design

17 Flood modelling stages Stage 1- Form Baseline Flood Model Review and validate EA Oxford Flood Risk Mapping Models Stage 2- Design and model the Raised Track Understand the effects of raising the railway track to the existing flood plain Stage 3- Identify and Assess Flood Mitigation Measures Assess various flood mitigation measures to offset any increase in flood envelope or depth Define the Scope of the Overall Project

18 Stage 1 - Baseline model Hydrology embedded in the Environment Agency model (January 2014) included the following return periods: 5yr 20yr 75yr 100yr 100 plus Climate Change (20%) 1000yr

19 Stage 2 flood model conclusions Results of modelling stage 2 show: The proposed track lifting scheme is effective and will improve the flood resilience of the main lines (but the lines will still flood during the more severe flood events greater than a 1 in 20 storm) What does this mean? In terms of the past 11 flood events the proposed track lifting would have kept the rail corridor open on eight occasions The duration of the line closure for the remaining three events would have been significantly less, as the peak water flows would recede below the rail levels much quicker Is this a satisfactory solution?

20 Flood depth differences existing vs raised track (1 in 5 Fluvial Event)

21 Flood depth differences existing vs raised (1 in 20 Fluvial Event)

22 Flood depth differences existing vs raised (1 in 100 plus climate change)

23 Flood modelling stage 3 mitigation measures Basic Requirement: Need to increase the conveyance of water through the railway corridor Problem: The volume of water to be conveyed varies considerably for each fluvial event Options: Single Culvert Multiple Culverts in different locations Open up Abingdon Road bridge and the divert water southwards

24 Culvert positioning Abingdon Road ridge

25 Final culvert design Twin-box culvert. Each box 3.6m wide by 1.8m deep. Overall length 82m Steel Orifice plate fitted to inlet to be removed when the WCC implemented and operational

26 Development of the culvert design New Issues: The proposed works now extend outside the railway corridor and as such would be subject to Planning Consent The proposed site is located within a Flood Zone 3 as defined by the National Planning Policy Framework and Strategic Flood Risk Assessment. As such no increase in flood risk would be permitted A number of scenarios were run with varying widths, depths and invert levels to ascertain the optimum design across all fluvial events No solution produced a zero impact in regards to increasing flood levels in the surrounding area The flood modelling confirmed an optimum solution of a twin-box culvert, each unit being 2.1m wide by 1.5m deep (internal dimensions)

27 Strouds underline bridge main line decks Main Line Bridge Decks Effect of proposed track lift

28 Strouds underline bridge down goods deck Bridge Span under Down Goods Line

29 Strouds underline bridge scope Redundant freight deck replaced Goods loop deck renewed and raised Main line decks refurbished and raised

30 Raised track design Constraints to Track Lifting: Need to raise the track above the peak water levels BUT provide provision for future OLE Clearances to Abingdon Road Bridge Location of S&C Junction and connection to NSC Depot Location of Stroud s Bridge Track formation considerations and construction time

31 Summary of the flood mitigating measures Track lift of 430mm beneath Abingdon Road, tapering out to 250mm at Strouds bridge, including ballast retention and significant track formation works Renewal of 9 S&C units Install a 82m long twinbox culvert to the north of Abingdon Road Replace down goods line bridge deck at Strouds Lift main line bridge decks at Strouds Replace existing redundant span at Strouds bridge with a combined foot and cable crossing structure Raise all signalling and E&P lineside assets onto platforms above flood level Just a simple track lifting scheme!

32 Planning the blockade Agreement was made with TOCs and FOCs to complete works in a blockade. TOCs preferred a period of continuous disruption and the complexity of works lent to a complete rail closure 16 day blockade from Saturday 29 th July to Monday 15 th August 2016 Shared possession with other key projects in the area 32

33 Planning the blockade To aid with compliance of the CDM regulations we made sure principle contractor roles and responsibilities were clearly defined for the two main principle contractors for track and civils works Multiple stakeholders involved with and influenced by Hinksey Travelling public Lineside neighbours Commercial neighbours Manage risks weather (high winds and rain) 33

34 Construction during the blockade Manpower 2 x 12 hour shifts. Over 100 people working at any time Different plant in use requiring careful planning and on site coordination 34

35 Specialist plant utilised PEM LEMs Tamper Kirow crane Crawler crane 35

36 Informing the public 36

37 Achieved within blockade 9 S&C units replaced; 200metres of plain line renewed; thousands of tonnes of ballast dropped; 44 culvert units installed; 2 main line bridge decks removed, refurbished and reinstalled; 1 new foot bridge installed; S&T modifications and reinstalled 37

38 Culvert 38

39 Culvert 39

40 Culvert 40

41 New S&T raised platform 41

42 Country end of renewal 42

43 London end of renewal 43

44 16 days in 220 seconds (This video is hosted in the the PWI Technical Hub) 44

TfL Managing Adaptation to Climate Change

TfL Managing Adaptation to Climate Change TfL Managing Adaptation to Climate Change 14 September 2010 Matthew Webb, Climate Change Strategy Manager TfL Group Sustainability Unit Transport for London London Underground 3m trips per day Traffic

More information

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection

More information

Climate change adaptation and rail. Dr Kate Avery Sustainability Specialist (Climate Change Adaptation) 23 rd January 2013

Climate change adaptation and rail. Dr Kate Avery Sustainability Specialist (Climate Change Adaptation) 23 rd January 2013 Climate change adaptation and rail Dr Kate Avery Sustainability Specialist (Climate Change Adaptation) 23 rd January 2013 1 Contents The challenge Our approach Opportunities and hurdles The Challenge Asset

More information

Hastings District Council. Whakatu Arterial Link Traffic Management Plan

Hastings District Council. Whakatu Arterial Link Traffic Management Plan Hastings District Council Whakatu Arterial Link Traffic Management Plan June 2014 Table of contents 1. Introduction... 2 1.1 Purpose of this report... 2 1.2 The Whakatu Arterial Link... 2 2. Traffic Management...

More information

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows: UNION PACIFIC RAILROAD SCOPE OF HYDROLOGIC/HYDRAULIC DESIGN ENGINEERING AND PERMITTING SERVICES FOR SIZING WATERWAY OPENINGS AT NEW AND REPLACEMENT STRICTURES These flood passage criteria were developed

More information

MEMORANDUM OF UNDERSTANDING THE FLOW OF THE RIVER THROUGH CIRENCESTER

MEMORANDUM OF UNDERSTANDING THE FLOW OF THE RIVER THROUGH CIRENCESTER 1. Introduction MEMORANDUM OF UNDERSTANDING THE FLOW OF THE RIVER THROUGH CIRENCESTER 1.1 The control and distribution of fluvial flow through Cirencester is manually controlled by the operation of sluice

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 INFRASTRUCTURE

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 INFRASTRUCTURE 33 INFRASTRUCTURE Automated maintenance is quicker, safer and more cost-effective Well-targeted maintenance enables more train paths to be available at night Advanced suspension system minimises noise

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer Place holder image thameswater.co.uk/developerservices Building over or close to a public sewer Did you know Thames Water is legally responsible for more than 100,000

More information

The changing face of London and Southeast Railway Architecture. Tony Ramanathan Systems Design Engineer Network Rail

The changing face of London and Southeast Railway Architecture. Tony Ramanathan Systems Design Engineer Network Rail The changing face of London and Southeast Railway Architecture Tony Ramanathan Systems Design Engineer Network Rail 1 Agenda What are the drivers Network Rail mandate Network Rail Project Governance (GRIP)

More information

Unique ID: (from PFRA database) Location: Clonfert, Co. Galway. Stage 1: Desktop Review

Unique ID: (from PFRA database) Location: Clonfert, Co. Galway. Stage 1: Desktop Review Location: Clonfert, Co. Galway Unique ID: 252906 (from PFRA database) Initial OPW Designation APSR AFRR IRR Co-ordinates Easting: 197134 Northing: 221731 River / Catchment / Sub-catchment Un-named minor

More information

PRINCESS ANNE DISTRICT STORMWATER PROJECTS

PRINCESS ANNE DISTRICT STORMWATER PROJECTS PRINCESS ANNE DISTRICT STORMWATER PROJECTS Topics o o o o o Sea Level Rise and the Southern Watersheds Ashville Park Sherwood Lakes Kingston Estates Drainage Operations & Maintenance in the Southern Watersheds

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

Lee Tunnel Flow Transfer System twin 2.4m diameter elevated steel gravity pipelines to transfer stormwater across Beckton STW

Lee Tunnel Flow Transfer System twin 2.4m diameter elevated steel gravity pipelines to transfer stormwater across Beckton STW www.waterprojectsonline.com Lee Tunnel Flow Transfer System twin 2.4m diameter elevated steel gravity pipelines to transfer stormwater across Beckton STW by Paul Furse CEng MICE T hames Water s Lee Tunnel

More information

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options)

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Sub-sector Guideline: (1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Basic Concept A. General Concept Climate change will increase

More information

Coleraine to Derry~Londonderry ROUTE UPGRADE WORKS

Coleraine to Derry~Londonderry ROUTE UPGRADE WORKS Coleraine to Derry~Londonderry ROUTE UPGRADE WORKS Alan Cudlipp CEng FICE FPWI Technical Director - Professional Head of Track Engineering, Mott MacDonald Contents Introduction and project summary Background

More information

Assessing Risks to Inform Resilience: a Criticality Assessment of the British Railway Network

Assessing Risks to Inform Resilience: a Criticality Assessment of the British Railway Network Infrastructure Resilience and Performance Assessing Risks to Inform Resilience: a Criticality Assessment of the British Railway Network Dr Raghav Pant 1, Dr Simon Blainey 2, Prof Jim Hall 3 and Prof John

More information

Preliminary Drainage Analysis

Preliminary Drainage Analysis Preliminary Drainage Analysis Tanimura and Antle Employee Housing Town of Spreckels County of Monterey, California LIB150205 May 29, 2015 Prepared For: Tanimura and Antle Produce Prepared By: 9699 Blue

More information

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. Box Culverts Box Culverts Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. 2 3 System Overview Forterra is one of the largest

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

HS1 Link The View from London

HS1 Link The View from London HS1 Link The View from London For HS2 Growth and Connectivity Conference 12 September 2014 Contents 1. TfL Position on HS2 & Hybrid Bill Petition 2. HS1 Link Issues & Possible Options 2 HS2 Progress To

More information

Track renewals. Creating tomorrow s railway

Track renewals. Creating tomorrow s railway Track renewals Creating tomorrow s railway Track renewals Creating tomorrow s railway Through close alliance and collaboration our aim is to be the partner of choice for all aspects of rail track renewal

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

Network Rail Procurement and Supply Chain Strategy

Network Rail Procurement and Supply Chain Strategy Appendix K Network Rail Procurement and Supply Chain Strategy MSBC Master (for NO use only)_first Issue.docx Infrastructure Projects CP5 Procurement and Supply Chain Strategy Supplier Briefing Central

More information

RETROFITTING AN EXISTING BALLAST DECK RAIL BRIDGE WITH A BALLASTLESS DECK IN AN OPERATIONAL COAL RAIL ENVIRONMENT

RETROFITTING AN EXISTING BALLAST DECK RAIL BRIDGE WITH A BALLASTLESS DECK IN AN OPERATIONAL COAL RAIL ENVIRONMENT RETROFITTING AN EXISTING BALLAST DECK RAIL BRIDGE WITH A BALLASTLESS DECK IN AN OPERATIONAL COAL RAIL ENVIRONMENT Evan Lo Andres Moreno Lara Simon Larsen Bachelor of Engineering Master of Engineering Bachelor

More information

ADAPTATION SYMPOSIUM Nicole Legault Environmental Policy Directorate Transport Canada

ADAPTATION SYMPOSIUM Nicole Legault Environmental Policy Directorate Transport Canada ADAPTATION SYMPOSIUM 2016 Nicole Legault Environmental Policy Directorate Transport Canada April 13, 2016 PURPOSE Explore key risks and opportunities for the transportation sector from a changing climate

More information

Guide to Alterations and Work at Premises We Rent Out

Guide to Alterations and Work at Premises We Rent Out Guide to Alterations and Work at Premises We Rent Out Updated: June 2016 Contents 1 Introduction 2 Permitted work work you do not need our consent for 3 Protecting the safety of the railway 4 Conditions

More information

MEETING DATE: March 22, 2017 PREPARED BY: DEPT. DIRECTOR: Jim Gilliam, Arts Administrator. Jennifer Campbell

MEETING DATE: March 22, 2017 PREPARED BY: DEPT. DIRECTOR: Jim Gilliam, Arts Administrator. Jennifer Campbell MEETING DATE: March 22, 2017 PREPARED BY: Jim Gilliam, Arts Administrator DEPT. DIRECTOR: Jennifer Campbell DEPARTMENT: Parks and Recreation CITY MANAGER: Karen P. Brust SUBJECT: San Elijo Lagoon Double

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

Stormwater Management System Project Review

Stormwater Management System Project Review TRANSIT NEW ZEALAND SH1 AVALON DRIVE BYPASS Project Review TRANSIT NEW ZEALAND TRANSIT NEW ZEALAND SH1 AVALON DRIVE BYPASS Project Review Prepared By Emma Innocente Environmental Engineer Cedric Malaval

More information

Outlet Structure Modeling

Outlet Structure Modeling Watershed Modeling using HEC-RAS Outlet Structure Modeling Jeff Wickenkamp, P.E., CFM, D.WRE Patrick Lach, P.E. Hey and Associates, Inc. Water Resources, Wetlands and Ecology Outline of Presentation Why

More information

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR July 12, 2002 A Paper Submitted for the AREMA Annual Conference by: Paul B. Satterly, P.E. HNTB CORPORATION 111 Monument Circle, Suite 1200 Indianapolis,

More information

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7 ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7 ENVIRONMENTAL IMPACT STATEMENT For ease of local identification this Environmental Impact Statement

More information

SEARs project justification and conclusion

SEARs project justification and conclusion 31 Project justification and conclusion This chapter presents a justification for the project and a conclusion to the environmental impact statement (EIS). The justification is based on the strategic need

More information

4.0 FLOOD MITIGATION OPTIONS

4.0 FLOOD MITIGATION OPTIONS 4.0 FLOOD MITIGATION OPTIONS Brainstorming sessions between WSA and KGS Group lead to the development of numerous feasible flood mitigation options for the Quill Lakes basin. Ultimately, six different

More information

Chapter 11 Culverts and Bridges

Chapter 11 Culverts and Bridges Chapter 11 Culverts and Bridges Contents 1.0 Introduction... 1 2.0 General Design... 1 2.1 Design Criteria... 1 2.2 Design Flows... 1 2.3 Permitting and Regulations... 1 2.4 Aesthetics and Safety... 2

More information

YORKSHIRE WATER SERVICES. Humbercare Sewerage Network Analysis

YORKSHIRE WATER SERVICES. Humbercare Sewerage Network Analysis YORKSHIRE WATER SERVICES Humbercare Sewerage Network Analysis Page 1 July 2008 1 Summary 1.1 Introduction 1.1.1 Following flooding in Hull in June 2007 we have been asked by Ofwat to investigate, model

More information

Safely designing High Speed Two

Safely designing High Speed Two Safely designing High Speed Two Challenges in building the organisation, and demonstrating the railway to be safe Dr Reuben McDonald, Head of System Safety, Security & Interoperability, HS2 16 th June

More information

Leasing of Railway Land

Leasing of Railway Land Discipline: Engineering (Track & Civil) Category: Standard Leasing of Railway Land ETD-17-01 Applicability New South Wales CRIA (NSW CRN) Primary Source ARTC NSW Standard EGS 08 Document Status Version

More information

The Northampton Mole Project A case study of the application of freight pipelines in an urban environment

The Northampton Mole Project A case study of the application of freight pipelines in an urban environment 1 The Northampton Mole Project A case study of the application of freight pipelines in an urban environment ISUFT 2016, Arlington, August 22-24, 2016 7 th International Symposium on Underground Freight

More information

One system crossing the boundaries

One system crossing the boundaries One system crossing the boundaries ERS - Embedded Rail System for optimum integration into tunnel, station and bridge structures How can you improve safety and accessibility in tunnels and stations? How

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: CULVERT DESIGN SPECIFIC SUBJECT: COUNTERSINKING AND LOW FLOW CONSIDERATIONS

More information

BNSF RAILWAY COMPANY

BNSF RAILWAY COMPANY BNSF RAILWAY COMPANY GUIDELINES FOR PREPARATION OF BRIDGE DEMOLITION & REMOVAL PLAN OVER THE BNSF RAILWAY OFFICE OF DIRECTOR BRIDGE ENGINEERING KANSAS CITY, KANSAS August 21, 2008 INDEX ITEM PAGE I. General

More information

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE The Existing Roadway Condition Assessment Report (ERCAR) should include the evaluation of all elements against new construction criteria.

More information

Adaptation to Extreme Weather Events and Climate Change

Adaptation to Extreme Weather Events and Climate Change Office of Planning, Environment and Realty Office of Infrastructure Adaptation to Extreme Weather Events and Climate Change SASHTO Meeting Robert Kafalenos, FHWA August 25, 2014 1 Planning for the Future

More information

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail

More information

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials. I. Drainage Report A. Executive Summary - Brief Overview of Project Drainage Design B. Project Description 1. Existing Conditions 2. Proposed Project Conditions 3. Project Justification Narrative - Basin

More information

The case for the Digital Railway. Patrick Bossert. Digital Railway Transformation Director. Agenda

The case for the Digital Railway. Patrick Bossert. Digital Railway Transformation Director. Agenda The case for the Digital Railway Patrick Bossert Digital Railway Transformation Director Agenda A railway that delivers better economic return for every invested in the network up to +40% seats at 30%

More information

Sunrise Project South I-205 Corridor Improvement Project

Sunrise Project South I-205 Corridor Improvement Project Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205

More information

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification 7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street

More information

report One system crossing the boundaries Always a step ahead in rail systems!

report One system crossing the boundaries Always a step ahead in rail systems! One system crossing the boundaries report Corkelast ERS - Embedded Rail System for optimum integration into tunnel, station and bridge structures Always a step ahead in rail systems! One system crossing

More information

WATERgraafsmeer innovative climate adaptation and urban transition

WATERgraafsmeer innovative climate adaptation and urban transition WATERgraafsmeer innovative climate adaptation and urban transition Johan de Bondt Chairman Maarten Claassen - Programmemanager Governance City of Amsterdam Sewerage and Stormwater Groundwater Drinking

More information

Application for resource consent Form B Damming and diversion of water

Application for resource consent Form B Damming and diversion of water Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or

More information

Making the Journey A Manifesto for Transport

Making the Journey A Manifesto for Transport Making the Journey A Manifesto for Transport 1 What is the UK s Transport Network? The local and national infrastructure that delivers transport by rail, road, air and water. This includes the operation

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 Phasing of Meetings April Meeting May Meeting October Review of Tax Day Storm Event and Immediate Actions Taken By City Review of Coordination

More information

DESIGN OF FLYOVER TRANSVERSE VERTICALLY BY USING HYDRAULIC JACK

DESIGN OF FLYOVER TRANSVERSE VERTICALLY BY USING HYDRAULIC JACK DESIGN OF FLYOVER TRANSVERSE VERTICALLY BY USING HYDRAULIC JACK M. Hari Sathish Kumar 1, K. S. Binitha 2, K. Balaji 3 1,2Assistant Professor, Department of Civil Engineering, PERI Institute of Technology,

More information

MTM REQUIREMENTS METROPOLITAN TRAIN MAINTENANCE DEPOT

MTM REQUIREMENTS METROPOLITAN TRAIN MAINTENANCE DEPOT Approval Amendment Records Approval Date Version Description 14/11/2011 1 Initial Version Disclaimer Metro Trains Melbourne makes no warranties, express or implied, that compliance with the contents of

More information

Chapter 1 Introduction

Chapter 1 Introduction Chapter 1 Introduction KEY POINTS The amount and value of freight are critical components of the overall economic health of Missouri. Missouri s multimodal freight system supports the movement of trucks,

More information

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations Contents Contents... 2 Preface... 3 Issue Record... 3 Assessment

More information

These potential changes and their implications are outlined in Annex 1.

These potential changes and their implications are outlined in Annex 1. Guidance Note Hydropower Guidance Note: This Guidance Note has been prepared by Natural Resources Wales (NRW) to provide applicants for abstraction and impoundment licences for hydropower schemes with

More information

Track desktop assessments for line speed improvements. David Ball, CEng MICE, FPWI

Track desktop assessments for line speed improvements. David Ball, CEng MICE, FPWI Track desktop assessments for line speed improvements David Ball, CEng MICE, FPWI THIS PRESENTATION WILL: Show ways to analyse and scope track works to facilitate raising the line speed from the safety

More information

The Infrastructure Decade

The Infrastructure Decade The Infrastructure Decade The Infrastructure Decade Introduction After the challenges of the downturn the UK economy is growing again. This has been achieved, in part, as a result of a renewed focus on

More information

Thames Water AMP6 Outcomes Reporting Policy Annex 2 Wholesale. Asset Health Control Limits & Failure Thresholds March 2015

Thames Water AMP6 Outcomes Reporting Policy Annex 2 Wholesale. Asset Health Control Limits & Failure Thresholds March 2015 Thames Water Outcomes Reporting Policy Annex 2 Wholesale Asset Health Control Limits & Failure Thresholds March 2015 Published: 31 March 2015 Contents 1 Introduction... 1 2 Wastewater Non-Infrastructure...

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

TONBRIDGE & MALLING BOROUGH COUNCIL. PLANNING and TRANSPORTATION ADVISORY BOARD. 15 November 2016

TONBRIDGE & MALLING BOROUGH COUNCIL. PLANNING and TRANSPORTATION ADVISORY BOARD. 15 November 2016 Part 1- Public TONBRIDGE & MALLING BOROUGH COUNCIL PLANNING and TRANSPORTATION ADVISORY BOARD 15 November 2016 Report of the Director of Planning, Housing & Environmental Health Matters for Recommendation

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Welcome to the Boulevard Lake Dam Class Environmental Assessment. Public Information Session #1. June 14, 2016

Welcome to the Boulevard Lake Dam Class Environmental Assessment. Public Information Session #1. June 14, 2016 Welcome to the Boulevard Lake Dam Class Environmental Assessment Public Information Session #1 June 14, 2016 Boulevard Dam - Overview Built approximately 100 years ago Owned and operated by the City of

More information

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds Local Flood Hazard Mitigation Program A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds Flood Hazard Mitigation Defined 2 2 Presentation Overview Why and how is the NYC

More information

Summary of Detention Pond Calculation Canyon Estates American Canyon, California

Summary of Detention Pond Calculation Canyon Estates American Canyon, California July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i

More information

Position Description

Position Description Position Description Name Position title Environmental Engineer Level Group Section Responsible to Responsibility for staff Rivers & Drainage Engineering Engineering Manager Rivers & Drainage None Position

More information

CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS

CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS CHAPTER 6 ADDITIONAL STANDARDS APPLYING TO SHORELAND AREAS AND PUBLIC WATERS Section 1 Intent. 49 Section 2 Floodplain Requirements 49 Section 3 Water-Oriented Accessory Structures 50 Section 4 Stairways,

More information

INCLUDE IN ALL PAVING PROJECTS UNLESS OTHERWISE DIRECTED BY TSB

INCLUDE IN ALL PAVING PROJECTS UNLESS OTHERWISE DIRECTED BY TSB 1.1 TESTING AND EVALUATION OF FINISHED PAVEMENT SURFACE SMOOTHNESS USING INTERNATIONAL ROUGHNESS INDEX (IRI) CRITERIA 1.1.1 General Contrary to the requirements of Specification 3.50, Asphalt Concrete

More information

Climate Data Training Session April 26, 2017 Ontario Science Centre

Climate Data Training Session April 26, 2017 Ontario Science Centre Adaptive Management To Address Climate Change Uncertainty in EA Process A Case Study of the Don Mouth Naturalization and Port Lands Flood Protection Project EA (DMNP EA) Climate Data Training Session April

More information

Passenger service for the Dudding Hill line: brief for feasibility study

Passenger service for the Dudding Hill line: brief for feasibility study Appendix 1: Specification for a Study Passenger service for the Dudding Hill line: brief for feasibility study Introduction The West London Alliance is currently investigating ways of accommodating the

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS 23 rd International Congress on Sound & Vibration Athens, Greece 10-14 July 2016 ICSV23 USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS Chris Skinner, Paul Shields and Yuyou Liu AECOM,

More information

Prepaving Conferences

Prepaving Conferences Prepaving Conferences Presenters ODOT: Bob Townsend Assistant Project Manager The Dalles Construction Office Knife River: Tyrone Belgarde Project Superintendent Knife River Corporation-Northwest Prepaving

More information

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

More information

Protecting Existing PCCP Subject to External Transient Loads. 200, Fort Worth, Texas 76109; phone (817) ;

Protecting Existing PCCP Subject to External Transient Loads. 200, Fort Worth, Texas 76109; phone (817) ; 203 Protecting Existing PCCP Subject to External Transient Loads James K. Johnson, P.E. 1, Alan C. Hutson, P.E. 2, Russell L. Gibson, P.E. 3 and Louie Verreault, P.E. 4 1 Engineer, Water Resources, Freese

More information

Small Scale Hydro Power Systems

Small Scale Hydro Power Systems Small Scale Hydro Power Systems Practicalities Workshop Matthew Rhodes Managing Director Agenda Site assessment Design Operations and maintenance Concluding project tips And all projects start from understanding

More information

CHAPTER 7. San Dieguito River Flooding Adaptation

CHAPTER 7. San Dieguito River Flooding Adaptation CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,

More information

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3

More information

Prepared by Irwin Juckes, PhD (Microbiology), MBA

Prepared by Irwin Juckes, PhD (Microbiology), MBA COMMENT ON DRAFT ENVIRONMENTAL IMPACT ASSESSMENT FOR LINKSFIELD MIXED USE INCLUSIONARY DEVELOPMENT (REFERENCE GAUT: 002/13-14/EO153) Prepared by Irwin Juckes, PhD (Microbiology), MBA Table of Contents

More information

King County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds

King County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds News Release Contact: Al Sanders 206-477-1016 August 31, 2015 Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds The Flood Control District

More information

New Castle County, DE. Floodplain Regulations

New Castle County, DE. Floodplain Regulations New Castle County, DE Floodplain Regulations John J. Gysling, PE CFM Department of Land Use New Castle County, DE February 26, 2009 Today s Presentation Floodplain Protection and Uses Terms and Definitions

More information

Climate Change: Background and Implications

Climate Change: Background and Implications Climate Change: Background and Implications American Public Works Association Conference on Climate Change Tempe, AZ April 9, 2008 Peter Schultz U.S. Climate Change Science Program Office, Director Outline

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need Environmental Impact Statement (EIS) Revised Purpose and Need June 23, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure

More information

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT ATHABASCA RIVER BRIDGE REHABILITATION PROJECT PROJECT INFORMATION Project Name Athabasca River Bridge Rehabilitation Project Location Highway 40 (over the Athabasca River), Entrance, Alberta Year Completed

More information

Bridge Strikes from Road Vehicles or Waterborne Vessels

Bridge Strikes from Road Vehicles or Waterborne Vessels Railway Group Standard Bridge Strikes from Road Vehicles or Waterborne Vessels Synopsis This document mandates requirements for the management of the risks to the operational railway from road vehicles

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 CONTROL, COMMAND AND COMMUNICATION

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 CONTROL, COMMAND AND COMMUNICATION THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 17 CONTROL, COMMAND AND COMMUNICATION Control centre optimises the positions of trains in real time Drivers receive information to optimise

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

SECTION 11: REGULATORY FLOODWAYS

SECTION 11: REGULATORY FLOODWAYS SECTION 11: REGULATORY FLOODWAYS Contents 11.1. The Floodway... 11-2 11.1.1. The floodway concept... 11-2 11.1.2. Floodway map... 11-2 11.1.3. Floodway permitting... 11-3 11.1.4. Changing the floodway...

More information

Liverpool City Region Candidate Major Schemes April 2013

Liverpool City Region Candidate Major Schemes April 2013 Region Candidate April 2013 Sponsoring Halton Borough Halton Borough Halton Borough Scheme Name: Detail: Estimated Silver Jubilee Bridge Major Maintenance M56 J11A Daresbury Enterprise Zone / East Runcorn

More information

STORMWATER AND EROSION CONTROL PERMIT

STORMWATER AND EROSION CONTROL PERMIT STORMWATER MANAGEMENT AND EROSION CONTROL PERMIT INSTRUCTIONS AND INFORMATION Any project that involves the disturbance of ANY quantity of land requires the applicant to receive approval for the project

More information