RESULTS AND CONCLUSIONS OF TECHNICAL - ECONOMIC FEASIBILITY STUDY OF LTO DUKOVANY NPP
|
|
- Theodore Lawrence Carter
- 6 years ago
- Views:
Transcription
1 RESULTS AND CONCLUSIONS OF TECHNICAL - ECONOMIC FEASIBILITY STUDY OF LTO DUKOVANY NPP ČEZ, a.s. Dušan Pluhař Lyon 4th International Conference on NPP Life Management
2 TECHNICAL-ECONOMIC STUDY - OBJECTIVE Purpose: Basis for decisions on Dukovany NPP operation after 2025 Objective: Determining the optimal LTO variant, basic assumptions and conditions Appraised variants of operation: +20 (up to , 50 years) and +30 (up to , 60 years) Objective of the economic part: Determine the NPV considered options such as LTO metric comparison and selection of the optimum (the sum of the discounted annual cash flow) A processing methodology was presented in Espoo 2015 Outputs from the assessment of the technical part, risk analysis and preliminary (not final) results of cost drivers assessment was presented in Vienna 2016 Now present the outputs of the economic evaluation and the overall outputs of the study 1
3 MODEL INPUTS FOR THE CALCULATION OF NPV AND SENSITIVITY ANALYSIS APPROXIMATION, PREDICTION Long-term achievable electrical performance of units, unit efficiency and self-consumption Availability (length of outages and failure due to implementation of the measure) Variable costs: nuclear fuel costs non fuel costs (cooling water and energy costs) fee for the permanent storage of spent nuclear fuel Fix costs: personal expenses overhead costs and insurance and headquarter overhead costs maintenance costs taxes decommissioning costs (creation of the reserve) CAPEX (the largest input - the set of cost measures, the output from the cost drivers assessment in the TES technical part) Depreciation (historical and future investments, spent nuclear fuel containers and fuel) Inflation and escalation coefficients (for different investment types) Forex a WACC (weighted average costs of capital) The calculated inputs - sales, gross margin, corp. tax, total depreciation CF DCF NPV 2
4 ESTIMATE OF CAPEX+OPEX LTO +10, +20 AND +30 THE OUTPUT FROM THE COST DRIVERS ASSESSMENT Costs are set conservatively, at nominal prices 2017 The cost of the LTO+30 is double compared to the LTO+20 Costs after 2037 in the LTO20 variant are spent on expanding the spent fuel storage 3
5 Costs (mil. Euro) LTO +30 X LTO +20 LTO +20 X LTO +10 LTO +10 X LTO 0 Maintenance costs
6 FINAL RESULTS OF COST DRIVERS ASSESSMENT COMPARISON RESULTS 2008, 2013, 2016 In 2008 was created first T-E study. In 2013 partial update for making Long term conception of Dukovany site, only cost drivers refer to systems, structures and construction, not other drivers. From 2014 to 2016 is created new T-E study. Main differences among them are: 40% higher total LTO costs in 2013 than 2008, above all due to +10 delay of many actions, post Fukushima actions. For +20 and +30 difference is around 15% - more knowledges - AMP In 2016 more individual actions, more detailed assessment, inputs from new developed Health Reports, more systematic work. Result is 20-25% higher costs in 2016 than 2013 and very different layout of costs, main difference is for +30 option Conclusion and experience: costs still rise with new knowledges, predictions and assessments are too optimistic. 5
7 SENSITIVITY ANALYSIS, INPUT FOR DOWN/UP SIDE SCENARIOS Sensitivity analysis - changing NPV depending on parameter change Purpose - for the right choice for deviations up / down side scenarios Performed on the main parameters of the model: Availability Nuclear fuel costs Cooling water costs Fee for the permanent storage of spent nuclear fuel Personal expenses Maintenance costs CAPEX (capital expenses) Decommissioning costs Special case is electricity price - the greatest impact on NPV 4 scenarios of the prediction of the development of electricity prices (price scenarios) For the same price scenario has the greatest impact on the NPV change unit availability In addition, investments (CAPEX) and fuel and maintenance costs Down/up side scenarios included a change in availability of ±1%, CAPEX +10% (LTO +30y +20%), tax utilization, potentials, decommissioning costs +25% and change of methodology 6
8 SCENARIOS OF THE DEVELOPMENT OF ELECTRICITY PRICES, DOWN/UP SIDE SCENARIOS - NPV RESISTANCE 4 scenarios of electricity price developments were used to calculate NPVs (SA price E): Stress test scenario SVET8 (lowest coal & oil prices, EU ETS collapse, energy savings) Inflation scenario (forward extrapolated by inflation) Central scenario (fundamental analysis ČEZ fuel prices, RSE, electricity market) Analytic scenario (average of analysts' views on the development of electricity prices) The reference scenario is Central, based on the resistance (robustness) scenarios - deviations of input parameters based on sensitivity analyzes: Downside scenario - worsening of parameters with the highest impact on NPV, known significant risk (CAPEX, availability, decommissioning reserve) Scenario of reduced operation - early closure of units in the period due to meet critical risks with such an impact (unexpectedly) Zero scenario - termination of units operation in 2017 as a borderline case NPV for comparison (decommissioning costs, operational and overhead costs after shutdown) Upside scenario - improving the NPV result (potentials, availability, corporate tax) 7
9 Mil. $ Mil. $ Mil. $ Mil. $ NPV OF SCENARIOS OF THE DEVELOPMENT OF ELECTRICITY PRICES, OPTIMAL VARIANT LTO +20 (50Y) Stress test scenario Inflation scenario LTO10 LTO20 LTO30 LTO10 LTO20 LTO30 Central scenario Analytic scenario NPV LTO+20 is almost the same in the central (reference) scenario as for +30, in the stress test it is significantly less negative, in the inflation order higher. LTO+30 is loaded greater uncertainties. Best by NPV and development of electricity prices - 50y of operation in LTO20 8 LTO10 LTO20 LTO30 LTO10 LTO20 LTO30
10 LTO+20 (OPERATION IN => 50 YEARS) RESISTANCE TO RISKS AND DOWNSIDES For LTO EDU represents commodity risk Decommissioning nuclear (reserve) and non-nuclear parts of Dukovany, operational and overhead costs after termination of units operation Zero scenario Financial stress test has shown that even sudden closure in shows NPV NPV LTO10 9
11 RISK ANALYSIS OUTPUTS - OPTIMAL VARIANT LTO +20 (50Y) Risk analysis is one of the basic part of the T-E study. According with standard ISO Outputs of risk analysis The risk register contains 111 risks, 74 opened Some of them are critical risks - high score (red) in inherent level for both LTO variants. Their impact is the negative or weakly positive LTO economy or the LTO's end-of-life shock before the target date. A significant part of the risks, even critical, are growing over time LTO high risks at inherent level and 5 after application of measures, LTO high risks at inherent and 11 at residual level LTO +20 is less affected by the risks, optimal variant 10
12 RISK ANALYSIS MAP OF RISKS 11
13 RISK ANALYSIS KEY ASPECTS AND RISKS OF LTO The length of operation determines mainly the development of legislation, political decisions and the price of electricity Legislation Safety requirements (extreme events, human activity, ) Development of legislation and regulation (fees, costs - decommissioning of NPP, permanent storage, EIA on LTO, EC notification, radioactive waste management,...) Policy Change of public opinion, politicians' attitudes (events, unstable operation, accidents) Pressure of NGOs, international institutions and governments (G, AUS,...) Economy Long-term decline in electricity prices Structure of supply and demand (RES, decentralization, capacity payments,...) Costs of refurbishment and impact on availability Conditions Availability of qualified personnel, loss of know-how, process quality 12 Stability of suppliers Lifetime of main components - technical risks (internals, liner, cabling, main condenser pipe
14 TECHNICAL-ECONOMIC STUDY OF LTO DUKOVANY NPP RESULTS AND CONCLUSIONS The optimal variant in terms of NPV, resistance downside scenarios, uncertainties and risks, is the operation until (50y), with the possibility of longer operation if the development of the main determinants (electricity prices, investments and their impact on availability, uncertainty and risk) will positive. To ensure the efficient operation of the horizon optimal variant is in addition to ensuring the required state of technology and project and mitigating the most serious risks, it is necessary to fulfill other basic prerequisites and necessary conditions in key areas: ensuring a sufficient number of sufficiently qualified and motivated staff ensuring the highest level of professionalism and quality of all management processes ensuring a functional and comprehensive knowledge management in nuclear processes maintaining a high level of acceptability of nuclear energy and the operation of the Dukovany NPP by public long-term conservation and increasing the capabilities and stability of key suppliers Fulfilling conditions contributes or leads to the mitigation of some critical risks. 13
15 CONCLUSION THANK YOU FOR YOUR ATTENTION
Sharing knowledge across Mediterranean Jordan. Cost factors of nuclear electriciy. Jean-Jacques GAUTROT Special Advisor to the AREVA CEO
Sharing knowledge across Mediterranean Jordan Cost factors of nuclear electriciy Jean-Jacques GAUTROT Special Advisor to the AREVA CEO Jordan,1 st March 2010 6.7 billion people Photo composite NASA sans
More informationFrom Market Uncertainty to Policy Uncertainty for Investment in LTO of NPP on Electricity Market
IAEA Fourth International Conference on Nuclear Power Plant Life Management Lyon, France 23-27 October 2017 From Market Uncertainty to Policy Uncertainty for Investment in LTO of NPP on Electricity Market
More informationSYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC
SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC 3.10.2016 ČEZ, a. s. Meeting at IAEA Vienna Overview of topics ČEZ nuclear fleet (basic features) Systematic measures targeted to improve
More informationPredictions of Nuclear Energy Market Share in the U.S. Electricty Market
Predictions of Nuclear Energy Market Share in the U.S. Electricty Market The 25th USAEE/IAEE North American September 21, 2005 A. Yacout, G. Conzelmann, V. Koritarov, L. Van Den Durpel Argonne National
More informationSubtask 1: Economic of PV System Performance and Reliability
TASK 13: PERFORMANCE AND RELIABILITY OF PV SYSTEMS Subtask 1: Economic of PV System Performance and Reliability Mauricio Richter (3E), Jan Vedde (SiCon) Mike Green (M.G.Lightning Electrical Engineering)
More informationDECOMMISSIONING OF NUCLEAR FACILITIES IN UKRAINE
DECOMMISSIONING OF NUCLEAR FACILITIES IN UKRAINE Tatiana Kilochytska State Nuclear Regulatory Committee of Ukraine Annual Forum for Regulators and Operators in the Field of Decommissioning International
More informationJoint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria
2473-9 Joint ICTP-IAEA School on Nuclear Energy Management 15 July - 3 August, 2013 Lecture Notes I. Mele IAEA, Vienna, Austria The IAEA Nuclear Energy Management School ICTP, Trieste, 15-2 August 2013
More informationIdentifying and Addressing the Support Needs in Member States Intending to Expand Existing Nuclear Power Programmes and Lessons Learned
International Conference on the Challenges Faced by TSOs in Enhancing Nuclear Safety and Security, 25-29 October 2010, Tokyo, Japan Identifying and Addressing the Support Needs in Member States Intending
More informationCoal cost projections
Coal cost projections Approach and risks to coal cost projections May 2016 Strategy with substance www.woodmac.com Background and Objectives Coal cost projections AEMO oversees system security of the National
More informationUNIVERSITÄT HANNOVER. next required reinvestment RI2 after 15 years; next required reinvestment RI1 after 10 years;
INSTITUT FÜR SIEDLUNGSWASSERWIRTSCHAFT UND ABFALLTECHNIK UNIVERSITÄT HANNOVER (INSTITUTE OF DOMESTIC WATERSUPPLY AND WASTE TECHNOLOGY OF THE UNIVERSITY OF HANOVER) O. PROF. DR.-ING. CARL FRANZ SEYFRIED
More informationNuclear-renewable hybrid energy systems for non-electric applications
Nuclear-renewable hybrid energy systems for non-electric applications Cost issues Saied Dardour 3E Analysis Unit Planning and Economic Studies Section Division of Planning, Information and Knowledge Management
More informationGuidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities
DRAFT Regulatory Document RD-152 Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities Issued for Public Consultation May 2009 CNSC REGULATORY
More informationAvailability and Costs of Supply-Side Electricity Options
Availability and Costs of Supply-Side Electricity Options Revis James Director Energy Technology Assessment Center EPRI Global Climate Change Research Seminar Washington, DC May 20, 2009 Key Messages The
More informationUnits 3 and 4 Cernavoda NPP Project Envisaged Ownership Structure and Operation and Maintenance
Units 3 and 4 Cernavoda NPP Project Envisaged Ownership Structure and Operation and Maintenance POWERed by people Alexandru HAVRIS Head of Projects Management Department SN Nuclearelectrica SA IAEA Technical
More informationIntegrated Review of Infrastructure for Safety - IRIS
Integrated Review of Infrastructure for Safety - IRIS Technical Meeting on Infrastructure Issues 2 February 2017, Vienna M - Board Room A - Department of Nuclear Safety & Security JUBIN Regulatory Activities
More informationPreliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development
Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of
More informationLife Cycle Analysis a 7D SM Future
Life Cycle Analysis a 7D SM Future Bob Prieto National Institute of Building Sciences Building Innovation 2014 Advancing Life-Cycle Performance. January 9, 2014 A Challenging Future Simple Complex Static
More informationMid-term Adequacy Forecast of the Czech Republic ČEPS 08/2016
Mid-term Adequacy Forecast of the Czech Republic 2016-2025 ČEPS 08/2016 Mid-term Adequacy Forecast (MAF CZ) According to Regulation (EC) No 714/2009 ENTSO-E shall adopt the European generation adequacy
More informationWM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA
Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1
More informationAtoms for the Future 2014 Paris September National Debate and Public Confidence in Sweden
Atoms for the Future 2014 Paris 12-13 September National Debate and Public Confidence in Sweden Ted Lindquist Coordinator Association of Swedish Municipalities with Nuclear Facilities KSO Association of
More informationFall Application Portfolio: East Coast Offshore Wind Farm Development. David Hwang ESD.71 Prof. Richard de Neufville
Fall 2009 Application Portfolio: East Coast Offshore Wind Farm Development David Hwang ESD.71 Prof. Richard de Neufville Contents 1 Abstract...3 2 Introduction...3 3 System Description...4 4 Sources of
More informationOur environment LOVIISA POWER PLANT. Join the. change
Our environment 2016 2016 LOVIISA POWER PLANT Join the change 40 years of carbon dioxide free electricity from Fortum s Loviisa power plant In 2016, the power plant generated a total of 8.33 terawatt hours
More informationRADIOACTIVE WASTE MANAGEMENT in CZECH REPUBLIC
RADIOACTIVE WASTE MANAGEMENT in CZECH REPUBLIC Vojtech Priman WATEC 4 th Meeting Vienna October 2004 CZECH REPUBLIC RADIOACTIVE WASTE REPOSITORY / NUCLEAR PLANT STRÁŽ LITOMERICE NUCLEAR POWER PLANT RESEARCH
More informationA story of Costs and Prices
A story of Costs and Prices PV Markzttan Masson, Director Ir Gaëtan Masson Director, Vice-Chairman, EU PV Technology & Innovation Platform Operating Agent, IEA-PVPS Task 1 BECQUEREL INSTITUTE Research
More informationImplementation of Lessons Learned from Fukushima Accident in CANDU Technology
e-doc 4395709 Implementation of Lessons Learned from Fukushima Accident in CANDU Technology Greg Rzentkowski Director General, Power Reactor Regulation Canadian Nuclear Safety Commission on behalf of CANDU
More informationSYLLABUS - ANALYSIS AND DECISION (20 credits)
Chartered Postgraduate Diploma in Marketing (Level 7) SYLLABUS - ANALYSIS AND DECISION (20 credits) This unit consists of three parts: Strategic audit, Strategic options, and Making strategic marketing
More informationImplementation of the Rules for the Continued Operation in Korea
Implementation of the Rules for the Continued Operation in Korea Presented by Jong-Jooh Jooh Kwon Contents I. Dynamic and Innovative Nuclear Energy Activities in Korea II. Process Implementing requirements
More informationZero Net Carbon Portfolio Analysis
Zero Net Carbon Portfolio Analysis Prepared for: Platte River Power Authority December 12, 2017 www.paceglobal.com Agenda Background Methodology Assumptions Cases Findings and Recommendations Page 2 Background
More informationThe 10-Day Advanced Financial Modelling & Petroleum Project Economics
An Intensive 2-Week Training Course The 10-Day Advanced Financial Modelling & Petroleum Project Economics 16-APR-17 29 Oct - 09 Nov 2017, Dubai This course is Designed, Developed, and will be Delivered
More informationJune 2014 Petr Kubín ČEZ, a.s.
Temelín 3&4 - update June 2014 Petr Kubín ČEZ, a.s. CEZ GROUP IS AN INTERNATIONAL UTILITY WITH A STRONG POSITION IN CEE CEZ Group in Poland (100% stake in Skawina, 100% in Elcho) Electricity generation,
More informationComputation and Analysis on Taiwan Index of Energy Security Risk
Institute of Nuclear Energy Research The 40 th Annual IAEE International Conference Computation and Analysis on Taiwan Index of Energy Security Risk Hui-Wen Huang 19 June, 2017 Outline Introduction Exposure
More informationHarmonized EUR revision E requirements corresponding to currently available technical solutions
Harmonized EUR revision E requirements corresponding to currently available technical solutions Csilla TOTH - EUR Steering Committee MVM Paks II Ltd., Hungary, Technical Director IAEA International Conference
More informationSynthesis on the Economics of Nuclear Energy
Synthesis on the Economics of Nuclear Energy Bruegel, Brussels February 05, 2014 William D haeseleer Responsible Officer CEU: ir. Marc Deffrennes Steering Committee: ENEF sub WG Opportunities / Competitiveness
More informationVisual Economic Tool FAQ
What is Opportunity Rate? The Visual Economic Tooldiscounts future costs to put all values in terms of their present value in todays dollars. This is done using the Opportunity Rate to discount future
More informationFOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP
FOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP NKS January 12-13, 2016 Ove Nilsson Sekretessklass: Open (S1) 1 2015-12-23 FOSH Forsmark Safety Enhancement Project F-0003165
More informationStatus of Decommissioning Preparation for Kori #1
Status of Decommissioning Preparation for Kori #1 http://www.khnp.co.kr December 6, 2017 KHNP Overview (1/2) AA (S&P), Aa2 (Moody s) KHNP Overview (2/2) Power Plants Operational status in Korea 24 22,529
More informationRESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP
RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP P. Krupa Ingeneer, e-mail: Krupa_Peter@ebo.seas.sk Bohunice NPPs Introduction The centre of upgrading activities in VVER NPP is clearly in
More informationLessons from Fukushima
Lessons from Fukushima October 11, 2011 The Institute of Energy Economics, Japan Masakazu Toyoda, Chairman & CEO, Outline : Lessons from Fukushima 1. One NPP accident could stop other plants as well 2.
More informationGeneration Technology Options in a Carbon- Constrained World
Generation Technology Options in a Carbon- Constrained World Prepared by the Energy Technology Assessment Center (Reference: EPRI Report 1022782) Levelized Cost of Electricity Analysis Objectives Provide
More informationNUCLEAR FUEL AND REACTOR
NUCLEAR FUEL AND REACTOR 1 Introduction 3 2 Scope of application 3 3 Requirements for the reactor and reactivity control systems 4 3.1 Structural compatibility of reactor and nuclear fuel 4 3.2 Reactivity
More informationEuropean level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.
Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that
More informationProgram Overview. Through the use of Excel, this course will teach you how to create and use financial models in your organization.
Program Overview How can you put data to work for you? Specifically, how can numbers in a spreadsheet tell us about present and past business activities, and how can we use them to forecast the future?
More informationEnergy Subsidies: Political Drivers and Options for Better Targeting
Energy Subsidies: Political Drivers and Options for Better Targeting NARUC Annual Meeting Baltimore, MD November 12, 2012 Doug Koplow Earth Track, Inc. 2067 Massachusetts Ave., 4 th Floor Cambridge, MA
More informationSENIOR REGULATORS MEETING Strengthening the Implementation of Defence in Depth IAEA Perspective
SENIOR REGULATORS MEETING Strengthening the Implementation of Defence in Depth IAEA Perspective 58th IAEA General Conference 25 September 2014 James Lyons Director of the Division of Nuclear Installation
More informationUPDATE OF THE CONCEPT OF RADIOACTIVE WASTE AND SPENT NUCLEAR FUEL MANAGEMENT (NATIONAL PROGRAMME OF THE CZECH REPUBLIC)
UPDATE OF THE CONCEPT OF RADIOACTIVE WASTE AND SPENT NUCLEAR FUEL MANAGEMENT (NATIONAL PROGRAMME OF THE CZECH REPUBLIC) Prague, November 2014. Table of contents 1. INTRODUCTION... 6 1.1 Objectives of the
More informationPermanent Load Shifting Program
1. Program Description Permanent Load Shifting (PLS) can help reduce system peak load by storing energy produced during off-peak period and shifting electricity use from on-peak to off-peak periods on
More informationLong Term Operation of Nuclear Power Plants in Spain: Preparing for the Future
XXVIII Congreso Anual de la Sociedad Nuclear Mexicana - 2017 LAS/ANS Symposium Long Term Operation of Nuclear Power Plants in Spain: Preparing for the Future Ignacio Marcelles, Eva Frutos, Xavier Jardí
More informationICEM DEVELOPMENT OF THE ENVI SIMULATOR TO ESTIMATE KOREAN SNF FLOW AND ITS COST
Proceedings of the 12 th International Conference on Environmental Remediation And Radioactive Waste Management ICEM 2009 October 11-15, 2009, Liverpool, England, UK ICEM 2009 16060 DEVELOPMENT OF THE
More informationThe Nuclear Safety Authority (ASN - Autorité de Sûreté Nucléaire),
REPUBLIQUE FRANÇAISE ASN Resolution 2014-DC-0406 of 21 th January 2014 instructing Electricité de France - Société Anonyme (EDF-SA) to comply with additional prescriptions applicable to the Gravelines
More informationIAEA-TECDOC-1478 Selection of decommissioning strategies: Issues and factors
IAEA-TECDOC-1478 Selection of decommissioning strategies: Issues and factors Report by an expert group November 2005 IAEA SAFETY RELATED PUBLICATIONS IAEA SAFETY STANDARDS Under the terms of Article III
More informationIAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities
DS447 Date: September 2014 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 11 MS comments incorporated Review Committee Member comments due 31 Oct Predisposal Management
More informationSECTION 14.0 CAPITAL COST ESTIMATES
SECTION 14.0 CAPITAL COST ESTIMATES 1 14.0 Capital Cost Estimates CONTENTS 14.0 CAPITAL COST ESTIMATES...4 14.1 Introduction...4 14.2 Overall Summary...4 14.3 Mining Capital Cost Estimate...5 14.3.1 Pre-Production
More informationPackaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517
Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517 Aurélie Brasch-Serres*, Mathias Chazot** * EDF-DP2D, 154 avenue Thiers, CS 60018, 69458 LYON CEDEX 06, FRANCE
More informationPaper P2 Management Accounting Decision Management. Examiner s Brief Guide to the Paper 16
May 2005 Examinations Managerial Level Paper P2 Management Accounting Decision Management Question Paper 2 Examiner s Brief Guide to the Paper 16 Examiner s Answers 17 The answers published here have been
More informationBackground. Introduction. Overview of vendor design review process
Executive Summary A pre-licensing review of a new nuclear power plant (NPP), also referred to as a vendor design review (VDR), provides an opportunity for CNSC staff to assess a design prior to any licensing
More informationGerman Energy Policy: Reactions after the Fukushima Accident ( Energiewende )
German Energy Policy: Reactions after the Fukushima Accident ( Energiewende ) - Energiewende & Nuclear Phase-out (NPo) - Energy consume & Energy mix - Consequences of the NPo - Self-imposed goals & EC-goals
More informationRadiation and Nuclear Safety Authority Regulation on the Safety of Disposal of Nuclear Waste Adopted in Helsinki on 22 December 2015
UNOFFICIAL TRANSLATION FROM FINNISH. LEGALLY BINDING ONLY IN FINNISH AND SWEDISH. REGULATION STUK Y/4/2016 Radiation and Nuclear Safety Authority Regulation on the Safety of Disposal of Nuclear Waste Adopted
More informationIAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities
DS447 Date: 20 February 2015 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 12 For submission to CSS Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle
More informationScenario Analysis of Power Mix in Taiwan
Scenario Analysis of Power Mix in Taiwan Chia-Hao Liu, Ching-Han Deng, Chia-An Chang* and Fu-Kuang Ko Institute of Nuclear Energy Research Abstract Carbon emissions have become a critical issue concerned
More informationPDF s of the RETScreen data sheets are attached, as are the photos used in the analysis.
From: To: Cc: Subject: Date: Attachments: Louie Azzolini Jim Sparling Ken Baigent; Nick Walker FW: Ekati info Friday, June 12, 2015 12:59:17 PM image001.png Ekati 50 kw Solar - Project Information.pdf
More informationAttachment VIII-1. July 21, 2011 Nuclear and Industrial Safety Agency
Assessment Procedures and Implementation Plan Regarding the Comprehensive Assessments for the Safety of Existing Power Reactor Facilities Taking into Account the Accident at Fukushima Dai-ichi Nuclear
More informationNPP PAKS II: ECONOMIC FEASIBILITY, IMPACT ON COMPETITION AND SUBSIDY COSTS
NPP PAKS II: ECONOMIC FEASIBILITY, IMPACT ON COMPETITION AND SUBSIDY COSTS MAY 2016 This report was prepared exclusively for Greenpeace AUTHORS Jan Ondrich +420 257 532 314 Jan.ondrich@candole.com Martin
More informationNuclear Power Economics and Markets
Nuclear Power Economics and Markets IBC - Decommissioning of Nuclear Reactors & Materials 29 30 September 2014; Miami, Florida Edward Kee Disclaimer The NECG slides that follow are not a complete record
More informationDriving Strategic Planning with Predictive Modeling O R A C L E W H I T E P A P E R N O V E M B E R
Driving Strategic Planning with Predictive Modeling O R A C L E W H I T E P A P E R N O V E M B E R 2 0 1 7 Table of Contents Introduction 1 Most Companies Feel the Effect of Uncertainty 1 The Challenge
More informationUpdating on NPP Life Management, Long Term Operation and post-fukushima Issues in Spain
IAEA Technical Working Group on Life Management of Nuclear Power Plants (TWG-LMNPP) Vienna, February 22-24, 2017 Updating on NPP Life Management, Long Term Operation and post-fukushima Issues in Spain
More informationDecommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective
Lesson Objectives International Atomic Energy Agency Define specific decommissioning terms of Nuclear Facilities The Process Understand the decommissioning process Review the various decommissioning strategies
More informationEconomic Indicators Assessment of NPP Project in Indonesia. Suparman Centre for Nuclear Energy Development
Economic Indicators Assessment of NPP Project in Indonesia Suparman Centre for Nuclear Energy Development INTRODUCTION Indonesia has performed: economics assessment using INPRO Methodology within its 2012-2014
More informationCommercial heat network modelling Presentation to Heat Modelling Unit at the Department of Energy and Climate Change 11 th June 2015
Commercial heat network modelling Presentation to Heat Modelling Unit at the Department of Energy and Climate Change 11 th June 2015 Agenda Introduction to decentralised energy practice at LE; How to build
More informationRegulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident
Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident O Phillips: Senior Executive Manager - National Nuclear Regulator The Fukushima Ministerial
More informationCGMA Competency Framework
CGMA Competency Framework Technical skills CGMA Competency Framework 1 Technical skills : This requires a basic understanding of the business structures, operations and financial performance, and includes
More informationCustomer Lifetime Value
Customer Lifetime Value Opportunities and Challenges Greg Firestone Mohamad Hindawi, PhD, FCAS March, 2013 Antitrust Notice The Casualty Actuarial Society is committed to adhering strictly to the letter
More informationFlexibility of the conventional Power Plants as necessary response to the electricity market conditions
International Power Summit Rome, 22 24 February 2017 Flexibility of the conventional Power Plants as necessary response to the electricity market conditions Agenda: - famous triangle: security of supply,
More informationDay 1: Oil & Gas Financial Statement Modeling in Excel
Day 1: Oil & Gas Financial Statement Modeling in Excel Day 1 Overview Participants develop an Oil & Gas (O&G) financial model completely from scratch, inputting historical data as well as macro and company-specific
More informationThe Nuclear Safety Authority (ASN),
FRENCH REPUBLIC ASN resolution 2012-DC-0276 of 26 June 2012 instructing Électricité de France Société Anonyme (EDF-SA) to comply with additional requirements applicable to the Bugey NPP (Ain département)
More informationDrilling, metallurgical test work and a new resource model add 21% to oxide gold reserves
LA ARENA GOLD OXIDE RESERVES INCREASED TO 1.28MM OZ AT AU PRICE OF $1,200 COMPLETION OF THE PRE-FEASIBILITY STUDY FOR THE PHASE II SULPHIDE Cu-Au PROJECT Drilling, metallurgical test work and a new resource
More informationManaging Volatility. Risk in mining investment decisions. Managing Volatility
Managing Volatility Risk in mining investment decisions Managing Volatility Previous page Contents page Next page Contents Managing volatility risk in mining investment decisions Introduction 2 Can your
More informationPAGE 38 THOMAS KUSTERER THE GERMAN ENERGY TRANSITION
PAGE 38 THOMAS KUSTERER THE AUTHOR PAGE 39 Thomas Kusterer Chief Financial Officer EnBW Energie Baden-Würtemberg AG The German Energy Transition Partnership Models and a Reliable Framework as a Basis for
More informationGUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs
GUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs CNCAN, ROMANIA 2016 1 TABLE OF CONTENTS 1. INTRODUCTION 1.1. Background 1.2. Purpose and scope of the guidelines 1.3. Structure of the guidelines 1.4.
More informationSome Doubts about Oxford s Argument on Stranding Thermal Coal in Japan
Some Doubts about Oxford s Argument on Stranding Thermal Coal in Japan Jun ARIMA Professor, Graduate School of Public Policies The University of Tokyo On May 12, the electronic version of the Nikkei carried
More informationEska Creek Preliminary Feasibility Analysis
Introduction Eska Creek Preliminary Feasibility Analysis This report examines the feasibility issues of energy and economics for a 1.8 MW hydroelectric project on Eska Creek (project). The Project is located
More informationMeetings for Sharing International Knowledge and Experience on Stress Tests
Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation
More informationUsing Enterprise Budgets to Compute Crop Breakeven Prices Michael Langemeier, Associate Director, Center for Commercial Agriculture
June 2017 Using Enterprise Budgets to Compute Crop Breakeven Prices Michael Langemeier, Associate Director, Center for Commercial Agriculture Enterprise budgets provide an estimate of potential revenue,
More informationSafety enhancement of NPPs in China after Fukushima Accident
Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015
More informationThe Stress Test Process in France (CSA*) Its impact on Research Facilities
BgNS International Conference NUCLEAR POWER FOR THE PEOPLE 10 13 October 2012, AUGUSTA SPA Hotel, Hissar, Bulgaria The Stress Test Process in France (CSA*) ---- Its impact on Research Facilities G. Cognet
More informationAbout Energy UK. Introduction
REC 34-15 Energy UK response to DG Comp investigation of Investment Contract (early Contract for Difference) for Lynemouth power station biomass conversion 10 May 2015 About Energy UK Energy UK is the
More informationLocal participation in the German Energiewende
Local participation in the German Energiewende The German Energiewende Reasons: Climate Protection: Replacing fossil energy carriers by green energy carriers Reduction of CO 2 -production Phasing out nuclear
More informationSupplier Guide Book. Collaborate, perform, grow together
Supplier Guide Book Collaborate, perform, grow together Message from our Chief Purchasing Officer Dear Supplier, DK Singh CPO Schneider Electric We are pleased to publish the Schneider Electric Supplier
More informationhigh-level radioactive waste in Korea include Law No "Nuclear Safety Act", Nuclear Safety Commission Regulation No. 14 "Rules on Technical Stan
Strategic and Technical Aspects in RD&D Program Development for HLW Disposal System in Korea JeongHyoun Yoon*, JeongHwan Lee and SeungHyun Kim Radioactive Waste Disposal R&D Department, Korea Radioactive
More informationLife Extension of Russian Nuclear Power Plants
Position Paper, October 2006 Life Extension of Russian Nuclear Power Plants Alexander Nikitin Igor Kudrik www.bellona.org Executive summary Russia is actively implementing a programme to extend the lifetime
More informationBCUC INQUIRY RESPECTING SITE C A-26
Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 November 16, 2017 BCUC
More informationCoastal Consumption of Off-Shore Wind Energy: Simulation and Optimization. Masterarbeit. vorgelegt von
Coastal Consumption of Off-Shore Wind Energy: Simulation and Optimization Masterarbeit zur Erlangung des akademischen Grades Master of Science (M.Sc.) im Studiengang Wirtschaftsingenieur der Fakultät für
More informationVATTENFALL FOR A FOSSIL FREE FUTURE Vattenfall AB Group Presentation 2017
VATTENFALL FOR A FOSSIL FREE FUTURE Vattenfall AB Group Presentation 2017 WE POWER CLIMATE SMARTER LIVING We will help power our customers to live free from fossil fuels within one generation 2 VATTENFALL
More informationCost Reduction Studies
Cost Reduction Studies (Trade Off Studies) peter@economicevaluation.com.au Version 1; July 2014 1 Level 3: Decision making Use your model to assess cost reduction ideas Level 2: Evaluating the business/project
More informationAmy Myers Jaffe Executive Director Energy and Sustainability University of California - DAVIS. Outlook for Global Oil Markets
Amy Myers Jaffe Executive Director Energy and Sustainability University of California - DAVIS Outlook for Global Oil Markets Cycle unlikely to progress in exactly the same manner as past cycles as it reflects
More informationYOUR CERTIFICATION PROCESS EXPLAINED
ISO 22000 FOOD SAFETY MANAGEMENT SYSTEMS FSSC 22000 FOOD SAFETY SYSTEM CERTIFICATION This document outlines the audit process for the above referenced standard. It outlines the stages to audit and gives
More informationOverview: energy yield simulations and calculation of LCOE for bifacial PV systems
Overview: energy yield simulations and calculation of LCOE for bifacial PV systems J.Libal, D. Berrian, R. Kopecek International Solar Energy Research Center (ISC), Konstanz, GERMANY Bifacial economics
More informationHard Issues To Consider in Business Valuation Engagements. Texas Society of Certified Public Accountants 27 th Annual CPE Tax Expo January 10, 2017
Hard Issues To Consider in Business Valuation Engagements Texas Society of Certified Public Accountants 27 th Annual CPE Tax Expo January 10, 2017 Presented by: J. Richard Claywell, CPA, ABV, ASA, CBA,
More informationECONOMY EFFICIENCY FOR RENEWABLE ENERGY SOURCES IN GREECE
ECONOMY EFFICIENCY FOR RENEWABLE SOURCES IN GREECE Electrical Engineering, PhD, Economist Tel.: +361 453738 Fax: +361 461826 e - mail: branchdk@hol.gr ABSTRACT Energy is one of the most valuable social
More information