I-SEM Business Liaison Group (BLG) NEMO. 21 st June 2017 Minutes & Notes
|
|
- Kellie Mercy Clarke
- 6 years ago
- Views:
Transcription
1 I-SEM Business Liaison Group (NEMO) 21 st June 2017 Minutes & Notes Meeting Details Meeting Purpose Location Chair Secretariat I-SEM Business Liaison Group (BLG) NEMO EirGrid, Dublin / Lync Mark Needham(I-SEM ) Louise Dalton (I-SEM ) Date 21 June 2017 Key Notes 1 & Decisions Peter Carruthers provided an update on the Implementation Project. A question was raised as to when the testing environment will be available to participants. Proposed changes to the interim IDA design were confirmed, following extensive discussion with GB NEMOs. Key changes include: o IDA1 gate closure at 17:30 rather than 15:30 o IDA3 to operate as a local auction rather than a regionally coupled auction for go live, with extension of IDA3 to include regional coupling to be based upon liquidity and market experience post go-live. A Change Request (JCR287) will be released for the IDA1 gate closure change and a Day-2 deferral request prepared for the IDA3 local auction change. A question was asked as to how long it will take for the intraday auction to clear. Answer: It will take approximately 45 minutes to clear, it is a full Euphemia auction and there are a number of procedures and checks to complete as it is a coupled auction. It was noted that these procedures, rather than any other aspect of the auction, which were the primary driver for the timeframe and were needed to manage the multiple parties involved in a coupled auctions (i.e. TSOs and NEMOs) 1 Additional to those covered in the meeting slide pack Page 1 of 7
2 A suggestion was raised that the UK intraday afternoon auction be moved to 15:00 from 15:30, clarification was given that EPEX were not supportive and there would need to be a consultation with GB market participants. It was suggested that the 17:30 auction might be brought forward to 14:00; however, clarification was given that there would have been difficulty in getting GB NEMO support for coupling due to the short window between 14:00 and 15:30, also the short window from 11:00 to the proposed new timeslot of 14:00 would potentially cause difficulties in adjusting for wind changes etc. A concern was raised that if the 15:30 GB auction satisfies GB participants, there is a risk that GB participants then simply won t turn up to the 17:30 auction, meaning the auction will be crossborder in theory but not in practice. It was noted that there is a risk to liquidity in establishing any new market and that SEMOpx had explored numerous options and feel that 17:30 will be the best option to provide agreement on the cross border elements as well as liquidity. Nordpool intend to introduce a regional intraday auction to GB at 14:30, the possibility of coupling to this rather than the 17:30 was brought up, however there is no liquidity in this auction and a too-short window from the 11:00 auction. A question was raised as to whether participants can register for the capacity market in order to meet registration deadlines and then not participate variable operators may not be sure of what they want to do until after the REFIT decision is published. Answer: variable generators are not obliged to take part in the capacity market and may opt not to register. For those who register, they will be obliged to take part in the auction at their qualified amount. Question: What is the maximum clip size for a block order? Answer: The final conditons for products will only be set after the successful completion of the PCR testing process. However, the current limit in other EPEX markets is 600 MW. Question: What is the back-up if SEMOpx market fails testing? Answer: This is a risk that needs to be managed by building a strategy that we are confident will pass. This will include as many tests as are appropriate to provide this confidence. SEMOpx noted that the primary concern at this point is addressing the underlying challenges in the testing process and that is the primary driver for the new strategy. Question: Can it be confirmed that without the advocacy route being successful, is it true that results of IAT3 testing shows that even the minimum product set would not be successful? Page 2 of 7
3 Answer: Until the advocacy route is fully explored, it is unclear what the test conditions will be. IAT3 indicated that the preferred option would not pass testing under the current conditions. However, IAT3 was not a test of the minimum approach and so we are not clear on whether this would pass. The minimum product set is proposed as simple and complex orders for go-live, with block orders to be implemented as soon as practicable afterwards. This approach is proposed as it provides participant certainty in relation to the products available for go live, provides functionality that is expected to be sufficient to enable the market to go live, and lowers the risk in relation to PCR approvals. Question: If version of Euphemia will not be available until Q1 and then during the testing product types may be changed on offering, what is impact on Market Trial e.g. if we start Market Trial with a minimum product types and then change based on PCR feedback will the Market Trial need to be reset and repeated? Answer: No, we will not be resetting Market Trial. It has been noted as a project risk that the PCR test will occur during market trial and that the uncertainty of the results may have caused a need for changes. SEMOpx have addressed this uncertainty by confirming the minimum approach of complex and simple order only for the DAM and committing to deliver at least this. It was pointed out that external factors can impact on the testing process and we cannot just rely on the testing process; we need external advocacy and the prioristisation of allocation process (that must recognise legislative implementation dates rather than the current first-come, first-served process). The consequence of us failing the PCR approval process will mean the SEM cannot couple with the European market, this argument is currently being made to the NEMO committee, who will decide of the methodology for managing changes to the day-ahead solution. While the NEMO committee will be the ultimate decision makers, due to their technical expertise, it is possible that the PCR group may feed into the NEMO committee (which is Europe wide) position if asked to do so. The RAs, through their role in ACER, are being asked to push the agenda and SEMOpx as a member of the NEMO committee will be pushing the agenda there as well A question was raised regarding reporting, the timescale mentions REMIT reporting, does the option imply that EMIR reporting is also relevant as it s a financial trade? A question was raised regarding C94A is the de-rating value going to come in the auction information pack in July? Answer: the information pack will contain tables outlining the de-rating factors for the various technologies. Participants will need to use these to determine the specific de-rating factor applicable to their unit. A question was asked regarding C94 and c92 forms will the updated forms be released with the Page 3 of 7
4 auction pack in July? [awaiting clarification on this. Either the forms or the pack will need to be updated and it is under discussion as to which will be done] Some participants have had difficulties with the LMS- only one module (Road to ISEM) appears to be working at present. This is being worked on, the training team is in contact with the LMS provider as a small amount of particpants have had a similar issues. During the Market Trial Update it was emphasised that the ideal nominee is a programme manager or someone with experience of a market trial. A question was raised regarding the relationship between a unit and balancing market entering into a breach status and triggering a trading halt. In this case, can the entity on the exchange sever ties? Answer: it was confirmed that in all cases, an entity may sever ties with a unit on the exchange as a change to their registration data. As regards timing, this will be subject to a registration process which is not yet defined but may take a number of working days to complete. The trading halt will be put in place following the expiration of the response period defined in the trading and settlement code. This response period is subject to RA consultation currently. Clarification was sought regarding product types on the continuous exchange will the products be in line with IFA blocks on the UK market. Answer: the pre-defined blocks for the continuous market are outlined in the draft SEMOpx operating procedures. These are based on the blocks used for the DAM. It will be possible to add new pre-defined blocks over time. A question was raised regarding timelines for trading and settlement code - there is no mention of the 28 July agreement date for signing in the ISEM milestone report. Answer: this date has been included in the transitional registration plan and communicated to registration contacts. The date in the level 2 milestones of 15 th of September is for the full completion of the accession process including the SEMO processing of forms. In order to complete this process on time, forms must be submitted to SEMO by the 28 th of July. Actions Action Responsibility Existing Actions From Previous Meetings Remaining Open After 21 May BLG Action 236: Action to check if there is any link back to the department regarding REFIT. Page 4 of 7
5 Action 237: Confirm with EPEX ASAP an indicative projected timeline for the 30 minute product and minimum accepted ratio. Request to provide a timeline for these changes ASAP. Action 243: Summarise what the three proposed Intraday auctions are. Action 246: RA rep to raise issue of REFIT internally and provide further information at next BLG. New actions from 21 June BLG Some participants have had difficulties with the LMS- only one module (Road to ISEM) appears to be working at present. This is being worked on, the training team is in contact with the LMS provider as a small amount of particpants have had a similar issues. Confirmation to be provided regarding C94 and c92 forms will the updated forms be released with the auction pack in July? Either the forms or the pack will need to be updated and it is under discussion as to which will be done. Clarification to be provided regarding reporting, the timescale mentions REMIT reporting, does the option imply that EMIR reporting is also relevant as it s a financial trade? Page 5 of 7
6 Appendix: Attendee List Name In Person Adam Diamond Aidan Cummins Aidan Jones Alan Reynolds Alex MacGregor Brian Mongan Catherine Joyce-O'Caollai Chloe Kinsella Darrell Thomas David Gascon David Horan Ellen Phelan Francis Mallon Glenn Hogg Gregg Allen Hugh Mullany Ian McLelland Julie-Anne Hannon Liz Kelly Louise Dalton Marie Barry Marina Petcova Mark McGarrity Mark Needhan Michael Kelleher Mike Guy Paraic Higgins Patrick O'Hagan Paul Comins Peter Carruthers Peter Grogan Philip Mc Daid Robert McCarthy Shauna Ferry Sinead O'Hare Tom Poole Company Go Power ElectroRoute ESBIE Electric Ireland DSU Brady Power NI Supply, Energia, Power NI PPB Indaver Ireland Cenergise RUSAL Aughinish ESB CUSTOMER SUPPLY _PES Viridian Interconnector Unit CRES Templederry PrePayPower Enerco Energy Bord Gais Energy ABB attending on behalf of AES ESB PGEN Bord na Mona Powergen Captured Carbon Limited Bord Gais Energy Dunmore Tynagh Energy Limited Viridian Group Gaelectric Interconnector Trading ROI Limited Budget Energy Ltd Project Plug Limited 'TA' ClickEnergy NIE Power Procurement Business Page 6 of 7
7 Adam Diamond Aidan Cummins Aidan Jones Alan Reynolds Alex MacGregor Brian Mongan Catherine Joyce-O'Caollai Chloe Kinsella Darrell Thomas David Gascon David Horan Ellen Phelan Francis Mallon Glenn Hogg Gregg Allen Hugh Mullany Ian McLelland Julie-Anne Hannon Liz Kelly Louise Dalton Go Power ElectroRoute Brady Power NI Supply, Energia, Power NI PPB Indaver Ireland Cenergise RUSAL Aughinish ESB CUSTOMER SUPPLY _PES Viridian Interconnector Unit CRES Templederry PrePayPower Enerco Energy Bord Gais Energy ABB attending on behalf of AES Page 7 of 7
I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions
I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions Meeting Details Meeting Purpose Location Chair Secretariat I-SEM Project Managers Group (PMG) EirGrid, Dublin / Conference
More informationI-SEM Business Liaison Group NEMO. 09 November2017
I-SEM Business Liaison Group NEMO 09 November2017 1 Agenda Update on NEMO Implementation Project TSO Counter trading Market Trial 2 Agenda Update on NEMO Implementation Project TSO Counter trading Market
More informationI-SEM Trialling of EUPHEMIA: Trial Plan
I-SEM Trialling of EUPHEMIA: Trial Plan 11 March 2015 CONTENTS 1 Introduction... 2 2 Final Plan... 3 2.1 Initial Phase... 3 2.2 Communication of Initial Phase Results... 3 2.3 Commercial Phase... 4 2.3.1
More informationJoint European Stakeholder Group. Tuesday 9 January 2018 Meeting 28 WebEx
Joint European Stakeholder Group Tuesday 9 January 2018 Meeting 28 WebEx Agenda ID Title Lead Time 1. Welcome & Introductions Chair 10:00-10:05 2. National Grid Update: European Network Codes Implementation
More informationSEMOpx Day-ahead Market Products Stage 2 Progress Report. March 2017
SEMOpx Day-ahead Market Products Stage 2 Progress Report March 2017 Contents 1 Introduction... 2 2 Purpose of the Document... 3 3 IAT STAGES... 4 4 Scope of IAT... 4 5 Structure of IAT... 5 5.1 Creation
More informationSEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017
SEMOpx Day-ahead Market Products Stage 3 Progress Report May 2017 Contents 1 Introduction... 3 2 Purpose of the Document... 4 3 IAT STAGES... 4 4 Scope of IAT... 6 5 Structure of IAT... 6 5.1 Creation
More informationI-SEM Milestones. November 2017
I-SEM Milestones November 2017 1 1.1 Milestone Descriptions Includes update since the approval of JCR 170 Ref Milestone & Description RA / TSO Baseline Date 1 2 3 4 5 6 7a 7b 7c Start Balancing Market
More informationBalancing Registration Data User Guide
Balancing Registration Data User Guide 29 th March 2017 Version 1.2 EirGrid 2016. Commercial In Confidence. Revision History Summary of Changes Version Revised By Initial Publication 1.0 I-SEM Project
More informationJoint European Stakeholder Group. Monday 25 th May 2017: Meeting 21 Elexon, London
Joint European Stakeholder Group Monday 25 th May 2017: Meeting 21 Elexon, London 1. Welcome & Introductions Barbra Vest Independent Chair 2. Interconnector projects update Caroline Kluyver and John Greasley
More information20 August Introduction
DECC-Ofgem stakeholder prioritisation session: Proposal for a Regulation establishing a Guideline on Capacity Allocation and Congestion Management (CACM) Introduction 20 August 2014 Following the meeting
More informationI-SEM. Integrated Single Electricity Market. Energy Portfolio Management solutions.
I-SEM Integrated Single Electricity Market. Energy Portfolio Management solutions. Why ABB? I-SEM Integrated Single Electricity Market. When choosing any vendor, Bord Gáis Energy looks for a company with
More informationRegulatory Authority Annual Report. Market Operator Performance
Regulatory Authority Annual Report Market Operator Performance Period: 1st October 2015 to 30th September 2016 Table of Contents 1 INTRODUCTION... 3 2 MANAGE CHANGE... 4 2.1 IT CAPITAL EXPENDITURE... 4
More informationJohn Bracken, Aileen Greaves & Paul Mallon Gerry Halligan. Stevie Donnelly, Gillian Kinsella, Mark Speers. Eamonn Murtagh, David Gascon
Date: 28 th September 2016 Time & Location 3pm - Conference Call Chair: David Walshe, RMDS Attendees: Name Location Jessica Gregory, Alice Mooney, Tracy Caffrey, Catherine Keane, Jim Mahony RMDS John Bracken,
More informationMarket Trial Working Group I-SEM Project
Market Trial Working Group I-SEM Project Dublin, 31 August 2017 1 Overview of the Session Meeting Details Meeting Purpose Chair Secretariat I-SEM Market Trial Working Group Mark Needham Louise Dalton Amy
More informationQuick Guide to the I-SEM
Quick Guide to the I-SEM 1 Contents 1 BACKGROUND... 3 2 THE NEW MARKET THE I-SEM... 6 3 HOW I-SEM WORKS... 7 4 IMPACT ON CONSUMERS... 9 5 I-SEM KEY BENEFITS... 10 Glossary of Key Terms... 11 2 1 BACKGROUND
More informationI-SEM Interconnectors Project
Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Initial Trial Report VERSION: 1.0 STATUS: Final for Publication DATE: 29 th SEPTEMBER 2017 Contents Introduction... 3 Objectives
More informationCarl Murphy, Alice Mooney, David Walshe, Catherine Keane. Alan Keegan, Fergus O Toole. John Bracken, Aileen Greaves, Jim Long
Date: 4 th April 2018 Time & Location 3pm - Conference Call Chair: Alan Keegan, CRU Attendees: Name Location Carl Murphy, Alice Mooney, David Walshe, Catherine Keane Alan Keegan, Fergus O Toole John Bracken,
More informationPerformance Monitoring Workshop. 6 th June Belfast 11 th June Dublin
Performance Monitoring Workshop 6 th June 2013 - Belfast 11 th June 2013 - Dublin Opening Remarks Anne Trotter # Topic Time Presenter Registeration 10:00-1 Opening Remarks 10:15 Anne Trotter (Chair) 2
More informationRole of PXs in coupling the markets & NEMO function. Arnold WEISS Head of Vienna Office EPEX SPOT SE
Role of PXs in coupling the markets & NEMO function Arnold WEISS Head of Vienna Office EPEX SPOT SE Energy Community Secretariat Energy Community Secretariat AGENDA I. European Day-Ahead Market Coupling
More informationChapter 2: Inputs. Chapter 3: Inputs
Chapter 2: Inputs Chapter 3: Inputs 1 Foreword (1/2) This section describes the data inputs to the scheduling and dispatch process including the source of the data and how it is used. There are thousands
More informationPÖYRY S VIEW ON MAIN ISSUES FOR PHASE II OF THE REVIEW OF THE SEM HLD 14 October 2013 Gary Keane
PÖYRY S VIEW ON MAIN ISSUES FOR PHASE II OF THE REVIEW OF THE SEM HLD 14 October 2013 Gary Keane The wider policy context for the Market Integration project is complicated and continues to change We have
More information3 rd EU Stakeholder Committee Meeting
3 rd EU Stakeholder Committee Meeting 03.02.2016 Content 1. Project Progress Key Achievements Challenges 2. Project Timeline 3. Local Implementation Projects and update on Belgian Borders Quick Wins 4.
More information27 October Allegato A
All TSOs proposal for the day-ahead firmness deadline (DAFD) in accordance with Article 69 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and
More informationLFC Block Operational Agreement Ireland and Northern Ireland
LFC Block Operational Agreement Ireland and Northern Ireland For Publication; 05/10/2018 Notice This document, provided by EirGrid and SONI, is the draft for stakeholder consultation of the proposal for
More informationI-SEM Trialing of EUPHEMIA: Initial Phase Results Overview. I-SEM EUPHEMIA Working Group 16 th April 2015
I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview I-SEM EUPHEMIA Working Group 16 th April 2015 EUPHEMIA Workshop Agenda Background of EUPHEMIA algorithm Overview of background and goal of EUPHEMIA
More informationPage 2 of 11. Date: 27 th June 2018 Time & Location 10:30 11:30 UR Offices, Belfast
Meeting Minutes Date: 27 th June 2018 Time & Location 10:30 11:30 UR Offices, Belfast Chair: Fergus O Toole, CRU Attendees: Name Location Carl Murphy, Alice Mooney, Tracy Caffrey RMDS Fergus O Toole CRU
More informationGreen Source Product Verification Report 2017
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Green Source Product Verification Report 2017 Information Paper Reference: CRU18204 Date Published: 14/09/2018 Closing Date: N/A www.cru.ie
More informationJoint European Stakeholder Group. Monday 25 th May 2017: Meeting 21 Elexon, London
Joint European Stakeholder Group Monday 25 th May 2017: Meeting 21 Elexon, London 1. Welcome & Introductions Barbra Vest Independent Chair 2. Interconnector projects update Caroline Kluyver and John Greasley
More informationExplanatory document to the proposal for the establishment of fallback procedures for Capacity Calculation Region Hansa in accordance with Article 44
Explanatory document to the proposal for the establishment of fallback procedures for Capacity Calculation Region Hansa in accordance with Article 44 of the Commission Regulation (EU) 2015/1222 of 24 July
More informationI-SEM Interconnectors Project
Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Trial and Participant Test Plan VERSION: 1.1 STATUS: Final for Publication DATE: 17 th JULY 2017 Contents Introduction...
More informationREPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN
REPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN 2016-2026 Table of Contents Abbreviations... 3 Glossary... 4 Introduction... 5 Description of Consultation Process... 5 Purpose of the Transmission
More informationExplanatory document concerning the Nordic TSOs proposal for arrangements concerning more than one NEMO in a bidding zone in accordance
Explanatory document concerning the Nordic TSOs proposal for arrangements concerning more than one NEMO in a bidding zone in accordance with Article 45 and 57 of the Commission Regulation (EU) 2015/1222
More informationDavid Maguire Irish Solar Energy Association Mike Quinn Bord na Móna Lisa Ryan, UCD Energy Institute Garry Connolly , Host in Ireland Jim Gannon
SPONSORS HOSTED BY SUPPORTERS CONFIRMED SPEAKERS David Maguire, Director, Irish Solar Energy Association Mike Quinn, CEO, Bord na Móna Lisa Ryan, Assistant Professor in Energy Economics, UCD Energy Institute
More informationBalancing Market Principles Statement
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 2.0 11 th April 2018 Version Control Version No. Date Notes 1.0
More informationGIE answer to EC s stakeholder consultation on the implementation of a data and transaction reporting framework for wholesale energy markets
Ref: 12GIE131 November 2012 GIE answer to EC s stakeholder consultation on the implementation of a data and transaction reporting framework for wholesale energy markets Introduction: Gas Infrastructure
More informationRegulatory Authority Annual Report. Market Operator Performance
Regulatory Authority Annual Report Market Operator Performance Period: 1st October 2013 to 30th September 2014 Table of Contents 1 INTRODUCTION... 3 2 MANAGE CHANGE... 4 2.1 IT CAPITAL EXPENDITURE 2010-2013...
More information17/02/2017 Implementation of CACM Guideline
Implementation of CACM Guideline 1 Implementation of CACM Guideline IEWT 2016 17 February 2017 Implementation of CACM Guideline 2 Where we come from Fragmented market landscape Voluntary ERI-process Status
More informationContent. Introduction. Amendments. Amendment to Article 5.1 on pre-coupling arrangements for single dayahead
Explanatory document concerning the Nordic TSOs request for amendments in accordance with Article 9(13) of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline on Capacity
More informationStakeholder Engagement Plan for the Distribution System Security and Planning Standards Review Project
- Stakeholder Engagement Plan for the Distribution System Security and Planning Standards Review Project Issuing Authority: Content Owner: Asset Management Ivan Codd Document Number: N/A Version: Rev No.1.0
More information11/02/2016. The Scheduling & Dispatch Process in I-SEM - Design Interpretation
11/02/2016 The Scheduling & Dispatch Process in I-SEM - Design Interpretation Release Date Version No. Summary of Changes 11/02/2016 1.0 Design Interpretation document published for discussion at Market
More informationReverse Charge Gas, Electricity, Gas and Electricity Certificates
Reverse Charge Gas, Electricity, Gas and Electricity Certificates This document should be read in conjunction with section 16(6) and 16(7) of the Value-Added Tax Consolidation Act 2010 (VATCA 2010) Document
More informationI-SEM Small Wind Information Session. 24 November 2016
I-SEM Small Wind Information Session 24 November 2016 1 Agenda 1. I-SEM Market Overview 2. I-SEM Registration Overview 3. Market Readiness Update 4. Market Trial Update 5. Systems Overview 6. AOB 2 Power
More informationAll NEMOs proposal for the back-up methodology in accordance with Article 36(3) of the Commission Regulation (EU) 2015/1222 of 24 July 2015
All NEMOs proposal for the back-up methodology in accordance with Article 36(3) of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and congestion
More informationBord Gáis Energy s Response to the Commission for Regulation of Utilities Proposed Decision on an Enduring Connection Policy Stage 1 (ECP-1)
Bord Gáis Energy s Response to the Commission for Regulation of Utilities Proposed Decision on an Enduring Connection Policy Stage 1 (ECP-1) 15th December 2017 At a principled level, the proposals set
More informationMinutes. Project Title. XBID Market. Title of Meeting. 4 th User Group Meeting. Date / Place. 29/06/16, 10:00 16:00 CET, Brussels
Minutes Project Title Title of Meeting Date / Place XBID Market 4 th User Group Meeting 29/06/16, 10:00 16:00 CET, Brussels Status Version Date Comment Draft 1 29/06/16 Draft provided to PP for review
More informationJoint European Stakeholder Group. Thursday 21 September 2017 Meeting 24 WebEx
Joint European Stakeholder Group Thursday 21 September 2017 Meeting 24 WebEx Agenda ID Title Lead Time 1 Welcome & Introductions Chair 10:00-10:05 2 CACM Methodologies, Inc. Recent Submission of the Capacity
More informationReverse Charge Gas, Electricity, Gas and Electricity Certificates
Reverse Charge Gas, Electricity, Gas and Electricity Certificates This document should be read in conjunction with section 16 of the VAT Consolidation Act 2010 (VATCA 2010) Document last Reviewed October
More informationJoint European Stakeholder Group. Wednesday 23 August 2017 Meeting 23 WebEx
Joint European Stakeholder Group Wednesday 23 August 2017 Meeting 23 WebEx Agenda ID Title Lead Time 1 Welcome & Introductions Chair 10:00-10:10 2 CACM Day ahead and intraday capacity calculation methodology
More information(Non-legislative acts) REGULATIONS
15.6.2013 Official Journal of the European Union L 163/1 II (Non-legislative acts) REGULATIONS COMMISSION REGULATION (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity
More informationDirected Contracts Implementation
Integrated Single Electricity Market (I-SEM) Directed Contracts Implementation Decision Paper SEM-17-081 15 th November 2017 Table of Contents Acronyms... 3 1. Introduction... 4 1.1 Background... 4 2.
More informationEuropean Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1.
European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1.1) Agenda Item Approximate start time Welcome: Tea and coffee 09:30
More informationREQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON
REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON ALL NEMO s PROPOSAL FOR BACK-UP METHODOLOGY SUBMITTED IN ACCORDANCE WITH ARTICLE 36(3) OF THE COMMISSION REGULATION
More informationBalancing Market Principles Statement
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 1.0 8 September 2017 Version Control Version No. Date Notes 1.0
More informationDS3 System Services Project Plan Detailed Design and Implementation Phase
DS3 System Services Project Plan Detailed Design and Implementation Phase Dated: 20/5/2015 Executive Summary The System Services work stream within the DS3 Programme relates to the procurement of services
More informationRate of Change of Frequency (RoCoF) Project Quarterly Report for Q3 2015
Rate of Change of Frequency (RoCoF) Project Quarterly Report for Q3 2015 DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Information Note CER/15/257 30 th October 2015 mvencius@cer.ie The Commission
More informationAll TSOs proposal for the day-ahead firmness deadline (DAFD) in accordance with Article 69 of
All TSOs proposal for the day-ahead firmness deadline (DAFD) in accordance with Article 69 of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and
More informationChange Control Process for the Co-Ordinated Retail Electricity Markets
Change Control Process for the Co-Ordinated Retail Electricity Markets Version 4.0 Issue Date October 2014 Version 4.0 Page 1 of 24 Date Version Reason For Change 14.12.09 Draft 0.1 Draft process to govern
More informationRate of Change of Frequency (RoCoF) Project Quarterly Report for Q4 2015
Rate of Change of Frequency (RoCoF) Project Quarterly Report for Q4 2015 DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Information Note CER/16/006 19 th January 2016 mvencius@cer.ie The Commission
More informationC O N N E C T I N G F U R T H E R G E N E R A T I O N I N N O R T H E R N I R E L A N D Next Steps Paper 29th June 2018
CONNECTING FURTHER GENERATION IN NORTHE RN IRELAND Next Steps Paper 29 th June 2018 Contents 1. Introduction... 3 2. Imminent Process Modifications... 4 2.1 Transmission Process SONI Connection Policy...
More informationIWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015
IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015 By e-mail to: ress@dcenr.gov.ie Introduction IWEA welcomes the opportunity to respond to the
More informationInterim Governance Arrangements for All Island Retail Market Harmonisation Project
Interim Governance Arrangements for All Island Retail Market Harmonisation Project Document Revision History Version Date Summary of Change Author Number 2 21 Oct 2009 First draft for review Various 3
More informationIntra-Day Trading Project. Market Participant Technical Overview. Conference call number: , pin: 79592
Intra-Day Trading Project Market Participant Technical Overview 3 rd August 2011, 10.30 am 13:00 pm Conference call number: 00353 1 6647777, pin: 79592 Welcome Welcome to this information session on the
More informationGuidelines on Appointments to State Boards Department of Public Expenditure and Reform, November 2014
Guidelines on Appointments to State Boards Department of Public Expenditure and Reform, November 2014 Introduction and Context 1. Background 1.1 In 2011 the Government introduced new arrangements for appointments
More informationConsultation report for the Channel CC Methodology proposal
Consultation report for the Channel CC Methodology proposal September 15 th, 2017 Disclaimer This assessment of stakeholders comments is submitted by all TSOs of the Channel Region to all NRAs of the Channel
More informationBusiness Process. BP_SO_4.2 Demand Forecasting for Scheduling & Dispatch
Business Process BP_SO_4.2 Demand Forecasting for Scheduling & Dispatch EirGrid and SONI support the provision of information to the marketplace by publishing operational data, processes, methodologies
More informationNORDENERGI SECRETARIAT
Your ref. Our ref. CHS ERGEG Electricity_transparency@ergeg.org Copenhagen, October 28, 2010 Nordenergi response to ERGEG consultation on draft Comitology Guideline on Fundamental Electricity Data Transparency
More informationRegulatory Approach to Maintaining Local Security of Supply in Electricity
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Regulatory Approach to Maintaining Local Security of Supply in Electricity Information Paper Reference: CRU17346 Date Published: 18/12/2017
More informationCROSS-BORDER CAPACITY RESERVATION. BSG Meeting Brussels, June 30 th, Rationale, options and challenges
CROSS-BORDER CAPACITY RESERVATION Rationale, options and challenges BSG Meeting Brussels, June 30 th, 2016 AGENDA 1. Starting Point: The EB GL and the rational for XB Capacity reservation 2. The Methods:
More informationConsultation Paper Contents Introduction Network Capacity and Operational Capability... 6
CONSULTATION ON CONNECTING FURTHER GENERATION I N NORTHERN IRELAND CONSULTATION PAPER 31 st January 2018 1. CONTENTS Consultation Paper... 1 1. Contents... 2 2. Introduction... 4 3. Network Capacity and
More information1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:
1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call
More informationAlternative Connection Application and Offer Process Proposal
Alternative Connection Application and Offer Process Proposal Consultation Paper 4 March 2016 Table of Contents 1. Executive Summary... 5 2. Introduction... 7 2.1 Purpose of this Paper... 7 2.2 Structure
More informationJoint European Stakeholder Group. Tuesday 13 March 2018 Meeting 30 London
Joint European Stakeholder Group Tuesday 13 March 2018 Meeting 30 London Agenda ID Title Lead Time 1. Welcome & Introductions Chair 10:00-10:05 2. BREXIT Scenarios Discussion 3. National Grid Update: 4.
More informationNational Energy Guarantee Draft Detailed Design Consultation Paper. Engineers Australia Submission
National Energy Guarantee Draft Detailed Design Consultation Paper Engineers Australia Submission 13 July 2018 Contact Details: Mark Stewart, Senior Policy Advisor Engineers Australia 11 National Circuit,
More informationAttendees Name Initials Company Caroline Wright CW Chair, National Grid (NGET) Lurrentia Walker
Minutes Meeting name STC Modification Panel Meeting Meeting number 146 Date of meeting Wednesday 26 April 2017 Time 10:00am 12:00pm Location G2-03, National Grid House, Warwick and teleconference Attendees
More informationNordREG hearing on TSO s & DSO s roles for enabling energy services
NordREG hearing on TSO s & DSO s roles for enabling energy services Preliminary reflections on presented reports and on (related) matters to consider Rickard Nilsson Senior Adviser Innovation & Market
More informationAnnual Audit of Compliance for Electricity & Gas Suppliers 2017
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Annual Audit of Compliance for Electricity & Gas Suppliers 2017 Information Paper Reference: CRU17355 Date Published: 20/12/2017 0
More informationHarmonised Other System Charges 2014/2015. Recommendations Paper
Harmonised Other System Charges 2014/2015 Recommendations Paper 9 th July 2014 Other System Charges 2014/2015 Recommendations 1. EXECUTIVE SUMMARY For the upcoming tariff period running from the 1st October
More informationGerry Halligan. Siobhan Melvin, Adrienne Costello. Stevie Donnelly, Gillian Kinsella. Adam Diamond, Catriona Barclay
Date: 29 th June 2016 Time & Location 12:45 15:45 UR Offices, Belfast Chair: D Paraschiv, CER Attendees: Name Location Jessica Gregory, Alice Mooney RMDS D Paraschiv, P Stack CER John Bracken, James Long,
More informationProposal for a common set of requirements used for the continuous trading matching algorithm
Proposal for a common set of requirements used for the continuous trading matching algorithm 13 November 2017 1. Background 1. This document is a common proposal developed by all Transmission System Operators
More informationESBCS Domestic Micro-generator Export Tariff Decision Paper
ESBCS Domestic Micro-generator Export Tariff Decision Paper DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/09/033 18 th February2008 degan@cer.ie The Commission for Energy Regulation,
More informationDS3 Rate of Change of Frequency Modification Recommendation to the CER
DS3 Rate of Change of Frequency Modification Recommendation to the CER Dated: 20/12/2012 1 P a g e Introduction The TSOs EirGrid and SONI are jointly recommending that the proposed RoCoF modification be
More informationGREECE-ITALY MARKET COUPLING: IMPACTS AND OPPORTUNITIES FOR POWER TRADERS
GREECE-ITALY MARKET COUPLING: IMPACTS AND OPPORTUNITIES FOR POWER TRADERS 10th of May 2018 PHINERGY SRLS WHO S PHINERGY WHAT WE DO Phinergy was born in 2014 from the experience of its founders Stefano
More informationInstitutional Arrangements for Virtual Reverse Flow at Moffat
Institutional Arrangements for Virtual Reverse Flow at Moffat DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: FURTHER INFORMATION: Decision Paper CER/11/113 4 th July 2011 cjohnston@cer.ie The Commission for
More informationBusiness Process. BP_SO_12.1 Unit Testing
Business Process BP_SO_12.1 Unit Testing EirGrid and SONI support the provision of information to the marketplace by publishing operational data, processes, methodologies and reports. This information
More informationRetail Market Co-Ordination Working Group
Date: 2 nd November 2016 Time & Location 12:45 13:45 - Belfast Chair: Jessica Gregory - ReMCoDS Attendees: Name Location Alice Mooney, David Walshe ReMCoDS Dana Paraschiv, Gina Kelly, CER Aileen Greaves,
More informationConsultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project
Consultation on DS3 System Services Contracts for Interim Arrangements DS3 System Services Implementation Project 21 April 2016 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,
More informationESB Generation & Wholesale Markets Response to:
ESB Generation & Wholesale Markets Response to: DS3: System Services Consultation Finance Arrangements February 13 th 2013 Part One: Introduction ESB Generation and Wholesale Markets (ESB GWM) welcome
More informationREQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM
REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON THE ALL TSO PROPOSAL FOR COMMON GRID MODEL METHODOLOGY (CGMM) 13 December 2016 1 I. Introduction and legal context
More informationConsultation on Connecting Further Generation in Northern Ireland. Call for Evidence
Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection
More informationI-SEM Project Managers Group. 24 April 2018
I-SEM Project Managers Group 24 April 2018 1 Focus of the Meeting As normal, first we ll summarise the Project Status and consider the key readiness indicators, notably the central systems defects. That
More informationRate of Change of Frequency (RoCoF) project Six Monthly Report for November 2016
Rate of Change of Frequency (RoCoF) project Six Monthly Report for November 2016 Document identifier: Authored by: Tom McCartan (Tom.Mccartan@soni.ltd.uk) Document version: 1 Checked by: N Watson Date
More informationIGG Agenda. Minutes from Previous IGG Meeting 10:15 10:20 Review of Action Items 10:20 10:40 CER Update 10:40 11:00. Gemserv Update 11:00 11:10
IGG Agenda Minutes from Previous IGG Meeting 10:15 10:20 Review of Action Items 10:20 10:40 CER Update 10:40 11:00 Gemserv Update 11:00 11:10 MRSO Update 11:10 11:20 ESB Networks Update 11:20 11:45 Retail
More informationMarket Operator User Group. Dublin, 22 November 2018
Market Operator User Group Dublin, 22 November 2018 1 Agenda Item Welcome Ex-Ante Market Balancing Market Disputes, Repricing and Resettlement Update Settlements & Funds Transfer Known Issues Update Query
More informationWhereas. (2) This Proposal takes into account the general principles, goals and other methodologies set in EBGL.
TSOs proposal for the establishment of common and harmonised rules and processes for the exchange and procurement of Balancing Capacity for Frequency Containment Reserves (FCR) in accordance with Article
More informationEuropean Update. 2nd July 2015
European Update Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. 2nd July 2015 1. General Update
More informationIEA Electricity Security Advisory Panel: Integrating new technologies while maintaining resource adequacy
IEA Electricity Security Advisory Panel: Integrating new technologies while maintaining resource adequacy The role of interconnectors in GB adequacy planning Steven Becker 28/09/2015 Overview Introduction
More informationEUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT. Programme for Supporting Renewable Energy in Ukraine
EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT TERMS OF REFERENCE Programme for Supporting Renewable Energy in Ukraine Support to the Entity responsible for target setting The Programme for Supporting
More informationConnection and Use of System Code (CUSC), Balancing and Settlement Code (BSC) & Grid Code
Stage 03: Workgroup Connection and Use of System Code (CUSC), Balancing and Settlement Code (BSC) & Grid Code CMP191 & P271: NETSO Consultation in relation to any potential changes to the BSC/CUSC which
More informationChapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process
Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process 1 Foreword Our scheduling and dispatch process incorporates a range of activities associated with managing the close to real-time
More informationMARKET PROCESS DESIGN. Retail Market Release Prioritisation Process
MARKET PROCESS DESIGN TABLE OF CONTENTS TABLE OF CONTENTS... 2 INTRODUCTION... 3 SCOPE... 3 HISTORY OF CHANGES... 3 REFERENCE DOCUMENTS... 4 BACKGROUND... 4 DESIGN PRINCIPLES... 4 PROCESS MAPS... 5 PROCESS
More information