I-SEM Project Managers Group. 24 April 2018

Size: px
Start display at page:

Download "I-SEM Project Managers Group. 24 April 2018"

Transcription

1 I-SEM Project Managers Group 24 April

2 Focus of the Meeting As normal, first we ll summarise the Project Status and consider the key readiness indicators, notably the central systems defects. That will provide the backdrop to consider JCR362, which sets out the Level 2 Milestones to the new Go-Live Date of 1 October The focus will be on the JCR, to explain the background the proposed dates and to consider how we shape the detailed plan beneath the Level 2 Milestones to work for us all. 2

3 Agenda 1. Previous Meeting Notes & Actions 2. Project Status & Key Risks 3. Readiness & Market Trial 4. JCR AOB 3

4 Previous Meeting Minutes & Actions I # Action Resolution Status 301 Consider the forum for discussion of Day 2 Issues and add to a future agenda of the PMG 337 Issue Market Readiness Assessment Survey, week commencing 26 March Keep action open until time allows to discuss on PMG agenda. Survey issued end of March; MRA Report to be published 24 April. Survey inputs were fed into the JPB/SEMC go-live date deliberations. Open Closed 338 Publish additional details on defects affecting the Market Trial. Defect reporting revised; additional details has now been provided over the past month and will continue to be issued going forward on a weekly basis. Closed 4

5 Previous Meeting Minutes & Actions II # Action Resolution Status 339 Publish and keep updated details on market reports that are working or are not working in Market Trial Report improved and published. Closed 340 Organise an additional meeting of the PMG for week commencing 26 March Meeting took place 29/03/2018, plus an additional meeting on 12/04/2018. Closed 341 Consider how to give insight and confidence into the progress of the Balancing Market certification in advance of the 8 May 2018 certification being completed. 342 Schedule a PMG meeting during the impact assessment window for JCR362 (to move the go-live date and update the outstanding Level 2 Milestones) No longer required, given that under the revised plan, certification is completed at least six weeks before go-live decision. Today s PMG meeting scheduled (24 April), three days before the impact assessment period ends. Closed Closed 5

6 Agenda 1. Previous Meeting Notes & Actions 2. Project Status & Key Risks 3. Readiness & Market Trial 4. JCR AOB 6

7 I-SEM Project Milestones Status Update

8 Current Progress on Milestones 2 milestones completed since 31 March 2018 PMG: TSOs #7L I-SEM Technical Specification Release 8.0 #234b I-SEM Data Publication Guide Issue 2 8

9 Current Progress on Milestones The slides which follow detail: 3 milestones currently reported as being late (red). In each case, the impacts and mitigating actions are noted All other milestones are currently reported as being on track, noting that all are not without some risk Please refer to the latest I-SEM Status Report for more details, which is published weekly on the SEMO website 9

10 Slipped Milestones Currently Red (1) #109a Effective date of ROI Generator and Supplier Licences: In response to a request by a Licence Holder to the Minister in DCCAE, an Appeals Panel was established on 10 Nov 17. It has a maximum period of six months to reach its decision. 10

11 Slipped Milestones Currently Red (2) #52 FTR Auction Commences: In light of the revised date for I- SEM Go Live and associated milestones (Refer to JCR_362) discussions are underway with the ICOs to determine revised dates for the FTR auctions. A Joint Change Request will be raised to amend the baseline date of this milestone, once revised dates have been agreed. 11

12 Slipped Milestones Currently Red (3) #215 MRC Approval: Objections were received from two parties in Great Britain identifying the outstanding decisions on foreign exchange rate and GB cost recovery as blockers. These were unexpected, as no blockers identified by the MRC JSC Members at their February meeting. Full approval from the MRC JSC could not be given until resolved. Following escalation and active negotiations, both parties withdrew their objections. MRC JSC has issued a conditional approval, awaiting confirmation from the parties that the issues have been resolved. Resolution expected at JSC meeting at end of this month. However, new I-SEM timeline introduces another dynamic and 30 April expected MRC Approval date is now considered to be at risk. 12

13 Milestones Subject to Change Requests The following Change Request was published on 20 April JCR_362: Revised I-SEM Go Live Date: Changing the baseline dates for the milestones (if approved) as follows: #9 BM Engine Certification Complete 6 Jul 2018 #86 Market Readiness Confirm Go Live 22 Aug 2018 #87 Market Trial Complete 30 Sep 2018 #250 I-SEM Go Live 01 Oct 2018 Additionally, the following new milestone will be introduced: #175 All Priority Defects Fixed/Deployed into Market Trial 1 Jun

14 Forward Look at Upcoming Milestones The following 4 TSO Level 2 Milestones are due to be completed by the end of May 18: #215 MRC Approval #119 Finalisation of SEMOpx Procedures #216 Intraday Regional & Member Test complete #217 Day Ahead MRC, Regional & Member Test complete 14

15 Forward Look at Upcoming Milestones There are no RA Level 2 Milestones due to be completed by the end of May

16 Forward Look at Upcoming Milestones The following ICO Level 2 Milestone is due to be completed by the end of May 18: #52 FTR Auctions commence However, as noted in the I-SEM Status Report and in JCR362, the baseline date will be replanned in due course in line with the revised I-SEM Go Live date. 16

17 Change Requests Approved No Change Requests have been approved since the last PMG. 17

18 Day 2 Requests No Day 2 Requests have been approved since the last PMG, and none are currently in the pipeline for consideration. The objective remains only to issue Day 2 Requests where absolutely essential to preserve the I-SEM Project timeline. 18

19 Top Risks I (not in any particular order) Suggest that we do not go through these in the meeting here, but consider them later in the agenda in relation to JCR362 and mitigating the delivery risks. Risk Mitigating Controls Trend Legislation/Licensing Delays: Risk that necessary legislation or licensing arrangements are not in place in time for Go-Live RAs on-going liaison with Departments Include relevant market readiness metrics against which to track and report progress Neutral Licence Appeal in Progress; Milestone #109a delayed. 19

20 Top Risks II Risk Mitigating Controls Trend BREXIT Impact: Risk that Government revisits I-SEM decision, or National Grid/Ofgem choose not to comply with the European Network Codes or not actively support the Target Model cross border arrangements, resulting in changes to scope, project delays, cost overruns, reduced quality, or potentially undermine I-SEM Ensure key decision makers are well informed about the benefits of market coupling Close liaison between RAs and Depts. Development of alternative models considering the impact of Brexit scenarios Up The risk has arguably increased in light of the delay to go-live. With the T-1 CM Auction run complete and Market Trial underway, the risk of a Brexit impact to go-live is likely trending down. However, the risk of a longer-term impact on the I-SEM arrangements post go-live is likely continuing to trend up. 20

21 Top Risks III Risk Mitigating Controls Trend Central System Testing / Defect Fixing: Risk that completion of Rigorous management processes for tracking Level testing / defect fixing of the vendor deliverables central systems slips, resulting in Strong hands-on those systems not being available management oversight when needed to progress Market Trial. This may result from of vendors, with robust slippages in the delivery and contractual testing of the multitude of systems (e.g. due to vendor nonperformance), arrangements Fill in as many vendor introduction of shortfalls as possible by necessary changes, volume of taking on additional defects or because of the responsibilities/work complexity in bringing together all those systems in the limited time available Plan agreed with ABB for defect fixes required for go-live; two major releases planned for April have been completed. Testing of the latest release is in progress. To support delivery to this plan, we have strengthened our vendor on-site presence and are testing defect fixes on an ongoing basis as they are completed by the vendor. 21

22 Top Risks IV Risk Mitigating Controls Trend External Dependencies - Regional Coupling & Cross Zonal Arrangements: Risk that NGET, Ofgem, GB NEMOs &/or ICOs will not deliver key elements/decisions required in a timely fashion resulting in Project delays, cost overruns, or reduced quality. Joint Steering Committee (JSC) (TSOs, NEMOs & ICOs) in place. Joint Implementation Group (JIG) (RAs, TSOs, NEMOs & ICOs) in place. Put in place framework agreements between regional partners. Agree cost sharing arrangements. Down SEM-GB Regional Coupling activities continue to progress well. Going live with a single GB NEMO for the Intraday Auctions was agreed at JSC and JIG meetings in early March. 22

23 Top Risks V Risk Mitigating Controls Trend Participant Access to Clearing Member Readiness workstream Down Bank: Risk that the clearing model may cause a barrier to entry for market participants, especially smaller participants. has been established which will be an actioned forum where issues can be discussed between NEMO and ECC. In excess of thirty Members registered and the Direct The result may be that smaller ECC implementing a direct clearing Clearing solution participants may not be able to solution for market participants. having been enter the DA and ID markets, established. with flow on consequences for Participants have managed this risk market readiness. by aggregating through intermediaries 23

24 Top Risks VI Risk Mitigating Controls Trend ABB s nmarket is not available to meet Project Timelines: Risk to progress of Market Trial, given the dependency of a large number of participants on ABB s nmarket Suite, in the event that the vendor s delivery plans slip. For individual participants to determine. Current status to be confirmed by nmarket participants at the meeting. 24

25 Top Risks VII Risk Mitigating Controls Trend Participant Readiness: Risk that Market Participants are not ready Regular market readiness assessment reporting. Regular market participant engagement. To be confirmed by participants at the meeting Participants have previously advised that this risk was trending up, given compressed timelines to finalise system development and processes, a lack of clarity regarding retail tariffs, and uncertainty on whether participants would be able to make changes to their own systems following updates to the I-SEM Technical Specification and I-SEM Data Publication Guide. In light of the revised date for go-live the current status will be confirmed by participants at the meeting. 25

26 Agenda 1. Previous Meeting Notes & Actions 2. Project Status & Key Risks 3. Readiness & Market Trial 4. JCR AOB 26

27 Readiness & Market Trial - Agenda Cut-down agenda this month, given the new Go-Live Date: a) System Defects current picture; slides follow b) Registration of Units slide follows c) Market Trial summary update to be given at the meeting; more detailed picture to be presented to MTCG this afternoon d) Participant Readiness - discussion 27

28 (a) System Defects I-SEM: Market Trial Priority Defects for Go-Live - Detailed Report Last Updated: 23 Apr

29 What s Included? This presentation details the Priority Defects for Go-Live, organised as follows: # Slide Topic Content Description 2 What s Included Describes what s included in the presentation. 3-9 Release Schedule 10 Defect Progression - Summary Planned 03-Apr / 22-Apr Baseline Comparison Summary Schedule By Vendor Release Date, Market Trial Release Date, and Audience - for the current and previous reporting periods. Defect Progression Summary - shows how defects have moved between Defect Stages since the previous report (16 April). Shows movement in defects release schedule between the 12-Mar-18 and 23-Apr-18 for defects that were planned for a 03-Apr / 22-Apr release from the system vendor Defect Impact Defect Impact Analysis for the upcoming releases Defect Details for Period: 03 Apr 2018 Defect Details for Period: 22 Apr 2018 Defect Details for Period: Release Pending Defect Details for Period: In EirGrid Testing Defect Progression - Breakdown by Type Detailed view of all Internal Priority for Go-Live defects expected to be remedied in a software release delivered to EirGrid on 02 Apr 2018 but not yet deployed to MT. Detailed view of all Market Participant-facing and Internal Priority for Go-Live defects that are expected to be remedied in a software release delivered to EirGrid on 22 Apr 2018 but not yet deployed to MT. Detailed view of all Market Participant-facing and Internal Priority for Go-Live defects that are not currently assigned an expected Release Date for delivery to EirGrid. Detailed view of all Market Participant-facing and Internal Priority for Go-Live defects that are currently in EirGrid Testing, or where test has completed successfully and is pending Market Trial deployment Defect Progression slides by Type (Market Participant Facing & Internal to TSO) - shows how defects have moved between Defect Stages since the previous report (16 April) 29

30 Release Schedule of Priority Defects for Go-Live: Summary as at 12-Mar-18 ABB to EirGrid Release Date Expected Release Date To Market Trial Market Participant Facing Defects Internal Defects Planned 03-Apr Planned 22-Apr Release Pending In EirGrid Test Total (Planned / Pending / In Test) 11-Apr 30-Apr - 19-Mar Total Defects Explanation of Headings Planned 03-Apr The total number of open defects remaining to be released to EirGrid on 03 April Planned 22-Apr The total number of open defects remaining to be released to EirGrid on 22 Apr Release Pending In EirGrid Test Total The total number of defects for which a release date has not yet been agreed between EirGrid and the vendors (continuing under discussion) The total number of defects that have been received by EirGrid and are currently undergoing test, prior to release into the Market Trial environment. The sum of the Planned, Release Pending, and In EirGrid Test values. 30

31 Release Schedule of Priority Defects for Go-Live: Summary as at 23-Mar-18 ABB to EirGrid Release Date Expected Release Date To Market Trial Market Participant Facing Defects Internal Defects Planned 03-Apr Planned 22-Apr Release Pending 11-Apr 30-Apr - In EirGrid Test Before 11-Apr Total (Planned / Pending / In Test) Total Defects Explanation of Headings Planned 03-Apr The total number of open defects remaining to be released to EirGrid on 03 April Planned 22-Apr The total number of open defects remaining to be released to EirGrid on 22 Apr Release Pending In EirGrid Test Total The total number of defects for which a release date has not yet been agreed between EirGrid and the vendors (continuing under discussion) The total number of defects that have been received by EirGrid and are currently undergoing test, prior to release into the Market Trial environment. The sum of the Planned, Release Pending, and In EirGrid Test values. - 31

32 Release Schedule of Priority Defects for Go-Live: Summary as at 30-Mar-18 ABB ABB to EirGrid to EirGrid Release Planned Planned Planned Planned Release Release Date Date 03-Apr 03-Apr 22-Apr 22-Apr Pending Test Closed Release In EirGrid Total In Test EirGrid (Pending Test Market Total (Planned / Pending / Pending Trial deployment) Expected Expected Release Release Date To 11-Apr 30-Apr Before Before - or on Before or on - Market Trial 11-Apr 30-Apr - 11-Apr - Date To Market Trial 11-Apr 11-Apr Market Participant Market Participant Facing Defects Facing Defects Internal Internal Defects Defects Total Defects Total Defects Explanation of Headings Planned 03-Apr The total number of open defects remaining to be released to EirGrid on 03 April 2018 Planned 22-Apr The total number of open defects remaining to be released to EirGrid on 22 Apr 2018 Release Pending In EirGrid Test Test Closed Total The total number of defects for which a release date has not yet been agreed between EirGrid and the vendors (continuing under discussion) The total number of defects that have been received by EirGrid and are currently undergoing test, prior to release into the Market Trial environment The total number of defects that have been received by EirGrid and which have completed test and are pending deployment to the Market Trial environment The sum of the Planned, Release Pending, In EirGrid Test, and Test Closed values In Test) 32

33 Release Schedule of Priority Defects for Go-Live: Summary as at 09-Apr-18 ABB ABB to EirGrid to EirGrid Release Planned Planned Planned Planned Release Release Date Date 03-Apr 03-Apr 22-Apr 22-Apr Pending Test Closed Release In EirGrid Total In Test EirGrid (Pending Test Market Total (Planned / Pending / Pending Trial deployment) Expected Expected Release Release Date To 11-Apr 30-Apr Before Before - or on Before or on - Market Trial 11-Apr 30-Apr - 11-Apr - Date To Market Trial 11-Apr 11-Apr Market Participant Market Participant Facing Defects Facing Defects Internal Internal Defects Defects Total Defects Total Defects Explanation of Headings Planned 03-Apr The total number of open defects remaining to be released to EirGrid on 03 April 2018 Planned 22-Apr The total number of open defects remaining to be released to EirGrid on 22 Apr 2018 Release Pending In EirGrid Test Test Closed Total The total number of defects for which a release date has not yet been agreed between EirGrid and the vendors (continuing under discussion) The total number of defects that have been received by EirGrid and are currently undergoing test, prior to release into the Market Trial environment The total number of defects that have been received by EirGrid and which have completed test and are pending deployment to the Market Trial environment The sum of the Planned, Release Pending, In EirGrid Test, and Test Closed values In Test) 33

34 Release Schedule of Priority Defects for Go-Live: Summary as at 11-Apr-18 ABB ABB to EirGrid to EirGrid Release Planned Planned Planned Planned Release Release Date Date 03-Apr 03-Apr 22-Apr 22-Apr Pending Test Closed Release In EirGrid Total In Test EirGrid (Pending Test Market Total (Planned / Pending / Pending Trial deployment) Expected Expected Release Release Before Date To or on Before 11-Apr 30-Apr Before - or on Before or on - Market Trial 30-Apr - 11-Apr - Date To Market Trial 30-Apr 30-Apr 30-Apr Market Participant Market Participant Facing Defects Facing Defects Internal Internal Defects Defects Total Defects Total Defects Explanation of Headings Planned 03-Apr The total number of open defects remaining to be released to EirGrid on 03 April 2018 Planned 22-Apr The total number of open defects remaining to be released to EirGrid on 22 Apr 2018 Release Pending In EirGrid Test Test Closed Total The total number of defects for which a release date has not yet been agreed between EirGrid and the vendors (continuing under discussion) The total number of defects that have been received by EirGrid and are currently undergoing test, prior to release into the Market Trial environment The total number of defects that have been received by EirGrid and which have completed test and are pending deployment to the Market Trial environment The sum of the Planned, Release Pending, In EirGrid Test, and Test Closed values In Test) 34

35 Release Schedule of Priority Defects for Go-Live: Summary as at 16-Apr-18 ABB ABB to EirGrid to EirGrid Release Planned Planned Planned Planned Release Release Date Date 03-Apr 03-Apr 22-Apr 22-Apr Pending Test Closed Release In EirGrid Total In Test EirGrid (Pending Test Market Total (Planned / Pending / Pending Trial deployment) Expected Expected Release Release Before Date To or on Before 11-Apr 30-Apr Before - or on Before or on - Market Trial 30-Apr - 11-Apr - Date To Market Trial 30-Apr 30-Apr 30-Apr Market Participant Market Participant Facing Defects Facing Defects Internal Internal Defects Defects Total Defects Total Defects Explanation of Headings Planned 03-Apr The total number of open defects remaining to be released to EirGrid on 03 April 2018 Planned 22-Apr The total number of open defects remaining to be released to EirGrid on 22 Apr 2018 Release Pending In EirGrid Test Test Closed Total The total number of defects for which a release date has not yet been agreed between EirGrid and the vendors (continuing under discussion) The total number of defects that have been received by EirGrid and are currently undergoing test, prior to release into the Market Trial environment The total number of defects that have been received by EirGrid and which have completed test and are pending deployment to the Market Trial environment The sum of the Planned, Release Pending, In EirGrid Test, and Test Closed values In Test) 35

36 Release Schedule of Priority Defects for Go-Live: Summary as at 23-Apr-18 ABB to EirGrid Release Date Expected Release Date To Market Trial Market Participant Facing Defects Internal Defects Planned 03-Apr Before or on 30-Apr Planned 22-Apr Release Pending 30-Apr - In EirGrid Test Before or on 30-Apr Test Closed (Pending Market Trial deployment) Before or on 30-Apr Total Defects Explanation of Headings Planned 03-Apr The total number of open defects remaining to be released to EirGrid on 03 April 2018 Planned 22-Apr The total number of open defects remaining to be released to EirGrid on 22 Apr 2018 Release Pending In EirGrid Test Test Closed Total The total number of defects for which a release date has not yet been agreed between EirGrid and the vendors (continuing under discussion) The total number of defects that have been received by EirGrid and are currently undergoing test, prior to release into the Market Trial environment The total number of defects that have been received by EirGrid and which have completed test and are pending deployment to the Market Trial environment The sum of the Planned, Release Pending, In EirGrid Test, and Test Closed values Total - 36

37 Addition Previous (16-Apr) Schedule of Priority Defects for Go-Live: Defect Progression Now (23-Apr) Planned 03-Apr Planned 22-Apr Release Pending Planned 03-Apr Planned 22-Apr Release Pending In EirGrid Test Test Closed Closed Deprioritised Total 16-Apr In EirGrid Test Total Test Closed 2 2 Closed Deprioritised 3 3 Total 09-Apr 170 New Total Defects

38 Baseline Comparison Planned 03-Apr 12-Mar-18 / 23-Apr-18 Category Total Participant Impacting Baseline (at 12 March) In EirGrid Test (at 12 March) 7 2 Brought Forward from 22 April Release or Unplanned bucket 13 6 New 8 5 Non priority 3 0 Total Reclassified as Non Defects / Non Priority 1 0 In Development 1 0 In EirGrid Test 7 4 Test Closed 2 2 Closed without code change 15 6 Deployed to Market Trial Total

39 Baseline Comparison Planned 22-Apr 12-Mar-18 / 23-Apr-18 Category Total Participant Impacting Baseline (at 12 March) 18 4 In EirGrid Test (at 12 March) 1 0 Brought Forward from Unplanned bucket 15 5 Pushed out from 3 April Release 9 6 New 19 5 Non priority 5 1 Total Reclassified as Non Defects / Non Priority 1 0 In Development 8 1 In EirGrid Test Test Closed 19 4 Closed without code change 5 2 Deployed to Market Trial 5 1 Total

40 Release Schedule of Priority Defects for Go-Live: Apr 11 MMS Defect Release Schedule / Analysis of Defect Impact 03 (11) April 2018 In EG Testing + Test Closed + 22 (30) April 2018 Release Pending Focus: Resolve high impact defects to facilitate 168-hour testing in Scenario 7 of Market Trial Functional Areas Addressed and the Impact to Market Participants: Component Defects Resolved Impact why it matters By The Numbers: Severity (1,2,3): 0, 0, 1 Audience (MP, Int): 0, 1 Settlement Reports Structural defects (Missing fields) MP systems can download and parse settlement data for shadow settlement and reconciliation. SEMOpx -> CSB Integration Ex Ante Volumes into CSB Settlement Allows Bal/Imb settlement calculations and credit/collateral management processes and reports to complete QBOA/PIMB Formulation The quality and resilience of Imbalance pricing and settlement calculations will materially improve. 40

41 Release Schedule of Priority Defects for Go-Live: In EG Testing + Test Closed + Apr 30 + Release Pending MMS Defect Release Schedule / Analysis of Defect Impact 03 (11) April 2018 In EG Testing + Test Closed + 22 (30) April 2018 Release Pending Focus: Resolve remaining priority defects to facilitate I-SEM go-live and continued trialling for MPs in Market Trial Functional Areas Addressed and the Impact to Market Participants: Component Defects Resolved Impact why it matters By The Numbers: Severity (1,2,3): 0, 23, 31 Audience (MP, Int): 18, 36 CSB Config Mgmt Fixed MP Chgs Mkt Ops must use database update for job config. Fixed MO Charges are not calculated by the system until resolved. Imbalance Price Incorrect flagging PIMB incorrect flags some units that do not contribute to constraints. This will cause incorrect price calculations when occurring. 41 Interfaces Unit Reg Timeshift When new unit is added, all systems must be able to identify and exchange data related to the unit.

42 Release Schedule of Priority Defects for Go-Live: In EG Testing + Test Closed + Apr 30 + Release Pending MMS Defect Release Schedule / Analysis of Defect Impact In EG Testing + Test Closed In EG Testing + Test Closed (30) April (11) April 2018 Release Pending Functional Areas Addressed and the Impact to Market Participants: Component Defects Resolved Impact why it matters Scheduling & Dispatch Reports Multiple Calculations Structures Sched. Config Resolving these defects will improve the quality of scheduling results and subsequent dispatch instructions. In the interim, schedules and DIs will continue be produced. Resolving these defects will correct erroneous calculations, time horizons, and aggregations. The ability to manage the scheduled run time via Market Operator configuration will be remedied. 42

43 Release Schedule of Priority Defects for Go-Live: Detail 03 Apr Release Market Participant Facing 03 Apr ( Internal testing and verification ) On or Before 30 Apr Release date to EirGrid Release to MT Environment ID Severity Category Description Previous Schedule 4710 Moderate Non-Functional Allow for automatic stslog process kill Planned 03-Apr-18 43

44 Release Schedule of Priority Defects for Go-Live: Detail 22 Apr Release Market Participant Facing 22 Apr Release date to EirGrid ( Internal testing and verification ) 30 Apr Release to MT Environment ID Severity Category Description Previous Schedule 5130 Major QBOA Default FPN values must be applied when absent from user submitted data. Planned 22-Apr-18 44

45 Release Schedule of Priority Defects for Go-Live: Detail 22 Apr Release TSO Internal 22 Apr Release date to EirGrid ( Internal testing and verification ) ID Severity Category Description Previous Schedule 30 Apr Release to MT Environment 5189 Major Interfaces Inconsistency in unit mapping table updates Not reported on 13-Apr - Not Go Live Critical 5177 Moderate QBOA Incorrect validation rule applied for Wind Instructions with different codes but the same effective time Release Pending 5076 Major MI Error when importing new unit in balancing market due to conflicting data types. One-off defect when adding new unit. Manual workaround in place until resolution in place. Planned 22-Apr Major Scheduling & Dispatch RTD & RTC not respecting Trip Instructions and RTD not respecting FAIL Instructions In EirGrid Test 4842 Major Scheduling & Dispatch Incorrect MIN OFF time calculation In EirGrid Test 4235 Major Scheduling & Dispatch SA and NCUC functions incorrectly applying the hierarchy of Operating Mode In EirGrid Test 45

46 Release Schedule of Priority Defects for Go-Live: Detail Pending Release Market Participant Facing dd mon Release date to EirGrid TBD ( Internal testing and verification ) ID Severity Category Description Previous Schedule REPT_071 & REPT_072 The fields BP_END_DATE and BP_START_DATE are not being displayed in the 5171 Moderate Reports report Release Pending dd mon Release to MT Environment TBD 46

47 Release Schedule of Priority Defects for Go-Live: Detail Pending Release Internal dd mon Release date to EirGrid TBD ( Internal testing and verification ) ID Severity Category Description Previous Schedule Scheduling & 5179 Major Dispatch The Inertia column in the Gen Op data table is showing incorrect values when new units are registered Release Pending 5135 Moderate CSB Due date parameters for Settlement Document Creation are incorrect Release Pending Inability to place the publication of specific reports on hold without compromising system performance 4834 Major Reports or the publication of other reports. Release Pending dd mon Release to MT Environment TBD 47

48 Release Schedule of Priority Defects for Go-Live: Detail In EirGrid Testing Market Participant Facing 03 Apr Release date to EirGrid ( Internal testing and verification ) ID Severity Category Description Previous Schedule On or Before 30 Apr Release to MT Environment 5187 Moderate Reports REPT_020 - Daily Load Forecast Summary Report is showing sum of total of the aggregate values for NI, ROI instead is should contain a NI, ROI and Aggregate forecast values Release Pending 5131 Major QBOA PIMB Calc not picking up latest Dispatch Instructions Planned 22-Apr Moderate Reports REPT_081 not delivered as specified: spliced price/quantity curve, ranked ASC by per aggregated associated quantity for each ISP. Planned 22-Apr Major Reports REPT_028 currently displaying aggregate values per jurisdiction/ trading day rather than 15-minute resolution as specified. Planned 22-Apr Moderate Reports REPT_023 currently aggregated instead of ISP resolution Planned 22-Apr Moderate Reports REPT_018, currently daily instead of ISP resolution Planned 22-Apr Moderate Reports REPT_042 Forecast Imbalance Report not including entire time horizon following DAGC (within day) Planned 22-Apr Moderate CSB CSB-TP06-SETT04 Market Operator Cost not calculated and included in Sett Rpts Planned 22-Apr Moderate CSB REPT_057/058 Energy Market Information Publication Indicative/Initial incorrect assignment of DIFF Charges to CMU (type CAU) In EirGrid Test 4255 Major Imbalance Pricing Imb. Pric. routine incorrectly flags units that do not contribute to constraints. No impact on PIMB calculation, but needs to be addressed. Planned 22-Apr Major QBOA QBOA TP6_003 Imbalance Settlement Period Boundary / PISP In EirGrid Test 4250 Major QBOA QBOA TP6_003 Imbalance Settlement Period Boundary / PISP In EirGrid Test 48

49 Release Schedule of Priority Defects for Go-Live: Detail In EirGrid Testing TSO Internal 03 Apr Release date to EirGrid ( Internal testing and verification ) On or Before 30 Apr ID Severity Category Description Previous Schedule If two physical nominations are created by the same participant organisation at the same time then an Not reported on 13-Apr - Not Go 5203 Moderate Interfaces error will occur during settlement Live Critical 5198 Moderate Interfaces Database read error during imbalance pricing calculation Not reported on 13-Apr - Not Go Live Critical 5140 Moderate Non-Functional Database cleanse of audit reporting tables Release Pending 5077 Major CSB CSB not importing MDP data for first 2 ISP after activating new unit (23:00 00:00). One-off defect when adding new unit. Manual workaround in place until defect resolution. Planned 22-Apr Moderate Scheduling & Dispatch Issue formulating DI for PS unit following commitment change (Gen/OFF/SP/SG to PUMP). Planned 22-Apr Major Scheduling & Dispatch Issue with Offline Merit Order Fast Start issuing operator edited DI Planned 22-Apr Moderate Interfaces Intermittent locking of EMSI interface. Workaround to stop and restart service in place until resolution. Planned 22-Apr-18 Scheduling & 4900 Major Dispatch Incorrect application of operating mode across LTS/RTC sequence Planned 03-Apr-18 Release to MT Environment 49

50 Release Schedule of Priority Defects for Go-Live: Detail In EirGrid Testing TSO Internal 03 Apr Release date to EirGrid ( Internal testing and verification ) ID Severity Category Description Previous Schedule Scheduling & 4790 Moderate Dispatch Local constraint management issue for priority dispatch. Planned 22-Apr Major CSB Correct issue with Event Management in CSB OUI Planned 22-Apr Moderate Interfaces Error with INT_100 Planned 22-Apr Major Scheduling & Dispatch RTD status message not displaying correctly Planned 22-Apr Major Scheduling & Dispatch NCUC defaulting heat state to warm in some cases Planned 22-Apr Major QBOA QBOA(3): Correct P5Min PDI In EirGrid Test 4123 Major Scheduling & Dispatch Scheduling advising IC trade to move ICRP from forbidden zone. This is not expected behavior Planned 22-Apr Moderate Scheduling & Dispatch Error loading LT Forecast for WPRED Planned 22-Apr-18 On or Before 30 Apr Release to MT Environment 50

51 Release Schedule of Priority Defects for Go-Live: Detail Test Closed Market Participant Facing 03 Apr Release date to EirGrid ( Internal testing and verification ) ID Severity Category Description Previous Schedule 5185 Moderate CSB Incorrect calculation of VAT on MO Settlement Document In EirGrid Test MO & CRM still showing weekly statements within the Settlement Calendar (REPT_067). Should be 5043 Moderate CSB monthly. In EirGrid Test 4382 Moderate QBOA QBOA Correct error with DQ calculation for non-dispatchable, priority dispatch units Test Closed 4344 Major QBOA QBOA TP6_008 SYNC / PSYN Test Closed On or Before 30 Apr Release to MT Environment 51

52 Release Schedule of Priority Defects for Go-Live: Detail Test Closed TSO Internal 03 Apr Release date to EirGrid ( Internal testing and verification ) ID Severity Category Description Previous Schedule 5184 Moderate CSB Update to MO Charge Type Records when org has a non-local places of establishment In EirGrid Test On or Before 30 Apr Release to MT Environment 5101 Moderate Interfaces Error in transfer of registration data updates between MMS and CSB In EirGrid Test 5050 Moderate CSB Incremental data import from MI does not correctly validate for a completed FULL import for all days in the import date range. In EirGrid Test 5048 Moderate Scheduling & Dispatch Intermittent behaviour where RTC producing OFF mode too early from a DESYNC instruction In EirGrid Test 4969 Moderate Scheduling & Dispatch LTS ER3 missing RD Desy. In EirGrid Test 4532 Moderate Scheduling & Dispatch Advisory DI not followed if Follow PN=Y and UUT=Y In EirGrid Test 4234 Major Scheduling & Dispatch Incorrectly truncating INC/DEC data In EirGrid Test 4172 Moderate Scheduling & Dispatch Blending flags process in WPRED Planned 03-Apr Moderate Scheduling & Dispatch Inconsistent display of time horizon across modules In EirGrid Test 2950 Moderate Scheduling & Dispatch Advisory dispatch display issue (operator view) In EirGrid Test 2912 Moderate Scheduling & Dispatch DSI incorrectly setting operating modes In EirGrid Test 52

53 Previous (16-Apr) Schedule of Market Participant Facing Priority Defects for Go- Live: Defect Progression Now (23-Apr) Planned 03-Apr Planned 22-Apr Release Pending In EirGrid Test Test Closed Closed Total 23-Apr Total Planned 03-Apr Planned 22-Apr Release Pending In EirGrid Test Test Closed 2 2 Closed Total 16-Apr 67 Total Defects

54 Addition Previous (16-Apr) Schedule of Internal Priority Defects for Go-Live: Defect Progression Now (23-Apr) Planned 03-Apr Planned 22-Apr Release Pending Planned 03-Apr Planned 22-Apr Release Pending In EirGrid Test Test Closed Closed Deprioritised Total 16-Apr In EirGrid Test Total Test Closed 0 Closed Deprioritised 3 3 Total 09-Apr 103 New Total Defects

55 (b) Registration Registration of Units in Market Trial: Units in Market Trial * *End to end testing ongoing. Units Pending *Progress has been slower than we expected and reported back in March; current expected date for these units to be in Market Trial: early May. *SEMO will advise Participants when they can access these units in Trial. Registration plan to be updated to fit with revised Project timeline. 55

56 (c) Market Trial - Update Status update to be given at the meeting. 56

57 (d) Participant Readiness Discussion invited at the meeting on current state of Participant Readiness, and any practical measures which the PMG should consider to help mitigate identified risks or issues impacting on the readiness of participants projects. 57

58 Agenda 1. Previous Meeting Notes & Actions 2. Project Status & Key Risks 3. Readiness & Market Trial 4. JCR AOB 58

59 JCR362 Purpose JCR362 issued 20 April. Impact Assessment Closes 27 April. The purpose of JCR362 is to propose and give effect to the changes required to the outstanding Milestones in the I-SEM Plan. Need for additional Milestones will be considered and discussed first with the PMG; if they prove necessary, those new Milestones will be introduced through one or more additional Change Requests. 59

60 JCR362 Summary JCR proposes a revised Go Live date, and associated interim milestones, as follows: completion of testing, and release of systems with no priority defects into Trial environment in June 2018; additional circa three month period for Market Trial; completion of BM certification by early July 2018; four week cutover period for the introduction of the new central market systems during September

61 JCR362 Detail Proposes to change the baseline dates for Milestones: #9 BM Engine Certification Complete 6 Jul 2018 #86 Market Readiness Confirm Go Live 22 Aug 2018 #87 Market Trial Complete 30 Sep 2018 #250 I-SEM Go Live 01 Oct 2018 New milestone to be introduced: #175 All Priority Defects Fixed/Deployed into Trial 1 Jun

62 Agenda 1. Previous Meeting Notes & Actions 2. Project Status & Key Risks 3. Readiness & Market Trial 4. JCR AOB 62

63 Any Other Business Opportunity to bring forward any other business for discussion. 63

64 Close Web: I-SEMproject@sem-o.com Thank you for your attendance. Next Conference Call: Next Meeting: 9 th May

I-SEM: Market Trial Deployments 03 May 2018

I-SEM: Market Trial Deployments 03 May 2018 03 May 2018 Defects deployed to Trial in Releases ISEM_CSB 1.0.25 - ISEM_CSB 1.0.30 and ISEM_MMS 1.1.5.1 - ISEM_MMS 1.1.6.3 Last Updated: 04 May 2018 1 03 May 2018 This presentation is organised as follows:

More information

I-SEM Milestones. November 2017

I-SEM Milestones. November 2017 I-SEM Milestones November 2017 1 1.1 Milestone Descriptions Includes update since the approval of JCR 170 Ref Milestone & Description RA / TSO Baseline Date 1 2 3 4 5 6 7a 7b 7c Start Balancing Market

More information

I-SEM Business Liaison Group NEMO. 09 November2017

I-SEM Business Liaison Group NEMO. 09 November2017 I-SEM Business Liaison Group NEMO 09 November2017 1 Agenda Update on NEMO Implementation Project TSO Counter trading Market Trial 2 Agenda Update on NEMO Implementation Project TSO Counter trading Market

More information

Market Trial Working Group I-SEM Project

Market Trial Working Group I-SEM Project Market Trial Working Group I-SEM Project Dublin, 31 August 2017 1 Overview of the Session Meeting Details Meeting Purpose Chair Secretariat I-SEM Market Trial Working Group Mark Needham Louise Dalton Amy

More information

I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions

I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions Meeting Details Meeting Purpose Location Chair Secretariat I-SEM Project Managers Group (PMG) EirGrid, Dublin / Conference

More information

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process 1 Foreword Our scheduling and dispatch process incorporates a range of activities associated with managing the close to real-time

More information

Market Operator User Group. Dublin, 22 November 2018

Market Operator User Group. Dublin, 22 November 2018 Market Operator User Group Dublin, 22 November 2018 1 Agenda Item Welcome Ex-Ante Market Balancing Market Disputes, Repricing and Resettlement Update Settlements & Funds Transfer Known Issues Update Query

More information

SEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017

SEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017 SEMOpx Day-ahead Market Products Stage 3 Progress Report May 2017 Contents 1 Introduction... 3 2 Purpose of the Document... 4 3 IAT STAGES... 4 4 Scope of IAT... 6 5 Structure of IAT... 6 5.1 Creation

More information

Chapter 2: Inputs. Chapter 3: Inputs

Chapter 2: Inputs. Chapter 3: Inputs Chapter 2: Inputs Chapter 3: Inputs 1 Foreword (1/2) This section describes the data inputs to the scheduling and dispatch process including the source of the data and how it is used. There are thousands

More information

I-SEM Programme Project Office Programme Change Control Procedure

I-SEM Programme Project Office Programme Change Control Procedure Project Office Programme Change Control Procedure Version: 1.1 FINAL Date: 8 March 2017 Document Control Production Authors Responsibility Date Jim McAllister I-SEM PMO 01/07/2015 Helen Mounsey I-SEM PMO

More information

Balancing Market Principles Statement

Balancing Market Principles Statement Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 1.0 8 September 2017 Version Control Version No. Date Notes 1.0

More information

Balancing Market Principles Statement

Balancing Market Principles Statement Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 2.0 11 th April 2018 Version Control Version No. Date Notes 1.0

More information

Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements

Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements CONSULTATION VERSION 7 April 2017 IMPORTANT INFORMATION This Balancing

More information

I-SEM Interconnectors Project

I-SEM Interconnectors Project Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Initial Trial Report VERSION: 1.0 STATUS: Final for Publication DATE: 29 th SEPTEMBER 2017 Contents Introduction... 3 Objectives

More information

Balancing Registration Data User Guide

Balancing Registration Data User Guide Balancing Registration Data User Guide 29 th March 2017 Version 1.2 EirGrid 2016. Commercial In Confidence. Revision History Summary of Changes Version Revised By Initial Publication 1.0 I-SEM Project

More information

Business Process. BP_SO_4.2 Demand Forecasting for Scheduling & Dispatch

Business Process. BP_SO_4.2 Demand Forecasting for Scheduling & Dispatch Business Process BP_SO_4.2 Demand Forecasting for Scheduling & Dispatch EirGrid and SONI support the provision of information to the marketplace by publishing operational data, processes, methodologies

More information

I-SEM Interconnectors Project

I-SEM Interconnectors Project Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Trial and Participant Test Plan VERSION: 1.1 STATUS: Final for Publication DATE: 17 th JULY 2017 Contents Introduction...

More information

Reliability Coordinator Transition Coordination Group Update

Reliability Coordinator Transition Coordination Group Update Reliability Coordinator Transition Coordination Group Update WECC RC Forum 1/24/19 Presented by Jim Shetler / Eric Whitley - RCTCG Agenda RC Transition Project Roll-Out Update Update on Activities to Date

More information

Electricity Market Reform Capacity Market Implementation Plan

Electricity Market Reform Capacity Market Implementation Plan Electricity Market Reform Capacity Market Implementation Plan This implementation plan identifies the key milestones and activities required to successfully implement the Capacity Mechanism Version 1.2

More information

Market Operator User Group. Dublin, 17 January 2019

Market Operator User Group. Dublin, 17 January 2019 Market Operator User Group Dublin, 17 January 2019 1 Agenda Item Welcome Known Issues & Day 1+ Update High Level Market Overview Ex-Ante Market Balancing Market Disputes & Repricing Update Settlements

More information

Revised SMIS+ implementation plan. 4 th August 2015 SMIS+ Team

Revised SMIS+ implementation plan. 4 th August 2015 SMIS+ Team Revised SMIS+ implementation plan 4 th August 2015 SMIS+ Team Content Purpose and rationale Revised implementation plan Design & Build Plan (including workstreams) Design & Build Phases Deployment Phase

More information

Joint European Stakeholder Group. Tuesday 9 January 2018 Meeting 28 WebEx

Joint European Stakeholder Group. Tuesday 9 January 2018 Meeting 28 WebEx Joint European Stakeholder Group Tuesday 9 January 2018 Meeting 28 WebEx Agenda ID Title Lead Time 1. Welcome & Introductions Chair 10:00-10:05 2. National Grid Update: European Network Codes Implementation

More information

V3 Pension Administration System Solution. October 2015 Quarterly Board Update

V3 Pension Administration System Solution. October 2015 Quarterly Board Update V3 Pension Administration System Solution October 2015 Quarterly Board Update 1 Agenda V3 Quarterly Update Page Project Overall Status Update 3 V3 PASS Project Status Gantt Chart 4 PASS V3 Project Milestones

More information

Intra-Day Trading Project. Market Participant Technical Overview. Conference call number: , pin: 79592

Intra-Day Trading Project. Market Participant Technical Overview. Conference call number: , pin: 79592 Intra-Day Trading Project Market Participant Technical Overview 3 rd August 2011, 10.30 am 13:00 pm Conference call number: 00353 1 6647777, pin: 79592 Welcome Welcome to this information session on the

More information

I-SEM Testing Tariff High Level Options Consultation

I-SEM Testing Tariff High Level Options Consultation I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on

More information

DS3 System Services Project Plan Detailed Design and Implementation Phase

DS3 System Services Project Plan Detailed Design and Implementation Phase DS3 System Services Project Plan Detailed Design and Implementation Phase Dated: 20/5/2015 Executive Summary The System Services work stream within the DS3 Programme relates to the procurement of services

More information

August 18, Energy Imbalance Market (EIM) Entity Readiness Criteria

August 18, Energy Imbalance Market (EIM) Entity Readiness Criteria Energy Imbalance Market (EIM) Entity Criteria August 18, 2015 Energy Imbalance Market (EIM) Entity Criteria Table of Contents 1 Introduction... 3 2 Criteria Categories... 4 2.1 Metrics, Criteria, and Thresholds...

More information

I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview. I-SEM EUPHEMIA Working Group 16 th April 2015

I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview. I-SEM EUPHEMIA Working Group 16 th April 2015 I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview I-SEM EUPHEMIA Working Group 16 th April 2015 EUPHEMIA Workshop Agenda Background of EUPHEMIA algorithm Overview of background and goal of EUPHEMIA

More information

I-SEM. Integrated Single Electricity Market. Energy Portfolio Management solutions.

I-SEM. Integrated Single Electricity Market. Energy Portfolio Management solutions. I-SEM Integrated Single Electricity Market. Energy Portfolio Management solutions. Why ABB? I-SEM Integrated Single Electricity Market. When choosing any vendor, Bord Gáis Energy looks for a company with

More information

20 August Introduction

20 August Introduction DECC-Ofgem stakeholder prioritisation session: Proposal for a Regulation establishing a Guideline on Capacity Allocation and Congestion Management (CACM) Introduction 20 August 2014 Following the meeting

More information

ECB-UNRESTRICTED T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK

ECB-UNRESTRICTED T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK Status: Baseline TABLE OF CONTENTS 1 INTRODUCTION... 1 2 CHANGE MANAGEMENT... 3 2.1 CHANGE MANAGEMENT FOR COMMON AND SPECIFIC CHANGE... 3 2.2 PRINCIPLES...

More information

ASP/AML Amendment Invoice Issue Resolution - Update. 11 th June th June 2018

ASP/AML Amendment Invoice Issue Resolution - Update. 11 th June th June 2018 ASP/AML Amendment Invoice Issue Resolution - Update 11 th June 2018 11th June 2018 Agenda 1. Introduction and Summary of Issues and Challenges 2. BAU Invoicing Exclusions Defects 3. Root Cause Analysis

More information

SEMOpx Day-ahead Market Products Stage 2 Progress Report. March 2017

SEMOpx Day-ahead Market Products Stage 2 Progress Report. March 2017 SEMOpx Day-ahead Market Products Stage 2 Progress Report March 2017 Contents 1 Introduction... 2 2 Purpose of the Document... 3 3 IAT STAGES... 4 4 Scope of IAT... 4 5 Structure of IAT... 5 5.1 Creation

More information

European Developments

European Developments European Developments Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Transmission Workgroup

More information

11/02/2016. The Scheduling & Dispatch Process in I-SEM - Design Interpretation

11/02/2016. The Scheduling & Dispatch Process in I-SEM - Design Interpretation 11/02/2016 The Scheduling & Dispatch Process in I-SEM - Design Interpretation Release Date Version No. Summary of Changes 11/02/2016 1.0 Design Interpretation document published for discussion at Market

More information

Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting

Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting 21 January 2009 Victorian AMI Program Phases 2006 Jul 2007 May 2010 2013 Establishment Phase Involved

More information

Settlement Frequently Asked Questions Contents

Settlement Frequently Asked Questions Contents Contents 1. What is the Settlement Calendar?... 3 2. How do I View my Invoices?... 3 3. Where can I see the Settlement Calendar?... 6 4. What are SEMO s Settlement Publication Timelines?... 7 5. What Payments

More information

European Update. 2nd July 2015

European Update. 2nd July 2015 European Update Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. 2nd July 2015 1. General Update

More information

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: 1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call

More information

V3 Pension Administration System Solution August 2013 Monthly Board Update

V3 Pension Administration System Solution August 2013 Monthly Board Update V3 Pension Administration System Solution August 2013 Monthly Board Update 2012 OCERS Agenda Project Overall Status Update 3 PASS V3 Project Status Gantt Chart 4 PASS V3 Project Milestones 5 Project Status

More information

I-SEM Small Wind Information Session. 24 November 2016

I-SEM Small Wind Information Session. 24 November 2016 I-SEM Small Wind Information Session 24 November 2016 1 Agenda 1. I-SEM Market Overview 2. I-SEM Registration Overview 3. Market Readiness Update 4. Market Trial Update 5. Systems Overview 6. AOB 2 Power

More information

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager Meter Data Management System (MDMS) Sharing Ricky Ip CLP Manager Agenda Introduction Objectives Critical Success Factors Change Management Lessons Learned 2 CLP Power Hong Kong Limited (CLP Power) is the

More information

Generation Attribute Tracking System (GATS) Overview of PJM-EIS

Generation Attribute Tracking System (GATS) Overview of PJM-EIS Generation Attribute Tracking System (GATS) Overview of PJM-EIS Presented at the GATS Subscriber Group Meeting April 15, 2005 Overview PJM Environmental Information Services, Inc. (PJM EIS) owns and administers

More information

IGG Agenda. Minutes from Previous IGG Meeting 13:30 13:35 Review of Action Items 13:35 14:00 CER Update 14:00 14:20. Gemserv Update 14:20 14:30

IGG Agenda. Minutes from Previous IGG Meeting 13:30 13:35 Review of Action Items 13:35 14:00 CER Update 14:00 14:20. Gemserv Update 14:20 14:30 IGG Agenda Minutes from Previous IGG Meeting 13:30 13:35 Review of Action Items 13:35 14:00 CER Update 14:00 14:20 Gemserv Update 14:20 14:30 MRSO Update 14:30 14:40 ESB Networks Update 14:40 15:00 Retail

More information

Electricity System Operator Forward Plan 2018/19

Electricity System Operator Forward Plan 2018/19 Electricity System Operator Forward Plan 2018/19 Contents 1. Our vision 2. An ambitious plan 3. A changing landscape 4. Value for consumers 5. A plan built with our customers and stakeholders 6. Our roles,

More information

Retail Markets Co-Ordination Working Group

Retail Markets Co-Ordination Working Group Retail Markets Co-Ordination Working Group Wednesday, 13 th May, 2015 CER Offices Dublin ReMCoWG Agenda Agenda Item Presenter Time Introduction Jessica Gregory 13:00 13:05 ReMCoSG Meeting Feedback Jessica

More information

ATTACHMENT DD. Reliability Pricing Model

ATTACHMENT DD. Reliability Pricing Model OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.

More information

Retail Markets Co-Ordination Working Group

Retail Markets Co-Ordination Working Group Retail Markets Co-Ordination Working Group Wednesday, 9 th March, 2016 UR Offices Belfast ReMCoWG Agenda Agenda Item Presenter Time Introduction Jessica Gregory 12:45 12:50 ReMCoSG Meeting Feedback Jessica

More information

Requirements Analysis and Design Definition. Chapter Study Group Learning Materials

Requirements Analysis and Design Definition. Chapter Study Group Learning Materials Requirements Analysis and Design Definition Chapter Study Group Learning Materials 2015, International Institute of Business Analysis (IIBA ). Permission is granted to IIBA Chapters to use and modify this

More information

Data Cleansing Workgroup. 24 th November 2014

Data Cleansing Workgroup. 24 th November 2014 Data Cleansing Workgroup 24 th November 2014 1 2 Agenda Actions From Last Meeting Progress Correction Factors 0.0 Root Cause (No Reads >4yrs) Business As Usual Cleansing Confirmed No Asset UKLP Data Activities

More information

Meeting System Needs with Demand Response - Work Plan and Technical Panel Timelines

Meeting System Needs with Demand Response - Work Plan and Technical Panel Timelines IESOTP 278-4b Meeting System Needs with Demand Response - Work Plan and Technical Panel Timelines Technical Panel May 5, 2014 Agenda What is our goal for demand response? Stakeholder Consultation IESO

More information

Joint European Stakeholder Group. Monday 25 th May 2017: Meeting 21 Elexon, London

Joint European Stakeholder Group. Monday 25 th May 2017: Meeting 21 Elexon, London Joint European Stakeholder Group Monday 25 th May 2017: Meeting 21 Elexon, London 1. Welcome & Introductions Barbra Vest Independent Chair 2. Interconnector projects update Caroline Kluyver and John Greasley

More information

MARKET OPENING PROGRAMME

MARKET OPENING PROGRAMME CER/03/285 Proposal for co-ordination of ongoing reform programmes in the Irish gas market Version 1.0 27 November 2003 Market Opening Programme Interim market opening options - Version 1.0 Document Control

More information

All NEMOs proposal for the back-up methodology in accordance with Article 36(3) of the Commission Regulation (EU) 2015/1222 of 24 July 2015

All NEMOs proposal for the back-up methodology in accordance with Article 36(3) of the Commission Regulation (EU) 2015/1222 of 24 July 2015 All NEMOs proposal for the back-up methodology in accordance with Article 36(3) of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and congestion

More information

3 rd EU Stakeholder Committee Meeting

3 rd EU Stakeholder Committee Meeting 3 rd EU Stakeholder Committee Meeting 03.02.2016 Content 1. Project Progress Key Achievements Challenges 2. Project Timeline 3. Local Implementation Projects and update on Belgian Borders Quick Wins 4.

More information

V3 Pension Administration System Solution. July 2014 Monthly Board Update

V3 Pension Administration System Solution. July 2014 Monthly Board Update V3 Pension Administration System Solution July 2014 Monthly Board Update Agenda V3 Monthly Update Page Project Overall Status Update 3 V3 PASS Project Status Gantt Chart 4 PASS V3 Project Milestones 5

More information

Integrated Marketplace. Participant Training Update. April 18, Gay Anthony SPP Customer Training

Integrated Marketplace. Participant Training Update. April 18, Gay Anthony SPP Customer Training Integrated Marketplace Participant Training Update April 18, 2012 Gay Anthony SPP Customer Training ganthony@spp.org Training Update Live deliveries of the Marketplace Overview and Preparing for TCR Mock

More information

Integrated Trading and Clearing (ITaC) Client Forum

Integrated Trading and Clearing (ITaC) Client Forum Integrated Trading and Clearing (ITaC) Client Forum 29 August 2018 1 Agenda ITaC Key Dates ITaC Conceptual Training ITaC End-To-End (ETE) Testing update ITaC Dress Rehearsal 18 August 2018 results feedback

More information

Gas Daft. Unaccounted for Gas Report. National Grid. Gas Transmission. October Target audience. Ofgem and other interested industry parties

Gas Daft. Unaccounted for Gas Report. National Grid. Gas Transmission. October Target audience. Ofgem and other interested industry parties Gas Daft Unaccounted for Gas Report National Grid Gas Transmission October 2017 Target audience Ofgem and other interested industry parties About this document This document sets out the work undertaken

More information

Driving performance through stakeholder engagement

Driving performance through stakeholder engagement Driving performance through stakeholder engagement Driving performance through stakeholder engagement 1 Driving performance through stakeholder engagement Introduction As articulated in our Getting the

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket Nos. ER12-1630 Operator Corporation ) ER14-971 Informational Report of the California Independent System

More information

Proposal for a common set of requirements for the DA price coupling algorithm

Proposal for a common set of requirements for the DA price coupling algorithm Proposal for a common set of requirements for the DA price coupling algorithm 13 November 2017 1. Background (1) This document is a common proposal developed by all Transmission System Operators (hereafter

More information

Business Process. BP_SO_12.1 Unit Testing

Business Process. BP_SO_12.1 Unit Testing Business Process BP_SO_12.1 Unit Testing EirGrid and SONI support the provision of information to the marketplace by publishing operational data, processes, methodologies and reports. This information

More information

5MS Systems Working Group

5MS Systems Working Group 5MS Systems Working Group SWG#1 - Friday, 24 August 2018 AEMO Offices: Level 9, 99 Gawler Place, Adelaide Level 10, 10 Eagle Street, Brisbane Level 22, 530 Collins Street, Melbourne Level 2, 20 Bond Street,

More information

Open Networks Project

Open Networks Project Open Networks Project Consultation on Phase 2 Work Programme 30 January 2018 Document Ref: ON-Phase 2 Programme T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 1 Introduction

More information

Transformation status update: September 2018

Transformation status update: September 2018 9 October 2018 Minister of Finance Minister of Revenue Transformation status update: September 2018 Executive summary 1. This report summarises the progress and highlights of transformation for September

More information

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project Consultation on DS3 System Services Contracts for Interim Arrangements DS3 System Services Implementation Project 21 April 2016 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,

More information

Proposal for a common set of requirements used for the continuous trading matching algorithm

Proposal for a common set of requirements used for the continuous trading matching algorithm Proposal for a common set of requirements used for the continuous trading matching algorithm 13 November 2017 1. Background 1. This document is a common proposal developed by all Transmission System Operators

More information

ESB Networks. Presentation to the IGG. 29 th August 2018

ESB Networks. Presentation to the IGG. 29 th August 2018 ESB Networks Presentation to the IGG 29 th August 2018 Agenda Long Term No Access I-SEM Smart Metering and Retail Program 2 esbnetworks.ie LONG TERM NO ACCESS INITIATIVE Peter Warner Manager Meter Reading

More information

(Non-legislative acts) REGULATIONS

(Non-legislative acts) REGULATIONS 15.6.2013 Official Journal of the European Union L 163/1 II (Non-legislative acts) REGULATIONS COMMISSION REGULATION (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity

More information

UK Link Shipper Engagement Day Agenda

UK Link Shipper Engagement Day Agenda UK Link Shipper Engagement Day Agenda Date: Thursday 2 nd October Venue: The Studios, Birmingham (capacity 120 cabaret style) Purpose: Share file formats overlaid on To-be processes following formal release

More information

NAPA SANITATION DISTRICT

NAPA SANITATION DISTRICT NAPA SANITATION DISTRICT PSOMAS COMPANY - TASK ORDER No. 25 HEADWORKS EQUIPMENT REHAB-REPLACE PROJECT (CIP 17726) Date: July 25, 2018 Issued under Professional Services Agreement dated ---------, 2018.

More information

V3 Pension Administration System Solution October 2013 Monthly Board Update

V3 Pension Administration System Solution October 2013 Monthly Board Update V3 Pension Administration System Solution October 2013 Monthly Board Update Agenda Project Overall Status Update 3 V3 PASS Project Status Gantt Chart 4 PASS V3 Project Milestones 5 Project Status Update

More information

IGG Agenda. Minutes from Previous IGG Meeting 10:15 10:20 Review of Action Items 10:20 10:40 CER Update 10:40 11:00. Gemserv Update 11:00 11:10

IGG Agenda. Minutes from Previous IGG Meeting 10:15 10:20 Review of Action Items 10:20 10:40 CER Update 10:40 11:00. Gemserv Update 11:00 11:10 IGG Agenda Minutes from Previous IGG Meeting 10:15 10:20 Review of Action Items 10:20 10:40 CER Update 10:40 11:00 Gemserv Update 11:00 11:10 MRSO Update 11:10 11:20 ESB Networks Update 11:20 11:45 Retail

More information

The purpose of this paper is to present the outcome of recent PR19 assurance activities for note by the Water Forum.

The purpose of this paper is to present the outcome of recent PR19 assurance activities for note by the Water Forum. BUSINESS PLAN UPDATE ASSURANCE DASHBOARD PAGE 1 OF 1 1. PURPOSE OF PAPER The purpose of this paper is to present the outcome of recent PR19 assurance activities for note by the Water Forum. 2. QUALITY

More information

10 th MESC. XBID Project Update. 6 th September 2017

10 th MESC. XBID Project Update. 6 th September 2017 10 th MESC XBID Project Update 6 th September 2017 Agenda 1. Project Timeline 2. Project Progress Achievements Challenges 3. Local Implementation Projects 4. Gate Closure Time 5. Summary 2 1. Project Timeline

More information

Interim Governance Arrangements for All Island Retail Market Harmonisation Project

Interim Governance Arrangements for All Island Retail Market Harmonisation Project Interim Governance Arrangements for All Island Retail Market Harmonisation Project Document Revision History Version Date Summary of Change Author Number 2 21 Oct 2009 First draft for review Various 3

More information

Security level: In confidence Report number: IR2018/570

Security level: In confidence Report number: IR2018/570 Inland Revenue report: Transformation status update: October 2018 Date: 12 November 2018 Priority: Medium Security level: In confidence Report number: IR2018/570 Action sought Action sought Deadline Minister

More information

Annex 2: Statement of work. Table of contents

Annex 2: Statement of work. Table of contents UNFCCC/CCNUCC Page 1 Annex 2: Statement of work Table of contents Annex 2... 2 Objective... 2 Engagement... 2 Overall approach... 2 Partnering... 3 Quality and reviews... 3 Developer contract... 4 Operator

More information

Project Management Step by Step Guide

Project Management Step by Step Guide Project Management Step by Step Guide BNH Expert Software ADVISOR Enterprise User's Guide Copyright 995 to 208 BNH Expert Software Inc. Latest Update: February 2, 208 All rights reserved. No part of this

More information

DCC Operations update. Industry Event 15 th December Dave Broady Operations Director, Smart DCC. DCC Public

DCC Operations update. Industry Event 15 th December Dave Broady Operations Director, Smart DCC. DCC Public DCC Operations update Industry Event 15 th December 2015 Dave Broady Operations Director, Smart DCC DCC Public Service Desk Core Team All staff trained by DCC 100% Availability in year up to 30 th November

More information

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources Market Issues Bulletin Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources March 10, 2015 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400

More information

Tusla Programme Management (PMO) Design and Establishment. Fergal Collins 20 th September 2018

Tusla Programme Management (PMO) Design and Establishment. Fergal Collins 20 th September 2018 Tusla Programme Management (PMO) Design and Establishment Fergal Collins 20 th September 2018 1 Contents Tusla Overview Executive Summary. Choosing an operating model for the PMO. 3 PMO Models to choose

More information

European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1.

European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1. European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1.1) Agenda Item Approximate start time Welcome: Tea and coffee 09:30

More information

Implementation of OAG recommendations. Status Report

Implementation of OAG recommendations. Status Report Implementation of OAG recommendations Status Report O r g a n i s a t i o n Civil Aviation Authority of New Zealand V e r s i o n Final (DW1208964-0) A u t h o r COO D a t e o f t h i s d o c u m e n t

More information

Program/Project Management

Program/Project Management PROCEDURE OVERVIEW PROGRAM/PROJECT MANAGEMENT PROCEDURE defines the project management infrastructure, reporting relationships and project management activities within SDLC.com. Project Managers, Program

More information

MARKET PROCESS DESIGN. Retail Market Release Prioritisation Process

MARKET PROCESS DESIGN. Retail Market Release Prioritisation Process MARKET PROCESS DESIGN TABLE OF CONTENTS TABLE OF CONTENTS... 2 INTRODUCTION... 3 SCOPE... 3 HISTORY OF CHANGES... 3 REFERENCE DOCUMENTS... 4 BACKGROUND... 4 DESIGN PRINCIPLES... 4 PROCESS MAPS... 5 PROCESS

More information

The Procedure for Agreement of Change of Supplier Readings and Resolution of Disputed Change of Supplier Readings

The Procedure for Agreement of Change of Supplier Readings and Resolution of Disputed Change of Supplier Readings The Procedure for Agreement of Change of Supplier Readings and Resolution of Disputed Change of Supplier Readings MAP 08 Version : 3.2 Status : Final Date : 30 th June 2016 Document Reference : MAP08_3.2

More information

GOVERNANCE SMART objectives / SUHFT board development programme

GOVERNANCE SMART objectives / SUHFT board development programme GOVERNANCE SMART objectives / SUHFT board development programme Specific objective Measurable Success Actions required Relevance / Outcome Owner Time Documented set of Trust Board objectives will be in

More information

2005 Major Projects. Project Description. Status and Milestone Deliverables

2005 Major Projects. Project Description. Status and Milestone Deliverables . 4 A799 Billing Simulator Status: Use case functionality has been delivered iteratively throughout 2005 as planned. The last phase of the project includes delivery of the remaining 39 use cases which

More information

Billing System Corrections (Baseline)

Billing System Corrections (Baseline) 2 A66 Billing System Corrections (Baseline) Billing Rate Schedule Allocation 8/2 Status: Billing system problem resolution continues on a regular basis by a dedicated team of development staff Once identified,

More information

Clinical trial databases are a crucial investment in clinical research. Part 4 - The "Life" of a Data Manager - Project Manager for the Database

Clinical trial databases are a crucial investment in clinical research. Part 4 - The Life of a Data Manager - Project Manager for the Database Clinical trial databases are a crucial investment in clinical research Part 4 - The "Life" of a Data Manager - Project Manager for the Database Speakers: M.Duvenhage K. Laras S. Erari 12 Oct 2018 Overview

More information

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for a common set of requirements, in accordance with Article

More information

WHAT S NEW IN PASTEL EVOLUTION VERSION 6.60

WHAT S NEW IN PASTEL EVOLUTION VERSION 6.60 WHAT S NEW IN PASTEL EVOLUTION VERSION 6.60 Softline Pastel s continuous investment in research and development ensures that you are kept up to date with the latest and most cutting-edge business management

More information

Transforming Internal Audit to Drive Business Performance. 21 June, 2011

Transforming Internal Audit to Drive Business Performance. 21 June, 2011 Transforming Internal Audit to Drive Business Performance 21 June, 2011 Agenda Stakeholder Needs from Survey Data Linking Business Performance to Internal Audit The Role of Risk Management Becoming a Strategic

More information

Market Simulation Fall 2018 Release

Market Simulation Fall 2018 Release Market Simulation Fall 2018 Release Trang Deluca Sr. Change & Release Planner September 17, 2018 Recordings Calls and webinars are recorded for stakeholder convenience, allowing those who are unable to

More information

Market Simulation Fall 2018 Release

Market Simulation Fall 2018 Release Market Simulation Fall 2018 Release Trang Deluca Sr. Change & Release Planner October 8, 2018 Recordings Calls and webinars are recorded for stakeholder convenience, allowing those who are unable to attend

More information

Market Rules Procedure on

Market Rules Procedure on ver. 1.0 Page 1 from 27 Transmission System and Market Operator of Kosovo (KOSTT) February 2015 ver. 1.0 Page 2 from 27 Department: Market Operator This Market Rules procedure (including as subsequently

More information

QUICK START GUIDE. SQF Implementation. for.

QUICK START GUIDE. SQF Implementation. for. QUICK START GUIDE for SQF Implementation www.22000-tools.com CONTENTS WHAT IS SQF? BENEFITS OF SQF SQF LEVELS SQF MODULES IMPLEMENTING SQF AND PREPARING FOR CERTIFICATION ASSIGN YOUR PEOPLE RESOURCES

More information