REPORT ON ROOT CAUSE ANALYSIS & CORRECTIVE ACTION FOR LEAKAGE IN WELD JOINT

Size: px
Start display at page:

Download "REPORT ON ROOT CAUSE ANALYSIS & CORRECTIVE ACTION FOR LEAKAGE IN WELD JOINT"

Transcription

1 REPORT ON ROOT CAUSE ANALYSIS & CORRECTIVE ACTION FOR LEAKAGE IN WELD JOINT Team Members: S. Rangaprasad Sr.DGM, Manufacturing M.K. Baranidharan DGM, Quality control M Gunasekaran DGM, Quality Assurance E Kallathieppan AGM, Manufacturing Raja Chacko Manager, Quality Control S. Suriyanarayanan- Manager, Design S.Pradeep Welding Engineer S.M. Balaji Sr. Engineer Quality Control Date: 07-JULY-2015 Ref: Customer Complaint No: LT Dated: 01-JUN-2015 Page 1 of 10

2 CONTENTS CONTENTS 1) Background 2) Preliminary Analysis & Interim Containment Action a) Verifications at L&T Valves Factory b) Verifications during assembly c) Correction at site 3) Root Cause Analysis a) Problem Description b) Sequence of events c) Cause and Effect Diagram d) Significant Causes e) Why- Why analysis 4) Corrective action Page 2 of 10

3 1.0 Background Observations: Weld leak Valve Body and pipe joint(refer image) in 6"2500SPL GATE WC6 T5 BW IBR PRVBT ACT BPM during commissioning. Page 3 of 10

4 Supplied Valve Details: 2 Valves of 6"2500SPL GATE WC6 T5 BW IBR PRVBT ACT BPM supplied to Rajpura boiler 1 No each to Unit 1 & Unit 2. Complaint received in valve supplied to Unit 1 &2. Project Valve Type Rajpura Boiler Gate Valve size 6 Class Material Quantity Main valve serial no Tag number 2500SPL WC6 2 No s C & C HCB01AA001 & 02HCB01AA001 Customer P.O LMB/F04/ /JPS(U-1&2) / 164 L&T Valves Sale Order Bypass valve /9770 & /6670 DN20 CL 2500 SPL F22 T-Globe valve (By pass) Pipe detail 3/4 P22 SCH XXS Pipe 2. Preliminary Analysis & Interim Containment Action: a) Verifications at L&T Valves Factory The following documents were verified and found in order: Page 4 of 10 Valve test reports (Quality dossiers) Pre Dispatch Inspection Report Final inspection report Internal valve test report Valve Assembly Record Receiving Inspection Reports

5 Material test certificate from BOF suppliers Review of Gear Unit Test Certificate We have verified the Quality records of the following manufacturing stages 1) Valve serial no: C / C Body Heat no: B12467 / B Foundry: Ultimate Alloys. 2) ANSI area coverage done in the Body casting & found accepted (RT No: UA / UA12-577) 3) 3/4 pipe received & found meeting the material specification(supplier: Sumitomo metal, Japan) 4) Test certificate, Valve test report made 5) Welding done as per approved WPS. Preheating, PWHT done as per approved procedures 6) DP test carried on the weld surface and found no significant indication noticed. 7) Pressure test done as per approved GAD & witnessed by LMB TPI Valve Serial No C ) SCN (Stores Credit Note) done after inspection at per L&T procedures & valves were cleared to painting. Before dispatch (PDI) inspection carried out & cleared. 2.0 Correction: Proposed to remove the defective weld portion at leak area up to pipe wall thickness and perform welding as per approved WPS. On completion of repair weld, PWHT of weld joint & NDE-PT shall be carried out on the surface of the weld. Page 5 of 10

6 3.0 Root Cause Analysis: a) Problem Description DESCRIPTION AREA DESCRIPTION What object has the defect Gate Valve WHAT What is the defect? Weld Leak WHERE Where specifically on the valve do you see the defect? Where geographically is the object observed? First seen - By the customer? Leakage thro weld joint (Leakage noticed inbetween Body & pipe weld joint) At customer site Rajpura, Punjab. Yes WHEN HOW BIG Similar Parts When seen since? When is the observation seen in the valve- while site, operation (i.e. when the valve is used)? When is the observation seen in the life of the object?(eg. when new or after few years of service) How many objects have noticed this observation? How many/much observation(s) per object While operation After the 6 month service Two valve One Page 6 of 10

7 CAUSE AND EFFECT DIAGRAM - DEFINE & VERIFY ROOT CAUSE METHODS/PROCESSES MACHINE Improper surface cleaning (scale/oily surface) Preheat & Post heat ment cycle not done as per approved procedure Unqualified welder Lack of Awareness on WPS/PQR Ammeter & voltmeter used in welding machine not calibrated Visual inspection of weld joints not done Inspection NDE method not performed Unapproved welding consumables used interpass temperature not maintained properly Leakage thro weld joint between Body & pipe Lack of fusion Pipe material grade not meeting specification MAN MATERIALS Page 7 of 10

8 S No CAUSES SIGNIFICANT / IN- SIGNIFICANT 1 Improper surface cleaning (scale/oily surface) Insignificant 2 Preheat & Post heat meant cycle not done as per approved procedure Insignificant 3 Ammeter & voltmeter used in welding machine not calibrated Insignificant 4 Visual inspection of weld joints not done Insignificant 5 Inspection NDE method not performed Insignificant 6 Interpass temperature not maintained properly Insignificant 7 Unqualified welder Insignificant 8 Lack of Awareness on WPS/PQR InSignificant 9 Lack of fusion Significant 10 Unapproved welding consumables used Insignificant 11 Pipe material grade not meeting specification Insignificant Page 8 of 10

9 S No CAUSES Verification status 1 Improper surface cleaning (scale/oily surface) 2 Preheat & Post heat ment cycle not done as per approved procedure 3 Ammeter & voltmeter used in welding machine not calibrated 4 Visual inspection of weld joints not done 5 Inspection NDE method not performed 6 Interpass temperature not maintained properly Base materials are cleaned properly before start of welding process & scales/oil if any are removed. Heat treatment process carried out as per approved WPS Ammeter & voltmeter used in welding machine are calibrated at periodic intervals as per calibration plan Visual inspection performed after PRV welding by qualified inspectors. Again inspected before clearing to painting in valve & in PDI (Pre Despatch Inspection) NDE-PT performed & cleared Temperature measured using Themal chalk & infrared temperature measurement gauge & welding performed. By this interpass temperature maintained as per approved WPS 7 Unqualified welder Welders are qualified as per the WPS & PQR & approval given for welding. Approved welders are only utilized to perform welding 8 Lack of Awareness on WPS/PQR Training given to all welders & briefed on WPS & PQR requirements. WPS & PQR display made in weld shop for better communication 9 Lack of fusion Found having lack of bonding between Weld metal & base metal 10 Unapproved welding consumables used 11 Pipe material grade not meeting specification Welding consumables procured from approved sources only Chemical & mechanical properties verified by supplier & Material Test certificate given. At L&T valves, material confirmation done using PMI & ensured Page 9 of 10

10 WHY WHY ANALYSIS Significant Cause / : lack of fusion in the weld Nonconformance Why? Lack of bonding due to welding work Why?? Non control on welding parameter Why? Lack of awareness of Welding operator Root Cause: Lack of awareness of Welding operator 4.0 Corrective action: Based on the above, the following corrective actions are suggested: a) Retraining to be given to welders to communicate on the process control measures to be followed to avoid weld defects. b) Shell test to be done for extended duration (60 minutes) during internal testing at L&T valves for critical valves. Prepared by Reviewed & Approved by Raja Chacko M. Gunasekaran Date: Page 10 of 10

BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION

BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION 2018 (Replaces February 2017) API Authorized Piping Inspectors must have a broad knowledge base relating to maintenance,

More information

Presented by: Gary Scribner Manager of Technical Services. Shanghai April The National Board of Boiler and Pressure Vessel Inspectors

Presented by: Gary Scribner Manager of Technical Services. Shanghai April The National Board of Boiler and Pressure Vessel Inspectors Presented by: Gary Scribner Manager of Technical Services Shanghai April 2016 1. Provides administrative and technical rules, and guidelines to follow for repairing or altering a pressure retaining item.

More information

2004 NBIC Interpretations

2004 NBIC Interpretations 2004 NBIC Interpretations INTERPRETATION 04-23 Subject: Part RC 1110, RC-2050(c), RC-3030(c), RC-3031(e) Question 1: Does RC-1110 specifically require acceptance of the jurisdiction for alternative NDE

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of Works for the Manufacture of Fusion Welded Pressure Vessels Revision 4, July 2015 Page 1 of 17 Lloyd s Register Group Limited, its subsidiaries

More information

Inspection and Test Plan for Gas Turbine

Inspection and Test Plan for Gas Turbine and Test Plan for Gas Turbine No. and Test Plan Reference Document Acceptance Criteria Verifying Document Activity By Remark Manuf. TPI Client 1 Pre Meeting Spec. Spec. MOM H H H Before Manufacturing 2

More information

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS BRITISH COLUMBIA SAFETY AUTHORITY Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS Prepared by: Ed Hurd P.Eng. Provincial Safety Manager, Boilers Date: March 2, 2012 Controlled

More information

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6 QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 WELDING HEAT TREATMENT PAGE 1 OF 6 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements for

More information

JOHN WOOD UNCONTROLLED COPY: THE JOHN WOOD COMPANY PO BOX HIGHLAND AVENUE OAKS, PENNSYLVANIA 19456

JOHN WOOD UNCONTROLLED COPY: THE JOHN WOOD COMPANY PO BOX HIGHLAND AVENUE OAKS, PENNSYLVANIA 19456 JOHN WOOD QUALITY CONTROL SYSTEM MANUAL FOR PRESSURE VESSELS CONSTRUCTED TO ASME BOILER & PRESSURE VESSEL CODE SECTION VIII, DIVISION 1 AND REPAIRS AND ALTERATIONS TO METALLIC PRESSURE RETAINING ITEMS

More information

Inspection and Welding Repairs of Pressure Vessels

Inspection and Welding Repairs of Pressure Vessels Inspection and Welding Repairs of Pressure Vessels BY S. V. GUPTE B.E., D.M.E. ASNT LEVEL III - RT,MT,PT,VT PRESSURE VESSEL INSPECTOR (API 510), (CCOE) PAINT AND COATING INSPECTOR (NACE INDIA) LEAD AUDITOR

More information

Guideline of the European Committee for Welding of Railway Vehicles - ECWRV ( ) - PART 2 Technical Interpretation of EN 15085

Guideline of the European Committee for Welding of Railway Vehicles - ECWRV ( ) - PART 2 Technical Interpretation of EN 15085 Guideline of the European Committee for Welding of Railway Vehicles - ECWRV (2016-09-07) - PART 2 Technical Interpretation of EN 15085 Contents 1 Introduction... 2 2 Interpretation of EN 15085-1... 2 3

More information

AWS D1.1 Structural Welding Code: You Specify It- Do You Know What It Really Says?

AWS D1.1 Structural Welding Code: You Specify It- Do You Know What It Really Says? AWS D1.1 Structural Welding Code: You Specify It- Do You Know What It Really Says? Wesley J. Oliphant, PE, AWS-CWI, F.SEI, F.ASCE ReliaPOLE Inspection Services Company, LLC 1 All welding shall be done

More information

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26 Company Name/Certificate Number: Page 1 of 26 a. Organization a.1. Has the Organizational Structure of the program identified the levels of management responsible for the Quality System Program, including

More information

Management System Requirements

Management System Requirements Management System Requirements Identification, Recognition, Application IAEA Technical Meeting Grading of the Application of Management System Requirements Vienna, 23 27 January 2012 RWE Technology GmbH

More information

MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator PERSONAL DATA LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator PERSONAL DATA LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 104126-MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator Has 10 years experience in the field of inspection and quality assurance / control related to chemical, petrochemical, power plants

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of a Foundry for the Manufacture of Steel Castings Revision 3, January 2015 Lloyd s Register Group Limited, its subsidiaries and affiliates and

More information

SECTION TAPPING SLEEVES AND VALVES

SECTION TAPPING SLEEVES AND VALVES SECTION 33 12 16.17 TAPPING SLEEVES AND VALVES PART 1: GENERAL 1.01 SCOPE Furnish, install and test all tapping sleeves, tapping valves, and tapping saddles as shown on the Drawings. 1.02 RELATED WORK

More information

QUALIFICATION TESTING OF FIELD WELDERS

QUALIFICATION TESTING OF FIELD WELDERS Page 1 of 9 Oklahoma DOT Materials & Testing December 5, 2003 (Updated to Reference 2009 Specifications 11/26/2012) (Added paragraph to the bottom of Roles and Responsibilities section. 11/14/2017) Publication:

More information

Accreditation of Hot Tap Organizations

Accreditation of Hot Tap Organizations Accreditation of Hot Tap Organizations TSSA Guide for Survey Teams Technical Standards & Safety Authority Boiler & Pressure Vessels Safety Division 3300 Bloor Street West 14 th Floor, Centre Tower, Etobicoke,

More information

Pressure Equipment Repair and Alteration Requirements

Pressure Equipment Repair and Alteration Requirements the pressure equipment safety authority Pressure Equipment Repair and Alteration Requirements AB-513 Edition 3, Revision 0 - Issued 2018-01-30 Table of Contents FOREWORD... iii 1.0 INTRODUCTION... 1 2.0

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-05 14 00.13 (May 2015) -------------------------------- Preparing Activity: NASA Superseding UFGS-05 14 00.13 (November 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

American Welding Society Nashville Section. Welding Procedure Development

American Welding Society Nashville Section. Welding Procedure Development American Welding Society Nashville Section Welding Procedure Development AWS & ASME Welding Procedures Welding Procedure Specification (WPS) Written document that provides direction to the welder for making

More information

a. Are the foundry s employees trained and familiar with portions of the system applicable to their position?

a. Are the foundry s employees trained and familiar with portions of the system applicable to their position? NAV 29 FOUNDRY OPERATIONS 1. Does the foundry have a documented quality system? a. Are the foundry s employees trained and familiar with portions of the system applicable to their position? b. What recognized

More information

Quality Management System

Quality Management System Quality Management System 6.1 Quality Q-Codes () 6.1 Quality Q-Codes Quality Clauses The following quality control clauses apply when specifically noted on the Gear Technology purchase order: Q1- Material

More information

WELDING ENGINEERING FABRICATION

WELDING ENGINEERING FABRICATION WELDING ENGINEERING FABRICATION Safety Our safety department is structured for optimal safety performance, communication and coverage. Safety is our top priority Our management team has over 280 years

More information

QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision # by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure

QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision # by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure 1.0 Scope: QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision #6 03-04-2016 by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure The purpose of this procedure is to define

More information

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi

M. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi The Code is a large document and it is sometimes very difficult to understand. Even for many of us who work with it every day. In my opinion there is no one person who could be termed as a Code Expert.

More information

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS p 1 of 6 UF-1 UF-12 PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGING the test temperature be higher than 20 F ( 29 C). Certification is required. An ultrasonic examination shall be made

More information

ASME B31.3 Process Piping

ASME B31.3 Process Piping ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 1 Piping Development Process 1. Establish applicable system

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

Presented by: Gary Scribner Manager of Technical Services. August The National Board of Boiler and Pressure Vessel Inspectors

Presented by: Gary Scribner Manager of Technical Services. August The National Board of Boiler and Pressure Vessel Inspectors Presented by: Gary Scribner Manager of Technical Services August 2016 2 3 PART 3, SECTION 1 REPAIRS AND ALTERATIONS GENERAL AND ADMINISTRATIVE REQUIREMENTS Additional administrative rules can be found

More information

METHOD STATEMENT FOR PIPE WELDING WORKS

METHOD STATEMENT FOR PIPE WELDING WORKS METHOD STATEMENT FOR PIPE WELDING WORKS Introduction This Method statement describes in detail the welding process for pipe work and the welder s qualification test procedures. This includes addressing

More information

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017 Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program

More information

KOPETZ BUSINESS PROCESS MAP LEVEL 1 INQUIRY TO DELIVERY

KOPETZ BUSINESS PROCESS MAP LEVEL 1 INQUIRY TO DELIVERY KOPETZ BUSINESS PROCESS MAP LEVEL 1 INQUIRY TO DELIVERY Sales Quality Accounting Shipping Receiving Purchasing Engineering Estimating Control Acquire Order Initiate Job Initiate Job Purchase,, and Approve

More information

GUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME RP CERTIFICATE OF AUTHORIZATION. The American Society of Mechanical Engineers

GUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME RP CERTIFICATE OF AUTHORIZATION. The American Society of Mechanical Engineers GUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME RP CERTIFICATE OF AUTHORIZATION The American Society of Mechanical Engineers Two Park Avenue New York, NY 10016 BPV GUI 04 11 08 2017 0 P age

More information

Guide for AWS Visual Weld Inspection

Guide for AWS Visual Weld Inspection Guide for Visual Weld Overview & Contents Scope This guide is intended to assist Owner/Operators, Contractors, Authority Having Jurisdiction (AHJ) personnel, Inspectors, Manufacturers and Contractors/Fabricators

More information

Quality Assurance in the Amusement Industry CLARK WESTERFIELD

Quality Assurance in the Amusement Industry CLARK WESTERFIELD Quality Assurance in the Amusement Industry 1 CLARK WESTERFIELD General Overview Steps to building a successful QA Program Put Someone in Charge with Authority to Act Understand the Basic Requirements

More information

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 1.0 SCOPE This document establishes the quality program requirements for an organization providing engineering

More information

Quality Control and Quality Assurance for Installation of Steel Deck

Quality Control and Quality Assurance for Installation of Steel Deck s American National standards institute/ steel deck institute QA/QC - 2011 Standard for Quality Control and Quality Assurance for Installation of Steel Deck copyright 2012 steel deck institute 1. General

More information

API-582. a practical approach for industrial welding practices. All rights reserved to thepetrostreet team

API-582. a practical approach for industrial welding practices. All rights reserved to thepetrostreet team Recommended Welding Guidelines API-582 a practical approach for industrial welding practices By The PetroStreet Team CONTENTS Key Sections: Θ Section 6 WELDING CONSUMABLES Θ Section 7 SHIELDING AND PURGING

More information

Page 1 / 11. Version 0 June 2014

Page 1 / 11. Version 0 June 2014 Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning

More information

EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL

EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL Revision: 6 Date 05/18/09 EPICOR, INCORPORATED 1414 E. Linden Avenue P.O. Box 1608 Linden, NJ. 07036-0006 Tel. 1-908-925-0800 Fax 1-908-925-7795 Table of Contents:

More information

ROTEK. IIInnInstI Instrument Corp. ISO 9001 Quality System Manual

ROTEK. IIInnInstI Instrument Corp. ISO 9001 Quality System Manual ROTEK IIInnInstI Instrument Corp. ISO 9001 Quality System Manual QSM900100-01 REV O MANUAL NO: 10 ISSUED TO: Rotek Web Site DATE OF ISSUE: 17 July 2002 APPROVALS: ORIGINATOR: Lawrence E. Weissbach Lawrence

More information

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications

More information

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service 1

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service 1 Designation: A 234/A 234M 02 Used in USDOE-NE Standards An American National Standard Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature

More information

Definitions contained in the above mentioned document and industry regulations are applicable herein.

Definitions contained in the above mentioned document and industry regulations are applicable herein. Quality Specification TEC-1021 21May12 Rev E Global Quality Management System Supplement for Various International Nuclear Quality Assurance Criteria, Regulations, and Requirements 1. SCOPE 1.1. Content

More information

DIVISION: METALS SECTION: STRUCTURAL STEEL FRAMING REPORT HOLDER: CAST CONNEX CORPORATION

DIVISION: METALS SECTION: STRUCTURAL STEEL FRAMING REPORT HOLDER: CAST CONNEX CORPORATION 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3031 Reissued 12/2017 This report is subject to renewal 12/2019. DIVISION: 05 00

More information

REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017

REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017 REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017 G. MANENTI, V. PESCUMA AND S. SARTI, ALFA LAVAL OLMI SPA, ITALY, PROVIDE AN OVERVIEW OF THE DELIVERY SCHEDULE FOR A KEY PIECE OF HEAT TRANSFER EQUIPMENT, PROCESS

More information

Available online at ScienceDirect. Procedia Engineering 86 (2014 )

Available online at  ScienceDirect. Procedia Engineering 86 (2014 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 86 (2014 ) 539 545 1st International Conference on Structural Integrity, ICONS-2014 Optimization of Integrity Testing of Piping

More information

Gas Transmission and Distribution Piping Systems

Gas Transmission and Distribution Piping Systems ASME B31.8-2007 (Revision of ASME B31.8-2003) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 AN AMERICAN NATIONAL STANDARD Three Park Avenue New York, NY 10016 CONTENTS

More information

REFERENCE SYLLABUS. for WELDING EXAMINER & WELDING EXAMINER IN TRAINING CERTIFICATES OF COMPETENCY EXAMINATIONS

REFERENCE SYLLABUS. for WELDING EXAMINER & WELDING EXAMINER IN TRAINING CERTIFICATES OF COMPETENCY EXAMINATIONS WELDING EXAMINER & CERTIFICATES OF COMPETENCY S AB-94 Edition 1, Revision 6, 2016-05-01 This syllabus is being phased out and will be discontinued on April 30, 2018. GENERAL INFORMATION INTRODUCTION: This

More information

IADC GLOBAL SUPPLY CHAIN COMMITTEE

IADC GLOBAL SUPPLY CHAIN COMMITTEE IADC GLOBAL SUPPLY CHAIN COMMITTEE Manufacturing Record Book Guidance (GU-IADC-SC-004) Effective date 1-January-2017 Copyrighted 2016, IADC Unlimited license is hereby granted for reproduction of this

More information

Qualification scheme for welders of aluminium alloys

Qualification scheme for welders of aluminium alloys (March 2009) Qualification scheme for welders of aluminium alloys 1. Scope 1.1 This document provides guidance for a qualification scheme for welders intended to be engaged in welding of aluminium alloys

More information

AAR SPECIFICATION M-214 INSPECTION CHECKLIST

AAR SPECIFICATION M-214 INSPECTION CHECKLIST AAR SPECIFICATION INSPECTION CHECKLIST I. ORGANIZATION 1. Is there separation between quality control and production responsibility? 2. Are there procedures for qualifying supervisors and methods of training

More information

General Document or OQE Comments SAT UNSAT

General Document or OQE Comments SAT UNSAT 4 Quality Management System 4.2.2 Quality Manual (A) Has a Quality Manual been developed that includes the scope of the QMS, the documented procedures established for Section 2 #1 the QMS, and a description

More information

Conformity Assessment. Dan Cheetham BPV Topics of Interest 2016 Certification 360

Conformity Assessment. Dan Cheetham BPV Topics of Interest 2016 Certification 360 Conformity Assessment Dan Cheetham BPV Topics of Interest 2016 Certification 360 BPV Requirements Boiler and Pressure Vessel Requirements (Quality Control Programs, Materials, Examination & Inspection,

More information

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service 1

Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service 1 Designation: A 420/A 420M 07 Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service This standard is issued under the fixed designation A 420/A 420M;

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

Vogt Valves The Connection Bulletin for Post Weld Heat Treatment of Socket Weld Valves CB 20

Vogt Valves The Connection Bulletin for Post Weld Heat Treatment of Socket Weld Valves CB 20 The Connection Bulletin for Post Weld Heat Treatment of Socket Weld Valves CB 20 Post Weld Heat Treatment of Socket Weld Valves Flow Control Division INTRODUCTION Some manufacturing and user construction

More information

Washington Association of Building Officials. Standard 1702 Steel Fabricator Registration Program

Washington Association of Building Officials. Standard 1702 Steel Fabricator Registration Program Washington Association of Building Officials Standard 1702 Steel Fabricator Registration Program July 2010 1 Steel Fabricator Registration Program Scope: This registration program was developed to assist

More information

ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL AC172. April 2017 (Effective June 1, 2017) PREFACE

ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL AC172. April 2017 (Effective June 1, 2017) PREFACE ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL April 2017 (Effective June 1, 2017) PREFACE The attached accreditation criteria have been issued to provide all interested

More information

Foreword. Welding Fabrication Standards Page 1

Foreword. Welding Fabrication Standards Page 1 Welding Fabrication Standards Page 1 Foreword During the year 2004, workshops regarding the Leonardo Continued Project where held in certain European Countries with the participation of experts from the

More information

RECERTIFICATION OF WELL CONTROL EQUIPMENT

RECERTIFICATION OF WELL CONTROL EQUIPMENT RECOMMENDED PRACTICE DNV-RP-E101 RECERTIFICATION OF WELL CONTROL EQUIPMENT OCTOBER 2008 FOREWORD (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property and

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

EVANS CAPACITOR COMPANY

EVANS CAPACITOR COMPANY DISTRIBUTION LIST: Location Book # Quality Manager 0001 President 0002 CEO 0003 Engineering Manager 0004 Production Manager 0005 Office Manager 0006 Page 1 of 33 REV A 11/18/03 TABLE OF CONTENTS Page Distribution

More information

PPI/TZ Standard Quality Requirements for Suppliers -SQRS-

PPI/TZ Standard Quality Requirements for Suppliers -SQRS- PPI/TZ Standard Quality Requirements for Suppliers -SQRS- AS9100, ISO 13485 and ISO 9001 Revision: March 19, 2014 For questions concerning Standard Quality Requirements for Supplier (SQRS), please contact

More information

PMA Quality Assurance Manual Rev. 2 Date 12 Feb 2016

PMA Quality Assurance Manual Rev. 2 Date 12 Feb 2016 PMA Quality Assurance Manual Date Aviation Technical Services, Inc. 3121 109 th Street SW Everett, WA 98204 425-423-3371 2600 West Casino Road Everett, WA 98204 10315 Airport Road Everett, WA 98204 www.atsmro.com

More information

CONNECTION BULLETIN. Vogt Valves. Experience In Motion. Post Weld Heat Treatment of Socket Weld Valves. FCD VVABR /05 (Replaces CB-20)

CONNECTION BULLETIN. Vogt Valves. Experience In Motion. Post Weld Heat Treatment of Socket Weld Valves. FCD VVABR /05 (Replaces CB-20) CONNECTION BULLETIN Vogt Valves Post Weld Heat Treatment of Socket Weld Valves FCD VVABR1020-00 01/05 (Replaces CB-20) Experience In Motion Post Weld Heat Treatment of Socket Weld Valves Introduction Some

More information

ASME B31.3 Process Piping. 19. What s Different in B31.1

ASME B31.3 Process Piping. 19. What s Different in B31.1 ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. What s Different in B31.1-1 19. What s Different in B31.1 Scope Organization of the Code

More information

API 653 Training Course

API 653 Training Course API 653 Training Course The API 653 Classes consist of "Pre-Course Home Study" materials and "5 days of Classroom" instructor lead training. Registration for the API 653 Training Course should be received

More information

Pressure Piping Construction Requirements

Pressure Piping Construction Requirements the pressure equipment safety authority Pressure Piping Construction Requirements AB 518 Edition 8, Revision 0 Issued 2017-08-24 Table of Contents FOREWORD... 1 1.0 SCOPE OF THIS DOCUMENT... 2 2.0 DEFINITIONS

More information

Conformity Assessment. Dan Cheetham BPV Requirements 4/12/16

Conformity Assessment. Dan Cheetham BPV Requirements 4/12/16 Conformity Assessment Dan Cheetham BPV Requirements 4/12/16 BPV Requirements Boiler and Pressure Vessel Requirements (Quality Control Programs, Materials, Examination & Inspection, etc.) Quality Control

More information

SOLAR KEYMARK SPECIFIC SCHEME RULES ANNEX E: FACTORY PRODUCTION CONTROL INFORMATIVE BASED ON ISO 9001 STANDARD COVERING THE PRODUCTION LINE

SOLAR KEYMARK SPECIFIC SCHEME RULES ANNEX E: FACTORY PRODUCTION CONTROL INFORMATIVE BASED ON ISO 9001 STANDARD COVERING THE PRODUCTION LINE SOLAR KEYMARK SPECIFIC SCHEME RULES ANNEX E: FACTORY PRODUCTION CONTROL INFORMATIVE BASED ON ISO 9001 STANDARD COVERING THE PRODUCTION LINE 1. General This annex specifies the requirements for the Factory

More information

Chrome Moly flanges and fittings

Chrome Moly flanges and fittings Chrome Moly flanges and fittings PRO Alloy is Europe s leading stockholder for Stainless, Duplex, Super Duplex, Chrome Moly flanges and fittings. introduction Our inventory consists of a complete range

More information

IADC GLOBAL SUPPLY CHAIN COMMITTEE. Manufacturing Record Book Guidance (GU-IADC-SC-004) Rev. 1

IADC GLOBAL SUPPLY CHAIN COMMITTEE. Manufacturing Record Book Guidance (GU-IADC-SC-004) Rev. 1 IADC GLOBAL SUPPLY CHAIN COMMITTEE Manufacturing Record Book Guidance (GU-IADC-SC-004) Rev. 1 1 Copyrighted 2017, IADC Unlimited license is hereby granted for reproduction of this document in its entirety,

More information

Quality Supplier Requirements for Beckwith Electric Co., Inc.

Quality Supplier Requirements for Beckwith Electric Co., Inc. Quality Supplier Requirements for Beckwith Electric Co., Inc. This Page Left Intentionally Blank To Our Valued Suppliers: One of the primary goals of Beckwith Electric is to provide the highest Quality

More information

"Welder Certification"

Welder Certification "Welder Certification" The purpose of this presentation is to introduce you to the various aspects of welder certification. This is not intended to cover all of the requirements for certification but only

More information

AASHTO/AWS D1.5M/D1.5:2008. Table of Contents

AASHTO/AWS D1.5M/D1.5:2008. Table of Contents Table of Contents Personnel...v Foreword...ix List of Tables... xviii List of Figures...xix List of Forms...xxi 1. General Provisions...1 1.1 Application...1 1.2 Base Metal...1 1.3 Welding Processes...1

More information

QUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A

QUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A Page 1 1 of 57 President Design Engineering Production Production Engineering Materials Control Purchasing Service Marketing Sales Contracts Human Resources Quality Assurance Quality Control Production

More information

Counterfeit Parts Prevention

Counterfeit Parts Prevention Counterfeit Parts Prevention 1.0 Purpose The purpose of this document is to describe the process performed to prevent the purchase and / or use of Counterfeit Parts and to outline the Detection, Mitigation

More information

SUPPLIER QUALITY SYSTEM SURVEY

SUPPLIER QUALITY SYSTEM SURVEY SUPPLIER QUALITY SYSTEM SURVEY DATE (M/d/yy): 55 Dragon Court Woburn, MA 01801 Tel: (781) 933-7300 Fax: (781) 935-4529 GENERAL INFORMATION Supplier Name: Physical Address: City: State: Zip: Sr. Company

More information

SYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION. Effective From :- UNDER DEVELOPMENT.

SYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION. Effective From :- UNDER DEVELOPMENT. SYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION Effective From :- UNDER DEVELOPMENT Prepared by: Curriculum development cell Institute of Research Development & Training,

More information

PPQ Requirements training pack for suppliers

PPQ Requirements training pack for suppliers PPQ Requirements training pack for suppliers 1 Purpose This appendix serves to define the concept of PPQ elements used within the PPQ process, and replace for Montreal a portion of Section B of EBQR. The

More information

EPRI QUALITY PROGRAM MANUAL

EPRI QUALITY PROGRAM MANUAL Controlled Copy No. : If no Controlled Copy No. is assigned; this copy is uncontrolled EPRI QUALITY PROGRAM MANUAL REVISION 13 Effective TOC: TABLE OF CONTENTS Sec. Title Page SUMMARY OF CHANGES... 2 Mapping

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS

More information

Spec 5CT 7th General Is WT control required for Grade K-55 seamless casing with additional SR2 requirements?

Spec 5CT 7th General Is WT control required for Grade K-55 seamless casing with additional SR2 requirements? Series 5 : Tubular Goods Last revised 3/27/06 Standard Edition Section Question Answer 7th 7th 8.8.2 & 8.8.3 As per paragraph 8.8.3 (Groups 3 and 4) of API 5CT the groove on the inside weld surface shall

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD ISO 15761 First edition 2002-12-15 Steel gate, globe and check valves for sizes DN 100 and smaller, for the petroleum and natural gas industries Robinets-vannes, robinets à soupape

More information

Manufacture of welded products - Welding workshop

Manufacture of welded products - Welding workshop CLASS PROGRAMME Approval of manufacturers DNVGL-CP-0352 Edition April 2016 Manufacture of welded products - Welding workshop The electronic pdf version of this document, available free of charge from http://www.dnvgl.com,

More information

The Master of Master Distribution

The Master of Master Distribution The Master of Master Distribution Stainless and Special Metals Pipe and Tubing Pipe Fittings Pipe Flanges Valves Supplying stainless products to industrial distributors since 1963 MASTER OF MASTER DISTRIBUTION

More information

Qualification scheme for welders of hull structural steels

Qualification scheme for welders of hull structural steels (Sept 2016) Qualification scheme for welders of hull structural steels 1. Scope 1.1 This document gives requirements for a qualification scheme for welders intended to be engaged in the fusion welding

More information

LT Industries SQFR 101

LT Industries SQFR 101 Page 1 of 5 LT Industries SQFR 101 Supplier Quality Flow down Requirements 1.0 GENERAL REQUIREMENTS: The supplier must flow down these requirements from LTI to their sub tier suppliers whenever those sub

More information

Anchor chain cables and accessories

Anchor chain cables and accessories CLASS PROGRAMME Approval of manufacturers DNVGL-CP-0254 Edition May 2016 The content of this service document is the subject of intellectual property rights reserved by ("DNV GL"). The user accepts that

More information

QW-482 WELDING PROCEDURE SPECIFICATION (WPS)

QW-482 WELDING PROCEDURE SPECIFICATION (WPS) QW-482 WELDING PROCEDURE SPECIFICATION (WPS) Company Name: J.T. Thorpe & Son, Inc. By: J. Jacob Dupree, P.E., Q.C. Manager Welding Procedure Specification No.: JTT-22-STUD Revision No. 0 Date: 4/15/2009

More information

NUMBER OF EMPLOYEES TOTAL ENGINEERING MANUFACTURING QUALITY SUPPLIER IN-HOUSE SPECIAL PROCESS CAPABILITIES

NUMBER OF EMPLOYEES TOTAL ENGINEERING MANUFACTURING QUALITY SUPPLIER IN-HOUSE SPECIAL PROCESS CAPABILITIES Kearfott/ACA SUPPLIER QUALITY SYSTEM SURVEY SUPPLIER NAME SUPPLIER CODE DATE ADDRESS & ZIP CODE AREA CODE & PHONE QUALITY MANAGEMENT (NAME & TITLE) PRODUCT LINE (DESCRIBE) NUMBER OF EMPLOYEES TOTAL ENGINEERING

More information

APPENDIX B Corrosion Management System Framework and Guidance

APPENDIX B Corrosion Management System Framework and Guidance APPENDIX B Corrosion Management System Framework and B.1 INTRODUCTION A framework for a Corrosion Management System (CMS) for assets is described in this Appendix. The CMS developed shall include and document

More information

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS TUBE TURNS INSULATED JOINTS are a pre-fabricated, non-separable, union used to isolate specific sections of pipelines

More information

INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1

INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1 TAKING PRESSURE VESSELS FROM CRADLE TO GRAVE SEMINAR INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1 Manish Waghare ABSG Consulting Inc., Singapore January 28, 2011 May 29, 2011 1 Presentation

More information

Quality Guideline for Suppliers. 1. Purpose

Quality Guideline for Suppliers. 1. Purpose Quality Guideline for Suppliers 1. Purpose The Quality Guideline (QGL) of Aumann Beelen GmbH forms an integral part of the purchase orders and is thus binding for all Suppliers, hereinafter referred to

More information

Rosen Aviation Supplier Quality Assurance Requirements

Rosen Aviation Supplier Quality Assurance Requirements 1. Purpose This document establishes the Quality Assurance Requirements for all Rosen Suppliers. This document is applicable to all Rosen Aviation Purchase Orders (POs). In addition to the requirements

More information