REPORT ON ROOT CAUSE ANALYSIS & CORRECTIVE ACTION FOR LEAKAGE IN WELD JOINT
|
|
- Frank Ross
- 6 years ago
- Views:
Transcription
1 REPORT ON ROOT CAUSE ANALYSIS & CORRECTIVE ACTION FOR LEAKAGE IN WELD JOINT Team Members: S. Rangaprasad Sr.DGM, Manufacturing M.K. Baranidharan DGM, Quality control M Gunasekaran DGM, Quality Assurance E Kallathieppan AGM, Manufacturing Raja Chacko Manager, Quality Control S. Suriyanarayanan- Manager, Design S.Pradeep Welding Engineer S.M. Balaji Sr. Engineer Quality Control Date: 07-JULY-2015 Ref: Customer Complaint No: LT Dated: 01-JUN-2015 Page 1 of 10
2 CONTENTS CONTENTS 1) Background 2) Preliminary Analysis & Interim Containment Action a) Verifications at L&T Valves Factory b) Verifications during assembly c) Correction at site 3) Root Cause Analysis a) Problem Description b) Sequence of events c) Cause and Effect Diagram d) Significant Causes e) Why- Why analysis 4) Corrective action Page 2 of 10
3 1.0 Background Observations: Weld leak Valve Body and pipe joint(refer image) in 6"2500SPL GATE WC6 T5 BW IBR PRVBT ACT BPM during commissioning. Page 3 of 10
4 Supplied Valve Details: 2 Valves of 6"2500SPL GATE WC6 T5 BW IBR PRVBT ACT BPM supplied to Rajpura boiler 1 No each to Unit 1 & Unit 2. Complaint received in valve supplied to Unit 1 &2. Project Valve Type Rajpura Boiler Gate Valve size 6 Class Material Quantity Main valve serial no Tag number 2500SPL WC6 2 No s C & C HCB01AA001 & 02HCB01AA001 Customer P.O LMB/F04/ /JPS(U-1&2) / 164 L&T Valves Sale Order Bypass valve /9770 & /6670 DN20 CL 2500 SPL F22 T-Globe valve (By pass) Pipe detail 3/4 P22 SCH XXS Pipe 2. Preliminary Analysis & Interim Containment Action: a) Verifications at L&T Valves Factory The following documents were verified and found in order: Page 4 of 10 Valve test reports (Quality dossiers) Pre Dispatch Inspection Report Final inspection report Internal valve test report Valve Assembly Record Receiving Inspection Reports
5 Material test certificate from BOF suppliers Review of Gear Unit Test Certificate We have verified the Quality records of the following manufacturing stages 1) Valve serial no: C / C Body Heat no: B12467 / B Foundry: Ultimate Alloys. 2) ANSI area coverage done in the Body casting & found accepted (RT No: UA / UA12-577) 3) 3/4 pipe received & found meeting the material specification(supplier: Sumitomo metal, Japan) 4) Test certificate, Valve test report made 5) Welding done as per approved WPS. Preheating, PWHT done as per approved procedures 6) DP test carried on the weld surface and found no significant indication noticed. 7) Pressure test done as per approved GAD & witnessed by LMB TPI Valve Serial No C ) SCN (Stores Credit Note) done after inspection at per L&T procedures & valves were cleared to painting. Before dispatch (PDI) inspection carried out & cleared. 2.0 Correction: Proposed to remove the defective weld portion at leak area up to pipe wall thickness and perform welding as per approved WPS. On completion of repair weld, PWHT of weld joint & NDE-PT shall be carried out on the surface of the weld. Page 5 of 10
6 3.0 Root Cause Analysis: a) Problem Description DESCRIPTION AREA DESCRIPTION What object has the defect Gate Valve WHAT What is the defect? Weld Leak WHERE Where specifically on the valve do you see the defect? Where geographically is the object observed? First seen - By the customer? Leakage thro weld joint (Leakage noticed inbetween Body & pipe weld joint) At customer site Rajpura, Punjab. Yes WHEN HOW BIG Similar Parts When seen since? When is the observation seen in the valve- while site, operation (i.e. when the valve is used)? When is the observation seen in the life of the object?(eg. when new or after few years of service) How many objects have noticed this observation? How many/much observation(s) per object While operation After the 6 month service Two valve One Page 6 of 10
7 CAUSE AND EFFECT DIAGRAM - DEFINE & VERIFY ROOT CAUSE METHODS/PROCESSES MACHINE Improper surface cleaning (scale/oily surface) Preheat & Post heat ment cycle not done as per approved procedure Unqualified welder Lack of Awareness on WPS/PQR Ammeter & voltmeter used in welding machine not calibrated Visual inspection of weld joints not done Inspection NDE method not performed Unapproved welding consumables used interpass temperature not maintained properly Leakage thro weld joint between Body & pipe Lack of fusion Pipe material grade not meeting specification MAN MATERIALS Page 7 of 10
8 S No CAUSES SIGNIFICANT / IN- SIGNIFICANT 1 Improper surface cleaning (scale/oily surface) Insignificant 2 Preheat & Post heat meant cycle not done as per approved procedure Insignificant 3 Ammeter & voltmeter used in welding machine not calibrated Insignificant 4 Visual inspection of weld joints not done Insignificant 5 Inspection NDE method not performed Insignificant 6 Interpass temperature not maintained properly Insignificant 7 Unqualified welder Insignificant 8 Lack of Awareness on WPS/PQR InSignificant 9 Lack of fusion Significant 10 Unapproved welding consumables used Insignificant 11 Pipe material grade not meeting specification Insignificant Page 8 of 10
9 S No CAUSES Verification status 1 Improper surface cleaning (scale/oily surface) 2 Preheat & Post heat ment cycle not done as per approved procedure 3 Ammeter & voltmeter used in welding machine not calibrated 4 Visual inspection of weld joints not done 5 Inspection NDE method not performed 6 Interpass temperature not maintained properly Base materials are cleaned properly before start of welding process & scales/oil if any are removed. Heat treatment process carried out as per approved WPS Ammeter & voltmeter used in welding machine are calibrated at periodic intervals as per calibration plan Visual inspection performed after PRV welding by qualified inspectors. Again inspected before clearing to painting in valve & in PDI (Pre Despatch Inspection) NDE-PT performed & cleared Temperature measured using Themal chalk & infrared temperature measurement gauge & welding performed. By this interpass temperature maintained as per approved WPS 7 Unqualified welder Welders are qualified as per the WPS & PQR & approval given for welding. Approved welders are only utilized to perform welding 8 Lack of Awareness on WPS/PQR Training given to all welders & briefed on WPS & PQR requirements. WPS & PQR display made in weld shop for better communication 9 Lack of fusion Found having lack of bonding between Weld metal & base metal 10 Unapproved welding consumables used 11 Pipe material grade not meeting specification Welding consumables procured from approved sources only Chemical & mechanical properties verified by supplier & Material Test certificate given. At L&T valves, material confirmation done using PMI & ensured Page 9 of 10
10 WHY WHY ANALYSIS Significant Cause / : lack of fusion in the weld Nonconformance Why? Lack of bonding due to welding work Why?? Non control on welding parameter Why? Lack of awareness of Welding operator Root Cause: Lack of awareness of Welding operator 4.0 Corrective action: Based on the above, the following corrective actions are suggested: a) Retraining to be given to welders to communicate on the process control measures to be followed to avoid weld defects. b) Shell test to be done for extended duration (60 minutes) during internal testing at L&T valves for critical valves. Prepared by Reviewed & Approved by Raja Chacko M. Gunasekaran Date: Page 10 of 10
BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION
BODY OF KNOWLEDGE API-570 AUTHORIZED PIPING INSPECTOR CERTIFICATION EXAMINATION 2018 (Replaces February 2017) API Authorized Piping Inspectors must have a broad knowledge base relating to maintenance,
More informationPresented by: Gary Scribner Manager of Technical Services. Shanghai April The National Board of Boiler and Pressure Vessel Inspectors
Presented by: Gary Scribner Manager of Technical Services Shanghai April 2016 1. Provides administrative and technical rules, and guidelines to follow for repairing or altering a pressure retaining item.
More information2004 NBIC Interpretations
2004 NBIC Interpretations INTERPRETATION 04-23 Subject: Part RC 1110, RC-2050(c), RC-3030(c), RC-3031(e) Question 1: Does RC-1110 specifically require acceptance of the jurisdiction for alternative NDE
More informationINS QA Programme Requirements
Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued
More informationMaterials and Qualification Procedures for Ships
Materials and Qualification Procedures for Ships Approval of Works for the Manufacture of Fusion Welded Pressure Vessels Revision 4, July 2015 Page 1 of 17 Lloyd s Register Group Limited, its subsidiaries
More informationInspection and Test Plan for Gas Turbine
and Test Plan for Gas Turbine No. and Test Plan Reference Document Acceptance Criteria Verifying Document Activity By Remark Manuf. TPI Client 1 Pre Meeting Spec. Spec. MOM H H H Before Manufacturing 2
More informationWelding Performance Qualification Test Administrators GUIDE FOR APPLICANTS
BRITISH COLUMBIA SAFETY AUTHORITY Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS Prepared by: Ed Hurd P.Eng. Provincial Safety Manager, Boilers Date: March 2, 2012 Controlled
More informationQUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6
QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 WELDING HEAT TREATMENT PAGE 1 OF 6 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements for
More informationJOHN WOOD UNCONTROLLED COPY: THE JOHN WOOD COMPANY PO BOX HIGHLAND AVENUE OAKS, PENNSYLVANIA 19456
JOHN WOOD QUALITY CONTROL SYSTEM MANUAL FOR PRESSURE VESSELS CONSTRUCTED TO ASME BOILER & PRESSURE VESSEL CODE SECTION VIII, DIVISION 1 AND REPAIRS AND ALTERATIONS TO METALLIC PRESSURE RETAINING ITEMS
More informationInspection and Welding Repairs of Pressure Vessels
Inspection and Welding Repairs of Pressure Vessels BY S. V. GUPTE B.E., D.M.E. ASNT LEVEL III - RT,MT,PT,VT PRESSURE VESSEL INSPECTOR (API 510), (CCOE) PAINT AND COATING INSPECTOR (NACE INDIA) LEAD AUDITOR
More informationGuideline of the European Committee for Welding of Railway Vehicles - ECWRV ( ) - PART 2 Technical Interpretation of EN 15085
Guideline of the European Committee for Welding of Railway Vehicles - ECWRV (2016-09-07) - PART 2 Technical Interpretation of EN 15085 Contents 1 Introduction... 2 2 Interpretation of EN 15085-1... 2 3
More informationAWS D1.1 Structural Welding Code: You Specify It- Do You Know What It Really Says?
AWS D1.1 Structural Welding Code: You Specify It- Do You Know What It Really Says? Wesley J. Oliphant, PE, AWS-CWI, F.SEI, F.ASCE ReliaPOLE Inspection Services Company, LLC 1 All welding shall be done
More informationNR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26
Company Name/Certificate Number: Page 1 of 26 a. Organization a.1. Has the Organizational Structure of the program identified the levels of management responsible for the Quality System Program, including
More informationManagement System Requirements
Management System Requirements Identification, Recognition, Application IAEA Technical Meeting Grading of the Application of Management System Requirements Vienna, 23 27 January 2012 RWE Technology GmbH
More informationMEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator PERSONAL DATA LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS
104126-MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator Has 10 years experience in the field of inspection and quality assurance / control related to chemical, petrochemical, power plants
More informationMaterials and Qualification Procedures for Ships
Materials and Qualification Procedures for Ships Approval of a Foundry for the Manufacture of Steel Castings Revision 3, January 2015 Lloyd s Register Group Limited, its subsidiaries and affiliates and
More informationSECTION TAPPING SLEEVES AND VALVES
SECTION 33 12 16.17 TAPPING SLEEVES AND VALVES PART 1: GENERAL 1.01 SCOPE Furnish, install and test all tapping sleeves, tapping valves, and tapping saddles as shown on the Drawings. 1.02 RELATED WORK
More informationQUALIFICATION TESTING OF FIELD WELDERS
Page 1 of 9 Oklahoma DOT Materials & Testing December 5, 2003 (Updated to Reference 2009 Specifications 11/26/2012) (Added paragraph to the bottom of Roles and Responsibilities section. 11/14/2017) Publication:
More informationAccreditation of Hot Tap Organizations
Accreditation of Hot Tap Organizations TSSA Guide for Survey Teams Technical Standards & Safety Authority Boiler & Pressure Vessels Safety Division 3300 Bloor Street West 14 th Floor, Centre Tower, Etobicoke,
More informationPressure Equipment Repair and Alteration Requirements
the pressure equipment safety authority Pressure Equipment Repair and Alteration Requirements AB-513 Edition 3, Revision 0 - Issued 2018-01-30 Table of Contents FOREWORD... iii 1.0 INTRODUCTION... 1 2.0
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-05 14 00.13 (May 2015) -------------------------------- Preparing Activity: NASA Superseding UFGS-05 14 00.13 (November 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationAmerican Welding Society Nashville Section. Welding Procedure Development
American Welding Society Nashville Section Welding Procedure Development AWS & ASME Welding Procedures Welding Procedure Specification (WPS) Written document that provides direction to the welder for making
More informationa. Are the foundry s employees trained and familiar with portions of the system applicable to their position?
NAV 29 FOUNDRY OPERATIONS 1. Does the foundry have a documented quality system? a. Are the foundry s employees trained and familiar with portions of the system applicable to their position? b. What recognized
More informationQuality Management System
Quality Management System 6.1 Quality Q-Codes () 6.1 Quality Q-Codes Quality Clauses The following quality control clauses apply when specifically noted on the Gear Technology purchase order: Q1- Material
More informationWELDING ENGINEERING FABRICATION
WELDING ENGINEERING FABRICATION Safety Our safety department is structured for optimal safety performance, communication and coverage. Safety is our top priority Our management team has over 280 years
More informationQC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision # by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure
1.0 Scope: QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision #6 03-04-2016 by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure The purpose of this procedure is to define
More informationM. F. Sullivan. 9/27/2016 Dr. Sandor Somogyi
The Code is a large document and it is sometimes very difficult to understand. Even for many of us who work with it every day. In my opinion there is no one person who could be termed as a Code Expert.
More informationPART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS
p 1 of 6 UF-1 UF-12 PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGING the test temperature be higher than 20 F ( 29 C). Certification is required. An ultrasonic examination shall be made
More informationASME B31.3 Process Piping
ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 1 Piping Development Process 1. Establish applicable system
More informationSECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)
SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density
More informationPresented by: Gary Scribner Manager of Technical Services. August The National Board of Boiler and Pressure Vessel Inspectors
Presented by: Gary Scribner Manager of Technical Services August 2016 2 3 PART 3, SECTION 1 REPAIRS AND ALTERATIONS GENERAL AND ADMINISTRATIVE REQUIREMENTS Additional administrative rules can be found
More informationMETHOD STATEMENT FOR PIPE WELDING WORKS
METHOD STATEMENT FOR PIPE WELDING WORKS Introduction This Method statement describes in detail the welding process for pipe work and the welder s qualification test procedures. This includes addressing
More informationAssociation of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017
Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program
More informationKOPETZ BUSINESS PROCESS MAP LEVEL 1 INQUIRY TO DELIVERY
KOPETZ BUSINESS PROCESS MAP LEVEL 1 INQUIRY TO DELIVERY Sales Quality Accounting Shipping Receiving Purchasing Engineering Estimating Control Acquire Order Initiate Job Initiate Job Purchase,, and Approve
More informationGUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME RP CERTIFICATE OF AUTHORIZATION. The American Society of Mechanical Engineers
GUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME RP CERTIFICATE OF AUTHORIZATION The American Society of Mechanical Engineers Two Park Avenue New York, NY 10016 BPV GUI 04 11 08 2017 0 P age
More informationGuide for AWS Visual Weld Inspection
Guide for Visual Weld Overview & Contents Scope This guide is intended to assist Owner/Operators, Contractors, Authority Having Jurisdiction (AHJ) personnel, Inspectors, Manufacturers and Contractors/Fabricators
More informationQuality Assurance in the Amusement Industry CLARK WESTERFIELD
Quality Assurance in the Amusement Industry 1 CLARK WESTERFIELD General Overview Steps to building a successful QA Program Put Someone in Charge with Authority to Act Understand the Basic Requirements
More informationSQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018
SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 1.0 SCOPE This document establishes the quality program requirements for an organization providing engineering
More informationQuality Control and Quality Assurance for Installation of Steel Deck
s American National standards institute/ steel deck institute QA/QC - 2011 Standard for Quality Control and Quality Assurance for Installation of Steel Deck copyright 2012 steel deck institute 1. General
More informationAPI-582. a practical approach for industrial welding practices. All rights reserved to thepetrostreet team
Recommended Welding Guidelines API-582 a practical approach for industrial welding practices By The PetroStreet Team CONTENTS Key Sections: Θ Section 6 WELDING CONSUMABLES Θ Section 7 SHIELDING AND PURGING
More informationPage 1 / 11. Version 0 June 2014
Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning
More informationEPICOR, INCORPORATED QUALITY ASSURANCE MANUAL
EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL Revision: 6 Date 05/18/09 EPICOR, INCORPORATED 1414 E. Linden Avenue P.O. Box 1608 Linden, NJ. 07036-0006 Tel. 1-908-925-0800 Fax 1-908-925-7795 Table of Contents:
More informationROTEK. IIInnInstI Instrument Corp. ISO 9001 Quality System Manual
ROTEK IIInnInstI Instrument Corp. ISO 9001 Quality System Manual QSM900100-01 REV O MANUAL NO: 10 ISSUED TO: Rotek Web Site DATE OF ISSUE: 17 July 2002 APPROVALS: ORIGINATOR: Lawrence E. Weissbach Lawrence
More informationNRC INSPECTION MANUAL INSPECTION PROCEDURE 35065
NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications
More informationStandard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service 1
Designation: A 234/A 234M 02 Used in USDOE-NE Standards An American National Standard Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature
More informationDefinitions contained in the above mentioned document and industry regulations are applicable herein.
Quality Specification TEC-1021 21May12 Rev E Global Quality Management System Supplement for Various International Nuclear Quality Assurance Criteria, Regulations, and Requirements 1. SCOPE 1.1. Content
More informationDIVISION: METALS SECTION: STRUCTURAL STEEL FRAMING REPORT HOLDER: CAST CONNEX CORPORATION
0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3031 Reissued 12/2017 This report is subject to renewal 12/2019. DIVISION: 05 00
More informationREPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017
REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017 G. MANENTI, V. PESCUMA AND S. SARTI, ALFA LAVAL OLMI SPA, ITALY, PROVIDE AN OVERVIEW OF THE DELIVERY SCHEDULE FOR A KEY PIECE OF HEAT TRANSFER EQUIPMENT, PROCESS
More informationAvailable online at ScienceDirect. Procedia Engineering 86 (2014 )
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 86 (2014 ) 539 545 1st International Conference on Structural Integrity, ICONS-2014 Optimization of Integrity Testing of Piping
More informationGas Transmission and Distribution Piping Systems
ASME B31.8-2007 (Revision of ASME B31.8-2003) Gas Transmission and Distribution Piping Systems ASME Code for Pressure Piping, B31 AN AMERICAN NATIONAL STANDARD Three Park Avenue New York, NY 10016 CONTENTS
More informationREFERENCE SYLLABUS. for WELDING EXAMINER & WELDING EXAMINER IN TRAINING CERTIFICATES OF COMPETENCY EXAMINATIONS
WELDING EXAMINER & CERTIFICATES OF COMPETENCY S AB-94 Edition 1, Revision 6, 2016-05-01 This syllabus is being phased out and will be discontinued on April 30, 2018. GENERAL INFORMATION INTRODUCTION: This
More informationIADC GLOBAL SUPPLY CHAIN COMMITTEE
IADC GLOBAL SUPPLY CHAIN COMMITTEE Manufacturing Record Book Guidance (GU-IADC-SC-004) Effective date 1-January-2017 Copyrighted 2016, IADC Unlimited license is hereby granted for reproduction of this
More informationQualification scheme for welders of aluminium alloys
(March 2009) Qualification scheme for welders of aluminium alloys 1. Scope 1.1 This document provides guidance for a qualification scheme for welders intended to be engaged in welding of aluminium alloys
More informationAAR SPECIFICATION M-214 INSPECTION CHECKLIST
AAR SPECIFICATION INSPECTION CHECKLIST I. ORGANIZATION 1. Is there separation between quality control and production responsibility? 2. Are there procedures for qualifying supervisors and methods of training
More informationGeneral Document or OQE Comments SAT UNSAT
4 Quality Management System 4.2.2 Quality Manual (A) Has a Quality Manual been developed that includes the scope of the QMS, the documented procedures established for Section 2 #1 the QMS, and a description
More informationConformity Assessment. Dan Cheetham BPV Topics of Interest 2016 Certification 360
Conformity Assessment Dan Cheetham BPV Topics of Interest 2016 Certification 360 BPV Requirements Boiler and Pressure Vessel Requirements (Quality Control Programs, Materials, Examination & Inspection,
More informationStandard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service 1
Designation: A 420/A 420M 07 Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low-Temperature Service This standard is issued under the fixed designation A 420/A 420M;
More informationGENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS
- June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS
More informationVogt Valves The Connection Bulletin for Post Weld Heat Treatment of Socket Weld Valves CB 20
The Connection Bulletin for Post Weld Heat Treatment of Socket Weld Valves CB 20 Post Weld Heat Treatment of Socket Weld Valves Flow Control Division INTRODUCTION Some manufacturing and user construction
More informationWashington Association of Building Officials. Standard 1702 Steel Fabricator Registration Program
Washington Association of Building Officials Standard 1702 Steel Fabricator Registration Program July 2010 1 Steel Fabricator Registration Program Scope: This registration program was developed to assist
More informationACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL AC172. April 2017 (Effective June 1, 2017) PREFACE
ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL April 2017 (Effective June 1, 2017) PREFACE The attached accreditation criteria have been issued to provide all interested
More informationForeword. Welding Fabrication Standards Page 1
Welding Fabrication Standards Page 1 Foreword During the year 2004, workshops regarding the Leonardo Continued Project where held in certain European Countries with the participation of experts from the
More informationRECERTIFICATION OF WELL CONTROL EQUIPMENT
RECOMMENDED PRACTICE DNV-RP-E101 RECERTIFICATION OF WELL CONTROL EQUIPMENT OCTOBER 2008 FOREWORD (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property and
More informationCQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,
More informationEVANS CAPACITOR COMPANY
DISTRIBUTION LIST: Location Book # Quality Manager 0001 President 0002 CEO 0003 Engineering Manager 0004 Production Manager 0005 Office Manager 0006 Page 1 of 33 REV A 11/18/03 TABLE OF CONTENTS Page Distribution
More informationPPI/TZ Standard Quality Requirements for Suppliers -SQRS-
PPI/TZ Standard Quality Requirements for Suppliers -SQRS- AS9100, ISO 13485 and ISO 9001 Revision: March 19, 2014 For questions concerning Standard Quality Requirements for Supplier (SQRS), please contact
More informationPMA Quality Assurance Manual Rev. 2 Date 12 Feb 2016
PMA Quality Assurance Manual Date Aviation Technical Services, Inc. 3121 109 th Street SW Everett, WA 98204 425-423-3371 2600 West Casino Road Everett, WA 98204 10315 Airport Road Everett, WA 98204 www.atsmro.com
More informationCONNECTION BULLETIN. Vogt Valves. Experience In Motion. Post Weld Heat Treatment of Socket Weld Valves. FCD VVABR /05 (Replaces CB-20)
CONNECTION BULLETIN Vogt Valves Post Weld Heat Treatment of Socket Weld Valves FCD VVABR1020-00 01/05 (Replaces CB-20) Experience In Motion Post Weld Heat Treatment of Socket Weld Valves Introduction Some
More informationASME B31.3 Process Piping. 19. What s Different in B31.1
ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. What s Different in B31.1-1 19. What s Different in B31.1 Scope Organization of the Code
More informationAPI 653 Training Course
API 653 Training Course The API 653 Classes consist of "Pre-Course Home Study" materials and "5 days of Classroom" instructor lead training. Registration for the API 653 Training Course should be received
More informationPressure Piping Construction Requirements
the pressure equipment safety authority Pressure Piping Construction Requirements AB 518 Edition 8, Revision 0 Issued 2017-08-24 Table of Contents FOREWORD... 1 1.0 SCOPE OF THIS DOCUMENT... 2 2.0 DEFINITIONS
More informationConformity Assessment. Dan Cheetham BPV Requirements 4/12/16
Conformity Assessment Dan Cheetham BPV Requirements 4/12/16 BPV Requirements Boiler and Pressure Vessel Requirements (Quality Control Programs, Materials, Examination & Inspection, etc.) Quality Control
More informationSOLAR KEYMARK SPECIFIC SCHEME RULES ANNEX E: FACTORY PRODUCTION CONTROL INFORMATIVE BASED ON ISO 9001 STANDARD COVERING THE PRODUCTION LINE
SOLAR KEYMARK SPECIFIC SCHEME RULES ANNEX E: FACTORY PRODUCTION CONTROL INFORMATIVE BASED ON ISO 9001 STANDARD COVERING THE PRODUCTION LINE 1. General This annex specifies the requirements for the Factory
More informationChrome Moly flanges and fittings
Chrome Moly flanges and fittings PRO Alloy is Europe s leading stockholder for Stainless, Duplex, Super Duplex, Chrome Moly flanges and fittings. introduction Our inventory consists of a complete range
More informationIADC GLOBAL SUPPLY CHAIN COMMITTEE. Manufacturing Record Book Guidance (GU-IADC-SC-004) Rev. 1
IADC GLOBAL SUPPLY CHAIN COMMITTEE Manufacturing Record Book Guidance (GU-IADC-SC-004) Rev. 1 1 Copyrighted 2017, IADC Unlimited license is hereby granted for reproduction of this document in its entirety,
More informationQuality Supplier Requirements for Beckwith Electric Co., Inc.
Quality Supplier Requirements for Beckwith Electric Co., Inc. This Page Left Intentionally Blank To Our Valued Suppliers: One of the primary goals of Beckwith Electric is to provide the highest Quality
More information"Welder Certification"
"Welder Certification" The purpose of this presentation is to introduce you to the various aspects of welder certification. This is not intended to cover all of the requirements for certification but only
More informationAASHTO/AWS D1.5M/D1.5:2008. Table of Contents
Table of Contents Personnel...v Foreword...ix List of Tables... xviii List of Figures...xix List of Forms...xxi 1. General Provisions...1 1.1 Application...1 1.2 Base Metal...1 1.3 Welding Processes...1
More informationQUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A
Page 1 1 of 57 President Design Engineering Production Production Engineering Materials Control Purchasing Service Marketing Sales Contracts Human Resources Quality Assurance Quality Control Production
More informationCounterfeit Parts Prevention
Counterfeit Parts Prevention 1.0 Purpose The purpose of this document is to describe the process performed to prevent the purchase and / or use of Counterfeit Parts and to outline the Detection, Mitigation
More informationSUPPLIER QUALITY SYSTEM SURVEY
SUPPLIER QUALITY SYSTEM SURVEY DATE (M/d/yy): 55 Dragon Court Woburn, MA 01801 Tel: (781) 933-7300 Fax: (781) 935-4529 GENERAL INFORMATION Supplier Name: Physical Address: City: State: Zip: Sr. Company
More informationSYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION. Effective From :- UNDER DEVELOPMENT.
SYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION Effective From :- UNDER DEVELOPMENT Prepared by: Curriculum development cell Institute of Research Development & Training,
More informationPPQ Requirements training pack for suppliers
PPQ Requirements training pack for suppliers 1 Purpose This appendix serves to define the concept of PPQ elements used within the PPQ process, and replace for Montreal a portion of Section B of EBQR. The
More informationEPRI QUALITY PROGRAM MANUAL
Controlled Copy No. : If no Controlled Copy No. is assigned; this copy is uncontrolled EPRI QUALITY PROGRAM MANUAL REVISION 13 Effective TOC: TABLE OF CONTENTS Sec. Title Page SUMMARY OF CHANGES... 2 Mapping
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS
More informationSpec 5CT 7th General Is WT control required for Grade K-55 seamless casing with additional SR2 requirements?
Series 5 : Tubular Goods Last revised 3/27/06 Standard Edition Section Question Answer 7th 7th 8.8.2 & 8.8.3 As per paragraph 8.8.3 (Groups 3 and 4) of API 5CT the groove on the inside weld surface shall
More informationINTERNATIONAL STANDARD
INTERNATIONAL STANDARD ISO 15761 First edition 2002-12-15 Steel gate, globe and check valves for sizes DN 100 and smaller, for the petroleum and natural gas industries Robinets-vannes, robinets à soupape
More informationManufacture of welded products - Welding workshop
CLASS PROGRAMME Approval of manufacturers DNVGL-CP-0352 Edition April 2016 Manufacture of welded products - Welding workshop The electronic pdf version of this document, available free of charge from http://www.dnvgl.com,
More informationThe Master of Master Distribution
The Master of Master Distribution Stainless and Special Metals Pipe and Tubing Pipe Fittings Pipe Flanges Valves Supplying stainless products to industrial distributors since 1963 MASTER OF MASTER DISTRIBUTION
More informationQualification scheme for welders of hull structural steels
(Sept 2016) Qualification scheme for welders of hull structural steels 1. Scope 1.1 This document gives requirements for a qualification scheme for welders intended to be engaged in the fusion welding
More informationLT Industries SQFR 101
Page 1 of 5 LT Industries SQFR 101 Supplier Quality Flow down Requirements 1.0 GENERAL REQUIREMENTS: The supplier must flow down these requirements from LTI to their sub tier suppliers whenever those sub
More informationAnchor chain cables and accessories
CLASS PROGRAMME Approval of manufacturers DNVGL-CP-0254 Edition May 2016 The content of this service document is the subject of intellectual property rights reserved by ("DNV GL"). The user accepts that
More informationQW-482 WELDING PROCEDURE SPECIFICATION (WPS)
QW-482 WELDING PROCEDURE SPECIFICATION (WPS) Company Name: J.T. Thorpe & Son, Inc. By: J. Jacob Dupree, P.E., Q.C. Manager Welding Procedure Specification No.: JTT-22-STUD Revision No. 0 Date: 4/15/2009
More informationNUMBER OF EMPLOYEES TOTAL ENGINEERING MANUFACTURING QUALITY SUPPLIER IN-HOUSE SPECIAL PROCESS CAPABILITIES
Kearfott/ACA SUPPLIER QUALITY SYSTEM SURVEY SUPPLIER NAME SUPPLIER CODE DATE ADDRESS & ZIP CODE AREA CODE & PHONE QUALITY MANAGEMENT (NAME & TITLE) PRODUCT LINE (DESCRIBE) NUMBER OF EMPLOYEES TOTAL ENGINEERING
More informationAPPENDIX B Corrosion Management System Framework and Guidance
APPENDIX B Corrosion Management System Framework and B.1 INTRODUCTION A framework for a Corrosion Management System (CMS) for assets is described in this Appendix. The CMS developed shall include and document
More informationINSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines
INSULATED JOINTS Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS TUBE TURNS INSULATED JOINTS are a pre-fabricated, non-separable, union used to isolate specific sections of pipelines
More informationINSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1
TAKING PRESSURE VESSELS FROM CRADLE TO GRAVE SEMINAR INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1 Manish Waghare ABSG Consulting Inc., Singapore January 28, 2011 May 29, 2011 1 Presentation
More informationQuality Guideline for Suppliers. 1. Purpose
Quality Guideline for Suppliers 1. Purpose The Quality Guideline (QGL) of Aumann Beelen GmbH forms an integral part of the purchase orders and is thus binding for all Suppliers, hereinafter referred to
More informationRosen Aviation Supplier Quality Assurance Requirements
1. Purpose This document establishes the Quality Assurance Requirements for all Rosen Suppliers. This document is applicable to all Rosen Aviation Purchase Orders (POs). In addition to the requirements
More information