From the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code

Size: px
Start display at page:

Download "From the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code"

Transcription

1 From the Safety Approach of a Nuclear Power Plant, to the Manufacturing and Welding of Mechanical Components in line with RCC-M Code Philippe Malouines AREVA RCC-M Sub-Committee Chairman Presented by Marcello Consonni TWI Welding Engineer RCC-M UK User Group Representative Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 1 Copyright 2015 by Afcen

2 1. AFCEN Codes in Nuclear Power Plant 2. RCC-M: General overview & Quality Assurance requirements 3. Implementation for welding activities & Use of NF EN ISO 3834 Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 2 Copyright 2015 by Afcen

3 1. AFCEN Codes in Nuclear Power Plant 2. RCC-M: General overview & Quality Assurance requirements 3. Implementation for welding activities & Use of NF EN ISO 3834 Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 3 Copyright 2015 by Afcen

4 EPR Reactor Full Scope of Supply Introduction of RCC-M into the process of construction of Nuclear Power Plants for mechnical equipment concerned by nuclear safety: NI: Nuclear Island, CI:Conventional Island BOP: Balance of Plant NI CI BOP Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 4 Copyright 2015 by Afcen

5 Main Systems of a PWR Nuclear Island Conventional Island Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 5 Copyright 2015 by Afcen

6 Nuclear Island (NI): thousands of items to weld NSSS: Nuclear Steam Supply System BNI: Balance of Nuclear Island Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 6 Copyright 2015 by Afcen

7 Key Takeaways Number of valves and equipment (EPR plant) Number of valves in NI and CI - BOP o In Nuclear Island o In Conventional Island 18,000 Valves 14,000 Valves 4,000 Valves 50% RCC-M classified systems o 6 % RCC-M Class 1 In Nuclear Island o 18 % RCC-M Class 2 In Nuclear Island o 26 % RCC-M Class 3 In Nuclear Island 50% non RCC-M classified European Standard Number of other items In Nuclear Island (estimation) Exchangers, Pumps, Tanks, o 176 Heat Exchangers (68 non-classified RCC-M) o 84 Tanks: 40 non-classified RCC-M o 220 Pumps (RCC-M 2 RCC-M 3 non classified RCC-M) Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 7 Copyright 2015 by Afcen

8 AFCEN Codes in Brief AFCEN Codes privilege ISO and EN Standards AFCEN method: to continuously integrate lessons learned o The development of AFCEN Codes is a living process with regular updates and new fields being covered. o Technical studies are used as a basis to prepare or add to Code Editions. Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 8 Copyright 2015 by Afcen

9 International Use of AFCEN Codes UK: Hinkley Point C1-2 (EPR) France: ASTRID (FBR GEN IV) China: Taishan (2 EPR) Finland: OL3 (EPR) CPR 1000 (18 PWR) CNP 650 (2 PWR) CNP 1000 (2 PWR) France: 58 PWR (1977->2000) 2 FBR (shutdown) China: ACPR 1000: several ACP 1000: several France: Flamanville 3 (EPR) Jules Horowitz Reactor : ITER (Vacuum Vessel) Korea: Ulchin 9-10 (PWR) China: Daya Bay (2 PWR) India: PFBR 500MWe Ling Ao (4 PWR) Qinshan II (2 PWR) Qinshan II ext (2 PWR) South Africa: Koeberg 1-2 (PWR) : Plants in operation : Plants under construction : Future plants Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 9 Copyright 2015 by Afcen

10 At the level of a country, grouping of all the local companies interested in working with AFCEN Codes o To adapt the codes to an international context o o o To develop a culture of cooperation and feedback between AFCEN and international members To help set up training sessions and special events To contribute to evolution of codes RCC-M UK User Group is Chaired by TWI (Technical Welding Institute) for 3 years o 6 th meeting in June 2015 o o 35 members Working on An International Scale: User Groups Numerous presentations by RCC-M experts; exchanges with UK companies and expression of needs; structuring of training offers and funding TWI / AFCEN MOU - UK 8 Chinese User groups (all codes, 2 for RCC-M) One European Workshop Agreement (CWA 064 Phase 2) o 3 Groups: RCC-M, RCC-MRx, ETC-C for identification of R&D needs CGN / AFCEN MOU - China Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 10 Copyright 2015 by Afcen

11 1. AFCEN Codes in Nuclear Power Plant 2. RCC-M: General overview & Quality Assurance requirements 3. Implementation for welding activities & Use of NF EN ISO 3834 Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 11 Copyright 2015 by Afcen

12 RCC-M Content and Structure Safety Report Subsection A : General requirements A 3000 Documents Section I A4000 RCC-M Quality Levels A 5000 Quality Management System Subsec.B Subsec.C Subsec.D Subsec.E Subsec.G Subsec.H Subsec. J Subsec.P Subsec. Z Section VI RPP* Applicability Section II Materials Section III Examination Section IV Welding Section V Manufacturing * RPP: Probationary Phase Rule B: Level 1 C: Leve l2 D: Level 3 E: Small equipment G: Reactor internals H: Supports J: Low pressure equip.. P: Penetrations Z: Appendix Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 12 Copyright 2015 by Afcen

13 RCC-M Content and Structure Safety Report Subsection A : General requirements Section I A4000 RCC-M Quality Levels A 5000 Quality Management System Subsec.B Subsec.C Subsec.D Subsec.E Subsec.G Subsec.H Subsec. J Subsec.P Subsec. Z Section VI RPP* Applicability Section II Materials Section III Examination Section IV Welding ISO 3834 Section V Manufacturing * RPP: Probationary Phase Rule B: Level 1 C: Leve l2 D: Level 3 E: Small equipment G: Reactor internals H: Supports J: Low pressure equip.. P: Penetrations Z: Appendix Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 13 Copyright 2015 by Afcen

14 A 5000 Quality Management System A 5000 Quality Management System (QMS) This chapter specifies the basic rules for the preparation and implementation of QMS of the parties involved in the supply chain of RCC-M safety classified components A 5110 Responsibilities of the Contractor, Manufacturer or Supplier Preparation and implementation of a QMS in accordance with the requirements of A Notifying each of its manufacturers and suppliers of the applicable quality assurance requirements. Verification that Contractors, Manufacturers and Suppliers meet the requirements specified Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 14 Copyright 2015 by Afcen

15 A 5000 Quality Management System A 5200 Quality Management System Requirements A 5210 Safety Culture Safety culture: overall characteristics and attitudes in organisations and individuals which establishes that, as an overriding priority, protection and safety issues receive the attention warranted by their significance. A 5220 Graded Approach Focus on Activities Important for Safety Important For Safety: item or activity which contribute to the quality and functionality of the product. Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 15 Copyright 2015 by Afcen

16 A 5000 Quality Management System A 5230 QMS Requirements (in additions to ISO ) General QMS requirements (responsibles, change management) Documents & Data Control (verificator different) Suitably Qualified & Experienced Personnel (SQEP in the UK) Design & Development Verification (verificator different) Procurement Specifications (cascade the requirements) Identification & Traceability of Product Monitoring & Measurement of Products Control of Non-Conforming Product Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 16 Copyright 2015 by Afcen

17 1. AFCEN Codes in Nuclear Power Plant 2. RCC-M: General overview & Quality Assurance requirements 3. Implementation for welding activities & Use of NF EN ISO 3834 Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 17 Copyright 2015 by Afcen

18 RCC-M Content and Structure Safety Report Subsection A : General requirements Section I A4000 RCC-M Quality Levels A 5000 Quality Management System Subsec.B Subsec.C Subsec.D Subsec.E Subsec.G Subsec.H Subsec. J Subsec.P Subsec. Z Section VI RPP* Applicability Section II Materials Section III Examination Section IV Welding Section V Manufacturing B: Level 1 C: Leve l2 D: Level 3 E: Small equipment G: Reactor internals H: Supports J: Low pressure equip.. P: Penetrations Z: Appendix Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 18 Copyright 2015 by Afcen

19 Section IV Section IV: Welding Scope o This section provides requirements for welding, which should be applied in conjunction with Subsections B, C, D according to equipment classification level (respectively 1, 2 and 3) and E, G, J, H, P for the other equipment. o RCC-M integrates technical requirements coming from European regulations on pressure equipment (PED 97/23/CE or soon 2014/68/UE) through harmonized European standards, in addition to specific requirements for components of large thickness which are used in Pressurized Water Reactor (PWR) designs. Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 19 Copyright 2015 by Afcen

20 Self-contained section covering every aspect of welding: Section IV: Welding Scope Base material Section II Welder/operator s qualification S4000 NF EN 287-1, ISO Filler metals qualification S5000 Workshop qualification S6000 Filler metals acceptance welds S2000 Production welds S7000 Production test coupon S7800 Non destructive exminations S7700 Hardfacing S8000 NF EN ISO Refers to Section IV Welding o S 1000 GENERAL o S 2000 ACCEPTANCE OF FILLER MATERIALS o S 3000 QUALIFICATION OF WELDING PROCEDURE o S 4000 QUALIFICATION OF WELDERS AND OPERATORS Welding procedure qualification S3000 o o o o NF EN ISO EN 473, EN IS S 5000 QUALIFICATION OF FILLER MATERIALS S 6000 QUALIFICATIONS OF PRODUCTION WORKSHOPS S 7000 PRODUCTION WELDS S 8000 HARDFACING Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 20 Copyright 2015 by Afcen

21 Workshop qualification Section IV, chapter S6000 lays out the requirements for workshop qualification. o Adequate means of production: Welding equipment shall be suitable for welding procedures Welding Requirements Working areas well equipped (including handling systems), adequate cleanliness level shall be maintained, according to the material to be produced Heat treatment installations shall be in good condition, with appropriate capacities for the works to be carried out o Staff and management: Welding and examination staff (including management) must be sufficiently skilled and competent. o Experience: The workshop must demonstrate adequate experience in the performance of products using comparable welding processes. The RCC-M sub-committee is currently adapting the implementation of NF EN ISO 3834 Quality requirement for welding» with requirements laid out in chapters A 5000 and S 6000 Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 21 Copyright 2015 by Afcen

22 Working methodology: NF EN ISO & are considered A cross matrix allowed to check if RCC-M requirements satisfy also NF ISO 3834 requirements Identification of differences Welding process qualification, welders/operators qualification, of RCC-M (Chapters S 3000, S 4000, ) are already compliant with ISO 3834 Most of the quality and organizational requirements for welding are in Chapters A 5000 and S 6000 and A 3500 ( Welding documents), Welding coordinator skill and authorization, has to be defined and integrate in RCC-M. It will be in Chapter S Chapter S 6000 will be also modified to deal with: Reception of new equipment, or equipment after maintenance, Follow up of manufacturing equipment in workshop Chapters S6000 and A 3000 must be consistent for document records and traceability Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 22 Copyright 2015 by Afcen

23 ISO 3834 certification alone does not imply compliance with the RCC-M requirements: RCC-M will publish a guidance document to assist welding workshops with upgrading their welding quality system for the production of welds for nuclear equipment The document will provide guidance on the additional requirements that manufacturers certified or working in compliance with ISO 3834 need to fulfil to meet RCC-M Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 23 Copyright 2015 by Afcen

24 Aberdeen, 8 th October, 2015 malouines.afcen@gmail.com 24 Copyright 2015 by Afcen

PRESENTATION OF THE 2014 REVISIONS TO THE RCC-M CODE

PRESENTATION OF THE 2014 REVISIONS TO THE RCC-M CODE Proceedings of the ASME 2014 Pressure Vessels & Piping Conference PVP2014 July 20-24, 2014, Anaheim, California, USA PVP2014-28501 PRESENTATION OF THE 2014 REVISIONS TO THE RCC-M CODE Philippe Malouines

More information

Nuclear Quality Standard Association

Nuclear Quality Standard Association Nuclear Quality Standard Association General information about Quality Management System in the nuclear industry This document is the property of NQSA Its copying, use or communication is subject to prior

More information

Graded approach practices for the mechanical components of French research reactor projects

Graded approach practices for the mechanical components of French research reactor projects Graded approach practices for the mechanical components of French research reactor projects Claude PASCAL RMR/RR Rabat IAEA conference, november 2011 Content Context Classification of SSCs Associated Requirements

More information

AFCEN and INTERNATIONAL HARMONIZATION

AFCEN and INTERNATIONAL HARMONIZATION www.afcen.com Association Française pour les règles de conception, de construction et de surveillance en exploitation des matériels des Chaudières Electro-Nucléaires AFCEN and INTERNATIONAL HARMONIZATION

More information

Effective planning and engagement: mitigating construction risk of the UK s first EPR. Samarth Sharma Strategy Manager Thursday 30th January 2014

Effective planning and engagement: mitigating construction risk of the UK s first EPR. Samarth Sharma Strategy Manager Thursday 30th January 2014 Effective planning and engagement: mitigating construction risk of the UK s first EPR Samarth Sharma Strategy Manager Thursday 30th January 2014 The value of experience: 4 EPR Reactor Units Under Construction

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

How to face higher quality expectations for the global nuclear supply chain

How to face higher quality expectations for the global nuclear supply chain Nuclear Science and Technology Symposium How to face higher quality expectations for the global nuclear supply chain Helsinki, 3 November 2016 Stephane GALOPIN stephane.galopin@fr.bureauveritas.com Nuclear

More information

RCC-MRx code: context, overview, on-going developments

RCC-MRx code: context, overview, on-going developments Quality Management System Certified ISO 9001:2008 RCC-MRx code: context, overview, on-going developments C PETESCH RCC-MRx Sub-Committee Chairwoman MatISSE/JPNM workshop on cross-cutting issues in structural

More information

CGN's Nuclear Energy Capabilities

CGN's Nuclear Energy Capabilities Business Overview NPP Construction Achievements NPP Operating Performance Overseas Business Core Nuclear Power Technologies CGN's Nuclear Energy Capabilities Nuclear Project Construction Capabilities Operations

More information

UK Nuclear New Build. Challenges and Solutions for Chinese Supply Chain Companies. Courtesy of EDF Energy

UK Nuclear New Build. Challenges and Solutions for Chinese Supply Chain Companies. Courtesy of EDF Energy UK Nuclear New Build Challenges and Solutions for Chinese Supply Chain Companies Courtesy of EDF Energy 2 Challenges and Solutions 1. Background CGN has signed agreements with EDF and the UK Government

More information

Responsibilities of the operating organization during construction and how to discharge them

Responsibilities of the operating organization during construction and how to discharge them Responsibilities of the operating organization during construction and how to discharge them Importance of an early, defined & strong involvement of the Owner/Operator in a New Build Project IAEA TM on

More information

IAEA Workshop on Construction Technologies for Nuclear Power Plants: A Comprehensive Approach

IAEA Workshop on Construction Technologies for Nuclear Power Plants: A Comprehensive Approach IAEA Workshop on Construction Technologies for Nuclear Power Plants: A Comprehensive Approach Paris, France, 12-16 December 2011 Workshop Director: Bismark.Tyobeka Local Counterpart: Michel Debes DRAFT

More information

Nuclear Quality Standard Association General information about Quality Management System in the nuclear industry

Nuclear Quality Standard Association General information about Quality Management System in the nuclear industry Nuclear Quality Standard Association General information about Quality Management System in the nuclear industry This document is the property of NQSA Its copying, use or communication is subject to prior

More information

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT DESIGN ASSESSMENT AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT 10/2016 Stephen J Walls, EDF Energy Nuclear New Build 1 Olivier Bard, EDF HINKLEY POINT C (HPC) 2 HPC Financial Investment

More information

RCC-MRx Context, Overview and on-going developments. IGORR 2017, Sydney 3-7 December 2017

RCC-MRx Context, Overview and on-going developments. IGORR 2017, Sydney 3-7 December 2017 Quality Management System Certified ISO 9001:2008 RCC-MRx 2015 Context, Overview and on-going developments Thierry Lebarbé, Cécile Pétesch (CEA), Dominique Bonne (Areva NP), Martine Blat (EDF), and Claude

More information

EDF Training in Support of a New Nuclear Project

EDF Training in Support of a New Nuclear Project EDF Training in Support of a New Nuclear Project Jean-Luc His EDF Engineering and Generation Training Unit IAEA TM on Human Resources Roadmaps and Capacity Building for New and Expanding Nuclear Power

More information

Practice on NDE Licensing and Inspection Qualifications for Nuclear Power Plant In-service Inspections

Practice on NDE Licensing and Inspection Qualifications for Nuclear Power Plant In-service Inspections 18 th World Conference on Nondestructive Testing, 16-20 April 2012, Duban, South Africa Practice on NDE Licensing and Inspection Qualifications for Nuclear Power Plant In-service Inspections Jinhong LIU,

More information

ABSTRACT. The Guidelines Section C is related to the classification and grading approach of NSQ100 (Chapters & 4.1.3).

ABSTRACT. The Guidelines Section C is related to the classification and grading approach of NSQ100 (Chapters & 4.1.3). Page 1 / 11 ABSTRACT This document is the Section C to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions

More information

JULES HOROWITZ REACTOR: RCC-MRx [1] APPLICABILITY FOR THE DESIGN PHASE OF EXPERIMENTAL DEVICES. S. GAY 1, S. GAILLOT 1

JULES HOROWITZ REACTOR: RCC-MRx [1] APPLICABILITY FOR THE DESIGN PHASE OF EXPERIMENTAL DEVICES. S. GAY 1, S. GAILLOT 1 JULES HOROWITZ REACTOR: RCC-MRx [1] APPLICABILITY FOR THE DESIGN PHASE OF EXPERIMENTAL DEVICES. S. GAY 1, S. GAILLOT 1 Abstract. 1) CEA, DEN, DTN, Nuclear Technology Department, CEA Cadarache. F-13108

More information

Nuclear Industry Localization Practices and Recommendations

Nuclear Industry Localization Practices and Recommendations Nuclear Industry Localization Practices and Recommendations NIASA Nuclear Industry Localization Conference Cape Town Jimmy T. Wang China Guangdong Nuclear Power Group June 1~3, 2011 1.Nuclear Power Development

More information

A wide range of products...

A wide range of products... Industeel experience is recognized worldwide and the compagny has been qualifed by several international organizations A wide range of products... RCCM ASME III ISO Manufacture License of Special Equipment

More information

RCC-M: CONTENT, WORKING APPROACH AND FUTURE EVOLUTIONS

RCC-M: CONTENT, WORKING APPROACH AND FUTURE EVOLUTIONS Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA Proceedings of the 2011 ASME Pressure Vessels and Piping Conference PVP2011

More information

PVP PVP

PVP PVP Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference Proceedings of the ASME 2011 Pressure Vessels & Piping Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, PVP2011 USA July

More information

Eur Ing Ian Hogarth CEng CIWE CEWE EWIE FWeldI Compliance Verification Engineer for TWI Certification Ltd.

Eur Ing Ian Hogarth CEng CIWE CEWE EWIE FWeldI Compliance Verification Engineer for TWI Certification Ltd. Eur Ing Ian Hogarth CEng CIWE CEWE EWIE FWeldI Compliance Verification Engineer for TWI Certification Ltd. How can I become a Responsible Welding Coordinator (RWC) to comply with ISO 3834 and ISO 14731-1?

More information

FRENCH NUCLEAR KNOWLEDGE MANAGEMENT EXPERIENCE. EDF SA. All rights reserved. EDF Nuclear Performance Model

FRENCH NUCLEAR KNOWLEDGE MANAGEMENT EXPERIENCE. EDF SA. All rights reserved. EDF Nuclear Performance Model FRENCH NUCLEAR KNOWLEDGE MANAGEMENT EXPERIENCE Summary Introduction Building personal knowledge Building collective knowledge Long term Knowledge Management Beyond one s own entity An example of success

More information

Course: 141 TIG WELDING OF STAINLESS STEEL. Module 9

Course: 141 TIG WELDING OF STAINLESS STEEL. Module 9 Course: 141 TIG WELDING OF STAINLESS STEEL Module 9 1 of 11 2 of 11 List of content MODULE 9...4 Delivery of the product...4 The European Welded Product Directives...5 The European Welded Product Standards...6

More information

Industry and Government working together to deliver Nuclear New Build Programme in UK. Dr Glen Little Industrial Adviser March 2017

Industry and Government working together to deliver Nuclear New Build Programme in UK. Dr Glen Little Industrial Adviser March 2017 Industry and Government working together to deliver Nuclear New Build Programme in UK Dr Glen Little Industrial Adviser March 2017 Contents 1 2 3 4 History of UK Nuclear Power Plant Maintenance of UK Nuclear

More information

First steps towards a European design and construction code for research reactors

First steps towards a European design and construction code for research reactors First steps towards a European design and construction code for research reactors C.Pascal - B.Drubay AREVA TA - CEA SEMT/LISN& AFCEN chairman of RCC-MRx Sub commission IGORR 13 Knoxville, september 2010

More information

THE SAFEST CONNECTION FOR NUCLEAR POWER PLANTS

THE SAFEST CONNECTION FOR NUCLEAR POWER PLANTS THE SAFEST CONNECTION FOR NUCLEAR POWER PLANTS en SAFETY IS WHEN CONTROL LEADS TO TRUST. Erne Fittings has been successfully completing international nuclear projects since the early 1970s. It is not for

More information

"Welder Certification"

Welder Certification "Welder Certification" The purpose of this presentation is to introduce you to the various aspects of welder certification. This is not intended to cover all of the requirements for certification but only

More information

VALVES OF A NUCLEAR FACILITY

VALVES OF A NUCLEAR FACILITY GUIDE YVL E.8 / 15 November 2013 VALVES OF A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 5 3 Licensee s component requirement specification 5 4 Manufacturer 6 5 Design 7 5.1 General 7 5.2

More information

FROG Owners Group A Worldwide Network of Experience. April 2012

FROG Owners Group A Worldwide Network of Experience. April 2012 FROG Owners Group A Worldwide Network of Experience April 2012 Origin FROG founded in 1991 Founding Members = utilities operating or building Nuclear Power Plants with Framatome supplying Nuclear Steam

More information

Conformity Assessment. Section III Nuclear Requirements Buenos Aires, Argentina May 2017

Conformity Assessment. Section III Nuclear Requirements Buenos Aires, Argentina May 2017 Conformity Assessment Section III Nuclear Requirements Buenos Aires, Argentina May 2017 ASME Section III Requirements Workshop Scope ASME Certificates of Authorization Quality Assurance Requirements Discussion

More information

UKEPR Issue 02

UKEPR Issue 02 Title: PCSR Sub-chapter 21.1 Project Organisation Total number of pages: 11 Page No.: I / III Chapter Pilot: G. MARTIN Name/Initials Date 04-05-2012 Approved for EDF by: A. PETIT Approved for AREVA by:

More information

"Welder Certification"

Welder Certification "Welder Certification" The purpose of this presentation is to introduce you to the various aspects of welder certification. This is not intended to cover all of the requirements for certification but only

More information

STEP 3 MANAGEMENT OF SAFETY AND QUALITY ASSURANCE ASSESSMENT OF THE EDF AND AREVA UK EPR DIVISION 6 ASSESSMENT REPORT NO.

STEP 3 MANAGEMENT OF SAFETY AND QUALITY ASSURANCE ASSESSMENT OF THE EDF AND AREVA UK EPR DIVISION 6 ASSESSMENT REPORT NO. Health and Safety Executive NUCLEAR DIRECTORATE GENERIC DESIGN ASSESSMENT NEW CIVIL REACTOR BUILD STEP 3 MANAGEMENT OF SAFETY AND QUALITY ASSURANCE ASSESSMENT OF THE EDF AND AREVA UK EPR DIVISION 6 ASSESSMENT

More information

Technical Specification for Analysis Section On-site Structural Analysis Services

Technical Specification for Analysis Section On-site Structural Analysis Services IDM UID TK32M9 VERSION CREATED ON / VERSION / STATUS 17 Jan 2017 / 1.2 / Approved EXTERNAL REFERENCE / VERSION Technical Specifications (In-Cash Procurement) Technical Specification for Analysis Section

More information

Overview of Draft API Standard 20M

Overview of Draft API Standard 20M Overview of Draft API Standard 20M Qualification of Suppliers of Machining Services for Use in the Petroleum and Natural Gas Industries API STANDARD 20M Slide 1 of 9 Overview Standard 20M provides methods

More information

Alliance for success IN THE NUCLEAR INDUSTRY

Alliance for success IN THE NUCLEAR INDUSTRY Alliance for success IN THE NUCLEAR INDUSTRY Boccard nuclear For half a century, we have been helping you throughout the industrial life cycle of your nuclear facilities from New build to Maintenance.

More information

TECHNICAL NOTICE FOR THE DOCUMENTS. ABM, KBM, TBM and TBV. Edition 1, Approved:

TECHNICAL NOTICE FOR THE DOCUMENTS. ABM, KBM, TBM and TBV. Edition 1, Approved: Technical notice 1(8) TECHNICAL NOTICE FOR THE DOCUMENTS ABM, KBM, TBM and TBV Edition 1, 2018-01-23 The Swedish Nuclear Power Companies have jointly produced this document. Any revision of this document

More information

Call for Nomination. Vacuum Vessel Assembly Welding

Call for Nomination. Vacuum Vessel Assembly Welding Call for Nomination Vacuum Vessel Assembly Welding Purpose ITER will be the world's largest experimental facility to demonstrate the scientific and technical feasibility of fusion power. The Vacuum Vessel

More information

News Magazine. Pharmaceutical Industry. C.L.A. stainless steel processing.

News Magazine. Pharmaceutical Industry. C.L.A. stainless steel processing. News Magazine Pharmaceutical Industry C.L.A. stainless steel processing www.claschio.it index Sect. One 01. Corporate Identity. Sect. Three 03. Mobile Preparation Units 10/11 03. Preparation Systems 12/13

More information

NUCLEAR STEAM GENERATOR TUBES & Nuclear Environment Products BY VALINOX NUCLÉAIRE

NUCLEAR STEAM GENERATOR TUBES & Nuclear Environment Products BY VALINOX NUCLÉAIRE NUCLEAR STEAM GENERATOR TUBES & Nuclear Environment Products BY VALINOX NUCLÉAIRE Valinox Nucléaire locations Vallourec is the world leader in premium tubular solutions primarily serving the energy markets

More information

Int. J. Nuclear Energy Science and Technology, Vol. X, No. Y, xxxx 1

Int. J. Nuclear Energy Science and Technology, Vol. X, No. Y, xxxx 1 Int. J. Nuclear Energy Science and Technology, Vol. X, No. Y, xxxx 1 ISO 9001 or IAEA GS-R-3? Eduardo Kibrit Quality Assurance Department Centro Tecnológio da Marinha em São Paulo (CTMSP) Brazilian Navy

More information

An Industry View on Harmonization of Codes & Standards

An Industry View on Harmonization of Codes & Standards An Industry View on Harmonization of Codes & Standards Dr. Andrew Wasylyk Project Manager - CORDEL 12 th April 2017 OECD NEA Workshop Paris, France IEA 2degree scenario: Nuclear is required to provide

More information

AREVA NP INAC October 23 rd André Salgado Brazil and South America

AREVA NP INAC October 23 rd André Salgado Brazil and South America INAC 2017 October 23 rd 2017 André Salgado Brazil and South America Agenda 1 business 2 Nuclear: answering new electricity market challenges From Areva Group to Areva NP New Areva Installed Base Components

More information

OE Supply-Chain in Nuclear Dr. Boris Gehring March 2017

OE Supply-Chain in Nuclear Dr. Boris Gehring March 2017 OE Supply-Chain in Nuclear Dr. Boris Gehring March 2017 2015-02-12 It should not finally look like this! Owners Engineers and Supply-Chain services In NPP New build, OE and SCS will help to keep: -Time-line

More information

Global Supply Chain & Localization, Issues and Opportunities: UK Programme Experience

Global Supply Chain & Localization, Issues and Opportunities: UK Programme Experience Global Supply Chain & Localization, Issues and Opportunities: UK Programme Experience Jon Halladay, Civil Nuclear, Department for International Trade INTERNATIONAL FRAMEWORK FOR NUCLEAR ENERGY COOPERATION

More information

Page 1 / 11. Version 0 June 2014

Page 1 / 11. Version 0 June 2014 Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning

More information

Pressure Points. Governing Code Edition Section I Table of Contents

Pressure Points. Governing Code Edition Section I Table of Contents Table of Contents Governing Code Edition... 1 Navigating the use of Small Products NX-2610... 3 Third Party Inspection... 4 ASME Three-Day Seminar... 6 Governing Code Edition Section I - 2017 The governing

More information

Our Contribution to the Forum

Our Contribution to the Forum Our Contribution to the Forum General presentation of the EPR TM Reactor CR1.1.1 Robustness PART 1 Margins - Simplicity PART 2 Quality of design and construction Quality of materials Redundancy PART 3

More information

WENRA. Recommendation in. in French reactors.

WENRA. Recommendation in. in French reactors. WENRA Recommendation in connection with macrosegregation anomalies found in French reactors. 1 01 Background 01.1 The findings in France In late 2014, mechanical tests performed on a Reactor Pressure Vessel

More information

Audit questions for DB Audit Tool Version 4.00

Audit questions for DB Audit Tool Version 4.00 Pos. Audit questions Management 1 How is your company organised? 2 Present the company and explain responsibilities. What strategic orientations are in place and are being pursued? 3 What manufacturing

More information

Overview for a feasibility study

Overview for a feasibility study Overview for a feasibility study What, Why & Objectives of Feasibility Study? International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready to

More information

Contract Quality Requirements Manual SLM Issue 3

Contract Quality Requirements Manual SLM Issue 3 Contract Quality Requirements Manual SLM 4.06.02 Issue 3 20 th October 2015 Gary Rushforth Supply Chain Quality Sellafield Ltd Introduction Sellafield Ltd (SL) aims to deliver excellence in everything

More information

QUALIFICATIONS NEEDED TO DESIGN, CONSTRUCT AND MANUFACTURE NUCLEAR SYSTEMS AND EQUIPMENT. Cosmos M. Voutsinos, P.Eng.

QUALIFICATIONS NEEDED TO DESIGN, CONSTRUCT AND MANUFACTURE NUCLEAR SYSTEMS AND EQUIPMENT. Cosmos M. Voutsinos, P.Eng. QUALIFICATIONS NEEDED TO DESIGN, CONSTRUCT AND MANUFACTURE NUCLEAR SYSTEMS AND EQUIPMENT Cosmos M. Voutsinos, P.Eng. 1638 Scenic Heights South, Lethbridge, Alberta, Canada 403-331-2212,

More information

PROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT

PROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT PDG PROJECT DESIGN A00.1 GUIDES PROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT Project Name: Name Project No.: Number Date: Date Document No.: PDG-PDG-PRO-A00.1 Date Created: 30 th Mar

More information

4 TH MDEP CONFERENCE on New Reactor Design Activities SESSION 1: CODES AND STANDARDS HARMONIZATION SEPTEMBER, LONDON

4 TH MDEP CONFERENCE on New Reactor Design Activities SESSION 1: CODES AND STANDARDS HARMONIZATION SEPTEMBER, LONDON Harmonising Nuclear Codes and Standards for Mechanical Components Professor Nawal K Prinja BSc, MSc, PhD, CEng, FIMechE Technical Director, Clean Energy, AMEC Foster Wheeler Chair of Mechanical Codes &

More information

NATO QUALITY ASSURANCE REQUIREMENTS FOR DESIGN, DEVELOPMENT AND PRODUCTION AQAP-110

NATO QUALITY ASSURANCE REQUIREMENTS FOR DESIGN, DEVELOPMENT AND PRODUCTION AQAP-110 AQAP-110 NATO QUALITY ASSURANCE REQUIREMENTS FOR DESIGN, DEVELOPMENT AND PRODUCTION AQAP-110 FEBRUARY 1995 I AQAP-110 NORTH ATLANTIC TREATY ORGANIZATION MILITARY AGENCY FOR STANDARDIZATION NATO LETTER

More information

ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS

ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS [Not applicable to ASME Sec. IV, Cast Iron and Aluminum Boilers, ASME Sec. VIII Div 1, UG-90 (c) (2) and Graphite Vessels, ASME Sec. VIII, Div.

More information

AREVA AND ATMEA NEW PROJECTS

AREVA AND ATMEA NEW PROJECTS AREVA AND ATMEA NEW PROJECTS LAS/ANS SYMPOSIUM July 23rd, 2014 Karl-Heinz POETS AREVA South America THE VOICE OF WISDOM DEFENDS NUCLEAR ENERGY Alternative sources of energy such as wind or solar are too

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

ASSYSTEM NUCLEAR 2020 POSITION & PERSPECTIVE

ASSYSTEM NUCLEAR 2020 POSITION & PERSPECTIVE ASSYSTEM NUCLEAR 2020 POSITION & PERSPECTIVE STEPHANE AUBARBIER. DECEMBER 10, 2014 45 YEARS EXPERIENCE, A RENEWED POSITION 2 ROAD MAP 1 WORLDWIDE NUCLEAR OUTLOOK 2 ASSYSTEM 4th NUCLEAR ENGINEERING FIRM

More information

IEEE SC-2 International Standard Review. RCC-E (1993) versus IEEE

IEEE SC-2 International Standard Review. RCC-E (1993) versus IEEE IEEE SC-2 International Standard Review RCC-E (1993) versus IEEE 323-2003 Historical Use of Standard On 10/19/1980, EdF, Framatome and Novatome establish AFCEN (French Society for Design & Construction

More information

Codes & Standards Comparison

Codes & Standards Comparison French Association for Design, Construction and Surveillance Rules of Nuclear Power Plant Components www.afcen.com MDEP General Meeting OECD Paris September 15-16, 2011 Association Française pour les règles

More information

Role of Nuclear Safety in Nuclear Export after Fukushima - Impact on Prospects of Chinese Nuclear Export

Role of Nuclear Safety in Nuclear Export after Fukushima - Impact on Prospects of Chinese Nuclear Export Role of Nuclear Safety in Nuclear Export after Fukushima - Impact on Prospects of Chinese Nuclear Export Nov. 21, 2014 Ning Li, Ph.D. Xiamen University, China Fast Growing NPPs in China 红沿河核电站 20 reactors

More information

A canter around the nuclear jumps..

A canter around the nuclear jumps.. A canter around the nuclear jumps.. Robert Davies Vice President New Build, AREVA UK Cambridge MPhil 8 th February 2012 Who are we? World leader in CO 2 -free power generation 9.1Bn in Annual Revenues

More information

Management System Requirements

Management System Requirements Management System Requirements Identification, Recognition, Application IAEA Technical Meeting Grading of the Application of Management System Requirements Vienna, 23 27 January 2012 RWE Technology GmbH

More information

Development of SAMG and its implementation in China

Development of SAMG and its implementation in China Development of SAMG and its implementation in China Yang Zhiyi 1, Zhang Lin 2, etc. 1. Nuclear and Radiation Safety Center, China 2. National Nuclear Safety Administration, China Vienna Austria, 2014/3/20

More information

F e b Des Muller Chairman for NIASA Supply Chain Development Subcommittee

F e b Des Muller Chairman for NIASA Supply Chain Development Subcommittee Aligning our Industry to a Nuclear New Build Program F e b 2 0 1 8 Des Muller Chairman for NIASA Supply Chain Development Subcommittee Content: 1. The Relevance of Nuclear Energy in Africa 2. Why Can SA

More information

Analysis of the optimization of the secondary hot piping for a sodium fast reactor

Analysis of the optimization of the secondary hot piping for a sodium fast reactor Analysis of the optimization of the secondary hot piping for a sodium fast reactor O. Ancelet 1, M.N. Berton 2, M. Blat 3, F. Dalle 1, Ph. Dubuisson 1, O. Gelineau 4, Y. Lejeail 2 1 CEA, Saclay France

More information

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS BRITISH COLUMBIA SAFETY AUTHORITY Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS Prepared by: Ed Hurd P.Eng. Provincial Safety Manager, Boilers Date: March 2, 2012 Controlled

More information

Swagelok Nuclear Capabilities. swagelok.com

Swagelok Nuclear Capabilities. swagelok.com Swagelok Nuclear Capabilities swagelok.com More than 50 Years of Nuclear Experience 1947 Swagelok Company founded Late 1950s Launched Nupro bellows valve for nuclear Late 1960s Began providing fittings

More information

HACCPEUROPA PUBLICATIONS ISO 22000:2005 FOOD SAFETY QUALITY MANUAL. ISO 22000:2005 Quality Manual

HACCPEUROPA PUBLICATIONS ISO 22000:2005 FOOD SAFETY QUALITY MANUAL. ISO 22000:2005 Quality Manual HACCPEUROPA PUBLICATIONS ISO 22000:2005 FOOD SAFETY QUALITY MANUAL ISO 22000:2005 Quality Manual QUALITY MANUAL ISO 22000:2005 Food Safety Management HACCPEuropa Publications 2012 Table of Contents Introduction...

More information

JOINT PROGRAMME OFFICE

JOINT PROGRAMME OFFICE JOINT PROGRAMME OFFICE REPORT ON THE JOINT REGULATORS TEAM INSPECTION OF EDF/AREVA s ARRANGEMENTS AS PART OF GENERIC DESIGN ASSESSMENT (QUALITY MANAGEMENT ARRANGEMENTS) DECEMBER 2007 Page 1 of 8 REQUESTING

More information

WELMEC European cooperation in legal metrology

WELMEC European cooperation in legal metrology WELMEC 8.6 Issue 1 WELMEC European cooperation in legal metrology Measuring Instruments Directive 2004/22/EC Presumption of Conformity of the Quality System of Manufacturers with Module D or H 1 when EN

More information

Role of NDE in Regulatory Oversight of Nuclear Power Plants

Role of NDE in Regulatory Oversight of Nuclear Power Plants Role of NDE in Regulatory Oversight of Nuclear Power Plants NDE2015, Hyderabad More info about this article: http://www.ndt.net/?id=21064 R.P. Gupta Atomic Energy Regulatory Board 022-25990568, e-mail:

More information

Nanyang. Commercial nuclear power in China can trace its history back to (SNPEC), and one of the key global nuclear valve

Nanyang. Commercial nuclear power in China can trace its history back to (SNPEC), and one of the key global nuclear valve Operating unit (13) Unit under construction (38) Planned unit (19) Proposed unit (70+) Nanyang A valve supplier s experience in the Chinese nuclear market Wuhu NPP Xianning NPP Taohuajiang NPP Xiaomoshan

More information

General Document or OQE Comments SAT UNSAT

General Document or OQE Comments SAT UNSAT 4 Quality Management System 4.2.2 Quality Manual (A) Has a Quality Manual been developed that includes the scope of the QMS, the documented procedures established for Section 2 #1 the QMS, and a description

More information

Manufacture of welded products - Welding workshop

Manufacture of welded products - Welding workshop CLASS PROGRAMME Approval of manufacturers DNVGL-CP-0352 Edition April 2016 Manufacture of welded products - Welding workshop The electronic pdf version of this document, available free of charge from http://www.dnvgl.com,

More information

Documentation required to be presented by. DAs and Material Manufacturers

Documentation required to be presented by. DAs and Material Manufacturers ITER_D_2MT72B v2.2 Documentation required to be presented by DAs and Material s in accordance with Regulatory and Code requirements for the ITER Vacuum Vessel and Port components Abstract This document

More information

RSC-G-009D-Annex1 (SP) Checklist for evaluation of a Project Safety Plan

RSC-G-009D-Annex1 (SP) Checklist for evaluation of a Project Safety Plan RSC-G-009D-Annex1 (SP) Checklist for evaluation of a Project Safety Plan Prepared by: Maik Wuttke 22.02.2012 Reviewed by: Mary Molloy 22.02.2012 1 Introduction This checklist will be employed by the RSC

More information

PRESS CONFERENCE. 3 September Jean-Bernard LÉVY Chairman and CEO. Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering

PRESS CONFERENCE. 3 September Jean-Bernard LÉVY Chairman and CEO. Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering PRESS CONFERENCE 3 September 2015 Jean-Bernard LÉVY Chairman and CEO Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering EDF, A RESPONSIBLE ELECTRICITY COMPANY, A CHAMPION OF

More information

SUPPLIES REVIEW. This English translation is provided for information only. Only the French original version constitutes a contractual document.

SUPPLIES REVIEW. This English translation is provided for information only. Only the French original version constitutes a contractual document. SQ 908 Indice E Railway Application Quality Specification ENSURING THE QUALITY OF PRODUCTS PURCHASED BY SNCF SUPPLIES REVIEW Issue date November 2009 This English translation is provided for information

More information

Zhao Weidong June, 2010 Toronto, Canada

Zhao Weidong June, 2010 Toronto, Canada Zhao Weidong June, 2010 Toronto, Canada Contents 1 Overview of TQNPC 2 Experiences of In-Service Inspection 2.1 Applicable Documents 2.2 Critical Components Inspections 3 Overview of Main ISI Service Providers

More information

The Spanish Nuclear Group for Cooperation: A Story of Success

The Spanish Nuclear Group for Cooperation: A Story of Success The Spanish Nuclear Group for Cooperation: A Story of Success C. Palacios The SNGC (Spanish Nuclear Group for Cooperation) is an alliance founded in 2006 for commercial cooperation between Spanish nuclear

More information

Supplier Evaluation Program Doosan QA Team / Jeong Sun Kim

Supplier Evaluation Program Doosan QA Team / Jeong Sun Kim Supplier Evaluation Program 2018.11.05 Doosan QA Team / Jeong Sun Kim Contents Introducing of Doosan Applicable Requirements for Supplier Evaluation Supplier Evaluation and Control Challenges/ Risks for

More information

Daya Bay Outage Management. Atoms for the Future 2012 Seminar Paris 24 October 2012

Daya Bay Outage Management. Atoms for the Future 2012 Seminar Paris 24 October 2012 Daya Bay Outage Management Atoms for the Future 2012 Seminar Paris 24 October 2012 Contents 1. Nuclear Power Development in China 2. Daya Bay Performance 3. Daya Bay Outage Management Nuclear power development

More information

M9C 1A3 VELO (PH) (FX)

M9C 1A3 VELO (PH) (FX) PROFESSIONAL DEVELOPMENT COURSES ANRIC Enterprises Inc. 701 Evans Ave, Suite 202 Toronto, ON M9C 1A3 (PH) 416-253-9459 (FX) 416-252-2553 www.anric.com PROFESSIONAL DEVELOPMENT COURSES CONTENTS INTRODUCTORY

More information

We take care of it. Company Manual

We take care of it. Company Manual We take care of it. Company Manual Quality Management System based on ISO 9001:2015 1. COMPANY POLICY...3 1.1. Company Mission Statement...3 1.2. Company Quality...3 2. PRODUCTS AND SERVICES...4 3. ORGANISATION...6

More information

Newsletter 4th Quarter 2012

Newsletter 4th Quarter 2012 Headlines RINGO VALVULAS Completes the Manufacturing and Testing of SDV Gate Valves in Sizes 24 & 28-03-12-2012 New Marketing Director at RINGO - 10-12-2012 New Supply for Doel 3&4 Nuclear Power Plant

More information

2001 NBIC Interpretations

2001 NBIC Interpretations 2001 NBIC Interpretations INTERPRETATION 01-41 Subject: Appendix 2 and Appendix 5 with 2003 Addendum Question: In the event of an alteration to a boiler in which the boiler heating surface and steaming

More information

Challenges on the Road to the 1 st National NPP A Countdown

Challenges on the Road to the 1 st National NPP A Countdown Zoran V. STOŠIĆ Director R&D Installed Base Engineering Director Sales & Marketing Ex Yugoslavia Peter SCHIMANN Installed Base Engineering VGB Projects Challenges on the Road to the 1 st National NPP A

More information

Experiences with the construction of EPR at Flamanville and Taishan

Experiences with the construction of EPR at Flamanville and Taishan Experiences with the construction of EPR at Flamanville and Taishan OECD/ Nuclear Energy Agency Workshop : Project and Logistics Management in Nuclear New Build NEA Headquarters, Issy-les-Moulineaux March

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL INSPECTION PROCEDURE CQV/EQV INSPECTION OF COMMERCIAL-GRADE DEDICATION PROGRAMS PROGRAM APPLICABILITY: 2504, 2507, 2700-01 INSPECTION OBJECTIVES 01.01 To verify that the dedicating

More information

The Nuclear Landscape A Snapshot of the Global Issues and Players

The Nuclear Landscape A Snapshot of the Global Issues and Players American Association for the Advancement of Science Annual Meeting February 12th 16th, 2009, Chicago Keeping the Lights on the Revival of Nuclear Energy for our Future The Nuclear Landscape A Snapshot

More information

SECTION III DIVISIONS 1 AND 2

SECTION III DIVISIONS 1 AND 2 SECTION III DIVISIONS 1 AND 2 Subject Interpretation File No. Division 1 Appendix N, Table N-1230-1; Damping Values (1998 Edition)... III-1-04-27 NI03-025 Code Cases 2142-1 and 2143-1... III-1-04-22 NI03-019

More information

FRAMATOME S LESSONS LEARNED ON RISK-INFORMED APPLICATIONS (RIA)

FRAMATOME S LESSONS LEARNED ON RISK-INFORMED APPLICATIONS (RIA) FRAMATOME S LESSONS LEARNED ON RISK-INFORMED APPLICATIONS (RIA) THE EXPERIENCE GAINED FROM OLKILUOTO 3 EPR PROJECT PSAM14 Conference Presenter: Hervé Brunelière, Reliability Senior Expert Other authors:

More information

AREVA Forward-looking Nuclear Energy. Karl-Heinz Poets AREVA South America

AREVA Forward-looking Nuclear Energy. Karl-Heinz Poets AREVA South America AREVA Forward-looking Nuclear Energy Karl-Heinz Poets AREVA South America Energy market: continued growth announced tep Macroeconomics Energy demand multiplied by 2 by 2050 1990 2010 2030 BUSINESS AS USUAL

More information

NQA-1 Graded Approach, 55-Gallon Drum Summary

NQA-1 Graded Approach, 55-Gallon Drum Summary 1, Organization 2, Quality Assurance program 3, Design 4, Procurement Document 5, Instructions, procedures, and Drawings 100 Basic 200 Structure and Responsibility 201 General 202 Delegation of Work 300

More information