Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project

Size: px
Start display at page:

Download "Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project"

Transcription

1 Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project US Army Corps of Engineers Zac Corum, PE, Hydraulic Engineer Travis Ball, PE, CFM, Hydraulic Engineer Seattle District U.S. Army Corps of Engineers ASFPM 2014 Conference 03-June, 2014

2 Overview of talk Elwha River Basin Overview Current Status on dam removals Project purpose Background on the Corps role in restoring the river Unique technical challenges associated with Lower Elwha Klallam Tribe Federal Levee modification project Lessons Learned July 2005 July 2013 photo credit: Ian Miller, WA Sea Grant

3 Elwha River Basin Federal/Tribal Levee You are here

4 Elwha River Basin Birds Eye View You are here Federal/Tribal Levee Glines Canyon Dam site about 20 feet left to go as of spring 2014 Elwha Dam site dam completely removed as of 2013

5 Elwha Basin Overview - Flood Hydrology Nov Dec Annual Exceedance Probability (AEP) % 1% 2% 5% 10% 20% 50%

6 Project Purpose: Ensure downstream flood risks to people, property, and water infrastructure not worsened by largest controlled release of sediment in history. Glines Canyon Dam removal in progress April 2014 (NPS)

7 Source of the issue #1 - Former Lake Mills Reservoir April , (NPS/USBR/USGS)

8 Source of the issue #1 - Former Lake Mills Reservoir April , (NPS/USBR/USGS)

9 Corps Role in Elwha River Restoration Conducted under Interagency Agreements with NPS in close coordination with Dept of Interior Floodplain studies on the Elwha Identify at risk properties and infrastructure Estimate change in flood risk Propose mitigation options to NPS Corps and NPS implement flood risk mitigation measures (levees, hatchery upgrades, well upgrades, private home elevation)

10 Corps Role in Elwha River Restoration Federal levee (raised, extended, new pump station) Elwha Water Facilities levees (new) Westside levee (raised)

11 Federal Levee Modification: Originally authorized and built in 1980s to provide 200-year level of protection with 4 feet of freeboard. Protects Reservation from riverine flooding, but not coastal flooding feet long, average increase of 3 feet. Certified to provide 95% CNEP of overtopping in 0.5% AEP event maintained after dam removal. Levee extended to prevent increased risk of flanking. New pump station for interior drainage Designed and constructed by USACE. Total cost of $8.7m.

12 Primary Technical Challenges associated with Federal levee modification project 1. How much do we need to raise the levee? 2. How far do we need to extend the levee? 3. How do we protect the levee from erosion and scour?

13 Factors affecting flood levels along Federal Levee 1. Tides, waves, and delta morphodynamics 2. Floods 3. Channel conditions 1. Cross section, roughness, planform, slope 2. Morphodynamics (River migration and avulsion) 4. Dam removal 1. Sediment supply, rate, type 2. Wood 5. Human intervention levees, roads, ELJs These are all inter-related, variable, uncertain, and time dependent when it comes to predicting flood elevations, modeling is required to understand relative contributions of these factors and their uncertainties.

14 How do we address complex flood problem? Risk and Uncertainty (R&U) Framework 1. What is existing reliability against flooding caused by overtopping? 2. Does reliability against overtopping after dam removal decrease? 3. If so, how much? 4. Elevate until existing reliability against overtopping achieved 5. For background:

15 USACE method for addressing flood impacts 1. Modify hydraulic models to reflect best guess and conservative sedimentation scenarios 2. Evaluate sensitivity of flood stage to different scenarios 3. Perform statistical analysis of stage uncertainty, also accounting for hydrologic uncertainty

16 Real world complications: Delta morpho-dynamics and effect on river flood levels 400 ft wide mouth in flood event 800 ft wide mouth in 2008

17 Real world complications: Delta morpho-dynamics and effect on river flood levels Large reduction in flood backwater from mouth widening results in justifiably lower levee elevations

18 Real world complications: Sediment fate and delta growth PREDICTION 2009 VS. REALITY 2014 Image credit: CWI & Roordaaerial.com

19 Putting it all together PDF? Flood elevation Likelihood of occurrence

20 Issue 2 Levee extent LiDAR saves the day! LiDAR identifies unknown paleo channel and terrace south of levee Updated hydraulic models indicate river can activate these channels during 50-year return interval flood, allowing water to flank levee Depending on aggradation scenario flows can change by 2 orders of magnitude Sensitivity analysis and risk based levee design used to set crest height. BUILDING STRONG

21 Issue 2 Levee extent south end Heavy vegetation obscured topography on high terrace during previous floodplain modeling efforts. No extension anticipated.

22 Issue 2 Levee extent south end 2000 LiDAR flight results in discovery of several paleo channels on high terrace and realization that flood protection needed to be extended to prevent levee flanking during 200-year design flood

23 Issue 2 Levee extent check your work 1. Paleo channel discovery resulted in decision to extend levee south to cutoff potential overflow path. River channel flood levels used for design. 2. Major problem identified with levee elevation at south end during final floodplain map revisions, using new data set and updated models. 3. Levee modified using emergency contract and now provides continuous 200-year level of protection Original design crest > 3 above main channel water level

24 Issue 2 Levee extent check your work 1. Paleo channel discovery resulted in decision to extend levee south to cutoff potential overflow path. River channel flood levels used for design. 2. Major problem identified with levee elevation at south end during final floodplain map revisions, using new data set and updated models. 3. Levee modified using emergency contract and now provides continuous 200-year level of protection Predicted design flood level in side channel from split flow analysis

25 Issue 2 Levee extent check your work 1. Paleo channel discovery resulted in decision to extend levee south to cutoff potential overflow path. River channel flood levels used for design. 2. Major problem identified with levee elevation at south end during final floodplain map revisions, using new data set and updated models. 3. Levee modified using emergency contract and now provides continuous 200-year level of protection New crest accounting for split flows and uncertainty

26 Issue 3 Levee slope and scour protection Risk Informed Revetment Design 1. River was actively migrating and avulsing under pre-dam removal conditions 2. CMZ informed by LiDAR and HEC-RAS modeling of existing and future conditions 3. Risk evaluation of setback levee segments 4. Risk based design to limit costs

27 Issue 3 Levee slope and scour protection

28 Issue 3 Levee slope and scour protection Severe risk slope protection Moderate-high risk slope protection

29 Lessons Learned Flood risk management in a complex, dynamic ecosystem requires good communication, creative thinking and risk informed decision making or much better models Restoration requires mitigation with traditional hard engineering approaches to make floodplain property owners whole Modification of a Federal levees is difficult and requires close coordination with Corps of Engineers and potentially imposes a significant technical and financial burden on proponent

30 Lessons Learned Creative thinking required, but traditional methods and tools are flexible enough to apply to unprecedented problems Corps H&H modeling and statistical approaches are technically robust and powerful way to demonstrate Federal Government is meeting its responsibilities when it comes to flood risk management Buying out properties reduces unknowns and reduces risks. It also simplifies the project and reduces need for due diligence during planning, design and implementation phases.

31 Unofficial Lessons Learned

32 Thank You Project Partners: Seattle District USACE, NPS, USBR, USGS, Lower Elwha Klallam Tribe, City of Port Angeles, Clallam County, URS, HDR, Watts-Delhur, PBS&J, JW Fowler, Fed Con Special thanks: Travis Ball, Brian Winter, Jeff Bohman, Tim Randle, Jennifer Bountry, Chris Magirl, Roordaaerial.com, Ian More info flood-protection.htm Zac Corum (206) zachary.p.corum@usace.army.mil

Tribal Partnership Program Jamestown S Klallam Tribe and USACE Dungeness River in Washington State

Tribal Partnership Program Jamestown S Klallam Tribe and USACE Dungeness River in Washington State Tribal Partnership Program Jamestown S Klallam Tribe and USACE Dungeness River in Washington State Zac Corum, PE, Sr. Hydraulic Engineer, Seattle District USACE Randy Johnson, Habitat Program Manager (JSKT)

More information

Hydrology and Flooding

Hydrology and Flooding Hydrology and Flooding Background The 1996 flood Between February 4, 1996 and February 9, 1996 the Nehalem reporting station received 28.9 inches of rain. Approximately 14 inches fell in one 48 hour period.

More information

American Water Resources Association Philadelphia Metropolitan Area Section

American Water Resources Association Philadelphia Metropolitan Area Section American Water Resources Association Philadelphia Metropolitan Area Section Levee Evaluation and Certification under the NFIP November 18, 2010 Insert picture(s) here Agenda Background and Overview Flood

More information

Title Advanced Hydraulic Modeling to Support Emergency Action Plans

Title Advanced Hydraulic Modeling to Support Emergency Action Plans Title Advanced Hydraulic Modeling to Support Emergency Action Plans Abstract Freese and Nichols, Inc. (FNI) developed an Emergency Action Plan (EAP) for a Levee Improvement District (LID) located in a

More information

ENGINEERING AND CONSTRUCTION BULLETIN

ENGINEERING AND CONSTRUCTION BULLETIN ENGINEERING AND CONSTRUCTION BULLETIN No. 2017-15 Issuing Office: CECW-CE Issued: 14 Jul 17 Expires: 14 Jul 19 SUBJECT: Managed Overtopping of Levee Systems CATEGORY: Guidance APPLICABILITY: The U.S. Army

More information

Friant Dam and Millerton Reservoir

Friant Dam and Millerton Reservoir San Joaquin River Restoration Program Floodplain Management Association Presentation SJRRP Update Continued: Impacts from Subsidence April 18, 2013 1 Friant Dam and Millerton Reservoir Completed in 1942

More information

Are You Ready for Risk and Uncertainty Analysis?

Are You Ready for Risk and Uncertainty Analysis? Are You Ready for Risk and Uncertainty Analysis? Presented to: Illinois Association for Floodplain And Stormwater Management Presented by: David T. Williams, Ph.D., P.E., P.H., CFM. D.WRE Senior Technical

More information

Appendix I: Fixed-400,000 af Flood Storage Operation

Appendix I: Fixed-400,000 af Flood Storage Operation Appendix I: Fixed-400,000 af Flood Storage Operation 1.0 FIXED-400,000 AF FLOOD STORAGE OPERATION This operation set provides a comparison of operations before the SAFCA/Reclamation interim agreement in

More information

Distributed Storage Alternative Screening Analysis February 17, 2015

Distributed Storage Alternative Screening Analysis February 17, 2015 Distributed Storage Alternative Screening Analysis February 17, 2015 Executive Summary The Distributed Storage Alternative (DSA) was conceptualized during the public comment and alternative screening process

More information

Everglades Restoration Climate Program

Everglades Restoration Climate Program Sea Level Change and Long Range Water Resources Planning for Florida Everglades Restoration Climate Program Change Application Concerns of USACE and Guidance Draft Sea Level on Sea Rise Level Planning

More information

Scope of Work Lower Arroyo Grande Creek Flooding Analysis

Scope of Work Lower Arroyo Grande Creek Flooding Analysis Scope of Work Lower Arroyo Grande Creek Flooding Analysis Overview Please note that the limits of work for the hydrologic and hydraulic analysis include the following: Detailed topographic surveys: flood

More information

DES MOINES RIVER RESERVOIRS WATER CONTROL PLAN UPDATES IOWA ASCE WATER RESOURCES DESIGN CONFERENCE

DES MOINES RIVER RESERVOIRS WATER CONTROL PLAN UPDATES IOWA ASCE WATER RESOURCES DESIGN CONFERENCE DES MOINES RIVER RESERVOIRS WATER CONTROL PLAN UPDATES 237 237 237 217 217 217 200 200 200 0 0 0 163 163 163 131 132 122 80 119 27 252 174.59 110 135 120 112 92 56 IOWA ASCE WATER RESOURCES DESIGN CONFERENCE

More information

Technical Memorandum. Hydraulic Analysis Smith House Flood Stages. 1.0 Introduction

Technical Memorandum. Hydraulic Analysis Smith House Flood Stages. 1.0 Introduction Technical Memorandum Hydraulic Analysis Smith House Flood Stages 1.0 Introduction Pacific International Engineering (PIE) performed a hydraulic analysis to estimate the water surface elevations of the

More information

Brian Rast, PE, CFM, PMP Lead Silver Jackets Coordinator, Kansas and Missouri Kris Lander, PE, CFM Hydrologist. June 4, 2015

Brian Rast, PE, CFM, PMP Lead Silver Jackets Coordinator, Kansas and Missouri Kris Lander, PE, CFM Hydrologist. June 4, 2015 Presentation to the Association of State Floodplain Managers Interagency Partnering for Flood Forecast Inundation Maps Brian Rast, PE, CFM, PMP Lead Silver Jackets Coordinator, Kansas and Missouri Kris

More information

Failure Consequence Classification

Failure Consequence Classification Failure Consequence Classification Audience: Dam Safety Officers (DSO) Owners of small dams Community emergency preparedness coordinators Introduction This document provides an overview of failure consequence

More information

Watersheds, Hydrology and Flooding

Watersheds, Hydrology and Flooding Watersheds, Hydrology and Flooding Greg Karlovits, P.E., CFM Hydrologist US Army Corps of Engineers Rock Island District US Army Corps of Engineers Outline of Topics Before lunch: Watersheds and basics

More information

Exploring*Common*Ground*between*Agriculture*and*Ecological* Restora9on*in*Large;River*Floodplains

Exploring*Common*Ground*between*Agriculture*and*Ecological* Restora9on*in*Large;River*Floodplains Columbia Environmental Research Center River Corridor Habitat Dynamics Exploring*Common*Ground*between*Agriculture*and*Ecological* Restora9on*in*Large;River*Floodplains Robert Jacobson, Ph.D. Supervisory

More information

Appendix J Hydrology and Hydraulics

Appendix J Hydrology and Hydraulics Appendix J Hydrology and Hydraulics Marsh Lake Dam Ecosystems Restoration Feasibility Study Hydraulics & Hydrology Appendix January 2011 Contents List of Figures iii List of Tables iii I. General 1 II.

More information

DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS

DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano, P.E. May 29, 2014 PROJECT BACKGROUND Integrated Pipeline Project 149 miles of pipeline 3 booster

More information

Restoration of Riparian Forests and Riparian Ecosystem Processes and Implications for Salmon Restoration. Katie Ross-Smith Jennifer Hammond

Restoration of Riparian Forests and Riparian Ecosystem Processes and Implications for Salmon Restoration. Katie Ross-Smith Jennifer Hammond Restoration of Riparian Forests and Riparian Ecosystem Processes and Implications for Salmon Restoration Katie Ross-Smith Jennifer Hammond Outline > Background California riparian communities Riparian

More information

HEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification

HEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification HEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification OFMA 2017 Annual Conference September 19, 2017 Presented by: Jeff Doudrick, PE, ENV SP Project Manager HNTB Corporation Agenda Project

More information

IAFSM 2010 Annual Conference. City of Rockford Keith Creek Greenway Flood Mitigation Project

IAFSM 2010 Annual Conference. City of Rockford Keith Creek Greenway Flood Mitigation Project IAFSM 2010 Annual Conference City of Rockford Keith Creek Greenway Flood Mitigation Project March 10, 2010 Introduction Problem Overview 1890 s Building of homes along Keith Creek 1920 s Home construction

More information

PAPERWORK REDUCTION ACT A. GENERAL

PAPERWORK REDUCTION ACT A. GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY - FEDERAL EMERGENCY MANAGEMENT AGENCY RIVERINE STRUCTURES FORM O.M.B No. 1660-0016 Expires: 12/31/2010 PAPERWORK REDUCTION ACT Public reporting burden for this form

More information

CHAPTER 7. San Dieguito River Flooding Adaptation

CHAPTER 7. San Dieguito River Flooding Adaptation CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,

More information

Breach Analyses of High Hazard Dams in Williamson County

Breach Analyses of High Hazard Dams in Williamson County Breach Analyses of High Hazard Dams in Williamson County John R. King 1, P.E., Kim Patak 2, P.E., Blaine Laechelin 3, E.I.T. Abstract The Upper Brushy Creek WCID operates 23 dams in the Upper Brushy Creek

More information

PA of NY&NJ - TETERBORO AIRPORT RUNWAY 6-24 Engineered Material Arresting System (EMAS) UNSTEADY-STATE FLOODPLAIN ANALYSIS

PA of NY&NJ - TETERBORO AIRPORT RUNWAY 6-24 Engineered Material Arresting System (EMAS) UNSTEADY-STATE FLOODPLAIN ANALYSIS 1 NEW JERSEY ASSOCIATION FOR FLOODPLAIN MANAGEMENT PRESENTATION FOR THE 10 TH ANNUAL CONFERENCE PA of NY&NJ - TETERBORO AIRPORT RUNWAY 6-24 Engineered Material Arresting System (EMAS) UNSTEADY-STATE FLOODPLAIN

More information

Outlet Structure Modeling

Outlet Structure Modeling Watershed Modeling using HEC-RAS Outlet Structure Modeling Jeff Wickenkamp, P.E., CFM, D.WRE Patrick Lach, P.E. Hey and Associates, Inc. Water Resources, Wetlands and Ecology Outline of Presentation Why

More information

Upper Mississippi River Basin Environmental Management Program Workshop

Upper Mississippi River Basin Environmental Management Program Workshop Presentation to the Upper Mississippi River Basin Environmental Management Program Workshop by Kara Mitvalsky Environmental Engineer US Army Corps of Engineers, Rock Island District August 18, 2005 Engineering

More information

Under a Changing Climate:

Under a Changing Climate: Engineering Methods for Precipitation Under a Changing Climate: Outline of the Problem J. Rolf Olsen Institute for Water Resources U.S. Army Corps of Engineers Alexandria, Virginia ASCE Committee on Adaptation

More information

SAN GABRIEL RIVER/SAN JOSE CREEK 1 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

SAN GABRIEL RIVER/SAN JOSE CREEK 1 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # SAN GABRIEL RIVER/SAN JOSE CREEK 1 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # 3805010052 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: MINIMALLY ACCEPTABLE

More information

San Luis Obispo Creek Watershed Hydrologic Model Inputs

San Luis Obispo Creek Watershed Hydrologic Model Inputs Jeff Werst San Luis Obispo County Department of Public Works 1050 Monterey Street San Luis Obispo CA 93408 December 14, 2007 Subject: San Luis Obispo Creek Watershed Hydrology and Hydraulic Model Dear

More information

Lewisville Dam. Draft Dam Safety Modification Environmental Assessment Public Review

Lewisville Dam. Draft Dam Safety Modification Environmental Assessment Public Review Lewisville Dam Draft Dam Safety Modification Environmental Assessment Public Review Stacy Gray (Project Manager) U.S. Army Corps of Engineers, Fort Worth District 27 September 2016 US Army Corps of Engineers

More information

NEPA Scoping Meeting Rahway River Basin, New Jersey Flood Risk Management Feasibility Study

NEPA Scoping Meeting Rahway River Basin, New Jersey Flood Risk Management Feasibility Study NEPA Scoping Meeting Rahway River Basin, New Jersey Flood Risk Management Feasibility Study U.S. Army Corps of Engineers New York District New Jersey Department of Environmental Protection Non-Federal

More information

Briefing to Elected Officials

Briefing to Elected Officials Passaic River Main Stem Flood Risk Management Project Preliminary Alternative Analysis Report Briefing to Elected Officials Bob Martin Commissioner New Jersey Department of Environmental Protection COL

More information

Appendix C, Attachment 4 June 11, Diversion Channel Outlet Hydraulic Modeling RAS and ADH

Appendix C, Attachment 4 June 11, Diversion Channel Outlet Hydraulic Modeling RAS and ADH Diversion Channel Outlet Hydraulic Modeling RAS and ADH 11 June 2012 1 Contents Introduction... 3 HEC-RAS modeling of Outlet... 3 Transition Structure Geometry... 3 ADH Modeling of Outlet and Floodplain...

More information

Risk Assessment and Habitat Restoration

Risk Assessment and Habitat Restoration Risk Assessment and Habitat Restoration Tim Abbe Jennifer Black Goldsmith A general introduction to risk assessment, decision tree analysis and our perspective interspersed with photos. 1 How accountable

More information

A Federal Family Comes Together Association of State Floodplain Managers Conference

A Federal Family Comes Together Association of State Floodplain Managers Conference A Federal Family Comes Together 2016 Association of State Floodplain Managers Conference Region 6 by the Numbers 5 States 5 USGS Offices 6 USACE Districts 6 HUC2 Regions 40 HUC4 Subregions 403 HUC8 Watersheds

More information

Port of Camas/Washougal Levee Recertification and Engineering Analysis Request for Proposal May 3, 2011

Port of Camas/Washougal Levee Recertification and Engineering Analysis Request for Proposal May 3, 2011 I. Project Summary As part of their Map Modernization Program, FEMA has initiated a countywide Flood Insurance Study (FIS) and Digital Flood Insurance Rate Map (DFIRM) for the Port of Camas/Washougal.

More information

Kansas Levee Certifications Assessments, Findings and Challenges. APWA Congress Denver, Co - Sept 18, 2011

Kansas Levee Certifications Assessments, Findings and Challenges. APWA Congress Denver, Co - Sept 18, 2011 Kansas Levee Certifications Assessments, Findings and Challenges APWA Congress Denver, Co - Sept 18, 2011 Introductions Presenters Doug Danaher, PE, CFM Wilson and Company Joe File, PE, CFM AMEC Brian

More information

Appendix B Stormwater Site Plan Submittal Requirements Checklist

Appendix B Stormwater Site Plan Submittal Requirements Checklist Stormwater Site Plan Submittal Requirements Checklist The Submittal Requirements Checklist is intended to aid the design engineer in preparing a Stormwater Site Plan. All items included in the following

More information

Manhattan Levee Section 216 Feasibility Study Public Workshop 17Apr13 Manhattan Kansas

Manhattan Levee Section 216 Feasibility Study Public Workshop 17Apr13 Manhattan Kansas Manhattan Levee Section 216 Feasibility Study Public Workshop 17Apr13 Manhattan Kansas Tuttle Creek Dam and Lake Kansas City District Project Development Team Manhattan, KS US Army Corps of Engineers 1

More information

HYDRAULIC CONNECTIVITY (HC) ENGINEERING & HYDRAULICS PERSPECTIVES

HYDRAULIC CONNECTIVITY (HC) ENGINEERING & HYDRAULICS PERSPECTIVES HYDRAULIC CONNECTIVITY (HC) ENGINEERING & HYDRAULICS PERSPECTIVES Presented at the UMRR HREP Team Meeting September 28, 2016 Jon Hendrickson Regional Technical Specialist, Eco-Hydraulics & WQ USACE, Mississippi

More information

RE: Recommendations for Staged Implementation of Alternative 3a

RE: Recommendations for Staged Implementation of Alternative 3a March 10, 2006 Ms. Julie Thomas Coastal San Luis Resource Conservation District 545 Main Street, Suite B-1 Morry Bay, Ca 93442 RE: Recommendations for Staged Implementation of Alternative 3a Dear Ms. Thomas,

More information

SUMMARY OF BACKGROUND INFORMATION REVIEWED

SUMMARY OF BACKGROUND INFORMATION REVIEWED TO: FROM: Mark Lobermeier, PE Ismael Martinez, PE Brad Woznak, PE, PH, CFM Tim Diedrich, PE DATE: RE: Kinni Corridor Plan - Hydrologic & Hydraulic Analysis Summary SEH No. RIVER 138553 14.00 This draft

More information

Hydraulic and Sediment Transport Modeling Strategy

Hydraulic and Sediment Transport Modeling Strategy Appendix B Hydraulic and Sediment Transport May 2014 Technical Memorandum Channel Capacity Report September 2014 San Joaquin River Restoration Program Hydraulic and Sediment Transport The San Joaquin River

More information

Technical Memorandum Public Draft Channel Capacity Report 2019 Restoration Year

Technical Memorandum Public Draft Channel Capacity Report 2019 Restoration Year Public Draft Channel Capacity Report 2019 Restoration Year 1 Table of Contents 2 1.0 Executive Summary... 1 3 2.0 Introduction... 1 4 3.0 Study Area... 3 5 4.0 Completed Channel Capacity Studies and Related

More information

AGUA FRIA RIVER 5 LEVEE SYSTEM MARICOPA COUNTY, ARIZONA NLD SYSTEM ID #

AGUA FRIA RIVER 5 LEVEE SYSTEM MARICOPA COUNTY, ARIZONA NLD SYSTEM ID # AGUA FRIA RIVER 5 LEVEE SYSTEM MARICOPA COUNTY, ARIZONA NLD SYSTEM ID # 3805020001 PERIODIC INSPECTION REPORT NO. 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: MINIMALLY ACCEPTABLE FINAL RATING

More information

PRESENTATION FOR THE POTENTIAL ADDITION OF SPECIAL FLOOD HAZARD AREAS

PRESENTATION FOR THE POTENTIAL ADDITION OF SPECIAL FLOOD HAZARD AREAS PRESENTATION FOR THE POTENTIAL ADDITION OF SPECIAL FLOOD HAZARD AREAS 1 255 255 255 237 237 237 217 217 217 200 200 200 Part 1: Summary of Floodplain Analysis for Los 0 Angeles 163 131 River239 110 112

More information

John Remus Assessment of Conceptual Nonstructural Alternative

John Remus Assessment of Conceptual Nonstructural Alternative John Remus Assessment of Conceptual Nonstructural Alternative Assessment of Conceptual Nonstructural Alternative Levee Setbacks along the Missouri River (Lower L-575 / Upper L-550 and Lower L-550) Missouri

More information

Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California

Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California Final Report September 2005 Prepared by Center for Ecosystem Management and Restoration, Oakland,

More information

Lower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM

Lower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM PLAN FORMULATION ADDENDUM Non-Structural Measure Descriptions Elevate Critical Infrastructure This measure would raise at-risk critical structures above the design inundation level. Elevation would be

More information

CHAPTER 7. San Dieguito River Flooding Adaptation

CHAPTER 7. San Dieguito River Flooding Adaptation CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,

More information

USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED

USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED 1 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56

More information

SECTION 7.0 PROJECT FEASIBILITY, ENGINEER S RECOMMENDATION AND DESIGN ISSUES NEEDING RESOLUTION

SECTION 7.0 PROJECT FEASIBILITY, ENGINEER S RECOMMENDATION AND DESIGN ISSUES NEEDING RESOLUTION SECTION 7.0 PROJECT FEASIBILITY, ENGINEER S RECOMMENDATION AND DESIGN ISSUES NEEDING RESOLUTION 7.1 PROJECT FEASIBILITY The determination of project feasibility is based upon several criteria established

More information

LOS ANGELES RIVER 7 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

LOS ANGELES RIVER 7 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # 3805010078 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: UNACCEPTABLE FINAL RATING DATE: AUGUST 26, 2015 PERIODIC INSPECTION

More information

Webinar for the Natural Floodplain Function Alliance 18 November 2013

Webinar for the Natural Floodplain Function Alliance 18 November 2013 Moving toward Floodplain Restoration at Scale on the Illinois River and Upper Mississippi Basin: Valuing Ecosystem Services, Demonstrating Flood Reduction, and Policy Implications Webinar for the Natural

More information

Water Data Needs and Applications in the Private Sector. Robert Annear, Vice President, Ph.D., P.E. Water is our nature

Water Data Needs and Applications in the Private Sector. Robert Annear, Vice President, Ph.D., P.E. Water is our nature Water Data Needs and Applications in the Private Sector Robert Annear, Vice President, Ph.D., P.E. Water is our nature GRN Forum: Global Water - 2010 and Beyond Oct 21 2010 - Oct 22 2010 Introduction Our

More information

SWAP Risk Informed Methods for Stormwater Assessment and Prioritization

SWAP Risk Informed Methods for Stormwater Assessment and Prioritization SWAP Risk Informed Methods for Stormwater Assessment and Prioritization Sara Hillegas Woida, Hydraulic Engineer US Army Corps of Engineers, Pittsburgh Thomas Maier, Biologist/Planner US Army Corps of Engineers,

More information

CORPS OF ENGINEERS: CLIMATE CHANGE AND THE COLUMBIA RIVER BASIN

CORPS OF ENGINEERS: CLIMATE CHANGE AND THE COLUMBIA RIVER BASIN CORPS OF ENGINEERS: CLIMATE CHANGE AND THE COLUMBIA RIVER BASIN 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102

More information

APPENDIX 4 ARROYO MODELING

APPENDIX 4 ARROYO MODELING APPENDIX 4 ARROYO MODELING The existing HEC-HMS model can serve as a baseline for further development and analysis of major arroyos in the city. The model would need to be updated and expanded to consider

More information

TECHNICAL MEMORANDUM Summerhill Rd Texarkana, Texas fax

TECHNICAL MEMORANDUM Summerhill Rd Texarkana, Texas fax TECHNICAL MEMORANDUM 5930 Summerhill Rd Texarkana, Texas 75503 903 838 8533 fax 903 832 4700 TO: Becky Griffith, Jon Jarvis FROM Spandana Tummuri SUBJECT: Technical Memorandum on IP Analysis PROJECT: Sulphur

More information

Clallam County Shoreline Master Program Update

Clallam County Shoreline Master Program Update Clallam County Shoreline Master Program Update Board of Commissioners Work Session November 13, 2017 Topics Buffers Channel Migrations Zones (CMZs) Mitigation and No Net Loss Importance of Buffers Provide

More information

DRAFT FOREST VIEW, ILLINOIS SECTION 205 FLOOD RISK MANAGEMENT APPENDIX E HYDROLOGY AND HYDRAULIC ANALYSIS

DRAFT FOREST VIEW, ILLINOIS SECTION 205 FLOOD RISK MANAGEMENT APPENDIX E HYDROLOGY AND HYDRAULIC ANALYSIS FOREST VIEW, ILLINOIS SECTION 205 FLOOD RISK MANAGEMENT APPENDIX E HYDROLOGY AND HYDRAULIC ANALYSIS U.S. Army Corps of Engineers, Chicago District Hydraulics and Environmental Engineering Section 17 March

More information

OVERVIEW OF RESERVOIR OPERATIONS AND FLOOD RISK MANAGEMENT

OVERVIEW OF RESERVOIR OPERATIONS AND FLOOD RISK MANAGEMENT OVERVIEW OF RESERVOIR OPERATIONS AND FLOOD RISK MANAGEMENT 255 255 255 237 237 237 0 0 0 217 217 217 163 163 163 200 200 200 COLUMBIA RIVER BASIN 131 132 122 239 65 53 80 119 27 110 135 120 252 174.59

More information

Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map

Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map Kentucky Dam Safety Hazard Mitigation Driving Local Mitigation Actions through Risk Map Michelle Meehan, PE Carey Johnson ASFPM 2013 Conference June 12, 2013 What We ll Talk About Today Overview of KDOW

More information

CHAPTER 3 FLOOD RELATED STUDIES

CHAPTER 3 FLOOD RELATED STUDIES CHAPTER 3 FLOOD RELATED STUDIES Although the area has experienced regular flooding there have been few formal flood studies until more recently. There are a number of water quality studies in the basins.

More information

Fargo-Moorhead Metropolitan Feasibility Study. Presentation for. City Engineers Association of Minnesota

Fargo-Moorhead Metropolitan Feasibility Study. Presentation for. City Engineers Association of Minnesota Fargo-Moorhead Metropolitan Feasibility Study Presentation for City Engineers Association of Minnesota January 28, 2010 Partners Corps of Engineers City of Fargo City of Moorhead Metropolitan Flood Management

More information

FEMA and Levees Levee Accreditation Reviews Proposed Changes to the FEMA Levee Policy

FEMA and Levees Levee Accreditation Reviews Proposed Changes to the FEMA Levee Policy Agenda FEMA and Levees Levee Accreditation Reviews Proposed Changes to the FEMA Levee Policy Page 2 FEMA and Levees FEMA and Levees FEMA does NOT own or operate any levees Establishment of appropriate

More information

Environmental Protection (NJDEP) The Louis Berger Group, Inc.

Environmental Protection (NJDEP) The Louis Berger Group, Inc. Hydraulic Modeling for Preliminary Evaluation of Potential Flooding Impacts for Various Dredging, Capping and Armoring Scenarios of The Lower Passaic River Restoration Abdulai Fofanah, PE, D.WRE, CFM Murat

More information

Technical Memorandum No. 8 June 3, 2013 Page 2. FEMA Floodplain Mapping Flood Elevations at WWTP

Technical Memorandum No. 8 June 3, 2013 Page 2. FEMA Floodplain Mapping Flood Elevations at WWTP Page 2 FEMA Floodplain Mapping Flood Elevations at WWTP Existing Flood Control Facilities The City of Davis WWTP is located immediately north of the Willow Slough Bypass and west of the Yolo Bypass (see

More information

PUBLIC INFORMATION MEETING Rahway River Basin Flood Risk Management Feasibility Study

PUBLIC INFORMATION MEETING Rahway River Basin Flood Risk Management Feasibility Study PUBLIC INFORMATION MEETING Rahway River Basin Flood Risk Management Feasibility Study COL Paul E. Owen District Engineer U.S. Army Corps of Engineers New York District New Jersey Department of Environmental

More information

Glades Reservoir Environmental Impact Statement (EIS)

Glades Reservoir Environmental Impact Statement (EIS) Glades Reservoir Environmental Impact Statement (EIS) Permit Application #SAS-2007-00388 Public Scoping Meeting Proposed Operational Plan/Scenarios March 2012 Glades Reservoir Environmental Impact Statement

More information

Hydrologic and Ecologic Analysis and Targets. Water Quality Targets and Feature Performance

Hydrologic and Ecologic Analysis and Targets. Water Quality Targets and Feature Performance WRAC Issues Workshop - Phase I Planning September 2, 2009 Temperince Morgan, River of Grass Project Liaison/Northern Everglades Program Implementation Manager Recap from August Workshop Restoration Concepts

More information

Levees and Extreme Water Levels in the Southern Louisiana

Levees and Extreme Water Levels in the Southern Louisiana Proactive By Design. Our Company Commitment Levees and Extreme Water Levels in the Southern Louisiana ASFPM 2015 Conference Kenneth D. Hunu, PE GZA GeoEnvironmental, Inc. Page 1 Hydrologic Setting Page

More information

SANTA MARIA RIVER 3A LEVEE SEGMENT SANTA BARBARA COUNTY, CALIFORNIA NLD SYSTEM ID #

SANTA MARIA RIVER 3A LEVEE SEGMENT SANTA BARBARA COUNTY, CALIFORNIA NLD SYSTEM ID # SANTA MARIA RIVER 3A LEVEE SEGMENT SANTA BARBARA COUNTY, CALIFORNIA NLD SYSTEM ID # 3805010095 PERIODIC INSPECTION REPORT NO. 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: MINIMALLY ACCEPTABLE FINAL

More information

Bridge Replacement Project. Preliminary Hydraulic Study. Lincoln, California BRLS-5089 (021) BRIDGE 19C Mcbean Park Drive at Auburn Ravine

Bridge Replacement Project. Preliminary Hydraulic Study. Lincoln, California BRLS-5089 (021) BRIDGE 19C Mcbean Park Drive at Auburn Ravine Bridge Replacement Project Preliminary Hydraulic Study Lincoln, California BRLS-5089 (021) BRIDGE 19C 0059 Mcbean Park Drive at Auburn Ravine Prepared By: Prepared By: Date 11/25/2014 Thomas S. Plummer

More information

Skagit River Flood Damage Reduction Study

Skagit River Flood Damage Reduction Study Skagit River Flood Damage Reduction Study Preliminary Measures Presentation Aug. 18, 2008 Introduction Preliminary measures are required by the Corps planning guidance - ER-1105-2-100. Six-Step Planning

More information

PROJECT SCREENING MATRIX: A User s Guide

PROJECT SCREENING MATRIX: A User s Guide Version 2.0 Page 1 of 7 November 9, 2010 PROJECT SCREENING MATRIX: A User s Guide BACKGROUND The Project Screening Matrix (Screening Matrix) is one of several tools that comprise the River Restoration

More information

Prototype modifications within a flood control channel to improve fish passage in Mill Creek near Walla Walla, WA

Prototype modifications within a flood control channel to improve fish passage in Mill Creek near Walla Walla, WA University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

The Big Picture Approach: Meeting Community Objectives through Local Levee Partnership Teams

The Big Picture Approach: Meeting Community Objectives through Local Levee Partnership Teams ASFPM 2015 National Conference The Big Picture Approach: Meeting Community Objectives through Local Levee Partnership Teams Andrew Martin, CFM and David Rubenstein, CFM June 2, 2015 Agenda Quick Review:

More information

LEVEE DISTRICT NO. 1 OF SUTTER COUNTY

LEVEE DISTRICT NO. 1 OF SUTTER COUNTY LEVEE DISTRICT NO. 1 OF SUTTER COUNTY STAR BEND SETBACK LEVEE AND HABITAT ENHANCEMENT PROJECT BASIS OF DESIGN FEBRUARY 2009 Prepared By: TABLE OF CONTENTS QUALITY CONTROL CERTIFICATION... iv 1.0 INTRODUCTION...

More information

Red River Flooding. June 2015 Caddo and Bossier Parishes. Presented by: Richard Brontoli RRVA, Executive Director

Red River Flooding. June 2015 Caddo and Bossier Parishes. Presented by: Richard Brontoli RRVA, Executive Director Red River Flooding June 2015 Caddo and Bossier Parishes Presented by: Richard Brontoli RRVA, Executive Director Kiwanis Club of SE Shreveport May 2, 2018 Where the Rain Falls Matters I-30 versus I-20 Caddo

More information

Hackensack River Flood Reduction Study Update

Hackensack River Flood Reduction Study Update Township of River Vale Hackensack River Flood Reduction Study Update November 11, 2013 Purpose of Study To Analyze Where Frequent Flooding Is Impacting Property and How It Might Be Reduced Hackensack River

More information

Preliminary Feasibility Study for South San Francisco Bay Shoreline Economic Impact Areas 1-10 Executive Summary

Preliminary Feasibility Study for South San Francisco Bay Shoreline Economic Impact Areas 1-10 Executive Summary Economic Impact Areas 1-10 Executive Summary Prepared For: Department of Water Resource Division of Flood Management State Of California Prepared By: Santa Clara Valley Water District February 2017 A preliminary

More information

COACHELLA VALLEY WATER DISTRICT GUIDELINE K-2 SLOPE (BANK) PROTECTION DESIGN GUIDANCE

COACHELLA VALLEY WATER DISTRICT GUIDELINE K-2 SLOPE (BANK) PROTECTION DESIGN GUIDANCE COACHELLA VALLEY WATER DISTRICT GUIDELINE K-2 SLOPE (BANK) PROTECTION DESIGN GUIDANCE K.2.1 General Requirements The design and construction of slope protection works may be required for several types

More information

FY16 RSM IPR Portland District, Optimizing Fall Creek Reservoir Flush TMDL s, Stanford Gibson, Chris Nygaard, Jim Crain, Jarod Norton

FY16 RSM IPR Portland District, Optimizing Fall Creek Reservoir Flush TMDL s, Stanford Gibson, Chris Nygaard, Jim Crain, Jarod Norton Fall Creek Reservoir Fall Creek Dam is at river mile 7.2 on Fall Creek, a tributary of the Willamette River, about 20 miles southeast of Eugene, OR. Dam works in coordination with Lookout Point and Hills

More information

Case Studies in Hazard Class Reductions Implementation of NY s Guidance for Dam Hazard Classification

Case Studies in Hazard Class Reductions Implementation of NY s Guidance for Dam Hazard Classification Case Studies in Hazard Class Reductions Implementation of NY s Guidance for Dam Hazard Classification Gregory J Daviero, PhD, PE, Principal Kevin Ruswick, PE, CFM, Associate May 2, 2014 Schnabel Engineering

More information

Technical Memorandum No River Geometry

Technical Memorandum No River Geometry Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.5 River Geometry Task: Collection and Analysis of River Geometry Data To: PRWFPA Staff Working Group Prepared by: J. Schaaf

More information

Modeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014

Modeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014 ASFPM 2014 Annual Conference Modeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014 Agenda Overview and Background Hydrology

More information

CLAY STREET BRIDGE REPLACEMENT

CLAY STREET BRIDGE REPLACEMENT HYDROLOGY /HYDRAULICS REPORT. EL DORADO COUNTY CLAY STREET BRIDGE REPLACEMENT Prepared by: Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762

More information

APPENDIX A HYDROLOGIC AND HYDRAULIC ANALYSIS

APPENDIX A HYDROLOGIC AND HYDRAULIC ANALYSIS APPENDIX A HYDROLOGIC AND HYDRAULIC ANALYSIS GENERAL The Hydrologic and Hydraulic information presented in this appendix is provided as a supplement to the Dallas Floodway Extension General Re-evaluation

More information

STREAMBANK RESTORATION DESIGN

STREAMBANK RESTORATION DESIGN STREAMBANK RESTORATION DESIGN WITH VINYL SHEET PILE GRADE CONTROL STRUCTURES BRUCE M. PHILLIPS, M.S., P.E. ABSTRACT Grade control structures are an effective channel stabilization measure which can eliminate

More information

Interagency Performance Evaluation Task (IPET) Force. Engineering and Operational Risk and Reliability Analysis. Robert C. Patev

Interagency Performance Evaluation Task (IPET) Force. Engineering and Operational Risk and Reliability Analysis. Robert C. Patev Interagency Performance Evaluation Task (IPET) Force Engineering and Operational Risk and Reliability Analysis Robert C. Patev Deputy and Technical Lead, IPET Risk and Reliability Team IPET Risk Assessment

More information

Dam Safety & Planning: Examples of Collaboration and Lessons Learned

Dam Safety & Planning: Examples of Collaboration and Lessons Learned US Army Corps of Engineers PLANNING SMART BUILDING STRONG Dam Safety & Planning: Examples of Collaboration and Lessons Learned Eric Halpin, P.E. Special Assistant for Dam & Levee Safety, HQUSACE Maria

More information

SAGE. Systems Approach to Geomorphic Engineering. R. Grandpre, PF Wagner, D Larson- Salvatore, CB Chesnutt Institute for Water Resources

SAGE. Systems Approach to Geomorphic Engineering. R. Grandpre, PF Wagner, D Larson- Salvatore, CB Chesnutt Institute for Water Resources SAGE Systems Approach to Geomorphic Engineering R. Grandpre, PF Wagner, D Larson- Salvatore, CB Chesnutt Institute for Water Resources US Army Corps of Engineers Innovative Approach to Coastal Landscape

More information

Removal of the Last Fish Barrier on the Lower Rogue River Shane K. Cline, PE HDR Inc, Portland, OR

Removal of the Last Fish Barrier on the Lower Rogue River Shane K. Cline, PE HDR Inc, Portland, OR Removal of the Last Fish Barrier on the Lower Rogue River Shane K. Cline, PE HDR Inc, Portland, OR ,, Jackson Co., OR ,, Jackson Co., OR Project History Located in Jackson County on the Rogue River Log

More information

Freight Street Development Strategy

Freight Street Development Strategy Freight Street Development Strategy Appendix B: Naugatuck River Floodplain Analysis Freight Street Development Strategy DECEMBER 2017 Page B-1 1.0 NAUGATUCK RIVER FLOODPLAIN AT FREIGHT STREET 1.1 Watershed

More information

MILL CREEK FISH PASSAGE CONCEPTUAL DESIGNS FINAL REPORT

MILL CREEK FISH PASSAGE CONCEPTUAL DESIGNS FINAL REPORT MILL CREEK FISH PASSAGE CONCEPTUAL DESIGNS FINAL REPORT Prepared for Tri State Steelheaders Contact: Brian Burns 216 N. Roosevelt, PO Box 1375 Walla Walla, WA 99362 Prepared by Waterfall Engineering, L.L.C.

More information

Constructing Wetlands for Wastewater Treatment: Design Considerations & Strategies for Success

Constructing Wetlands for Wastewater Treatment: Design Considerations & Strategies for Success Constructing Wetlands for Wastewater Treatment: Design Considerations & Strategies for Success Metropolitan Water Reclamation District of Greater Chicago and V3 Companies Introductions Jennifer Maercklein,

More information

Training on Roads for Water and Resilience

Training on Roads for Water and Resilience Training on Roads for Water and Resilience ROADS AND FLOODS Floods have costs and benefits Costs: damage to infrastructure and houses, lost lives and crops Benefits: sedimentation provides fertile lands,

More information