Southwest Health System Construction Newsletter October 21, 2017

Size: px
Start display at page:

Download "Southwest Health System Construction Newsletter October 21, 2017"

Transcription

1 Southwest Health System

2 A Week in Review Patient Wing Asphalt Base was completed this week in the north section of the parking lot Sheetrock is substantially complete and everything should be ready for paint by the end of next week Painting was on hold this week to allow other subcontractors to complete work in more areas Headwall issues have been resolved and installation began this week for headwalls and cabinets Concrete paving at the ED entrance was completed Monday and additional snow melt tubing has been added to the sidewalks around the entrance and the sidewalks were poured on Friday The exterior automatic doors and the automatic operators are installed for the interior doors. There was an outage Monday to swap ATS-6 out with a temporary transfer switch to allow for the relocation of ATS-6 and permanent connection at its new location and an outage Thursday for ATS-2 Empire electric arrived earlier Thursday to switch power to the new Transformer MOB Sheetrock hanging on one side of walls on the first floors is almost complete Liquid flashing is almost complete the thermal air and water barrier system Windows on the first floor are almost complete, and everywhere should be complete next week Felt paper and the metal lath is being installed on north, west, and south walls in preparation for the stucco scratch coat next week Scaffold is going up on the east side to prepare for the start of stucco on the east well Nunn installed a sleeve for Atmos s gas line to allow site work to continue while The layout for curb and gutter and asphalt paving was done Thursday

3 Patient Wing Headwall installation is starting, plumbers and electricians will place their devices and the walls will be moved back

4 Patient Wing Concrete for the ED entrance and sidewalks poured this week after snow melt tubing was set

5 Patient Wing Four Corners was here this week to place asphalt base in the north parking lot

6 What s Next? Patient Wing Four Corners Asphalt is planned to be here in the next few weeks to pave the north section of the parking lot Ceramic tile is planned to be delivered the week of the 23 rd and installation will begin in the patient room toilets and showers The painter will return next week to complete paint in the ED corridor and areas in the Patient Wing proper that are ready for paint Stucco finish coat at the ED corridor will begin next week to allow the sidewalk to cure over the weekend before scaffold is set up Emergency power work will begin now that normal power work is complete The combination of additional snow melt tubing in the sidewalks and a few other hiccups has pushed the opening of the emergency entrance to October 30 th ASSA Abloy will return Monday to install the sliding door on the public vestibule Ceiling grid and tile and MEP trimout will start next Tuesday or Wednesday after paint is complete in the ED corridor MOB Sheetrock hanging will continue next week with rock on both sides and finishers following after The elevator subcontractor is planned to be here next week to inspect the elevator hoist beams and begin installation if everything has been resolved Window installation is planned to finish up by the end of next week Atmos has said they will be here in a couple weeks to get their gas line in Nunn is pushing to get the asphalt paving at the MOB complete this year before the plants shut down

7 MOB Sheetrock hanging on one side of walls in the first floor is almost complete

8 MOB Liquid flashing on the northeast corner and windows on the first floor are almost complete

9 Subcontractors on Site Present CRG (Excavation & Utilities) Miller Bonded (Patient Wing Electrical) Nichols Electric (MOB Electrical) Reigles Mechanical (Plumbing) Four Suns Builders (Framing & Sheetrock) Garrhs (HVAC) Cooper Fire Protection (Fire Suppression) Cruzan Construction (Demolition & Backing) Sun Glass (Windows and Storefronts) Advanced Concrete (Concrete) Four Corners Asphalt (Asphalt paving) ASSA Abloy (Automatic Entrances) Nunn Construction (General Work) Arriving Soon OTIS Elevator (MOB Elevator)

10 Weekly Weather

Southwest Health System Construction Newsletter October 7, 2017

Southwest Health System Construction Newsletter October 7, 2017 Southwest Health System A Week in Review Patient Wing Interior sheetrock is 99% complete in the Patient Wing proper Taping and finishing is following behind sheetrock, and Nunn is preparing rooms for paint

More information

New Ringgold Middle School. Project Slideshow August 26, 2017

New Ringgold Middle School. Project Slideshow August 26, 2017 New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo

More information

PAULDING COLLEGE & CAREER ACADEMY

PAULDING COLLEGE & CAREER ACADEMY PAULDING COLLEGE & CAREER ACADEMY 000110 OF THE PROJECT MANUAL FOR THE CONSTRUCTION OF: PAULDING COLLEGE & CAREER ACADEMY DALLAS, GEORGIA DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 TITLE

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #158 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #158 Douthit Hills Student Community, Clemson University Project Tony Greene February 16, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed 1 ST Coat of Paint in C5 Corridors. Completed Test & Balance in Building C. Completed Final Paint in B1 Corridors. Completed

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #168 Douthit Hills Student Community, Clemson University Project Rush Dunaway

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #168 Douthit Hills Student Community, Clemson University Project Rush Dunaway April 27, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Continued Installing Wireless Access Points in Bldg C. Continued Signing Off Punch List Items in the West Zone. Continued Cleaning Interior

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene October 6, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Hardscapes East of Building C. Completed Building D Dumpster Pad. Completed Brick on Site Wall North of Building D. Completed

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

Columbia County Health Care Center Added Amenities

Columbia County Health Care Center Added Amenities Columbia County Health Care Center Added Amenities Columbia County Board Meeting on January 16th, 2013 Building Exterior Added Amenities 1. Upgraded nail-base roofing insulation to 3 thickness on Center

More information

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project: RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:

More information

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #161 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #161 Douthit Hills Student Community, Clemson University Project Tony Greene March 9, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Final Paint in Building B Electrical Rooms. Completed Final Clean in C1 Units. Completed Installing Carpet/Base in Building D Corridors.

More information

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages TABLE OF CONTENTS VOLUME 1 DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages SCHEDULE OF DRAWINGS...... 1 PROJECT PERSONNEL & DIRECTORY......

More information

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 01 Project Title Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets 00 21

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #142 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #142 Douthit Hills Student Community, Clemson University Project Tony Greene October 27, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Tie-in & Start-up of HUB Sanitary Lift Station. Completed Brick on Stair Walls West of Building C. Completed Pouring the

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene August 25, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Turned All East Zone Parking Lots Over to Clemson. Completed Trench Drain on Bradley Road. Completed Pouring Walls for Building D

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

Fiddler's Marsh Cove

Fiddler's Marsh Cove Fiddler's Marsh Cove Tom McLellan 450-0326 Prepared: 6/14/2018 Lot Number D16 D31 D6 D25 D18 D15 D29 D7 D26 D20 Model MADISON2 MADISON2 CHANDLER MADISON2 MADISON2 MADISON2 LYNDON VALE ULYSSA MADISON2 Elevation

More information

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements SECTION A CM INSTRUCTIONS TO BIDDERS SECTION B BID CATEGORY DESCRIPTIONS & BID FORMS BC-07: Building HVAC and Plumbing BC-08: Building Electric BC-09: General Trades BC-10: Masonry BC-11: Precast Structural

More information

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE TABLE OF CONTENTS SECTION TITLE DATE Division 00 Procurement and Contracting Requirements 000101... Project Title Page 000116... CAD Standards 001116... Invitation to Bid 002113... Instructions to Bidders

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene March 2, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Final Paint in B6 Corridors. Completed Final Clean in CL1 Units. Continued Signing Off Punch List Items in the West Zone. Continued

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No. 20140101C CONSTRUCTION ESTIMATE AND PROJECT BUDGET Dated June 7. 2014 Estimated Cost HARD COSTS $ 1,560,284 Core Renovations (Toilet Rooms, Ceilings

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...

More information

TAXABLE PAYMENTS FACTSHEET. If you run a business in the building and. construction industry then you ll soon need

TAXABLE PAYMENTS FACTSHEET. If you run a business in the building and. construction industry then you ll soon need If you run a business in the building and construction industry then you ll soon need to do your Taxable Payments reporting. This factsheet contains a summary of the key tax changes surrounding taxable

More information

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6 PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #119 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #119 Douthit Hills Student Community, Clemson University Project Joe Jett May 19, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Continued Final Inspections @ Buildings G & F. Continued Punch List in Buildings G, F, & E. Continued Carpet Install @ Building F. Finished

More information

260,000 SF Building Profile

260,000 SF Building Profile Expanding Your Development & Investment Perspectives 260,000 SF Building Profile Precast & Brick Exterior Finish 245,000 SF Production/Warehouse 7,500 SF Office & 7,500 SF Mezzanine 50 x 50 Bays, 24 Clear

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #135 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #135 Douthit Hills Student Community, Clemson University Project Tony Greene September 8, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Received Certificate of Occupancy for Bldgs E, F, & G. Completed Spreading Topsoil North of Building B. Completed Footings at Building

More information

TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018

TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 The February 5, 2018 meeting of the Manchester Building Committee was held in the Manchester Room at the Town Hall. Manchester Building

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

ONE AND TWO FAMILY DWELLING PERMIT APPLICATION REQUIREMENTS

ONE AND TWO FAMILY DWELLING PERMIT APPLICATION REQUIREMENTS ONE AND TWO FAMILY DWELLING PERMIT APPLICATION REQUIREMENTS Submit a permit application with all applicable items completed, including inserts, when you construct a new building, construct an addition,

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Expanding Your Development & Investment Perspectives 159,000 SF Building Profile

Expanding Your Development & Investment Perspectives 159,000 SF Building Profile Expanding Your Development & Investment Perspectives 159,000 SF Building Profile Metal & EIFS Exterior Finish 150,000 SF Production/Warehouse 4,500 SF Office & 4,500 SF Mezzanine 50 x 50 Bays, 24 Clear

More information

The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits

The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits 3. Development and Septic Fees 4. Tarion New Home Warranty

More information

Request for Proposal

Request for Proposal 12 E 4 th St, Duluth MN 55805 July 17, 2018 Request for Proposal BID #: Grand Marais Phase 2 2018 PROJECT NAME: Nordic Star Housing Development Phase 2 ANNOUNCEMENT DATE: July 17, 2018 DUE DATE: July 24,

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

1065 N Canyon St, Ste. 8, Hildale, UT Cell: (435) N Richard

1065 N Canyon St, Ste. 8, Hildale, UT Cell: (435) N Richard 385 N Richard CRITICAL IMPROVEMENTS Windows, Doors, Cabinets Replace Crtitically Broken Windows Recommended to Finish Windows, Doors, Cabinets Replace Broken Windows 1065 N Canyon St, Ste. 8, Hildale,

More information

Inspection Report. Property Address:

Inspection Report. Property Address: Inspection Report provided by: Safe Side Home Inspection Inspector: Corey Stuart TN License # 778 434 Margaret Circle McMinnville, TN 37110 safesideinspection@blomand.net Property Address: 1234 Anywhere

More information

DESIGN & CONSTRUCTION GUIDELINES

DESIGN & CONSTRUCTION GUIDELINES DESIGN & CONSTRUCTION GUIDELINES EDITION: USF FACILITIES MANAGEMENT - DC 5 DCG FACILITIES MANAGEMENT DESIGN & CONSTRUCTION PHONE: (813) 974-2845 4202 E. FOWLER AVENUE, OPM 1000 TAMPA, FLORIDA 33620-7550

More information

Property Condition Assessment. Summary Report

Property Condition Assessment. Summary Report www.real-estate-inspections.com Property Condition Assessment Summary Report Subject Property Prepared for: Client in Detroit File Number: 05-15-005 Inspector: Craig Milliken, PE CPM Real Estate Inspections,

More information

C P A. Presented By Jason G. Smith, CCM, LEED AP. Founder and Principal of Construction Analysis and Planning, LLC

C P A. Presented By Jason G. Smith, CCM, LEED AP. Founder and Principal of Construction Analysis and Planning, LLC C P A CONSTRUCTION ANALYSIS AND PLANNING, LLC Presented By Jason G. Smith, CCM, LEED AP Founder and Principal of Author of Construction Management: Subcontractor Scopes of Work 1 Division of work: Primary

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #128 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #128 Douthit Hills Student Community, Clemson University Project Joe Jett July 21, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Continued Punch List in Buildings G, F, & E. Continued Commissioning in Building E. Cherry Road & Martin Street opened to public traffic.

More information

PHYSICAL PLANT OPERATIONAL & MAINTENANCE ADMINISTRATIVE PROCEDURE. Section Subject Effective date Procedure Number

PHYSICAL PLANT OPERATIONAL & MAINTENANCE ADMINISTRATIVE PROCEDURE. Section Subject Effective date Procedure Number PHYSICAL PLANT OPERATIONAL & MAINTENANCE ADMINISTRATIVE PROCEDURE Section Subject Effective date Procedure Number Administration Work Orders May 30, 2013 A-06 Purpose This procedure is designed to augment

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

NEW CONSTRUCTION PERMIT APPLICATION

NEW CONSTRUCTION PERMIT APPLICATION NEW CONSTRUCTION PERMIT APPLICATION Plans must be submitted fourteen (14) business days prior to the next regularly scheduled Building Committee meeting, which are held every 2 nd and 4 th Monday of each

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene January 19, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Carpet & Base in B6 Corridor. Completed 1 ST Coat of Paint in B4 Corridor. Completed 2 ND Coat of Paint in C3 Units Completed

More information

District of Ucluelet Building Permit Guide

District of Ucluelet Building Permit Guide District of Ucluelet Building Permit Guide The purpose of this guide is to advise on the applicable regulations within the District of Ucluelet regarding construction, repairs, alterations or additions

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Carter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications

Carter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications Carter's Oshkosh (SIS) #1185 - The Center at Pearland Parkway - Pearland, TX 77581 - Scope Of Work / Bid Qualifications Please fill out the blanks associated with your trade scope or work with the words

More information

Work Performed Please see the attached list of Construction Codes and mark all that your company typically performs

Work Performed Please see the attached list of Construction Codes and mark all that your company typically performs SUBCONTRACTOR PROFESSIONAL SERVICES PREQUALIFICATION FORM Prequalification Form will NOT be accepted unless completed in its entirety. Business Information Company Name: Primary Address 1: Primary Address

More information

Renovation Progress. July 2-6, Week 39

Renovation Progress. July 2-6, Week 39 Renovation Progress July 2-6, 2012 Week 39 Jul 2 Plaster mud applied to upper section of walls along 1 st Ottilia hallway Jul 2 Markings indicate the location of kitchen fire extinguisher boxes Jul 2 Plumbers

More information

Job Cost Summary 11/27/08

Job Cost Summary 11/27/08 by Division with % Complete Job# = 186 Sample Company 2005 Job Cost Summary 186 Williams Post Office 1 General Requirements 1000.000 GENERAL REQUIREMENTS % COMPLETE 25 % COMPLETE % COMPLETE % COMPLETE

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements 700 Paris Ave. PO Drawer 9 Port Royal, SC 29935 Application for Permit - P O Drawer 9, Port Royal South Carolina Permit

More information

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding

More information

1065 N Canyon St, Ste. 8, Hildale, UT Cell: (435) S Pioneer

1065 N Canyon St, Ste. 8, Hildale, UT Cell: (435) S Pioneer 1065 N Canyon St, Ste. 8, Hildale, UT 84784-0283 Cell: (435) 819-0128 125 S Pioneer 1065 N Canyon St, Ste. 8, Hildale, UT 84784-0283 Cell: (435) 819-0128 CRITICAL IMPROVEMENTS Framing Demo Tin Fence Exterior

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

Dr. Edward Livingston Trudeau Building. 118 Main Street, Saranac Lake, NY. Building Systems Report. June 24, 2018

Dr. Edward Livingston Trudeau Building. 118 Main Street, Saranac Lake, NY. Building Systems Report. June 24, 2018 G2 Gordon + Gordon Architecture. LLC Dr. Edward Livingston Trudeau Building 118 Main Street, Saranac Lake, NY Building Systems Report June 24, 2018 Harry Gordon, FAIA 164 Otter Slide Road Saranac Lake

More information

DOCUMENT BID DOCUMENT

DOCUMENT BID DOCUMENT DOCUMENT 00 40 00 BID DOCUMENT 1 Submit bids in compliance with Document 00 21 00Instructions to Bidders. Fill in blanks which pertain to the project or indicate N/A. The Owner reserves the right to reject

More information

Southington, CT. Project Manager: Ann Micacci, REALTOR Ext WinterberryWoodsLiving.com

Southington, CT. Project Manager: Ann Micacci, REALTOR Ext WinterberryWoodsLiving.com Southington, CT Project Manager: Ann Micacci, REALTOR 203-272-1821 Ext. 327 WinterberryWoodsLiving.com 330 SOUTH MAIN STREET, CHESHIRE, CT 06410 PHONE: 203-272-1821 2620 WHITNEY AVENUE, HAMDEN, CT 06518

More information

NAAHB Workgroup Index General Ledger Account

NAAHB Workgroup Index General Ledger Account NAAHB Workgroup Index General Ledger Account 1000 Series Preparation/Preliminaries 1000 Permits/Fees 1010 Building Permits 1020 HBA Assessments 1030 Warranty Fees 1100 Architectural/Engineering 1110 Blue

More information

The Inspection Process. Waxhaw N.C.

The Inspection Process. Waxhaw N.C. The Inspection Process In Waxhaw N.C. This information is provided by the Waxhaw Enforcement Division to assist you in the progression of your project. Nothing in this document should be considered "Code"

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

Yardmen Arena Expansion & Renovation Project Update

Yardmen Arena Expansion & Renovation Project Update For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville

More information

PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE

PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE HUMPHREYS COUNTY BOARD OF SUPERVISOR BELZONI, MISSISSIPPI APRIL 20, 2016 EMILY POOLE ARCHITECTURE,

More information

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS ARCHITECTURE, LLC 1827 1 ST AVENUE NORTH, SUITE 104 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 3 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D HOSKINS

More information

CAREERS. in the Construction TRADES

CAREERS. in the Construction TRADES CAREERS in the Construction TRADES Electrical Modern life would not be possible without electricians. If you like to know how electric currents make things work, then this is the trade for you. Qualified

More information

PROJECT STATUS REPORT Coronado Elementary School - - Reconstruction Period Ending: 5/31/2015 Scope: Reconstruction Project Construction Status: Architect: WLC Architects Project Manager: Project Engineer:

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

THE CONSTRUCTION SUPERVISOR

THE CONSTRUCTION SUPERVISOR City of Aurora Building Inspections 15151 E Alameda Pkwy Aurora, CO 80012 (303) 739-7420 THE CONSTRUCTION SUPERVISOR When a building permit has been issued for any construction within the City, the Supervisor

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #131 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #131 Douthit Hills Student Community, Clemson University Project Joe Jett August 11, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Continued Punch List in Buildings G, F, & E. Continued Commissioning in Building E. Continued Site Punch List in East Zone. Poured

More information

Thurgood Marshall Recreation Center Summary

Thurgood Marshall Recreation Center Summary Thurgood Marshall Recreation Center Summary Address Building Purpose 5150 Mark Trail Way Dallas, TX 75232 Recreation Center Original Year of Construction 1970 Building Area 21,300 SF Inspection Date August

More information

City of Rohnert Park Building Department Inspection Descriptions

City of Rohnert Park Building Department Inspection Descriptions 200 SITE REVIEW: Prior to a permit being issued the Fire / Building Department is authorized to examine existing buildings, structures, and site for which an application has been filed. 201 PRECONSTRUCTION

More information