Update on FCPS Construction/Renovation Projects. August 2015

Size: px
Start display at page:

Download "Update on FCPS Construction/Renovation Projects. August 2015"

Transcription

1 Update on FCPS Construction/Renovation Projects

2 Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project Cost: $22,377,666 Change Orders to Date (18): $97,325 Scheduled Contract Completion Date: July 2015 % of Contract Completed: 90.08% Revised Completion Date per GC:

3 Jessie Clark Middle -- Renovation Rendering of Final Façade

4 Jessie Clark Middle -- Renovation Work Completed to Date: Begin sidewalks and loading dock area. Grade for paver installation at student drop off. Hang ceiling clouds in the Cafeteria. Finish terrazzo floors. Continue with room finishes. Current Work Effort (August): Complete paver installation at student drop off. Complete plumbing installation in Kitchen. Hook up Kitchen equipment and energize freezer/cooler. Complete finishes in Cafeteria. Complete utility installations including power, data and controls.

5 Jessie Clark Middle -- Renovation Parent Drop Off Paver Installation -- Entry Parent Drop Off Fam-Con Classroom

6 Jessie Clark Middle -- Renovation FMD Classroom Kitchen Cafeteria / Kitchen Cafeteria

7 Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (4): $32,409 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 49.0% Revised Completion Date per GC: No Change

8 Squires Elementary -- Renovation Rendering of Final Façade

9 Squires Elementary -- Renovation Work Completed to Date: The elevator is complete and operational (Phase 1). Drywall finishing and paint are complete in Area A (Phase 1). VCT, carpet and terrazzo floors are complete in Area A (Phase 1). Casework is complete in Area A (Phase 1). Sidewalks, curbs, and asphalt paving are complete (Phase 1). Current Work Effort (August): Area A punch list items to be completed / corrected (Phase 1). Area B grade beams and footings to begin (Phase 2). Area B under-slab plumbing to begin (Phase 2). Area B stem walls to begin (Phase 2). Area B interior building demolition to begin (Phase 2).

10 Squires Elementary -- Renovation New Front Entry New Front Office Media Center Temporary Kindergarten Classroom

11 Squires Elementary -- Renovation Rotunda Main Entry Corridor Art Room Casework New Parking

12 New Elementary at Passage Mound Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (2): $74,859 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 9.94% Revised Completion Date per GC: No Change

13 New Elementary at Passage Mound Rendering of Final Façade

14 New Elementary at Passage Mound Work Completed to Date: Start Masonry Walls, Area A. Complete underground plumbing, Area B classrooms. Complete underground electric, Area B. Start footings and foundations, Area D. Set fire vault and install site fire lines. Current Work Effort (August): Start Masonry walls, Area B. Start and complete footings and foundations, Areas C and D. Install 1st course of CMU, Areas C and D. Install gravel and pour slab, Area D.

15 New Elementary at Passage Mound Site Towards Area B Lower Curb Cut CMU Walls Area A Slab Area B

16 New Elementary at Passage Mound Media Center Foundations Area D Foundation Work Area D Rebar Detail Street View

17 New Elementary at Georgetown Road Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (3): $18,871 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 23.0% Revised Completion Date per GC: No Change

18 New Elementary at Georgetown Road Rendering of Final Façade

19 New Elementary at Georgetown Road Work Completed to Date: Site contractor continues to work on site sub-grading. Continue installation of concrete footings and foundation walls at Area D. Below slab plumbing and sanitary piping on-going at Area D. Underground CMU in Area D has started. CMU in Area C is around 50% complete. CMU in Area B is approximately 30% Installation of door frames in Areas B & C are on-going. Current Work Effort (August): Complete installation of concrete footings and foundation walls and floor slabs. Under-slab plumbing and sanitary to complete. Under ground sanitary, water and sprinkler to continue. Mezzanine decking and structural steel to begin in Area C. Foam cavity insulation to begin in Area A, B & C. CMU installation will continue.

20 New Elementary at Georgetown Road Gym Under-slab Slot in Bedrock Wing B Front Wing B Corridor

21 New Elementary at Georgetown Road Wing C End Wall Wing C Mezzanine Deck Wing C Rear Kitchen Under-slab

22 New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (1): $0 Scheduled Contract Completion Date: July 2017 % of Contract Completed: 4.67% Revised Completion Date per GC: No Change

23 New High at Winchester Road Rendering of Final Façade

24 New High at Winchester Road Work Completed to Date: Continue site grading to establish a Building Pad. Blasting at building pad to be completed, blasting to continue in areas of solid rock at parking lot. Foundations for Area E4 to begin. Submittal & Review of construction materials. Current Work Effort (August): Access road work and parking lot blasting will be completed and building pad work will continue. Foundations in areas E-3 & E-4 to complete and interior foundations will begin. ICF walls will continue in areas E-3 & E-4. Under-slab electrical and plumbing will begin in Area C.

25 New High at Winchester Road Job Trailer ICF Concrete Interior Footings Blasting and Earthwork

Update on FCPS Construction/Renovation Projects. September 2015

Update on FCPS Construction/Renovation Projects. September 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. November 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Update on FCPS Construction/Renovation Projects. August 2016

Update on FCPS Construction/Renovation Projects. August 2016 Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012 GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown

More information

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School

More information

New Ringgold Middle School. Project Slideshow August 26, 2017

New Ringgold Middle School. Project Slideshow August 26, 2017 New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School

More information

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

March 2018 Progress. Work Completed, Week Ending 3/23/18:

March 2018 Progress. Work Completed, Week Ending 3/23/18: March 2018 Progress Work Completed, Week Ending 3/23/18: Continued draft curtains and liner panels. Continued running power to hangar doors. Continued installation of bath accessories in the gang bathrooms.

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

PROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main

More information

DENNIS TOWNSHIP FEASIBILITY STUDY

DENNIS TOWNSHIP FEASIBILITY STUDY DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT

More information

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012 Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap

More information

Darlington Area Schools - Building Evaluations

Darlington Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Pate Elementary School Observed By: Creed/Carter Principal: Grade

More information

Yardmen Arena Expansion & Renovation Project Update

Yardmen Arena Expansion & Renovation Project Update For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville

More information

SECTION ALTERNATES

SECTION ALTERNATES SECTION 01 23 00 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

CONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.

CONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN. CONSTRUCTION UPDATE JUNE THIS IS AUBURN. WOODFIELD DRIVE EXTENSION FACILITIES MANAGEMENT ARCHITECT: GOODWYN, MILLS, CAWOOD D&J ENTERPRISES $1.4 APRIL Woodfield Drive entrance from South Donahue Drive.

More information

TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018

TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 The February 5, 2018 meeting of the Manchester Building Committee was held in the Manchester Room at the Town Hall. Manchester Building

More information

LLANO ISD SCHOOL BOARD MEETING. January 2016

LLANO ISD SCHOOL BOARD MEETING. January 2016 LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

Civic Center Renovation News

Civic Center Renovation News Civic Center Renovation News February 15, 2015 Virginia Avery of Wells, ME was the first guest to enter the newly renovated Civic Center at the Maine Home, Remodeling and Garden Show! She was presented

More information

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the

More information

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary

More information

CIRCLE K SUB-CONTRACTOR BID FORM

CIRCLE K SUB-CONTRACTOR BID FORM CIRCLE K SUB-CONTRACTOR BID FORM Store No: 3308 Address: 8985 Will Clayton Pkwy Date: Bid Due September 17, 2014 Sub Contractor: Trade CONSTRUCTION TAX Construction Tax EXCAVATION / DIRT WORK Cut / Fill

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

ST. CLOUD, MN 316,000 Square Feet Situated on Acres

ST. CLOUD, MN 316,000 Square Feet Situated on Acres ST. CLOUD, MN 316,000 Square Feet Situated on 49.56 Acres For additional information contact: Gerald P. Norton Tel: 952.831.1993 E mail: gnorton@binswanger.com B. Andrew Lubinski Tel: 952.831.1931 E mail:

More information

Auburn University Construction Project Update March 2010

Auburn University Construction Project Update March 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Facilities Construction

Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction August 2013 Leroy San Miguel Dr. Folks Middle School ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE

More information

Introduction & Project Background

Introduction & Project Background Introduction & Project Background Project Background is located in Pasadena, Maryland and is owned and maintained by Anne Arundel County School District. A new elementary school to replace the existing

More information

Darlington Area Schools - Building Evaluations

Darlington Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Cain Elementary School Observed By: Creed/Carter Principal: Grade

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL

More information

ST. CLOUD, MN. 316,000 Square Feet Situated on Acres. For additional information contact:

ST. CLOUD, MN. 316,000 Square Feet Situated on Acres. For additional information contact: ST. CLOUD, MN 316,000 Square Feet Situated on 49.56 Acres For additional information contact: Gerald P. Norton Tel: 952.831.1993 E-mail: gnorton@binswanger.com B. Andrew Lubinski Tel: 952.831.1931 E-mail:

More information

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri

More information

Hartsville Area Schools - Building Evaluations

Hartsville Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 8, 2012 Hartsville Area Schools - Building Evaluations School Name: West Hartsville Elementary Observed By: Cannon/Carter Principal:

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

La Porte Independent School District 2014 Bond Program Status Report August 11, 2015

La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte Independent School District 2014 Bond Program Status Report August 11, 2015 La Porte ISD 2014 Bond Program ADMINISTRATION: Superintendent: Lloyd Graham Deputy Superintendent: Dr. Linda Wadleigh

More information

Darlington Area Schools - Building Evaluations

Darlington Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior

More information

DISCOVERY ELEMENTARY SCHOOL

DISCOVERY ELEMENTARY SCHOOL DISCOVERY ELEMENTARY SCHOOL COMMUNITY UPDATE #11 April 2015 COMPLETED AND ONGOING CONSTRUCTION ACTIVITIES The north half of the Discovery Elementary School (DES) building referred to below encompasses

More information

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW HISTORIC PRESERVATION REVIEW submitted to: DC Historic Preservation Office Office of Planning ARCHITECTS ARCHITECTURAL NARRATIVE Bruce Monroe Elementary School at Park View is among the schools included

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #131 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #131 Douthit Hills Student Community, Clemson University Project Joe Jett August 11, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Continued Punch List in Buildings G, F, & E. Continued Commissioning in Building E. Continued Site Punch List in East Zone. Poured

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

PROJECT STATUS REPORT Coronado Elementary School - - Reconstruction Period Ending: 5/31/2015 Scope: Reconstruction Project Construction Status: Architect: WLC Architects Project Manager: Project Engineer:

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #158 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #158 Douthit Hills Student Community, Clemson University Project Tony Greene February 16, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed 1 ST Coat of Paint in C5 Corridors. Completed Test & Balance in Building C. Completed Final Paint in B1 Corridors. Completed

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

School Assessment Report

School Assessment Report School Assessment Report School: Humphries Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:35:17 AM FOR OFFICIAL USE ONLY Final School Assessment

More information

Oconomowoc Area School District Facility Construction Update June 29, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018 Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #142 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #142 Douthit Hills Student Community, Clemson University Project Tony Greene October 27, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Tie-in & Start-up of HUB Sanitary Lift Station. Completed Brick on Stair Walls West of Building C. Completed Pouring the

More information

North Allegheny School District

North Allegheny School District North Allegheny School District January 18, 2017 Preparing all students for success in a changing world NAI was last renovated in 1997 Money was set aside during recent bond issue for renovations to occur

More information

School Assessment Report

School Assessment Report School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School

More information

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved.

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved. Sri Ganesha Temple HTNT Construction Update (June, 2016) With Lord Ganesha s Blessing We start everything Architect View of the Ganesha Temple at Finish Sri Ganesha Temple HTNT Construction Milestones

More information

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form. Project: Ben Steele Middle School Addendum #: 2 Date Issued: January 11, 2016 Description of Addendum & Attachments: 1. A Pre Bid Meeting is scheduled for January 18 th, 2016. Attendance is strongly encouraged,

More information

Perimeter Site Improvements

Perimeter Site Improvements Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff

More information

2451 Bert Drive, Hollister, CA

2451 Bert Drive, Hollister, CA PROPERTY FOR LEASE OR SALE Overview: Located on 15.37 acres (8.35 acres are developed), this well-maintained, ±170,144 SF, Class C light industrial manufacturing facility features office, manufacturing

More information

Cost and Methods Analysis

Cost and Methods Analysis Technical Assignment 2 Cost and Methods Analysis Cathy Neiderer Pasadena Elementary School Technical Assignment 2 Table of Contents Executive Summary... 3 Detailed Project Schedule... 4 Site Layout Planning...

More information

CENTENNIAL SCHOOL DISTRICT

CENTENNIAL SCHOOL DISTRICT CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites

More information

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE II RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING

More information

For Sale. $2,199,000 Office/Warehouse/ Manufacturing th Avenue Baldwin, WI 63 & 12

For Sale. $2,199,000 Office/Warehouse/ Manufacturing th Avenue Baldwin, WI 63 & 12 836 Minnesota Street S. Bayport, MN 55003 Website: www.greystone-commercial.com Email: info@greystone-commercial.com For Sale US HIGHWAYS 63 & 12 $2,199,000 Office/Warehouse/ Manufacturing Office/Warehouse/

More information

DAVIS ELEMENTARY SCHOOL

DAVIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (06-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 63% COMPLETE As

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As

More information

Hartsville Area Schools - Building Evaluations

Hartsville Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 8, 2012 Hartsville Area Schools - Building Evaluations School Name: Principal: Grade Levels: Site Size: Student Population: Staff Size:

More information

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department.

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department. City of Goshen Instructions for Residential Permit Application Why do you need a building permit? Your home is a large investment, and if your construction project does not comply with the codes adopted

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene August 25, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Turned All East Zone Parking Lots Over to Clemson. Completed Trench Drain on Bradley Road. Completed Pouring Walls for Building D

More information

NYC Department of Education

NYC Department of Education Building Assessment Survey 2017-2018 Asset: SAINT FRANCIS COLLEGE - BROOKLYN, 180 REMSEN STREET, New York, 11201 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-02-05

More information