1 INFRASTRUCTURE REVISED ADVERTISING SCHEDULE 2017/2018 CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure Contract Services Branch Garry Street
2 Winnipeg, MB R3C 3P The Construction Tender and Material Supply Tender Advertising Schedule is released annually in the fall. The 2017/2018 Advertising Schedule will be updated and posted quarterly. All Tenders associated with this advertising schedule can be found at: Details of submission requirements are contained within each bid opportunity and advertisement. All bid opportunities in the advertising schedule are competitive open tenders. Bid Submission Requirements will be identified in each Tender.
3 Construction Tenders Manitoba Infrastructure and Transportation Revised Fall Advertising Schedule for 2017 Construction Season July 2017 Region Tender For: Hwy. Location 03 Bituminous Levelling 259 PTH km East of PTH 1 19-Jul Bituminous Pavement (Includes Passing Lanes) 003 PTH PTH Jul Drainage Improvements Manning Canal (Vicinity of Ile des Chȇnes) 22-Jul Grading 282 PTH PR Jul-17 2 Supply of Structural Steel Girders (341-02) At Assiniboine River (W/B) 0.8km W of PTH Jul Supply of Precast - girders ( ) Main at Friedenstahl 22-Jul Supply of Precast - girders ( ) Main at Ridgeville 02 Grading (Including Gravel) (Gravel Road Restoration) 305 PTH PTH 3 26-Jul Jacking Culverts Portage Diversion East Outside Drain Vicinity of Portage La Prairie 26-Jul Bituminous Pavement 008 PTH Clandeboye Road 26-Jul-17 Concrete Pavement (Rehabilitation) 101 North Perimeter: At PTH 7 (Includes Legs & Loops) 04 Grading (Frost Tapers) 020 PTH 5 -- PR 272 (Various Locations) 29-Jul Grading (Includes Gravel) (Gravel Road Restoration) km South of PTH 6 -- PTH 6 29-Jul-17 Minor Structure Rehabilitation Various Sites 29-Jul Construct Detour (341-02) 001 At Assiniboine River (W/B): 0.8km West of PTH 26 Aug 01 Structure ( ) At Peterson Creek Aug 05 Grading 391 Thompson -- Suwannee River (Various Locations) Aug 31 Structure Rehabilitation ( ) Seine River Diversion Aug 02 Bituminous Pavement km West of PTH PTH 16 (E/B) Aug 05 Grading km North of Sasagiu Rapids -- PR 375 Aug 04 Stockpiling Aggregate Grandview - Roblin - Swan River - Pine River Area Aug
4 Construction Tenders Manitoba Infrastructure and Transportation Revised Fall Advertising Schedule for 2017 Construction Season July 2017 Region Tender For: Hwy. Location 04 Stockpiling Aggregate Dauphin - McCreary - Rorketon Area Aug 32 Safety Improvements Fairford Dam and Control Structures (Municipality of Grahamdale) Aug 32 Drainage Improvements Grassmere Drain (Vicinity of West St. Paul) Aug 02 Culvert Replacement 009 Vicinity of Winnipeg Beach Aug 04 Structure ( ) At Wilson River: 6.1km North of PTH 20A (North of Dauphin) Aug 04 Structure ( ) At Ochre River: 1.0km West of PTH 20A 03 Structure Rehabilitation ( ) At Assiniboine River, Flood Relief: 6.1km W of PR 463 Sep 04 AST (Includes Grade & Base) km North of PR km North of PR 269 Sep 04 Stockpiling Aggregate Ericksdale - Ashern - Gypsumville Area Sep 02 Intersection Improvements km West of PTH 3 -- PTH 100 (Vicinity of Oak Bluff) Sep 03 Bituminous Pavement (Includes Grading) 016 PR West Jct PR 264 (Solsgirth Curves) Sep 01 Embankment Works ( ) At Marsh River: 2.5km West of PR 200 (North of Ste Elizabeth) Sep 05 Stockpiling Aggregate Vicinity of Split Lake -- Gillam Area Sep 03 Structure Rehabilitation ( ) At Assiniboine River, Underpass at Grand Valley Sept 01 Jacking Concrete Culverts km West of PTH 12 to Brokenhead River E/B W/B Sep 01 Structure ( ) At Marsh River: 2.5km West of PR 200 (North of Ste Elizabeth) Sept 01 Bituminous Pavement (Includes Grading & Base) 011 East of PR West of Pine Falls Sep 03 Structure ( ) At Bosshill Creek: 1.0km S of PTH 001 Oct 03 Structure ( ) At Bosshill Creek: 1.0km S of PTH 001 Oct 31 Structure ( ) Main at Friedenstahl Oct 31 Structure ( ) Main at Ridgeville Oct
5 Construction Tenders Manitoba Infrastructure and Transportation Revised Fall Advertising Schedule for 2017 Construction Season July 2017 Region Tender For: Hwy. Location 01 Precast - Deck Panels ( ) 313 At Winnipeg River: 2.6km East of PTH 11 (East of Lac du Bonnet) Oct
6 Manitoba Infrastructure Revised Fall Advertising Schedule for the 2017 Construction Season Material Supply Tenders Region Tender For: Hwy. Location Public Release July 2017 All Highway Marking Paint Various Locations February All Glass Beads for Highway Marking Paint Various Locations February All Dust Control Chemical Various Locations March All Asphalt Cements and Emulsified Asphalts* Various Locations March - October All Bituminous Hot Mix for Highway Repairs Various Locations May * - Tenders for asphalt materials will be issued after the corresponding construction tenders.
REVISED ADVERTISING SCHEDULE
INFRASTRUCTURE REVISED ADVERTISING SCHEDULE CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure Contract Services Branch 1630 215 Garry Street Winnipeg, MB R3C 3P3 204 945 3637 The Construction
More informationREVISED ADVERTISING SCHEDULE
INFRASTRUCTURE REVISED ADVERTISING SCHEDULE CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure Contract Services Branch 1630-215 Garry Street Winnipeg, MB R3C 3P3 204-945-3637 The Construction
More informationManitoba Infrastructure: Service Delivery Review
Manitoba Infrastructure: Service Delivery Review Manitoba Infrastructure is committed to ensuring safe, reliable and sustainable infrastructure and services for Manitoba and its communities. The Department
More informationASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ECMS ADVANCED INFORMATION LETTING MARCH 1, 2018 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
As of February14, 2018 SNYDER COUNTY SR 2007(012) #93607 PROPOSAL:$16.56 PLANS:$4.40 12X18:$5.40 24X36:$78.00 The description and location of the project are as follows: The work is the furnishing and
More informationDIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS
OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006
More informationWater and Waste Department
Water and Waste Department 2015 CAPITAL WORKS CONSTRUCTION PROGRAM Presentation to Manitoba Heavy Construction Association April 17, 2015 1 Capital Budget CAPITAL BUDGET 2015 Approved 2016 to 2020 2015
More informationElectrical Work. NOV Embankments Over Swamps and Compressible Soils
GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification
More informationSelect Subgrade Material, Compacted
314.1 GENERAL B314 SHOULDER, SELECTED SUBGRADE, AND STOCKPILING OPSS.PROV 314 Granular materials meeting the requirements of OPSS.PROV 1010 are obtained from pits and quarries, and recycled materials.
More informationRE: HWY 63:02 HIGHWAY EMBANKMENT REPAIR NORTH OF LABICHE RIVER BRIDGE COMPLETION REPORT
THURBER ENGINEERING LTD. Suite 200, 9636-51st Avenue EDMONTON, Alberta T6E 6A5 Phone (780) 438-1460 Fax [780) 437-7125 I \ DO THURBER February 2, 1999 File: 15-16-101 Alberta Transportation & Utilities
More informationCENTRAL ASSINIBOINE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT
CENTRAL ASSINIBOINE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT Planning Area Boundary: The Central Assiniboine planning area covers the reach of the Assiniboine River from just
More informationDirector Environmental Assessment and Licensing Branch Manitoba Conservation Suite 160, 123 Main Street Winnipeg, Manitoba R3C 1A5
Director Environmental Assessment and Licensing Branch Manitoba Conservation Suite 160, 123 Main Street Winnipeg, Manitoba R3C 1A5 Dawn Fraser Manager, Environment & Public Affairs Lafarge Canada Inc.
More informationJOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018
JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018 On Maintenance of Traffic Details Sheet No. 46 there is a note that states I-49 Stage Construction is to be Completed Prior to Beginning Work on Hwy.
More informationNotice of Alteration Environment Act Licence 1331 R Upgrades to Storm Water Management System
Environmental Stewardship Division Environmental Approvals Branch 123 Main Street, Suite 160, Winnipeg, Manitoba R3C 1A5 T 204 945-8321 F 204 945-5229 www.gov.mb.ca/conservation/eal September 18, 2014
More informationTIRE DERIVED AGGREGATE (TDA) FOR MANITOBA MUNICIPAL ROADS
TECHNICAL REPORT TIRE DERIVED AGGREGATE (TDA) FOR MANITOBA MUNICIPAL ROADS Cost Effective High Performing Environmentally Friendly TDA installed at Strollway Street, Town of Winnipeg Beach BEFORE Frost
More informationLIST OF ACTIVE OPSSs
LIST OF ACTIVE OPSSs DIVISION 1 - GENERAL SPECIFICATIONS 100 PROV MTO General Conditions of Contract Nov 2016 Jan 12, 2017 102 COMM Weighing of Materials Oct 1992 Mar 17, 1994 106 PROV Electrical Work
More informationCanada. Manitoba. S. Topping (Water Resources)
MANITOBA S PROGRESS TOWARDS LIVING WITH THE RED Steve Topping, P.Eng. LINKING SCIENCE TO WATER POLICY ICEWarm Conference Adelaide, SA November 20 th, 2008 S. Topping (Water Resources) The Hudson Bay Drainage
More informationHighway Construction Program
Highway Construction Program Monthly Delivery Progress Report Watch List October 2018 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,
More informationAPPENDIX I APPENDIX I SAMPLE COST ESTIMATES AND SUMMARY
APPENDIX I SAMPLE COST ESTIMATES AND SUMMARY May 7, 2002 This page left blank intentionally. May 7, 2002 Preliminary Cost Estimate Summary ESTIMATE TYPE A ABC Consulting Hwy 99:06 ABC Project No. 1234-01-56789
More informationWinnipeg River Bridge on PR313 at Lac du Bonnet. June 2014
Winnipeg River Bridge on PR313 at Lac du Bonnet June 2014 Regional Context Local Area Purpose and Need The Winnipeg River Bridge on PR313 was originally constructed in 1930 as a trolley and vehicle bridge.
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationSUPPLEMENTAL ECMS ADVANCED INFORMATION DECEMBER 1, 2016 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
Updated November 15, 2016 BEAVER COUNTY SR 588(B18) #91922 PROPOSAL:$22.80 PLANS:$18.04 12X18:$22.14 24X36:$319.80 X-SEC:$3.52 12X18:$4.32 24X36:$62.40 The description and location of the project is as
More informationFISHER RIVER INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT
FISHER RIVER INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT Disclaimer: The hydrologic conditions presented in this report are estimates
More informationRe: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy
Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy Presentation to Executive Committee September 21, 2015 1 Overview Project Background Procurement Options Analysis
More informationBy Andrew Lindsay Government of Manitoba Manitoba Infrastructure and Transportation (MIT) Highway Planning and Design
By Andrew Lindsay Government of Manitoba Manitoba Infrastructure and Transportation (MIT) Highway Planning and Design Information on the Province of Manitoba Brief history of MIT s linear referencing system
More informationAn Overview of 2009 Spring Flooding in Manitoba
An Overview of 2009 Spring Flooding in Manitoba August 2009 An Overview of 2009 Spring Flooding in Manitoba Many areas of southern Manitoba experienced serious flooding in the spring of 2009 due to high
More information1971 HISD REPORTS. Highway Mileage on State, State Toll, County and Municipal Systems by County and by District
1971 HISD REPORTS This is a description of the HISD reports compiled annually by HISD. HISD-4 HISD-4T HISD-5 HISD-6 HISD-7 HISD-8 HISD-9 Highway Mileage on State, State Toll, County and Municipal Systems
More informationRe: PW Appendix 3 - Part 8
Demolish S/W DVP ramp, FGE WBL (including Logan Ramp), Don River bridge WB, and existing LSB WBL Construct new S/W DVP ramp, FGE WBL ramp, Don River bridge WB, and remaining portion of LSB WB roadwork.
More informationCUY-480-Valley View Bridge. Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street
CUY-480-Valley View Bridge Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street Agenda Welcome Project Overview Prequalification & Work types Procurement Overview Matchmaker 2
More informationSouth Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018
South Canal Bank Road and South Canal Reconstruction at Highway 400 Presentation for MTO Executive Review January 30, 2018 2014 2017 K. Smart Associates Limited By Kenn Smart P. Eng. Background South Canal
More informationSUMMARY OF COMMENTS/RECOMMENDATIONS
SUMMARY OF COMMENTS/RECOMMENDATIONS PROPONENT: Cyr Construction 1998 Ltd. PROPOSAL NAME: Concrete Batch Plant CLASS OF DEVELOPMENT: 1 TYPE OF DEVELOPMENT: Concrete Batch Plant CLIENT FILE NO.: 5523.00
More informationSUMMARY OF COMMENTS/RECOMMENDATIONS
SUMMARY OF COMMENTS/RECOMMENDATIONS PROPONENT: Northland Ready Mix Concrete PROPOSAL NAME: Concrete Batch Plant CLASS OF DEVELOPMENT: 1 TYPE OF DEVELOPMENT: Manufacturing Plant CLIENT FILE NO.: 5330.00
More informationComparative Analysis of Pavement Rehabilitation Designs Using AASHTOWare Pavement ME, AASHTO 1993 and Surface Deflection Methods
Comparative Analysis of Rehabilitation Designs Using AASHTOWare ME, AASHTO 1993 and Surface Deflection Methods M. Alauddin Ahammed, Ph.D., P.Eng. Design Engineer Materials Engineering Branch Manitoba Infrastructure
More informationTRANSPORTATION HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA
HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA 2008/09 $52.0 M 85% SELF-PERFORMED Widen 12 miles of Interstate 10 to six lanes including the reconstruction
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200 GRADING 219.101 Light Duty Straw
More informationTarbutton Road Interchange and I-20 Frontage Roads. Estimating and Planning Group
Tarbutton Road Interchange and I-20 Frontage Roads Dr. N. Wasiuddin Braden Smith Jared Taylor John Harrison Sarah Wells Samantha Tatro Ryan Ross Instructor Project Manager Transportation Group Geotechnical
More informationASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ECMS ADVANCED INFORMATION LETTING MAY 24, 2018 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
ASSOCIATED PENNSYLVANIA CONSTRUCTORS Updated May 4, 2018 FULTON COUNTY SR 0000(FMC) #109343 PROPOSAL:$21.36 PLANS:$9.02 12X18:$11.07 24X36:$159.90 X-SEC:$7.48 12X18:$9.18 24X36:$132.60 This project involves
More informationMaintains the status quo even though deteriorated. To keep at original condition or use.
Chapter 14 14.1 ROUTINE MAINTENANCE Maintains the status quo even though deteriorated. To keep at original condition or use. NOTE: All items include labor and material. Ma 1 Smoothing Surface - Strictly
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw
More informationSTIP Project Description Guidance Revised December 14, 2015
General Guidance The guidance below applies to all local and MnDOT projects shown in the STIP. STIP Project Description Guidance The project description must clearly identify the specific route, point
More informationRestoring Wreck Pond Inlet Jenna Krug, Habitat Restoration Coordinator
Restoring Wreck Pond Inlet Jenna Krug, Habitat Restoration Coordinator Borough of Spring Lake Borough of Sea Girt Project Location: Wreck Pond Watershed ~12.8 square miles (8,172 acres) Drains the following
More informationPUBLIC INFORMATION MEETING June 24, 2015
Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase
More informationCONTRACT ID : COMPLETION DATE : 09/15/08 =========
PAGE : 1 COMPLETION DATE : 09/15/08 PROJECT(S): ER-1453(310)X LOCATION(S): YORK, CULVERT REPLACEMENT MAINE STATE DEPARTMENT OF TRANSPORTATION A TRUE COPY : TITLE : ATTEST : CONTRACT DESCRIPTION : YORK,
More informationPlessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions
Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared
More informationWater and Waste Department
Water and Waste Department 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Presentation to Manitoba Heavy Construction Association, March 7 th, 2012 Capital Budget Capital s Summary 2012 Capital Budget 2013 to
More informationFox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS
Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # 2016-04 PROJECT SPECIFICATIONS TABLE OF CONTENTS SECTION 100 GENERAL... 1 SECTION 200 MATERIALS... 1 CONSTRUCTION METHODS... 1 SECTION
More information304 - SURFACE TREATMENTS - OPSS 304
04 - S - OPSS 04 04.1 GENERAL For economic reasons, roadways having low traffic volumes will often be selected for double surface treatment or prime and surface treatment in place of Hot Mix paving. Primed
More informationReclamation Manual Design Data Collection Guidelines Chapter 5 Typical Design Data Package Template
Reclamation Manual The Introduction (Chapter 1) for these design data collection guidelines contains additional information concerning: preparing a design data collection request, design data collection
More informationZoo Interchange Reconstruction
May 14, 2013 Roberto Gutierrez, PE WisDOT Chris Hager, PE - WisDOT Zoo Interchange Reconstruction Overview of Presentation overview WisDOT Southeast Region I-94 North-South I794/I-94 restriping Hoan bridge
More informationARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company
James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw
More informationLAKE WINNIPEG COMMUNITY-BASED MONITORING NETWORK 2017 REGIONAL REPORTS
LAKE WINNIPEG COMMUNITY-BASED MONITORING NETWORK 217 REGIONAL REPORTS UPPER ASSINIBOINE RIVER CONSERVATION DISTRICT LAKE WINNIPEG COMMUNITY-BASED MONITORING NETWORK: OVERVIEW Lake Winnipeg, the world s
More informationMINISTRY OF TRANSPORTATION ONTARIO MANAGING OUR ASSETS
MINISTRY OF TRANSPORTATION ONTARIO MANAGING OUR ASSETS Financial Management Institute of Canada November 19, 2008 Ministry s Assets Mature network - large inventory Over 16,500 km Over 2,800 bridges 8
More informationTHE RED RIVER FLOODWAY EXPANSION PROJECT
THE RED RIVER FLOODWAY EXPANSION PROJECT Presentation to APEGM September 21, 2005 OUTLINE Reason for the Project Design Update Contribution of Engineers and Scientists Environmental Approval Process Construction
More informationBridge Asset Management City of Battle Creek Planning and Projects
Bridge Asset Management City of Battle Creek Planning and Projects Michigan Bridge Conference, March 20, 2013 Gregory B. Rickmar P.E., Public Works Department, City of Battle Creek Alan Halbeisen, P.E.
More informationSummary of Main Manure Regulations in Manitoba
Summary of Main Manure Regulations in Manitoba A. Winter and Fall Application of Manure 1 Winter means between & including Nov 10 & Apr 10 of the same winter about 150 days. Fall means between Sept 10
More informationB HOT MIX, HOT LAID ASPHALTIC CONCRETE OPSS 313
B 313-1 OPSS 313 313-1.1 GENERAL HL,, Mixture, and/or Mix, is hot mixed, hot laid asphaltic concrete, used for pavement construction and other uses. 1. HL 1 This dense graded surface course mix is used
More informationSR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five
SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed Florida Department of Transportation District Five Project Overview Location SR 600 / US 92, Volusia County FPN:
More informationPCL Definitions for the Local Program J01 3R Policy J04 3P Policy J06 Local Bridges and Township Bridge Program Bridge Work Activities
PCL Definitions for the Local Program Projects that are administered by the Central Bureau of Local Roads. Engineering, utilities and land acquisition are coded with the PCL for the type of construction
More informationHAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003
HAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003 Reviewed and accepted by FHWA on September 29, 2003 Note: Guidelines was revised on to correct
More information313-1 HOT MIX ASPHALT - OPSS.PROV 313
313-1 - OPSS.PROV 313 313-1.1 GENERAL Hot mix asphalt consists of several mix types, which are grouped into two categories: Stone Mastic Asphalt and Superpave as detailed below. The type of hot mix asphalt
More information313-1 HOT MIX ASPHALT - OPSS.PROV 313
313-1 - OPSS.PROV 313 313-1.1 GENERAL Hot mix asphalt consists of several mix types, which are grouped into two categories: Stone Mastic Asphalt and Superpave as detailed below. The type of hot mix asphalt
More informationSUPPLEMENTAL ECMS ADVANCED INFORMATION JULY 14, 2016 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
Updated June 27, 2016 BEAVER COUNTY SR 7446(LBB) #92912 PROPOSAL:$54.72 PLANS:$42.46 12X18:$52.11 24X36:$752.70 EXSTRUCT:$48.62 12X18:$59.67 24X36:$861.90 The description and location of the project is
More informationTown of South Bruce Peninsula Bridge and Culvert Inspections OSIM Inspection Report
Town of South Bruce Peninsula OSIM Inspection Report Prepared By: R.J. Burnside and Associates Limited 3 Ronell Crescent, Collingwood L9Y 4J6 Prepared for: Town of South Bruce Peninsula January 2015 File
More informationICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT
ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT Disclaimer: The hydrologic conditions presented in this
More informationGCI Survey---Lake Winnipeg Watershed
IISD-GWSP Conference. Winnipeg May 1-4, 2012 Water-Energy-Food Nexus GCI Survey---Lake Winnipeg Watershed A. A. WARKENTIN Hydrometeorologist GCI Survey Lake Winnipeg Watershed PRESENTATION OUTLINE WATERSHED
More informationSECTION B1 BITUMINOUS CONCRETE PAVING GENERAL
SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL This section covers the restoration of roadways and sidewalks, in whole or in part, with bituminous concrete paving. WITHIN 4 DAYS OF BACKFILLING IN AREAS
More informationThe Standards referred to shall be the most recent edition.
Page 1 of 7 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described hereunder shall consist of the excavation of trenches and tunnels; the supply and installation of pipe and/or encasement pipe; the
More informationBALFOUR INTERCHANGE PHASE 1 CONSTRUCTION PRE-BID MEETING
BALFOUR INTERCHANGE PHASE 1 CONSTRUCTION PRE-BID MEETING WHO WE ARE The Contra Costa Transportation Authority (CCTA) is a public agency formed by Contra Costa County voters in 1988 to manage the county
More informationQUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINSTRATOR MARCH 26, 2019
QUARTERLY STORMWATER UPDATE FLOOD CONTROL PROJECTS TONI ALGER, P.E. STORMWATER ENGINEERING CENTER ADMINSTRATOR MARCH 26, 2019 D a s h b o a r d Aragona Drainage Improvements, 7-400 Ashville Park Drainage
More informationTABLE OF CONTENTS 1.0 INTRODUCTION AND AQUIFER CHARACTERIZATION...1
TABLE OF CONTENTS PAGE 1.0 INTRODUCTION AND AQUIFER CHARACTERIZATION...1 2.0 DOMESTIC WELLS...3 2.1 INTRODUCTION...3 2.2 BACTERIA...4 2.3 NITRATE+NITRITE AS NITROGEN)...4 2.4 PESTICIDES...5 2.5 CONDUCTIVITY...5
More informationTo receive future notification of specification revisions, provide your address to Bruce Peters at:
PUBLIC WORKS DEPARTMENT SERVICE DES TRAVAUX PUBLICS Engineering Division Division de l ingénierie To all Standard Construction Specification Holders: March 10, 2003 Specification book holders are responsible
More informationMinimum Sample and Test Requirements (MSTR)
South Dakota Department of Transportation Minimum Sample and Test Requirements (MSTR) Table of Contents Page 1. Asphalt Construction:... 1 1.1 Asphalt Concrete, Hot Mix... 3 A. Aggregate, Composite...
More informationTownship of McNab/Braeside Reconstruction/Rehabilitation of Goshen Road
Township of McNab/Braeside Reconstruction/Rehabilitation of Goshen Road Prepared for: Mr. Ryan Frew, P. Eng. Township of McNab/Braeside 2508 Russett Drive Arnprior, ON K7S 3G8 Prepared by: McIntosh Perry
More informationKeeyask Infrastructure Project
Keeyask Infrastructure Project Terrestrial and Aquatic Monitoring Plan Annual Report 2014-2015 December 2015 KEEYASK INFRASTRUCTURE PROJECT TERRESTRIAL AND AQUATIC MONITORING PLAN Water Quality: Annual
More informationAward of Contract No for the Rehabilitation of the Moon River Bridges on Muskoka Road 169 in the Township of Muskoka Lakes
TO: FROM: Chair and Members Engineering and Public Works Committee Elvis Jose, P.Eng., PMP, C.E.T. Manager of Engineering Services DATE: August 19, 2016 SUBJECT: REPORT NO: Award of Contract No. 16-313-158
More informationMATERIALS DIVISION MEMORANDUM SIGNATURE:
MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Notice of Revision to Materials Division s Manual of Instructions Chapter VI SPECIFIC SUBJECT: Incorporation of a new section titled as Project Selection
More informationARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS
ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS CONTRACT # 2016138 TRACS No. Project No. County District Gross
More informationCONSTRUCTION SPECIFICATION FOR RUBBLIZING CONCRETE PAVEMENT AND CONCRETE BASE
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 361 NOVEMBER 2011 CONSTRUCTION SPECIFICATION FOR RUBBLIZING CONCRETE PAVEMENT AND CONCRETE BASE TABLE OF CONTENTS 361.01 SCOPE 361.02 REFERENCES 361.03
More informationPreconstruction Community Meeting
SHIPLEY S CHOICE DAM REHABILITATION PROJECT Preconstruction Community Meeting Larry Mathena Project Manager Anne Arundel County Dept. of Public Works Shipley s Choice Elementary School September 13, 2018
More informationI-11 Project Nevada Transportation Conference. Ryan Wheeler, P.E. NDOT, Senior Project Manager. Nevada Department of Transportation
I-11 Project 2017 Nevada Transportation Conference Ryan Wheeler, P.E. NDOT, Senior Project Manager Nevada Department of Transportation nevadadot.com About NDOT NDOT Core Values: Respect treating others
More informationADVERTISEMENT SET DECEMBER 2013
Sheet List Table GREELEY CANAL #2 WCR 21 PROJECT AREA N SH-392 ADVERTISEMENT SET DECEMBER 2013 LINE DESCRIPTION PROPOSED LINE POWER / COMMUNICATIONS EXISTING LINE LINE DESCRIPTION PROPOSED LINE BOUNDARY
More informationPUBLIC NOTICE. From: Corporate Services Date: March 26, 2012 Re: Federal Gas Tax Reporting
PUBLIC NOTICE From: Corporate Services Date: March 26, 2012 Re: Federal Gas Tax Reporting In order to qualify for Federal Gas Tax funding, municipalities must annually file Schedule C with AMO detailing
More informationProject Type: Drainage and Storm Systems
580 Dakin Avenue Box Culvert & Utility Improvements Project $944,952 Improvements to approx. 3,000 lf of existing 4'x5' concrete box culvert; clean interior, patch surface, fill joints/cracks; install
More informationAlberta Transportation Bridge Inspection & Maintenance System (Web 2005) Bridge. Bridge Inspection Form Type Lot No. 1
Bridge File Number Year Built/Year Supstr 02082-1 Bridge 1960/1960 Bridge or Town Name CORONATION Located Over Located On 599:06 C1 18.890 Water Body Cl./Year Navigabil. Cl./Year Legal Land Location RIBSTONE
More informationConstruction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018
Construction Coordination & Management Planning MassDOT-Highway/MBTA 495/MetroWest Partnership Briefing July 11, 2018 Overview The Construction Coordination and Management Planning exercise was a 100-day
More informationINFO. ON SPECIFIC QUANTITIES IS AVAILABLE WITH AN APC SPECIAL SERVICE BULLETIN SUBSCRIPTION
Updated November 17, 2008 PHILADELPHIA COUNTY SR 30(ADA) PROPOSAL:$14.40 The description and location of the project is as follows: For the design and construction of ADA compliant concrete curb ramps
More informationChapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction
Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the
More informationYear Pre Total County Debt (Bonds & BANS) Mitigation Fees
CR 9 (Bradt Hollow Road) Over Fox Creek Bridge Replacement Project Replacement of a 156 ft. long x 32ft. wide, 3 span pre stressed concrete box beam bridge over Fox Creek in the Town of Berne. The bridge
More informationSTATUS REPORT Congestion-Relief Program. Steve Gillen Illinois Asphalt Pavement Association March 12, 2007
STATUS REPORT Congestion-Relief Program Steve Gillen Illinois Asphalt Pavement Association March 12, 2007 Beginning Year 3 of Congestion-Relief Program Governor s $5.3 billion Congestion-Relief Program
More informationOatman Highway at Sacramento Wash Crossing Federal Aid No. 000-MMO-0(216)T ADOT Project No MO MMO T C
87-Hour Bridge Construction in Arizona ABC and ARC at the Speed of Commerce Mohave County (Topock), Arizona Oatman Highway at Sacramento Wash Crossing Federal Aid No. 000-MMO-0(216)T ADOT Project No. 0000
More informationMAINE DEPARTMENT OF TRANSPORTATION BID DATE OF OPENING : CALL ORDER : CONTRACT ID : PROJECTS STP-1277(700)S
MAINE DEPARTMENT OF TRANSPORTATION BID DATE OF OPENING : CALL ORDER : CONTRACT ID : 012777.00 PROJECTS ------------------------------ STP-1277(700)S COUNTY : ANDROSCOGGIN CONTRACT ID : 012777.00 MAINE
More informationI-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:
More informationDESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL. Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents
DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents Introduction This design bulletin provides a number
More informationB HOT MIX ASPHALT - OPSS.PROV 313
B313-1 - - OPSS.PROV 313 313-1.1 GENERAL Hot mix asphalt consists of several mix types, which are grouped into two categories: Stone Mastic Asphalt and Superpave as detailed below. The type of hot mix
More informationARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS
ARIZONA DEPARTMENT OF TRANSPORTATION INFRASTRUCTURE DELIVERY AND OPERATIONS DIVISION CONTRACTS AND SPECIFICATIONS SECTION TABULATION OF BIDS CONTRACT # 2018026 TRACS No. Project No. County District Gross
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)
FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM ADA Central, Contract 3 DBNUM: 15419 / UPC: 154190 This contract will bring projects into compliance with current ADA design requirements that could
More informationProposer shall make note of and/or incorporate all changes listed below into the requested
Request for Proposal (RFP) Bid No: 18-10-1940LE Addendum No. 4 Date: November 27, 2018 To: All Proposers Subject: Addendum No. 4 Consisting of nine (9) Pages RFP No.: Project Name: Owner: 18-10-1940LE
More informationLIST OF DIRECTIVES AND MEMORANDA
LIST OF DIRECTIVES AND MEMORANDA Technical Policies and Standards HSBM DO 2014-01 Format and Method for Policies Issued by HSB To provide guidance for the format and method of communicating the implementation
More information100 Pavement Requirements Pavement Design Concepts 200-1
Table of Contents 100 Pavement Requirements 100-1 101 Design Responsibility 100-1 102 Structural Design Period 100-1 102.1 Priority System Design Period... 100-1 102.2 General System Design Period... 100-2
More informationSUMMARY OF COMMENTS/RECOMMENDATIONS
SUMMARY OF COMMENTS/RECOMMENDATIONS PROPONENT: 6409840 Manitoba Ltd. (Tritec Concrete) PROPOSAL NAME: Tritec Concrete Concrete Batch Plant CLASS OF DEVELOPMENT: 1 TYPE OF DEVELOPMENT: Manufacturing - CLIENT