1 United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil BILL OF QUANTITIES

2 Lot # 1 Construction & Rehabilitation of Al Sikka Bridge

3 SECTION 1: Demolition, Excavation and Backfilling Works Introduction: the contractor shall visit the site and make all investigations deemed necessary to ascertain the nature of the existing conditions of the structures to be demolished or to receive any alteration, and satisfy him as to the form and nature of works to be carried out, and the existing site conditions. It shall be understood that all salvaged materials and fittings are the UNDP property and stored as instructed by the UNDP. 1.1 Cutting & Removal of the existing demolished bridge elements (2 fallen slabs, 3 damaged piers to the base level, ground slab as min needed for work, hand rails, existing steel bridge two side wire mesh and whatsoever obstructing the works to be executed, according to the design drawings ), and transporting of surplus material to approved places. The price includes careful demolishing of existing temporary steel bridge and support and transports all elements to the ministry of public works stores. The price includes also all safety precautions that any deemed necessary for executing the works including of supplying and erecting support scaffolding system to support the bridge slab before demolishing the damage' slab and piers and during the construction phase according to approved shop drawings and engineer's instructions. The contractor has to submit a work-plan regarding this item for approval of the Engineer. (Demolished bridge length is about 21m and average width =5.2m) UNIT RATE Lump Sum 1

4 1.2 Excavation in any kind of soil/concrete from natural levels to upper levels of the existing foundations according to drawings, and Engineer s instruction including: -Cutting the existing Wadi Gaza lining slab should be by using mechanical saw. -Dewatering the surface the ground water during the excavation works. Note: Payment to the contractor according to engineering measurement 1.3 Backfilling from the excavated level to the bottom level of the ground slab using granular fill (Kurkar) compacted to 98% of maximum dry density in layers not exceeding 25cm thick. Note: Payment to the contractor according to engineering measurement SECTION 1 M UNIT RATE M

5 SECTION 2: Concrete Works The following items include: Using new plywood 18mm thick for concrete fair face works Polythene sheet for concrete elements exposed to the soil Supply and cast plain concrete B200-10cm thick as shown in drawings Supply and fix concrete shuttering using tie-rods patent rods, after removal of tie caps it will be filled with non shrinkage cement grout. Supply reinforcement steel bars, bend, shape and fix to specified locations, Supply and cast ready-mixed concrete using mechanical vibrators, curing, and testing, required admixtures for concrete. Two coats of water-proof hot bitumen for all elements under the ground level (foundation, col. Neck, col. To the level of the ground slab) Rubbing and cleaning of existing steel reinf. The price includes using a suitable system to pump way any kind of ground and surface water out of the suit during the work in underground elements till concrete hardening. 2.1 Supply and cast reinforced concrete (B350) for Foundations, including all requirements to complete the works as per drawings and engineer s instructions. M Supply and cast reinforced F.F concrete (B400) for Col and Col neck, as per drawings and engineer s instructions. M Supply and cast reinforced F.F concrete (B400-fair face) for Tie Beam, Upper Caps, including support beam, as per drawings and engineer s instructions. UNIT RATE M 3 58

6 2.4 Supply and cast reinforced concrete (B- 350 fair face) for Bridge solid slab, (Fair Face finished), (thickness=30cm) including drop beams, inverted beams and all other required works according to drawings. Including treatment of the expansion joint as detailed in drawings, and according to engineer's instructions 2.5 Supply and cast reinforced concrete (B- 300) for the concrete lining ground slab 15cm thick including polythene sheet(0.15mm thick) under slab price includes compaction of soil under ground slab including expansion joint between old and new slab and around the columns. As per drawings and engineer s instructions. 2.6 Ditto, but for the damaged elements everywhere along the existing bridge. The price includes removing the brittle part, drilling and fixing new steel bars with approved epoxy and applying bonding agent to the existing concrete, as per drawings and engineer's instruction. M 3 77 M 2 48 M 3 3 UNIT RATE SECTION 2

7 SECTION 3: Road Works 3.1 Remove the rubble, garbage and clean out the Wadi sides to reach the concrete lining surface. And storm water channel including transporting of surplus material to approved places. Ton 500 UNIT RATE 3.2 Supply and cast reinforced concrete (B300) for retaining wall, shuttering work shall be using Tie-Rode ''patent rods'', after removal of tie caps it shall be filled with non shrinkage cement grout. The item includes excavation backfilling compaction beneath the foundation painting the buried parts with two coats of hot bitumen over primer coat and all requirements to complete the works as per drawings and engineer's instruction. 3.3 Supply and cast reinforced concrete (B250) for Retaining beam 20cm*50cm. The item includes excavation, backfilling, compaction beneath the beam, painting the buried parts with two coats of hot bitumen over primer coat and all requirements to complete the works as per drawings and engineer's instruction 3.4 Supply and cast reinforced concrete (B250) for concrete storm water gutter and chutes, The item includes excavation, backfilling, compaction the subgrade, painting the buried parts with two coats of hot bitumen over primer coat and all requirements to complete the works as per drawings and engineer's instruction 3.5 Supply and lay and level approved granular sand (Kurkar) with CBR 30,20cm thick in one layer for sub base with watering and compaction up to 97% of maximum dry density MDD. M 2 20 M 3 40 M 3 15 M

8 3.6 Supply, lay and level base course material with CBR 80 for the carriage way, 25cm thick in two layers with watering and compaction up to 100% of maximum dry density machine. 3.7 Supply, lay and level base course material with CBR 80 for the old bridge, 30cm thick in two layers to reach the design level of wearing surface with watering and compaction up to 100% of maximum dry density machine. The item will include removal of existing rubble to approved place 3.8 Supply, lay and level base course material with CBR > 80 for the shoulders, 12.5cm thick in one layer with watering and compaction up to 100% of maximum dry density machine. The item will include removal of existing rubble to approved place 3.9 Supply, lay and level base course material with CBR > 80 for underneath the retaining wall, 20cm thick in two layers with watering and compaction up to 100% of maximum dry density MDB Supply and lay compacted asphalt binder course (3/4'' nominal aggregate size) 6 cm average thickness, compacted to at least 98%, including spraying the concrete slab with RC2 binder coat or MCO to the base course at the rate of I.2kg/m2 and all required test. All in according with the specifications, drawings, and engineer's instructions. M M M M 2 40 M UNIT RATE SECTION 3

9 4.1 Supply and install handrail of the bridge comprising of F4 & F3 galvanized steel pipes with required welding. The work includes fixing and painting as per the drawings and engineer s instructions. The painting should be done by using a primer polyzinc layer and two layers of colored paint according the drawings and Engineer s instructions. Price also includes painting of curbstone according to engineer's instructions. 4.2 Supply and fix signboard showing allowed vehicles to pass over the bridge as per drawings. The work shall include galvanized steel posts, concrete foundations, Timber or ply backboards and all other required works. 4.3 Supply and fix from one side a galvanized steel plate 300*10mm to the cover the old expansion joints. Fixation shall use expandable bolts. Supply and fix cast iron rainwater drainage grit 90x40cm including galv. Steel plate tray and galv. Steel pipe and all necessary fittings and pieces as indicated in drawings and according to the engineer's instructions. Linear Meter NO 2 Linear Meter No 4 UNIT RATE 4.5 Supply and lay UPVC pipe 6'', SN8 including concrete encasement 30cm*30cm, elbow, Tee AND all fittings to complete the work as per drawings and the engineer's instructions. Linear Meter 100 SECTION 4

10 Section No. 1 SUMMARY OF LOT#1 Section Description Value Demolition, Excavation, Backfilling and Stone Works. 2 Concrete Works 3 Road works 4 Miscellaneous Works Total VAT ZERO Grand Total Grand Total in Words. Contractor Authorized Person to sign Signature Stamp Date... Address.. Tel. Fax

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES

More information

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. Beit Hanoun Emergency Water Supply Project "Beit Hanoun Emergency Water Supply Project" " Rehabilitation and Construction of Beit Hanoun Water Network " BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE Bill of Quantities PREAMBLE TO

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Construction Salah El Deen Road Median From Al Zawaida entrance to Al Maghazi Northern entrance PAL 10-00071488 Bill of Quantity (BOQ) PREAMBLE TO BILL OF QUANTITY (BOQ)

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated

More information

Rehabilitation of Omar Bin El Khattab, Al Karama, and Saeed Dakka Roads in Jabalia by Using Crushed Material

Rehabilitation of Omar Bin El Khattab, Al Karama, and Saeed Dakka Roads in Jabalia by Using Crushed Material Rehabilitation of Omar Bin El Khattab, Al Karama, and Saeed Dakka Roads in Jabalia by Using Crushed Material Bill of Quantity of Omar Bin El Khattab Road Item No. 1.1 Description Unit Qty. Clean, excavate

More information

Estimate FOR THE SEPTIC TANK

Estimate FOR THE SEPTIC TANK Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks

More information

CONSTRUCTION AND REHABILITATION OF FENCE AT GPL'S VERSAILLES COMPOUND

CONSTRUCTION AND REHABILITATION OF FENCE AT GPL'S VERSAILLES COMPOUND BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg, Georgetown. 1.2 Engineer The Engineer

More information

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY D DEMOLITION & SITE CLEARANCE D1 GENERAL CLEARANCE 6-D152 Open bush and thicket in and around ha 0.02 the ponds. Locally disposed. D2 REMOVAL OF TREES AND STUMPS 6-D212 Trees of girth: 150 mm - 500 mm

More information

BILL SUMMARY. March 15, 2018 BILL No. DESCRIPTION AMOUNT

BILL SUMMARY. March 15, 2018 BILL No. DESCRIPTION AMOUNT PROJECT: CONSTRUCTION OF NEW TIMBER WHARF, SOUTHERN BILL No. DESCRIPTION AMOUNT 1 PRELIMINARIES 2 DEMOLISHION WORKS 3 TIMBER WHARF CONSTRUCTION 4 CATWALK CONSTRUCTION BILL SUMMARY 5 CONCRETE WALKWAY CONSTRUCTION

More information

Heavy Rib. Page 1 of 6. Expanded Mesh & Metal Products. Key Product Features:

Heavy Rib. Page 1 of 6. Expanded Mesh & Metal Products. Key Product Features: TMI- is used widely in construction work for joints, stop-end, retaining walls and columns. It creates a strong bond base for successive pours. is fixed as permanent formwork. Key Product Features: Unique

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities. for LOCATED AT PRIMARY & SECONDARY SCHOOL.

Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities. for LOCATED AT PRIMARY & SECONDARY SCHOOL. Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities for SIX CHAMBER VIP LATRINE FACILITY LOCATED AT PRIMARY & SECONDARY SCHOOL YEI RIVER COUNTY South Sudan JUN,

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION Edition

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION Edition CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION PURPOSE, INTENT AND INTERPRETATION OF SPECIFICATIONS The purpose of these Specifications is to establish, where applicable, minimum acceptable standards

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems SECTION 02607-1 1.0 GENERAL 1.1 SCOPE: A. This section covers the work necessary for the construction of sanitary and storm system manholes, catch basins, and miscellaneous concrete structures complete.

More information

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General DESIGN STANDARDS Division 02 Existing Conditions- Site Work General I. This Division includes: A. Demolition B. Clearing and Grubbing C. Excavation, Backfill and Compaction D. Pavement Base E. Paving and

More information

Description Unit Quantity Rate Kshs. Amount Kshs.

Description Unit Quantity Rate Kshs. Amount Kshs. BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove

More information

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9080 - Concrete Steps, Handrails, and Safety Rail CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL PART - GENERAL.0 SECTION INCLUDES

More information

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS

ODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B401: DELETED B402: DELETED B403: DELETED B404: STRUCTURE/CULVERT IDENTIFICATION SIGNS B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B406: ITEM 514 - FIELD PAINTING, MISC.; REPAIR PAINTING

More information

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT Roof Parapet (Detail 911) 21 0 380 380 40 Tie Beams (Detail 8) Tie Beams (Detail 8) FGL Raft foundation (Detail 6) 4 H=0 min Column (Detail 7) + 0.00 PLAIN CONCRETE,6 ELEVATION VIEW 1/0 FGL Floor Tank

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS Section 02501 PART 1 GENERAL 1.01 SUMMARY This Section includes ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT

More information

Underground Exhaust System

Underground Exhaust System Operation and Maintenance Manual Underground Exhaust MONOXIVENT - SOURCE CAPTURE SYSTEMS - info@ Oct. - 2015 Underground Duct Construction Standards 1. Dig trench depth to allow for minimum distance from

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

REPUBLIC OF LEBANON MINISTRY OF ENERGY AND WATER UNITED NATIONS DEVELOPMENT

REPUBLIC OF LEBANON MINISTRY OF ENERGY AND WATER UNITED NATIONS DEVELOPMENT REPUBLIC OF LEBANON MINISTRY OF ENERGY AND WATER UNITED NATIONS DEVELOPMENT PROGRAMME FEASIBILITY ASSESSMENT AND DESIGN OF A WASTEWATER MANAGEMENT SYSTEM IN AL AMAYER-WADI KHALED (KNAISSE VILLAGE) VOLUME

More information

ROAD PAVEMENTS GENERAL

ROAD PAVEMENTS GENERAL ROAD PAVEMENTS GENERAL Contents Clause Title Page 701 Pavement Construction... 2 702 Horizontal Alignments, Surface Levels and Surface Regularity of Pavement Courses... 2 703 Not Used... 4 704 Not Used...

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

Section 401. PIPE CULVERTS

Section 401. PIPE CULVERTS 401.02 Section 401. PIPE CULVERTS 401.01. Description. This work consists of constructing pipe culverts of the size and class required, including excavation and backfill. 401.02. Materials. Provide materials

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) OF THR 8th PRIMARY SCHOOL TOILETS IN MYTILENE. Annex A - BILL OF QUANTITIES 1/9

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) OF THR 8th PRIMARY SCHOOL TOILETS IN MYTILENE. Annex A - BILL OF QUANTITIES 1/9 RFP/GRC/LSV/2017-005: RENOVATION (CIVIL WORKS) OF THR 8th PRIMARY SCHOOL TOILETS IN MYTILENE Annex A - BILL OF QUANTITIES 1/9 The Contractor shall consider in his price all costs or expenses of all requirements

More information

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations.

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations. DURA-CRETE S-SERIES PRECAST CONCRETE WALL SPECIFICATIONS PART 1 GENERAL 1.01 SECTION INCLUDES A. Concrete Screen Wall Description: Work under this item shall consist of furnishing and erecting a wall in

More information

Table of Contents. List of Drawings

Table of Contents. List of Drawings SCOPE OF WORK Hastings Stadium Exhibition Park, 81 London Road, Guelph, Ontario Structural and Maintenance Remedial Work Prepared For City of Guelph City Hall, 1 Carden Street, Guelph, ON N1H 3A1 Prepared

More information

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE Bridge Manual - Part I - June 2007 5-1 CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE 5.1 GENERAL This chapter is intended to instruct the Designer in the preparation and submission of Special Provisions and

More information

ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE...

ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE... ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL... 3 2. DESCRIPTION OF ITEMS... 5 3. PRICES TO BE FULLY INCLUSIVE... 5 4. COVERAGE... 6 5. BIDDER TO PRICE EACH ITEM... 6 6.

More information

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013 SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR

More information

SECTION CHAIN LINK FENCES AND GATES (PARK)

SECTION CHAIN LINK FENCES AND GATES (PARK) SECTION 02821 CHAIN LINK FENCES AND GATES (PARK) PART I GENERAL 1.1 SECTION INCLUDES A. Installation of chain link fences, and gate units provided by single source including erection accessories, fittings,

More information

Method of Measurement for Road Works Series MM Structural Concrete

Method of Measurement for Road Works Series MM Structural Concrete Method of Measurement for Road Works Series MM 1700 - CC-RMP-01700 December 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 5 REINFORCING STEEL. 5.1 General Certification Fabrication...

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 5 REINFORCING STEEL. 5.1 General Certification Fabrication... SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 5 REINFORCING STEEL TABLE OF CONTENTS 5.1 General...5-1 5.2 Certification...5-1 5.3 Fabrication...5-1 5.4 Handling and Storage...5-1 5.5 Field Repair of Epoxy

More information

Aluminum Component Pipe Railings

Aluminum Component Pipe Railings 1 SECTION 05 7360 ALUMINUM COMPONENT PIPE RAILINGS PART 1 GENERAL 1.01 SECTION INCLUDES A. Aluminum component pipe handrails and railings. 1.02 RELATED REQUIREMENTS A. Section 02 9000: Landscaping: Installation

More information

8367 TRANSPORTATION WORKER 3

8367 TRANSPORTATION WORKER 3 TRANSPTATION WKER 3 Nature of Work Under limited supervision, at the journey level performs skilled work in the construction and maintenance of highways, related buildings and structures, and erecting

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

Appendix 4. Bills of Quantities

Appendix 4. Bills of Quantities Appendix 4. Bills of Quantities 201 A4.1 Deep trench latrines Partitions of local materials 1m apart Timber foot rests and floor plates Lightweight timber frame Excavated soil (used for back-fill) Plastic

More information

A. BILL OF QUANTITIES FOR SANITARY SEWER

A. BILL OF QUANTITIES FOR SANITARY SEWER Note: Unit prices of BoQ items shall include the execution of all small and unforeseen works not covered by BoQ, but that are necessary to be carried out during construction for smooth process of works

More information

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL SECTION 321200 - PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The Contractor for this work shall be held to have read all of the Bidding Requirements, the Proposal Forms, the General Conditions of

More information

EINRIP. Specification and Construction Issues

EINRIP. Specification and Construction Issues EINRIP Specification and Construction Issues There are a significant number of changes in the Specification Not all issues can be discussed here A more detailed list of changes will be provided with bid

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT SECTION 220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

SikaProof Bentonite Plastic DPM overlap - Compacted Backfill Scale 1:5. Detail no: SB01 - Nov 2013

SikaProof Bentonite Plastic DPM overlap - Compacted Backfill Scale 1:5. Detail no: SB01 - Nov 2013 100 100 1.1 Metre wide piece of fully bonded to cast concrete 300 SikaSwell P Profile 2010H Compacted backfill Plastic DPM Min. 300mm overlap with Bentonite Paste in the lap 300 300 Plastic DPM overlap

More information

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated:

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated: SECTION 04220 CONCRETE UNIT MASONRY PART 1 - GENERAL 1.01 SCOPE: A. The CONTRACTOR shall furnish all labor, materials and equipment necessary for the masonry construction as shown on the drawings or as

More information

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures Journal of Civil Engineering and Architecture 9 (2015) 213-224 doi: 10.17265/1934-7359/2015.02.010 D DAVID PUBLISHING Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation,

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

FORMDECK. constructions. constructions

FORMDECK. constructions. constructions FORMDECK constructions constructions Introduction Formdeck300 (FD300) is a very efficient and durable permanent metal tray formwork, reinforcement and ceiling system used for suspended concrete slab construction.

More information

DUCTILE IRON PIPE AND FITTINGS

DUCTILE IRON PIPE AND FITTINGS Section 02501 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT

More information

Highway Cost Index Estimator Tool Final report PRC 17-73

Highway Cost Index Estimator Tool Final report PRC 17-73 Highway Cost Index Estimator Tool Final report PRC 17-73 Highway Cost Index Estimator Tool Texas A&M Transportation Institute PRC 17-73 March 2018 Authors Brett Huntsman Brianne Glover, J.D. Samir Huseynov

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS CONCRETE SIDEWALKS AND DRIVEWAYS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary

More information

SECTION PRECAST STRUCTURAL PRETENSIONED CONCRETE

SECTION PRECAST STRUCTURAL PRETENSIONED CONCRETE PART 1 - GENERAL 1.1 DESCRIPTION: SECTION 03 41 33 PRECAST STRUCTURAL PRETENSIONED CONCRETE SPEC WRITER NOTE: Delete between //--// if not applicable to project. Also delete any other item or paragraph

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

SPECIAL SPECIFICATION 4385 Railroad Bridge Construction

SPECIAL SPECIFICATION 4385 Railroad Bridge Construction 2004 Specifications CSJ 0912-71-622 SPECIAL SPECIFICATION 4385 Railroad Bridge Construction 1. Description. Construct Railroad bridges following the recommendations in the applicable Chapters of the current

More information

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS December 2012 CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions Specifications...

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

3.3 Wall Construction

3.3 Wall Construction 3.3 Wall Construction Introduction Sections 3.1 and 3.2 deal with the specifics of laying and the fixing of reinforcing steel. This section primarily looks at the grouting and general construction of the

More information

Department of Transportation Pierre Region Office 104 S. Garfield Bldg. A Pierre, South Dakota / FAX: 605/

Department of Transportation Pierre Region Office 104 S. Garfield Bldg. A Pierre, South Dakota / FAX: 605/ Connecting South Dakota and the Nation Department of Transportation Pierre Region Office 104 S. Garfield Bldg. A Pierre, South Dakota 57501-5405 605/773-3464 FAX: 605/773-6215 May 6, 2011 RE: 0009-391

More information

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories. SECTION 02830 CHAIN LINK FENCES AND GATES (GALVANIZED) 1.0 GENERAL 1.1 Section Includes A. Fence framework, fabric, gates, and accessories. B. Excavation for post bases; concrete footing for posts. C.

More information

HITT STREET UNIVERSITY PROJECT #: CP REFER TO CP PLANS FOR ELECTRICAL DUCTBANK IN HITT STREET INSTALL:

HITT STREET UNIVERSITY PROJECT #: CP REFER TO CP PLANS FOR ELECTRICAL DUCTBANK IN HITT STREET INSTALL: N 1133521.33 E 1689742.43 STA: 10+53.07 INSTALL: 2-10" 90 BENDS CONNECT TO MIDDLEBUSH HALL INTERIOR PLANT PLUMBING MIDDLEBUSH HALL HW1 HWS HWR 10+00 FREDRICK APARTMENTS FINE ARTS INSTALL 422 LF 10" HWS

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3 CITY OF TORONTO TS 3.65 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS 3.65.01 SCOPE...3 TS 3.65.02 TS 3.65.03 REFERENCES...3

More information

SECTION STRUCTURAL PRECAST CONCRETE

SECTION STRUCTURAL PRECAST CONCRETE SECTION 03500 STRUCTURAL PRECAST CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Section Includes. This section covers Prestressed or Precast concrete member construction, including product design not shown on

More information

SCHEDULE A BILL OF QUANTITIES Part - I : Construction of Road

SCHEDULE A BILL OF QUANTITIES Part - I : Construction of Road Sl.Pg.No.193 Name of Work : Construction of 20.0 m. wide road in Sector 16 under 12.5% scheme around Shelghar Village at Ulwe Node, Navi Mumbai. SCHEDULE A BILL OF QUANTITIES Part - I : Construction of

More information

DIVISION 15-MECHANICAL SECTION SUPPORTS AND ANCHORS PN PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Pipe and equipment support systems.

DIVISION 15-MECHANICAL SECTION SUPPORTS AND ANCHORS PN PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Pipe and equipment support systems. PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pipe and equipment support systems. B. Inserts. 1.02 RELATED SECTIONS A. Section 15890 - Ductwork Supports. 1.03 DEFINITIONS A. Supports: Attachments, hangers,

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

CONSTRUCTION SUMMARY REPORT

CONSTRUCTION SUMMARY REPORT Edison Engineers Inc. 89 King Street W. Suite 3 Dundas (Hamilton) Ontario Canada L9H 1V1 Info@edisonengineers.ca CONSTRUCTION SUMMARY REPORT To: Halton Condominium Corporation No. 70 c/o Wilson Blanchard

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Furnish equipment, materials, and labor required for the supply, casting, finishing, curing, and testing of cast-in-place concrete, as

More information

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket 1993 Specifications CSJ 0331-04-045 SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket 1. Description. This Item shall govern for the furnishing, installing and energizing a sacrificial

More information

REQUIREMENTS FOR CONCRETE MIX DESIGN

REQUIREMENTS FOR CONCRETE MIX DESIGN REQUIREMENTS FOR CONCRETE MIX DESIGN Requirements of concrete mix design should be known before calculations for concrete mix. Mix design is done in the laboratory and samples from each mix designed is

More information

PART 5 WATER SYSTEMS

PART 5 WATER SYSTEMS PART 5 WATER SYSTEMS Abbreviations and Symbols Plan 501 Abbreviations and symbols for water... 205 Concrete Boxes and Hardware 502 27" Frame and cover... 207 503 38" Frame and cover... 209 505 Concrete

More information

Description. This work shall consist of furnishing materials and placement of modular block wall constructed in accordance with

Description. This work shall consist of furnishing materials and placement of modular block wall constructed in accordance with MODULAR CONCRETE BLOCK RETAINING WALL WITH GROUND REINFORCING The Standard Specifications are revised as follows: 732-R-310r 1of 11 Rev. 12-03-03 SECTION 105, AFTER LINE 48, INSERT AS FOLLOWS: When constructing

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00 Description Page No Summary Amount Summary 1/7 230,694.60 22,019.25 22,642.65 2/6 96,801.30 80,150.60 114,056.00 Total Per Unit (MYR) 327,495.90 102,169.85 136,698.65 Total Unit(s) X 1 2 2 Total Per Type

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

CONCRETE FORMWORK CHECKLIST AT SITE

CONCRETE FORMWORK CHECKLIST AT SITE CONCRETE FORMWORK CHECKLIST AT SITE Concrete formwork is a temporary supporting structure for concrete when it is placed at the construction site to keep the concrete in position and shape till it gets

More information

www.fastformsystems.com info@fastformsystems.comm South Tel: 00 44 (0) 207 1481274 North Tel: 00 44 (0) 8456 171152 Fast-Form The Complete Formwork system Safer / Faster / Greener / Cheaper One system,

More information

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems. SECTION 33 05 13 MANHOLES AND STRUCTURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems. B. Related Sections: 1. Section 03 20 00 - Concrete

More information

Design of Rigid Pavements

Design of Rigid Pavements Traffic and Highway Engineering (ІІ) CVL 4324 Chapter 20 Design of Rigid Pavements Dr. Sari Abusharar Assistant Professor Civil Engineering Department Faculty of Applied Engineering and Urban Planning

More information

APPENDIX B ABC STRUCTURES DESIGN GUIDE

APPENDIX B ABC STRUCTURES DESIGN GUIDE APPENDIX B ABC STRUCTURES DESIGN GUIDE The Cohos Evamy Partners TABLE OF CONTENTS Page No. DISCLAIMER... I 1. STRUCTURAL DESIGN GUIDELINES... 1 2. GENERAL REQUIREMENTS (FIGURE B.2, STEP 1)... 1 3. GENERAL

More information

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE BE IT ORDAINED by the Town Council of the Town of Plainville: SECTION 1. SUBDIVISIONS. All subdivisions hereinafter developed within

More information

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours Basic Edition Standard Estimate Report Page 1 Name 1000 General Conditions 1107 Professional Consultant 10 Surveying 1.00 day 600.000 /day 600 - - - - - - 600 Professional Consultant 600 600 8.00 hours

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

SECTION UTILITY MANHOLES AND STRUCTURES

SECTION UTILITY MANHOLES AND STRUCTURES SECTION 33 05 14 UTILITY MANHOLES AND STRUCTURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Precast reinforced concrete manholes and structures with tongue-and-groove joints with masonry transition

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Furnish equipment, materials, and labor required for the supply, casting, finishing, curing, and testing of cast-in-place concrete, as

More information

CONCRETE BLOCK MASONRY

CONCRETE BLOCK MASONRY CONCRETE BLOCK MASONRY CONTENT Introduction Types Manufacturing process Properties Advantages Introduction These are the concrete blocks either hollow or solid. A hollow unit is that unit which has core

More information

Polysewer Gravity Sewer System SPECIFICATION

Polysewer Gravity Sewer System SPECIFICATION Polysewer Gravity Sewer System SPECIFICATION July 2014 SCOPE OF WORKS To meet the specific performance criteria detailed within this specification and accompanying drawings. The completed drainage systems

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

BISON PRECAST FLOORING SPECIFICATION

BISON PRECAST FLOORING SPECIFICATION BISON PRECAST FLOORING SPECIFICATION 1.0 SCOPE OF THE SPECIFICATION 1.01 Relates to: This specification covers the design, manufacture and associated site work of the following types of floors:- Hollowcore

More information

Elevated Slab Sequence

Elevated Slab Sequence Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)

More information