Robinson Landing Condominium Pre- Construction Meeting

Size: px
Start display at page:

Download "Robinson Landing Condominium Pre- Construction Meeting"

Transcription

1 Robinson Landing Condominium Pre- Construction Meeting March 22, 2018

2 Topics of Presentation 1. Team Introductions 2. Project Overview 3. Overall Schedule and Condominium Schedule (Draft) 4. Sequence of Condominium Construction 5. Activities Related to Condominium Construction Cut Off Wall Mass Excavation 6. Project Operations Site Logistics and Management Haul Routes Parking Pedestrian Circulation Traffic Control Work Hours 7. Construction Monitoring 8. Communication Plan 9. Q&A 2

3 Condominium Project Team OWNER/DEVELOPER RTS Condo Associates LLC Adam Thormahlen, Project Manager Greg Griffin, Director of Construction (301) (301) Adam Hayes, Director of Engineering CITY OF ALEXANDRIA, Transportation & Environmental Services Emilio Pundavela, Civil Engineer IV Michael Downing, Inspector II CITY OF ALEXANDRIA, Code Administration Pete Mensinger, Special Projects Manager GENERAL CONTRACTOR- Donohoe Construction Company Jon Sandberg, Senior Project Manager Neal Frumkin, Project Executive (202) (202) Jack Barry, Senior Superintendent Maria Mulheren, Project Engineer

4 Condominium Project Overview

5 Project Location 5

6 Aerial View 6

7 Site Plan 7

8 Garage Plan 8

9 View of Building 1 from River 9

10 View of Building 2 from River 10

11 View of Building 3 from Wolfe Street 11

12 View of Pioneer Mill Way 12

13 View of Promenade looking south 13

14 View of Townhomes from Duke Street 14

15 View of Townhomes from South Union 15

16 Overall Schedule of Construction Late Spring/Summer 2018: Install Cutoff Wall Late Summer 2018: Excavation/Barging Fall/Winter 2018: Concrete Construction Spring/Summer 2019: Building Skin Fall/Winter 2019: Building Interiors Fall/Winter 2019: Site Work Winter 2019/Spring 2020: Substantially Completed 16

17 Sequence of Condominium Construction Schedule is an illustrative draft. It is provided to represent estimated durations and sequence of building construction. It is subject to change. 17

18 Sequence of Condominium Construction Schedule is an illustrative draft. It is provided to represent estimated durations and sequence of building construction. It is subject to change. 18

19 Sequence of Condominium Construction Schedule is an illustrative draft. It is provided to represent estimated durations and sequence of building construction. It is subject to change. 19

20 TRD Soil Mix Wall TRD soil mix walls are mixed-in-place using a specialized vertical cutter post mounted on a base crawler machine. The vertical cutter post, resembling a large chain saw, is inserted vertically in sections by the crawler machine until the design depth of the wall is reached. The crawler machine then advances along the wall alignment while the cutter post cuts and mixes the in situ soil with cement-based binder slurry injected from ports on the post. The vertical mixing action blends the entire soil profile, eliminating any stratification, and creates a soil mix wall with a high degree of uniformity and low permeability. 20

21 Project Operations

22 Site Logistics Plan This is subject to change 22

23 Site Logistics Description A secure perimeter fence with gates at access points will establish the limits of the Condo Construction area. Field Office will be located in 2 Duke Street Building with some additional temporary trailers located on site. Overall construction sequence will move from Building 3 in SW Corner towards Building 1 in NE corner Initial laydown and staging for cut off wall effort will be on townhouse pads 7,8 & 9 with material delivery via South Union. Additional Lay down areas are located adjacent to bulkhead and on pier. (Purple Area) Mass Excavation will utilize a conveyor system to load barges at pier. Duration will be 6-8 weeks. Material staging will be between buildings and river Constrained site will necessitate materials will be delivered on a just in time basis. Access lanes in yellow. Two tower cranes will be utilized for the project. First crane will be located at Building 8 and in use for ~20 weeks. Second crane will be located between Building 1 & 2 and will be in use for ~32 weeks. 23

24 Site Management A Donohoe Representative will be onsite when any work is being performed. The building will be designated as non- smoking for the duration of construction. A designated smoker area will be established and posted. Portable toilets will be located throughout the site at approximately 1 per 25 workers. Donohoe will have a labor force that will regularly pick up trash and loose construction debris across the site, including sweeping of streets at entrances. Designated lunch areas will be established with waste receptacles for trash. Rodent abatement will continue for the duration of the construction Post and maintain No street parking for construction workers signs at entrances and at site perimeter. Regular safety inspections are performed by Donohoe Safety Department 24

25 Haul Routes A Haul Route is approved by the City of Alexandria. Inbound traffic will use Franklin Street to Union Street and Outbound traffic will use Union St. to Gibbon Street. The Haul Route is subject to change at the discretion of the City of Alexandria Department of Transportation and Environmental Services at Permit issuance. 25

26 Parking Construction workers will either park off site without a charge to the workers or with locational preference on site given to those who carpool. Construction workers shall not be permitted to park on the public streets. Construction workers who use Metro, DASH, Bike Share or another form of mass transit to the site, we will subsidize a minimum of 80% of the fees for mass transit. These provisions are written into each subcontract. A preconstruction meeting will be held with each subcontractor to go over this requirement and we will provide them with the various commuting/parking opportunities prior to starting work on site. 26

27 Parking Construction Phase Duration Estimated avg. number of workers on site Number of parking spaces needed Number of available spaces on site SOE/Excavation 4 months Foundations Garage Work Building Structure & Skin Building Finishes 4 months months months Onsite garage 27

28 Available Parking 28

29 Pedestrian Circulation Pedestrian access on north side of Wolfe Street and the east side of South Union Street will be closed until streetscape improvements are completed. Donohoe will obtain required permits and maintain control devices (signs) to safely direct pedestrians to opposite side of the street. Construction Fence located at back of sidewalk will be moved to the edge of lane during the lane closure period and returned to the back of sidewalk when the work is complete. 29

30 Traffic Control Intermittent temporary lane closures will be required throughout the construction effort to assure safety for the community and the construction work force. When necessitated, the required lane closure permits will be obtained and a combination of traffic signs, flagging stations, barriers and other devices will be used to safely manage the traffic. Full street closures may be required under certain limited events (crane erection, etc). This will be very limited and coordinated closely with the City Staff. All closures will be properly noticed by at least 72 hours The Vehicular Traffic Management will be coordinated with the Pedestrian Traffic Management when sidewalk closures are also required. 30

31 Work Hours All Construction Activities will comply with the Alexandria Noise Control Code Title 11, Chapter 5, which permits construction activities to occur Monday through Friday 7AM to 6PM and Saturdays from 9AM to 6PM. No construction activity will be permitted on Sundays and Federal holidays. If circumstances arise that necessitate work outside designated hours, the waiver will be requested from the City staff. 31

32 Construction Monitoring Construction monitoring shall be performed in accordance with the requirements of all plan approvals and permit conditions, as well the procedures outlined in the approved Health & Safety Plan and the approved Soil and Groundwater Monitoring Plan. The designated Site Safety Officer will monitor contractors for compliance. Archeologist will be present for all ground disturbing activities in areas that have not been cleared. An Environmental Technician will test soils for contamination in areas not previously cleared. Exposure monitoring will be performed using a PID by the Environmental Technician during soil excavation activities. If the concentration of VOCs is below the action limit of 25 parts-per-million (ppm), no action will be required. However, if VOCs exceed 25 ppm, Level C PPE will be required. Engineering controls, such as sprayers or water trucks, will be used to prevent dust or visual emissions during the construction process. The Environmental Technician will test groundwater in compliance with the VA DEQ VPDES permit issued for the property prior to discharging any water. If contaminant concentrations exceed the VPDES permit limit, the water will be treated to reduce contaminant concentrations to acceptable levels prior to discharge. 32

33 Adjacent Property Protection Offsite monitoring of adjacent properties will be conducted during ground disturbing construction activities in accordance with the Construction Monitoring plan. Crack Gauge Monitoring- crack monitoring gauges were previously installed prior to demolition. These gauges will be read with a caliper monthly. Vibration Monitoring- a written Structures Monitoring Plan (SMP) was developed previously which includes the installation of seismographs to obtain vibration measurements at the surrounding structures. Each seismic station will be equipped with a cellular modem for communication. We will keep the same parameters for project thresholds as established during the Phase 1 Activities. If vibrations reach or exceed established project thresholds, then a text message or will be sent to alert designated project personnel. Project personnel will then identify the source of the vibration and determine if adjustments in the construction methods are required. Settlement Monitoring Settlement monitoring gauges have been installed. These gauges will be monitored for any changes in adjacent properties Damage Claim Protocol- Located on the Robinson Landing Website as well as the City of Alexandria website. 33

34 Communication Plan Project Website robinsonlanding.com Link to Construction Updates Presentation slides Posted on City Website and Project Website City Ad Hoc Monitoring Group on Waterfront Construction Normally scheduled on the 1 st Monday of the month Project Contacts for Condo Construction Adam Thormahlen athormahlen@eya.com Greg Griffin ggriffin@eya.com Jon Sandberg jons@donohoe.com Jack Barry jackb@donohoe.com Construction@RobinsonLanding.com 34

35 Closing Remarks and Q & A Q&A 35

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Topics of Presentation 1. Team Introductions 2. Project Overview Location, Aerial View & Site Plan 3. Overall Schedule 4. Sequence

More information

Robinson Landing: Pre-Demo Meeting July 6, 2016

Robinson Landing: Pre-Demo Meeting July 6, 2016 Robinson Landing: Pre-Demo Meeting July 6, 2016 Table of Contents 1. Team Introductions 2. Project Overview 3. Phase I Activities Schedule Buildings for Demolition 226 Strand Demolition Cut & Cap of Utilities

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

MAINE MEDICAL CENTER

MAINE MEDICAL CENTER MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES The District of West Vancouver requires a Traffic Management Plan (TMP) to be submitted for acceptance by the Land Development

More information

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014 New Stadium Project Construction Activity Mitigation Program January 22, 2014 Construction Mitigation Plan Introduction It is the primary goal of HHRM, JV to minimize negative effects on traffic and the

More information

GENERAL NOTES REQUIRED NOTES ON ALL PLANS

GENERAL NOTES REQUIRED NOTES ON ALL PLANS GENERAL NOTES REQUIRED NOTES ON ALL PLANS ALL MATERIALS, WORKMANSHIP AND CONSTRUCTION SHALL CONFORM TO THE CURRENT CITY OF SANTA ROSA DESIGN AND CONSTRICTIOIN STANDARDS AND CONSTRUCTION SPECIFICATIONS

More information

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017 1107 E. Madison Street Student Housing Project Monthly Update May 12, 2017 Anticipated Completion: Fall 2018 About the Project: This newly constructed building will be ten stories providing eight floors

More information

LAKE + FOREST CONSTRUCTION TIMELINE

LAKE + FOREST CONSTRUCTION TIMELINE LAKE + FOREST CONSTRUCTION TIMELINE Below is a construction timeline in connection with the project at Lake Street and Forest Avenue. All dates are approximate and subject to change based on weather and

More information

CONSTRUCTION MANAGEMENT PLAN LIMELIGHT HOTEL PREPARED FOR THE CITY OF KETCHUM, IDAHO

CONSTRUCTION MANAGEMENT PLAN LIMELIGHT HOTEL PREPARED FOR THE CITY OF KETCHUM, IDAHO CONSTRUCTION MANAGEMENT PLAN LIMELIGHT HOTEL PREPARED FOR THE CITY OF KETCHUM, IDAHO Table of Contents A. General Information and Schedule a. General Information Pg. 1 b. Site Location Map Pg. 2 c. Anticipated

More information

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. Contact the Planning Department at 970-429-2799 with any questions. November 2017

More information

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE Chapter 17: Construction A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter discusses the various activities that would be involved in constructing Hamilton Green. The potential for significant adverse

More information

City of West Hollywood Construction Period Mitigation Plan

City of West Hollywood Construction Period Mitigation Plan City of West Hollywood Construction Period Mitigation Plan Construction in an urban environment like the City of West Hollywood, presents challenges that require a well thought-out construction period

More information

811 Emerson St. - Demolition & Site Prep

811 Emerson St. - Demolition & Site Prep 811 Emerson St. - Demolition & Site Prep 811 Emerson St. Evanston, IL 60201 CA Focus Evanston Property Owner, LLC General Contractor Owner Architect Construction Management Plan Phase I January 24t h,

More information

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Meeting Agenda Pre-Construction Meeting Meeting Purpose and Format Project Status Update Introduction of Construction Contractor

More information

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing OVERVIEW Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing Construction Liaison Group Nov 7th, 2013 1 WORKS IN PROGRESS Construction Liaison Group Nov 7 th, 2013

More information

Quanta Resources Superfund Site: Yesterday & Today

Quanta Resources Superfund Site: Yesterday & Today Quanta Resources Superfund Site: Yesterday & Today Edgewater has a rich industrial history. Previous industrial practices from the late 1880s to the 1980s contaminated soil, surface water, river sediments,

More information

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House May 22, 2018 1 Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House Rendering of Trail and Community Improvements at Project Completion 2

More information

STREET ADDRESS OF EVENT: Description of Event:

STREET ADDRESS OF EVENT: Description of Event: TEMPORARY USE PERMIT STREET ADDRESS OF EVENT: Description of Event: To Run from: (Date) (Hour) AM PM To: (Date) (Hour) AM PM Applicant: (Print) Applicant address: (Print) City, State Zip: Phone: Fax: Email:

More information

ARCHITECTUS FEBRUARY 2010

ARCHITECTUS FEBRUARY 2010 ARCHITECTUS PEDESTRIAN AND TRAFFIC MANAGEMENT PLAN FOR DEMOLITION, EXCAVATION AND CONSTRUCTION OF COLLEGE OF FINE ARTS CAMPUS, PADDINGTON FEBRUARY 2010 COLSTON BUDD HUNT & KAFES PTY LTD ACN 002 334 296

More information

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver

More information

Jobsite Specifications The A standard provides jobsite specifications for each of the following hazards:

Jobsite Specifications The A standard provides jobsite specifications for each of the following hazards: Overview of American National Standard A10.34-2001 Protection of the Public on or Adjacent to Construction Sites American National Standard for Construction and Demolition Operations The A10.34-2001 standard

More information

AGENDA REPORT. To: Attachments: 1. Site Location and Outreach Map 2. Recommended Permit Conditions 3. Fencing Location

AGENDA REPORT. To: Attachments: 1. Site Location and Outreach Map 2. Recommended Permit Conditions 3. Fencing Location 9 Meeting Date: May 8, 2018 Item Number: D 6 To: From: Subject: AGENDA REPORT Honorable Mayor & City Council Robert Welch, Acting City Engineer Raj Patel, City Building Official ASBESTOS ABATEMENT PERMIT

More information

Property and Public Protection Plan

Property and Public Protection Plan Property and Public Protection Plan OTTO CONSTRUCTION PROPERTY AND PUBLIC PROTECTION PLAN Otto Construction s pre-planning of construction activities includes procedures to protect the general public and

More information

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS PART 1 GENERAL 1.1 DESCRIPTION A. Temporary Utilities: Electricity, lighting, heating, cooling, ventilation, water, and sanitary facilities. B. Temporary Controls: Barriers, fencing, erosion control, exterior

More information

West Village, 70 Mississauga Road South, Mississauga. Construction Management Plan Phase I: Demolition & Remediation

West Village, 70 Mississauga Road South, Mississauga. Construction Management Plan Phase I: Demolition & Remediation West Village, 70 Mississauga Road South, Mississauga Construction Management Plan Phase I: Demolition & Remediation FINAL, revision 1 January 26, 2018 Table of Contents 1.0 INTRODUCTION... 2 2.0 HOARDING

More information

Construction Notice: Infrastructure Renewal on York and Talbot Streets

Construction Notice: Infrastructure Renewal on York and Talbot Streets Construction Notice: Infrastructure Renewal on York and Talbot Streets Date: March 22, 2019 To: Business owner, resident and/or property owner Project Details: The City of London in partnership with J-AAR

More information

District of North Vancouver Construction Traffic Management Plan Guidelines

District of North Vancouver Construction Traffic Management Plan Guidelines District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction

More information

It is the CONTRACTORS RESPONSIBILITY to use OSHA approved shoring

It is the CONTRACTORS RESPONSIBILITY to use OSHA approved shoring PERMIT# EXCAVATION/RIGHT OF WAY PERMIT ATE: NOTE: No permit shall be issued \vithout CURRENT Montana Contractors License, Insurance and Bonding on file with the Public Works epartment. It is the CONTRACTORS

More information

Navigating Jurisdictional Safety Permits + Requirements

Navigating Jurisdictional Safety Permits + Requirements Navigating Jurisdictional Safety Permits + Requirements Andrew Geisert Safety Manager Caitlin Harris Assistant Safety Manager SESSION AGENDA 1. Overview 2. DC Requirements 3. Maryland Requirements 4. Virginia

More information

811 Emerson St. - Mixed Use Building

811 Emerson St. - Mixed Use Building 8 Emerson St. - Mixed Use Building 8 Emerson St. Evanston, IL 6020 CA Focus Evanston Property Owner, LLC General Contractor Owner Architect Construction Management Plan Phase 2-4 February 4t h, 208 TABLE

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

PROJECT ADDRESS: THRIFT AVE, WHITE ROCK, BC EXCAVATION -

PROJECT ADDRESS: THRIFT AVE, WHITE ROCK, BC EXCAVATION - Project Management By: SEMIAH :SITE SAFETY PLAN 5645-199th Street Langley, BC V3A 1H9 Tel: (604) 530-5646 Fax: (604) 530-0980 Website: www.marcon.ca PROJECT ADDRESS: 15241 THRIFT AVE, WHITE ROCK, BC EXCAVATION

More information

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation

More information

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/ CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA 34695 PHONE: 727/724-1555 FAX: 727/724-1566 RIGHT-OF-WAY / EASEMENT USE PERMIT DATE SUBMITTED: EXPIRATION DATE: Submit the following to the

More information

PART II - CODE OF ORDINANCES Chapter 16 - CONSTRUCTION, REHABILITATION AND PROPERTY MAINTENANCE REGULATIONS ARTICLE VIII. PROPERTY MAINTENANCE

PART II - CODE OF ORDINANCES Chapter 16 - CONSTRUCTION, REHABILITATION AND PROPERTY MAINTENANCE REGULATIONS ARTICLE VIII. PROPERTY MAINTENANCE Sec. 16-291. Construction site management. (a) Construction site management plan required. No building permit shall be issued unless a construction site management plan has been submitted and approved

More information

This development project is undertaken by Snowmass Acquisition Company, a subsidiary of Related Colorado, LLC.

This development project is undertaken by Snowmass Acquisition Company, a subsidiary of Related Colorado, LLC. Executive Summary In accordance with the Town of Snowmass Village requirements, this document shall serve as the Construction Management Plan for the following project: Brush Creek Sanitary Sewer and Water

More information

B. OVERVIEW OF CONSTRUCTION ACTIVITIES

B. OVERVIEW OF CONSTRUCTION ACTIVITIES Attachment F: Construction A. INTRODUCTION As discussed in Attachment A, Project Description and Screenings, the proposed installation would involve the placement of a skeletal stainless steel sculpture

More information

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis MEMORANDUM To: CAJA Environmental Services, LLC Date: From: Subject: Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis LLG

More information

SECTION TRAFFIC REGULATIONS

SECTION TRAFFIC REGULATIONS PART 1 GENERAL 1.1 DESCRIPTION A. Traffic Control permits, notifications, mobilization, temporary signs, barriers, lights, flagging personnel, striping, markings, and demobilization and removal. 1.2 RELATED

More information

Concrete Waste Management

Concrete Waste Management Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective

More information

RE: Jackson Row - truck route

RE: Jackson Row - truck route Will Rasbach From: Sent: To: Cc: Subject: Mayor Pat Patterson Tuesday, January 13, 2015 3:46 PM Will Rasbach; Bart Robinson; Randy Barber (rbarber@oxfordms.net); jowens@oxfordpolice.net

More information

SECTION ASPHALT PAVING AND SURFACING

SECTION ASPHALT PAVING AND SURFACING SECTION 02500 ASPHALT PAVING AND SURFACING PART 1 - GENERAL 1.01 WORK INCLUDED A. Traffic control as required to divert vehicular and pedestrian traffic around construction. B. Spreading and compacting

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Miscellaneous Demolition & Concrete Removal Future Ball Square Station

Miscellaneous Demolition & Concrete Removal Future Ball Square Station Green Line Extension Project Construction Outlook (July 22 Aug. 17) Work schedule subject change based on weather or other factors = New information since last update Miscellaneous Demolition & Concrete

More information

Metro Purple Line Extension

Metro Purple Line Extension metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,

More information

Public Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival

Public Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival Proposed Liberty Village Natural Gas Pipeline Project Public Open House Please sign-in at the registration table upon arrival Feel free to approach any team member to discuss the project Share your thoughts

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Frequently Asked Questions The Basics Who, What, When, Where, Why, How Why is the project being performed? The project is being constructed to reduce flooding in

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Why is the project being performed? Frequently Asked Questions The Basics Who, What, When, Where, Why, How The project is being constructed to reduce flooding in

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Kings 826 LP Project Manager: Demetri Oarmos Phone:

Kings 826 LP Project Manager: Demetri Oarmos Phone: ~COASTAL PACIFIC CONSTRUCTION. INC. Draft Construction Period Management Plan Project Location: 826 N Kings Road, West Hollywood, CA 90046 Date: March 10, 2015 Construction in an urban environment flke

More information

Construction Environment Management Plan. Planning Condition 5.

Construction Environment Management Plan. Planning Condition 5. Construction Environment Management Plan. Planning Condition 5. No development shall take place, including any works of demolition, until a construction method statement in respect of construction environment

More information

The Grande Excelsior Lanai Screen Enclosures Requirements for Decorators, Contractors and Subcontractors

The Grande Excelsior Lanai Screen Enclosures Requirements for Decorators, Contractors and Subcontractors The Grande Excelsior Lanai Screen Enclosures Requirements for Decorators, Contractors and Subcontractors 1. Owners must register with The Grande Preserve Management Office providing the name, address,

More information

Builder Agreement. Access to build in Mountainside Village constitutes agreement to abide by the following:

Builder Agreement. Access to build in Mountainside Village constitutes agreement to abide by the following: Builder Agreement Access to build in Mountainside Village constitutes agreement to abide by the following: 1. It shall be the responsibility of each builder in Mountainside Village ( Builder ) that the

More information

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No PART 1 GENERAL 1.1 RELATED DOCUMENTS REQUIREMENTS COMMON TO ALL WORK CATEGORIES 1. Drawings and general provisions of the Contract, including General Special Conditions and other Division 1 Specification

More information

Impacts considered are of noise or dust resulting from construction activities or truck traffic.

Impacts considered are of noise or dust resulting from construction activities or truck traffic. October 11, 2017 Tyler Monroe Vice President, Development TSA Housing 11812 San Vicente Blvd Los Angeles, CA 90049 310) 820-4888 Mr. Monroe: RE: Construction Plan - Montecito II, Hollywood CA Per your

More information

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON. REQUEST FOR TENDER - SERVICES 1. PURPOSE AND SCOPE This specification is intended to govern the supply of all labour, materials and equipment for the dismantling, demolition of a single dwelling on the

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.05 EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 The bid opening date is Thursday March 15, 2018 at 11:00 a.m. The following changes

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

Thomas Connors Executive Director, Construction Site Safety

Thomas Connors Executive Director, Construction Site Safety Thomas Connors Executive Director, Construction Site Safety Agenda Site Safety Plans Site Safety Requirements BEST Squad Inspections 2 Site Safety Plans 4 Site Safety Logistics Plan Material/ Personal

More information

ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM

ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM ATTACHMENT C MITIGATED NEGATIVE DECLARATION AND MITIGATION AND MONITORING REPORTING PROGRAM CITY OF PASADENA 175 NORTH GARFIELD AVENUE PASADENA, CA 91109 PROPOSED MITIGATED NEGATIVE DECLARATION PROJECT

More information

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES 1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE LATEST EDITION OF THE STANDARD PLANS OF THE CITY OF LA QUINTA, THE LATEST EDITION OF THE STANDARD SPECIFICATIONS

More information

Westside Subway Extension

Westside Subway Extension Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives

More information

Brooklyn Station Construction Open House

Brooklyn Station Construction Open House Brooklyn Station Construction Open House November 16, 2011 Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Louise Little, Greater University

More information

Cityline Sunnyvale Construction Mitigation Plan Approved by the City of Sunnyvale June 29, 2017

Cityline Sunnyvale Construction Mitigation Plan Approved by the City of Sunnyvale June 29, 2017 Cityline Sunnyvale Construction Mitigation Plan Approved by the City of Sunnyvale June 29, 2017 The Project Developer will construct the Cityline Sunnyvale project, Block 1, Block 2, Block 3 (temporary),

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

REQUEST FOR CONSTRUCTION BIDS May 23, 2017

REQUEST FOR CONSTRUCTION BIDS May 23, 2017 REQUEST FOR CONSTRUCTION BIDS May 23, 2017 Cambridge Greenway Trail / Railroad Bridge Replacement Flood Mitigation Project 1.0 Project Background A former railroad bridge that currently carries the Cambridge

More information

LAND DISTURBANCE PERMIT

LAND DISTURBANCE PERMIT SPRINGVILLE CITY Application Date: 110 South Main Springville, UT 84663 Permit Number: (801) 491-2780 Caselle #2208 Project Name: Project Address: LAND DISTURBANCE PERMIT Priority Site Owner s Name Phone

More information

UC Press Building 2120 Berkeley Way Berkeley, CA

UC Press Building 2120 Berkeley Way Berkeley, CA CONSTRUCTION NOISE REDUCTION PROGRAM FOR: UC Press Building 2120 Berkeley Way Berkeley, CA RGD Project #: 17-057 PREPARED FOR: Berkeley Way, LLC 1958A University Ave. Berkeley, CA 94704 PREPARED BY: Harold

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

DEMOLITION BY USE OF EXPLOSIVES

DEMOLITION BY USE OF EXPLOSIVES INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC 91.3303.9 Effective: 7-14-95 DOCUMENT NO. P/BC 2002-020 Revised: 11-17-00 Previously Issued As: MGD #105 DEMOLITION BY USE OF EXPLOSIVES

More information

Application for a Residential Building Permit

Application for a Residential Building Permit Town of Chevy Chase 301-654-7144 (phone) 4301 Willow Lane 301-718-9631 (fax) Chevy Chase, MD 20815 townoffice@townofchevychase.org Town Permit No.: Application for a Residential Building Permit Please

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 18, 2015

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of July 18, 2015 ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 18, 2015 DATE: July 9, 2015 SUBJECT: U-3372-13-1, USE PERMIT AMENDMENT for an amendment to Condition #12.A.5) to permit construction

More information

B. DESCRIPTION OF CONSTRUCTION ACTIVITIES

B. DESCRIPTION OF CONSTRUCTION ACTIVITIES Chapter 15: Construction Impacts A. INTRODUCTION This chapter describes activities required for construction of Alternative A (the no action alternative) and the three build alternatives: Alternatives

More information

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 Additional Fees Additional fees may be charged by PennDOT consistent with Sections 411 and 420 of the State Highway Law and Regulations 441.4(d)

More information

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER 1993 Specifications CSJ 8015-24-003 SPECIAL SPECIFICATION TO ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER 1. DESCRIPTION. This item shall govern all work required to remove groundwater encountered

More information

NEW CONSTRUCTION APPLICATION

NEW CONSTRUCTION APPLICATION NEW CONSTRUCTION APPLICATION CONSTRUCTION COMMITMENT AND CONTRACTOR GUIDELINES The General Contractor is solely responsible for the compliance of these guidelines by all subcontractors, suppliers, and

More information

WORK AND PROJECT REQUIREMENTS

WORK AND PROJECT REQUIREMENTS WORK AND PROJECT REQUIREMENTS BID PACKAGE 3A SITE CONCRETE & CONCRETE TURNKEY CRABAPPLE MIDDLE SCHOOL REPLACEMENT April 26, 2018 EXHIBIT B CONSTRUCTION DOCUMENTS AND SPECIFICATIONS shall be acknowledged

More information

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment 1993 Specifications CSJ'S 0912-71-554 & 0912-71-555 SPECIAL SPECIFICATION ITEM 1016 Tree Preservation and Treatment 1. Description. This section specifies the requirements for protecting trees and related

More information

CONSTRUCTION DUST AND NOISE MONITORING REPORT OFFICE DEVELOPMENT EXAMPLE LTD RP

CONSTRUCTION DUST AND NOISE MONITORING REPORT OFFICE DEVELOPMENT EXAMPLE LTD RP CONSTRUCTION DUST AND NOISE MONITORING REPORT OFFICE DEVELOPMENT EXAMPLE LTD RP01-19999 CONSTRUCTION DUST AND NOISE MONITORING REPORT PROJECT: OFFICE DEVELOPMENT CLIENT: EXAMPLE LTD CLIENT ADDRESS: EXAMPLE

More information

Generator for Maintenance/Police Complex

Generator for Maintenance/Police Complex NOTICE TO ALL BIDDERS ADDENDUM NO. 1 TO TUCSON AIRPORT AUTHORITY 11/29/2018 In accordance with the Project Specifications and Contract Documents, and as noted in the Instructions to Bidders, Bidders on

More information

SECTION AIR POLLUTION AND HAZARDOUS WASTE CONTROLS

SECTION AIR POLLUTION AND HAZARDOUS WASTE CONTROLS 1.0 GENERAL 1.01 DESCRIPTION SECTION 01 57 22 AIR POLLUTION AND HAZARDOUS WASTE CONTROLS The Work specified in this Section consists of eliminating or minimizing air and soil pollution generated by construction

More information

Réseau express métropolitain

Réseau express métropolitain Réseau express métropolitain Presentation of upcoming work for construction of the Canora and Mont-Royal Stations 2018-06-19 Purpose of this meeting Inform you of upcoming work over the next several months

More information

DEMOLITION OF BUILDINGS

DEMOLITION OF BUILDINGS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC Chapter 33 Effective: 01-01-2017 DOCUMENT NO.: P/BC 2017-039 Revised: 01-22-2019 Previously Issued As: P/BC 2014-039 DEMOLITION OF BUILDINGS

More information

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley Existing Project Conditions General Conditions Estimate The Center for Health Research and Rural Advocacy is constructed under the supervision of the Geisinger Facilities Division. The project team develops

More information

St. Tammany Parish Government Department of Procurement P. O. Box 628 Covington, LA Phone: (985) Fax: (985)

St. Tammany Parish Government Department of Procurement P. O. Box 628 Covington, LA Phone: (985) Fax: (985) St. Tammany Parish Government Department of Procurement P. O. Box 628 Covington, LA 70434 Phone: (985) 898-2520 Fax: (985) 898-5227 Pat Brister Parish President February 5, 2016 Please find the following

More information

DEMOLITION OF BUILDINGS

DEMOLITION OF BUILDINGS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC Chapter 33 Effective: 01-01-2014 DOCUMENT NO.: P/BC 2014-039 Revised: 05-11-2016 Previously Issued As: P/BC 2008-039 DEMOLITION OF BUILDINGS

More information

Delaware Street

Delaware Street A t t a c h m e n t 1 F i n d i n g s a n d C o n d i t i o n s 2004-06 Delaware Street Use Permit #09-10000052 JULY 22, 2010 CEQA FINDINGS 1. The project is categorically exempt from the provisions of

More information

City of Reno Public Works

City of Reno Public Works City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE11-00XXX Applicant: Job Description:

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

EROSION CONTROL AND GRADING PERMIT APPLICATION

EROSION CONTROL AND GRADING PERMIT APPLICATION EROSION CONTROL AND GRADING PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT 1735 MONTGOMERY STREET OROVILLE, CA 95965 530-538-2420 FAX (530) 5382426 www.cityoforoville.org APPLICATION DATE PERMIT FEE

More information

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017 UCSF Mission Bay & Dogpatch Construction Community Meeting Agenda Welcome Project Communications Construction Context Project Updates Minnesota Housing Center for Vision Neuroscience Precision Cancer Medicine

More information

STATEMENT OF OFFICIAL ACTION

STATEMENT OF OFFICIAL ACTION STATEMENT OF OFFICIAL ACTION 72 LA CUESTA (APN: 262-032-015) EDP-2016-034 JANUARY 22, 2018 STATEMENT OF OFFICIAL ACTION ACTION: Zoning Administrator Approval SUBJECT: Major Modification to Elevated Deck

More information

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES Environmental / Social issue/ aspect/ activity Anticipated negative impact Management and mitigation

More information

Construction Method Statement

Construction Method Statement Construction Method Statement Planning Application Phase 17 October 2014 for 79-85 Monier Road London E3 2PS Penten Group Ltd 816 Garratt Lane London SW17 0LZ Tel: 020 8772 4040 Description Contents Page

More information