1 Birmingham Public Schools 2015 BOND ISSUE PROGRAM Project Status Update Tuesday June 5, 2018
2 Agenda Dashboard Update for Website Summer 2018 Construction Project Preview Summer 2018 Construction Progress Update
3 Dashboard Report (on website) 2015 Bond Issue Program Monthly Dashboard Report Presented June 5, 2018 GOALS AND OBJECTIVES The plan is to complete the work over a five-year period ( ) Work will begin in some form at every school within the first two years. Why Now? 2017 Historically low interest rates Preserves our limited General Fund Decreasing Foundation Grant Benefits of the Bond: 2018 Enhance Safety and Security Upgrade Buildings and Sites Upgrade Technology 2019 Cost: $66 million year millage Zero increase to the current millage rate of 3.9 mills FACILITIES PROJECT PHASING Elementary School Secure Entry Upgrades, Select Athletic Field Upgrades, and other Phase 1 Projects (i.e. Roofing, Mechanical, Paving, etc.) Secure Entry Upgrades at Secondary Buildings, Groves High School; Performing Arts Upgrades, Media Collaboration Space, Athletics Projects. Other District Wide Phase 2 Projects (i.e. Roofing, Mechanical, Plumbing, Electrical, Paving, etc.) Seaholm High School; Performing Arts Improvements, Media / Collaboration Space, Athletics, & Building Renovations. Other Phase 3 Projects (i.e. Roofing, Paving, etc.) Phase 4 Projects: Roof replacement, Furniture Replacement, Technology Improvements, etc. Phase 5 Projects: Roof replacement, Replacement Furniture, Technology Improvements, etc. See Construction Manager report for more information SHORT TERM MILESTONE TASKS TECHNOLOGY UPDATE Technology Phase 1 Projects Summer 2016 Technology Phase 2 Projects Summer 2017 West Maple Pool Renovation Completion 8/1/2018 Replace staff computers Partial Roof Replacement at Seaholm Start 6/18/2018 Upgrade classroom A/V system Paving Replacement at Seaholm Start 6/18/2018 Technology Phase 3 Projects Summer 2018 Seaholm Performing Arts Renovation Start 3/1/2018 Replace Video Surveillance System for Groves Meadow Lake Abatement & Demolition Start 6/25/2018 Technology corresponding to the 2018 Seaholm renovations Seaholm Chiller Installation Complete Rewire high school piano lab Replace the network firewall Technology Phase 4 Projects Summer 2019 Technology Phase 5 Projects Summer 2020
4 Dashboard Report (on website) 2015 Bond Issue Program Monthly Dashboard Report Presented June 5, 2018 Description Original Budget Current Budget % Current Commitments * Actuals Paid * Cost to Complete Building Exterior $7,283,994 $4,778, % ($4,632,682) ($3,549,613) Building Interior $2,694,120 $3,137, % ($2,887,939) ($2,065,224) Safety and Security $2,145,985 $2,096, % ($2,107,948) ($1,958,016) Mechanical Systems $8,423,189 $10,751, % ($10,858,404) ($8,900,087) Electrical Systems $387,336 $564, % ($406,464) ($279,103) Plumbing Systems $3,046,321 $570, % ($579,174) ($543,772) Furniture & Equipment $2,545,354 $2,597, % ($328,192) ($322,113) Athletics $1,942,492 $1,861, % ($1,706,896) ($1,587,646) Media / Collaboration $199,659 $187, % ($162,025) ($121,354) Performing Arts $5,031,384 $6,490, % ($6,414,133) ($3,306,550) Site Improvements $2,693,039 $2,754, % ($1,835,164) ($1,801,173) Technology $29,590,690 $30,194, % ($22,706,610) ($19,105,652) Totals: $65,983,563 $65,983, % ($54,625,633) ($43,540,302) Percentage: Click link to your school Note: all budget transfers have been within the same project category BUDGET SUMMARY - as of May 31, % 66.0% * Includes prorated amount for indirect costs / professional fees Bingham Farms Midvale Center Quarton Berkshire Seaholm Greenfield Pembroke West Maple Derby Others (Ops, Trans, Tech) $1,080,350 $833,313 $120,843 $1,903,598 $129,816 $26,731 $0 $94,937 $41,053 $3,257,488 $1,017,433 $3,445,360 $11,950, % CASH FLOW / FINANCES - as of April 30, 2018 BOND SERIES I - SOLD JUNE 23, 2015 BOND SERIES II - SOLD January 2018 Construction Fund* $ 33,392,124 Construction Fund Deposit " $ 12,573,928 Net Earned Interest $ 1,515,826 Net Earned Interest / Fees # $ 28,815 Total Funds Available $ 34,907,950 Total Funds Available $ 12,602,743 Expenditures $ (22,407,085) Expenditures $ (125,272) Current Funds Available + $ 12,500,865 Current Funds Available + $ 12,477,471 Actuals Spent per Owner's Rep $ (22,407,085) Actuals Spent per Owner's Rep $ (125,272) Variance $ - Variance $ - * Per Closing Statement + per Bank/Investment Statements # per BPS trial balance " estimated
5 Summer 2018 Construction Project Preview Summer 2018 Construction Projects: Seaholm Performing Arts Center Renovation Seaholm heating ventilation and air conditioning unit replacement Seaholm Heating Ventilation and Air Conditioning updated controls Seaholm pool sound system revisions Seaholm pool and gym locker room floor replacement Groves visitor bleacher foundation rework Seaholm fire alarm system New furniture at Elementary, Middle & High Schools West Maple Roof Top Unit Replacement Seaholm Chiller Replacement Partial roof replacement at Seaholm Parking lot (Phase 2) replacement located by Community Ed at Seaholm Summer 2018 Technology Projects: Complete the remaining interactive display, master clock, and television removal at high schools Patch and painting where equipment was removed Replace video surveillance system for Groves and Seaholm (pending board resolution) Network and Wireless hardware replacement
6 Summer 2018 Construction Progress Update Seaholm High School: Masonry block walls for the addition are completed and vapor barrier installed. Brick for the addition has begun. Precast plank for the roof has been set and grouted. Roof blocking is completed, roofing has started. Underground plumbing and electrical in the addition is ongoing. Roof drains have been installed. Installation of the rigging above the stage has started. Fire protection and duct work above the stage is completed. Starter Boxes and Master Control Cabinet on the stage have been installed. Dimming & controls wiring is 75% complete and sound system conduit is complete. Auditorium house lighting is 60% complete. Caliper masonry has been completed. The metal decking was installed and the concrete on the calipers has been completed. Demolition of the old boilers in our new dressing room area has been completed, the walls have been removed and saw cutting of the floor has been completed. Roof openings and curbs for the Energy Recovery Unit have been completed Beverly Elementary: Work will begin when school is dismissed for summer break. West Maple Elementary: Work will begin when school is dismissed for summer break.
7 Summer 2018 Project Preview Phase 2 Design Community Ed Parking Lot Seaholm
8 Summer 2018 Project Preview Partial Roof Replacement Seaholm
9 Summer 2018 Project Preview Performing Arts Center Renovation Seaholm
10 Summer 2018 Construction Progress Photos Seaholm Performing Arts Stage Caliper
11 Summer 2018 Construction Progress Photos Seaholm Performing Arts Center Demolition of Old Boiler Room
12 Summer 2018 Construction Progress Photos Seaholm Performing Arts Center Starter Boxes and Master Control Cabinet
13 Summer 2018 Construction Progress Photos Seaholm Performing Arts Center Painted Stage Ceiling, Walls and Cabinet
14 Summer 2018 Construction Progress Photos Seaholm Performing Arts Center Scene Shop Addition Looking Northwest
15 Summer 2018 Construction Progress Photos Seaholm Performing Arts Center Scene Shop Addition Looking Southeast
16 Summer 2018 Construction Progress Photos Seaholm Performing Arts Center Scene Shop Addition
17 Questions & Answers Thank You
Oconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationFACILITY NEEDS ASSESSMENT CURRENT PRIORITY ONE PROJECTS
9 - MARCH - 2015 Professional Team TMP Architecture, Inc. Peter Basso Associates, Inc. Integrated Design Solutions SUMMARIES SUMMARIES District Totals ELEMENTARY SCHOOLS Beverly Bingham Farms Greenfield
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationJames Lick High School
James Lick High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan James Lick High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew P.
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationOconomowoc Area School District Facility Construction Update June 29, 2018
Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major
More information2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014
2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included
More informationIndependence Adult Center
Campus Master Plan March 15, 2004 Master Plan Contents Volume I: District Master Plan Andrew P. Hill High School Campus Master Plan Foothill High School Campus Master Plan Independence High School Campus
More informationYardmen Arena Expansion & Renovation Project Update
For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior
More informationBend La Pine Schools 2016 Sites and Facilities Project Needs List
New Elementary 33,155,940 Construct new elementary school 33,155,940 New High School 129,028,000 Construct new high school 129,028,000 Bear Creek Elementary 4,028,138 Add instructional multi use space
More informationWissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017
Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.
More informationSanta Teresa High School
Santa Teresa High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan Santa Teresa High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew
More informationFACILITY COMPONENTS - MIDDLE SCHOOL
SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls
More informationProject Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope
Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope
More informationMinuteman Regional Vocational Technical School
Minuteman Regional Vocational Technical School List of Recommendations L1 AAB compliance: Improvements to front entrance (concrete ramps, railings, etc.) Required by AAB cost trigger L2 AAB compliance:
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationChenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017
Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections
More informationN o v e m b e r
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why
More informationBOYERTOWN AREA SENIOR HIGH SCHOOL
BOYERTOWN AREA SCHOOL DISTRICT ADDITIONS & RENOVATIONS To BOYERTOWN AREA SENIOR HIGH SCHOOL MONTHLY PROGRESS REPORT No. 10 November / December 2015 Construction Manager D Huy Engineering, Inc. Architect
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More information4.1.3 Project Manual
4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01
More informationHinsdale Township High School District 86 Referendum Project Listing April 2, Approved
Hinsdale Township High School District 86 Referendum Project Listing April 2, 2019 - Approved 1-12-2019 Project Category and Description Central South Total Security Replace Intercom System Install a completely
More informationAl Behrman Elementary School
Mulberry Street Al Behrman Elementary School Relocate reception and principal s office to be adjacent to main entrance doors; provide secure entrance sequence and increase transparency to the exterior
More informationMadison School District. Strategic Five-Year Facility Maintenance Plan
Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationCOMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry
GREATER ALBANY PUBLIC SCHOOLS Critical Facility Upgrades 2018 Progress Update Investments in Existing Capital Assets: Safe Warm - Dry Critical Facility Upgrades Goals Investing in existing capital assets
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationWARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y 2 0 1 8 Agenda Overview of the Bond 2018 Work 2 Agenda Overview of the Bond 2018 Work 3 Overview of Bond Why Now? Interest rates remain at historic
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope
More informationBOND CONSTRUCTION UPDATE
BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationOverbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %
8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior
More informationMOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS
MOORESTOWN HIGH SCHOOL 06/22/15 08/28/15 Security vestibule at main entrance and transportation office; replacement of selected exterior doors; access controls at exterior doors 06/22/15 12/31/15 Upgrade
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls
More informationMidland Public Schools
Midland Public Schools Facility Renewal Proposal A 12-15 Year Plan February 24, 2015 Bond Proposal Why is this needed? Age of facilities Energy inefficiency School safety and security issues Aging bus
More informationDAVIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationSHEPHERD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFEASIBILITY STUDY SEPTEMBER 1 8,
FEASIBILITY STUDY SEPTEMBER 1 8, 2 0 1 2 OVERVIEW PAUL SWARTZ, AIA, PP PRINCIPAL-IN-CHARGE JIM PETRO, AIA PROJECT ARCHITECT STUART J. HEISEY, PE MECHANICAL ENGINEER LEED AP BD+C The last feasibility study
More informationReferendum Implementation
SPACE Net Gain (new) Classrooms Claremont = +47 Hillcrest & Elizabeth = +20 Utilization Gain SGS = +25 at 6-8 MS level SAFETY Annex Connection To Franklin Park Repair Parking Lots, Sidewalks & Outdoor
More informationBiddeford School Department
Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6
More informationFrost Technical Center
Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera
More informationAUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT. WORK IN PROGRESS August 2011
AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS August 2011 Masonry and Concrete Improvements Status: Contractor: Pioneer Masonry Restoration Inc., Seattle WA. Construction
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationBALLOU SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE
More information3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades $300,000 C. Tilden Entrance Upgrades $50,000 D. Door and Glass Improvements $500,000 E. Alert Systems $800,000
More informationSTUART-HOBSON MIDDLE SCHOOL
INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationUpdate on FCPS Construction/Renovation Projects. August 2016
Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:
More informationLLANO ISD SCHOOL BOARD MEETING. January 2016
LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationNorth Tonawanda City School District
N.T. CAPIT AL I MPROVE MENT PROJECT North Tonawanda City School District Vincent J. Vecchiarella Superintendent of Schools Special Edition April 2008 $48 Million Capital Project at NO COST to the Taxpayers
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationCold Spring School District
Cold Spring School District Deferred Maintenance & Capital Facilities Program July 9, 2018 Deferred Maintenance District Fund 14 School Facilities Maintenance in General Three types of maintenance projects
More informationRadnor Township School District CAPITAL IMPROVEMENT PLAN COSTS
Radnor Township School District CAPITAL IMPROVEMENT PLAN COSTS 2015-16 Budget 2015-16 Actual 2016-17 2017-18 2018-19 2019-20 ADM 112,000 22,815 116,000 112,000 110,000 60,000 TRANS 370,000 355,180 431,800
More information: I EJM /~. / $ 20, $ 1,183, $ 373, $ 373, Janua!Y 3, 2012 Page 1 of 4 SUMMER 2012 PROJECTS ALSIP SCHOOL DISTRICT NO.
I : I 1. Asbestos Abatement Project: SUMMER 2012 PROJECTS /~. / Janua!Y 3, 2012 Page 1 of 4 a. Prairie Junior High School Asbestos Abatement for Plumbing 35,000.00 b. Stony Creek School Asbestos Abatement
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationGFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1
GFW Schools Task Force Meeting 1/23/19 1 AGENDA 1. Introductions 2. Review of building tours Primary Needs 3. Review Space Programs 4. Review Concept Options District and Facility needs 5. Review Concept
More informationBOYERTOWN AREA SENIOR HIGH SCHOOL
BOYERTOWN AREA SCHOOL DISTRICT ADDITIONS & RENOVATIONS To BOYERTOWN AREA SENIOR HIGH SCHOOL MONTHLY PROGRESS REPORT No. 11 January 2016 Construction Manager D Huy Engineering, Inc. Architect KCBA Architects
More informationAuxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.
Capital Projects Status Report October 1, 2018 Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah 84119 P 801.974.8365 F 801.974.8375 Current Projects 1. Edison construction update: In Area
More informationCOOLIDGE SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationCoos Bay Best Bond Cost Breakdowns
Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationSOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED
SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EPENSES FORM UPDATED 12-14-18 This information is a summary of multiple reports which assist District Leadership in maintaining a to do list for
More informationFacility Improvements
CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation
More informationSANTA ROSA JUNIOR COLLEGE
EXPENDITURES Eligible Bond Program Costs 1,363,848 451,690 622,090 74,757 10,295 85,053 2,522,681 RENOVATION AND MODERNIZATION Upgrade classrooms, laboratories, support service space at all locations 298,139
More informationMONTHLY PROGRESS REPORT
MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report
More informationPATTERSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1945 BUILDING AREA 78,300 SF CURRENT PROGRAM CAPACITY 368 ENROLLMENT 2008 463 WARD 8 PROPOSED PROGRAM CAPACITY 500 Site Plan PATTERSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More information*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.
SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial
More informationFacilities Feasibility Study Laurence G. Paquin Building Condition Assessment
Summary of Findings The Laurence G. Paquin Building Facility located at 2200 SINCLAIR LANE in Baltimore, Maryland, was built in 1975. It comprises 65,666 gross square feet. The total current deficiencies
More informationLa Conner School District
hoarch.com La Conner School District Capital Bond Planning Meeting 4 - Master Plan Options / Budget Estimates July 18th, 2012 4010 Lake Washington Blvd, NE, Suite 320 Kirkland, Wa 425 828 8948 Agenda Meeting
More informationWARREN CONSOLIDATED SCHOOLS
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE May 2017 Agenda Overview of Bond 2017 Work Next Steps 2 Overview of Bond Why Now? Interest rates remain at historic lows, allowing $134.5 million to
More informationHealth Life Safety Survey and Master Facilities Plan
Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master
More informationBOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project
BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the
More information6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After
Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationWATKINS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFACILITY COMPONENTS - ELEMENTARY SCHOOL
SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking
More informationLECKIE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationNALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationCapital Projects Progress Report. January Presented by
Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428
More informationLegend. ANTICIPATED LONG-TERM CAPITAL PROJECTS: PER SCHOOL through
Legend Highlights Priority 1 Projects Highlights the projects identified through the building conditions survey that have been included in the 2017-18 through 2022-2023 Long Term Capital Plan ANTICIPATED
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationCity High Middle School pre-design recommendations. March 29, 2017
City High Middle School pre-design recommendations March 29, 2017 City High Middle School table of contents 2 3 4 5 6 7 8 9 10 11 12 13 table of contents project description and purpose existing systems
More informationEdmonton Public School District No. 7
EXECUTIVE SUMMARY 1. Overall Impressions The 1966 non-core school has actively pursued an ongoing maintenance and upgrade program to improve a number of past problem areas within the school. Extensive
More informationSECTION 6 PRELIMINARY PROGRAM AND BUDGET
SECTION 6 PRELIMINARY PROGRAM AND BUDGET Lake Mills Area School District Preliminary Space Program for a 500 student functional capacity High School 13-Jan-15 Occupants # rooms SF/room Total SF Additional
More information1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %
8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior
More informationUpdate on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationNew Hall High School Project Summary Report to the Board of Education June 3, 2015
New Hall High School Project Summary Report to the Board of Education June 3, 2015 Trade Procurement Status: Bid Package# Description Status Firm 1 Mass Excavation Awarded John Pohar & Sons 2 Concrete
More informationLOVEJOY Independent School District
Long-Range Facilities Planning Projected Bond Sale Project Series 2014 Series 2018 Series 2023 Total (2013 Cost) (with 6% Yearly Inflation) 1. Hart Elementary $ 6,716,424 $ 6,168,802 $ 1,200,121 $ - $
More informationAppendix J - Custom Uniformat for EDU Migration
Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationDeficiency ID Qty UoM Priority. K Play Area Requires Impact Resistant Material Ea. 2
School and Site Level Deficiencies Site K Play Area Requires Impact Resistant Material 1320 1 Ea. 2 Exterior Basketball Goals Are Damaged And Require Replacement 1322 1 Ea. 4 Bus drop-off area does not
More informationSchedule of Values Cruise Terminal 2 Expansion
Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General
More information2016 BOND INFORMATION
2016 BOND INFORMATION This publication is provided as a public service by the offices of Operations and Maintenance, Communications and Financial Services. www.svvsd.org @svvsd 395 South Pratt Parkway,
More informationSOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************
SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 6 O DATE: December 5-7, 2017 ****************************************************************************** SUBJECT USD Dakota Dome Renovation
More informationBoard Work Session Feasibility Study. January 9, 2017
Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking
More informationDOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.
DOCUMENT 00 43 36B EXPANDED SUBCONTRACTORS LISTING TO: CLARK COUNTY SCHOOL DISTRICT hereinafter called "Owner" FROM: ~AU;)"''"-' Oeve\,(;p,-...e,.,,... IA... t. ~o~ t>.m..e>u,i-j (Print Company Name) Pe-Mo1..,,,-t,:;>.tJ
More informationLUFacilities Policy Service Level Agreement v1.1
PURPOSE The Service Level Agreement (SLA) for University provides a detailed list of services offered by the LU Department. The SLA identifies which services are funded by the approved Lehigh University
More information