BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

Size: px
Start display at page:

Download "BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project"

Transcription

1 BOYERTOWN AREA SCHOOL DISTRICT February 28, 2017

2 Junior High West Project Overview On June 16, 2015 the board of school directors authorized KCBA Architects to begin the design development stage of the Junior High West project. At the May 24, 2016 facilities meeting, administration along with representatives from Fidevia and KCBA presented a $13,079,158 base project with an additional $2,323,706 in soft costs and $1,844,809 in contingency. * Additionally, the board was presented with additional items to consider for the project.

3 Junior High West Project Overview On May 31, 2016 the facilities committee was presented with the final project scope with the additions that were made at the previous meeting. That evening, the board approved the project scope and directed administration to include it for final approval at the June 14, 2016 board meeting. The budget presented included the following: Original Base Project: $13,079,158 Additional Options Selected: $ 3,594,871 Soft Costs: $ 2,323,706 Contingency: $ 1,844,809 Final Estimated Project Cost: $20,842,574 On June 14, 2016, the board of school directors approved the presented project scope.

4 OVERALL BUILDING UPGRADES 1. New HVAC System w/ AC Includes both gyms Replacing boilers 2. New electrical system Lighting (LED) Power Switch Gear 3. Data systems upgrade 4. Security Upgrades Expand camera system Security hardware 5. Paint walls 6. Replace acoustical ceilings

5 1963 GENERAL BUILDING UPGRADES Replace windows Asbestos abatement & new floor tile Replace doors & hardware General ADA renovations Replace casework Replace student lockers Replace stage rigging Upgrade stage lighting system 1963 SPECIFIC BUILDING UPGRADES 1998 SPECIFIC UPGRADES

6 Specific Building Upgrades Entrance & office suite New addition Toilet room renovations STEM fit-out Art room fit-out Science lab upgrades Locker room renovations

7 SITE WORK Resolve pedestrian/vehicle conflict at front entry Reconstruct deteriorated asphalt Paving Replace deteriorated curbs Replace deteriorated sidewalks Replace site lights with LED

8 DESIGN DEVELOPMENT ESTIMATE Estimate Preparation Fidevia Construction Management & Consulting Based upon 80+ sheets of drawings Multiple coordination meetings Estimate Summary Construction estimate Soft costs estimate Design development contingency Total project estimate $16,674,059 $ 2,323,706 $ 1,844,809 $20,842,574

9 MIDDLE SCHOOL WEST PROJECT FUNDING Primary Source Amount Amount Purpose Borrowed Received December 2014 BASH General Obligation Bond $30,000,000 $33,000,000 BASH Emmaus Note $15,000,000 $15,000,000 December 2015 BASH General Obligation Bond $15,000,000 $16,500,000 JHW General Obligation Bond $15,000,000 $16,500,000 Total $75,000,000 $81,000,000 BASH Project $60,000,000 Available Funding $21,000,000 Since December of 2014, the district has incurred a debt obligation of $75,000,000 which has yielded a total of $81,000,000 of available funding. Of the $81,000,000, there is still $21,000,000 available to be used for the Junior High West renovation project.

10 MIDDLE SCHOOL WEST PROJECT TIMELINE October 8, 2013 June 16, 2015 July 21, 2015 Sept. 22, 2015 Jan. 19, 2016 Feb. 16, 2016 April 2016 Board approved the submission of PlanCon Parts A & B (Project Justification and Schematic Design) Board approved the start of design development by KCBA Architects Board approved the re-submission of parts A & B to update the documents to include KCBA Architects as the Architect of Record Board approved the authorization to issue requests for proposal for GESA renovation at Junior High West as well as elementary HVAC installation Information shared with the facilities committee related to the fact that JH West cannot be included in the GESA and therefore will require the HVAC addition to be included in the PlanCon renovation project Board approved the authorization to issue requests for proposal for Construction Management Services with a deadline of March 25, 2016 Reviewed Construction Manager Proposals and identifed the successful candidate

11 MIDDLE SCHOOL WEST PROJECT TIMELINE CONT. June 2016 Dec Nov. 29, 2016 Jan. 9, 2017 Jan. 30, 2017 Feb. 14, 2017 Feb. 28, 2017 March 7, 2017 End-March 2017 Aug. 15, 2018 Sept. 15, 2018 Completed design development Completion of Construction Documents Board approved the submission of PlanCon Part F (construction documents) Release construction documents for bidding Phone conference with PDE as a part of the PlanCon Part F process Bid opening Present bids to the Board of School Directors Board approves the bids and PlanCon Part G (project accounting and bids to PDE) Begin construction Substantial completion Final completion

12 Recommended Alternates Replace sidewalks along 2 nd Street $35,000 Resolve pedestrian/vehicle $25,000 conflict in front driveway Replace corridor student lockers $110,000 Replace library carpet $12,000 Replace gym floor $65,000 Replace basketball goals and scoreboard $40,600 Replace stage rigging $20,600 Replace parking lot lights with LED lights $34,000 Mill and overlay north parking lot $125,000 Polish and seal all existing terrazzo floors $140,000

13 Contractor Bid Results General Contractor ER Stubner Mechanical Contractor Matchline Mechanical LLC Electrical Contractor Pagoda Electrical Inc. Plumbing Contractor Jay R. Reynolds Asbestos Abatement Contractor Sargent *price includes recommended alternates Bid Price* $8,405,000 $5,169,000 $2,708,943 $939,900 $197,440 Total $17,420,283

14 Design Estimate to Bid Pricing Comparison May 31 Estimated Bid Pricing Construction Cost $ 16,674,059 $ 17,420,283 Soft Costs $ 2,323,706 $ 2,323,706 Design Development Contingency* (10%) Construction Contingency* (6%) $ 1,844,809 NA NA $ 1,098,585 Total Project Budget $ 20,842,574 $ 20,842,574 *The design development contingency is typically larger than the construction contingency to account for the design decisions that need to be done during the development of construction documents as well as changes in the bidding market.

15 Total Project Budget Summary Project Item Cost Construction Cost $17,420,283 Soft Costs $2,323,706 Contingency (6%) $1,098,585 Total Project Cost $20,842,574

16 Questions

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture FACILITY ASSESSMENT PRESENTATION 11 October 2017 SCHRADERGROUP architecture AGENDA 1. 1 Facility Assessment Review 2. 2 Prioritizing the Scope of Work with Associated Costs 3 Timeline of Work 3. 4 Procurement

More information

BOYERTOWN AREA SENIOR HIGH SCHOOL

BOYERTOWN AREA SENIOR HIGH SCHOOL BOYERTOWN AREA SCHOOL DISTRICT ADDITIONS & RENOVATIONS To BOYERTOWN AREA SENIOR HIGH SCHOOL MONTHLY PROGRESS REPORT No. 10 November / December 2015 Construction Manager D Huy Engineering, Inc. Architect

More information

FEASIBILITY STUDY SEPTEMBER 1 8,

FEASIBILITY STUDY SEPTEMBER 1 8, FEASIBILITY STUDY SEPTEMBER 1 8, 2 0 1 2 OVERVIEW PAUL SWARTZ, AIA, PP PRINCIPAL-IN-CHARGE JIM PETRO, AIA PROJECT ARCHITECT STUART J. HEISEY, PE MECHANICAL ENGINEER LEED AP BD+C The last feasibility study

More information

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current

More information

BOYERTOWN AREA SENIOR HIGH SCHOOL

BOYERTOWN AREA SENIOR HIGH SCHOOL BOYERTOWN AREA SCHOOL DISTRICT ADDITIONS & RENOVATIONS To BOYERTOWN AREA SENIOR HIGH SCHOOL MONTHLY PROGRESS REPORT No. 11 January 2016 Construction Manager D Huy Engineering, Inc. Architect KCBA Architects

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

DENNIS TOWNSHIP FEASIBILITY STUDY

DENNIS TOWNSHIP FEASIBILITY STUDY DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

New Ringgold Middle School. Project Slideshow August 26, 2017

New Ringgold Middle School. Project Slideshow August 26, 2017 New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo

More information

Hampton Township School District High School Feasibility Study. Final Feasibility Study Presentation. VEBH Architects

Hampton Township School District High School Feasibility Study. Final Feasibility Study Presentation. VEBH Architects 2018 High School Feasibility Study Final Feasibility Study Presentation January 28, 2019 1 Study Updates I. Latest HS Concepts for Academic / Wellness Redesign II. Associated Conceptual Construction Costs

More information

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening

More information

Cherry Hill School District Building Project Summary. August 8, 2018

Cherry Hill School District Building Project Summary. August 8, 2018 Cherry Hill School District Building Project Summary August 8, 2018 Progress Update: Bond Referendum 2018 As of August 8, 2018, the Cherry Hill Public School District has not yet received approval from

More information

ROD Grant Round 4 Presentation June 9, 2014

ROD Grant Round 4 Presentation June 9, 2014 ROD rant Round 4 Presentation June 9, 2014 713 Creek Road Bellmawr, NJ 08031 Telephone (856) 396-6200 Facsimile (856) 396-6205 Please visit us on the web at www.garrisonarch.com 2 Agenda NJDOE Application

More information

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.

More information

CENTENNIAL SCHOOL DISTRICT

CENTENNIAL SCHOOL DISTRICT CENTENNIAL SCHOOL DISTRICT Middle School Feasibility Study Project PLANNING STUDY PRESENTATION 24 May 2016 Middle School Master Planning Process 1. Familiarized team with existing middle schools and sites

More information

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. August 2015 Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project

More information

Health Life Safety Survey and Master Facilities Plan

Health Life Safety Survey and Master Facilities Plan Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master

More information

Table of Contents Hampton Dumont Community School District November 5, 2013

Table of Contents Hampton Dumont Community School District November 5, 2013 Table of Contents Hampton Dumont Community School District November 5, 2013 Facility Assessment Overview & Proposed Design Options 1. Option 1 Alleviate Congestion at South Side Elementary Existing Facility

More information

Schematic Design D ecember 2018

Schematic Design D ecember 2018 Hey wor th CUSD #4 - Gymnasium Addition Schematic Design D ecember 2018 Prepare d by: It s more than a school, it s your future. Hey wor th CUSD #4 - Gymnasium Addition Schematic Design D ecember 2018

More information

N o v e m b e r

N o v e m b e r WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why

More information

3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades $300,000 C. Tilden Entrance Upgrades $50,000 D. Door and Glass Improvements $500,000 E. Alert Systems $800,000

More information

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Information Session Agenda Background. Scope of work and why these renovations are important. Project cost. How

More information

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry GREATER ALBANY PUBLIC SCHOOLS Critical Facility Upgrades 2018 Progress Update Investments in Existing Capital Assets: Safe Warm - Dry Critical Facility Upgrades Goals Investing in existing capital assets

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main

More information

HERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School

HERITAGE MIDDLE SCHOOL. Overview: Livingston School District Heritage Middle School HERITAGE MIDDLE SCHOOL Overview: The is located at 20 Foxcroft Drive and consists of a three-story building with Three-Story Classroom and Multi-Purpose Room Additions completed in 2002. The building has

More information

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED

SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EXPENSES FORM UPDATED SOUTH COLONIE CENTRAL SCHOOL DISTRICT FACILITY ESTIMATED EPENSES FORM UPDATED 12-14-18 This information is a summary of multiple reports which assist District Leadership in maintaining a to do list for

More information

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story

More information

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After Contents 1 Program Outline Gymnasium Restrooms Storage rooms IDF 2 Finish Outline Walls Flooring Ceiling Roof 3 MEP Outline Plumbing Mechanical Electrical 4 Communication and Security Guideline Communication

More information

North Allegheny School District

North Allegheny School District North Allegheny School District January 18, 2017 Preparing all students for success in a changing world NAI was last renovated in 1997 Money was set aside during recent bond issue for renovations to occur

More information

Coos Bay Best Bond Cost Breakdowns

Coos Bay Best Bond Cost Breakdowns Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of

More information

Paulsboro Public Schools

Paulsboro Public Schools BOND REFERENDUM PRESENTATION January 27, 2015 713 Creek Road Bellmawr, NJ 08031 Telephone (856) 396-6200 Facsimile (856) 396-6205 Please visit us on the web at www.garrisonarch.com 1 05-12-14 AGENDA NJDOE

More information

PROJECT UPDATE August 28, 2014

PROJECT UPDATE August 28, 2014 PROJECT UPDATE August 28, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

BALLOU SENIOR HIGH SCHOOL

BALLOU SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront

More information

BOND CONSTRUCTION UPDATE

BOND CONSTRUCTION UPDATE BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND

More information

SEATON ELEMENTARY SCHOOL

SEATON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

The Report: Priority 1 thru 5 $ 2,933,064 New Construction $ 6,797,031 Less Redlined Items $ 218,060

The Report: Priority 1 thru 5 $ 2,933,064 New Construction $ 6,797,031 Less Redlined Items $ 218,060 Building Condition Assessment Facilities Feasibility Study 124 - Leonelo H. Gonzalez Elementary Educational Needs $ 6,881,962 Safety & Security Needs $ 532,225 Exterior Needs $ 893,302 Needs $ 471,995

More information

38% 62% Project Funding. TPS Systems and Infrastructure needs

38% 62% Project Funding. TPS Systems and Infrastructure needs TPS Systems and Infrastructure needs Project Funding Roof replacements (BGP, TMS) Plumbing upgrades Boiler replacements Code compliant systems, PA, Fire Alarm, Area of Refuge Concrete repair Floor repair

More information

Project Status Report Property and Finance Committee Meeting August 6, 2013

Project Status Report Property and Finance Committee Meeting August 6, 2013 Westmont Hilltop School District Project Status Report Property and Finance Committee Meeting August 6, 2013 S. Dwight Knouse II, AIA, LEED AP Russell D. Greaser, Project Manager Matthew T. Filan, PE,

More information

Madison School District. Strategic Five-Year Facility Maintenance Plan

Madison School District. Strategic Five-Year Facility Maintenance Plan Madison School District Strategic Five-Year Facility Maintenance Plan 2016 2020 Dear Madison Stakeholder, Throughout the past twenty years, Madison School District has experienced tremendous growth. Since

More information

Biddeford School Department

Biddeford School Department Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6

More information

Smart Bomb w words. Stella Maris Project Update. IBI Group

Smart Bomb w words. Stella Maris Project Update. IBI Group Smart Bomb w words Stella Maris Project Update IBI Group Architectural / Engineering Services Sag Harbor Union Free School District January 28, 2019 Schedule SED Approval Received. Building permit has

More information

Instructional Science Facility Phase I

Instructional Science Facility Phase I Instructional Science Facility Phase I University of Wisconsin La Crosse Campus August 26, 2015 UWL Science Lab Building Phase 1 1 Project Schedule Timeline July Aug Sept Oct Nov Dec Jan Feb Mar Apr May

More information

A Report to the Board of Education: Ten-Year Health/Life Safety Review. February 12, 2018

A Report to the Board of Education: Ten-Year Health/Life Safety Review. February 12, 2018 A Report to the Board of Education: Ten-Year Health/Life Safety Review February 12, 2018 1 Overview of the Ten Year Health Life Safety Survey Process Every ten years, each local school board is required

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

PROJECT UPDATE SEPTEMBER 11, 2014

PROJECT UPDATE SEPTEMBER 11, 2014 PROJECT UPDATE SEPTEMBER 11, 2014 Information shown above was provided to district tax payers and stakeholders prior to May bond election. ELEMENTARY SCHOOL #8 $ 34,000,000 Bond Allocation BOND 2013 PROJECT

More information

WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y

WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y 2 0 1 8 Agenda Overview of the Bond 2018 Work 2 Agenda Overview of the Bond 2018 Work 3 Overview of Bond Why Now? Interest rates remain at historic

More information

Priority 1 Maintenance Projects Total Investment Needed: $54,875,317. Elementary Schools

Priority 1 Maintenance Projects Total Investment Needed: $54,875,317. Elementary Schools Priority 1 Maintenance Projects Total Investment Needed: $54,875,317 Appleton Elementary Elementary Schools Total Priority 1 Need: $1,513,280 * Replace roofing in 3 areas * Add air handling units in cafeteria,

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN GREENWICH PUBLIC SCHOOLS Greenwich, CT November 27, 2017 Addendum to Agenda Item: 2018-2019 SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN Please note edited pages should replace original sheets in

More information

Frost Technical Center

Frost Technical Center Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera

More information

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1 GFW Schools Task Force Meeting 1/23/19 1 AGENDA 1. Introductions 2. Review of building tours Primary Needs 3. Review Space Programs 4. Review Concept Options District and Facility needs 5. Review Concept

More information

Update on FCPS Construction/Renovation Projects. June 2016

Update on FCPS Construction/Renovation Projects. June 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

New Hall High School Project Summary Report to the Board of Education June 3, 2015

New Hall High School Project Summary Report to the Board of Education June 3, 2015 New Hall High School Project Summary Report to the Board of Education June 3, 2015 Trade Procurement Status: Bid Package# Description Status Firm 1 Mass Excavation Awarded John Pohar & Sons 2 Concrete

More information

WATKINS ELEMENTARY SCHOOL

WATKINS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Stevens High School Pre Bond Presentation Claremont, NH

Stevens High School Pre Bond Presentation Claremont, NH Stevens High School Pre Bond Presentation Claremont, NH Existing Conditions Existing Conditions Existing Conditions Existing Conditions Proposed site features New main entry that is ADA accessible New

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation. June 13, 2016

Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation. June 13, 2016 Board Meeting Presentation FEASIBILITY STUDY South Montgomery Community School Corporation June 13, 2016 Schedule/Major Milestones 2015 November December Data Collection Board Meeting- Update 2016 January

More information

DAVIS ELEMENTARY SCHOOL

DAVIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-

More information

CENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program. MONTHLY REPORT March 31, 2009

CENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program. MONTHLY REPORT March 31, 2009 CENTINELA VALLEY UNION HIGH SCHOOL DISTRICT Facilities Planning and Construction Program MONTHLY REPORT March 31, 2009 Construction Management 414 W. 4 th Street, Suite L Santa Ana, CA. 92701 Table of

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

: I EJM /~. / $ 20, $ 1,183, $ 373, $ 373, Janua!Y 3, 2012 Page 1 of 4 SUMMER 2012 PROJECTS ALSIP SCHOOL DISTRICT NO.

: I EJM /~. / $ 20, $ 1,183, $ 373, $ 373, Janua!Y 3, 2012 Page 1 of 4 SUMMER 2012 PROJECTS ALSIP SCHOOL DISTRICT NO. I : I 1. Asbestos Abatement Project: SUMMER 2012 PROJECTS /~. / Janua!Y 3, 2012 Page 1 of 4 a. Prairie Junior High School Asbestos Abatement for Plumbing 35,000.00 b. Stony Creek School Asbestos Abatement

More information

2006 FUSD Bond Information Guide

2006 FUSD Bond Information Guide Message from Superintendent Hickman On behalf of the Flagstaff Unified School District (FUSD) staff and members of the Governing Board, I extend my appreciation to the voters of our community, who have

More information

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District Lemm Elementary Restoring the Heart of the Community Target Dat e: August 2018 March Update Lemm restoration contract awarded to ICI Construction on March 2nd Contractor began mobilization on March 5th

More information

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope Project Scope & Budget Breakdown Mandatory Scope Recommended Additional Scope Wish List Scope Site Plan EXISTING Site Plan PROPOSED First Floor Plan PROPOSED Basement Floor Plan PROPOSED Mandatory Scope

More information

SHEPHERD ELEMENTARY SCHOOL

SHEPHERD ELEMENTARY SCHOOL INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Birmingham Public Schools

Birmingham Public Schools Birmingham Public Schools 2015 BOND ISSUE PROGRAM Project Status Update Tuesday June 5, 2018 Agenda Dashboard Update for Website Summer 2018 Construction Project Preview Summer 2018 Construction Progress

More information

Darlington Area Schools - Building Evaluations

Darlington Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 2, 2012 Darlington Area Schools - Building Evaluations School Name: Brunson-Dargan Observed By: Creed/Carter Principal: Mrs. Ada O Sindab

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

Edmonton Public School District No. 7

Edmonton Public School District No. 7 EXECUTIVE SUMMARY 1. Overall Impressions The 1966 non-core school has actively pursued an ongoing maintenance and upgrade program to improve a number of past problem areas within the school. Extensive

More information

Referendum Implementation

Referendum Implementation SPACE Net Gain (new) Classrooms Claremont = +47 Hillcrest & Elizabeth = +20 Utilization Gain SGS = +25 at 6-8 MS level SAFETY Annex Connection To Franklin Park Repair Parking Lots, Sidewalks & Outdoor

More information

Lisbon School Department. 5 Year Plan-Buildings, Grounds, Equipment, & Technology. April 2016

Lisbon School Department. 5 Year Plan-Buildings, Grounds, Equipment, & Technology. April 2016 April 2016 Following is a list of items that the Lisbon School Department deems necessary for Capital Improvements for the next 5 years. Capital Improvements shall mean any construction project exceeding

More information

Capital Projects Update

Capital Projects Update Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being

More information

Cupertino Union School District

Cupertino Union School District Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

Total Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020

Total Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020 Construction Project Project Project Schools/Projects in 2017 in 2017 Escalation in 2019 in 2020 Arlington High School 8,752,608 12,545,469 Building Additions 5,975,000 8,695,418 12.4% 9,773,649 1,198,608

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Davenport School District - Long Range Facilities Maintenance Plan

Davenport School District - Long Range Facilities Maintenance Plan Re-surface & stripe tennis Courts $42,000 Summer 0f 2009 @ a cost of $38,239 Timeline Within next five years? Projected Cracks repaired with floating system & courts were re-sealed and re-painted Sumer

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent RENOVATION PRELIMINARY DESIGN PRESENTATION The Board of Education of Baltimore County Verletta White, Interim Superintendent AGENDA 2 Project Location General Information Existing Conditions Structural

More information

SCARSDALE PUBLIC SCHOOLS Bond Project Planning Update

SCARSDALE PUBLIC SCHOOLS Bond Project Planning Update SCARSDALE PUBLIC SCHOOLS 2017 Bond Project Planning Update November 6, 2017 2018 Bond Project Scope Review 1) District-wide Improvements 2) Greenacres Spatial 3) Security Vestibules 4) Summary Totals 2017

More information

Pottsgrove School District

Pottsgrove School District Pottsgrove School District Pottsgrove High School Additions/Renovations Project Summary February 7, 2014 Eight East Broad Street Hatfield, PA 19440-2401 215.368.5806 Executive Summary In the summer of

More information

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. December 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Presented November 21, 2013 BEDFORD PUBLIC SCHOOLS. Facility Assessment Report. pmcresa.com

Presented November 21, 2013 BEDFORD PUBLIC SCHOOLS. Facility Assessment Report. pmcresa.com Presented November 21, 2013 BEDFORD PUBLIC SCHOOLS Facility Assessment Report pmcresa.com December 4, 2013 Mr. Mark Kleinhans Superintendent Bedford Public Schools 1623 Sterns Road Bedford, MI 48182 Dear

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance Consent ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance Consent ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance Consent AGENDA ITEM: 7 L DATE: June 27-29, 2017 ****************************************************************************** SUBJECT: FY18 HEFF M&R Projects

More information

SCARSDALE PUBLIC SCHOOLS Bond Project Planning

SCARSDALE PUBLIC SCHOOLS Bond Project Planning SCARSDALE PUBLIC SCHOOLS 2017 Bond Project Planning October 23, 2017 2017 Bond Project Planning - Overview 1) December 2014 Bond (2013-2014) Work in this bond included for Heathcote, Edgewood, Middle School,

More information

Chino Valley Unified School District Monthly Construction Update

Chino Valley Unified School District Monthly Construction Update h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:

More information

Stella Maris School Renovation Project

Stella Maris School Renovation Project Stella Maris School Renovation Project Project Update Smart Bomb w words AGENDA Agenda Building Projects for Stella Maris Early Education Center- Scope and Cost: Stella Maris Capital Improvements Project

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

Work Performed Please see the attached list of Construction Codes and mark all that your company typically performs

Work Performed Please see the attached list of Construction Codes and mark all that your company typically performs SUBCONTRACTOR PROFESSIONAL SERVICES PREQUALIFICATION FORM Prequalification Form will NOT be accepted unless completed in its entirety. Business Information Company Name: Primary Address 1: Primary Address

More information

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...

More information

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS

BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS January 9, 2017 SUMMARY OF OCTOBER 17 TH PRESENTATION 1. Five-Year Capital Facilities Plans & 15-year History 2. 2016-2020

More information

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment Summary of Findings The Matthew A. Henson ES Facility located at 1600 N. Payson Street in Baltimore, Maryland, was built in 1964. It comprises 75,228 gross square feet. The total current deficiencies for

More information

Capital Projects Progress Report. September Presented by

Capital Projects Progress Report. September Presented by Capital Projects Progress Report September 2018 Presented by October 5, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York

More information

Naperville Public Library. Parking Lot Work Naper Blvd. Library & 95 th St. Library

Naperville Public Library. Parking Lot Work Naper Blvd. Library & 95 th St. Library Naperville Public Library Request for Pricing Parking Lot Work Naper Blvd. Library & 95 th St. Library Submission Date/Time: May 31, 2018, at 10:00 a.m. CST Place: Nichols Library-Board Room 200 West Jefferson

More information