1 5 YEAR CAPITAL IMPROVEMENT PROGRAM 329

2 City of Hermosa Beach Department of Public Works Capital Improvement Program For Fiscal Years Thru PROJECT NAME FY FY16-17 FY FY FY UNFUNDED AMOUNT TOTALS STREET AND HIGHWAY IMPROVEMENTS 330 CIP Street Improvements CIP Street Improvements 2 CIP Gould Avenue (from Manahttan Ave. to PCH) CIP PCH/Aviation Beautification Project CIP Opticom GPS Pre-Emption System CIP PCH Traffic Improvements CIP Bicycle Sharrows Installation CIP th Street Improvements Traffic Calming Program SUBTOTAL 749, ,468 1,018,000 1,025,000 1,021,000 1,016,000 1,000,000 4,062,000 5,829,468 67, , , ,450 1,300,000 44,440,000 45,740, , , , ,975 20,000 20, , , ,000 1,040,000 50,000 50,000 3,530,893 2,800,000 1,021,000 1,016,000 1,000,000 50,436,705 54,717,066 SEWER/STORM DRAIN IMPROVEMENTS CIP Sewer Improvements - Various Locations CIP Sewer Rehabilitation Project Stormwater/Urban Run-off Diversion Project SUBTOTAL 104, ,975 5,500,000 5,500,000 11,000,000 10,000,000 10,000,000 5,604, ,500, ,000,000 21,104,975 PARKS IMPROVEMENTS CIP Lawn Bowling Green Complex CIP South Playground Improvement CIP Citywide Park Master Plan CIP Clark Field Energy Efficient Electrical Upgrades - Phase II SUBTOTAL 60,000 60, , , ,853 15,308,147 15,452, , ,000 1,202, ,308,147 16,510,939 1 Detail sheets for all projects with amounts are included only in the section and are not included in the 5 Year CIP section 2 Project will be assigned a new CIP number for each subsequent year

3 City of Hermosa Beach Department of Public Works Capital Improvement Program For Fiscal Years Thru PROJECT NAME FY FY16-17 FY FY FY UNFUNDED AMOUNT TOTALS PUBLIC BUILDINGS AND GROUNDS IMPROVEMENTS 331 CIP Fire Station Renovation & Upgrades CIP Downtown Strategic Plan Implementation CIP Police Facilities Improvements CIP New Corporate Yard Facility CIP Fire Department Tower Demolition CIP Municipal Solar Facility Plan and Installations CIP Community Center General Improvements Phase III 2 CIP City Facilities ADA Transition Plan & Improvements CIP Citywide Energy Conservation Upgrades CIP City Right of Way ADA Improvements CIP Municipal Pier Structure Repairs - Phase II CIP Municipal Pier Structure Repairs - Phase III 2 CIP Surf Memorial CIP Comprehensive City Facilities Master Plan CIP LED Lights for Lot D CIP Community Center, Plaza, and Park Improvements City Hall General Improvements CNG Fueling Station Community Center General Improvements Community Center Theatre Upgrade Fire Station Replacement Police Building General Improvement SUBTOTAL ANNUAL PROJECT COST TOTALS 154, , ,832 4,600,000 4,847, , ,000 50,000 18,500,000 50, , ,000 50,000 50,000 50,000 90,000 90, ,000 50,000 50, , , , , , , , , , , , , , , , , , , , ,067 95,000 95,000 16,500 16,500 69,688 69,688 7,200,000 7,200, , ,000 29,200,000 29,200,000 6,200,000 6,200,000 6,750,000 6,750,000 7,800,000 7,800,000 2,373, , , , ,000 82,185,000 66,058,007 12,711, ,929, ,390,987 1 Detail sheets for all projects with amounts are included only in the section and are not included in the 5 Year CIP section 2 Project will be assigned a new CIP number for each subsequent year

4 FISCAL YEAR CATEGORY: Street and Highway Improvements PROJECT NO./TITLE: CIP Opticom GPS Pre-Emption System The Opticom GPS System consists of components that will be installed on all traffic signals in the city and on all the fire units. Once installation is complete, the system will work as follows: 1. Using a global network of GPS satellites, Opticom GPS System vehicle equipment calculates vehicle speed, direction, and longitude and latitude information. 2. Intersection equipment is programmed with an approach map to define corridors for priority control activity. 3. As the vehicle enters the intersection s radio range, it sends updated speed, position and identification information, as well as turn signal status, every second. 4. The Opticom GPS System intersection equipment sends the priority request to the Opticom GPS Phase Selector in the controller cabinet, which requests a green light through normal controller functions. 5. The system recognizes the activated turn signal and relays the priority call forward to the next appropriate intersection. 6. All of the activity can be tracked remotely by traffic management personnel. This project is being coordinated with Manhattan Beach (the requested amount is Hermosa s portion). The two Beach Cities experience very heavy traffic conditions. The Opticom GPS System improves travel time by sequencing traffic signals to green for fire/paramedic units responding to emergencies. The two fire departments are working together to install the same system. STATUS: Opticom project begins in 2015 to be completed by GPS Intersection Antennas $30, M Cards $30, Card Rack $3, Installation Cable $1, M Vehicle Kit $28,000 Clamp for Antennae 605 Vehicle Installation $4,800 Intersection Installation 11,000 PROJECT TOTAL: $109,705 TOTAL FY CIP FUNDING: None 332

5 CATEGORY: Street and Highway Improvements PROJECT NO./TITLE: Traffic Calming Program The purpose of this project is to develop a Traffic Calming Program that addresses neighborhood traffic safety concerns. The development of the program will require partnering with citizens and/or community groups to become actively involved in the development of traffic calming strategies. The goal of the Traffic Calming Program is to improve the quality of life within residential neighborhoods by identifying traffic problems and to find acceptable and appropriate solutions. The main objectives of the program will be to reduce the speed of vehicle traffic, promote other forms of non-motorized transportation, reduce cutthrough traffic, minimize the negative effects of automobile travel, create attractive streets, and to improve the safety and convenience of pedestrians and cyclists. STATUS: Engineering $50,000 PROJECT TOTAL: $50,000 TOTAL FY CIP FUNDING: None 333

6 CATEGORY: Sewer/Storm Drain Improvements PROJECT NO./TITLE: Stormwater/Urban Run-off Diversion Project Design and construction of a stormwater/urban run-off diversion system(s). Project diverts urban run-off and limited stormwater from three-existing major storm drain networks into underground infiltration basins and/or fields in the Greenbelt and adjacent feasible sites. Project meets the City s NPDES permit requirements to improve receiving bodies water quality. Estimated Indirect Costs including, Engineering, permits, testing & inspection, construction management: $1,950,000 Construction: $8,050,000 PROJECT TOTAL: $10,000,000 TOTAL FY CIP FUNDING: None 334

7 CATEGORY: Public Buildings and Ground Improvements PROJECT NO./TITLE: City Hall General Improvement Renovations to the existing 23,000 SF City Hall including interior improvements, department relocations, efficiency improvements, exterior improvements, potential seismic upgrades, ADA upgrades, and site improvements. The City Hall/Civic Center was constructed circa Although, renovations of the architectural floor plan were performed in 2001, the facility is in need of major architectural, energy-efficient, electromechanical and seismic upgrades. Renovation of the facility is recommended to extend the service life of the building. STATUS: Estimated Indirect costs including Space Planning, Architecture, Engineering, Permits, Testing & Inspection, and Construction Management $1,450,000 Estimated Construction $5,750,000 PROJECT TOTAL: $7,200,000 TOTAL FY CIP FUNDING: None 335

8 CATEGORY: Public Building and Grounds PROJECT NO./TITLE: CNG Fueling Station This project proposes installing a Compressed Natural Gas (CNG) Fueling Station to support City Fleet natural gas vehicles and potentially for public use. It consists of installing fueling station pumps and an above ground natural gas tank.. This project will be a step forward and a key component to support the City s Clean Fleet Policy and Action Plan. The station will support current and future City CNG fueled fleet vehicles. STATUS: FY 15-16: Research available funding sources. Preliminary Engineering Engineering Construction $20,000 $75,000 $750,000 PROJECT TOTAL: $845,000 TOTAL FY CIP FUNDING: None 336

9 CATEGORY: Public Buildings and Ground Improvements PROJECT NO./TITLE: Community Center General Improvement Renovations to the existing 33,814 SF Community Center including interior, exterior, potential seismic upgrades, ADA upgrades, and site improvements. The Community Center is approximately 75-years and in need of architectural, seismic and numerous code requirement upgrades. Improvement will include renovating the center to a modern energy efficient multipurpose facility. Renovation of the facility is recommended to extend the service life of the building. Estimated Indirect costs including: Space Planning, Architecture, Engineering, Permits, Testing & Inspection, and Construction Management $7,300,000 Estimated Construction $21,900,000 PROJECT TOTAL: $29,200,000 TOTAL FY CIP FUNDING: None 337

10 CATEGORY: Public Buildings and Ground Improvements PROJECT NO./TITLE: Community Center Theater Upgrades Renovation of the existing 20,200 SF Theater including new ceilings, acoustics, stage upgrades, lighting, audio, seating, pre-function areas, and overall finish upgrades. The Theatre received minor improvements that included energy efficient lighting and ADA upgrades. The facility is approximately 75-years and is in need of major exterior and interior improvements to serve as a modern Community Entertainment Center. Estimated Indirect costs including Space Planning, Architecture, Engineering, Permits, Testing & Inspection, and Construction Management $1,550,000 Estimated Construction $4,650,000 PROJECT TOTAL: $6,200,000 TOTAL FY CIP FUNDING: None 338

11 CATEGORY: Public Buildings and Ground Improvements PROJECT NO./TITLE: Fire Station Replacement Design and construction of a new 10,000 SF, 3-Bay Fire Station located potentially off-site from the existing Civic Center. Fire Station will be designed and constructed according to the Essential Services Act. Fire Station will include Apparatus Bays, Kitchen, Administration, Dormitories, Emergency Generator, Fueling Island, and all supporting services. The Facility was constructed circa 1959 and is in need of major architectural, seismic and numerous code requirement upgrades as described in the RRM Design Group report. This report determined that it will be more cost effective to demolish and rebuild the entire facility. STATUS: Estimated Indirect costs including Space Planning, Architecture, Engineering, Permits, Testing & Inspection, and Construction Management $1,750,000 Estimated Construction $5,000,000 PROJECT TOTAL: $6,750,000 TOTAL FY CIP FUNDING: None 339

12 CATEGORY: Public Buildings and Ground Improvements PROJECT NO./TITLE: Police Building General Improvement Renovations to the existing 15,600 SF Police Building including interior, exterior, potential seismic upgrades, ADA upgrades, and site improvements. Improvements will ensure the upgrades comply with the Essential Services Act of the California Building Code. The Facility was constructed circa 1959 and is in need of architectural, seismic and numerous code requirement upgrades. Improvement will include renovating the building to a modern and efficient law enforcement facility. Renovation of the facility is recommended to extend the service life of the building. STATUS: Estimated indirect costs including Space Planning, Architecture, Engineering, Permits, Testing & Inspection, and Construction Management $1,560,000 Estimated Construction $6,240,000 PROJECT TOTAL: $7,800,000 TOTAL FY CIP FUNDING: None 340

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session Long-Term Capital Improvement Funding Plan March 18, 2014 City Council Study Session Overview Long-term 10 year view to know what s planned Project Overview Focus on FY 2014-15 and FY 2015-16 Funding Plan

More information

This is the title of the proposed project. A CIP contract or project number will be assigned to the projects as funding is established.

This is the title of the proposed project. A CIP contract or project number will be assigned to the projects as funding is established. BUILDING PROJECTS PROJECT DESCRIPTIONS The CIP includes a general list of projects scheduled during each of the five years of the program, followed by detailed project sheets arranged by project category,

More information

City of Victoria Aging Infrastructure Review and Assessment

City of Victoria Aging Infrastructure Review and Assessment City of Victoria Aging Infrastructure Review and Assessment Presented by Engineering and Public Works Department February 2012 Presentation Outline Infrastructure Definition and Examples City of Victoria

More information

Engineering Department

Engineering Department Engineering Department Stormwater Mission: To provide for the efficient and effective cleaning and repair of the stormwater collection system and implement the federally mandated Stormwater Pollution Prevention

More information

MAINTENANCE & OPERATIONS

MAINTENANCE & OPERATIONS MAINTENANCE & OPERATIONS Department Goal The goal of the Maintenance & Operations Department for the - Capital Improvement Budget/Program is to maintain, refurbish or upgrade municipal facilities to maximize

More information

Engineering Department Stormwater

Engineering Department Stormwater Engineering Department Stormwater Prepared by:, Director Assisted by: Mary Phelps Verle Holland Steven Tam Andy Yeung Gina De la Torre Serenity Cummings Engineering Department Stormwater Mission: To provide

More information

Public Works Department Five Year Capital Improvement Plan FY PROPOSED

Public Works Department Five Year Capital Improvement Plan FY PROPOSED Public Works Department Five Year Capital Improvement Plan FY 2019-2023 PROPOSED Capital Improvement Plan Summary STREET DIVISION PROJECTS 141 Asphalt Sidewalk Replacement Program Funding Source Adopted

More information

Administration Building Needs Assessment

Administration Building Needs Assessment Town Hall Meeting with the Habersham County Board of Commissioners Administration Building Needs Assessment JUNE 13, 2016 Detailed Evaluation Performed in 2015 Engineering Evaluation Site/Civil Architectural

More information

Capital Improvement Summary by Fund

Capital Improvement Summary by Fund Capital Improvement Summary by Fund Central Services Fund Desciption F Y 2017 F Y 2018 F Y 2019 F Y 2020 F Y 2021 Total 2017-2021 Cost Revenues: Pay as you Go 1,000,000 1,000,000 Vehicle Leases - 1,250,000

More information

NEPA THE NATIONAL ENVIRONMENTAL PROTECTION ACT CEQA THE CALIFORNIA ENVIRONMENTAL QUALITY ACT

NEPA THE NATIONAL ENVIRONMENTAL PROTECTION ACT CEQA THE CALIFORNIA ENVIRONMENTAL QUALITY ACT NEPA THE NATIONAL ENVIRONMENTAL PROTECTION ACT Enacted in 1969 to provide review of Federal projects to identify significant impacts. NEPA applies to a project that requires discretionary actions by a

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

Civil District Court Parish of New Orleans. Image Courtesy of EDR MA. Renovation & Utilization Feasibility

Civil District Court Parish of New Orleans. Image Courtesy of EDR MA. Renovation & Utilization Feasibility Civil District Court Parish of New Orleans Image Courtesy of EDR MA Renovation & Utilization Feasibility Challenges with Courthouse Design Courthouse Space Standards and Requirements Charity Hospital Building

More information

SECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT

SECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT SECTION 7 Public Infrastructure, Facilities and Services 8Chapter 8 INFRASTRUCTURE ELEMENT INF-2 CHAPTER 8 Infrastructure Element INTRODUCTION Cupertino s public infrastructure works in tandem with the

More information

Town of Andover Department of Municipal Services Facility

Town of Andover Department of Municipal Services Facility Town of Andover Department of Municipal Services Facility July 2014 Project History Original facility constructed in 1965 Lewis Street DPW Yard Master Plan Study completed in 2000 Lewis Street Site West

More information

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program STAFF REPORT DATE: November 14, 2017 TO: Bryan Montgomery, City Manager Approved and Forwarded to the City Council FROM: SUBJECT: Kevin Rohani, P.E. Public Works Director/City Engineer FY 2017/18 First

More information

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project

More information

General Plan Draft Outline

General Plan Draft Outline General Plan Draft Outline Contents General Plan... 1 Draft Outline... 1 PART I: GENERAL PLAN OVERVIEW... 3 Chapter 1: Introduction and General Plan User Guide... 3 What Is a General Plan?... 3 About Envision

More information

PERMITTED USES: Within the B-4 Planned Arterial Business District the following uses are permitted:

PERMITTED USES: Within the B-4 Planned Arterial Business District the following uses are permitted: 6.17 - B-4 PLANNED ARTERIAL BUSINESS DISTRICT 6.17.1 INTENT: The B-4, Planned Arterial Business District is designed to encourage a unified development approach along the major highway corridors. The principal

More information

ENGINEERING DEPARTMENT

ENGINEERING DEPARTMENT ENGINEERING DEPARTMENT ADMINISTRATION Engineering Services/ Traffic and Transportation Engineering Services/ Stormwater Engineering Services/ Utilities Engineering Technical Services Engineering Field

More information

Woodlake General Plan Draft Environmental Impact Report

Woodlake General Plan Draft Environmental Impact Report 5.0 UNAVOIDABLE ADVERSE ENVIRONMENTAL EFFECTS The following potential adverse environmental effects appear to be unavoidable if the Woodlake General Plan is implemented, even if certain mitigation measures

More information

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system.

Foundations for the new pumps have been constructed. Contractor is constructing emergency connection to LADWP system. Water Projects Pump Station No. 8 Rehabilitation (CIP No. 0796) Scope of Work: Rehabilitation of aging mechanical equipment and the associated piping at the existing pump station adjacent to Reservoir

More information

PLATINUM LEVEL AWARD WINNER. City of Downey Sustainability Best Practices Activities

PLATINUM LEVEL AWARD WINNER. City of Downey Sustainability Best Practices Activities PLATINUM LEVEL AWARD WINNER City of Downey Sustainability Best Practices Activities About This Document This document tracks and shares local agency best practice activities completed and counted as part

More information

ENGINEERING DEPARTMENT

ENGINEERING DEPARTMENT ENGINEERING DEPARTMENT Additional information about the Engineering Department may be obtained by calling Tim Bailey, P.E., Director of Engineering, at (919) 469-4030, through email at tim.bailey@townofcary.org

More information

Zone 1 Report to the Zone Commissioners By Jason Uhley, General Manager-Chief Engineer November 2018

Zone 1 Report to the Zone Commissioners By Jason Uhley, General Manager-Chief Engineer November 2018 Zone 1 Report to the Zone Commissioners By Jason Uhley, General Manager-Chief Engineer November 2018 Current/Recent Construction Projects Monroe MDP - Monroe Channel Stage 4 (1-8-00071-04) Construction

More information

Montague Proposed DPW FAQ

Montague Proposed DPW FAQ Montague Proposed DPW FAQ Prepared by the Public Works Facility Planning Committee 1. What does the DPW do for the community? Montague DPW touches the lives of residents every day by maintaining the Town

More information

2012 ASSET MANAGEMENT UPDATE

2012 ASSET MANAGEMENT UPDATE 2012 ASSET MANAGEMENT UPDATE Stewardship of Current Infrastructure and Facilities City of Nanaimo 2012 Asset Management Update City of Nanaimo 2012 Asset Management Update Executive Summary The required

More information

Capital Investment Program CAPITAL BUDGET

Capital Investment Program CAPITAL BUDGET Capital Investment Program 2012-2014 CAPITAL BUDGET Table of Contents Page CAPITAL BUDGET FUNDING ALLOCATION 3 S Asset Management Projects Roadway Maintenance 4 Downtown ADA Ramp Upgrades 5 Storm Drain

More information

1 April 8, 2015 Public Hearing

1 April 8, 2015 Public Hearing 1 April 8, 2015 Public Hearing APPLICANT: PROPERTY OWNER: CONTE ACQUISITIONS, LLC STAFF PLANNER: Kevin Kemp REQUEST: Conditional Use Permit (Craft Brewery) ADDRESS / DESCRIPTION: 1805 Laskin Road, Suite

More information

sewers ANd storm drains Storm Drain Under Construction, 1916

sewers ANd storm drains Storm Drain Under Construction, 1916 sewers ANd storm drains Storm Drain Under Construction, 1916 A d o p t e d C A p I t A L I M p R o V e M e N t p R o G R A M F I s C A L Y e A R 2 1 9 FY 219-223 Capital Improvement Program FY 218 FY 219

More information

Construction Look Ahead February 2018

Construction Look Ahead February 2018 To our 9 th and Colorado redevelopment neighbors: Construction Look Ahead February 2018 Block 7South Exterior Bridge walkway between Block 7 South building and the existing Parking Garage the installation

More information

CITY OF ELMHURST SUSTAINABILITY POLICY

CITY OF ELMHURST SUSTAINABILITY POLICY CITY OF ELMHURST SUSTAINABILITY POLICY INTRODUCTION Across America, citizens are involved in environmental initiatives and concerned about improving local and global environmental quality. Concerns about

More information

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS 2018-19 THROUGH 2022-23 Project Number Stg No. Project

More information

Project Information. Nominations of Artists. University of Houston

Project Information. Nominations of Artists. University of Houston UNIVERSITY OF HOUSTON SYSTEM SYSTEM WIDE ART ACQUISTION COMMITTEE AGENDA ITEM ITEM: UH University Center Transformation Project Artwork-Artists Nominations DATE PREVIOUSLY SUBMITTED: NA SUMMARY: Nominations

More information

Request for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2

Request for Proposals No ; Various On-call Professional Design and Engineering Services Addendum No. 1 Page 2 Addendum Number 1 Request for Proposals No. 17-001 Various On-call Professional Design and Engineering Services To all prospective firms under specifications for Request for Proposals (RFP) No. 17-001,

More information

Traffic. Community Planning and Development. Traffic Administration Traffic Engineering. Paint and Signs

Traffic. Community Planning and Development. Traffic Administration Traffic Engineering. Paint and Signs Community Planning and Development Administration 101-7710 Transportation Planning 101-7720 Engineering Paint and Signs 141-7750 Communications 101-7740 Data 141-7760 Signals 141-7770 Safety and Signals

More information

SECTION 10 - HIGHWAY COMMERCIAL ZONE (C2) REGULATIONS

SECTION 10 - HIGHWAY COMMERCIAL ZONE (C2) REGULATIONS SECTION 10 - HIGHWAY COMMERCIAL ZONE (C2) REGULATIONS 10.1 GENERAL USE REGULATIONS 10.1.1 PERMITTED USES No land, building, or structures shall be used or erected in the Highway Commercial Zone (C2) except

More information

South Bay Metro Green Line Extension

South Bay Metro Green Line Extension Meeting Agenda Project overview and update Recap of the Scoping Meetings Progress on the project alternative and proposed station locations Meeting Schedule 6:00 Open House 6:30 Presentation 7:15 Public

More information

6.13 Utilities and Service Systems

6.13 Utilities and Service Systems 6.13 6.13.1 Introduction This section describes impacts for utilities and service systems that would result from construction and operation of the CEQA Alternatives. 6.13.2 Regulatory Setting There are

More information

EIGHT PLANNING FACTORS

EIGHT PLANNING FACTORS EIGHT PLANNING FACTORS Under the provisions of SAFETEA-LU, all Metropolitan Planning Organizations (MPOs) are required to consider eight (8) broad planning factors in the development of multi-modal transportation

More information

Welcome Center, New Student Services, and Career and Employment Services

Welcome Center, New Student Services, and Career and Employment Services Architectural Program Welcome Center, New Student Services, and Career and Employment Services East Memorial Stadium Renovation May 2014 Prepared By Table of Contents Introduction.... 1 Competitive Market....

More information

Capital Improvement Projects Fiscal Year PRadopted

Capital Improvement Projects Fiscal Year PRadopted Capital Improvement Projects Fiscal Year 2015-2017 2017 PRadopted CITY OF OAKLAND FY 2015-17 ADOPTED CAPITAL IMPROVEMENT PROGRAM Mayor Libby Schaaf Members of the City Council Lynette Gibson McElhaney

More information

3 CUMULATIVE METHODS AND PROJECTS

3 CUMULATIVE METHODS AND PROJECTS 3 CUMULATIVE METHODS AND PROJECTS 3.1 INTRODUCTION This chapter is an introduction to the cumulative impacts analysis contained within each respective environmental impact category subsection of Chapter

More information

/ Policy Number: Policy Name: Capital Planning and Development Processes Definitions

/ Policy Number: Policy Name: Capital Planning and Development Processes Definitions Page 1 7-101 Definition A. Alternative Construction Delivery Methods: Building Delivery Processes that vary from the more standard Design-Bid-Build model. These may include Construction Manager-At-Risk

More information

VILLAGE OF DOWNERS GROVE REPORT FOR THE VILLAGE COUNCIL MEETING NOVEMBER 28, 2006 AGENDA

VILLAGE OF DOWNERS GROVE REPORT FOR THE VILLAGE COUNCIL MEETING NOVEMBER 28, 2006 AGENDA VILLAGE OF DOWNERS GROVE REPORT FOR THE VILLAGE COUNCIL MEETING NOVEMBER 28, 2006 AGENDA ITEM SUBJECT: TYPE: SUBMITTED BY: Fire Station 2 Design Development Plans Resolution Ordinance Motion Discussion

More information

ARTICLE IV. ZONING DISTRICTS DIVISION 9. M-X MIXED USE DISTRICT. (2) Ensure sensitivity to the surrounding neighborhood;

ARTICLE IV. ZONING DISTRICTS DIVISION 9. M-X MIXED USE DISTRICT. (2) Ensure sensitivity to the surrounding neighborhood; ARTICLE IV. ZONING DISTRICTS 36-263 DIVISION 9. M-X MIXED USE DISTRICT Sec. 36-261. Purpose. The purposes of the M-X mixed use district are to: (1) Provide areas for mixed use development that are carefully

More information

CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MAY 3, 2017

CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MAY 3, 2017 TO: FROM: CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MAY 3, 2017 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER SUBJECT:

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

Transportation and Utilities

Transportation and Utilities 4 Section 4 Transportation and Utilities 4.0 Introduction Transportation and utility systems are essential to accommodate and support development proposed in the Future Land Use Map. The following pages

More information

MIRACOSTA COMMUNITY COLLEGE DISTRICT

MIRACOSTA COMMUNITY COLLEGE DISTRICT MIRACOSTA COMMUNITY COLLEGE DISTRICT FACILITIES MASTER PLAN UPDATE MARCH 16, 2016 PHASE TWO: Board of Trustees Presentation 1 Facilities Master Plan Update: Cost Community Learning Center San Elijo Campus

More information

- FACT SHEET - THE GUIDING PRINCIPLES

- FACT SHEET - THE GUIDING PRINCIPLES THE GUIDING PRINCIPLES The General Plan begins with seven ideas that together create a vision for the City s future. When the City approved the General Plan in 1994, these idea were dubbed the Seven Guiding

More information

SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS

SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS 14.1 GENERAL USE REGULATIONS 14.1.1 PERMITTED USES No land, building, or structures shall be used or erected in the General Industrial Zone (M2) unless

More information

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH

DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS THROUGH RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT DESIGN & CONSTRUCTION BUDGET AND FIVE YEAR CIP PROJECT SUMMARY - ZONE 1 FISCAL YEARS 2017-18 THROUGH 2021-22 Project Number Stg No. Project

More information

11.0 NOISE ELEMENT NOISE ELEMENT THE CITY OF AMERICAN CANYON GENERAL PLAN 11-1

11.0 NOISE ELEMENT NOISE ELEMENT THE CITY OF AMERICAN CANYON GENERAL PLAN 11-1 NOISE ELEMENT 11-1 STATUTORY REQUIREMENTS Government Code Section 65302(f) states the following: The General Plan shall include a noise element which shall identify and appraise noise problems in the community.

More information

PUBLIC WORKS. Public Works

PUBLIC WORKS. Public Works PUBLIC WORKS Department includes CIP and Production, Operations, Transportation, and Finance divisions Overall, 66 positions eliminated in FY2010 Details on the two largest divisions follow; representative

More information

Preliminary Five-Year Capital Improvement Program. City of Mesa, Arizona. for the. Fiscal Years 2012/ /2017

Preliminary Five-Year Capital Improvement Program. City of Mesa, Arizona. for the. Fiscal Years 2012/ /2017 Preliminary Five-Year Capital Improvement Program City of Mesa, Arizona for the Fiscal Years 2012/2013-2016/2017 Mayor Scott Smith Councilmembers Scott Somers Vice Mayor Dave Richins District 6 District

More information

Capital Facilities Element

Capital Facilities Element Capital Facilities Element Purpose The Growth Management Act requires cities to prepare a capital facilities element consisting of: 1. An inventory of current capital facilities owned by public entities,

More information

Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update

Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update February 24, 2015 Overview Wastewater Collection System Customer Base 16,276 SFR 1,968 MFR 1,364 COM/IND

More information

Philip A. Ginsburg, General Manager Dawn Kamalanathan, Director of Planning and Capital Division

Philip A. Ginsburg, General Manager Dawn Kamalanathan, Director of Planning and Capital Division Date November 1, 2017 To: Through: From: Recreation and Park Commission Capital Committee Philip A. Ginsburg, General Manager Dawn Kamalanathan, Director of Planning and Capital Division Brett Desmarais,

More information

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT FY 15-20 CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2-

More information

A UCC Building permit is not required for the exceptions listed below for COMMERCIAL application: (403.42): Building construction for the following:

A UCC Building permit is not required for the exceptions listed below for COMMERCIAL application: (403.42): Building construction for the following: New buildings or renovations to existing buildings for which an application for a permit was made to the Department or a municipality before April 9, 2004. New buildings or renovations to existing buildings

More information

Capital Improvement Budget Discussion. October 23, 2017

Capital Improvement Budget Discussion. October 23, 2017 Capital Improvement Budget Discussion October 23, 2017 Agenda 1. Summary of 2018 Capital Improvement Program 2. Process of determining projects 3. CIP project discussion 4. Modification to existing sidewalk

More information

Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009

Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009 Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009 FINAL 1 Table of Contents Slide Number Executive Summary 3 Understanding the Outcomes Report 5 Measuring results

More information

Rapid Transit in Winnipeg. Winnipeg TOD Summit November 17, 2014

Rapid Transit in Winnipeg. Winnipeg TOD Summit November 17, 2014 Rapid Transit in Winnipeg Winnipeg TOD Summit November 17, 2014 Presentation Overview Rapid Transit (RT) in Winnipeg What is RT? What are our RT plans? Near term Longer term Comments re: TOD OurWinnipeg

More information

CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA

CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA Our Mission: To provide a supplemental financial mechanism for the revitalization of Crystal City, Potomac Yard, and Pentagon

More information

Green Line extension Project Fall 2009

Green Line extension Project Fall 2009 Introduction The Massachusetts Department of Transportation (MassDOT) is proposing to extend the Green Line to improve transit service, mobility, and regional access for residents and visitors of Cambridge,

More information

CHAPTER 3 DISTRICTS AND REGULATIONS ARTICLE DISTRICTS

CHAPTER 3 DISTRICTS AND REGULATIONS ARTICLE DISTRICTS CHAPTER 3 DISTRICTS AND REGULATIONS ARTICLE 1317 - DISTRICTS 1317. 11 HIGHWAY COMMERCIAL 1317.11.1 INTENT The Highway Commercial district is coded to provide for the location of auto-oriented and auto-dependent

More information

CP-3. Planned Commercial District-3. Section Use. Buildings and lots in the CP-3 district may be used for the following purposes:

CP-3. Planned Commercial District-3. Section Use. Buildings and lots in the CP-3 district may be used for the following purposes: CP-3 Planned Commercial District-3 Section 1510. Purpose. The CP-3 district, to be known as a "Planned Commercial District," is intended to preserve neighborhood-scaled commercial uses and to promote new

More information

These findings and the Mitigation Monitoring Program ( MMP, attached as Exhibit B) address only the impacts of the West Branch Library Project.

These findings and the Mitigation Monitoring Program ( MMP, attached as Exhibit B) address only the impacts of the West Branch Library Project. Page 1 of 6 FINDINGS OF FACT REGARDING ENVIRONMENTAL IMPACTS, MITIGATION MEASURES, ALTERNATIVES AND OVERRIDING CONSIDERATIONS FOR THE BERKELEY WEST BRANCH LIBRARY PROJECT INTRODUCTION: The Berkeley Branch

More information

City of Rohnert Park When Permits are Required

City of Rohnert Park When Permits are Required Permits are required as provided below based on the applicable code governing the trades involved in a building project. In some instances more than one trade may be involved in a project so be sure to

More information

Riverton City s 2013 Strategic Plan Report Card

Riverton City s 2013 Strategic Plan Report Card Riverton City s 2013 Strategic Plan Report Card Priority: Economic Development Facilitate Balanced Economic Development with an emphasis on: 1. Development of the Western Commercial District (WCD) Economic

More information

3.0 PROJECT DESCRIPTION

3.0 PROJECT DESCRIPTION 3.0.1 REGIONAL SETTING Hermosa Beach is located in southwest Los Angeles County and encompasses 1.4 square miles, or 979 acres, with 1.8 miles of coastline along Santa Monica Bay. Manhattan Beach borders

More information

2016/2017 Organizational Chart. Effective 7/1/2016 Budgeted 29 FTE Positions Budgeted 1 Part-Time Position Budgeted 4 Intern Positions

2016/2017 Organizational Chart. Effective 7/1/2016 Budgeted 29 FTE Positions Budgeted 1 Part-Time Position Budgeted 4 Intern Positions 2016/2017 Organizational Chart Effective 7/1/2016 ed 29 FTE Positions ed 1 Part-Time Position ed 4 Intern Positions Ricardo Sandoval Administrative Secretary (1) Transportation/Land Development Project

More information

Revenues and expenditures increase based on the tax district increase due to increases in real estate assessments in CY 2016 compared to CY 2015.

Revenues and expenditures increase based on the tax district increase due to increases in real estate assessments in CY 2016 compared to CY 2015. CRYSTAL CITY, POTOMAC YARD, AND PENTAGON CITY TAX INCREMENT FINANCING AREA Our Mission: To provide a supplemental financial mechanism for the revitalization of Crystal City, Potomac Yard, and Pentagon

More information

City of Valdosta Land Development Regulations

City of Valdosta Land Development Regulations Section 210-3 Urban Commercial Corridor Overlay District (A) Purpose. The purposes of the Urban Commercial Corridor Overlay District are to: (1) Promote the general health, safety, and welfare of the community.

More information

Table of Contents. LASAN CLARTS OPF Abbreviated Feasibility Report November 17, Page 1 of 10

Table of Contents. LASAN CLARTS OPF Abbreviated Feasibility Report November 17, Page 1 of 10 Table of Contents I. Executive Summary... 2 II. Project Concept and Goals... 3 III. Waste Stream Composition... 3 IV. Project Data... 4 V. Existing Facility... 5 VI. Location of OPF on the CLARTS Site...

More information

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted:

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted: 6.24 - MX - MIXED USE DISTRICT 6.24.1 INTENT: The purpose of the MX Mixed Use District is to accommodate the development of a wide-range of residential and compatible non-residential uses (including major

More information

RURAL CENTER COMMUNITY ROLE COUNCIL ROLE RURAL CENTER ALL COMMUNITIES

RURAL CENTER COMMUNITY ROLE COUNCIL ROLE RURAL CENTER ALL COMMUNITIES Orderly and Efficient Land Use Align land use, development patterns, and infrastructure to make the best use of public and private investment. Plan for forecasted population and household growth at overall

More information

OMNITRANS. Established in 1976 Serving the San Bernardino Valley. 16 Million Passengers Per Year Three Facilities Fleet. 15 Cities 480 Square Miles

OMNITRANS. Established in 1976 Serving the San Bernardino Valley. 16 Million Passengers Per Year Three Facilities Fleet. 15 Cities 480 Square Miles OMNITRANS Established in 1976 Serving the San Bernardino Valley 15 Cities 480 Square Miles 16 Million Passengers Per Year Three Facilities Fleet 167 Standard Coaches 14 Articulated sbx Coaches 105 Paratransit

More information

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 WORK LEGEND OVERALL WORK TO BOTH BUILDINGS 1 2 3 4 Existing corridors will receive new

More information

Georgetown Water Storage Class Environmental Assessment Study

Georgetown Water Storage Class Environmental Assessment Study Georgetown Water Storage Class Environmental Assessment Study Public Information Centre Cedarvale Community Centre 181-185 Main Street South Thursday, September 4th, 2008 6:30 p.m. 8:30 p.m. Why are we

More information

1255 Eastshore Highway

1255 Eastshore Highway Z O N I N G A D J U S T M E N T S B O A R D S t a f f R e p o r t 1255 Eastshore Highway FOR BOARD ACTION MARCH 23, 2017 Use Permit #ZP2016-0224 to establish automobile repair services in an existing 38,000

More information

FORT MONMOUTH PLANNING, ENGINEERING, ARCHITECTURAL & ENVIRONMENTAL CONSULTING SERVICES OVERVIEW

FORT MONMOUTH PLANNING, ENGINEERING, ARCHITECTURAL & ENVIRONMENTAL CONSULTING SERVICES OVERVIEW FORT MONMOUTH PLANNING, ENGINEERING, ARCHITECTURAL & ENVIRONMENTAL CONSULTING SERVICES OVERVIEW D A N S C H N E P F, P R I N C I P A L F R A N K T Y B O R O S K I, D I R E C T O R, F E D E R A L P R A

More information

environment Natural Systems

environment Natural Systems environment Natural Systems Wheaton will grow greener through redevelopment by creating a sustainable community that conserves energy and uses roofs and green spaces to filter stormwater and purify air.

More information

# Teckler Boulevard Self Storage Preliminary PUD Project Review for Planning and Zoning Commission

# Teckler Boulevard Self Storage Preliminary PUD Project Review for Planning and Zoning Commission #2014-13 Teckler Boulevard Self Storage Preliminary PUD Project Review for Planning and Zoning Commission Meeting Date: March 19, 2014 and April 2, 2014 Requests: 1. Special Use Permit to allow a Preliminary

More information

REHABILITATION PACKAGE 4-a

REHABILITATION PACKAGE 4-a 4-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 4-a Rehab option 4-a is a rehabilitation package whereby all spans of the existing steel truss structure would be rehabilitated and strengthened.

More information

Article 7. COMMERCIAL AND MIXED USE ZONES

Article 7. COMMERCIAL AND MIXED USE ZONES COMMERCIAL AND MIXED USE ZONES 24-21 Article 7. COMMERCIAL AND MIXED USE ZONES Sections: 24-21 Purpose of the Commercial and Mixed Use s 24-22 Land Use Regulations for Commercial and Mixed Use s 24-23

More information

OTHER CEQA CONSIDERATIONS

OTHER CEQA CONSIDERATIONS Chapter 5 OTHER CEQA CONSIDERATIONS CEQA Guidelines Section 15128 requires that an EIR disclose the reasons why various possible environmental effects of a proposed project are found not to be significant

More information

EJ Industrial Spine BOA Nomination Study

EJ Industrial Spine BOA Nomination Study A. Selecting Priority Sites Section V. Redevelopment of Priority Sites Section IV of this Nomination Study presents a summary of the analyses of the Study Area and market conditions affecting the E-J BOA

More information

CIBL Categories of Work Classification Guidelines

CIBL Categories of Work Classification Guidelines 11 May 06 CIBL Categories of Work Classification Guidelines The following is provided as guidelines for classifying design, engineering and construction work. Project examples are provided for reference

More information

Sec. 12. District and intent -- C-G, General Commercial District.

Sec. 12. District and intent -- C-G, General Commercial District. The provisions of this district are intended to apply to an area intended to be developed and preserved as a major commercial center serving the commercial needs of the community and region. The type of

More information

Uniform Construction Code

Uniform Construction Code Uniform Construction Code When the UCC Requires Permits and Inspections (A Zoning Certificate may be required even though the project does not require a UCC Building Permit.) As a general rule, the UCC

More information

What is a stormwater utility fee?

What is a stormwater utility fee? What is a stormwater utility fee? A stormwater utility fee is similar to a water or sewer utility fee. In essence, customers pay a fee to convey stormwater from their properties. The City of Goodlettsville

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

BUILDING REUSE STUDY HENRY T. WING SCHOOL PUBLIC FORUM #2

BUILDING REUSE STUDY HENRY T. WING SCHOOL PUBLIC FORUM #2 BUILDING REUSE HENRY T. WING SCHOOL PUBLIC FORUM #2 SANDWICH, MA JULY 13, 2015 Site Plan AREA UNDERSTANDI TOTAL GSF = 103,275 NG THE DATES CONSTRUCTED DATE CONSTRUCTED UNDERSTANDI NG THE INITIAL 7 OPTIONS

More information

TEMPLATE A P S S I T E M A S T E R P L A N N I N G

TEMPLATE A P S S I T E M A S T E R P L A N N I N G TEMPLATE A P S S I T E M A S T E R P L A N N I N G Albuquerque Public Schools Department of Facilities Design + Construction January 1, 2017 1 INTRODUCTION & OVERVIEW Albuquerque Public Schools develops

More information

ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10

ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10 ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10 Section 7-10.1 Off Street Parking. Off-street parking spaces, with proper access from a street, alley or driveway shall be provided in all districts

More information

REPORT ACCOMPANYING THE FIRST AMENDMENT TO THE ASTOR-WEST URBAN RENEWAL PLAN. City of Astoria November 21, 2016

REPORT ACCOMPANYING THE FIRST AMENDMENT TO THE ASTOR-WEST URBAN RENEWAL PLAN. City of Astoria November 21, 2016 REPORT ACCOMPANYING THE FIRST AMENDMENT TO THE ASTOR-WEST URBAN RENEWAL PLAN City of Astoria November 21, 2016 Prepared by Elaine Howard Consulting, LLC Elaine Howard Scott Vanden Bos Tiberius Solutions,

More information

SUSTAINABILITY ACTION PLAN 7/14/2009 DRAFT FRAMEWORK

SUSTAINABILITY ACTION PLAN 7/14/2009 DRAFT FRAMEWORK SUSTAINABILITY ACTION PLAN 7/14/2009 DRAFT FRAMEWORK Sustainability Action Plan DRAFT FRAMEWORK Table of Contents INTRODUCTION... 1 What is Sustainability and Why Pursue It?... 1 Purpose and Scope... 1

More information

BASIC DESIGN PRINCIPLES

BASIC DESIGN PRINCIPLES Chapter 1: Purpose of Design Guidelines C H A P T E R 1 BASIC DESIGN PRINCIPLES Historic preservation is an established part of city planning in Anderson. Over the past decades, the community has initiated

More information

SECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT

SECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT SECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT 5.1 - Introduction In accordance with CEQA Guidelines Section 15126.6, this Draft Subsequent Environmental Impact Report (DSEIR) contains a comparative impact

More information