1 Design Techniques for Stream Restoration: Working in Arid and Semi-Arid Climates with Hydromodification Concerns Presented By: Tory R. Walker, PE, CFM, LEED GA September 30, 2014

2 Brief Overview Short History Lesson MS4 (Stormwater) Permit as a Catalyst Regional Factors & Influencers Case Studies

3 Short History Lesson 5 water quality 1 natural 4 Detention & MPDs 2 ditches 3 channels

4 What Are You Looking At? from Stormwater Magazine

5 MS4 Permits as a Catalyst Recent focus on problem of hydromodification Intention is commendable, science is lacking Science has been imported Approach is over simplified Conservative assumptions Result is a convoluted set of rules with little resemblance to reality You can t legislate how nature should behave!

6 Factors & Influencers Precipitation data and geologic data have influenced urban development Consider how MS4 permits should be written to properly address the impacts of hydromodification Present a more effective approach that is scientifically robust & practical MUST UNDERSTAND THESE FACTORS OR ELSE!

7 The Fatal Conceit (coined by Friedrich Hayek) To summarize - the belief that people can manipulate and control complex systems that they don t understand and have good outcomes. Invariably, when they do that, they not only do not have good outcomes, they get all kinds of unintended consequences. Complex systems, by definition, are systems that no one of us can fully understand. Each of us sees only a part of it, and yet when we manipulate it, we continue to be surprised by the results.

8 Climatic Influence The Mediterranean climate in Southern California entices people there to live, work, and play

9 BUT Devastation from occasional winter storms Flooding and mudslides Erosion of channels Sediment deposition downstream Damage to utilities, roads and bridges Loss of life and property Infrequency causes short term memory!

10 Climatic Influence- Seasonal 7.00 Seasonal Precipitation in Oceanside (cm) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 60% 2%

11 Climatic Influence- Long Term Variation

12 Climatic Influence SoCal climatic patterns do not represent most of the U.S.

13 yet the majority of LID and hydromodification management tools have been developed & applied elsewhere, including: Computer Simulation Models & Studies Stream restoration tools & techniques

14 # of days of Rainfall per Year Rainfall Distribution Typical Distributions of Annual Precipitation in Days per Year S. Coastal Vancouver, BC 60 San Diego LIGHT HEAVY EXTREME

15 % of Runoff Rainfall Distribution Typical Distributions of Annual Precipitation as Percentages S. Coastal Vancouver, BC San Diego LIGHT HEAVY EXTREME

16 Climate Vast geographic differences demonstrates need for calibration of continuous simulation hydrologic models LID tools and onsite hydromodification management devices may function differently depending on climate Understand how precipitation infiltrated will behave in soils and underlying geology

17 Geological Influences

18 Urban Environment Established communities have grown around and adapted to environmental conditions and constraints Example: San Diego County currently imports over 80% of its water from outside the County Building and development standards established in recognition of environmental conditions and societal values in the area

19 Building Out an Urban Environment Southern California is largely built out Most desirable land has been developed More challenging (and costly) lands have yet to be developed Some developed land gets redeveloped New development is often adjacent to existing built environment Must carefully consider all potential impacts on both built environment and natural environment

20 Urban Environment & Water Water is still relatively inexpensive and reliable Typical residential water budget is 50% to 60% outside uses Typical landscaping requires 50 inches of irrigation Over-irrigation frequently leads to Slope instability Settlement Mold growth Seepage through foundations Undermining of roads & utilities Now EPA is pushing LID (i.e., infiltration) to reduce hydromodification impacts!

21 Hydromodification Simple Definition: Erosion of waterways and subsequent sediment deposition downstream, often due to modifications in the watershed Examples: Covering the land with impervious surfaces Deprives waterways of sediment Increased runoff volumes, durations, & peaks in those same waterways Flood Control Dams Traps sediment Reduces damaging peak flows & volumes

22 Effects of Urbanization on Hydrology (Peak, Volume, Duration) Disruption of natural water balance Increased flood peaks Increased stormwater runoff More frequent flooding Increased bankfull flows

23 Traditional Response to Hydromodification Impacts addressed by improving (channelizing and hardening) waterways Protecting adjacent lands from periodic flooding Protecting against erosion Often resulting in concrete lining or rock riprap lining Allowing for more adjacent lands to be developed Urban environment encroached upon previously flood-prone lands Habitat was assigned less value by society than potential uses of adjacent lands

24 Hydromodification Degradation Many waterways in Southern California were not improved through the traditional approach Various degrees of degradation resulted Common factors affecting stream degradation include: Percentage and locations of impervious areas within watershed Soils and geology of watershed Sediment sizes within watershed Slope of waterway Time passed since development

25 Oso Creek in San Juan Capistrano

26 Escondido Creek in Escondido

27 Agua Hedionda Creek in Vista

28 Geology Consensus Based Science The Permit FOG Vegetation

29 Hydromodification Myths Common Myths (over-simplification): 1. Precise definition of critical low-flow threshold is fundamental to determine hydromodification impacts 2. A small change in imperviousness of an already heavily altered system will change the erosion response 3. Many heavily altered watersheds and creeks can be restored to natural (pre-columbian) conditions 4. Designing over-sized onsite hydromodification management facilities for new developments may significantly improve current problems

30 Hydromodification and the SoCal MS4 Permit Fails to consider mitigating factors that exist in nature Wetland and riparian vegetation Channel irregularities Ability of many creeks to self-armor Climatic Variation Fails to consider fluvial systems that are in a state of dynamic equilibrium Assumes that critical low-flow threshold is the point at which a natural channel becomes unstable FACT: in Southern California, infrequent episodic events are far more influential!

31 Sediment Transport - Southern California Most sediment is transported during medium to extreme events

32 Sediment Transport - Tijuana River 53% of sediment transported occurs for peak flows larger than Q10 * Typical range valid for non-mediterranean climates is not representative of the optimum range of analysis in Southern California Misguided efforts to tightly control extremely small flows (i.e., 10% of Q 2 ) accomplishes very little of significance Greatly increases size of onsite hydromodification management facilities * 73 years of daily data

33 Sensitivity of an Impacted System Previous studies of natural fluvial systems As little as 3% of impervious area can be sufficient to cause a natural system to begin to degrade or unravel Long term response of fluvial systems to impervious area is not well understood Predictions can be based on similar systems Some systems remain vulnerable (Oso Creek) Some in a state of new dynamic eq. (Escondido Creek) Some in between (needing some level of restoration)

34 Systematic Approach to Hydromodification Management Observe response of fluvial system to previous increase in impervious area over time Study aerial photography and topography GIS analysis HEC-RAS Other fluvial geomorphic tools Fluvial Geomorphic Studies Reasonable Assessments of Vulnerability

35 One Approach to Watershed Rehabilitation Deconstructing urban environment over time Restoration to pre-columbian natural systems All new development needs a zero net impact LID and onsite hydromodification management Existing development would follow suit Required retention of 85 th Percentile runoff Natural condition as a point for comparison If underlying soils unsuitable for infiltration, other LID practices implemented Green roofs; Cisterns and rain barrels REMEMBER FACTORS & INFLUENCERS!

36 A Flawed Approach Society would bear cost of condemning all currently protected properties adjacent to waterways Alternatives will cause pressure to infiltrate against better judgment Displaced homes and businesses would need to relocate (new impacts) Not smart growth

37 A Flawed Approach (cont.) California Environmental Quality Act (CEQA) requires consideration of potential impacts to surrounding land uses, both natural and built Potential impacts Flooding Environmental degradation Impacts to groundwater quality and quantity CEQA checklist addresses groundwater depletion Does not address Increases of infiltration Increases to groundwater levels

38 A Balanced Approach Start with multidiscipline team of experts! Use the best available data, models and tools Rigorous adherence to the scientific method Further develop modeling tools based on local data Application to realities that characterize the Region Climatic Geologic Urban Economic Calibrate parameters

39 MS4 Permit Alternative Compliance Focus on impaired receiving waters rather than onsite LID and hydromodification management Allowing water quality goals to be achieved sooner Establish Water Quality Equivalency (currency) In-lieu fee mechanism (like wetlands program) Numerous stream restoration and rehabilitation projects have been already identified Improves physical, chemical and biological characteristics of waterway

40 Oso Creek Watershed Watershed area is 20 sq. miles, creek is 13.5 miles long From Upper Oso Reservoir, through Mission Viejo, to North San Juan Capistrano Tributary to Trabuco Creek Watershed is highly urbanized, creek is mostly hardened

41 Impaired Area Reach End of hardened channel to Trabuco Creek Within City of San Juan Capistrano Both public and private property Vital infrastructure (roads, railroad, water, sewer) Land use historically agriculture

42 Area Issues Active erosion due to hydromodification (upstream development) Sedimentation downstream Trabuco Creek is critical habitat for Steelhead Trout Loss of natural creek functions Decreased flood capacity downstream Development of private land infeasible Threat to existing infrastructure

43 May 1994

44 June 2002

45 April 2005

46 November 2009

47 March 2011

48 Issues to Identify in Restoration Plan Stabilization of creek bed and banks Re-establishment of natural creek functions Potential groundwater replenishment Protection of adjacent and downstream properties Downstream flood capacity preserved Protection of existing infrastructure, such as railroad and sewer lines

49 Stabilize Creek Bed and Banks

50

51 Re-Establish Natural Creek Functions

52 Groundwater Replenishment

53 Protection of Property

54 Preserve Downstream Flood Capacity Trabuco Creek at San Juan Creek

55

56

57 Conceptual Design Typical Plan View Re-establishment of natural creek profile Creek bed stabilization (grade control) Creek bank stabilization (rock groins)

58 Conceptual Design Typical Profile Re-establishment of Natural Creek Profile

59 Creek Bed Stabilization (Natural Rock Grade Control)

60 Benefits of Grade Control Reduces velocity Reduces bed and bank erosion Promotes sediment buildup Protects existing infrastructure Enhances aquatic biology with riffle pool stream profile Replenishes groundwater Restores bed and bank vegetation Natural attenuation of peak flows

61 Creek Bank Stabilization with Rock Groins Reduces velocity Reduces bank erosion Allows for habitat variation Preserves low flow channel Stabilizes channel bank Plan View Cross Section

62 Agua Hedionda Area Reach About 35 miles north of downtown San Diego Includes portions of Carlsbad, Vista, Oceanside, San Marcos Approximately 31 square miles & 37 linear miles of streams Terminates at the Agua Hedionda Lagoon

63 Agua Hedionda Creek Stable System (circa 1900) High Groundwater Recharge Equilibrium Sediment Transport High Floodplain Function Low Discharge Velocities Dynamic and Broad Riparian Zone Diverse Riparian Habitat Sustainable Vegetation Mosaic Cool Seasonal Aquatic System

64 Agua Hedionda Creek - Present Early Incised System (Present) Depressed Groundwater Table High Groundwater Export Low Groundwater Recharge High Channel Bank Erosion Confined Low Floodplain Function High Discharge Velocities Diminishing Riparian Zone Width Low Diversity Riparian Habitat Poor Riparian Plant Recruitment Cool Seasonal/Perennial Aquatic System

65 Agua Hedionda Creek - Present

66 Agua Hedionda Creek Restoration Project Floodplain Inundation Map Detailed HEC-RAS study Surveyed cross-sections 50 feet apart on average Incorporated hydraulic parameters specific to each cross section Useful for sediment transport analysis Evaluated 2-year, 10-year & 100-year

67 Preliminary Design Proposed Structures 9 grade control structures - 6 larger structures - 3 smaller (riffle) structures

68 Preliminary Design Proposed Structures

69 Preliminary Design Proposed Structures 5 areas of Bank Stabilization Natural stone toe with plantable gabions Natural stone toe to top of bank (2:1 slope) - Requires more room - Many mature trees limit its use

70 Agua Hedionda Creek Mature Incised System (circa 2040) Groundwater Conditions Same High Channel Bank Erosion Confined Low Floodplain Function High Discharge Velocities Diminishing Riparian Zone Width Low Diversity, Narrow Riparian Habitat High Scour Plant Loss Opportunistic Exotic Plant Recruitment Warm Seasonal/Perennial Aquatic System

71 Agua Hedionda Creek Restoration Project Preliminary Design Grade Control Structures

72 QUESTIONS? Tory Walker (760)

Stormwater and LEED. Vancouver LEED User s Group May 27, Craig Kipkie, M.Sc., P.Eng, LEED AP

Stormwater and LEED. Vancouver LEED User s Group May 27, Craig Kipkie, M.Sc., P.Eng, LEED AP Stormwater and LEED Vancouver LEED User s Group May 27, 2005 Craig Kipkie, M.Sc., P.Eng, LEED AP Outline Sustainable Sites 2 Stormwater credits SSc6.1 SSc6.2 Synergies with other Credits Case Study How

More information

South St. Vrain / Hall Meadows Restoration Planning August 20, 2015

South St. Vrain / Hall Meadows Restoration Planning August 20, 2015 South St. Vrain / Hall Meadows Restoration Planning August 20, 2015 Agenda Introductions Purpose & Goals of Meeting Planning Area Master Plan Restoration Planning: Cost Estimates, Grants, Scope, Timeline

More information

A Case for the Design and Modeling of BMP Infiltration and LID Techniques. By: Bob Murdock

A Case for the Design and Modeling of BMP Infiltration and LID Techniques. By: Bob Murdock A Case for the Design and Modeling of BMP Infiltration and LID Techniques 2009 IAFSM Annual Conference 2009 IAFSM Annual Conference By: Bob Murdock Presentation Outline 1. Runoff Reduction (RR) and Low

More information

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports APPENDIX H H.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan

More information

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines Pennsylvania Stormwater Best Management Practices Manual Chapter 3 Stormwater Management Principles and Recommended Control Guidelines 363-0300-002 / December 30, 2006 Chapter 3 Stormwater Management Principles

More information

CHAPTER 7. San Dieguito River Flooding Adaptation

CHAPTER 7. San Dieguito River Flooding Adaptation CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,

More information

FEMA s Mitigation Support for Resiliency: Innovative Drought and Flood Mitigation Projects

FEMA s Mitigation Support for Resiliency: Innovative Drought and Flood Mitigation Projects FEMA s Mitigation Support for Resiliency: Innovative Drought and Flood Mitigation Projects Jordan Williams, CFM Eric Kenney, PE, CFM May 4, 2017 2 Hazard Mitigation Purpose: Research climate resilient

More information

STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC

STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS By Marcus Rubenstein, CPESC WHAT IS STREAM RESTORATION? The return of a stream s lost natural functions, usually resulting from watershed alterations,

More information

Municipal Stormwater Management Planning

Municipal Stormwater Management Planning Municipal Stormwater Management Planning Christopher C. Obropta, Ph.D., P.E. Water Resources Extension Specialist with Rutgers Cooperative Extension Assistant Professor with Department of Environmental

More information

LID & Detention Pond Sizing Tool to Address Hydromodification and Water Quality in Clackamas County

LID & Detention Pond Sizing Tool to Address Hydromodification and Water Quality in Clackamas County LID & Detention Pond Sizing Tool to Address Hydromodification and Water Quality in Clackamas County Leah Johanson, Water Environment Services February 12 th, 2015 Agenda» WES History/Stormwater Standards»

More information

STREAMBANK RESTORATION DESIGN

STREAMBANK RESTORATION DESIGN STREAMBANK RESTORATION DESIGN WITH VINYL SHEET PILE GRADE CONTROL STRUCTURES BRUCE M. PHILLIPS, M.S., P.E. ABSTRACT Grade control structures are an effective channel stabilization measure which can eliminate

More information

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall 6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures

More information

Chapter 1. Introduction

Chapter 1. Introduction Chapter 1 Introduction James P. Heaney, Robert Pitt, and Richard Field Introduction Stormwater has traditionally been considered a nuisance, requiring rapid and complete drainage from areas of habitation.

More information

Review of State and Federal Stormwater Regulations November 2007

Review of State and Federal Stormwater Regulations November 2007 Review of State and Federal Stormwater Regulations November 2007 By: James T. Spaulding, PE, CPESC Joseph M. Ducharme, Jr., PE TTG ENVIRONMENTAL CONSULTANTS, LLC 27 LOCKE ROAD, CONCORD, NH 03301-5301 TELEPHONE:

More information

Implementing Stormwater Management through Split-Flow Drainage Design

Implementing Stormwater Management through Split-Flow Drainage Design Implementing Stormwater Management through Split-Flow Drainage Design Stuart Patton Echols PhD, ASLA, RLA Assistant Professor - Department of Landscape Architecture 210 Engineering Unit D Center for Watershed

More information

Climate Change & Urbanization Have Changed River Flows in Ontario

Climate Change & Urbanization Have Changed River Flows in Ontario Climate Change & Urbanization Have Changed River Flows in Ontario by Trevor Dickinson & Ramesh Rudra Water Resources Engineering University of Guelph Acknowledgements Agencies NSERC, OMAF & Environment

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

Leila Talebi and Robert Pitt. Department of Civil, Construction, and Environmental Engineering, The University of Alabama, P.O. Box , Tuscaloosa

Leila Talebi and Robert Pitt. Department of Civil, Construction, and Environmental Engineering, The University of Alabama, P.O. Box , Tuscaloosa Leila Talebi and Robert Pitt Department of Civil, Construction, and Environmental Engineering, The University of Alabama, P.O. Box 870205, Tuscaloosa May 2012 Global consumption of water increases every

More information

Chapter Three: Discussion and Conclusion. 3.1 Introduction/Overview. 3.2 Countywide Stream Assessment

Chapter Three: Discussion and Conclusion. 3.1 Introduction/Overview. 3.2 Countywide Stream Assessment 3.1 Introduction/Overview The objective of this study was to develop a stream prioritization tool that evaluates stream reaches in terms of the potential water quality improvements that could be achieved

More information

Paraprofessional Training Session 1

Paraprofessional Training Session 1 Paraprofessional Training Session 1 Part 2: Stormwater Basics November 26, 2012 Rutgers University, Cook Campus Christopher C. Obropta, Ph.D., P.E. Extension Specialist in Water Resources Associate Professor

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

New Draft Model BMP Design Manual for San Diego Region

New Draft Model BMP Design Manual for San Diego Region New Draft Model BMP Design Manual for San Diego Region Public Input 2013 Storm Water Permit June 10, 2014 & June 11, 2014 1 Welcome Sign-In Refreshments Sponsor Break Q&A and Input 2 Outline of Presentation

More information

iswm TM Criteria Manual City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June Chapter 1

iswm TM Criteria Manual City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June Chapter 1 City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June 2010... Chapter 1 i CITY OF AZLE iswm CRITERIA MANUAL FOR SITE DEVELOPMENT AND CONSTRUCTION Incorporating the Regional NCTCOG Integrated

More information

Functional Uplift Based Stream Assessment & Restoration Design

Functional Uplift Based Stream Assessment & Restoration Design Functional Uplift Based Stream Assessment & Restoration Design Darcy K.L. Turner Senior Environmental Scientist, Biohabitats, Inc. (dturner@biohabitats.com) Christopher A. Streb, PE Ecological Engineer,

More information

MS4 Programs: Quality, the Other Stormwater Q. Dan Bounds, PE, D.WRE IAFSM March 9, 2017

MS4 Programs: Quality, the Other Stormwater Q. Dan Bounds, PE, D.WRE IAFSM March 9, 2017 MS4 Programs: Quality, the Other Stormwater Q Dan Bounds, PE, D.WRE IAFSM March 9, 2017 MS4 Rule and Regulations MS4 Municipal Separate Storm Sewer System A conveyance or system of conveyances (catch basins,

More information

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS I. POLICY STATEMENT Auburn University's (the University's) "Policy for Natural Resource Management Areas" implements the Campus Master Plan Land Use Element

More information

Chehalis Basin Strategy Programmatic SEPA Draft EIS

Chehalis Basin Strategy Programmatic SEPA Draft EIS Chehalis Basin Strategy Programmatic SEPA Draft EIS History of Flooding I-5 closed in 1990, 1996, 2007, 2009 Five largest flood events occurred since 1986 2 History of Habitat Degradation Harvest has been

More information

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from

More information

New Castle County, DE. Floodplain Regulations

New Castle County, DE. Floodplain Regulations New Castle County, DE Floodplain Regulations John J. Gysling, PE CFM Department of Land Use New Castle County, DE February 26, 2009 Today s Presentation Floodplain Protection and Uses Terms and Definitions

More information

San Antonio Water System Mitchell Lake Constructed Wetlands Below the Dam Preliminary Hydrologic Analysis

San Antonio Water System Mitchell Lake Constructed Wetlands Below the Dam Preliminary Hydrologic Analysis San Antonio Water System enhancement. This recommendation was based on limited water quality data provided by SAWS and using a free-water surface constructed wetland with approximately 112 acres of wetted

More information

Stream Corridor Protection and Adaptive Management Manual. Prepared for the City of Independence, Missouri

Stream Corridor Protection and Adaptive Management Manual. Prepared for the City of Independence, Missouri Stream Corridor Protection and Adaptive Management Manual Prepared for the City of Independence, Missouri Rock Creek Independence, Missouri By Patti Banks Associates and Applied Ecological Services, Inc.

More information

PRENTISS CREEK (SUB-E) KENSINGTON PLACE CONCEPT PLAN VILLAGE OF DOWNERS GROVE, ILLINOIS AUGUST, 2011

PRENTISS CREEK (SUB-E) KENSINGTON PLACE CONCEPT PLAN VILLAGE OF DOWNERS GROVE, ILLINOIS AUGUST, 2011 PRENTISS CREEK (SUB-E) KENSINGTON PLACE CONCEPT PLAN VILLAGE OF DOWNERS GROVE, ILLINOIS AUGUST, 2011 Submitted to: NATHANIEL HAWK, STAFF ENGINEER VILLAGE OF DOWNERS GROVE 5101 WALNUT AVENUE DOWNERS GROVE,

More information

Development of a Stormwater Management Plan for Phase II Small MS4s Insight and Innovation

Development of a Stormwater Management Plan for Phase II Small MS4s Insight and Innovation Development of a Stormwater Management Plan for Phase II Small MS4s Insight and Innovation Ohio Water Environment Association 2016 Technical Conference & Expo June 29, 2016 Objective To create a Stormwater

More information

Green Infrastructure BMPs. Hydrologic Performance Small Storms

Green Infrastructure BMPs. Hydrologic Performance Small Storms Green Infrastructure BMPs Hydrologic Performance Small Storms Clay Emerson, Ph.D. Princeton Hydro Robert G. Traver, Ph.D., PE Department of Civil and Environmental Engineering Villanova University Director,

More information

Urban Hydrology Characteristics and their Influence on Urban Stream Restoration Technology. Presented by:

Urban Hydrology Characteristics and their Influence on Urban Stream Restoration Technology. Presented by: Urban Hydrology Characteristics and their Influence on Urban Stream Restoration Technology Presented by: Michael Clar Ecosite, Inc. James Gracie Brightwater, Inc. BACKGROUND Many streams in urban areas

More information

Lecture 9A: Drainage Basins

Lecture 9A: Drainage Basins GEOG415 Lecture 9A: Drainage Basins 9-1 Drainage basin (watershed, catchment) -Drains surfacewater to a common outlet Drainage divide - how is it defined? Scale effects? - Represents a hydrologic cycle

More information

Water Balance Methodology

Water Balance Methodology Water Balance Methodology Integrating the Site with the Watershed and the Stream March 2012 An initiative under the umbrella of the Water Sustainability Action Plan for British Columbia Water Balance Methodology

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

16.0 Water Quality Management Criteria for Developed Land

16.0 Water Quality Management Criteria for Developed Land October 2003, Revised February 2005 Criteria for Developed Land Page 1 16.1 Introduction 16.0 Water Quality Management Criteria for Developed Land Stormwater quality control is an integral part of any

More information

Good morning, Chairman Yaw, Chairman Yudichak, Chairman Vulakovich, Chairman Costa,

Good morning, Chairman Yaw, Chairman Yudichak, Chairman Vulakovich, Chairman Costa, Testimony of Patrick McDonnell, Secretary Pennsylvania Department of Environmental Protection Joint Hearing on Flooding and Emergency Response Senate Environmental Resources & Energy and Veterans Affairs

More information

Note that the Server provides ArcGIS9 applications with Spatial Analyst and 3D Analyst extensions and ArcHydro tools.

Note that the Server provides ArcGIS9 applications with Spatial Analyst and 3D Analyst extensions and ArcHydro tools. Remote Software This document briefly presents the hydrological and hydraulic modeling software available on the University of Nice Server with Remote Desktop Connection. Note that the Server provides

More information

December 7, Dr. Christine Pomeroy University of Utah Civil and Environmental Engineering MCE Salt Lake City, UT. Dear Dr.

December 7, Dr. Christine Pomeroy University of Utah Civil and Environmental Engineering MCE Salt Lake City, UT. Dear Dr. December 7, 2012 Dr. Christine Pomeroy University of Utah Civil and Environmental Engineering MCE 2042 Salt Lake City, UT 84112 Dear Dr. Pomeroy, The following document is the final report of the Red Butte

More information

6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff

6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff October 2003, Revised February 2005 Chapter 6.0, Runoff Page 1 6.1 Introduction 6.0 Runoff The timing, peak rates of discharge, and volume of stormwater runoff are the primary considerations in the design

More information

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What

More information

Urban Rainwater Harvesting Systems: Promises and Challenges

Urban Rainwater Harvesting Systems: Promises and Challenges TheWaterChannel Webinar #5 Urban Rainwater Harvesting Systems: Promises and Challenges By Vishwanath S Zenrainman@gmail.com www.ircsa.org www.rainwaterclub.org Thanks for coming. The webinar will begin

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Regulatory Requirements

Regulatory Requirements CHAPTER 1 Regulatory Requirements 1.0 Introduction The negative impacts of unmanaged stormwater runoff present a challenge to the City of Philadelphia, including increased runoff pollutant concentrations,

More information

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01 Stormwater Management Studies PDS Engineering Services Division Revised Date: 2/28/08 INTRODUCTION The City of Overland Park requires submission of a stormwater management study as part of the development

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Science Supporting Policy: The Case For Flow Quantity

Science Supporting Policy: The Case For Flow Quantity MassDEP Water Management Program Science Supporting Policy: The Case For Flow Quantity Integrating Water Resources Management UMASS Conference April 8, 2008 Overview Human impact on streamflow and aquatic

More information

Western Washington Hydrology Model (WWHM) Software Introduction. Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington

Western Washington Hydrology Model (WWHM) Software Introduction. Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington Western Washington Hydrology Model (WWHM) Software Introduction Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington Clear Creek Solutions Hydrology Expertise Clear Creek

More information

7/16/2012. Post Construction Best Management Practices (PCBMPs) Article VIII: Post Construction Best Management Practices

7/16/2012. Post Construction Best Management Practices (PCBMPs) Article VIII: Post Construction Best Management Practices Post Construction Best Management Practices (PCBMPs) Article VIII: Post Construction Best Management Practices Presented by Jennifer Boyer DuPage County DEC Includes BMPs intended to provide volume control

More information

Existing Conditions

Existing Conditions 3.1.4 Hydrology and Water Quality This section addresses the potential hydrology, water quality, and stormwater/flooding impacts associated with implementation of The Villages Escondido Country Club Project

More information

Department of the Army Permit Application

Department of the Army Permit Application Department of the Army Permit Application DA File Number U.S. Army Corps of Engineers Honolulu District Date Received by CEPOH-RO Send Completed Application to: Honolulu District, U.S. Army Corps of Engineers

More information

PIMA COUNTY COMPREHENSIVE PLAN CO PIMA COUNTY REGIONAL COMPREHENSIVE PLAN POLICY MAJOR PLAN AMENDMENT

PIMA COUNTY COMPREHENSIVE PLAN CO PIMA COUNTY REGIONAL COMPREHENSIVE PLAN POLICY MAJOR PLAN AMENDMENT PIMA COUNTY COMPREHENSIVE PLAN CO7-07-04 PIMA COUNTY REGIONAL COMPREHENSIVE PLAN POLICY MAJOR PLAN AMENDMENT Arizona law [A.R.S. 11-821(C)(3)] requires: Planning for water resources that addresses: a)

More information

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP)

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP) Elements of the Storm Water Management Plan Storm Water Pollution Prevention Plan (SWPPP) Small Construction Site Storm Water Management Rodney Hendrick Water Quality Specialist LSU Ag Center Plan Requirements

More information

STREAM AND BUFFER AREA PROTECTION/RESTORATION

STREAM AND BUFFER AREA PROTECTION/RESTORATION STREAM AND BUFFER AREA PROTECTION/RESTORATION AMENDMENT OPTIONS TO STRENGTHEN POLICY IN HEADWATERS AREAS DRAFT SUBSEQUENT TO THE JANUARY 25, 2007 MEETING OF THE PLANNING COMMISSION ENVIRONMENT COMMITTEE

More information

M.L. Kavvas, Z. Q. Chen, M. Anderson, L. Liang, N. Ohara Hydrologic Research Laboratory, Civil and Environmental Engineering, UC Davis

M.L. Kavvas, Z. Q. Chen, M. Anderson, L. Liang, N. Ohara Hydrologic Research Laboratory, Civil and Environmental Engineering, UC Davis Assessment of the Restoration Activities on Water Balance and Water Quality at Last Chance Creek Watershed Using Watershed Environmental Hydrology (WEHY) Model M.L. Kavvas, Z. Q. Chen, M. Anderson, L.

More information

What is a stormwater utility fee?

What is a stormwater utility fee? What is a stormwater utility fee? A stormwater utility fee is similar to a water or sewer utility fee. In essence, customers pay a fee to convey stormwater from their properties. The City of Goodlettsville

More information

SECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS

SECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS SECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS Page 4-1 INTRODUCTION 4-3 4-1.01 Applicability of VMCs 14.24, 14.25, 14.26 4-4 4-1.02 Minimum Requirements - Projects Below Threshold

More information

SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN

SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN BACKGROUND INFORMATION Project SWIM? Aquatic Control? Exotic Control? Mitigation Bank? Type No No No No Mitigation Restoration and enhancement Type

More information

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report Prepared for: Cameron McCarthy Landscape Architects LLP

More information

Adjusted Flood Prone Acres

Adjusted Flood Prone Acres Adjusted Flood Prone Acres The flood prone area is defined as the area adjacent to the stream that is innundated or saturated when the elevation of the water is at twice the maximum depth at bankfull stage

More information

TORCH LAKE TOWNSHIP WATER QUALITY ACTION PLAN

TORCH LAKE TOWNSHIP WATER QUALITY ACTION PLAN TORCH LAKE TOWNSHIP WATER QUALITY ACTION PLAN Elk-River-Chain-of-Lakes Gaps Analysis Project The Watershed Center Grand Traverse Bay Tip of the Mitt Watershed Council Michigan Department of Natural Resources

More information

APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY)

APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) Hydromodification design criteria for the North Orange County permit area are based on the 2- yr, 24-hr

More information

Information for File # PRH

Information for File # PRH Information for File # 2016-02602-PRH Applicant Corps Contact Tom Morley Paul Hauser Address 152 Baker Drive, Redwood Falls, MN 56283 E-Mail Paul.R.Hauser@usace.army.mil Phone 651-290-5357 Primary County

More information

Background / Regulatory Requirements

Background / Regulatory Requirements Chapter 2 Background / Regulatory Requirements This Chapter summarizes the impacts of development on stormwater quality and quantity and explains the postconstruction stormwater control requirements for

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Issue paper: Aquifer Water Balance

Issue paper: Aquifer Water Balance Issue paper: Aquifer Water Balance 1. Introduction And Background 1.1. Purpose and Scope The population in Kitsap County has grown rapidly in recent years and is expected to increase substantially in the

More information

In re: Town of Norwich Pool Dam Reconstruction, Stream Alteration Permit Application

In re: Town of Norwich Pool Dam Reconstruction, Stream Alteration Permit Application Agency of Natural Resources October 20, 2015 Neil R. Fulton Town Manager Town of Norwich P.O. Box 376 Norwich, VT 05055 In re: Town of Norwich Pool Dam Reconstruction, Stream Alteration Permit Application

More information

Pennsylvania Stormwater Best Management Practices Manual DRAFT - JANUARY Section 1 Introduction and Purpose of Stormwater BMP Manual

Pennsylvania Stormwater Best Management Practices Manual DRAFT - JANUARY Section 1 Introduction and Purpose of Stormwater BMP Manual Pennsylvania Stormwater Best Management Practices Manual DRAFT - JANUARY 2005 Section 1 Introduction and Purpose of Stormwater BMP Manual This page intentionally left blank. Section 1 Introduction and

More information

Stormwater Volume and Treatment Methods Simplifying the Numbers. IAFSM March 10, Presented by: Tom Powers P.E., CFM, LEED AP, CPESC

Stormwater Volume and Treatment Methods Simplifying the Numbers. IAFSM March 10, Presented by: Tom Powers P.E., CFM, LEED AP, CPESC Stormwater Volume and Treatment Methods Simplifying the Numbers IAFSM March 10, 2011 Presented by: Tom Powers P.E., CFM, LEED AP, CPESC Introduction GOALS: Improve understanding of Rate and Volume (Quantity)

More information

Fort Leonard Wood, Missouri. September 2013

Fort Leonard Wood, Missouri. September 2013 Fort Leonard Wood, Missouri September 2013 1 Presenters Shannon Kelly, Physical Scientist Clean Water Act Program Manager Directorate of Public Works Environmental Division Environmental Compliance Branch

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

VILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN

VILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN VILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN Elk-River-Chain-of-Lakes Gaps Analysis Project The Watershed Center Grand Traverse Bay Tip of the Mitt Watershed Council Michigan Department of Natural Resources

More information

The Impacts of Climate Change on Portland s Water Supply

The Impacts of Climate Change on Portland s Water Supply The Impacts of Climate Change on Portland s Water Supply Richard Palmer and Margaret Hahn University of Washington Department of Civil and Environmental Engineering Joe Dvorak, Dennis Kessler, Azad Mohammadi

More information

REGIONAL STORMWATER CAPTURE & USE FEASIBILITY STUDY TAC MEETING #1 - JULY 18, 2017

REGIONAL STORMWATER CAPTURE & USE FEASIBILITY STUDY TAC MEETING #1 - JULY 18, 2017 REGIONAL STORMWATER CAPTURE & USE FEASIBILITY STUDY TAC MEETING #1 - JULY 18, 2017 Agenda 1. Welcome & Introductions Project Team Technical Advisory Committee (TAC) 2. Study Overview 3. TAC Charter 4.

More information

Characteristics of Land Resources

Characteristics of Land Resources Chapter Chapter 1 Characteristics of Land Resources The geology, soils and topography of Woodford County T he geology, soils and topography of an area are important to the community planning process for

More information

SECTION 11: REGULATORY FLOODWAYS

SECTION 11: REGULATORY FLOODWAYS SECTION 11: REGULATORY FLOODWAYS Contents 11.1. The Floodway... 11-2 11.1.1. The floodway concept... 11-2 11.1.2. Floodway map... 11-2 11.1.3. Floodway permitting... 11-3 11.1.4. Changing the floodway...

More information

Camp Creek: Tackling Erosion and Improving Water Quality in a Recreational Playground Mitchellville, Iowa

Camp Creek: Tackling Erosion and Improving Water Quality in a Recreational Playground Mitchellville, Iowa Camp Creek: Tackling Erosion and Improving Water Quality in a Recreational Playground Mitchellville, Iowa Rachel Conrad, PE, CFM IAFSM March 10 th, 2016 Outline Project Background and Goals Modeling Results

More information

Urban Hydrology and Storm Water Management. iwater_3rd International Event Juan Jose Galan Vivas (Aalto University)

Urban Hydrology and Storm Water Management. iwater_3rd International Event Juan Jose Galan Vivas (Aalto University) Urban Hydrology and Storm Water Management iwater_3rd International Event Juan Jose Galan Vivas (Aalto University) OBJECTIVES of the LECTURE Provide the basics to understand the hydraulic factors and variables

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

SECTION 3 NATURAL RESOURCES

SECTION 3 NATURAL RESOURCES SECTION 3 NATURAL RESOURCES The natural environment plays a large role in planning for future development. Environmental conditions, such as topography, wetlands, floodplains, and water bodies, can often

More information

Plan Formulation Strategies for Ecosystem Restoration Projects

Plan Formulation Strategies for Ecosystem Restoration Projects Plan Formulation Strategies for Ecosystem Restoration Projects Leigh Skaggs Office of Water Project Review PCoP Webinar 1 September 2016 US Army Corps of Engineers A quick recap from our April PCoP webinar

More information

Module 10b: Gutter and Inlet Designs and Multiple Design Objectives

Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of

More information

Project Goals and Scoping

Project Goals and Scoping Prepared for: Boulder County, Colorado Flood Planning & Preliminary Design Services for South St. Vrain Creek Restoration at Hall Ranch and Scoping May 24, 2016 Meeting with General Public In association

More information

San Diego Hydrology Model (SDHM 3.0) Reviewer Workshop. Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington

San Diego Hydrology Model (SDHM 3.0) Reviewer Workshop. Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington San Diego Hydrology Model (SDHM 3.0) Reviewer Workshop Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington Clear Creek Solutions Hydrology Expertise Clear Creek Solutions,

More information

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 Phasing of Meetings April Meeting May Meeting October Review of Tax Day Storm Event and Immediate Actions Taken By City Review of Coordination

More information

Module 2: Basic Stormwater Principles

Module 2: Basic Stormwater Principles Module 2: Basic Stormwater Principles 2a. Overview... 2 Inspectors and stormwater management...2 Definition of stormwater runoff...3 VSMP technical criteria...3 Environmental Site Design...4 Best management

More information

Challenges in Seoul Metropolitan for restoring urban water cycle

Challenges in Seoul Metropolitan for restoring urban water cycle Challenges in Seoul Metropolitan for restoring urban water cycle Reeho Kim*, Seung Won Lee, Jung-hun Lee Daehee Lee, Muhammad Shafique Korea Institute of Civil Engineering and Building Technology 1 Table

More information

the 2001 season. Allison brought high winds and street flooding to Houston, after

the 2001 season. Allison brought high winds and street flooding to Houston, after Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of

More information

L-THIA Online and LID in a watershed investigation

L-THIA Online and LID in a watershed investigation L-THIA Online and LID in a watershed investigation Larry Theller Agricultural and Biological Engineering, Purdue University Great Lakes Sedimentation Workshop Ann Arbor Mi. L-THIA On-line watershed delineation

More information

FREQUENTLY ASKED QUESTIONS: URBAN STREAM RESTORATION BMP. David Wood Chesapeake Stormwater Network. Lisa Fraley-McNeal Center for Watershed Protection

FREQUENTLY ASKED QUESTIONS: URBAN STREAM RESTORATION BMP. David Wood Chesapeake Stormwater Network. Lisa Fraley-McNeal Center for Watershed Protection FREQUENTLY ASKED QUESTIONS: David Wood Chesapeake Stormwater Network URBAN STREAM RESTORATION BMP Lisa Fraley-McNeal Center for Watershed Protection Bill Stack Center for Watershed Protection FREQUENTLY

More information

Water sensitive urban design. Developing design objectives for urban development in South East Queensland

Water sensitive urban design. Developing design objectives for urban development in South East Queensland Water sensitive urban design Developing design objectives for urban development in South East Queensland Version 2-8 November 2007 Contents Contents......... ii Executive Summary............1 1 Introduction.........1

More information

Rainwater Management. Dr. Iftikhar Ahmad. College of Earth and. University of The Punjab Lahore

Rainwater Management. Dr. Iftikhar Ahmad. College of Earth and. University of The Punjab Lahore Rainwater Management in Major Cities of Punjab Dr. Iftikhar Ahmad College of Earth and Environmental Sciences. University of The Punjab Lahore Need For Rainfall Harvesting in Urban Areas of Punjab Groundwater

More information

Project Drainage Report

Project Drainage Report Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater

More information

Lower Columbia River Pile Dike Assessment

Lower Columbia River Pile Dike Assessment Lower Columbia River Pile Dike Assessment David Gorman, PE August 2, 2011 Credits Hans R. Moritz, US Army Corps of Engineers Portland District Carl Kassebaum, AECOM Project Manager AECOM Coastal and Rivers

More information

Santa Margarita Region Hydromodification Management Plan

Santa Margarita Region Hydromodification Management Plan May 2014 Santa Margarita Region Hydromodification Management Plan In compliance with Order No. R9-2010-0016, this HMP has been developed by the Riverside County Copermittees Table of Contents Santa Margarita

More information