1 PART 1 - GENERAL SECTION MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities and controls. B. Specific requirements for Work of each Contract are also indicated in individual Specification Sections and on Drawings. C. Related Requirements: 1. Section "Summary of Work" for the Work covered by Contract Documents, restrictions on use of Project site, phased construction, coordination with occupants, and work restrictions. 2. Section "Temporary Facilities and Controls" for specific requirements for temporary facilities and controls. 3. Refer to each Section in every Division for further explanation of Work Scopes for various Prime Contracts, especially Divisions 03, 07, 11, 13, and 31 where work is specified for more than one Prime Contract DEFINITIONS AND ABBREVIATIONS A. Permanent Enclosure: As determined by Architect, the condition at which roofing is insulated and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures equivalent in weather protection to permanent construction. B. Abbreviations used in this Section relate to various Contracts and Contractors and are as follows: 1. GC: General Construction Contract. 2. HC: Heating, Ventilating, and Air Conditioning (HVAC) Contract. 3. PC: Plumbing Contract. 4. EC: Electrical Contract. Issued for Construction

2 1.03 GENERAL REQUIREMENTS OF CONTRACTS A. Contract Documents consist of project manual, drawings, and modifications as defined within the Conditions of the Contract. Each Contractor shall be responsible for reviewing the entire set of Contract Documents to determine what specification Sections and Drawings are applicable to their Contract work. Perform Contract Work identified anywhere within the Contract Document set. B. Extent of Contract: Unless the Agreement contains a more specific description of the Work of each Contract, requirements indicated on Drawings and in Specification Sections determine which Contract includes a specific element of Project. 1. Unless otherwise indicated, the work described in this Section for each Contract shall be complete systems and assemblies, including products, components, accessories, and installation required by Contract Documents. 2. Trenching, backfilling, and other excavation for work of each Contract shall be the work of that Contract. Refer to various Sections in Division Blocking, backing panels, sleeves, and metal fabrication supports for the work of each Contract shall be the work of that Contract. Refer to Sections and Materials to be installed in concrete and unit masonry walls shall be furnished by each Contract and installed by General Construction Contract. 4. Furnishing of access panels for the work of each Contract shall be the work of that Contract. Installation of access panels in various wall or ceiling construction types shall be the work of General Construction Contract. 5. Concrete equipment pads for the work of each Contract shall be the work of that Contract. Various pad requirements are shown on Drawing S-501. Refer to various Sections in Division Roof-mounted equipment curbs for the work of each Contract shall be furnished by that Contract and installed by General Construction Contract. 7. Painting for the work of each Contract shall be the work of General Construction Contract, unless otherwise indicated. 8. Cutting and Patching: Provided under each Contract for its own work. 9. Through-penetration firestopping for the work of each Contract shall be provided by each Contract. Refer to Section Coordination: Coordinate work of each Contract with other Contracts, including but not limited to scheduling, preparation, layout, and installation of primary and secondary materials of each system. a. Where materials supplied by one Contract are installed under another Contract, furnish to installing Contractor in a timely manner and to prevent construction delays. Issued for Construction

3 b. Where delays occur that impact construction schedule and necessitate liquidated damages, Contractor furnishing delayed materials shall be held culpable. 11. Protection: Each Contract shall be responsible for protecting their own installations. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion. Comply with manufacturer's written instructions for temperature, relative humidity, and other required project conditions. 12. Louvers that are part of mechanical equipment shall be provided by HVAC Contractor, while balance of louvers shall be provided by General Contractor. 13. Lighting pole bases and bolt patterns are the responsibility of General Contractor in construction of precast system. Electrical Contractor shall coordinate with General Contractor for required bolt patterns based on lighting pole base plate configurations. 14. General Contractor shall provide Gates and parking ramp Fare Gates. Electrical Contractor shall provide communication, power, conduit, and wiring. 15. General Contractor shall provide smoke dampers at top of elevator shafts as part of elevator work scope. Power, control conduit, and wiring shall be provided by Electrical Contractor; run from each smoke damper to Elevator Control Panel. 16. General Contractor shall provide fencing and gates in Section Electrical Contractor shall provide gate operators and other items specified in Section Both Contractors shall coordinate these installation accordingly. C. Temporary Facilities and Controls: In addition to specific responsibilities for temporary facilities and controls indicated in this Section and in Section "Temporary Facilities and Controls," each Contractor is responsible for the following: 1. Installation, operation, maintenance, and removal of each temporary facility necessary for its own normal construction activity, and costs and use charges associated with each facility, except as otherwise provided for in this Section. 2. Plug-in electric power cords and extension cords, supplementary plug-in task lighting, and special lighting necessary exclusively for its own activities. 3. Its own field office, complete with necessary furniture, utilities, and telephone service. 4. Its own storage and fabrication sheds. 5. Temporary enclosures for its own construction activities. 6. Staging and scaffolding for its own construction activities. 7. General hoisting facilities for its own construction activities 8. Waste disposal facilities, including collection and legal disposal of its own hazardous, dangerous, unsanitary, or other harmful waste materials. Issued for Construction

4 9. Progress cleaning of work areas affected by its operations on a daily basis. 10. Secure lockup of its own tools, materials, and equipment. 11. Portable generator to perform welding. 12. Construction aids and miscellaneous services and facilities necessary exclusively for its own construction activities. 13. Excavation support and protection. 14. Barricades, warning signs, and lights. D. Temporary Heating, Cooling, and Ventilation: Refer to Section Temporary Facilities for detailed identification of responsibility during construction period. E. Use Charges: Comply with the following: 1. Temporary Sanitary Facilities: Include the cost for sewer service use by all parties engaged in construction activities at Project site in the General Construction Contract. 2. Water Service: Owner will pay for monthly consumption use charges for water service by all entities engaged in construction activities at Project site for project duration. 3. Electric Power Service: Owner will pay for monthly consumption use charges for electric power service by all entities engaged in construction activities at Project site for project duration. 4. Communication Services: Each Contractor shall include the cost for data, internet, and telephone services to their own construction trailer at Project site for project duration. F. Utilities: 1. Each Contractor shall be responsible for various temporary and permanent utilities associated with their work and trade and are as defined elsewhere in this Section as follows: a. General Contractor: Article b. HVAC Contractor: Article c. Plumbing Contractor: Article d. Electrical Contractor: Article Where a piece of equipment or system provided by one Contractor requires a MEP and related connection, conform to following work responsibility: a. Contractor who furnishes the equipment or system shall install that piece of equipment or system, unless otherwise indicated. b. Any MEP work within the equipment or system shall be provided by Contractor providing that piece of equipment or system. c. Source of utility for that piece of equipment or system shall be provided by that MEP Contractor. d. Final connection between that piece of equipment or system and source of MEP shall be made by that MEP Contractor. Issued for Construction

5 3. HVAC Coordination Drawings: The HVAC Contractor shall serve as the lead Contractor with respect to producing and submitting HVAC Coordination Drawings, which shall be signed off on by each Prime Contractor prior to submission to the A/E. The Plumbing, Electrical, and General Contractors shall work with the HVAC Contractor to locate and route their respective utility lines, equipment, and structural appurtenances on the HVAC Coordination Drawings GENERAL CONSTRUCTION CONTRACT A. General Construction (GC) Contract shall generally include, but not be limited to, providing the Work indicated on Civil, Architectural, Structural, Liquid Fuel Systems and Equipment Drawings and General Construction related Specifications, summarized herein for the construction of Phase 2. A summary of General Construction work elements include, but are not limited to the following; refer to the entire set of Contract Documents for all General Construction related work. 1. Civil work elements include: a. Temporary facilities including site sanitary, and site construction entrance. b. Demolition of existing structures pavement, and other site features. c. Excavation and removal of underground storage tanks (USTs) and backfilling. d. Site preparation. e. Grading and excavation for construction of new building elements. f. Site improvements. g. Security fencing and gates. h. Modifications to existing site utilities, including storm and sanitary sewers, water supply and distribution lines, and gas lines to a point 5 feet outside the building line. i. Underground storm water detention basins. j. Erosion and sedimentation control. k. Fuel island pre-engineered structure, concrete slabs on grade, liquid fuel lines, and liquid fuel island distribution equipment. l. Fence enclosure with gates around CNG equipment compound area. m. On-grade parking lot. n. Creating test pits for soil sampling by Owner or Owner s agent. 2. Architectural and structural work elements include: a. Demolition of various components of buildings and structures. b. Foundation systems. c. Below-grade building construction, including excavation, backfill, and thermal and moisture protection. d. Floor and roof superstructure systems, including: construction of steel building frame, joists, floor and roof decks; and precast concrete building frame and related components. e. Exterior closure, including masonry, metal stud walls, and metal panel exterior walls, parapets, doors, windows, louvers, and insulated membrane roof system with roof specialties and exterior rain drainage. f. Interior construction, including masonry partitions with metal stud walls in selected areas, doors, interior glazed openings, and interior finishes consisting of painted gypsum board, ceramic tile, resilient flooring, and acoustical ceilings. Issued for Construction

6 g. Fit up of restrooms, locker rooms, and break rooms, including toilet accessories, lockers, and casework. h. Furnishings, including casework, window treatments, and floor grilles and mats. i. Stairs, railings, ladders, and other miscellaneous metals. j. Miscellaneous items, including painting of mechanical and electrical work, unless otherwise indicated. k. Conveying systems, including elevators and vehicle lifts. l. Equipment, including the following: 1) Loading dock equipment. 2) Diesel fueling systems. 3) Gasoline fueling systems. 4) Fluids management system. 5) Owner furnished equipment scheduled to be installed by Contractor. m. Liquid Fueling system work elements as indicated. 3. Selective demolition. B. Temporary facilities and controls in the General Construction Contract include, but are not limited to, the following and as referenced in Section Temporary Facilities : 1. Construction Manager s operations trailer. 2. Temporary facilities and controls that are not otherwise specifically assigned to the Plumbing Contract, HVAC Contract, Electrical Contract, and CNG Contract. 3. Sediment and erosion and stormwater control. 4. Unpiped temporary toilet fixtures, wash facilities, and drinking water facilities, including disposable supplies. 5. Temporary enclosure for building exterior, until building is permanently enclosed, except as indicated. 6. Temporary heat until building is permanently enclosed, except as indicated. 7. Temporary roads and paved areas. 8. Temporary traffic control measures onsite and at adjacent roads for construction activities, on-site EMTA bus circulation, and service deliveries. 9. Project identification and temporary signs. 10. General waste disposal facilities. 11. Pest control. 12. Temporary stairs. 13. Temporary fire-protection facilities. 14. Site enclosure fence. Issued for Construction

7 15. Security enclosure and lockup. 16. Restoration of facilities used as temporary facilities HVAC CONSTRUCTION CONTRACT A. HVAC Construction (HC) Contract shall generally include, but not be limited to, providing the Work indicated on HVAC Drawings and HVAC related Specifications, summarized herein for the construction of Phase 2. A summary of HVAC work elements include, but are not limited to the following; refer to the entire set of Contract Documents for all HVAC related work. 1. HVAC system equipment, instrumentation, and building automation controls. 2. Exhaust systems. 3. Ductwork and hot- and chilled-water supply piping systems. 4. Vibration isolation. 5. Testing and balancing of all installed systems. 6. Field painting of exterior equipment and damaged factory finishes. 7. Concrete pads, and hangers and supports. 8. Mechanical connections to equipment furnished by other Prime Contracts. 9. Louvers that are part of mechanical equipment shall be provided by HVAC Contractor. 10. Selective demolition. B. Temporary facilities and controls in the HVAC Contract include, but are not limited to, those referenced in Section Temporary Facilities : 1.06 PLUMBING CONSTRUCTION CONTRACT A. Plumbing Construction (PC) Contract shall generally include, but not be limited to, providing the Work indicated on Plumbing Drawings, Fuel System Drawings for lubrication systems and compressed air systems, and related Specifications, summarized herein for the construction of Phase 2. A summary of Plumbing work elements include, but are not limited to the following; refer to the entire set of Contract Documents for all Plumbing related work. 1. Sanitary drainage system including drains, piping, and fittings. Make final connections to site piping provided by General Contractor. 2. Storm drainage piping and fittings and insulation. Make final connections to site piping provided by General Contractor. 3. Domestic Water Distribution System including piping, fittings, valves, pressure regulators, backflow preventers, and plumbing fixtures. Make final connections to site piping provided by General Contractor. Issued for Construction

8 4. Domestic Water Heating System including heaters, piping, circulation pumps, and valves. 5. Piping insulation and identification. 6. Compressed air systems. 7. Lubrication distribution systems including installation of piping between the maintenance building and fuel island, including excavation and backfill. 8. Waste lubrication collection systems. 9. Natural Gas Piping System complete with valves and regulators. 10. Testing and Sterilization of installed domestic water systems. 11. Complete fire suppression systems, including piping, valves, sprinklers, standpipe, and connections to water supply lines. 12. Special plumbing systems, including miscellaneous, hangers, hooks, bracing, mounting, and supports for materials and equipment in following systems. Work scopes by Plumbing Contractor shall include required piping, trenching, bedding, and backfill. a. Compressed air distribution systems b. Natural gas. c. Vehicle Lubrication and Fluid distribution systems. d. Waste lubrication collection systems. 13. Plumbing connections to equipment furnished by other Prime Contracts. Plumbing Contractor shall provide valve for equipment supplier to make connection. 14. Selective demolition. B. Temporary facilities and controls in Plumbing Contract include, but are not limited to, the following: 1. Plumbing connections to existing systems and temporary facilities and controls furnished by other Prime Contracts ELECTRICAL CONSTRUCTION CONTRACT A. Electrical Construction (EC) Contract shall generally include, but not be limited to, providing the Work indicated on Electrical Drawings and Electrical related Specifications, summarized herein for the construction of Phase 2. A summary of Electrical work elements include, but are not limited to the following; refer to the entire set of Contract Documents for all Electrical related work: 1. Coordinate electrical service requirements with power company and provide electrical services from Power Company at locations indicated. 2. Site electrical distribution. Issued for Construction

9 3. Conduit, wire, and field connections for equipment and systems in Divisions Where power and subsequent equipment are in other than Division 16 work, provide conduit, wire, and field connections from power source to disconnect switch and network related connection switch. Conduit, wire, and field connections from EC provided disconnect switch and network related connection switch for motors, controllers, devices, panels, filters, transformers, indicators, and related system equipment shall be provided by appropriate Contractor as specified under Divisions 01, 8, 11, 13, 14, and 21-23, unless otherwise indicated in Contract Documents. 4. Lightning and surge protection equipment wiring at process instrumentation transmitters. 5. Raceway system for Data Highway Cables and specialty cable systems. 6. Raceway system for Fiber Optic Network System and other specialty cable systems. 7. Security system with CCTV cameras, card readers, and security interface system. 8. VoIP telephone system extending existing VoIP telephone system with handsets, speakers and accessories. 9. Power wiring for heating, ventilating, and air conditioning equipment provided under other related Divisions, including power wiring for 120 Volt unit heater motors and thermostats. 10. Precast manholes, covers, handholes, and light pole bases. 11. Modifications to existing control systems including installation of auxiliary motor starter contacts, relays, switches, as required to provide control functions or inputs. 12. Coordinate with Telecommunications Service Provider to provide telephone services from service provider. 13. Coordinate with Telecommunications Service Provider to provide internet services to facility using Cable. 14. Testing of electrical equipment. 15. Set electrical protective devices in accordance with NETA standards and in accordance with protective coordination study. 16. Provide Short Circuit, System Protective Device Coordination Analysis and Arc Fault Analysis. 17. Gas monitoring system for detection and alarming of flammable and toxic gases including conduit, wiring and terminations to terminate alarm status information from gas monitoring system to Fire Alarm System and to Building Management System (BMS). 18. Electrical connections to equipment furnished by other Prime Contracts. 19. Selective demolition. Issued for Construction

10 20. Concrete encased duct banks including excavation, backfill, concrete encasement, and stone base complete as detailed on electrical drawings. 21. Emergency generator system and related accessories. B. Temporary facilities and controls in Electrical Contract include, but are not limited to, the following: 1. Electric power service and distribution. 2. Lighting, including site lighting. 3. Electrical connections to existing systems and temporary facilities and controls furnished by other Prime Contracts. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION Issued for Construction

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

KU West Campus LEEP II High Bay Facility Project # , A (c)

KU West Campus LEEP II High Bay Facility Project # , A (c) Number Revision Title Rev Date Discipline Bulletin Drawings B-West Structural Category S051 0 General Notes - Sheet 1 7/31/13 Structural Bid Package B- West Campus S052 0 General Notes - Sheet 2 7/31/13

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

PAULDING COLLEGE & CAREER ACADEMY

PAULDING COLLEGE & CAREER ACADEMY PAULDING COLLEGE & CAREER ACADEMY 000110 OF THE PROJECT MANUAL FOR THE CONSTRUCTION OF: PAULDING COLLEGE & CAREER ACADEMY DALLAS, GEORGIA DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 TITLE

More information

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6 PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation

More information

Appendix J - Custom Uniformat for EDU Migration

Appendix J - Custom Uniformat for EDU Migration Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations

More information

Schedule of Values Cruise Terminal 2 Expansion

Schedule of Values Cruise Terminal 2 Expansion Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General

More information

DESIGN & CONSTRUCTION GUIDELINES

DESIGN & CONSTRUCTION GUIDELINES DESIGN & CONSTRUCTION GUIDELINES EDITION: USF FACILITIES MANAGEMENT - DC 5 DCG FACILITIES MANAGEMENT DESIGN & CONSTRUCTION PHONE: (813) 974-2845 4202 E. FOWLER AVENUE, OPM 1000 TAMPA, FLORIDA 33620-7550

More information

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 01 Project Title Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets 00 21

More information

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS 669.7403.001 West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS Page C-111 Advertisement for Bids 1-2 C-200 Instruction to Bidders 1-10 C-410 Bid Form for Construction Projects

More information

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7 TABLE OF CONTENTS ( = Rev 11/15) Update #7 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes (New) B-9 Record Drawings B-10 Variance Procedure

More information

TABLE OF CONTENTS. (Δ = Rev 06/08)

TABLE OF CONTENTS. (Δ = Rev 06/08) TABLE OF CONTENTS (Δ = Rev 06/08) INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-9 Record Drawings B-10 Variance Procedure B-11 Surface Water Procedures (New Section)

More information

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules

More information

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8 TABLE OF CONTENTS ( = Rev 04/17) Update #8 INTRODUCTION REQUEST FOR REVISION FORMS TAB A TABLE OF CONTENTS TAB B PROCEDURES B-4 International Suite of Codes B-9 As-Builts and Record Drawings B-10 Variance

More information

SECTION TEMPORARY FACILITIES AND CONTROLS

SECTION TEMPORARY FACILITIES AND CONTROLS SECTION 015000 TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 GENERAL A. Each Contractor shall be responsible for arranging for and providing construction facilities and temporary controls as required

More information

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project: RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: ARCHITECT/ENGINEER ADDRESS:

More information

PROJECT MANUAL PROJECT LABOR AGREEMENT

PROJECT MANUAL PROJECT LABOR AGREEMENT June 30, 2017 ISSUED FOR BID: January 25, 2018 PROJECT MANUAL PROJECT LABOR AGREEMENT VOLUME 6 OF 6: DIVISIONS 26 33 City School District of Albany Albany High School Additions & Renovations Phase 1 CSArch

More information

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements SECTION A CM INSTRUCTIONS TO BIDDERS SECTION B BID CATEGORY DESCRIPTIONS & BID FORMS BC-07: Building HVAC and Plumbing BC-08: Building Electric BC-09: General Trades BC-10: Masonry BC-11: Precast Structural

More information

APPLICATION AND CERTIFICATE FOR PAYMENT

APPLICATION AND CERTIFICATE FOR PAYMENT AND CERTIFICATE FOR PAYMENT TO OWNER: MASTER TEMPLATE - SAVE PROJECT FILE 1 DATE: 10/5/2012 PERIOD TO: ARCHITECT: PROJECT NO: CONTRACTOR'S FOR PAYMENT Application is made for payment, as shown below, in

More information

VOLUME 4 DIVISION SPECIFICATIONS

VOLUME 4 DIVISION SPECIFICATIONS Page 1 Section Title Consultant Pages VOLUME 4 DIVISION 00-01 SPECIFICATIONS Division 00 - Procurement and Contracting Requirements 00 01 07 SEALS PAGE All 5 00 01 11r6 TABLE OF CONTENTS All 7 00 21 13r1

More information

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Plumbing - 220000 Without limiting the application of all of the Contract Documents to the Subcontract,

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

B. RESIDENTIAL MASTER PLUMBER $ $ $

B. RESIDENTIAL MASTER PLUMBER $ $ $ FEE SCHEDULE FOR LICENSE Res. Non-Res. Out of State BUILDING CATEGORIES A. GENERAL CONTRACTOR (Unlimited Scope) B. BUILDING CONTRACTOR $ 100.00 $ 150.00 $ 300.00 Limited to construction and remodeling

More information

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING

More information

ADDENDUM 3 - JULY 24, 2015

ADDENDUM 3 - JULY 24, 2015 CAMINO REAL REGIONAL MOBILITY AUTHORITY EL PASO STREETCAR PROJECT SPECIAL SPECIFICATION EP-MSF Maintenance and Storage Facility. Description. Construct the Maintenance and Storage Facility (MSF) building

More information

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages TABLE OF CONTENTS VOLUME 1 DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages SCHEDULE OF DRAWINGS...... 1 PROJECT PERSONNEL & DIRECTORY......

More information

CAMPUS STANDARDS HANDBOOK

CAMPUS STANDARDS HANDBOOK CAMPUS STANDARDS HANDBOOK OFFICE OF PHYSICAL PLANNING AND CONSTRUCTION UNIVERSITY OF CALIFORNIA, SANTA CRUZ Italics indicate recent revisions. THESE STANDARDS ARE PROVIDED TO UCSC CONSULTANTS FOR GUIDANCE

More information

City Of Mendota Construction Procedures

City Of Mendota Construction Procedures City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time

More information

PROJECT SPECIFICATIONS

PROJECT SPECIFICATIONS PROJECT SPECIFICATIONS CITY OF PORTLAND BUREAU OF ENVIRONMENTAL SERVICES PROJECT SPECIFICATIONS FOR ANKENY PUMP STATION UPGRADE BES project number E07833 STANDARD REQUIREMENTS (DIVISION 0) GENERAL REQUIREMENTS

More information

Northwestern Facilities

Northwestern Facilities Northwestern Facilities NU Master Specification - Issuances Record & Summary of Changes Only the most current version of an NU Master Specification is included as a PDF for download on this website. The

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 1A-8 Issue date: October 2014 CONSTRUCTABILITY REVIEW 1. The Consultant shall be required to perform a constructability review with the College, Fund s Design Coordinator, Fund s Construction

More information

City of Westerville Guide to Commercial Inspections

City of Westerville Guide to Commercial Inspections City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist This checklist is a convenient reference to the 2012 Michigan Building Code. The checklist

More information

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested. Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

ADDENDUM NO. 2 Consisting of 3 pages and Attachments

ADDENDUM NO. 2 Consisting of 3 pages and Attachments 10404-125 Street, Edmonton, AB. T5N 1T2 Tel: 780.455.5975 Fax: 780.454.2397 info@cdyarchitect.com ADDENDUM NO. 2 Consisting of 3 pages and Attachments PROJECT: Maina Centre Ville Phase II, Beaumont, Alberta

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND STATE UNIVERSITY CONSTRUCTION FUND The following checklist show the general items required by the Agreement and the Program Directives. Unless included in the lump sum fee or the Schedule B of the Consultant

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls

More information

PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE

PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE HUMPHREYS COUNTY BOARD OF SUPERVISOR BELZONI, MISSISSIPPI APRIL 20, 2016 EMILY POOLE ARCHITECTURE,

More information

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised 02011 Soil Boring Data (Create for each site) (01/04) 02050 Demolition (Create for each existing building)

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

BILL NO. 1 GENERAL ITEMS. Item No. Description Lump Sum Prices Excluding HST

BILL NO. 1 GENERAL ITEMS. Item No. Description Lump Sum Prices Excluding HST Page 1 SECTION 00 72 00 - GENERAL CONDITIONS BILL NO. 1 GENERAL ITEMS 1 Bonds... $ 2 Insurance... $ 3 Permits and fees... $ 4 Warranty certificates... $ 5 Supervision... $ SECTION 01 32 17 - SCHEDULE 6

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking

More information

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract

More information

March 2018 Progress. Work Completed, Week Ending 3/23/18:

March 2018 Progress. Work Completed, Week Ending 3/23/18: March 2018 Progress Work Completed, Week Ending 3/23/18: Continued draft curtains and liner panels. Continued running power to hangar doors. Continued installation of bath accessories in the gang bathrooms.

More information

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening. DOCUMENT 00 43 36B EXPANDED SUBCONTRACTORS LISTING TO: CLARK COUNTY SCHOOL DISTRICT hereinafter called "Owner" FROM: ~AU;)"''"-' Oeve\,(;p,-...e,.,,... IA... t. ~o~ t>.m..e>u,i-j (Print Company Name) Pe-Mo1..,,,-t,:;>.tJ

More information

Table of Contents Chapter 1 INTRODUCTION Chapter 2 DEFINITIONS Chapter 3 DELIVERABLES Chapter 4 BASIS OF DESIGN

Table of Contents Chapter 1 INTRODUCTION Chapter 2 DEFINITIONS Chapter 3 DELIVERABLES Chapter 4 BASIS OF DESIGN Chapter 1 INTRODUCTION 1.00.00 Introduction Chapter 2 DEFINITIONS 2.00.00 Definitions Chapter 3 DELIVERABLES 3.00.00 Deliverables Chapter 4 BASIS OF DESIGN 4.01.01 Energy and Environment 4.01.02 Codes,

More information

PROFESSIONAL DESIGN MANUAL INDEX

PROFESSIONAL DESIGN MANUAL INDEX PROFESSIONAL DESIGN MANUAL INDEX DIVISION A--GENERAL PROJECT REQUIREMENTS... A2-A15 A.1 INTRODUCTION... A-2 A.2 CODES COMPLIANCE (VERIFY CITY REQUIREMENTS)... A-5 A.3 SPECIAL SUBSURFACE AND LAND CONDITIONS...

More information

A. Section includes busway and fittings including plug-in units.

A. Section includes busway and fittings including plug-in units. SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:

More information

SECTION : OPERATION & MAINTENANCE MANUALS

SECTION : OPERATION & MAINTENANCE MANUALS SECTION 01 17 73: OPERATION & MAINTENANCE MANUALS 1. GENERAL: A. This section includes requirements for Contract Record - Operations and Maintenance manuals required prior to project closeout including,

More information

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM

More information

PROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California

PROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California PROGRAM COST MODEL for PEER Tall Buildings Study Concrete Structural Option Los Angeles, California March 8, 2010 PEER Tall Buildings Study Concrete Structural Option March 8, 2010 CONTENTS Page Nos. Overall

More information

DIVISION 1 GENERAL REQUIREMENTS CONSULTANT/VENDOR REQUIREMENTS BUILDING INFORMATION MODELING (BIM) REQUIREMENTS

DIVISION 1 GENERAL REQUIREMENTS CONSULTANT/VENDOR REQUIREMENTS BUILDING INFORMATION MODELING (BIM) REQUIREMENTS DIVISION 1 GENERAL REQUIREMENTS CONSULTANT/VENDOR REQUIREMENTS BUILDING INFORMATION MODELING (BIM) REQUIREMENTS PART 1 - GENERAL 1.0 RELATED DOCUMENTS 1.0.1 Drawings, General Conditions of the Contract

More information

Administration Building Needs Assessment

Administration Building Needs Assessment Town Hall Meeting with the Habersham County Board of Commissioners Administration Building Needs Assessment JUNE 13, 2016 Detailed Evaluation Performed in 2015 Engineering Evaluation Site/Civil Architectural

More information

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised 02011 Soil Boring Data (Create for each site) (05/15) 02050 Demolition (Create for each existing building)

More information

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised 02011 Soil Boring Data (Create for each site) (05/15) 02050 Demolition (Create for each existing building)

More information

186 TH AIR REFUELING WING KEY FIELD, MERIDIAN, MS ADDENDUM #1 PERFORMANCE WORK STATEMENT

186 TH AIR REFUELING WING KEY FIELD, MERIDIAN, MS ADDENDUM #1 PERFORMANCE WORK STATEMENT 186 TH AIR REFUELING WING KEY FIELD, MERIDIAN, MS PROJECT NUMBER MDVL092051 Renovate Vehicle Maintenance Facility Bldg 200 23 June 2017 ADDENDUM #1 PERFORMANCE WORK STATEMENT 1.0 SCOPE. This addendum to

More information

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No. 20140101C CONSTRUCTION ESTIMATE AND PROJECT BUDGET Dated June 7. 2014 Estimated Cost HARD COSTS $ 1,560,284 Core Renovations (Toilet Rooms, Ceilings

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

State of Ohio Ohio School Facilities Commission TABLE OF CONTENTS

State of Ohio Ohio School Facilities Commission TABLE OF CONTENTS State of Ohio Ohio School Facilities Commission TABLE OF CONTENTS TABLE OF CONTENTS DEFINITIONS NOTICE TO BIDDERS INSTRUCTIONS TO BIDDERS BID FORM. BID GUARANTY AND CONTRACT BOND Article 1 Contract Information

More information

COMMERCIAL TENANT IMPROVEMENT PERMIT APPLICATION

COMMERCIAL TENANT IMPROVEMENT PERMIT APPLICATION COMMERCIAL TENANT IMPROVEMENT PERMIT APPLICATION OFFICIAL USE ONLY Date: Permit #: Received by: For Staff Use Only: OFD ELEC Planning SITE LOCATION Site Address: Tax Parcel Number: TYPE OF WORK Building

More information

Bid Package 22A Plumbing Systems

Bid Package 22A Plumbing Systems Bid Package 22A Plumbing Systems The successful Subcontractor acknowledges and agrees to the requirements set forth by this bid package and its descriptions and in conjunction with all other Construction

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

Henderson County High School Career and Technical Education Addition and Renovation Addendum # 1

Henderson County High School Career and Technical Education Addition and Renovation Addendum # 1 Henderson County High School Career and Technical Education Addition and Renovation Addendum # 1 Date: April 24, 2015 Attached Pre Bid Agenda Attached Pre Bid Sign In Sheet Attached Addendum # 1 from RBS

More information

Florida Army National Guard Construction Facilities Management Office. Scope of Work:

Florida Army National Guard Construction Facilities Management Office. Scope of Work: Florida Army National Guard Construction Facilities Management Office Florida Armory Revitalization Program (FARP) Design Guidelines October 2008 Scope of Work: To provide complete design for the renovation/alterations

More information

J~e~~r Senior Director of Construction Services Facilities Design and Construction UNIVERSITY OF CALIFORNIA, SAN DIEGO.

J~e~~r Senior Director of Construction Services Facilities Design and Construction UNIVERSITY OF CALIFORNIA, SAN DIEGO. BERKELEY DAVIS IR VINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SAN!' A BARBARA SANT A CRUZ OFFICE OF THE ASSIST ANT VICE CHANCELLOR CAMPUS ARCHITECT - FACILITIES DESIGN & CONSTRUCTION TEL:

More information

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE TABLE OF CONTENTS SECTION TITLE DATE Division 00 Procurement and Contracting Requirements 000101... Project Title Page 000116... CAD Standards 001116... Invitation to Bid 002113... Instructions to Bidders

More information

SECTION ALTERATION PROJECT PROCEDURES

SECTION ALTERATION PROJECT PROCEDURES SECTION 013516 ALTERATION PROJECT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for protection of existing facilities during construction operations. 2. Demolition and removals

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

More information

School Construction Authority Architecture & Engineering

School Construction Authority Architecture & Engineering SECTION 1 1.0 GENERAL 1.1 CONTRACT REQUIREMENTS 1.1.1 Drawings 1.1.1.1 Border Sheets 1.1.1.2 Drawing Numbering Convention 1.1.2 Specifications 1.1.2.1 Specification Format and Instruction 1.1.3 Report

More information

Florida Army National Guard Construction Facilities Management Office. Scope of Work:

Florida Army National Guard Construction Facilities Management Office. Scope of Work: Florida Army National Guard Construction Facilities Management Office Florida Armory Revitalization Program (FARP) Design Guidelines September 2011 Scope of Work: To provide complete design for the renovation/alterations

More information

SECTION TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY

SECTION TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities. 1.2

More information

SECTION GROUNDING AND BONDING

SECTION GROUNDING AND BONDING SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

* Cost Code# * Description * Division 1100 Summary 1 - General Requirements 1200 Price and Payment Procedures 1 - General Requirements 1300

* Cost Code# * Description * Division 1100 Summary 1 - General Requirements 1200 Price and Payment Procedures 1 - General Requirements 1300 * Cost Code# * Description * Division 1100 Summary 1 - General Requirements 1200 Price and Payment Procedures 1 - General Requirements 1300 Administrative Requirements 1 - General Requirements 1400 Quality

More information

JULY 11, 2017 SECTION MARRIOTT MIDTOWN DUAL BRAND BULLETIN NO. 4 AC/MOXY SECTION BULLETIN NO. 4

JULY 11, 2017 SECTION MARRIOTT MIDTOWN DUAL BRAND BULLETIN NO. 4 AC/MOXY SECTION BULLETIN NO. 4 JULY 11, 2017 SECTION 009504-1 BULLETIN NO. 4 AC/MOXY 20150080 PART 1 - GENERAL SECTION 009504 BULLETIN NO. 4 1.1 GENERAL REQUIREMENTS A. The Contract Documents for the above project are revised as described

More information

TABLE OF CONTENTS ENGINEERING SPECIFICATIONS AND STANDARDS

TABLE OF CONTENTS ENGINEERING SPECIFICATIONS AND STANDARDS 2 Cutting and Patching 01 73 29 n-a Susanne Terharn 12/21/11 2 Demolition 02 40 00 n-a Susanne Terharn 10/03/11 2 Concrete 03 00 00 n-a Rich Vlasak 12/21/11 2 Cementitious Underlayment 03 54 00 n-a Rich

More information

S CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS

S CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS S CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS This Attachment lists the items to be provided by the Architect in accordance with Owner/Architect Agreement. This list is not all-inclusive, nor is it

More information

Delta Gamma Sorority Renovation Budget Scope 3/7/2018

Delta Gamma Sorority Renovation Budget Scope 3/7/2018 Delta Gamma Sorority Renovation Budget Scope 3/7/2018 PROJECT: Barbara Cerni Delta Gamma Sorority Tallahassee, Fla. This scope is based on the 50% Construction Documents drawn by BKJ Architecture dated

More information