1 UNOPS Peguy-Ville, 13 January 2016 CLARIFICATIONS NOTES 1 Reference No. ITB-HTOC /re-tendering Provision and installation of a CCTV system Cap an Port Dear Bidders: Following the site visit held on 8 th of January 2016, this clarification provides responses to questions raised and is relevant to the process mentioned in reference. It should be considered in the preparation of your bids. A. Questions/responses from site visit 1) Given that the port currently relies on a Generator for power source (for 20 hours/day), should one account for a backup source in proposal? The system will be fitted with a backup electrical supply capable of maintaining the total operation for a period not less than 24 hours. 2) Given that infrastructure is lacking, wiring cameras to port grid should be included in our proposal? Yes, please refer to section G of the technical requirements 3) Existing light poles are on a main switch that only turns on at night, so if we were to use these existing poles, re-wiring would be required to be done? Yes, please refer to section G of the technical requirements 4) Additional installation of poles may pose an issue to deliverable timeline, is client willing to be flexible if proposed? If the poles are proposed for aerial wiring, this is no longer an issue as the wiring is underground. If the additional poles are required to meet the surveillance objectives please provide details on delays in your proposal. 5) What is minimum storage capacity that would be required for the CCTV system? (How many days/months to be saved?) Since this has a direct cost on budget, supplier should propose a storage capacity and budget options. 6) Where is the proposed location/room for the CCTV Feeds? a. Minimum server room area (to be proposed)? b. Minimum Surveillance room area (to be proposed)? For the time being the Building of Surete will be considered as the main location for the UNOPS Tel: , Rue Marion, Péguy-Ville htocproc@unops.org Pétion-Ville

2

3 PHASE 1 PRELIMINARY URGENT ITEMS TO BE PROCURED AS PER APN REQUEST AND SPECIFICATIONS CCTV SYSTEM A- Objective It is a visual assessment tool that merely records events as they occur, and should therefore be used in conjunction with other security measures. The idea for the Cap an Port is to install one non-threat detection CCTV camera at the main gate and three threat detection CCTV cameras (intelligent video) for perimeter, pier, warehouses, auxiliary gates, and cargo yard coverage. B- Specifications The system will need to be used in three basic visual identification ways: 1. Personal identification: Allows the viewer to personally identify something within the scene. 2. Action identification: Allows the viewer to capture the events occurring in front of the camera as they actually happened. 3. Scene identification: Allows the scene to stand on its own merit. The system needs to allow security personnel to monitor several areas from a single location. The system will need to include: 1. Deterrence of theft 2. Forensic evidence for incident investigations and prosecution 3. Employee safety 4. Port Liability 5. Marketing of port facilities' security as well as transmitting pictures of facilities attributes. The system will need to meet the International Ship and Port Facility Security (ISPS) Code requirements particularly ISPS sections A Prevention of weapons and dangerous substances from entering the facility A Controlling access to the port facility A Monitoring of the port facility A Monitoring of restricted areas A Supervising the handling of cargo A Supervising the handling of ship's stores All the cameras will need to be installed on existing light poles so as to minimize cost. An integrate camera feed to a central command center located in the security office by UNOPS in Tel: / 81 / 82 / 83 3, rue Marion, Peguy Ville

4 the main gate (location to be validated). CCTV screens must be linked to threat detection cameras and video analytics so unauthorized activities can be alarmed, identified, and analyzed in the security command center quickly enough to dispatch security personnel. A preliminary study (to be validated) has suggested the need of 4 Pan/Track/Zoom cameras (7-70mm lens) mounted on existing light poles as follows: a) 1 non-threat detection camera mounted to observe the main gate (light pole closest to the gate and adjacent to fenced car storage); b) 1 threat detection camera mounted on the light pole by the corner farthest from the security office, by the warehouse that is closest to the main gate, to provide coverage for domestic cargo operations, warehouse, and part of the main pier; c) 1 threat detection camera mounted on the last light pole of the main pier to provide coverage for the piers, part of the cargo yard, and part of the perimeter fencing; d) 1 threat detection camera mounted on the light pole between the fenced car storage and the cargo yard to provide coverage for the car storage, part of the cargo yard, two auxiliary gates, and part of the perimeter. The system will be fitted with a backup electrical supply capable of maintaining the total operation for a period not less than 24 hours. The system may be hardwired or wireless. In both cases the electrical feed will be underground as detailed in section G. In the case of a wireless system, conduit quantity is reduced to 2 versus 3 and the AWG 36 grounding system and related accessories not required. All other conditions apply. In the case of a wireless system, the bidder must demonstrate prior to award that the system will operate according to the stated requirement. C- Quantities To be determined. D- Delivery 12 to 16 weeks after receipt of firm order and payment security E- Shipping Shipping is the responsibility of the supplier, excluding all an taxes, duties, etc. Ocean transportation charges need to be included in the proposal. F- Service 3 years of service to be included with standard manufacturer warranty. The selected company will be required to do a thorough engineering site visit and a proposal will be needed to suggest a solution for the Port that will need to be approved by APN. UNOPS in Tel: / 81 / 82 / 83 3, rue Marion, Peguy Ville

5 All material, software, licenses, installation and setup to be included in the contract of service. In the proposal, needs to be included the annual operating and maintenance costs. G Installation (method of work and materials) Conduits and physical installation All wiring between poles and/or building shall be underground. Underground conduits shall be PVC and above ground conduit galvanized steel. Transition from underground to above ground conduits shall be made with a watertight connector (glued on the PVC side and threaded on the steel side). The transition will be made underground. A total of 3 conduits shall be installed between poles and/or buildings (1 for electrical supply, 1 for video feed and one spare) Minimum installation depth of conduits shall be 600mm. Minimum size of conduits shall be 60mm. Trench are to be as straight and direct as possible Route through unstable soil such as mud, shifting soils, or other hazards should be avoided. Longitudinal runs of conduits should not be located directly over or under other underground facilities such as gas, water sewer lines, and septic system. Whenever possible the horizontal distance between these facilities should be a minimum of 2 meter to permit access and maintenance of either facilities. Caution ribbon shall be installed above each conduits. A #6 AWG shall be directly buried in the bottom of the trench, prior the installation of any conduits. Each end shall either be tied with the next run or connected to a grounding rod. All ends, joints and internal finish of the conduit shall be free of sharp edges or burrs which could damage the cable. All buried joints shall be glued with cement as recommended by the conduit manufacturer. Any change in direction between lengths of straight rigid conduit greater than 5 degrees shall be made in electrical sweeps, or with a very gradual sweeping change CCTV equipment requiring 120--v power shall be installed below the communication cables on overhead--fed poles Pole junction of cable will be within a stainless steel enclosure located not less than 2.4 meter above ground level. The equipment shall maintain a minimum clearance of 1 meter from secondary service wire and installed not less than 8 feet from ground line. For street light poles, CCTV electrical connection to the utility s power source shall be through a polarized, three--prong plug connected to an electric utility s 120--volt pole UNOPS in Tel: / 81 / 82 / 83 3, rue Marion, Peguy Ville

6 mounted outlet, provided by the electric utility. For wood poles, cameras can be connected to secondary. Drilling into other than wooden poles is strictly prohibited. Camera and control box(es) must be secured to the pole with approved metal straps or metal brackets bolted onto the pole. A minimum of two stainless steel straps must be used to secure the camera to the pole. The straps shall be a minimum of 1/2 inch width and inches thickness with a tensile each. The buckles shall be rated at double the tensile strength of the straps or approximately 3,000 pounds. If a pole mount adapter plate is used, it shall have a minimum load bearing rating of 200 pounds. Trench excavation, backfilling and compacting. Accurately locate and record on project record documents abandoned and active utility lines rerouted or extended. It is the contractor responsibility to identify, protect and repair any damages incurred during the work phase. Trenches are to be excavated to the widths, lines and grades indicated on the sketch. Trenches for conduits are to be excavated to a minimum width of 300mm on each side of the conduit. Under no circumstances shall excavated material from trench excavations be left, even temporarily, where it will interfere with other contractor's operations. When excavations are to be made in bituminous or concrete pavement, the pavement shall be saw cut and removed before beginning excavation. Pavement removal shall be a minimum of 300mm beyond trench or pit walls. Conduit shall be bedded as specified in the appropriate sections of these specifications or as remainder of the trench above the bedding shall be backfilled with suitable trench backfill material and compacted as specified in this specification section. Do not cover or enclose work of this section before obtaining required inspections, tests, approvals, and location recording. Sufficient time shall be allowed, after notice is given that the work is ready for inspection, for making all examinations and tests. Trench backfill shall be made in layers not to exceed six inches (6") measured loose. Each layer shall be thoroughly compacted before the next layer is placed. Backfill shall be compacted by mechanical tampers or other approved methods to maximum dry density of 98% in conformance with ASTM D1556 or ASTM D2167. Water settling, puddling and jetting are not acceptable compaction methods. Care shall be taken to prevent pieces of excavated bituminous or concrete pavement from becoming mixed with backfill material. Provide all shoring, sheathing, bracing, sheet piling (wood or steel) necessary to conduct and complete the work safely, to maintain sides of excavation in safe and stable condition where required for the protection of utility services. Any settlement in the UNOPS in Tel: / 81 / 82 / 83 3, rue Marion, Peguy Ville

7 shoring supports shall be immediately adjusted. Restore surface features at areas disturbed by excavation, and re-establish original grades unless otherwise indicated. Replace removed sod immediately after backfilling is completed. Patch existing pavement in the path of underground conduit to re-establish finish and to same thickness. The Contractor shall be held responsible for any damage to adjoining or adjacent work and buildings. Stockpile, haul from site, and legally dispose of off-site all waste materials, including excess excavated materials, rock, trash, and debris. Materials Underground conduits: PVC schedule 40 conduits and fittings Above ground conduits: Schedule 40 galvanized steel and assorted threaded couplers and fittings. Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, 150 mm wide and 0.1 mm thick, continuously inscribed with a description of the utility; colored as follows: - Red: Electric. - Orange: CCTV and other communications. Junction panel, pole mounted: NEMA 4X suitably sized, Fabricated in accordance with UL specifications from 14 or 12 gauge Type 304 stainless steel standard. All seams continuously welded and ground smooth. Rolled lip around three sides of door and all sides of door opening for watertight seal. Neoprene gasket attached to door with oil resistant adhesive. Clamps on three sides of door for watertight seal. Stainless steel external hardware. Hasp and staple provided for padlocking. External mounting feet. Standard plastic self-adhesive print pocket. Grounding rod: Hot dipped galvanized steel rod 16mm diameter, 2.4 meter long with corresponding ground clamp. Conduit bedding material: Sand exempt of rock larger than 4mm Back fill material: Select and well graded material. Maximum particle size 19mm. UNOPS in Tel: / 81 / 82 / 83 3, rue Marion, Peguy Ville

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

Community Services Dept., City of Mississauga Subdivision Requirements Manual Page 1 of 5 Specifications Revised: September 26, 2005

Community Services Dept., City of Mississauga Subdivision Requirements Manual Page 1 of 5 Specifications Revised: September 26, 2005 Subdivision Requirements Manual Page 1 of 5 PART I - GENERAL 1.1 Related Work.1 Rough Grading: Section 02211 1.2 Scope of Work.1 This section includes the supply and installation of all labour and materials

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

Section 2: Underground

Section 2: Underground Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,

More information

CONSTRUCTION SPECIFICATION FOR GROUNDING

CONSTRUCTION SPECIFICATION FOR GROUNDING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 609 NOVEMBER 2001 CONSTRUCTION SPECIFICATION FOR GROUNDING TABLE OF CONTENTS 609.01 SCOPE 609.02 REFERENCES 609.03 DEFINITIONS - Not Used 609.04 DESIGN

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System

SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System 2004 Specifications Houston District SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System 1. Description. Furnish and place a Multi-Duct Conduit (MDC) system that is suitable for installation in an outdoor

More information

DIVISION 1100 TRAFFIC

DIVISION 1100 TRAFFIC SECTION 1102 STREET LIGHTING GENERAL INFORMATION The Idaho State Electrical Board has determined that all street lights are to be provided with an external fuse disconnect, in a junction box between the

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES SECTION 2831 ITEM F-162 CHAIN-LINK FENCES PART 1 - GENERAL 1.1 DESCRIPTION. This item shall consist of furnishing and erecting a chain-link fence in accordance with these specifications and the details

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

Procurement Services SVC East Fowler Avenue Tampa, Florida (813)

Procurement Services SVC East Fowler Avenue Tampa, Florida (813) Procurement Services SVC 1073 4202 East Fowler Avenue Tampa, Florida 33620 (813) 974-2481 Web Address: https://www.usf.edu/business-finance/purchasing/public-bids/rfi.aspx October 12, 2018 Invitation to

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

Section 7: Specifications

Section 7: Specifications Section 7: Specifications 29 31 Building Boundary of Clear Area See Note # 1 8' Shrubs 8' Concrete Pad Equipment 8' TRAVELED WAY M Meter Pedestal 8' Curb Protective Vehicle Posts (Bollards) If Required

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

Colorado River Aqueduct Pumping Plants 230 kv Disconnect Switches Replacement

Colorado River Aqueduct Pumping Plants 230 kv Disconnect Switches Replacement DATE: July 15, 2011 ADDENDUM NUMBER: 2 MODIFYING: Specifications No. 1698 PROJECT: Colorado River Aqueduct Pumping Plants 230 kv Disconnect Switches Replacement BID TIME AND DATE: 2:00 p.m., July 19, 2011

More information

CITY OF UNION, OREGON TECHNICAL SPECIFICATIONS SECTION 9 UNDERGROUND UTILITIES

CITY OF UNION, OREGON TECHNICAL SPECIFICATIONS SECTION 9 UNDERGROUND UTILITIES A. GENERAL 1. Scope. These specifications cover the installation of the utility systems and appurtenances for the electrical power, telephone, gas, and television as shown in the Drawings. The Work includes,

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section AUTOMATIC CONTROL VALVE INSULATED ENCLOSURE (HOT BOX)

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section AUTOMATIC CONTROL VALVE INSULATED ENCLOSURE (HOT BOX) Section 15959 PART 1 GENERAL 1.01 SUMMARY This Section includes the furnishing and the installation of Automatic Control Valve Insulated Enclosures (Hot Boxes) for control valves installed on water lines

More information

STREET LIGHTING GENERAL INFORMATION

STREET LIGHTING GENERAL INFORMATION SECTION 1102 STREET LIGHTING GENERAL INFORMATION These specifications are for street lighting that is to be dedicated to the public and maintained by the City of Meridian. Such installations require a

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

SECTION 1101 TRAFFIC SIGNALS AND APPURTENANCES END OF SECTION

SECTION 1101 TRAFFIC SIGNALS AND APPURTENANCES END OF SECTION SECTION 1101 SIGNALS AND APPURTENANCES PART 1 GENERAL 1.4 SUBMITTALS E. Submit warranty for all supplied material and workmanship for a period of two years from final acceptance. The warranty must state

More information

A. Product Data shall be provided for each type of product indicated.

A. Product Data shall be provided for each type of product indicated. 32 31 13 CHAIN LINK FENCES AND GATES SECTION 1 GENERAL 1.1 SUMMARY This Section includes the following: 1. Chain Link Fences 2. Gates for Chain Link Fences. See electrical specifications for electrical

More information

CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS

CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS PART 1 - GENERAL 1.01 SUMMARY A. Section Includes furnishing and installing chain-link fabric fence, gate, and appurtenances. 1.02

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

Merrimac Municipal Light Department. Commercial Developments Policy

Merrimac Municipal Light Department. Commercial Developments Policy Merrimac Municipal Light Department Commercial Developments Policy General: This document provides specific instructions for the provision of underground electrical facilities associated with the construction

More information

CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS

CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS October 1990 CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS 1. GENERAL CONDITIONS...1 3. DESCRIPTION...1 5. MATERIALS...1 5.1 General...1 5.2 Testing and Approval...1 5.3 Irrigation Pipe and Fittings...1

More information

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS PART 1 - GENERAL 01.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification sections, apply to work of this Section.

More information

Diffused Aeration Piping Equipment

Diffused Aeration Piping Equipment 1.0 General 1.1. The specifications in this section include all components of the Diffused Aeration System with the exception of the individual diffuser units. Refer to additional specification sections

More information

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.

More information

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual [Type text] Heber Light & Power Developers & Excavators Electrical Service Requirements Manual May 2017 E.1.1 - GENERAL REQUIREMENTS PURPOSE This section was prepared to aid developers, contractors, engineers

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 603 NOVEMBER 2017 (Formerly OPSS 603, November 2015) Note: The PROV published in November 2017 replaces OPSS 603 COMMON, November 2015 with no technical

More information

SPECIFICATIONS SCOPE OF WORK

SPECIFICATIONS SCOPE OF WORK SPECIFICATIONS SCOPE OF WORK The intent of this contract is for the supply of all necessary labour, materials, and equipment to install underground traffic signal plant, vehicles detection loops, installation

More information

Specifications for Electrical Underground Residential Distribution Systems

Specifications for Electrical Underground Residential Distribution Systems Specifications for Electrical Underground Residential Distribution Systems Specification DDS-2 Revision 13, February 2010 ONCOR ELECTRIC DELIVERY COMPANY SPECIFICATIONS FOR ELECTRICAL UNDERGROUND RESIDENTIAL

More information

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 41 UNDERGROUND ELECTRICAL CONSTRUCTION A. This section specifies the furnishing, installation, and connection of precast manholes and pullboxes with ducts

More information

Gas meter clearances and service installation requirements

Gas meter clearances and service installation requirements FEBRUARY 2018 Gas meter clearances and service installation requirements CALL PSE S CUSTOMER CONSTRUCTION SERVICES AT 1-888-321-7779 OR VISIT PSE.COM/CUSTOMERCONSTRUCTION FOR MORE INFORMATION. Builder/owner/developer

More information

Customer Requirements Conduit Installations, High Voltage

Customer Requirements Conduit Installations, High Voltage Application Requirements for high voltage underground conduit systems, installed by customer or contractor, which will be owned and maintained by Tacoma Power. High voltage underground conduit installations

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 616 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03

More information

If a new residence s electrical service is not located within 200 feet of existing

If a new residence s electrical service is not located within 200 feet of existing Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must

More information

SPECIAL SPECIFICATION 7191 Illumination

SPECIAL SPECIFICATION 7191 Illumination 1993 Specifications For Routine Maintenance Contracts Only Houston District SPECIAL SPECIFICATION 7191 Illumination 1. Description. This Item shall govern for the preventive maintenance, repair and/or

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

ITEM 555 CHAIN LINK FENCING

ITEM 555 CHAIN LINK FENCING ITEM 555 AFTER MARCH 1, 2012 CHAIN LINK FENCING 555.1 Description. This item shall govern for furnishing the quantities of chain link fencing and gates as shown on the plans, including all posts, bracing

More information

APPENDIX A MEASUREMENT AND PAYMENT

APPENDIX A MEASUREMENT AND PAYMENT P-150 DEMOLITION 4.01 Removal of pavement shall be measured per square yard based on the area shown on the plans. Any pavement removed outside the designed limits of removal because the pavement was damaged

More information

SECTION 1208 CHAIN LINK FENCING DESCRIPTION

SECTION 1208 CHAIN LINK FENCING DESCRIPTION SECTION 1208 CHAIN LINK FENCING 1208-1 DESCRIPTION This item covers the requirements for furnishing materials and constructing new chain link fences and gates in accordance with the details included herein

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS TABLE OF CONTENTS 11.01 SCOPE OF WORK... 1 11.02 REFERENCES... 1 11.03 MATERIALS... 2 11.04 GRANULAR & NATIVE BACKFILL... 2 11.05 CONSTRUCTION... 2 11.06 MEASUREMENT FOR PAYMENT... 5 11.07 BASIS OF PAYMENT...

More information

B. Fiberglass for construction in back lot easements placed on cast-in-place base.

B. Fiberglass for construction in back lot easements placed on cast-in-place base. Section 02083 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Fiberglass manholes for unpaved areas placed on top of a precast base to form a manhole. B. Fiberglass for construction in back lot easements

More information

Procedures for Connecting to Central Sewer System

Procedures for Connecting to Central Sewer System Procedures for Connecting to Central Sewer System These procedures and requirements are taken from the Taney County Regional Sewer District s appoved Sewer Use Regulation, Article 4 Building Sewers and

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY CAST-IN-PLACE. Section CAST-IN-PLACE CONCRETE MANHOLES

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY CAST-IN-PLACE. Section CAST-IN-PLACE CONCRETE MANHOLES PART 1 GENERAL 1.01 SUMMARY This Section includes: Section 02081 CAST-IN-PLACE A. Cast-in-place concrete manholes for sanitary sewers and storm sewers, including box sewers. B. Pile-supported concrete

More information

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD SPECIFICATIONS Establishing Minimum Standards for as Related To Fire Protection STANDARD # 103 REVISED 04/01/19 PAGES 7 SCOPE: These specifications shall

More information

Basic Service. This Section provides information regarding a. Introduction

Basic Service. This Section provides information regarding a. Introduction Basic Service Introduction This Section provides information regarding a new electric Basic Service for a single phase service less than or equal to 400 amps, and a three phase service less than 50kW.

More information

CW 3550 Chain Link and Drift Control Fence TABLE OF CONTENTS

CW 3550 Chain Link and Drift Control Fence TABLE OF CONTENTS January 2014 SPECIFICATION CW 3550 R3 CW 3550 Chain Link and Drift Control Fence TABLE OF CONTENTS 1. GENERAL CONDITIONS... 1 3. DESCRIPTION... 1 5. MATERIALS... 1 5.1 Drift Control Fence... 1 5.1.1 Approved

More information

CITY OF GARDEN PLAIN, KANSAS STANDARDS AND SPECIFICATIONS FOR GAS YARD LINES & METER SETS

CITY OF GARDEN PLAIN, KANSAS STANDARDS AND SPECIFICATIONS FOR GAS YARD LINES & METER SETS All gas yard lines shall be installed, repaired or replaced in accordance with the standards and specifications herein and in accordance with the rules and regulations as set forth in the city s OQ, and

More information

SECTION 10 - TRENCHING AND BACKFILLING

SECTION 10 - TRENCHING AND BACKFILLING SECTION 10 - TRENCHING AND BACKFILLING 10.1 General A. Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 10.1.1 Related requirements

More information

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

ITEM NO. 824 SERVICE SUPPLY LINES (WATER) ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 603 APRIL 2010 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF DUCTS TABLE OF CONTENTS 603.01 SCOPE 603.02 REFERENCES 603.03 DEFINITIONS 603.04 DESIGN

More information

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

A. Backfill: Soil material or controlled low-strength material used to fill an excavation. GSA Project No.: GS-P-03-14-AZ-5044 SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Preparing subgrades for walks. 2. Excavating and backfilling for structures. 3. Subbase

More information

New Conduit Specification

New Conduit Specification New Conduit Specification Combines Portions of Sections 715, 783 & 992 into New Section 630. Coordinated Effort Between Traffic Operations, ITS, Lighting, Construction, and Industry New Conduit Specification

More information

UNDERGROUND SERVICES SECONDARY

UNDERGROUND SERVICES SECONDARY Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-

More information

Clarification to Bidders Responses

Clarification to Bidders Responses Clarification to Bidders Responses # Question Answer 1 There is no mention of the excavation work in between the lightning pole columns i.e. the depth of excavation, distance between columns, electrical

More information

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER COMMUNICATIONS LIGHTING Street Lighting Plan 710 Riser... 287 730 Collar for street light pole... 289 731 Pull box... 291 732 Trench for street light

More information

SECTION MOTOR CONTROL CENTER

SECTION MOTOR CONTROL CENTER SECTION 16445 MOTOR CONTROL CENTER PART 1 GENERAL 1.01 DESCRIPTION A. This section covers the contract item Motor Control Center (MCC). The contract item includes demolition and removal of existing MCC;

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown

More information

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems.

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems. Date Description of Change Pages / Sections Modified ID 6/15/16 Entire document - mgl44 PART 1 - INTRODUCTION 1.1 PURPOSE A. This section is intended to provide design guidelines for Utility Direct Buried

More information

SECTION PACKAGE BOOSTER PUMP STATIONS

SECTION PACKAGE BOOSTER PUMP STATIONS SECTION 331223 PACKAGE BOOSTER PUMP STATIONS Scope: The Contractor shall install a pump station at two locations to be determined by the Owner. These pump stations shall be designed to deliver flow to

More information

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations. Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 616 APRIL 2018 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03 DEFINITIONS

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Addendum #4 NEW LOW HEAD OXYGEN SYSTEM Contractor EXHIBIT T SPECIAL PROVISIONS SECTION METAL SHADE STRUCTURE

Addendum #4 NEW LOW HEAD OXYGEN SYSTEM Contractor EXHIBIT T SPECIAL PROVISIONS SECTION METAL SHADE STRUCTURE SECTION 13 34 00 METAL SHADE STRUCTURE PART 1 - GENERAL 1.01 STRUCTURE TYPE A. Structure shall be free standing rigid frame and gable roof with slopes as indicated. Structure shall also include foundation,

More information

REQUEST FOR PROPOSAL Asphalt & Concrete Repair

REQUEST FOR PROPOSAL Asphalt & Concrete Repair REQUEST FOR PROPOSAL 2017 Asphalt & Concrete Repair English Landing Elementary School Union Chapel Elementary School Lakeview Middle School Park Hill High School Prairie Point Elementary School Congress

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF MODULAR PAN SYSTEM PART 1 GENERAL 1.1

More information

PERMANENT PAVEMENT REPAIR NO SCALE

PERMANENT PAVEMENT REPAIR NO SCALE SAWCUT EXISTING PAVEMENT 2" BITUMINOUS CONCRETE SURFACE COURSE, CLASS 2 (MIN) CLEAN EDGE PRIOR TO PAVING AND PAINT WITH LIQUID BITUMEN. INSTALL SEALANT OVER JOINT UPON COMPLETION 2" BITUMINOUS CONCRETE

More information

Bear Exhibit Fence Upgrades. The following modifications are hereby made part of the contract documents:

Bear Exhibit Fence Upgrades. The following modifications are hereby made part of the contract documents: ADDENDUM TO BID T2017-04 Metropolitan Park District Department of Planning, Design and Development 4702 South 19 th Street Tacoma WA 98405 Date Prepared: November 17, 2017 Bid Number: T2017-04 Addendum

More information

SECTION STORM SEWER COLLECTION SYSTEM

SECTION STORM SEWER COLLECTION SYSTEM SECTION 02722 STORM SEWER COLLECTION SYSTEM PART 1 GENERAL 1.01 SUMMARY A. This section addresses the installation of storm sewer collection mains and includes the acceptable products, materials, and construction

More information

SECTION CHAIN LINK FENCES AND GATES (PARK)

SECTION CHAIN LINK FENCES AND GATES (PARK) SECTION 02821 CHAIN LINK FENCES AND GATES (PARK) PART I GENERAL 1.1 SECTION INCLUDES A. Installation of chain link fences, and gate units provided by single source including erection accessories, fittings,

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Sheet 1 of 7 NOTE: This special provision is generally written in the imperative mood. The subject, the

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

TERMS AND CONDITIONS FORM

TERMS AND CONDITIONS FORM TERMS AND CONDITIONS FORM IMPORTANT : READ ALL THE FOLLOWING TERMS AND CONDITIONS AND SIGN THE ACCEPTANCE CLAUSE FOLLOWING IT 1. The offers through post or hand delivery should be addressed to The Head,

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

Special Provision No. 541S01 October OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced with the following:

Special Provision No. 541S01 October OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced with the following: CHAIN LINK FENCE - Item No. GATES - Item No. Special Provision No. 541S01 October 1998 AMENDMENT TO OPSS 541, DECEMBER 1990 OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced

More information

A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION ALBERTVILLE, ALABAMA

A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION ALBERTVILLE, ALABAMA McKee and Associates Architecture and Interior Design Addendum No. FOUR Date: 09.24.18 Project: A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Change History Date Description of Change Pages / Sections Modified Change Approver Initials 8/1/17 Update sections Materials and Special Requirements 3 F. 2. 4 H. 2.; 10. & 11(added) 6/15/16 Updated division

More information

DESIGN GUIDELINES WIRING AND CONDUITS PAGE 1 of 7

DESIGN GUIDELINES WIRING AND CONDUITS PAGE 1 of 7 DESIGN GUIDELINES WIRING AND CONDUITS PAGE 1 of 7 1.1. REFERENCE STANDARDS 1.1.1. Publications listed below (including amendments, addenda, revisions, supplements and errata) form a part of this specification

More information

1. Contractor shall obtain a valid electrical permit from the Town of Perinton.

1. Contractor shall obtain a valid electrical permit from the Town of Perinton. Fairport Electric allows one electric service location per tax parcel. To obtain this service, Fairport Electric will require the following prior to energization. IN THE TOWN OF PERINTON: 1. Contractor

More information

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines.

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines. SECTION 15.0 PIPE TRENCHES 15.01 Clearing and Grubbing The developer/contractor shall be responsible for the clearing and grubbing of the entire right-of-way. See Sections 13.01 and 14.01. Clearing and

More information

LABOR AND MATERIAL PROPOSAL

LABOR AND MATERIAL PROPOSAL LABOR AND MATERIAL PROPOSAL CLIENT: CITY OF KINSTON, NC PROJECT: POD NO. 2 PROJECT NO.: 15-8103-8015 CONTRACTOR: DATE: GROUP DESCRIPTION QTY UNIT 3.1 Structures 1 Lot UNIT PRICING CONTRACTOR- LABOR FURNISHED

More information