Brad Cordek. Lighting - Recessed compact fluorescent faculty, offices, classrooms.

Size: px
Start display at page:

Download "Brad Cordek. Lighting - Recessed compact fluorescent faculty, offices, classrooms."

Transcription

1 Project Overview - Dates of Construction: Dec May 2006 Project Size: Approx. 66,500 square feet Cost Information: GMP contract $21.8 million Project Delivery: Design-Bid-Build Building Description - The has some very unique interior space layouts such as recital/dance studios, set design/ prep/construction areas, orchestra/ensemble practice areas, and a 600 seat auditorium complete with full stage, sound/lighting systems, and a 12,000 pound orchestra lift. All of these areas possess the most exquisite high-end finish and millwork. Exterior wise, MACA s skin is a combination of stone, glass and metal panels, with balconies surrounding the building on three sides. The also has an attached two-story performing theater constructed as a stone cylinder. Project Team - Owner: Mercersburg Academy General Contractor: James G. Davis Construction Architect: Polshek Partnership Architects L.L.P. Structural Engineer: Severud Associates MEP Engineer: Thomas Polise Consulting Engineer, P.C. Civil Engineer: RHS Engineering, Inc. Geotechnical Engineer: Geoconcepts Engineering, Inc. Structural - Foundation composed of spread footings ( tons per square foot rock bearing). MACA Site has limestone pockets, which can cause sink holes to develop. Mezzanine, Ground, Second, and Upper Balcony floors composed of steel framing system with 5.5 NWC slabs on metal decking. Low Roof floor composed of steel framing system with 3 metal rook decking. Catwalk and High Roof areas composed of steel framing system with 5.5 NWC slabs on metal decking. Mechanical - 8 supply and return fans (varies from 35,000 3,500 CFM s). 7 fan coil units. 2 chilled and hot water centrifugal pumps. 1 exhaust and toilet exhaust fan. 1 heat exchanger. Lighting - Recessed compact fluorescent faculty, offices, classrooms. Pendant mounted fluorescent dance studios. Recessed round fluorescent corridors, theater. Electrical - Incoming service at 5 KV. Comes into 1500 KVA transformer (4160 V primary - 480/277 V secondary). Switchboards: Main A, Main MDP-M, Theater DP- TA, Theater DP-TB, Emergency Distribution. Brad Cordek CM Option

2 Table of Contents Section Pages A. Executive Summary 1 B. Project Delivery System 2 C. Project Schedule 3 D. Building Systems Summary 3-4 E. Project Cost Evaluation 5-6 F. Site Plan of Existing Conditions 7 G. Local Conditions 7 H. Client Information 7-8 Appendix 9

3 1. Existing Construction Conditions A. Executive Summary Tech Assignment 1 touched upon some important aspects of MACA. The project will be delivered through the least risk, traditional design-bid-build approach. Davis Construction is serving as the general contractor in this arrangement holding a GMP contract with Mercersburg Academy. Reviewing the project schedule shows that the will be constructed over a 19 month schedule. MACA has no sequencing issues or phased construction. A table containing the building systems was also developed. The Center for the Arts requires demolition and excavation support, and has steel framing, CIP concrete, masonry, a mechanical system, an electrical system, and a curtain wall system. The curtain wall system in MACA proves to be most interesting in the fact that it is a combination of exposed teak and mahogany, steel, and glass. The exposed wood presents some durability issues. MACA will cost $16.29 million (building costs only). This price increases to $21.76 million when the site work, permitting, and general conditions are added in. Both the D4 and R.S. Means estimates came in lower at $14.2 and $11.16 million (building costs only) respectively. The site plan for the was compiled with Mercersburg Academy in mind. The positions of items, such as the crane, have been located as far out of the line of sight as possible. MACA jobsite fencing near the mall area on the campus has fabric lining to further protect the scenic views at Mercersburg Academy. Local conditions at Mercersburg parallel the attributes. The building is located on spread footings, but careful attention must be paid for the presence of sink holes, which occur from porous limestone pockets below the sites surface. Mercersburg Academy is constructing the to replace an outdated Boone Hall (home of the theater and musical departments). They expect this building to be constructed in a timely manner at a reasonable cost to Mercersburg, while also consistently maintaining the scenic beauty of the campus. 1

4 B. Project Delivery System MACA follows a traditional delivery system of design-bid-build. The owners, Mercersburg Academy, addressed the following criteria when deciding upon a delivery system: financial, time, design, and quality. They looked for a system that provided the least risk to the project. The traditional approach has been the predominant delivery system for construction over the years. It brings a sense of security to any owner in that it presents the least uncertainty on how the project will progress, while also allowing contractual protection for the owner. This in turn represents the least level of risk. The following organizational structure outlines the hierarchy within the MACA project. It also shows the relationships between key project players, being a contract or just an informal relationship. Owner Mercersburg Academy Debbie Rutherford LS Owners Rep JFW Project Management James Wilson FB GMP Theater Consultant Theater Projects Consultants Architect Polshek Partnership Charles Brainerd GC James G. Davis Construction Ted Holt - PM LS Engineers Structural: Severud Associates MEP: Thomas Polise Consulting Eng. Civil: RHS Eng. Geotech: GeoConcepts Eng. LS Acous. Consultant Acoustic Dimensions Contract Legend: LS Lump Sum GMP Guaranteed Maximum Price FB Fee Based Contract (typical) 2

5 C. Project Schedule Summary A one page MS Project schedule for MACA can be found attached in the Appendix. The foundation sequence of the schedule basically consists of excavation, spread footings, and a partial retaining/foundation wall on three sides of the building. On the other hand, the structural activities in the schedule consist of a slab on grade, slabs on metal decking, and steel columns and beams. Lastly, wall/floor finishes, doors/casework/millwork, and fixtures and trim compile the finishing sequence. D. Building Systems Summary Yes No Work Scope If yes, address these questions / issues X Demolition Required? Involves complete demolition and removal of existing building and site components, salvage of some existing items, and preparation of existing areas to receive work. Demolition does not include any asbestos or hazardous material removal. X Structural Steel Frame MACA has a combination of diagonal bracing and lateral moment connections as its bracing system. Every floor, except the SOG, is composed of a 5.5 NWC 18-gauge composite slab on metal deck. A large mobile crane will place the steel from locations on both the East and West sides of the footprint. X Cast in Place Concrete The only CIP concrete on the job are the spread footings, floor slabs, and a two-story architecturally exposed concrete exterior foundation wall on the South, East and North sides of the building. Placement will be by truck. The formwork selection for these features is usually made by the subcontractor. Since MACA is not under construction yet, an assumption of plywood can be made for the formwork. 3

6 X Precast Concrete NA X Mechanical System The mechanical room is located on the Lower Level floor on the North side of the building. An all air, VAV system is employed in the. It distributes air through aluminum ductwork. MACA is protected by a standpipe sprinkler system at a temperature classification of 165 F. X Electrical System Incoming service at MACA is 5 KV with a 1500 KVA transformer. The main switchboard is a 277/480 V 3 phase 4 wire 3000 amp bus. A 230 KW emergency generator provides back-up power. X Masonry The only stone used on MACA is a two story high (Lower Level Mezzanine) Pennsylvania limestone and bluestone veneer located on the North, South and West elevations. This non-load bearing façade is connected to the building with ties. The stone will be completed one building face at a time with minimum scaffolding. X Curtain wall The window wall system on MACA is composed of teak & mahogany, steel, and glass units. The design responsibility is that of the architects. A Duratherm system wall is specified in the specs, so this curtain wall system lends itself well to a custom installation. X Support of Excavation The initial excavation strategy will involve an attempt to step back the walls at a safe slope in order to perform the excavation. If there is not enough room, another system will be explored. Either way, the system will not be permanent. There will be no need for a dewatering system. 4

7 E. Project Cost Evaluation Actual Building Construction Cost and Costs per square foot (*Not including land costs, site work, permitting, general conditions etc.): o $16.29 million o $245/s.f. Total Project Costs and Costs per square foot: o $21.76 million o $344.85/s.f. Major Building Systems Costs and Costs per square foot: o Structural System $1.76 million $26.56/s.f. o Mechanical System $2.82 million $42.41/s.f. o Electrical System $1.78 million $26.87/s.f. o Theater Performance Equipment $1.64 million $24.73/s.f. Design Contingency and % design contingency related to Construction Costs: o $779,410 o 4.8% Parametric estimate from D4Cost Estimating Software (please find a complete copy of the estimate attached in the Appendix): o Smart averaged three separate buildings: Herberger Theater Center 80,000 s.f. / 827 seat theater / 327 seat stage American Music Theater Lancaster, PA Fine & Performing Arts Center 84,000 s.f / 600 seat theater with orchestra lift o Overall Building Cost: $14.2 million $21.35/s.f. o Structural System $2.67 million $40.19/s.f. o Mechanical System $1.66 million $25.03/s.f. 5

8 o Electrical System $2.04 million $30.71/s.f. Square Foot Estimate from R.S. Means 2004 Square Foot Costs: o Closest building type to the is College, Classroom, 2-3 stories 4 story building 66,500 s.f. 650 l.f. perimeter o Overall Cost from Means (please find the complete cost data attached in Appendix): $11.16 million $167.87/s.f. A high school center for the arts turned out to be difficult to price as far as the estimates are concerned. The cost data was relatively unknown. There were some pretty distinct differences between both the D4 and R.S. Means estimates when compared with the actual building cost. The D4 estimate actually proved to be the closer of the two, with a difference of only $2 million less than the actual building cost. Accounting for this difference was the inconsistencies between the mechanical and electrical systems, along with the theater performance equipment. The other estimate from R.S. Means did not come as close, posting a difference of $5 million less than the actual building cost, doubling the D4 estimate. The primary driving force for this discrepancy is the fact that the closest match to the in Means was a 2-3 story college classroom. Most of this cost difference is caught up in the theater area, as the college classroom did not have a theater. 6

9 F. Site Plan of Existing Conditions The Site Plan of Existing Conditions is attached in the Appendix. G. Local Conditions Some local conditions exist which can influence a project. In South-central Pennsylvania where Mercersburg is located, there is no distinct preferred method of construction, although steel buildings are the typical structural system. Labor-wise, MACA is primarily a non-union job, matching the local labor force for the most part. Parking regulations also exist on the site because of the lack of parking space. Only the superintendent and foreman of subcontractors will be allowed parking directly on site. It will be the responsibility of each subs foreman to bus the remaining laborers onto the site from a parking lot one mile away. Recycling and tipping fee information is not available. In the Geo-technical Report, it was concluded that the proposed building may be supported on spread footings placed on natural soils, bedrock, or new compacted fill. Limestone bedrock, disintegrated limestone, natural lean clay and silt soils, or new compacted fill should be encountered at normal spread footing depths. Interestingly, subsurface conditions on the site are known to contain limestone pockets, which are a red flag indicator of possible sink holes. To ensure that these sink holes are not present underneath the footings, an air track probe will be conducted at each footing location. Finally, a permanent under-floor sub-drainage system, including sumps and pumps, will be necessary to maintain ground water levels below the lowest level. H. Client Information The owner of the is Mercersburg Academy, a private high school in South-central Pennsylvania. This facility is being constructed to replace the old, out-dated existing Boone Hall, which was home to the theater and musical departments at Mercersburg. Cost expectations for the project are fairly high, as the building is currently over budget. Mercersburg doesn t want an extremely high priced building, but they do expect a very high quality of finishes, which inherently drives up the price. Overall building quality and safety both carry high expectations with Mercersburg as they do with any owner. Mercersburg Academy keeps their campus facilities, buildings, and landscaping immaculate. Schedule-wise, there is an ample schedule length of 20 months, so there is no rush to fast track the project. Since there are no phased occupancy requirements with the building, sequencing will not be an issue; the building will be occupied upon final building completion. There are a few keys to completing the project to the owner s satisfaction. Mercersburg expects 7

10 a high quality, on time. They want the construction to occur safely and the jobsite to be as less of an eyesore to the scenic campus as possible. 8

11 Tech Assignment #1 Appendix - MACA Construction Schedule - R.S. Means and Cost Data - MACA Site Plan of Existing Conditions 9

12 Mercersburg Academy Construction Schedule ID Task Name Duration Start Finish 1 General Contractor Selection 4 wks Fri 4/16/04 Thu 5/13/ Mar Apr a Jun Jul AugSep Oct NovDec Jan e Mar Apr a Jun Jul AugSep Oct NovDec Jan e Mar Apr a Jun Jul AugSep Oct General Contractor Selection 2 Design Packages 9.4 wks Wed 5/26/04 Mon 8/2/04 3 Budget, Bid & Establish Project GMP 15.8 wks Fri 6/4/04 Fri 9/24/04 4 Release Major Subcontractors 0 wks Mon 9/20/04 Mon 9/20/04 5 Submit / Approve / Release Key Materials 36.4 wks Wed 8/25/04 Fri 5/13/05 Design Packages Budget, Bid & Establish Project GMP 9/20 Release Major Subcontractors Submit / Approve / Release Key Materials 6 7 CONSTRUCTION 90.1 wks Mon 9/20/04 Thu 6/29/06 CONSTRUC 8 NTP 0 days Fri 10/1/04 Fri 10/1/04 10/1 NTP 9 Initial Siteworks & Demolition 10 wks Mon 9/20/04 Tue 11/30/04 10 Footings & Elevator Pit 3 wks Wed 12/1/04 Tue 12/21/04 11 Underslab MEP 2 wks Wed 12/15/04 Thu 12/30/04 12 Concrete floor slabs 12 wks Fri 12/31/04 Fri 3/25/05 13 Steel Superstructure & Metal Decking 11.5 wks Thu 1/20/05 Mon 4/11/05 14 Building Structure Complete 0 days Thu 4/28/05 Thu 4/28/05 15 Façade, Roofing, Porch 22 wks Thu 4/28/05 Mon 10/3/05 16 Building Envelope Complete 0 days Mon 10/3/05 Mon 10/3/05 17 Lower Level / Studio Theater / Lower Orchestra Pit MEP Rough-In & Millwork 44.5 wks Thu 5/19/05 Wed 4/5/06 18 Ground Floor / Main Theater / Stage MEP Rough-In & Millwork 43 wks Fri 6/3/05 Fri 4/7/ nd Floor / Lower Balcony MEP Rough-In & Millwork 34 wks Fri 6/17/05 Fri 2/17/ rd Floor / Upper Balcony / Catwalk / Gridiron MEP Rough-In & Millwork 40.5 wks Fri 7/1/05 Wed 4/19/06 21 System Start Up & Testing 2 wks Wed 4/5/06 Tue 4/18/06 22 Complete Siteworks - Utilites/Hardscape/Infrasctructure 30 wks Mon 6/6/05 Mon 1/9/06 23 Commissioning, Weather Delay, Final Inspections 10 wks Wed 4/19/06 Wed 6/28/06 24 Project Substantial Completion 0 days Thu 6/29/06 Thu 6/29/06 Initial Siteworks & Demolition Footings & Elevator Pit Underslab MEP Concrete floor slabs Steel Superstructure & Metal Decking 4/28 Building Structure Complete Façade, Roofing, Porch 10/3 Building Envelope Complete Lower Level / Studio The Ground Floor / Main The 2nd Floor / Lower Balcony ME 3rd Floor / Upper Balc System Start Up & Tes Complete Siteworks - Utilites/Hard Commissioni 6/29 Project Subs

13 Estimate of Probable Cost Mercersburg Academy - Center for th - Nov PA - Lancaster Prepared By: Prepared For:,, Fax: Fax: Building Sq. Size: Site Sq. Size: Bid Date: Building use: Educational No. of floors: 4 Foundation: Spread Footing No. of buildings: Exterior Walls: Curtainwall Project Height: Interior Walls: Drywal/Gypsum Sheathing 1st Floor Height: Roof Type: EPDM 1st Floor Size: Floor Type: Project Type: NEW Division Percent Sq. Cost Amount 00 Bidding Requirements , General Requirements ,372, Site Work , Concrete ,349, Masonry , Metals ,322, Wood & Plastics , Thermal & Moisture Protection , Doors & Windows , Finishes ,347, Specialties , Equipment , Furnishings , Special Construction Conveying Systems , Mechanical ,664, Electrical ,041,891 Total Building Costs ,143,515

14 R.S. Means Cost Calculation - 4 story building - 66,500 s.f l.f college classroom closest building to $121.20/s.f. from the chart (steel frame, face brick, concrete block back-up) Perimeter Adjustment ( )/100 l.f. = -$0.01 Height Adjustment (0.75/ft.)(20 ft.) = +$15.00 Adjusted S.F. Value = $ Total Cost = ($136.19/s.f.)(66,500 s.f.)(0.98)(1.103)(1.10) = $10,768,646 Additions $193,347 Basement $97,050 Elevators $1,675 Sound System $102,600 Auditorium Seating Grand Total = $11.16 million

15

THE PLAZA AT PPL CENTER ALLENTOWN, PA

THE PLAZA AT PPL CENTER ALLENTOWN, PA Building Function and Primary Use The owner of the new Plaza at PPL Center is Liberty Property Trust, but the primary tenant is PPL, which will use the building as the headquarters for its new subsidiaries

More information

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor

More information

TECHNICAL ASSIGNMENT 2

TECHNICAL ASSIGNMENT 2 PENN STATE AE SENIOR THESIS 2011-2012 TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis TECHNICAL ASSIGNMENT 2 Cost and Schedule Analysis BRIANNE KYLE Construction Management Thesis Advisor: Dr. Chimay

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley Existing Project Conditions General Conditions Estimate The Center for Health Research and Rural Advocacy is constructed under the supervision of the Geisinger Facilities Division. The project team develops

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

ECMC Skilled Nursing Facility Architectural Engineering Senior Thesis AE 481W Thesis Proposal Dr. Ali Memari January 13 th, 2012

ECMC Skilled Nursing Facility Architectural Engineering Senior Thesis AE 481W Thesis Proposal Dr. Ali Memari January 13 th, 2012 ECMC Skilled Nursing Facility Architectural Engineering Senior Thesis 2011 Class: Subject: Faculty Consultant: Submitted: AE 481W Thesis Proposal Dr. Ali Memari January 13 th, 2012 Table of Contents Executive

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

MANHATTAN COLLEGE STUDENT COMMONS

MANHATTAN COLLEGE STUDENT COMMONS MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons

More information

HOTEL NORTHEAST U.S. JORDAN RUTHERFORD STRUCTURAL OPTION FACULTY ADVISOR DR. THOMAS BOOTHBY AE SENIOR THESIS APRIL 8, 2013

HOTEL NORTHEAST U.S. JORDAN RUTHERFORD STRUCTURAL OPTION FACULTY ADVISOR DR. THOMAS BOOTHBY AE SENIOR THESIS APRIL 8, 2013 HOTEL NORTHEAST U.S. JORDAN RUTHERFORD STRUCTURAL OPTION FACULTY ADVISOR DR. THOMAS BOOTHBY AE SENIOR THESIS APRIL 8, 2013 HOTEL N.E.U.S. BUILDING INFORMATION SITE Located in the Northeast United States

More information

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form. Project: Ben Steele Middle School Addendum #: 2 Date Issued: January 11, 2016 Description of Addendum & Attachments: 1. A Pre Bid Meeting is scheduled for January 18 th, 2016. Attendance is strongly encouraged,

More information

Voigt 1. Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1.

Voigt 1. Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1. Voigt 1 Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1 Executive Summary Located in northwest Washington, D.C. at the corner of

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report Michael A. Troxell Structural Option Advisor: Professor Parfitt College of Business Administration Oct. 5, 2005 Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

More information

2003 International Residential Building Code

2003 International Residential Building Code 2003 International Residential Building Code Section R305 Ceiling Height Habitable rooms, hallways, corridors, bathrooms, toilet rooms, laundry rooms and basements shall have a ceiling height of not less

More information

Mount Vernon Elementary School Grades PK 5

Mount Vernon Elementary School Grades PK 5 Barbour County Schools Comprehensive Educational Facilities Plan 2010-2020 Mount Vernon Elementary School Grades PK 5 Blackwood Associates, Inc. / MSES consultants, Inc. / Roy Blizzard and Associates Mount

More information

EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire

EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire Additional Instructions and Clarifications 1. Please review ARC 4496 before beginning the project identification

More information

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Executive Summary The proposed thesis will include an investigation of two different alternative structural

More information

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University November 16 th, 2007 William J. Buchko AE 481w Senior Thesis The Pennsylvania State University Thesis Advisor: Kevin Parfitt Table of Contents Executive Summary... 3 Structural System Overview Foundation...

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

Project Address: Name of Person Completing Form:

Project Address: Name of Person Completing Form: Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties

More information

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404 LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:

More information

The Rockville Library Final Thesis Proposal

The Rockville Library Final Thesis Proposal The Rockville Library Final Thesis Proposal Construction Management Advisor: Dr. Messner Table Of Contents I. Cover Page Pg. 1 II. Table Of Contents Pgs. 2-3 III. Executive Summary Pg. 4 IV. Thesis Abstract

More information

JMU Capital Projects SWaM Outreach Event Presentations

JMU Capital Projects SWaM Outreach Event Presentations JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom

More information

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8 WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs November 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements....................................

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using

More information

Devin Learn Construction Management AE Senior Thesis

Devin Learn Construction Management AE Senior Thesis Devin Learn Construction Management AE Senior Thesis 5 th and 6 th Floor Fit-Out & Cardiac Elevator Addition Introduction Vs. Retro- Pre-Cast Floor System s at ICRA Partitions and Conclusions Questions

More information

KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner

KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner McLean, Virginia Brooke Helgesen Advisor: Dr. Chimay Anumba Construction Management PRESENTATION OUTLINE Cost/ Schedule Impact KAISER PERMANENTE

More information

Structural Inspection

Structural Inspection General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized

More information

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE - 268-5161 Residential Accessory Structures This information has been compiled for the benefit of any person

More information

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST This list is provided as a guide to help you understand the information that must be contained on the construction drawings. This list is not all-inclusive of all building codes but is used as a general

More information

Salt lake city Public Safety Building. Case Study CS 2. Grounded in strength.

Salt lake city Public Safety Building. Case Study CS 2. Grounded in strength. Salt lake city Public Safety Building CS 2 Case Study Grounded in strength. Forterra Structural & Specialty Products High-Efficiency Design, Precast Envelope System Put Dramatic Public Safety Building

More information

Johns Hopkins Graduate Student Housing. Thesis Proposal. 929 North Wolfe Street Baltimore, Maryland Brad Oliver Structural Advisor: Professor Memari

Johns Hopkins Graduate Student Housing. Thesis Proposal. 929 North Wolfe Street Baltimore, Maryland Brad Oliver Structural Advisor: Professor Memari Johns Hopkins Graduate Student Housing 929 North Wolfe Street Brad Oliver Structural Advisor: Professor Memari 12/09/2011 Table of Contents Executive Summary -... 3 Introduction... 4 Structural Systems...

More information

MEMORIAL SLOAN-KETTERING CANCER CENTER

MEMORIAL SLOAN-KETTERING CANCER CENTER MEMORIAL SLOAN-KETTERING CANCER CENTER SENIOR THESIS PRESENTATION THE PENNSLYVANIA STATE UNIVERSITY DEPARTMENT OF ARCHITECTURAL ENGINEERING PRESENTATION OUTLINE INTRODUCTION BUILDING DESCRIPTION EXISTING

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS FLOOR SYSTEM ANALYSIS Objective The objective of the following breadth study is to determine if an alternative floor system for Building N would be more advantageous than the existing floor system. The

More information

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours Basic Edition Standard Estimate Report Page 1 Name 1000 General Conditions 1107 Professional Consultant 10 Surveying 1.00 day 600.000 /day 600 - - - - - - 600 Professional Consultant 600 600 8.00 hours

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

Structural Redesign Gravity System

Structural Redesign Gravity System Redesign Gravity System Design Considerations A composite floor system was used for this design to maximize the efficiency of the material being used. This type of system requires less material and provides

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT 1 East Franklin Street Phone: 301-790-4163 Third Floor Hagerstown, MD 21740 Fax: 301-791-2650 BUILDING PERMIT APPLICATION FOR RESIDENTIAL ACCESSORY

More information

LIFE SCIENCES BUILDING STRUCTURAL CONCEPTS AND EXISTING CONDITIONS

LIFE SCIENCES BUILDING STRUCTURAL CONCEPTS AND EXISTING CONDITIONS Structural Technical Report 1 LIFE SCIENCES BUILDING STRUCTURAL CONCEPTS AND EXISTING CONDITIONS Prepared for: Dr. Aly M. Said Dr. Thomas Boothby Professor Kevin Parfitt Dr. Charles D. Cox Prepared by:

More information

Bioscience Research Building

Bioscience Research Building Bioscience Research College Park, Maryland Presentation Agenda and Construction Features Analysis Analysis Research Features Presentation Agenda Construction Features: CM at Risk 2 year schedule (July

More information

Global Village Rochester Institute of Technology Rochester, New York

Global Village Rochester Institute of Technology Rochester, New York Presentation Outline Welcome Introduction Architecture Existing Structure Problem Statement Arch. Breadth Structural Depth Conclusion Questions Global Village Rochester Institute of Technology Rochester,

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

191 National Business Park Annapolis Junction, MD

191 National Business Park Annapolis Junction, MD Annapolis Junction, Maryland Kara Prince Architectural Engineering Option Senior Thesis 2005 Project Team Annapolis Junction, MD Owner: Corporate Development Services General Contractor: Riparius Construction,

More information

WOOD USE IN NONCOMBUSTIBLE BUILDINGS

WOOD USE IN NONCOMBUSTIBLE BUILDINGS INTRODUCTION The National Building Code of Canada (NBCC) 1 requires that some buildings be of noncombustible construction under its prescriptive requirements. Its use in certain types of buildings such

More information

4 EXTREME FOUNDATION PANELS

4 EXTREME FOUNDATION PANELS 4 EXTREME FOUNDATION PANELS For House Crawl Space On Concrete Footings 1. The type of soil is a factor in determining foundation construction details such as footing design, backfill, and drainage provisions.

More information

Elevated Slab Sequence

Elevated Slab Sequence Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)

More information

Peter Dahl Technical Assignment #1 Executive Summary

Peter Dahl Technical Assignment #1 Executive Summary Primary Faculty Consultant: Riley Due Date: Wednesday, October 8 th, 2003 Technical Assignment #1 Existing Site Conditions Executive Summary The construction of any tunnel is unique, but when you put that

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

Structural Technical Report #2 By Robert Whitaker

Structural Technical Report #2 By Robert Whitaker Structural Technical Report #2 By Robert Whitaker Robert Whitaker Structural ~ Parfitt Parkview at Bloomfield Station Bloomfield, NJ 10-31-05 Executive Summary This report covers the comparative redesign

More information

Proposal. PricewaterhouseCoopers Oslo, Norway

Proposal. PricewaterhouseCoopers Oslo, Norway Proposal James Wilson Structural Option AE 481W Senior Thesis The Pennsylvania State University Faculty Consultant: Professor M. Kevin Parfitt Table of Contents Executive Summary...2 1. Existing Conditions...3

More information

One and Two Family Additions

One and Two Family Additions One and Two Family Additions An addition to a house, duplex, garage, or an accessory structure requires a building permit prior to performing any construction. Building Department & Permit Office Mon-Fri

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

Margaret Batts Tobin Laboratory

Margaret Batts Tobin Laboratory Roof Evaluation of Margaret Batts Tobin Laboratory The University of Texas At San Antonio Performed for UTSA Zero/Six Consulting, LLC 8423 Stewart Road Galveston, Texas 77554 409 740 0090 voice Table of

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal The following documentation provides an example submittal for the LEED-NC v2.1 Energy & Atmosphere Credit 1 (EAc1). This sample EAc1 submittal

More information

THE POTTING SHED PF-1D-1144 CONSTRUCTION DRAWINGS PROJECT PLAN INDEX FOUNDATION / FLOOR PLAN 2 ROOF PLAN 3

THE POTTING SHED PF-1D-1144 CONSTRUCTION DRAWINGS PROJECT PLAN INDEX FOUNDATION / FLOOR PLAN 2 ROOF PLAN 3 THE POTTING SHED CONSTRUCTION DRAWINGS Corresponds with the garden shed built for Progressive Farmer s Idea House & Farmstead, August 2004 issue, page 42 Topped with a handsome roof and trimmed with custom-cut

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

BOWIE LEARNING CENTER

BOWIE LEARNING CENTER BOWIE LEARNING CENTER Bowie Learning Center BUILDING DATA BOWIE LEARNING CENTER 900 North Elm St., Weatherford, TX 76086 Year Built 1936 No. of Buildings No. of Portables 0 Approx. Total Square Footage

More information

HILLSBOROUGH TOWNSHIP CODE ENFORCEMENT

HILLSBOROUGH TOWNSHIP CODE ENFORCEMENT HILLSBOROUGH TOWNSHIP CODE ENFORCEMENT SAMPLE GUIDE FOR RESIDENTIAL DECKS revised 7 16 Call before you dig! 1 800 272 1000 New Jersey One Call. Utility Mark Out. THIS GENERIC GUIDE IS NOT ALL INCLUSIVE

More information

Chapel House- Design Process- Envelope and Energy savings

Chapel House- Design Process- Envelope and Energy savings Colgate - Chapel House Renovation Heating Energy - Summary rev. 9/23/16 With Actual Blower Door Assembly R-Values Other Loads DORMITORY Stone Wall Window Spandrel Sill/Band Slab Edge (below grade) Roof

More information

Technical Assignment 2

Technical Assignment 2 Central Bed Tower Expansion University of Virginia Charlottesville, VA Technical Assignment 2 October 19, 2011 Sarah Bell Faculty Advisor: Craig Dubler Construction Management Executive Summary University

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

DOCUMENT BID FORM - STIPULATED SUM

DOCUMENT BID FORM - STIPULATED SUM DOCUMENT 004113 BID FORM - STIPULATED SUM Architect s Project No. 2007024EXC Project: Excell Academy for Tenant: Excell Academy for Higher Learning, Inc. Higher Learning Interiors Package 6510 Zane Avenue

More information

Abington Memorial Hospital Abington, PA. Project Description

Abington Memorial Hospital Abington, PA. Project Description Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene October 6, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Completed Hardscapes East of Building C. Completed Building D Dumpster Pad. Completed Brick on Site Wall North of Building D. Completed

More information

The designer shall also submit additional information required by the University as described and underlined below.

The designer shall also submit additional information required by the University as described and underlined below. I. Structural Engineering Submissions The designer shall submit all information required by the State Construction Office (SCO) as described in the State Construction Manual Chapter 300 - Project Design

More information

Totaling approximately 617,000

Totaling approximately 617,000 Totaling approximately 617,000 sq. ft, the mixed-use Embassy Suites hotel development is among the largest of several newly built hotels in the business district adjoining New York s bustling Wall Street

More information

STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804

STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804 STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION PROJECT #: CAP 1804 FRANCONIA NOTCH STATE PARK FRANCONIA, NEW HAMPSHIRE BID SET 8/4/2017 DRAWING LIST:

More information

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS **************************************************************************

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-02 42 91 (May 2010) ------------------------- Preparing Activity: USACE Nontechnical Title Revision (August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS SECTION TABLE

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

Table of Contents for Guide Specifications

Table of Contents for Guide Specifications Table of Contents for Guide Specifications 01270A Measurement and Payment 01355A Environmental Protection 01356A Storm Water Pollution Prevention Measures 01421 Basic Storm Water Pollution Prevention Plan

More information

62 POTOMAC STREET WEST ROXBURY, MA 02132

62 POTOMAC STREET WEST ROXBURY, MA 02132 62 POTOMAC STREET SET P R O J E C T T E A M COVER 1. ALL WORK SHALL BE IN COMPLIANCE WITH ALL APPLICABLE LOCALS BUILDING CODES AND REGULATIONS. 2. CONTRACTOR SHALL BE RESPONSIBLE FOR S REQUIRED FOR CONSTRUCTION

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

THE STRATA UNIT May 25, 2008

THE STRATA UNIT May 25, 2008 THE STRATA UNIT May 25, 2008 Over the years, we have been asked time and time again from our experience as a cost consultant and a project manager from both a restoration and renovation point of view What

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules

More information

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866) TECHNICAL NOTE On Cold-Formed Steel Construction $5.00 Light Gauge Steel Engineers Association Washington, D.C. 20005 Toll Free (866) 465-4732 www.lgsea.com DESIGN OF BY-PASS SLIP CONNECTORS IN COLD-FORMED

More information

Kennedy Krieger Institute Outpatient Medical Center Baltimore, Maryland

Kennedy Krieger Institute Outpatient Medical Center Baltimore, Maryland Kennedy Krieger Institute Katie Sennett - CM Senior Thesis Advisor: Dr. Messner April 9, 2008 Kennedy Krieger Institute Project Team Construction Management Estimated Project Cost: $35,000,000 Size: 115,000

More information

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS

More information

Cafeteria Modernization

Cafeteria Modernization United States Department of the Interior Cafeteria Modernization Construction Management Dr. Reilly Department of the Interior Cafeteria Modernization 1849 C Street NW, Washington D.C. October 4, 2010

More information

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803

More information

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)

INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Name: Karardi, Shibpur, Narsingdi, Narsingdi Dhaka Bangladesh 10 May 2013 The Alliance for Bangladesh Worker Safety Page 1/15 10 May 2013 Introduction

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

Retrofit of an Existing Californian Hospital to Immediate Occupancy Standards One Year Later Again R. Jay Love, S.E.

Retrofit of an Existing Californian Hospital to Immediate Occupancy Standards One Year Later Again R. Jay Love, S.E. Retrofit of an Existing Californian Hospital to Immediate Occupancy Standards One Year Later Again R. Jay Love, S.E. Degenkolb Engineers MCEER 2006 Annual Meeting Diagnostic & Treatment Building Designed

More information

Attachment D-1: Civil/Structural Scope of Work

Attachment D-1: Civil/Structural Scope of Work Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

INOVA Office Building I. Adolfson & Peterson Construction. Keri Burson:

INOVA Office Building I. Adolfson & Peterson Construction. Keri Burson: INOVA Office Building I Adolfson & Peterson Construction Keri Burson: kburson@a-p.com; 303-363-7101 Category #9 Best Building Project General Contractor ($10 - $40 Million) Why this project should win

More information

TECHNICAL REPORT 2 BUILDING CODES, SPECIFICATIONS, AND LOADS

TECHNICAL REPORT 2 BUILDING CODES, SPECIFICATIONS, AND LOADS TECHNICAL REPORT 2 BUILDING CODES, SPECIFICATIONS, AND LOADS SECOND & STATE BUILDING HARRISBURG PA JADOT A MOOSMAN STRUCTURAL OPTION Primary AE Faculty Consultant... Dr. Thomas E. Boothby Date of Submission...

More information

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION Permit No. 175 Beaver Drive, P.O. Box 486 DuBois, PA 15801 Phone: 814-375-1111 Fax: 814-375-1117 Toll Free: 855-PENNSAF LOCATION OF PROPOSED

More information

William W. Wilkins Professional Building

William W. Wilkins Professional Building William W. Wilkins Professional Building Columbus, Ohio Michelle Benoit Senior Thesis Presentation Spring 2007 Structural Option Introduction Existing Structure Floor System Lateral System Proposal Structural

More information