1 SCOPE OF WORK Facility Improvement Assessment Albert C. Wagner Youth Correctional Facility Chesterfield Township, Burlington County, N.J. PROJECT NO. C STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt. Governor DEPARTMENT OF THE TREASURY Andrew P. Sidamon-Eristoff, Treasurer DIVISION OF PROPERTY MANAGEMENT AND CONSTRUCTION Steven Sutkin, Director Date: Document Format Revision (7/25/14)

2 SECTION TABLE OF CONTENTS PAGE I. OBJECTIVE... 4 II. CONSULTANT QUALIFICATIONS... 4 A. CONSULTANT & SUB-CONSULTANT PRE-QUALIFICATIONS... 4 III. PROJECT SCHEDULE... 4 A. PRELIMINARY ASSESSMENT STUDY SCHEDULE... 5 B. APPROVED ASSESSMENT STUDY SCHEDULE... 5 IV. PROJECT SITE LOCATION & TEAM MEMBERS... 5 A. PROJECT SITE ADDRESS... 5 B. PROJECT TEAM MEMBER DIRECTORY DPMC Representative: Client Agency Representative:... 6 VI. PROJECT DEFINITION... 6 A. BACKGROUND... 6 B. FUNCTIONAL DESCRIPTION OF THE FACILITY... 6 VII. CONSULTANT DESIGN RESPONSIBILITIES... 6 A. FACILITY ASSESSMENT STUDY/REPORT REQUIREMENTS... 7 B. BUILDINGS INCLUDED IN STUDY... 7 C. FACILITY WIDE SYSTEMS NOT INCLUDED IN ASSESSMENT... 8 D. DATA GATHERING... 8 E. STUDY REQUIREMENTS Building Photographs: Building Description: Building Exterior: Building Interior: Power House Boilers Additional Upgrades:... 9 F. BUILDING UTILITY AND OPERATIONAL SYSTEMS... 9 G. BUILDING SECURITY AND SITE SECURITY... 9 H. BUILDING LIFE SAFETY AND HEALTH STANDARDS I. HAZARDOUS BUILDING MATERIALS J. BUILDING ENERGY EVALUATIONS K. SITE EVALUATION PAGE 2

3 L. ESTIMATED PROJECT COSTS M. PROJECT COMMENCEMENT Project Directory: Site Access: Existing Documentation: Scope of Work: Project Schedule: N. BUILDING & SITE INFORMATION Building Classification: Site Plan: O. REPORT FORMAT P. PROGRESS MEETINGS & PRESENTATIONS Progress Meetings: Study Presentations: X. GENERAL REQUIREMENTS A. SCOPE CHANGES XI. ALLOWANCES A. HAZARDOUS MATERIALS TESTING AND REPORT ALLOWANCE XII. SUBMITTAL REQUIREMENTS A. CONTRACT DELIVERABLES XIII. SOW SIGNATURE APPROVAL SHEET XV. EXHIBITS A. PROJECT LOCATION PLAN B. FACILITY KEY PLAN PAGE 3

4 I. OBJECTIVE The objective of this project is to conduct a Facility Assessment Study of the Albert C. Wagner Youth Correctional Facility buildings to identify building deficiencies, required building improvements and security improvements to develop a capital improvement plan. The study shall evaluate the building envelopes, HVAC, electrical and security systems. Based on the study findings, the Consultant shall prepare a report with recommendations and cost estimates for the deficiencies and improvements identified. II. CONSULTANT QUALIFICATIONS A. CONSULTANT & SUB-CONSULTANT PRE-QUALIFICATIONS The Consultant shall be a firm pre-qualified with the Division of Property Management & Construction (DPMC) in the P001 Architectural Professional Discipline and have in-house capabilities or Sub-Consultants pre-qualified with DPMC in: P002 Electrical Engineering P003 HVAC Engineering P004 Plumbing Engineering P025 Estimating/Cost Analysis P037 Asbestos Design P065 Lead Paint Evaluation as well as all other Architectural, Engineering and Specialty Disciplines necessary to complete the project as described in this Scope of Work (SOW). III. PROJECT SCHEDULE PROJECT PHASE ESTIMATED DURATION (Calendar Days) 1. Preliminary Draft Assessment & Presentation 70 Project Team Review & Comment Final Draft Assessment & Presentation 21 Project Team Review & Comment Final Facility Assessment Report 14 PAGE 4

5 A. PRELIMINARY ASSESSMENT STUDY SCHEDULE The Consultant shall submit a bar chart schedule with their technical proposal. The bar chart schedule developed by the Consultant shall reflect the recommended project phases, activities, and durations. A written narrative shall also be included with the technical proposal explaining the schedule submitted and the reasons why and how it can be completed in the time frame proposed by the Consultant. This schedule and narrative will be reviewed by the Consultant Selection Committee as part of the evaluation process and will be assigned a score commensurate with clarity and comprehensiveness of the submission. B. APPROVED ASSESSMENT STUDY SCHEDULE The Consultant will issue the approved project Assessment Study schedule at the first kickoff meeting. This schedule will be binding for the Consultant s activities and will include the start and completion dates for each activity. The Consultant and Project Team members shall use this schedule to ensure that all milestone dates are being met for the project. The Consultant shall update the schedule to reflect performance periodically (minimally at each design phase) for the Project Team review and approval. Any recommendations for deviations from the approved schedule must be explained in detail as to the causes for the deviation(s) and impact to the overall project schedule. IV. PROJECT SITE LOCATION & TEAM MEMBERS A. PROJECT SITE ADDRESS The location of the project site is: Albert C. Wagner Youth Correctional Facility 454 Ward Avenue Chesterfield Township, NJ GPS Coordinates: , See Exhibit A for the project location map. B. PROJECT TEAM MEMBER DIRECTORY PAGE 5

6 The following are the names, addresses, and phone numbers of the Project Team members. 1. DPMC Representative: Name: Address: Nurul Hasan, Project Manager Division Property Management & Construction 20 West State Street, 3 rd Floor Trenton, NJ Phone No: (609) No: Nural.Hasan@treas.nj.gov 2. Client Agency Representative: Name: Address: Raymond Albert, Project Manager Department of Corrections PO Box 863 Trenton, New Jersey Phone No: (609) No: Raymond.Albert@doc.state.nj.us VI. PROJECT DEFINITION A. BACKGROUND The Department of Corrections wants to identify and quantify the improvements required to the buildings and building systems of the Albert C. Wagner Youth Correctional Facility in order to develop a multi-year master plan to upgrade the facility. B. FUNCTIONAL DESCRIPTION OF THE FACILITY The Albert C. Wagner Youth Correctional Facility is situated on 589 acres, of which approximately 450 acres are cultivated for the New Jersey Department of Corrections Farm Operation. The main building is a medium security facility. Adjacent to the main facility is an administrative close custody unit for the housing of maximum security inmates and inmates placed under administrative segregation. The facility also includes a minimum custody unit. Programs for mental health, group counseling, and academic and vocational education are available. VII.CONSULTANT DESIGN RESPONSIBILITIES PAGE 6

7 A. FACILITY ASSESSMENT STUDY/REPORT REQUIREMENTS The report shall contain a narrative of the surveys, inspections, and investigations conducted for each item listed. Recommendations for replacement, repair, and/or upgrade of building components shall be described and prioritized based on life safety and useful life. All recommendations shall include cost estimates at current rates. Plans, drawings and colored photographs related to the building and components shall be included for reference. All survey data, interviews, field notes, energy savings calculations, review comments, etc. shall be included in the Facility Assessment Study. The project requirements outlined in this Scope of Work will provide an overview of the services that are required by the Consultant. Items described for assessment may not be all-inclusive and shall not limit the Consultant s responsibility for the services required. The Consultant s responsibility will be to provide a context that will allow decisions to be made regarding which deficiencies, improvements or upgrade should be undertaken with the funding available. B. BUILDINGS INCLUDED IN STUDY The following buildings shall be included in the assessment study, refer to EXHIBIT B for building location by building number: Bldg. No. Building Name Administrative, Wing A & B - 41,130 SF 02 Wing A - 6,210 SF 03 Wing B 6,210 SF 04 Wing C /Dining -27,180 SF 05 Wing D 20,340 SF 06 Wing E 18,000 SF 07 Wing G -21,450 SF 08 Laundry 8,850 SF 09 Industries/Votech 31,570 SF 10 Gymnasium 19,940 SF 11 Visitors Center 3,240 SF 12 Wing H 3,570 SF 15 Storage Hut 1,900 SF 16 Maintenance/Votech 10,890 SF 35 Wing F 1,350 SF 36 Administrative Close Supervision Unit 33,830 SF 36A Administrative Close Supervision Unit Support -3,570 SF 37 Wing I 14,990 SF 37A Wing I, Support Building 3,650 SF 39 Internal Affairs 1,920 SF 40 AD SEG Administration 2,330 SF PAGE 7

8 41 Central Control 1,020 SF C. FACILITY WIDE SYSTEMS NOT INCLUDED IN ASSESSMENT Note that the following facility wide distribution/collection systems (systems between buildings) are not included in the assessment/report: Electrical Distribution Steam and Condensate Distribution Potable Water System Sewage Collection System D. DATA GATHERING The Consultant shall meet with the Project Team and representatives of the Facility to develop a procedure and schedule for accessing the buildings for data collection. Surveys, measurements, photographs, and other data collection methods shall be performed in such a way to minimize disruption to the building occupants. E. STUDY REQUIREMENTS The facility shall be inspected and all building components shall be identified for physical condition, life expectancy, and renovation or replacement requirements. The Assessment Report shall include, but is not limited to the following: 1. Building Photographs: Provide colored photographs of the site, exterior of the building, roof, and system components. 2. Building Description: Provide a brief description of the building that includes the function of the building, system components, condition and estimated useful life. 3. Building Exterior: Provide a description and condition of the building exterior elements such as, type of construction, building materials, number of entrances, location and capacity of loading docks, and rooftop mechanical rooms (if applicable). Identify all building repairs that are not required by code but are necessary to achieve an objective of no "major maintenance" for the next twenty (20) years including, but not limited to: PAGE 8

9 exterior lighting systems, structural systems, foundations, water infiltration problems, exterior walls and finishes, masonry, pointing, caulking, roofing system (parapets, flashing, capping, ect.) and life expectancy, roof square footage, gutters, leaders, scuppers, interior roof drains, windows and door types, Barrier-Free accessibility, etc. 4. Building Interior: Provide a description and condition of the building interior elements including: floor construction, ceiling and lighting systems, doors and fire ratings, storage adequacy, telecommunication rooms, lobbies, break rooms, office and conference rooms, special use areas, toilet rooms, cafeteria, computer rooms, etc. Identify the type and condition of the paint, carpeting, tiled floors, drywalls, plaster, partitions, millwork, and signage. Investigate areas where stained ceiling tiles exist and explore above to determine possible causes. 5. Power House Boilers In addition to the power house envelop and interior condition, evaluate the condition, efficiency and life expectancy of the boilers in the power house. Include recommendations for repairs and/or replacement. 6. Additional Upgrades: The Consultant shall identify any building upgrades and improvements that, if completed, could be considered substantial improvements and could also require additional upgrades according to the Uniform Construction Code or any other applicable Codes. F. BUILDING UTILITY AND OPERATIONAL SYSTEMS Provide a description and condition of the existing building utilities and operational systems including, age, capacities, nameplate data, etc. Recommend upgrades for each utility and operational system, if necessary. The utility and related systems within the buildings described below shall include, but are not limited to the following: Electric Service, Electric Distribution System, Gas Distribution System, Water Distribution System, Steam System and Distribution, Sanitary System, Communication System, HVAC & Environmental Control Systems, Fire Protection System, Energy Management Systems, Emergency Power System, and Elevator System. G. BUILDING SECURITY AND SITE SECURITY PAGE 9

10 Provide a description and condition of the existing building security systems. Recommend upgrades for each system, if necessary. The security systems within the buildings shall include, but are not limited to the following: Sally ports, control stations, cell door control, camera systems, central control/monitoring H. BUILDING LIFE SAFETY AND HEALTH STANDARDS Evaluate each building as to life safety and health standards. Based on this information, provide a list of recommended upgrades and their associated costs. Items shall include, but not limited to the following: Identify and evaluate all labeled doors, exit signage, stair designs, stair closures, handrails, fire rated construction materials, fire extinguishers, fire escapes and means of egress (Administration Building is of particular concern), sprinklers, fire alarm, detection systems, emergency lighting, strobe and horn annunciation units, fire alarm tie-in to local department, building ventilation, toilet exhausts, lighting levels, Barrier-Free, and elevator systems. Verify if any visible mold growth exists in areas where water infiltration, has or is, occurring. I. HAZARDOUS BUILDING MATERIALS Consultant shall survey the building(s) and, if deemed necessary, collect samples of materials that are suspected of containing hazardous materials and analyze them for the presence of hazardous materials including: 1. Asbestos in accordance with N.J.A.C. 5:23-8, Asbestos Hazard Abatement Subcode. 2. Lead in accordance with N.J.A.C. 5:17, Lead Hazard Evaluation and Abatement Code. 3. PCB s in accordance with 40 CFR 761, Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions. Consultant shall engage a firm certified in the testing and analysis of materials containing PCB s. Consultant shall document their procedure, process and findings and include in the report a Hazardous Materials Survey Report identifying building components containing hazardous materials Consultant shall estimate the cost of hazardous materials sample collection, testing, analysis and preparation of the Hazardous Materials Survey Report and include that amount in their fee proposal line item entitled Hazardous Materials Testing and Report Allowance, refer to paragraph XI.B. PAGE 10

11 There shall be no mark-up of subconsultant or subcontractor fees if subconsultants or subcontractors are engaged to perform any of the work defined in paragraph VII.G Hazardous Building Materials. All costs associated with managing, coordinating, observing and administrating subconsultants and subcontractors performing hazardous materials sampling, testing, analysis, report preparation shall be included in the consultant s lump sum fee proposal. J. BUILDING ENERGY EVALUATIONS Review this facility for potential energy savings and make recommendations with construction costs to include, but is not limited to the following: Building Automation System, Lighting Systems and Controls, Plumbing Flow Restrictors, Pipe Insulation, Environmental Controls, Insulation, Windows, Fuel Systems, and Renewable Energy Resources. K. SITE EVALUATION Review the existing building site and identify the current conditions and provide recommended improvements with related design and construction costs to include, but not limited to: Identify all parking area locations, their capacities, use, general condition, drainage, curbing, Barrier-Free access, lighting, gates, fencing, and paving. Identify the existing pedestrian routes and evaluate the sidewalks, curbing, lighting, Barrier-Free access provisions, delineated crosswalks, etc. L. ESTIMATED PROJECT COSTS The Consultant shall provide construction cost estimates associated with the recommended building improvements. Cost estimates shall be in CSI format (2004 Edition) for all appropriate divisions and sub-divisions. M. PROJECT COMMENCEMENT A pre-study meeting shall be scheduled with the Consultant and the Project Team members at the commencement of the project to obtain and/or coordinate the following information: 1. Project Directory: Develop a project directory that identifies the name and phone number of key designated representatives who may be contacted during this study. PAGE 11

12 2. Site Access: Develop procedures to access the project site and provide the names and phone numbers of approved escorts when needed. Obtain copies of special security and policy procedures that must be followed during all work conducted at the facility and include this information in Division 1 of the specification. 4. Existing Documentation: Copies of the following documents, on compact disk (CD) shall be provided to each Consulting firm at the pre-proposal meeting to assist in the bidding process. DPMC Project No. C0588, Infrastructure/Support Facility Inventory, prepared by the Vitetta Group, dated November 30, DPMC Project No. C , Replacement of Boilers, prepared by Miller-Remick Corporation, dated March 5, DPMC Project No. C , Roof Replacement at Wings A, B, D, E and Linkways, prepared by ARMM Associates, dated July 20, DPMC Project No. C , Perimeter Security Fence Addition & Perimeter Roadway Modification, prepared by Lammey & Giorgio, dated March 16, DPMC Project No. C , Roof Replacement, prepared by USA Architects Planners + Interior Designers, dated August 12, DPMC Project No. C , Switchgear Upgrades and Cable Replacement, prepared by Gannett Fleming, dated July 18, DPMC Project No. C Steam & Condensate Pipe Replacement, prepared by Miller- Remick Corporation, dated March Review these documents and any additional information that may be provided at a later date such as reports, studies, surveys, equipment manuals, as-built drawings, etc. The State does not attest to the accuracy of the information provided and accepts no responsibility for the consequences of errors by the use of any information and material contained in the documentation provided. It shall be the responsibility of the Consultant to verify the contents and assume full responsibility for any determination or conclusion drawn from the material used. If the information provided is insufficient, the Consultant shall take the appropriate actions necessary to obtain the additional information required. All original documentation shall be returned to the provider at the completion of the project. 5. Scope of Work: Review the design and construction administration responsibilities and the submission requirements identified in this Scope of Work with the Project Team members. Items such as: PAGE 12

13 contract deliverables, special hours for site access based on Client Agency programs or building occupancy, security needs and coordination with other project activities at the site shall be addressed. 6. Project Schedule: Review and update the project design and construction schedule with the Project Team members. N. BUILDING & SITE INFORMATION The following information shall be included in the study report. 1. Building Classification: Provide the building Use Group Classification and Construction Type for each building. 2. Site Plan: A site plan shall be provided. The site plan shall include, but not be limited to, the following: The size and location of buildings and additions as well as other structures. Existing site vehicular and pedestrian roads, walkways and parking areas. O. REPORT FORMAT The Final Facility Assessment Report shall be submitted in a bound book format. It shall include an Executive Summary and all supporting documentation. Each bound book shall include the Report on compact disk (CD) in an Adobe Portable Document Format (.pdf). Ten (10) copies of the report shall be provided at each submittal phase. P. PROGRESS MEETINGS & PRESENTATIONS 1. Progress Meetings: Conduct the appropriate number of review meetings with the Project Team members during the project so they may determine if the project meets their requirements, question any aspect of the contract deliverables, and make changes where appropriate. The Consultant shall describe the philosophy and process used in the development of the study and the various alternatives considered to meet the project objectives PAGE 13

14 It shall also be the responsibility of the Consultant to arrange and require all critical Sub- Consultants to be in attendance at the design review meetings. Record the minutes of each design meeting and distribute within seven (7) calendar days to all attendees and those persons specified to be on the distribution list by the Project Manager. 2. Study Presentations: The minimum number of design presentations required for each phase of this project is identified below for reference: Preliminary Draft Assessment Phase: One (1) oral presentation at phase completion. Final Draft Assessment Phase: One (1) oral presentation at phase completion. Final Facility Assessment Report: One (1) oral presentation at phase completion. X. GENERAL REQUIREMENTS A. SCOPE CHANGES The Consultant must request any changes to this Scope of Work in writing. An approved DPMC 9d Consultant Amendment Request form reflecting authorized scope changes must be received by the Consultant prior to undertaking any additional work. The DPMC 9d form must be approved and signed by the Director of DPMC and written authorization issued from the Project Manager prior to any work being performed by the Consultant. Any work performed without the executed DPMC 9d form is done at the Consultant s own financial risk. XI. ALLOWANCES A. HAZARDOUS MATERIALS TESTING AND REPORT ALLOWANCE Consultant shall estimate the costs to complete the hazardous materials survey, sample collection, testing and analysis and preparation of a Hazardous Materials Survey Report noted in paragraph VII.C.1 and enter that amount on their fee proposal line item entitled Hazardous Materials Testing and Report Allowance. Consultant shall attach a detailed cost breakdown sheet for use by DPMC during the proposal review and potential fee negotiations. The cost breakdown sheet shall include, but not be limited to, the following information: PAGE 14

15 Description of tasks and estimated cost for the following: o Sample collection o Sample testing o Preparation of an Hazardous Materials Survey Report Any funds remaining in the Hazardous Materials Testing and Report Allowance will be returned to the State at the close of the project. XII.SUBMITTAL REQUIREMENTS A. CONTRACT DELIVERABLES 1. Preliminary Draft Facility Assessment Study 2. Final Draft Facility Assessment Study 3. Final Facility Assessment Study PAGE 15

16

17 XV.EXHIBITS The attached exhibits in this section include a site map. END OF SCOPE OF WORK PAGE 17

18 LOCATION MAP Albert C. Wagner Youth Correctional Facility 454 Ward Avenue Chesterfield Township, NJ GPS Coordinates: , Albert C. Wagner Youth Correctional Facility EXHIBIT A

19 FACILITY KEY PLAN Albert C. Wagner Youth Correctional Facility EXHIBIT B

STATE OF NEW JERSEY Honorable Jon S. Corzine, Governor

STATE OF NEW JERSEY Honorable Jon S. Corzine, Governor SCOPE OF WORK FACILITY ENERGY AUDIT New Lisbon Developmental Center Woodland Twp, Burlington County, N.J. PROJECT NO. A1085-00 STATE OF NEW JERSEY Honorable Jon S. Corzine, Governor DEPARTMENT OF THE TREASURY

More information

SCOPE OF WORK. Interior Stair Modifications PROJECT NO. C

SCOPE OF WORK. Interior Stair Modifications PROJECT NO. C SCOPE OF WORK Interior Stair Modifications Mountainview Youth Correctional Facility Annandale, Hunterdon County, N.J. PROJECT NO. C0955-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable

More information

SCOPE OF WORK. Generator Installation. NJDOT Freehold Maintenance Facility Freehold, Middlesex County, N.J. PROJECT NO. T

SCOPE OF WORK. Generator Installation. NJDOT Freehold Maintenance Facility Freehold, Middlesex County, N.J. PROJECT NO. T SCOPE OF WORK Generator Installation NJDOT Freehold Maintenance Facility Freehold, Middlesex County, N.J. PROJECT NO. T0527-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno,

More information

SCOPE OF WORK. Chilled Water Piping Insulation PROJECT NO. A

SCOPE OF WORK. Chilled Water Piping Insulation PROJECT NO. A SCOPE OF WORK Chilled Water Piping Insulation Treasury Print Shop Trenton, Mercer County, N.J. PROJECT NO. A1164-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt. Governor

More information

SCOPE OF WORK. Emergency Generator Installation PROJECT NO. S

SCOPE OF WORK. Emergency Generator Installation PROJECT NO. S SCOPE OF WORK Emergency Generator Installation Johnstone Campus Bordentown, Burlington County PROJECT NO. S0567-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt. Governor

More information

SCOPE OF WORK. Bordentown Training Facility Renovations PROJECT NO. T

SCOPE OF WORK. Bordentown Training Facility Renovations PROJECT NO. T SCOPE OF WORK Bordentown Training Facility Renovations NJDOT Bordentown Training Facility Bordentown, Burlington County, N.J. PROJECT NO. T0573-00 STATE OF NEW JERSEY Honorable Philip D. Murphy, Governor

More information

STATE OF NEW JERSEY Honorable Jon S. Corzine, Governor

STATE OF NEW JERSEY Honorable Jon S. Corzine, Governor SCOPE OF WORK LOCKING SYSTEM UPGRADES East Jersey State Prison Building #5, Wing 3 Rahway, Middlesex County, N.J. PROJECT NO. C0818-00 STATE OF NEW JERSEY Honorable Jon S. Corzine, Governor DEPARTMENT

More information

SCOPE OF WORK. Structural Repairs & Window Installation PROJECT NO. T

SCOPE OF WORK. Structural Repairs & Window Installation PROJECT NO. T SCOPE OF WORK Structural Repairs & Window Installation NJDOT Vineland Vehicle Repair Garage Vineland, Cumberland County, N.J. PROJECT NO. T0530-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor

More information

SCOPE OF WORK. Fire Protection Upgrades for Emergency Generator Fuel Supply System PROJECT NO. A

SCOPE OF WORK. Fire Protection Upgrades for Emergency Generator Fuel Supply System PROJECT NO. A SCOPE OF WORK Fire Protection Upgrades for Emergency Generator Fuel Supply System Richard J. Hughes Justice Complex Trenton, Mercer County, N.J. PROJECT NO. A1139-00 STATE OF NEW JERSEY Honorable Chris

More information

SCOPE OF WORK. Sanitary Sewer and Water Service Installation PROJECT NO. T

SCOPE OF WORK. Sanitary Sewer and Water Service Installation PROJECT NO. T SCOPE OF WORK Sanitary Sewer and Water Service Installation NJDOT Bordentown Training Facility Bordentown, Burlington County, N.J. PROJECT NO. T0580-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor

More information

SCOPE OF WORK. Communication Tower Installation PROJECT NO. C

SCOPE OF WORK. Communication Tower Installation PROJECT NO. C SCOPE OF WORK Communication Tower Installation Southern State Prison Correctional Facility Delmont, Cumberland County, N.J. PROJECT NO. C0891-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable

More information

CODE COMPLIANCE PLAN REVIEW PROCEDURES

CODE COMPLIANCE PLAN REVIEW PROCEDURES CODE COMPLIANCE PLAN REVIEW PROCEDURES 1. All construction for state agencies on state-owned or state leased-purchased properties or facilities are to submit design documents for code compliance plan reviews

More information

SCOPE OF WORK HVAC UPGRADES PROJECT NO. A STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt.

SCOPE OF WORK HVAC UPGRADES PROJECT NO. A STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt. SCOPE OF WORK HVAC UPGRADES Department of State Auditorium Trenton, Mercer County, N.J. PROJECT NO. A1115-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor Honorable Kim Guadagno, Lt. Governor

More information

Commercial Tax Abatement

Commercial Tax Abatement A confirmation letter is issued by the City upon receipt of this application. This application is not effective and not considered filed until the confirmation letter has been issued. Filing does not assure

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

SCOPE OF WORK. Walt Whitman House Visitor Center Rehabilitation PROJECT NO. P

SCOPE OF WORK. Walt Whitman House Visitor Center Rehabilitation PROJECT NO. P SCOPE OF WORK Walt Whitman House Visitor Center Rehabilitation Walt Whitman House Visitor Center Complex Camden, Camden County, N.J. PROJECT NO. P1172-00 STATE OF NEW JERSEY Honorable Chris Christie, Governor

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

VFA SAMPLE RFP (DETAILED FACILITY CONDITION ASSESSMENT)

VFA SAMPLE RFP (DETAILED FACILITY CONDITION ASSESSMENT) VFA SAMPLE RFP (DETAILED FACILITY CONDITION ASSESSMENT) I. Purpose As part of a strategic planning directive, the has decided to undertake a comprehensive condition audit and plant capital renewal

More information

Project Information Session / Meet and Greet # 3

Project Information Session / Meet and Greet # 3 ATL WEST DECK COMPONENT Project Information Session / Meet and Greet # 3 Holder-Austin-Moody-Bryson, a Joint Venture October 10 th, 2017 Agenda 1. HAMB, a JV Company Overview 2. ATL West Deck Project Description

More information

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Physical Plant Division Engineering and Architectural Services Department

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320 REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE 2015 2016 ROOF AND HVAC REPLACEMENT PROJECT PW1320 Issued by: City of Stockton Public Works Department 22 E. Weber Avenue, Room 301 Stockton, CA 95202

More information

TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ FAX

TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ FAX TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ 08014 856-467-3626--- FAX 856-467-9260 Application for Certificate of Occupancy for Change of Occupancy Pursuant to Chapter 119 of the Township

More information

Career Center Advance Planning/Design Services Code Item 321

Career Center Advance Planning/Design Services Code Item 321 The University of North Carolina at Charlotte Temporary Office Space Facilities Management - Capital Projects Hickory Building (Building #536 on Campus Map) 9316 Mary Alexander Road Charlotte, NC 28223

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services... A-2. B. Architectural Programming... A-5 EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services... A-2 B. Architectural Programming... A-5 1. Project Initiation... A-5 C. Design Services... A-6 1. Schematic Design Phase...

More information

Received by:* Date Received:* Zoning Approval:* Date:* PERMIT#:* *ZONING: *SETBACKS: FRONT ft/ SIDE ft/ REAR ft *FLOOD ZONE:

Received by:* Date Received:* Zoning Approval:* Date:* PERMIT#:* *ZONING: *SETBACKS: FRONT ft/ SIDE ft/ REAR ft *FLOOD ZONE: HENDRY COUNTY BUILDING, LICENSING & CODE ENFORCEMENT POST OFFICE BOX 2340 * 640 SOUTH MAIN STREET * LABELLE, FLORIDA 33975 * (863) 675-5245 * FAX: (863) 674-4194 1100 OLYMPIA ST CLEWISTON, FLORIDA 33440

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

CITY OF CHICAGO DEPARTMENT OF BUILDINGS

CITY OF CHICAGO DEPARTMENT OF BUILDINGS CITY OF CHICAGO DEPARTMENT OF BUILDINGS GUIDELINES FOR THE PREPARATION OF REQUESTS FOR QUALIFICATIONS FOR THE SELECTION OF CONSULTING FIRMS TO PERFORM LIFE SAFETY EVALUATIONS The Chicago Department of

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28- 1 Metz Elementary School Site Summary Address 84 Robert Martinez Jr. Austin, TX 78702 Number of Permanent Campus Facilities 1 Original Year of Construction 1993 Total Campus Building Area (combined) 61,905

More information

Zoning- check the zoning on the property you are planning to build on, this can be done at the municipal office.

Zoning- check the zoning on the property you are planning to build on, this can be done at the municipal office. SINGLE DETACHED DWELLING Before your application can be deemed complete and ready for processing you will need the following: (Please hand in entire application package including this cover sheet) Zoning-

More information

COOLIDGE SENIOR HIGH SCHOOL

COOLIDGE SENIOR HIGH SCHOOL INITIAL YEAR BUILT 1940 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1240 ENROLLMENT 2008 652 WARD 4 PROPOSED PROGRAM CAPACITY 1100 Site Plan COOLIDGE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services...

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER. A. Basic Services...A-1. B. Pre-Design and Start-Up Services... EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT/ENGINEER A. Basic Services...A-1 B. Pre-Design and Start-Up Services...A-3 1. Project Initiation...A-3 2. Development of Architectural Program...A-4

More information

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements 700 Paris Ave. PO Drawer 9 Port Royal, SC 29935 Application for Permit - P O Drawer 9, Port Royal South Carolina Permit

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: OWNER: Shell and Core Improvements-1235 Mission Scope 3: Roofs 1 & 3 DATE: December 29, 2017 1235 Mission

More information

LECKIE ELEMENTARY SCHOOL

LECKIE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1970 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 471 ENROLLMENT 2008 321 WARD 8 PROPOSED PROGRAM CAPACITY 400 Site Plan LECKIE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Code Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617)

Code Requirements for Existing Buildings. R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) Code Requirements for Existing Buildings R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS) was established in 1945 and currently

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

PRESCRIPTIVE COMPLIANCE METHOD

PRESCRIPTIVE COMPLIANCE METHOD CHAPTER PRESCRIPTIVE COMPLIANCE METHOD 3 SECTION 301 GENERAL 301.2 Building materials. Building materials shall comply with the requirements of this section. 301.2.1 Existing materials. Materials already

More information

JMU Capital Projects SWaM Outreach Event Presentations

JMU Capital Projects SWaM Outreach Event Presentations JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2

More information

Mount Vernon Elementary School Grades PK 5

Mount Vernon Elementary School Grades PK 5 Barbour County Schools Comprehensive Educational Facilities Plan 2010-2020 Mount Vernon Elementary School Grades PK 5 Blackwood Associates, Inc. / MSES consultants, Inc. / Roy Blizzard and Associates Mount

More information

CITY OF NOVI. Police Department

CITY OF NOVI. Police Department CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master

More information

University of Texas. Austin, TX. TAS Variance Application Guidelines For Qualifying Historic Structures

University of Texas. Austin, TX. TAS Variance Application Guidelines For Qualifying Historic Structures University of Texas Austin, TX TAS Variance Application Guidelines For Qualifying Historic Structures Architecture, Planning and Historic Preservation, Inc. 2900 S. Congress Ste 200 Austin, TX 78704 512.444.4220

More information

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

OFFICE OF EDUCATIONAL FACILITIES FLORIDA BUILDING CODE SECTION 423 APPLICATION MATRIX

OFFICE OF EDUCATIONAL FACILITIES FLORIDA BUILDING CODE SECTION 423 APPLICATION MATRIX 423.1 Scope: Public educational facilities 423.2 Public schools and community colleges general requirements 423.2.1 Owner 423.2.2 Exemption from local requirements 423.2 Code enforcement 423.3.1 School

More information

BUILDING CODES & DESIGN CRITERIA

BUILDING CODES & DESIGN CRITERIA BUILDING CODES & DESIGN CRITERIA Adopted Building Codes: 2006 International Building Code (IBC) 2006 International Residential Code (IRC) 2006 International Mechanical Code (IMC) 2006 International Plumbing

More information

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 CONTENTS A. PURPOSE B. DESIGNATED RESPONSIBILITIES C. DEFINITIONS D. PROJECT SUBMITTAL PROCEDURE E. REQUIREMENTS

More information

BOWIE LEARNING CENTER

BOWIE LEARNING CENTER BOWIE LEARNING CENTER Bowie Learning Center BUILDING DATA BOWIE LEARNING CENTER 900 North Elm St., Weatherford, TX 76086 Year Built 1936 No. of Buildings No. of Portables 0 Approx. Total Square Footage

More information

DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016

DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016 DeKalb County School District/Stadiums Avondale Stadium Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition Summary

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

Architectural Services

Architectural Services Architectural Services 2016 Capital Improvement Program Request for Proposal Number: 18-20 Title of the Projects: Renovations to Weaver Middle School Procurement Department Bibb County School District

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS **************************************************************************

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-02 42 91 (May 2010) ------------------------- Preparing Activity: USACE Nontechnical Title Revision (August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS SECTION TABLE

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

Bureau Policy for Tent Permit

Bureau Policy for Tent Permit Bureau Policy for Tent Permit Introduction: Occasionally we receive applications for erecting temporary or permanent tents at schools or commercial establishments. This policy is generated to give a general

More information

Basement Renovation Guide For Residential Dwellings

Basement Renovation Guide For Residential Dwellings 1 Development Services Department Building Permit & Inspection Services Basement Renovation Guide For Residential Dwellings This document is a guide for home owners and does not cover all possible conditions.

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

Thule Prototype BIM Manual for Dormitories. February 5, 2010

Thule Prototype BIM Manual for Dormitories. February 5, 2010 Thule Prototype BIM Manual for Dormitories February 5, 2010 TABLE OF CONTENTS INTRODUCTION Executive Summary 2 Goals 2 Scope and Use 2-4 Program Assumptions Kit of Parts GUIDELINE INTEGRATION Site Design

More information

Residential Building Permit Application

Residential Building Permit Application City of Twin Falls Building Department 324 Hansen Street East P.O. Box 1907 Twin Falls, ID 83303-1907 208-735-7238 208-736-2256 www.tfid.org PROJECT INFORMATION Project Residential Building Permit Application

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

Perimeter Site Improvements

Perimeter Site Improvements Perimeter Site Improvements Phase 1-5 Architect: W+W Architects and Planners Anticipated Milestone Activities: Phase 1, 2 & 3 Construction Manager: Bernards 08.08.13 Directional Signage Contractor: Woodcliff

More information

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE Based upon B3 Minnesota Sustainable Building Guidelines VERSION 2.1 Notes to the reader have been added to this document within numerous text boxes

More information

Fire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II

Fire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II Fire Inspection and Code Enforcement, 7 th Edition Chapter 6 Building Construction: Components Today we will Discuss fire walls, party walls, fire partitions, and curtain walls Discuss roof types and coverings

More information

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No.

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No. SPECIAL CONDITIONS Article I, Section A delete this paragraph in its entirety and replace it with the following language: Owner s representative to act on its behalf with respect to this Agreement shall

More information

Bronx Mental Health Redevelopment Project

Bronx Mental Health Redevelopment Project Bronx Mental Health Redevelopment Project Residential Village Bronx Campus Transitional Living Residences, Haven House Horizon House, and Studio Apartments BIM Orientation December 20, 2012 1 Bronx Mental

More information

Building Information Modeling (BIM) Execution Plan

Building Information Modeling (BIM) Execution Plan 10/19/2017 for [Stanford Project Name] [Stanford Project Number] Developed by [Primary A/E] TABLE OF CONTENTS USE OF THE BIM EXECUTION PLAN... 3 1. PROJECT INFORMATION... 3 2. PROJECT SCHEDULE AND MILESTONES...

More information

Addendum #02 New County Office Building Responses to RFP Questions

Addendum #02 New County Office Building Responses to RFP Questions Sam Lin Manager Project Development Unit 1402 Maple Street Redwood City, CA 94063 650-369-4766 September 22, 2017 slin@smcgov.org Addendum #02 New County Office Building Responses to RFP Questions To All

More information

Demolition Safety!!!!

Demolition Safety!!!! Sample Written Program For Your Company For Demolition Safety Provided By: P.O. Box 2136 Slidell, LA 70458 Phone: 985-781-1444 Fax: 985-718-4957 Email: info@se-safety.com Demolition Safety Program Purpose

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

2014 Commercial Plan Submittal Checklist

2014 Commercial Plan Submittal Checklist City of Aurora Public Works Department AURORA PUBLIC SCHOOLS AND CHERRY CREEK PUBLIC SCHOOLS 2014 Commercial Plan Submittal Checklist Permit Center 15151 E. Alameda Parkway, Ste 2400 Aurora, CO 80012 303-739-7420

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

Request for Proposal: City of Claremont Parking Garage Evaluation & Maintenance Program

Request for Proposal: City of Claremont Parking Garage Evaluation & Maintenance Program Request for Proposal: City of Claremont Parking Garage Evaluation & Maintenance Program October 2015 Page 1 of 10 Table of Contents 1.0 General Information 2.0 Evaluation & Maintenance Program Overview

More information

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732)

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732) THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ 08904 PHONE (732)572-4420 February 10, 2017 Window Replacements at Samuel J Kronman Building and Park Terrace

More information

THE CONSTRUCTION SUPERVISOR

THE CONSTRUCTION SUPERVISOR City of Aurora Building Inspections 15151 E Alameda Pkwy Aurora, CO 80012 (303) 739-7420 THE CONSTRUCTION SUPERVISOR When a building permit has been issued for any construction within the City, the Supervisor

More information

BUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER

BUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER THE CORPORATION OF THE MUNICIPALITY OF SOUTH HURON 322 Main Street South, P.O. Box 759, Exeter, Ontario N0M 1S6 PHONE: (519) 235-0310 FAX: (519) 235-3304 TOLL FREE: 1-877-204-0747 WEBSITE: www.southhuron.ca

More information

FACILITIES DESIGN STANDARDS

FACILITIES DESIGN STANDARDS FACILITIES DESIGN STANDARDS 7th Edition June 21, 2016 Use only the most current copy of these Design Standards. Most current Edition including revisions can be found at the MnSCU Facilities website. http://www.finance.mnscu.edu/facilities/design-construction/resources.html

More information

COMMERCIAL PLANS SUBMITTAL CHECKLIST For Commercial and Multi-family (3 or more units) Building Permit Applications

COMMERCIAL PLANS SUBMITTAL CHECKLIST For Commercial and Multi-family (3 or more units) Building Permit Applications COMMERCIAL PLANS SUBMITTAL CHECKLIST For Commercial and Multi-family (3 or more units) Building Permit Applications Building Permit Application (3 rd Page MUST be signed & notarized by Owner!) Plans can

More information

Building Code 8 th Edition

Building Code 8 th Edition Massachusetts State Building Code 8 th Edition Kevin S. Hastings, P.E., LEED AP R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com RW R.W. Sullivan Engineering

More information

Building Permit Application Instructions INFORMATION REQUIRED FOR ISSUANCE OF A BUILDING PERMIT

Building Permit Application Instructions INFORMATION REQUIRED FOR ISSUANCE OF A BUILDING PERMIT Building Permit Application Instructions NOTICE: Keep these instructions for your records. Please read and understand these instructions completely prior to completing and submitting your building permit

More information

Property Condition Assessment (PCA) Checklist c:\users\joseph\documents\hhc\blog\pca cklist template.doc Friday, August 11, 2006

Property Condition Assessment (PCA) Checklist c:\users\joseph\documents\hhc\blog\pca cklist template.doc Friday, August 11, 2006 FORUM for Historic Harvard Property Assessment (PCA) Checklist c:\users\joseph\documents\hhc\blog\pca cklist template.doc Friday, August 11, 2006 The purpose of this document is to identify in checklist

More information

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS This guide is intended to provide the homeowner or contractor with the

More information

How to estimate the cost of new air conditioning system to an existing storage warehouse.

How to estimate the cost of new air conditioning system to an existing storage warehouse. How to estimate the cost of new air conditioning system to an existing storage warehouse. 1 How to estimate the cost of new air conditioning system to an existing storage warehouse. Table of Contents Section

More information

Questions and Answers about Madison Crescent and Noise Issues

Questions and Answers about Madison Crescent and Noise Issues Questions and Answers about Madison Crescent and Noise Issues Question: What codes were applicable to our condos when they were built? Answer: The Virginia Uniform Statewide Building Code (VUSBC) - The

More information

Standard Plan Review - Project Submittal Checklist

Standard Plan Review - Project Submittal Checklist Standard Plan Review - Project Submittal Checklist DATE: PROJECT ADDRESS: PROJECT MANAGER: RETURN TO PM WITH CORRECTIONS 2 nd INTAKE APPOINTMENT Submit the following requirements, as applicable, at the

More information

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

DESIGN DEVELOPMENT PHASE

DESIGN DEVELOPMENT PHASE UNIVERSITY OF MICHIGAN DESIGN DELIVERABLES FEBRUARY 2012 As part of the deliverables for formal UM review at each of the major phases of design listed below, the Design Professional shall submit this "Design

More information

Model Written Indoor Air Quality Program. The Summit Board of Education Administrative Offices 14 Beekman Terrace Summit, NJ

Model Written Indoor Air Quality Program. The Summit Board of Education Administrative Offices 14 Beekman Terrace Summit, NJ Model Written Indoor Air Quality Program Summit Public Schools The Summit Board of Education Administrative Offices 14 Beekman Terrace Summit, NJ 07901-1702 Prepared by: Mr. Louis J. Pepe, RSBA Mr. Angelo

More information