The Standard New Road Project

Size: px
Start display at page:

Download "The Standard New Road Project"

Transcription

1 Agile Construction Initiative The Standard New Road Project Benchmark method ACI/DLV/ 96/017

2 The Standard New Road Project Authors David Madigan, Agile Construction Initiative Document control information: Date of issue 31 March, 1997 Document number ACI/DLV/ 96/017 Circulation Public Version 3.00 To obtain a copy of this document contact ACI at: School of Management University of Bath Bath, BA2 7AY United Kingdom Tel: + 44 (0) Fax: + 44 (0) A.P.Graves@bath.ac.uk Web: Copyright University of Bath, 1997 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means electronic, mechanical, photocopying, recording or otherwise without the prior written permission of the copyright holder. 2

3 Table of Contents 0. TABLE OF CONTENTS INTRODUCTION THE AGILE CONSTRUCTION INITIATIVE THE PRINCIPLES OF BENCHMARKING THE PURPOSE OF THIS DOCUMENT PRODUCT BREAKDOWN STRUCTURE DEVELOPING THE PRODUCT BREAKDOWN STRUCTURE HIGHWAYS AGENCY CESMM ADVANTAGES AND DISADVANTAGES DETAILED COMPARISON FINAL PRODUCT BREAKDOWN STRUCTURE SIZING ELEMENTS PRINCIPLES OF MEASUREMENT GENERAL COMMENTS ON MEASUREMENT EARTHWORKS IN SITU CONCRETE CONCRETE ANCILLARIES DRAINAGE PIPES PIPEWORK - MANHOLES PILES ROADS AND PAVING RESULTS FROM PILOTS THE NEED FOR SIZING ITEMS GENERAL DIFFICULTIES IN OBTAINING DATA CONCLUSIONS ANNEX A - DERIVATION OF SIZING ITEMS FOR MANHOLES...26 FIGURE 1 EARTHMOVING OPERATIONS...11 FIGURE 2 TYPICAL CROSS SECTION OF A ROAD...22 FIGURE 3 COMPOSITE CONSTRUCTION...23 FIGURE 4 RIGID CONSTRUCTION...23 FIGURE 5 LABOUR GANG HOURS VERSUS MANHOLE VOLUME...26 TABLE 1 HIGHWAYS AGENCY MEASUREMENT METHOD - SERIES...7 TABLE 2 MAIN CATEGORIES OF CESMM...8 TABLE 3 ADVANTAGES AND DISADVANTAGES OF BOQ AND CESMM...8 TABLE 4 DETAILED COMPARISON OF BOQ AND CESMM...8 TABLE 5 PRODUCT BREAKDOWN STRUCTURE...9 TABLE 6 EXCAVATION TIMES FOR DIFFERENT TYPES OF MATERIAL...13 TABLE 7 EQUIVALENT QUANTITY OF EXCAVATION...13 TABLE 8 VARIATION OF EXCAVATION TIMES WITH MATERIAL TYPE...14 TABLE 9 EQUIVALENT QUANTITY OF EXCAVATION...14 TABLE 10 VARIATION OF MAKE AND FIX TIME WITH TYPE OF FORMWORK...16 TABLE 11 SIMPLIFIED FORMWORK PRODUCTIVITY FACTORS...16 TABLE 12 CALCULATION OF EQUIVALENT QUANTITIES OF FORMWORK

4 Introduction The Agile Construction Initiative The Agile Construction Initiative (ACI) is a new project under the government s Innovative Manufacturing Initiative (IMI), funded by the Engineering and Physical Sciences Research Council (EPSRC). ACI has been set up to research into the transfer of lean production practices pioneered by leading Japanese manufacturing companies to the UK civil engineering industry. The leading industrial partner will be Balfour Beatty Civil Engineering Limited (BBCEL) based in the UK. The research is being undertaken by the University of Bath, School of Management. The programme of work consists of a number of elements. Primarily, the project will undertake benchmarking to compare the current performance of the UK construction industry with the best in the world. It will develop ideas on what constitutes best practice in the construction industry. Best practices identified by the programme will be piloted by the Agile Construction Initiative within the industrial partners before being disseminated to the industry at large. In parallel to this work research will be conducted on financial control systems, managing the value chain and life cycle assessment. The principles of benchmarking Benchmarking is a management tool that is currently enjoying a high profile. Many projects are being carried out under the banner of benchmarking and it is important to outline what ACI understands by the term. ACI has adopted the following definition of benchmarking: Benchmarking is a systematic and continuous measurement process; a process of continuously measuring and comparing an organisation s business processes against business process leaders anywhere in the world to gain information which will help the organisation take action to improve its performance. 1 In order to develop a methodology some additional principles have been adopted, based on the work of the International Motor Vehicle Program (IMVP). 1. Standard products 2. Measures of performance 1 The definition was developed by the International Benchmarking Clearinghouse (IBC) 4

5 3. Indicators of practice. The use of standard products allows fair comparison to be made between different organisations. It is important to compare apples to apples. The standard product is defined by the set of activities that result in the construction of the standard product. Measures of performance are used to find the organisations that are capable of delivering superior performance to their customers. The starting point for lean thinking is the concept of value. Organisations exist to create value for their customers and this must be reflected in the measures of performance. Indicators of practice are used a the stepping stone into deep case studies of successful organisations. They point to the best practices that allow the organisations to deliver superior performance. The purpose of this document The overall benchmark method is described in full in the ACI Working Paper Benchmark Method: Building on CESMM. The purpose of this document is to describe one of the standard products that has been developed to benchmark the civil engineering industry. This standard product is a new road construction. The document describes the activities that are included in the definition of the standard product and the principles of measurement that apply to these activities. 5

6 Product breakdown structure Developing the product breakdown structure The product breakdown structure defines the construction products that when assembled together on site make up the standard new road. The list was arrived at by doing the following: 1. Excluding all products that were considered non-standard and for which it would be difficult to get data from all participating projects. 2. Taking the 20% of components that represented about 80% of the cost of the standard product. 3. Generalising the component definitions to make it easier to get returns from all participating projects. This resulted in about fifty elements in the standard new road. Two standard documents were using in generating the component definitions; the Highways Agency Bill of Quantities and the ICE s CESMM3. These are rather different in character as a result of the generalisation in CESMM3 to make it applicable to all civil engineering contracts. The following sections contrast the two documents and then introduce the final product breakdown structure for the new road project. Highways Agency The Highways Agency measurement method is organised into a number of different series of construction components. Series 400 Safety Fences Safety Barriers And Pedestrian Guardrails Beam Safety Fences Vertical Concrete Barrier Series 500 Drainage And Service Ducts Drains Sewers Piped Culverts And Service Ducts (Excludng Filter Drains, Narrow Filter Drains And Fin Drains) Fin Drains And Narrow Filter Drains Filter Drains Linear Soakway Chambers Concrete Channels Series 600 Earthworks Excavation Excavation In Hard Material Deposition Of Fill Compaction Of Fill Topsoiling And Storage Of Topsoil Grassing Completion Of Formati0n Series 700 Pavements 6

7 CESMM3 Sub Base Flexible Pavement Rigid Pavement Bridge Decks.Surfacing Series 1100 Kerbing footways and paved areas Kerbs, Channels, Edgings And Combined Drainage And Kerb Blocks Series 1200 Traffic Signs & Roadmarkings Roadmarkings Table 1 Highways Agency measurement method - series The applicable sections of CESMM3 are as follows: Code Description E EARTHWORKS F IN SITU CONCRETE G CONCRETE ANCILLARIES G1 Formwork: rough finish G2 Formwork: fair finish G3 Formwork: other stated finish G4 Formwork: stated surface finish G5 Reinforcement G8 Concrete accessories G81 Finishing of top surfaces I PIPEWORK - PIPES K PIPEWORK - MANHOLES ETC M STRUCTURAL METALWORK M5 Erection of members for bridges N MISCELLEANOUS METALWORK N15 Bridge parapets P PILES P1 Bored cast in place concrete piles R ROADS & PAVING R3 Sub-bases, flexible road bases and surfacing R4 Concrete pavements R6 Kerbs, channels and edgings R8 Ancilliaries R82 Surface markings W WATERPROOFING X MISC. X1 Fences X18 Metal crash barriers 7

8 Table 2 Main categories of CESMM Advantages and disadvantages Highways Agency BoQ UK Highways projects site measurement systems will match this format well. The match between BoQ items and site activities is good. Little work has to be done on the BoQ to turn it into the benchmark method. Site performance isn t recorded in same categories as BoQ Detailed comparison CESMM3 The performance on individual construction activities can be compared for non-highways and highways sites The match will not be so good in all cases. More work has to be done. Site performance isn t recorded in same categories as CESSM3 Table 3 Advantages and disadvantages of BoQ and CESMM Item Highways Agency CESMM3 Placement of concrete Divides items according to location in structures; superstructure, ends Divides items according to type of pour; slab, wall, base, column supports Distinguishes between Excavation Formwork Reinforcement concrete mixes. Separate items for compaction Uses Highways Agency materials definitions (in particular chalk is treated separately) Uses Highways Agency formwork definitions Table 4 Detailed comparison of BoQ and CESMM Final product breakdown structure Simpler materials definitions Distinguishes between straight and deformed reinforcement The final product breakdown structure is shown in Table 5. The breakdown is based on the Highways Measurement Method and CESSM. The breakdown is simplified to tie up with the way that data is collected on site. 8

9 Sizing elements Classification Description C31 Insitu concrete in Superstructure C32 Insitu concrete in End Supports C33 Insitu concrete in Intermediate Supports C34 Insitu concrete in Underpass/Culvert main construction C7 Insitu concrete in blinding not exceeding 75mm in thickness E11 Excavation of acceptable material; Topsoil E12 Excavation in cutting and other excavation other than topsoil and rock E311 Deposition of acceptable material in embankments and other areas of fill; material other than topsoil and rock E322 Deposition of acceptable material in landscape areas E51 Topsoiling of varying thickness to surfaces sloping at 10 degrees or less to the horizontal E52 Topsoiling of varying thickness to surfaces sloping exceeding 10 degrees to the horizontal E7 Completion of formation F11 Formwork in Superstructure F12 Formwork in End Supports F13 Formwork in Intermediate Supports F14 Formwork in Underpass/Culvert main construction I11 Carrier drain, internal diameter from greater than 150mm and less than or equal to 450mm, in a trench depth to invert less than or equal to 3m I12 Carrier drain, internal diameter from greater than 450mm and less than or equal to 750mm in trench depth to invert less than or equal to 3m I21 Edge of carriageway drain; narrow; in trench depth not exceeding 1.5m I3 Manhole I4 Gullies P1 Vertical 600 or 750mm diameter cast-in-place main piling (boring, concrete and reinforcement) P2 Vertical 900mm or 1050mm diameter cast-in-place main piling (boring, concrete and reinforcement) R11 Granular sub-base in main carriageway R12 Lean concrete sub-base in main carriageway R22 Heavy Duty Macadam basecourse in main carriageway R23 Heavy Duty Macadam roadbase in main carriageway R31 Wearing Course in main carriageway R32 Continuous Reinforced Concrete Pavement in main carriageway S1 High yield steel deformed bar reinforcement in superstructure S2 High yield steel deformed bar reinforcement in end supports S3 High yield steel deformed bar reinforcement in intermediate supports S4 High yield steel deformed bar reinforcement in underpass/culvert main construction SF1 Safety fence; untensioned single sided open box beam straight or curved exceeding 50 metres radius SF2 Safety fence; tensioned double sided corrugated beam straight or curved exceeding 50 metres radius Table 5 Product breakdown structure The final product breakdown structure is inadequate for making like for like comparisons between different sites. The categories are too broad. To 9

10 overcome this the concept of sizing elements are introduced. These work as follows: 1. The site submits are return for a given element in the product breakdown structure. The return contains the quantity of the item produced. 2. The product breakdown structure categories are too general for fair comparison so the quantities are adjusted using sizing elements. 3. The quantity adjustment means that the comparison is being made against the same construction product. This is best illustrated by an example. 1. Formwork performance data is collected according to the part of the structure that is being constructed; superstructure, end supports etc. 2. However, two end supports are not the same design and will contain different mixes of individual types of formwork. 3. In order to make fair comparison, the quantities of different classes of formwork are listed and then these are converted to equivalent quantities of a single class of formwork. 4. The conversion is based on the different times it takes to fix each different class of formwork according to the CESSM3 Price Database 1996/7. The classes that are used are i) horizontal, sloping or battered ii) vertical and iii) curved. The quantities of each of these that go together to make up the total quantity on the return are listed. They are then converted to equivalent quantities of horizontal formwork. The total quantity of horizontal equivalent is then used to compare performance. 10

11 Principles of measurement General comments on measurement Earthworks Excavation General The benchmark method requires the following data to supplied for each of the activities that make up the standard new road project. 1. The total quantity of the component produced by the activity. 2. The amount of working time that the construction gang spent producing the component. 3. The theoretical capability of the construction gang based on the plant configuration in use. In order to make sure that a fair comparison is made between projects a number of additional factors will be measured that may affect performance. If necessary the affect of these will be removed before project performance is compared. The following sections define the principles of measurement for different classes of construction components that make up the new road project. Disposal Re-use Double handling Import Figure 1 Earthmoving operations 2 2 Taken from Barnes, M (1992) CESMM3 Handbook, London: Thomas Telford 11

12 Effort calculation Capability calculation Sizing factors Excavation and filling/compaction are separated. The reason for this is because of the varying destinations and sources for excavated and filling material. This is shown in Figure 1. The amount of effort required is calculated for each piece of excavation plant. The time is then the amount of time that the piece of plant is working. The time includes time that the plant is idle awaiting trucks to load and plant breakdowns, but excludes meal breaks and breaks for poor weather. The calculation is the same for motor scrapers. They will not suffer idle time awaiting trucks but may have idle time waiting for access to the cutting area. As the productivity may vary according to the type of material being excavated, this information will be included on the returns to allow its significance to be investigated. The rate of production that the excavation plant should be capable of producing working 100% of the time according to the manufacturers specification. The rate of production will need to take into account the properties of the material being excavated, in particular the bulking factor of the material. The rate of production of excavators is related to the type of material being dug. In order to make fair comparison on excavation, the returns need to be adjusted to a common material type. The default material is Medium hard clay with cobbles. Returns for other types of materials will be adjusted. The quantities will be adjusted to equivalent quantities of the default material. The following adjustments will be made to the working time according to the type of material being excavated: 12

13 Factors to measure Material being excavated Multiplier (Equivalent quantity = measured measured * Multiplier) Firm sand 0.70 Soft loam, sandy clay 0.85 Medium hard clay with cobbles 1.00 Gravel 1.10 Broken stone 1.25 Stiff clay with boulders 1.33 Soft chalk 2.50 Table 6 Excavation times for different types of material Sample calculation: Material Quantity (m 3 ) Equivalent quantity (m 3 ) Medium hard clay with cobbles 40,000 40,000 Broken stone 60,000 75,000 TOTAL 100, ,000 Table 7 Equivalent quantity of excavation Working time = 262 hours Gross productivity = 262/100,000 = 2.62 per 1000m 2 Adjusted productivity = 262/115,000 = 2.28 per 1000m 2 1. The average distance the material is being hauled over (in km) 2. Whether the haul is all contained within the site or goes on to public roads. (1 = within site, 2 = on public roads). 3. The destination of the material. Filling and compaction General comments Effort calculation Filling and compaction will be measured as a single activity. The amount of effort is calculated for each piece of compaction plant. The amount of effort will be the working time of the compaction plant. The time 13

14 Capability calculation Sizing factors includes time that the plant is idle awaiting material to compact and plant breakdown, but excludes meal breaks, breaks for poor weather. The rate of production that the excavation plant should be capable of producing working 100% of the time according to the manufacturers specification and the appropriate design tables of numbers of passes required for the material being compacted. 1. The material being compacted. The rate of production of excavators is related to the type of material being dug. In order to make fair comparison on excavation, the returns need to be adjusted to a common material type. The default material is Medium hard clay with cobbles. Returns for other types of materials will be adjusted. The quantities will be adjusted to equivalent quantities of the default material. The following adjustments will be made to the working time according to the type of material being excavated: Material being excavated Multiplier (Equivalent quantity = measured quantity * Multiplier) Firm sand 0.70 Soft loam, sandy clay 0.85 Medium hard clay with cobbles 1.00 Gravel 1.10 Broken stone 1.25 Stiff clay with boulders 1.33 Soft chalk 2.50 Table 8 Variation of excavation times with material type Sample calculation: Material Quantity (m 3 ) Equivalent quantity (m 3 ) Medium hard clay with cobbles 40,000 40,000 Broken stone 60,000 75,000 TOTAL 100, ,000 Table 9 Equivalent quantity of excavation Working time = 262 hours 14

15 Factors to measure In situ concrete General Effort calculation Gross productivity = 262/100,000 = 2.62 per 1000m 2 Adjusted productivity = 262/115,000 = 2.28 per 1000m 2 1. The average distance the material is being hauled over (in km) 2. Whether the haul is all contained within the site or goes on to public roads. (1 = within site, 2 = on public roads). 3. The source of the material. Separate items are included for different types of pour. The amount of effort is calculated as the working time from start to finish on a particular concrete pour. The figure includes time preparing for the pour, the pour itself and any time required to finish the concrete and repair any cracks etc. The time excludes meal breaks and curing time for the concrete. Capability calculation Sizing factors Not applicable. None. Factors to measure 1. Indicate the type of pour (1 = Concrete pump; 2 = Direct from concrete mixer, 3 = Manual (using dumper, excavator shovel etc), 4 = Skip and crane) Concrete ancillaries Formwork General Separate returns are required for end supports, intermediate supports, superstructure and culvert/underpass main construction. 15

16 Effort Calculation Capability Calculation Sizing factors The effort calculation shall be the total man hours in fabricating, assembling, striking and cleaning/repairing the formwork. The calculation should include the assembly and striking of any falsework required to support the formwork. Not applicable. The time taken to fix formwork of different types is shown below. 3 Rough Fair Extra Smooth Horizontal Sloping Battered Vertical Curved Table 10 Variation of make and fix time with type of formwork This has been simplified to three categories: Type of formwork Horizontal, sloping or battered Correction factor Vertical 1.65 Curved 2.25 Table 11 Simplified formwork productivity factors Formwork quantities will be converted into equivalent horizontal formwork quantities. Example: 1 3 Source: Harris, EC (1996) CESMM3 Price Database 1996/7, London: Thomas Telford 16

17 Type of formwork Measured Qty, m 2 Horizontal equivalent, m 2 Horizontal, sloping or battered Vertical Curved Factor to measure Reinforcement General Effort Calculation Capability Calculation Sizing factor TOTAL Table 12 Calculation of equivalent quantities of formwork Working time = 320 hours Gross productivity = 320/316 = 1.01 hours per m 2 Adjusted productivity = 320/518 = 0.62 hours per m 2 1. Where is the formwork manufactured? (1 = on-site, 2 = off-site) 2. How many times on average is formwork re-used? Separate returns are required for end supports, intermediate supports, superstructure and culvert/underpass main construction. The effort calculation shall be the total man hours in handling and fixing of reinforcement. The calculation shall include all effort from the arrival of steel on site to the start of the concrete pour. The time shall include time waiting for deliveries, information etc but exclude meal breaks. Not applicable. 1. The nominal size of the reinforcement bars. The time taken to fix reinforcement is proportional to the mass per unit length of the reinforcement. If the standard nominal size of the reinforcement bars is taken to be 20mm, then the quantity of reinforcement can be adjusted to an equivalent quantity of 20mm nominal size reinforcement. The equivalent quantity of 20mm nominal size reinforcement is then calculated as: 17

18 q 20 = q m { 1 ( 20 )} d 20 d + am m... Equation 1 m 2 Where, m - the mass per kg of the steel actually fixed m 20 - the mass per kg of 20mm nominal size steel q - the quantity of steel actually fixed. q 20 - the equivalent quantity of 20mm nominal size steel. d m - the nominal size of the steel actually fixed d 20 - the nominal size of the default reinforcement (20mm) Example: Factor to measure Drainage pipes General Effort measurement Nom Size, mm Qty, tonne Mass, kg/m Qty (20mm), Tonne TOTAL Working time = 98 hours Gross productivity = 98/10.4 =9.42 hours per tonne Adjusted productivity = 98/13.07=7.50 hours per tonne 1. Is the steel delivered JIT? The measurement will include all activities related to drainage installation, including excavation, supporting of trenches, installation of pipes, backfilling and testing. The effort will be the total working time of each gang that is advancing a single line of drainage. Working time shall include any time waiting for preceding activities, but will not include meal breaks or breaks due to weather conditions. Capability calculation Not applicable. 18

19 Sizing factors Factor to measure 1. Nominal bore, mm 2. Depth to invert, m The time taken to lay a carrier drain varies linearly with the nominal bore of the pipe and the depth to invert. There are four zones in which these relationships hold: 1. Small, shallow pipes (nominal bore < 450mm, depth < 3m) 2. Small, deep pipes (nominal bore < 450mm, depth > 3m) 3. Large, shallow pipes (nominal bore > 450mm, depth < 3m) 4. Large, deep pipes (nominal bore > 450mm, depth > 3m) For each zone, the time taken to lay a drain can be expressed as: t = t0 + a. dnom + b. hnom... Equation 2 Where, d nom - the nominal depth in metres h nom - the nominal pipe diameter in mm. The equivalent quantity of nominal sized pipes, is then given by the following: { ( ) ( )} q = q 1 + a d d + h h... Equation 3 nom nom nom Length,m Depth, m Diameter, mm Length of nominal pipe,m Working time = 16 hours Gross productivity = 16/200 = 0.08 hours per m Adjusted productivity = 16/167.5 = 0.10 hours per m 1. Type of excavation (1 = hand, 2 = excavator, 3 = trencher) 2. Type of material. 3. Type of support to pipes (1 = concrete bed, 2 = concrete bed + surround, 3 = granular bed, 4 = granular bed + surround, 5 = granular bed + haunch, 9 = other) 19

20 4. Type of pipe (1 = clay, 2 = concrete, 3 = iron, 4 = steel, 5 = PVC, 6 = GRP, 7 = polyethylene, 9 = other) Pipework - Manholes General Effort measurement The depths of manholes shall be measured from the tops of covers to channel inverts of base slabs, whichever is lower. The measurement will include all items, including excavation, installation of the manhole, installation of pipework and fittings and backfilling. Capability calculation Sizing Factors Not applicable. 1. Internal diameter of the manhole, D 2. The depth of the manhole, h. The time taken to install the manhole is found to be a function of the volume, V = πd 2 * h... Equation 4 Where, D - the internal diameter of the manhole, mm h - the depth of the manhole, m The time taken to install a manhole is then, t = 1 + a( V Vnom)... Equation 5 Where, V nom is the volume of the standard manhole. The equivalent number of nominal sized manholes, is then given by the following: ( ( nom )) q = q 1 + a V V... Equation 6 nom Depth, m Diameter, mvolume, m Number of nominal tan Working time = 7.3 hours Gross productivity =7.3 hours per manhole 20

21 Factor to measure Piles General Effort calculation Adjusted productivity = 7.3/ = hours per manhole 1. Type of manhole (1 = Brick, 3 = In situ concrete, 5 = Precast concrete, 9 = Other) The length of piles shall be those required, from the cut-off level to the toe level. Will include all operations including setting up the rig, boring, reinforcement, placing of concrete and breaking down any excess. Working time shall be the total working time on the pile including breakdowns and waiting for materials but excluding meal breaks and breaks due to weather. Capability calculation Not applicable. Factor to measure 1. Number of piles. Roads and paving Sub-bases, flexible road bases and surfacing General A typical cross section of a road pavement is shown in Figure 2. The capping layer is only required if the subgrade is weak. 21

22 Surfacing Road surface Wearing course Base course Roadbase Pavement Pavement foundation Sub-base Formation Capping Subgrade Formation Effort Calculation Capability calculation Sizing factor There are two variations of interest; rigid pavement construction and composite construction (Error! Reference source not found.). The effort calculation will be carried out for the gang of men and machines that are advancing a single line of road. In the case of flexible road layers this will probably correspond to a paving machine. In the case of the rigid pavement this will correspond to a concrete train. The capability calculation will be based on the rated output of the paving machine or concrete train. 1. Depth of the road layer, mm The time taken to lay a m 2 of roadworks and paving is proportional to the depth of the layer. t Figure 2 Typical cross section of a road = ad... Equation 7 If the nominal depth of a road layer is d nom, then the equivalent quantity of nominal depth roadworks and paving is given by the following: q nom d = q....equation 8 dnom Example: Base course nominal depth is 50mm. 22

23 Surfacing Road surface Wearing course Base course Roadbase Pavement Pavement foundation Lean-mix Capping Subgrade Formation Figure 3 Composite construction Pavement Surfacing Pavement foundation Road surface Reinforcement mesh Concrete Polythene Sub-base Subgrade Formation Factor to measure Figure 4 Rigid construction Return, nominal depth is 75mm. Quantity is 1000m 2.. The equivalent quantity of 50mm base course is 1500m 2. Working time = 7.3 hours Gross productivity =7.3 hours per 1000m 2 Adjusted productivity = 7.3/1.5 = 4.9 hours per 1000m The actual width of the road 2. The actual depth of the layer. 23

24 Results from pilots The need for sizing items The pilots showed up difficulties in the original concept. The list of construction activities was initially based more directly of CESMM. This proved problematic for the following reasons: 1. Site data collection did not generally go down to the required level of detail. Increasingly site data collection is based on the activities on the project plan. These would have items such as fix formwork on abutment. There was no way to separate data amongst the different types of formwork in CESMM. 2. Using the CESMM definitions led to a list of 55 construction activities that accounted for about 80% of the value of the standard project. When visiting other sites it was impossible to get returns on all 55 due to differences in the designs. Sizing items have two main advantages: 1. They allow the data to be collected at a level that suits the sites - resulting in returns on only about 30 construction activities. 2. They allow the data to be adjusted for differences in the designs on different sites so that a like for like comparison of performance can be made. General difficulties in obtaining data Whilst sizing items helped a great deal in the development of the method, there were still difficulties with the quantity and quality of data on site. The information required by the benchmark method is all available on site to some degree. However, it is often fragmented amongst different individuals - engineers, quantity surveyors, accountants etc. Sometimes differences in the way that these different groups collect data makes it difficult to combine the data in the way that we require. There is also a difficulty with obtaining consistency with respect to the productive units. When counting hours on an activity like formwork, some sites only included carpenters hours, whilst others included carpenters and labourers. Similarly, on plant intensive activities it is often difficult to extract the hours for the productive units from the general plant hours. As a result the amount of that can be achieved with historic data may be limited. It may be necessary to work only with live sites, training site personnel in the benchmark method. 24

25 Conclusions The standard new road project has proved that the principles adopted by ACI for benchmarking civil engineering projects can be applied in practice. However, pilot trials have highlighted difficulties with both the design of the method and its implementation. Having learnt from these experiences ACI is now ready to roll out the method on a wider scale and will be looking for projects to benchmark over the next few years, in order to build up a comprehensive picture of the relative performance of civil engineering projects. This information will then be used to derive guidelines about best practice in civil engineering. 25

26 Annex A - Derivation of sizing items for manholes The data in the CESMM price book was put into a table. Several attempts were made to find a physical characteristics of the manhole that varied linearly with the time taken to install a manhole. It was found that the time taken varied with the volume of the manhole, calculated as follows: V 2 D = π 4 h... Equation 9 A regression analysis was carried out on the data to determine the relationship between the production time and the volume. The results are shown in Figure 5. X Variable 1 Line Fit Plot Labour Gang Hours Y Predicted Y V olum e of m anhole (m 2) Figure 5 Labour gang hours versus manhole volume The relationship was then normalised around the time taken to install a 1200mm diameter, 3m deep manhole. The resulting equation is given by the equation: t t t 0 = a t + t V...Equation 10 nom nom nom But, we know that t = t nom when V = V nom, so the equation can be rewritten as follows: 26

27 { } t a t = 1 + t V V...Equation 11 nom nom nom Rather than adjust the working time, it is better to adjust the quantity produced to achieve the same effect. That is the actual quantity of a product is modified to give an equivalent quantity of the nominal size product. It is this nominal equivalent quantity that is used to determine the productivity of the project. I.e. ( ) Q= Q a a 1 + t V V nom...equation 12 nom Where Q a is the actual quantity produced and Q is the equivalent quantity of the nominal sized product. 27

Agile Construction Initiative. Benchmark Method. Building on CESMM ACI/DLV/ 96/015

Agile Construction Initiative. Benchmark Method. Building on CESMM ACI/DLV/ 96/015 Agile Construction Initiative Benchmark Method Building on CESMM ACI/DLV/ 96/015 BENCHMARK METHOD AGILE CONSTRUCTION INITIATIVE Benchmark method Author David Madigan, Agile Construction Initiative Document

More information

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2 Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2 PARTICULAR SPECIFICATIONS FOR THE CONSTRUCITON OF STORM WATER DRAINAGE NETWORK March 2018 BUREAU TECHNIQUE POUR LE DEVELOPPEMENT P.O.B

More information

ITEM No. D E S C R I P T I O N UNIT QTY. 5-E343.2 In class III material m³ 1,260 - Max. Depth: m For disposal

ITEM No. D E S C R I P T I O N UNIT QTY. 5-E343.2 In class III material m³ 1,260 - Max. Depth: m For disposal EARTHWORKS Excavation for foundations 5E343.2 In class III material m³ 1,260 Max. Depth: 0.50 1 m For disposal 5E334.2 In class III material m³ 720 Max. Depth: 1 2 m For disposal Filling Ancillaries 5E723.0

More information

Requirements for Measuring and Pricing of Drainage and Service Ducts

Requirements for Measuring and Pricing of Drainage and Service Ducts Requirements for Measuring and Pricing of Drainage and Service Ducts October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for

More information

Method of Measurement for Road Works Series MM Earthworks

Method of Measurement for Road Works Series MM Earthworks Method of Measurement for Road Works Series MM 600 - CC-RMP-00600 March 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Requirements for Measuring and Pricing of Structural Concrete

Requirements for Measuring and Pricing of Structural Concrete Requirements for Measuring and Pricing of Structural Concrete October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Cost Estimate Summary Site Prep Supervision Works Cost Risk OB Works + Risk + OB Total Union Street / Laburnum Row Junction 12,353 5,147 73,006

Cost Estimate Summary Site Prep Supervision Works Cost Risk OB Works + Risk + OB Total Union Street / Laburnum Row Junction 12,353 5,147 73,006 Cost Estimate Summary Site Prep Supervision Works Cost Risk OB Works + Risk + OB Total Union Street / Laburnum Row Junction 12,353 5,147 73,006 14,996 9,051 97,053 114,553 Union Street / Trematon Avenue

More information

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY D DEMOLITION & SITE CLEARANCE D1 GENERAL CLEARANCE 6-D152 Open bush and thicket in and around ha 0.02 the ponds. Locally disposed. D2 REMOVAL OF TREES AND STUMPS 6-D212 Trees of girth: 150 mm - 500 mm

More information

Technical Data Sheet NEC/GRAN/95:01

Technical Data Sheet NEC/GRAN/95:01 Technical Data Sheet NEC/GRAN/95:01 Installation Guidance Notes Granular Surround Note : These guidance notes refer only to the installation of Granular surround underground tanks. These guidance notes

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

Method of Measurement for Road Works Series MM Drainage and Service Ducts

Method of Measurement for Road Works Series MM Drainage and Service Ducts Method of Measurement for Road Works Series MM 500 - CC-RMP-00500 March 2015 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

DRAFT. Draft Bill of Quantities. Drainage

DRAFT. Draft Bill of Quantities. Drainage Draft Bill of Quantities September 2015 STORM DRAINAGE INFORMATION Measurement notes Drawings used : WYG (80) 140 Rev T1, D-(80) 001 Rev T1, D-(80) 002 Rev T1, D-(80) 003 Rev T1 and D-(80) 004 Rev T1 All

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

Initial Construction Costs For Various Pavement and Drainage Options

Initial Construction Costs For Various Pavement and Drainage Options Interpave Initial Construction Costs For Various Pavement and Drainage Options Final Prepared For Interpave Scott Wilson Ltd Interpave Pavement Design CONTENTS 1. Overview 2. Summary of Pavement Types

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES INCLUDING KERB & GUTTER (CHANNEL) C224 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C224 ISSUE: NO:1 October 2007 TABLE OF CONTENTS

More information

Introduction to the Guidance on Measuring and Pricing

Introduction to the Guidance on Measuring and Pricing Introduction to the Guidance on Measuring and Pricing October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing and improving

More information

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

Civil Engineering Standard Method of Measurement Examples

Civil Engineering Standard Method of Measurement Examples Civil Engineering Standard Method of Measurement Examples CESMM4 Civil Engineering Standard Method of Measurement Examples Institution of Civil Engineers Published by ICE Publishing, One Great George

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS TABLE OF CONTENTS 11.01 SCOPE OF WORK... 1 11.02 REFERENCES... 1 11.03 MATERIALS... 2 11.04 GRANULAR & NATIVE BACKFILL... 2 11.05 CONSTRUCTION... 2 11.06 MEASUREMENT FOR PAYMENT... 5 11.07 BASIS OF PAYMENT...

More information

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00 Description Page No Summary Amount Summary 1/7 230,694.60 22,019.25 22,642.65 2/6 96,801.30 80,150.60 114,056.00 Total Per Unit (MYR) 327,495.90 102,169.85 136,698.65 Total Unit(s) X 1 2 2 Total Per Type

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 602 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information

SERIES 1100 KERBS, FOOTWAYS AND PAVED AREAS

SERIES 1100 KERBS, FOOTWAYS AND PAVED AREAS MANUAL OF CONTRACT DOCUMENTS FOR HIGHWAY WORKS VOLUME 1 THE SPECIFICATION FOR HIGHWAY WORKS SERIES 1100 KERBS, FOOTWAYS AND PAVED AREAS Contents Clause Title Page 1100 (02/17) General 2 #1101 Precast Concrete

More information

SECTION 303 CULVERTS

SECTION 303 CULVERTS 303.01 Scope - This section covers the construction of pipe culverts. 303.01.01 Definitions for the purposes of this section, the following general terms are defined as follows: a) Backfilling means the

More information

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems.

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems. The Most Advanced Name in Water Management Solutions TM The most cost-effective slotted and trench surface drain systems. A sensible alternative to metal and concrete Since 1987, Duraslot surface drains

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

SECTION EROSION CONTROL DEVICES

SECTION EROSION CONTROL DEVICES SECTION 02374 PART 1 GENERAL EROSION CONTROL DEVICES 1.1 SUMMARY A. Section Includes: 1. Diversion Channels. 2. Rock Energy Dissipator. 3. Paved Energy Dissipator. 4. Rock Basin. 5. Rock Barriers. 6. Sediment

More information

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations. Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information

Design Guidelines October 2016: Issue 3. Section 4 Civil.

Design Guidelines October 2016: Issue 3. Section 4 Civil. Design Guidelines October 2016: Issue 3 Section 4 Civil. www.canterbury.ac.nz/learningresources Standards in the Design Guidelines Suite Design Standard Guidelines Index: 01 General 02 Architecture 03

More information

AN ISO 9001 & COMPANY TENDER DOCUMENT. TENDER No: EPI/WRO/CON/757/0119 FOR

AN ISO 9001 & COMPANY TENDER DOCUMENT. TENDER No: EPI/WRO/CON/757/0119 FOR AN ISO 9001 & 14001 COMPANY TENDER DOCUMENT TENDER No: EPI/WRO/CON/757/0119 FOR Construction of Boundary Wall and allied works for DHH & MCH Hospital at Kendrapara at Odisha state VOLUME III PRICE BID

More information

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required

More information

Bill of Quantities. Bill 1: Site Preparatory Works. Page No. 1/7. Bill 1 Page 1/1. Contract No.

Bill of Quantities. Bill 1: Site Preparatory Works. Page No. 1/7. Bill 1 Page 1/1. Contract No. Bill 1: Site Preparatory Works Page No. 1/7 Bill 1 Page 1/1 1.1 Construction of access roads to quarry sites LS 1 including their maintenance throughout the working period 1.2 Construction of deviations

More information

406 - PIPE SEWERS - MTC FORM 406

406 - PIPE SEWERS - MTC FORM 406 406 - - MTC FORM 406 INDEX 406.1 GENERAL Types of Pipe Pipe Strength, Rigid Pipes Polyethylene Pipe Strength - Rigid or Flexible Pipe Strength and Treatment, Flexible Pipes Selection of Type, Strength

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Retaining Walls. Made Easy

Retaining Walls. Made Easy Retaining Walls Made Easy Retaining Walls Made Easy! Contents Page 1 Contents Page 2 Foreword Page 3 Demolition Page 3 Removal Vegetation Page 3 Excavation Page 4 Reinforcement Steel Page 6 Concreting

More information

Bill No.1: Preliminaries

Bill No.1: Preliminaries Bill No.1: Preliminaries Item No. Description of Works Qty. 1 Mobilization 1.1 This item should include site office for the use of the Engineer's and Employer's staffs with the necessary facilities, furniture,

More information

Method of Measurement for Road Works Series MM Pavements

Method of Measurement for Road Works Series MM Pavements Method of Measurement for Road Works Series MM 700 - CC-RMP-00700 March 015 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C222 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C222 ISSUE: NO:3 July 2018 TABLE OF CONTENTS CLAUSE CONTENTS PAGE GENERAL... 2 C222.01

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

Section 02 SUBSTRUCTURE

Section 02 SUBSTRUCTURE 02 Section 02 SUBSTRUCTURE 1. Trenches to be level, square and free from loose material and standing water. Steps and sides of foundations must be plumb. 2. All tree roots must be removed. Trench depths

More information

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. Box Culverts Box Culverts Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. 2 3 System Overview Forterra is one of the largest

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

2-DAY NATIONAL WORKSHOP ON RELEVANCE OF BESMM4 IN TOTAL COST MANAGEMENT OF CONSTRUCTION/ENGINEERING WORKS ORGANIZED BY:

2-DAY NATIONAL WORKSHOP ON RELEVANCE OF BESMM4 IN TOTAL COST MANAGEMENT OF CONSTRUCTION/ENGINEERING WORKS ORGANIZED BY: 2-DAY NATIONAL WORKSHOP ON RELEVANCE OF BESMM4 IN TOTAL COST MANAGEMENT OF CONSTRUCTION/ENGINEERING WORKS ORGANIZED BY: THE NIGERIAN INSTITUTE OF QUANTITY SURVEYORS HELD AT: BARCELONA HOTELS, NO. 23 BLANTYRE

More information

SERIES NG 1100 KERBS, FOOTWAYS AND PAVED AREAS

SERIES NG 1100 KERBS, FOOTWAYS AND PAVED AREAS MANUAL OF CONTRACT DOCUMENTS FOR HIGHWAY WORKS VOLUME 2 NOTES FOR GUIDANCE ON THE SPECIFICATION FOR HIGHWAY WORKS SERIES NG 1100 KERBS, FOOTWAYS AND PAVED AREAS Contents Clause Title Page NG 1101 General

More information

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems.

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems. The Most Advanced Name in Water Management Solutions TM The most cost-effective slotted and trench surface drain systems. A sensible alternative to metal and concrete Since 1987, Duraslot surface drains

More information

Project: King Abdulaziz International Airport KAIA 2

Project: King Abdulaziz International Airport KAIA 2 Project: King Abdulaziz International Airport KAIA 2 Jeddah, KSA King Abdulaziz International Airport Phase 1 Development Project Project Newsletter Client / Owner: Saudi Binladin Group 22 June 2013. Newsletter

More information

July Bill No.1: Preliminaries

July Bill No.1: Preliminaries Bill No.1: Preliminaries 1 Mobilization 1.1 This item should include site office for the use of the Engineer's and Employer's staffs with the necessary facilities, furniture, computers, printers, photocopier,

More information

ULTRA FLO STEEL PIPE PRODUCT GUIDE

ULTRA FLO STEEL PIPE PRODUCT GUIDE DRAINAGE SOLUTIONS SINCE 1908 ULTRA FLO STEEL PIPE PRODUCT GUIDE LARGE-DIAMETER STORM SEWER PIPE DELIVERS SUPERIOR HYDRAULIC PERFORMANCE FAST INSTALLATION DURABLE NESTABLE PIECES VALUE EFFICIENT HYDRAULICS

More information

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems.

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems. The Most Advanced Name in Water Management Solutions TM The most cost-effective slotted and trench surface drain systems. A sensible alternative to metal and concrete Since 1987, Duraslot surface drains

More information

BELMURO WALL SYSTEM INSTALLATION GUIDE

BELMURO WALL SYSTEM INSTALLATION GUIDE BELMURO WALL SYSTEM INSTALLATION GUIDE TABLE OF CONTENTS TABLE OF CONTENTS... 1 SYSTEM DESCRIPTION... 2 DRY STACK SYSTEM: INSTALLATION GUIDE... 5 GEOGRID WALL SYSTEM: INSTALLATION GUIDE... 9 MASONRY WALL

More information

Installation Information 2016

Installation Information 2016 Installation Information 2016 DENDRO-SCOTT Root Barrier... why use anything else? DENDRO-SCOTT Root Barrier, recognised by the Environment Agency, is known for its quality and reliability. It is flexible

More information

Installation Information 2018

Installation Information 2018 Installation Information 2018 DENDRO-SCOTT Root Barrier... why use anything else? DENDRO-SCOTT Root Barrier, recognised by the Environment Agency, is known for its quality and reliability. It is flexible

More information

Features Include: Near Vertical Walls Do it Yourself No Concrete Footings Required

Features Include: Near Vertical Walls Do it Yourself No Concrete Footings Required Features Include: Near Vertical Walls Do it Yourself No Concrete Footings Required Tel: Office: +27 (0)11 964 2995 Fax number: +27 (0)86 601 6692 info@dsmmasonry.co.za www.dsmmasonry.co.za Range three

More information

1.02 RELATED WORK: Refer to the following sections for related work:

1.02 RELATED WORK: Refer to the following sections for related work: SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete

More information

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS SECTION 10.1 GENERAL 10.1.1 SCOPE This part of the Manual covers the structural design and installation of reinforced concrete pipe for railway culverts. Pipe geometry may be circular, arch, or elliptical.

More information

Method of Measurement for Road Works Series MM Structural Concrete

Method of Measurement for Road Works Series MM Structural Concrete Method of Measurement for Road Works Series MM 1700 - CC-RMP-01700 December 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

NOTES ON CORRUGATED PLASTIC PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION

NOTES ON CORRUGATED PLASTIC PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION TNZ F/5 Notes: 2000 NOTES ON CORRUGATED PLASTIC PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION These notes are for guidance and must not be included in the Contract Documents In general subdivision numbers

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

Construction Specification for General Excavation

Construction Specification for General Excavation Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03

More information

CONTENTS. Cellular Confinement System INTRODUCTION MATERIALS Multi-Cell Fill... 2

CONTENTS. Cellular Confinement System INTRODUCTION MATERIALS Multi-Cell Fill... 2 Johannesburg +27 (0)11 922 3300 Pinetown +27 (0)31 717 2300 Cape Town +27 (0)21 531 8110 East London +27 (0)43 727 1055 www.kaytech.co.za Cellular Confinement System CONTENTS INTRODUCTION... 2 1. MATERIALS...

More information

DIVISION 4100 SITEWORK

DIVISION 4100 SITEWORK DIVISION 4100 SITEWORK SECTION 4115 EARTHWORK PART 1 - GENERAL 1.01 SCOPE This section covers the grading and compaction of excavations, embankments, structural foundations, and planted areas. 1.02 REFERENCES

More information

SAFE WORK PROCEDURE 038 PIT CONSTRUCTION MARCH 2014 DOC. NO. D14/184671

SAFE WORK PROCEDURE 038 PIT CONSTRUCTION MARCH 2014 DOC. NO. D14/184671 MORELAND CITY COUNCIL Operations Centre 7-9 Walter Street Hadfield Vic 3046 Tel: 8311 4300 Approved by the Walter Street OHS committee Date: September 2014 Operation Brief Description of Activity Limitations

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

highways, drainage, runoff, surface, sub-surface, systems Carrier pipe

highways, drainage, runoff, surface, sub-surface, systems Carrier pipe SCI LECTURE PAPERS SERIES HIGHWAY DRAINAGE SYSTEMS Santi V Santhalingam Highways Agency, Room 4/41, St. Christopher House Southwark Street, London SE1 0TE Telephone +44 (0) 171 921 4954 Fax +44 (0) 171

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3 CITY OF TORONTO TS 3.70 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS 3.70.01 SCOPE...3 TS

More information

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 902 DECEMBER 1983 CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES 902.01 SCOPE 902.02 REFERENCES 902.03 DEFINITIONS TABLE OF

More information

Sabah Shawkat Cabinet of Structural Engineering 2017

Sabah Shawkat Cabinet of Structural Engineering 2017 3.9 Concrete Foundations A foundation is a integral part of the structure which transfer the load of the superstructure to the soil without excessive settlement. A foundation is that member which provides

More information

Detailed Estimating-Introduction. Dr. Al-Hammad

Detailed Estimating-Introduction. Dr. Al-Hammad Detailed Estimating-Introduction By Dr. Al-Hammad Outline Introduction Successful Construction Estimating The Detailed Estimating Procedure The stretch - out - Length concept (SOL) Site Work and Excavation

More information

Special Provision No. 421F01 April 2006

Special Provision No. 421F01 April 2006 RIGID PIPE CULVERTS Item No. FLEXIBLE PIPE CULVERTS Item No. CSP ARCH CULVERTS Item No. STRUCTURAL PLATE CSP Item No. CORRUGATED STEEL PIPE EXTENSIONS Item No. ROCK EXCAVATION FOR CULVERTS Item No. CLAY

More information

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 2004 Specifications CSJ 0264-07-028 SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm

More information

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 APRIL 2004 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 353 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS TABLE OF CONTENTS 353.01 SCOPE 353.02 REFERENCES 353.03 DEFINITIONS

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

- Earthwork Operations & Equipments

- Earthwork Operations & Equipments - Earthwork Operations & Equipments Earthwork Operations Those construction processes that involve the soil or earth in its natural form and that precede the building of the pavement structure itself Basic

More information

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM T. C. NEEL and K.BOZKURT ABSTRACT This work shall consist of the design, manufacture

More information

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS) RETAINED SOIL SYSTEM, TRUE ABUTMENT - Item No. RETAINED SOIL SYSTEM, FALSE ABUTMENT - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, HIGH PERFORMANCE - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, MEDIUM PERFORMANCE

More information

GROUNDtrax GROUNDGRIDZ

GROUNDtrax GROUNDGRIDZ INSTALLATION GUIDE The product is asymmetric and must be lifted by placing the hands on the diagonally opposed corners of the central paver (as shown). 1. Place grids onto the prepared well consolidated

More information

Municipal Inspection and Construction Guidelines Section I Roadworks SECTION I ROADWORKS I-1 GENERAL

Municipal Inspection and Construction Guidelines Section I Roadworks SECTION I ROADWORKS I-1 GENERAL I-1 GENERAL SECTION I ROADWORKS The Consultant Engineer is to monitor all specified asphalt, granular materials and sub-grade preparation to ensure all road and curb construction is undertaken as outlined

More information

freestone eco Prestige & quality DIY vertical wall Large blocks - 10/m 2 Smooth surface finish No concrete footings

freestone eco Prestige & quality DIY vertical wall Large blocks - 10/m 2 Smooth surface finish No concrete footings freestone eco Retaining Wall SystemTM The Freestone ECO Retaining Wall System TM is a more sustainable DIY, vertical retaining wall which is manufactured with up to 40% recycled glass aggregate to provide

More information

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu INSTALLATION INSTRUCTIONS Note: The following installation instructions are based off of ASTM E 1643 (Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or Granular

More information

EDGE RESTRAINT SYSTEM

EDGE RESTRAINT SYSTEM EDGE RESTRAINT SYSTEM Whether its decorative block paving or precast flags, alternate edge restraint systems are taking the world of paving by storm and IrandiPRO is South Africa s first such system. Proudly

More information

FREESTONE ECOTM. Retaining Wall SystemTM. No one knows Blocks and Pavers better

FREESTONE ECOTM. Retaining Wall SystemTM. No one knows Blocks and Pavers better FREESTONE ECOTM Retaining Wall SystemTM The Freestone ECO Retaining Wall System TM is a more sustainable DIY, vertical retaining wall which is manufactured with up to 40% recycled glass aggregate to provide

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

Manual Road Building Option Routes:

Manual Road Building Option Routes: Recommended Qualification Structure for Road Building and Maintenance (Construction) Level 2 This structure has been recommended by employers and stakeholders from the above occupational area for organisations

More information

Manual Road Building Option Routes:

Manual Road Building Option Routes: Recommended Qualification Structure for Road Building and Maintenance (Construction) Level 2 This structure has been recommended by employers and stakeholders from the above occupational area for organisations

More information

Mini Beany. Combined Kerb and Drainage System. Water Linear Management Drainage Design Guide Mini Beany Linear Drainage Channel

Mini Beany. Combined Kerb and Drainage System. Water Linear Management Drainage Design Guide Mini Beany Linear Drainage Channel Mini Beany, Conservation, Bedford Conservation Silver Grey Standard Grey Mini Beany Combined Kerb and Drainage System Mini Beany is a low to medium capacity combined kerb and drainage system which evolved

More information

Surface Infrastructure Restoration for Utility Cuts DIVISION 14 Shallow Buried Utilities Section _Mar29_2016.pdf Page 1 of 20 INDEX

Surface Infrastructure Restoration for Utility Cuts DIVISION 14 Shallow Buried Utilities Section _Mar29_2016.pdf Page 1 of 20 INDEX 14001_Mar29_2016.pdf Page 1 of 20 INDEX 14001-0 REQUEST TO CUT CITY SURFACE INFRASTRUCTURE 2 14001-1 COST SCHEDULE FOR WORK PERFORMED BY CITY FORCES 2 14001-2 SPECIFICATIONS FOR WORK PERFORMED BY EXTERNAL

More information