American Society of Military Engineers

Size: px
Start display at page:

Download "American Society of Military Engineers"

Transcription

1 Presentation to American Society of Military Engineers Runway 9-27 Rehabilitation Project POHNPEI INTERNATIONAL AIRPORT, FSM Presented by Wadgy A. Guirguis, P.E. President August 14, 2012 PROJECT SCOPE OF WORK New Runway Turn-around New Runway & Taxiway Edge Lights New Runway Shoulders New Security Perimeter Fence & Road New Runway Turn-around Asphalt Overlay New Electrical Vault New ARFF Location Proposed JICA Funded Expansion 1

2 Distressed Runway Pavement Areas Existing Runway Dilemma: Two specific areas within the Runway are known to have continually settled for decades. Airlines have complained about the EXCESSIVE RUNWAY DIP prompting safety concerns. Topographic survey indicates a 6 inch difference between low-point and finish grade elevation. GMP is tasked to provide a PERMANENT SOLUTION to the settlement problem. Distressed Runway Pavement Areas Distressed Runway Pavement Areas 2

3 Geotechnical Investigation Subsurface conditions at the distressed areas were identified through geotechnical investigation by Geolabs Inc. Subsurface profiles show the pavement distressed areas is underlain by fill materials consisting of the following feet: Loose to medium dense gravel and sand with varying amounts of silt feet: Very soft alluvial deposits of silty clay feet: Lagoonal deposits of loose silty and clayey sand. Medium hard to hard basalt rock formation. 143 feet and below: Subsurface Soil Profile RUNWAY SURFACE 0 ELEVATION FEET (MSL) 20 FILL CORALLINE DETRITUS 40 FILL RECENT ALLUVIUM RECENT ALLUVIUM LAGOONAL DEPOSIT 60 CORALLINE DETRITUS DISTRESSED RUNWAY PAVEMENT AREAS LAGOONAL DEPOSIT ALLUVIUM BASALT ROCK FORMATION CROSS--SECTION CROSS 3

4 Distressed Runway Pavement Areas Probable Causes of Pavement Settlement: Due to consolidation settlement of the soft Alluvium soils between depths of feet below the existing runway surface. Estimated ultimate settlement in the range of 6-7 feet in approximately 25 to 30 years. Distressed Runway Pavement Areas Remedial Measures Considered: RECURRING PAVEMENT OVERLAY DEEP COMPACTION GROUTING CONCRETE PILES WITH CONCRETE PILE CAP 4

5 Distressed Runway Pavement Areas PAVEMENT OVERLAY Installation of new asphalt pavement course over the existing asphalt pavement. Advantages: Low risk with known construction variables. Short construction time duration. Lowest initial cost of alternatives considered. Disadvantages: Temporary resolution of settlement problem. Overlay roughly every 3 years. Financial burden of funding maintenance program. Distressed Runway Pavement Areas DEEP COMPACTION GROUTING Injection of a low-slump grout or cement into the very soft alluvial soils. Mixture densifies the highly compressible Alluvium soil. Advantages: Soil stabilization with minimal disruption to operations. Easier setup and quicker installation time for shorter overall construction duration than pile system. Lower initial cost than concrete pile alternative. Successfully used for soil densification of feet depths. 5

6 Distressed Runway Pavement Areas DEEP COMPACTION GROUTING(continued) Disadvantages: Method has not been proven for depths beyond 50 feet. Higher initial cost than the pavement overlay alternative. No successful track record. This option eliminated from further analysis. Distressed Runway Pavement Areas CONCRETE PILES WITH PILE CAP Installation of 16 inch concrete piles to 140 feet depth with continuous concrete pile cap slab over piles. Advantages: PERMANENT RESOLUTION of settlement problem. Disadvantages: Highest initial cost of alternatives considered. The longest construction duration of alternatives considered. May require extended closure of Runway. 6

7 Life Cycle Cost Analysis BASE CASE: Recurring asphalt overlay every 3 years as part of a maintenance program. ALTERNATIVE CASE: Installation of concrete piles and pile cap for a PERMANENT SOLUTION. Life Cycle Cost Analysis OVERLAY Base Case Estimated Costs: Initial Capital Cost: $ 00 Repair & Maintenance Cost: Construction Cost $ 420,000 Administration (5%) $ 21,000 Settlement Monitoring (5%) $ 21,000 Design (10%) $ 42,000 CM (10%) $ 42,000 Total Cost (in 2006 dollars) $ 546,000 7

8 Life Cycle Cost Analysis PILING Alternative Case Estimated Costs: Initial Capital Cost: $ 7,800,000 Repair & Maintenance Cost: $ 00 Total Cost (in 2006 dollars) $ 7,800,000 Life Cycle Cost Analysis Repair Alternatives Live Expectancy: Use life expectancy of subgrade to reach 100% consolidation. Estimate 50 years. Inflation Rate: Estimate 4.0%, based on report from January 2006 Pacific Magazine. 8

9 Life Cycle Cost Analysis SUMMARY OF PRESENT WORTH VALUES Discount Rate 3% 4% 5% OVERLAY Base Case NPV $11,755,613 $9,100,000 $7,197,932 PILING Alternative Case NPV $7,800,000 $7,800,000 $7,800,000 Life Cycle Cost Analysis FINDINGS Piling alternative is a cost effective remedial method. Relieves financial burden of maintenance funding. Eliminates future disruption to airport operations. Reinforces Public confidence in Runway safety. 9

10 Recommended Remedial Measure CONCRETE PILE CAP RUNWAY SURFACE 0 ELEVATION FEET (MSL) 20 FILL CORALLINE DETRITUS 40 RECENT ALLUVIUM FILL 140 feet long piles LAGOONAL DEPOSIT RECENT ALLUVIUM 60 CORALLINE DETRITUS DISTRESSED RUNWAY LAGOONAL DEPOSIT PAVEMENT AREAS ALLUVIUM BASALT ROCK FORMATION CROSS--SECTION CROSS DESIGN CONSTRAINTS OPERATIONAL CONSIDERATIONS Keeping Runway open for all flights. Minimizing interruptions to airport operations. CONSTRUCTION CONSIDERATIONS Installation of piles and pile cap without continuous, extended closure of the Runway. 10

11 RUNWAY DESIGN CRITERIA Current Runway Data: Length: 6,000 feet Width: 150 feet Surface: Asphalt FAA Airplane Design Group (ADG): , : III FAA Airport Approach Category (AAC): Pohnpei Airport: C FAA Minimum Runway Design Width: Pohnpei Airport: 100 feet width Runway DESIGN PLAN DESIGN RESOLUTION Provide for operational use of 100 feet wide Runway. Phase construction activities to allow use of Runway with concurrent installation of piles and pile cap. 11

12 DESIGN PLAN DESIGN ISSUES TO RESOLVE Construction of additional Runway pavement. Temporary work to the Runway airfield lights and navigational aids. Piles and pile cap installation. FAA approval of the Design Plan. Airlines approval of the Design Plan. PHASE 1 CONSTRUCTION STEP 1 Construction of Haul Road (location of new access road) Construction of Staging Area (site of new ARFF) 12

13 PHASE 1 CONSTRUCTION STEP 2 Construct new 25 feet pavement shoulders PHASE 1 CONSTRUCTION STEP 2 (continued) Remove existing edge lights and replacement with battery powered, portable lights Install battery powered, portable threshold lights Existing REIL to remain Existing PAPI system to remain Install new edge light base and conduit bank for final installation Install new threshold light base and conduit bank for final installation 13

14 PHASE 1 CONSTRUCTION STEP 3 Re-stripe Runway for southern 100 feet use prior to next flight operation Relocate battery powered, portable edge lights to new Runway configuration Relocate battery powered, portable threshold lights and REIL to new Runway configuration PHASE 1 CONSTRUCTION STEP 4 Close northern half of Runway 14

15 PHASE 1 CONSTRUCTION STEP 5 Drive new concrete piles on 10 feet spacing and construct pile cap on northern half of Runway PHASE 2 CONSTRUCTION STEP 1 Re-stripe Runway for 100 feet northern half use prior to next flight operation Relocate battery powered, portable edge lights to Runway configuration Relocate battery powered, portable threshold lights to new Runway configuration 15

16 PHASE 2 CONSTRUCTION STEP 2 Close southern half of Runway. PHASE 2 CONSTRUCTION STEP 3 Phase I completes construction on the northern half of the Runway. Drive new concrete piles on 10 feet spacing and construct pile cap on southern half of Runway. 16

17 PHASE 3 CONSTRUCTION Re-stripe Runway for full 150 feet wide use prior to next flight operation. Install 2 inch asphalt overlay over entire 150 feet width of Runway, including shoulders. Resurface in foot width paving lanes during temporary closure of runway. ADDITIONAL WORK TO BE PHASED IN New Runway Turn-around New Taxiway Edge Lights New Security Perimeter Fence & Road New Runway Turn-around Taxiway and Apron Asphalt Overlay New Electrical Vault New ARFF Location Proposed JICA Funded Expansion 17

18 POST DESIGN CHALLENGES Two Bid opening events with no Bidder. Third Bid opening event with only one Bidder. Bid price was $86 million. Initial estimate was $56 million. AIP Grants were to be re-allocated. POST DESIGN CHALLENGES (continued) Re-Phase Construction activities according to AIP Funding. Re-Design the ARFF to eliminate pile foundation. Negotiating with the sole source proved to be difficult. Construction schedule was delayed. 18

19 PRE-CONSTRUCTION PHASE 1 19

20 PHASE 2 PHASE 3 20

21 PHASE 4 POHNPEI RUNWAY

22 POHNPEI INTERNATIONAL AIRPORT ARFF Mahalo! 22

ADVANCED PAVEMENT TECHNOLOGY USED FOR REHABILITATION OF RUNWAYS AT EDMONTON INTERNATIONAL AIRPORT

ADVANCED PAVEMENT TECHNOLOGY USED FOR REHABILITATION OF RUNWAYS AT EDMONTON INTERNATIONAL AIRPORT ADVANCED PAVEMENT TECHNOLOGY USED FOR REHABILITATION OF RUNWAYS AT EDMONTON INTERNATIONAL AIRPORT Ludomir Uzarowski, Ph.D., P.Eng. and Rabiah Rizvi, B.A.Sc., Golder Associates Ltd. Darrin Schuster, P.Eng.

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

PREPARED BY: ALBERT NEUMANN E.I. PROJECT MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION, DISTRICT 5

PREPARED BY: ALBERT NEUMANN E.I. PROJECT MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION, DISTRICT 5 SR 19 OVER LITTLE LAKE HARRIS BRIDGE 110026 SUBSTRUCTURE REPAIR LAKE COUNTY, FL PREPARED BY: ALBERT NEUMANN E.I. PROJECT MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION, DISTRICT 5 DAVID THOMPSON P.E. ENGINEER

More information

Subsurface Investigation Report. Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois

Subsurface Investigation Report. Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois AGI Project No. -11 Subsurface Investigation Report For the Proposed New 1-Story Building 6447 Grand Avenue Gurnee, Illinois Prepared for Mr. Steve Panko Key Development Partners, LLC North State Street,

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

Alligator Cracking. Light. Medium. High

Alligator Cracking. Light. Medium. High Alligator Cracking Description: A series of interconnecting cracks caused by fatigue failure on the asphalt concrete surface under repeated traffic loading. Causes: Loads in excess of the current pavement

More information

is a possibility of the existence of permafrost as a result

is a possibility of the existence of permafrost as a result 111.2 CERTAIN ASPECTS OF ALASKA DISTRICT ENGINEERS EXPERIENCE IN AREAS OF MARGINAL PERMAFROST E. L. Long In nearly twenty years of engineering and construction experience in Alaska, the Alaska District

More information

Temporary Structures. Excavations and Excavation Supports

Temporary Structures. Excavations and Excavation Supports UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Excavations and Excavation Supports CM 420

More information

PARKING LOTS 4, 7, AND 8 RECONSTRUCTION REPORT

PARKING LOTS 4, 7, AND 8 RECONSTRUCTION REPORT PARKING LOTS 4, 7, AND 8 RECONSTRUCTION REPORT Converse Project No. 15-81-177-01 Prepared For: David Evans and Associates, Inc. 17782 17th Street, Suite 200 Tustin, California 92780 Prepared By: 10391

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois AGI Project No. 13-276 Subsurface Investigation Report For the Proposed New Retail Center 9601 South Pulaski Road Evergreen Park, Illinois Prepared for Mr. Feras Sweis FHS Design + Build LLC 2010 West

More information

Statement of Qualifications

Statement of Qualifications Statement of Qualifications GeoTest, Inc. 2135 S. 116th Street West Allis, WI USA Geotechnical Engineering Construction Materials Testing Construction Observation and Documentation Geological and Industrial

More information

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS. SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract

More information

Best Practices in the Design and Construction of Airfield Composite Pavements. George Nowak, P.Eng.

Best Practices in the Design and Construction of Airfield Composite Pavements. George Nowak, P.Eng. Best Practices in the Design and Construction of Airfield Composite Pavements George Nowak, P.Eng. 2010 CAPTG Workshop Calgary, Sunday September 12, 2010 Outline Types and Design HMA on PCC only Why Composite

More information

Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer

Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer 96 th Annual NC AWWA-WEA Conference Chuck Shue, PE McKim & Creed, Inc. Senior Project Manager Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer OUTLINE Project overview

More information

Pavement Design. TTP Orientation Seminar 2011

Pavement Design. TTP Orientation Seminar 2011 Pavement Design TTP Orientation Seminar 2011 What are Pavements? Engineered structures in contact with the earth's surface built to facilitate movement of people and goods Pedestrians Personal vehicles

More information

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two. Design Manual Chapter 6 - Geotechnical 6C - Pavement Systems 6C-1 Pavement Systems A. General Information This section addresses the importance of pavement foundations and the potential for pavement problems

More information

Subsurface Investigation Report

Subsurface Investigation Report AGI Project No. 17-154 Subsurface Investigation Report For the Proposed New One-Story Building Addition 7030 West 111 th Street Worth, Illinois Prepared for T63 Development LLC 11052 Mayflow er Lane Orland

More information

Pavement Update Track: Engineering

Pavement Update Track: Engineering Pavement Update Track: Engineering 2017 ACC Airports Technical Workshop June 21-22, 2017 Arlington, VA Gregory D. Cline, P.E. FAA Airport Engineering AAS-100 gregory.cline@faa.gov (202) 267-8814 Pavement

More information

Municipality of Waterville Public Sidewalk Repair Policy

Municipality of Waterville Public Sidewalk Repair Policy Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by

More information

Taxiway embankment over soft ground using staged construction

Taxiway embankment over soft ground using staged construction Taxiway embankment over soft ground using staged construction R. Wells, X. Barrett & T. Wells Trigon Kleinfelder, Inc., Greensboro, North Carolina, United States ABSTRACT: The Piedmont Triad International

More information

Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS

Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # 2016-04 PROJECT SPECIFICATIONS TABLE OF CONTENTS SECTION 100 GENERAL... 1 SECTION 200 MATERIALS... 1 CONSTRUCTION METHODS... 1 SECTION

More information

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River DEEP FOUNDATIONS 207 Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River W. Robert Thompson, III, 1 M.ASCE, P.E., Jeffrey R. Hill, 2 M.ASCE, P.E., and J. Erik Loehr,

More information

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25 General Info Number: PROJECT NO. 43-17-03 Description: BRIDGE DECK REPAIR AND REHABILITATION, ARLINGTON ROAD OVER OHIO TURNPIKE M.P. 122.3, JOPPA ROAD OVER OHIO TURNPIKE M.P. 128.5, DEAN ROAD OVER OHIO

More information

Attachment D-1: Civil/Structural Scope of Work

Attachment D-1: Civil/Structural Scope of Work Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

Performance of Mechanically Stabilized Earth walls over compressible soils

Performance of Mechanically Stabilized Earth walls over compressible soils Performance of Mechanically Stabilized Earth walls over compressible soils R.A. Bloomfield, A.F. Soliman and A. Abraham The Reinforced Earth Company, Vienna, Virginia, USA ABSTRACT: Two projects have recently

More information

Introduction to Pavement Overlays

Introduction to Pavement Overlays Introduction to Pavement Overlays Course No: C02-046 Credit: 2 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

Experience of a Large Scale Unintentionally Long Surcharge on Organic Soils

Experience of a Large Scale Unintentionally Long Surcharge on Organic Soils Experience of a Large Scale Unintentionally Long Surcharge on Organic Soils Ying Liu, Ph.D., P.E., Senior Engineer, Group Delta Consultants, Inc., 37 Amapola Ave., Suite 212, Torrance, CA. Email: yingl@groupdelta.com

More information

Steel screw settlement reduction piles for a raft foundation on soft soil

Steel screw settlement reduction piles for a raft foundation on soft soil Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Alexei Murashev Opus International Consultants Limited, Wellington, New Zealand. Keywords: piled raft, settlement

More information

Life Cycle Cost Analysis

Life Cycle Cost Analysis Life Cycle Cost Analysis Washington Street Widening 144 th Avenue to 148 th Avenue City of Thornton Deborah Turner, PE Overview Project Location What is Life Cycle Cost Analysis? Project Background 7 Steps

More information

How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.

How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc. 1 How to Select the Appropriate Pavement Rehabilitation Option David Rettner, PE American Engineering Testing, Inc. 2 Pavement Rehabilitation Selection Understanding the Problem 3 Pavement Assessment Pavement

More information

CE 6012 Ground Improvement Techniques Question Bank

CE 6012 Ground Improvement Techniques Question Bank CE 6012 Ground Improvement Techniques Question Bank Unit I INTRODUCTION Role of ground improvement in foundation engineering - methods of ground improvement Geotechnical problems in alluvial, laterite

More information

DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS

DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS DUCTILE IRON PILES DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS Designed to resist both compression and tension loads in either end-bearing or friction,

More information

Concrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay

Concrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay Overlays February 22, 2012 ACPA Pennsylvania Chapter Overlays John M. Becker, P.E. ACPA Penn Chapter February 22, 2012 One of 25 state paving associations affiliated with ACPA National Comprised of approximately

More information

Pavement Design and Construction of Taxilane S to Accommodate New Large Aircraft at LAX

Pavement Design and Construction of Taxilane S to Accommodate New Large Aircraft at LAX Pavement Design and Construction of Taxilane S to Accommodate New Large Aircraft at LAX Katie Chou, Ph.D., P.E. Hatch Mott MacDonald, Los Angeles Office Presented to: 2011 SWIFT Conference, Montreal Date:

More information

Cement Stabilized Aggregate Base

Cement Stabilized Aggregate Base Supplemental Technical Specification for October 28, 2015 Cement Stabilized Aggregate Base SCDOT Designation: SC-M-308 (10/15) 1. SCOPE 1.1. Cement Stabilized Aggregate Base (CSAB) consists of aggregate,

More information

Pavement Condition Report

Pavement Condition Report Pavement Condition Report Marshall Southwest Minnesota Regional Airport (MML) Prepared for: Office of Aeronautics Minnesota Department of Transportation 222 East Plato Boulevard Saint Paul, MN 55107 (800)

More information

or (800)

or (800) WWW.CELL-CRETE.COM or (800) 669-0433 CALIFORNIA (Lic #243404), OREGON, WASHINGTON, NEVADA, UTAH, IDAHO, MONTANA, ARIZONA, HAWAII, ALASKA, WESTERN CANADA Re: Cellular Concrete as Engineered Fill I m pleased

More information

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1 PUBLIC WORKS DEPARTMENT David A. Jones, P.E., Director April 7, 2017 Webster Street Sub-Surface Stormwater Storage System Bid No. 2017-022 Bid Date: 4/13/17 ADDENDUM NO 1 Please make the following changes

More information

ADDENDUM #2 JUNE 30, It is required that all bidders acknowledge receipt of Addenda on Page BF-2 of the Bid Form.

ADDENDUM #2 JUNE 30, It is required that all bidders acknowledge receipt of Addenda on Page BF-2 of the Bid Form. ADDENDUM #2 JUNE 30, 2017 APRON REHABILITATION PHASE 3 HENRY E. ROHLSEN AIRPORT ST. CROIX, U.S. VIRGIN ISLANDS FAA AIP No.: 3-78-0002-037-2017 This addendum modifies or interprets the proposal documents

More information

PCCP on Cement Treated FDR Connersville Municipal Airport Apron Reconstruction. May 14, 2015

PCCP on Cement Treated FDR Connersville Municipal Airport Apron Reconstruction. May 14, 2015 PCCP on Cement Treated FDR Connersville Municipal Airport Apron Reconstruction May 14, 2015 PCCP on Full Depth Reclamation Today s Program Project Design Considerations & Details: BFS FDR Basics: Project

More information

MNDOT PAVEMENT DESIGN MANUAL

MNDOT PAVEMENT DESIGN MANUAL MNDOT PAVEMENT DESIGN MANUAL Chapter 9 truction and Rehabilitation Alternates MnDOT Pavement Engineer Date Contents Introduction... 1 900 Existing Pavement-Types... 2 910 Rehabilitation with HMA Overlay

More information

FOUR CORNERS POWER PLANT POST-CLOSURE PLAN (d) LINED ASH IMPOUNDMENT (LAI) FC_PostClosPlan_008_

FOUR CORNERS POWER PLANT POST-CLOSURE PLAN (d) LINED ASH IMPOUNDMENT (LAI) FC_PostClosPlan_008_ FOUR CORNERS POWER PLANT POST-CLOSURE PLAN 257.104(d) LINED ASH IMPOUNDMENT (LAI) FC_PostClosPlan_008_20161017 Post-Closure Plan Contents 257.104(d)(1) The owner or operator of a CCR unit must prepare

More information

FOUR CORNERS POWER PLANT POST-CLOSURE PLAN (d) LINED DECANT WATER POND (LDWP) FC_PostClosPlan_009_

FOUR CORNERS POWER PLANT POST-CLOSURE PLAN (d) LINED DECANT WATER POND (LDWP) FC_PostClosPlan_009_ FOUR CORNERS POWER PLANT POST-CLOSURE PLAN 257.104(d) LINED DECANT WATER POND (LDWP) FC_PostClosPlan_009_20161017 Post-Closure Plan Contents 257.104(d)(1) The owner or operator of a CCR unit must prepare

More information

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003 ODOT Geotechnical Information Exchange Seminar Ground Improvement Martin G. Taube, P.E., P.G. February 4, 2003 Nicholson Construction Company 12 McClane Street Cuddy, PA 15031 ph. (412) 221-4500 fax (412)

More information

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter. STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer

More information

Pavement Preservation with Thin Lift Concrete Overlays. Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center

Pavement Preservation with Thin Lift Concrete Overlays. Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center Pavement Preservation with Thin Lift Concrete Overlays Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center Concrete Overlay Guide second edition Contents 1. Overview of

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3

More information

Airport Pavement Rehabilitation 2015 Minnesota Airports Conference

Airport Pavement Rehabilitation 2015 Minnesota Airports Conference Airport Pavement Rehabilitation 2015 Minnesota Airports Conference St. Cloud, Minnesota April 16, 2015 David L. Rettner, P. E. American Engineering Testing, Inc. Pavement Life Cycle Routine Maintenance

More information

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT): SECTION 31 32 13.16 CEMENT STABILIZATION PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the specifications for cement stabilization of sandy or silty soil and consists of pulverizing, addition

More information

Houston County Airport (CHU)

Houston County Airport (CHU) Final Report Pavement Condition Report Houston County Airport (CHU) Prepared for: Office of Aeronautics Minnesota Department of Transportation 222 East Plato Boulevard Saint Paul, MN 55107 (800) 657-3922

More information

Minnesota Airport System Pavement Evaluation 2010 Update

Minnesota Airport System Pavement Evaluation 2010 Update Minnesota Airport System Pavement Evaluation 2010 Update Park Rapids Municipal Airport (PKD) Park Rapids, Minnesota Prepared for: Office of Aeronautics Minnesota Department of Transportation 222 East Plato

More information

AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS

AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS AMERICA RIDES ON US KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS KEYS TO A SUCCESSFUL ALTERNATE BIDDING PROCESS INTRODUCTION With alternate bidding, road and highway agencies offer the opportunity to

More information

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description September 22, 2016 American Infrastructure Development, Inc. 3810 Northdale Boulevard, Suite 170 Tampa, Florida 33624 Attn: Mr. Mohsen Mohammadi, Ph.D., P.E. Senior Consultant Mob: (813) 244-6609 E-mail:

More information

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE BE IT ORDAINED by the Town Council of the Town of Plainville: SECTION 1. SUBDIVISIONS. All subdivisions hereinafter developed within

More information

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

ENGINEERING DESIGN & IMPROVEMENT STANDARDS ENGINEERING DESIGN & IMPROVEMENT STANDARDS 2016 Prepared by: Engineering Division For latest edition of these Improvement Standards, refer to City of Visalia website at: www.visalia.city/engineeringdocuments

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

File No Supplemental November Geotechnical and Environmental Consulting Engineers

File No Supplemental November Geotechnical and Environmental Consulting Engineers Supplemental Information & Geotechnical Recommendations Proposed New Solar Valley Location B (East of Building No. 7) Cañada Community College 4200 Farm Hill Boulevard Submitted to: Mr. Peter Hempel Construction

More information

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation Design and Construction of Concrete Overlays By: James K. Cable, P.E. Cable Concrete Consultation PCC OVERLAY AGENDA Current design & construction features What is needed in a PCC overlay set of plans?

More information

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014 1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment,

More information

Washtenaw Community College Design & Construction Facilities Management 4800 East Huron River Drive Ann Arbor, MI

Washtenaw Community College Design & Construction Facilities Management 4800 East Huron River Drive Ann Arbor, MI Washtenaw Community College Design & Construction Facilities Management 4800 East Huron River Drive Ann Arbor, MI 4810-4800 GEOTECHNICAL INVESTIGATION FOR Proposed Pavement Rehabilitation Parking Lots

More information

GEOTECHNICAL INVESTIGATION STUDENT HOUSING BUILDINGS UCCS SUMMIT VILLAGE COLORADO SPRINGS, COLORADO

GEOTECHNICAL INVESTIGATION STUDENT HOUSING BUILDINGS UCCS SUMMIT VILLAGE COLORADO SPRINGS, COLORADO GEOTECHNICAL INVESTIGATION STUDENT HOUSING BUILDINGS UCCS SUMMIT VILLAGE COLORADO SPRINGS, COLORADO Prepared for: UNIVERSITY OF COLORADO AT COLORADO SPRINGS Facilities Services 1420 Austin Bluffs Parkway

More information

REQUEST FOR PROPOSAL Asphalt & Concrete Repair

REQUEST FOR PROPOSAL Asphalt & Concrete Repair REQUEST FOR PROPOSAL 2017 Asphalt & Concrete Repair English Landing Elementary School Union Chapel Elementary School Lakeview Middle School Park Hill High School Prairie Point Elementary School Congress

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER CHAPTER 3 Site Preparation In preparation for constructing buildings on a property, the builder must consider a number of factors related to code requirements. The buildings must be located according to

More information

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates LA Transportation Conference: 10 Jan 2011 Drilled Shaft Foundations For Two Mississippi River Bridges in Louisiana Dan Brown and Associates Projects John James Audubon Bridge, St. Francisville New Construction

More information

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2 ABSTRACT SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR Robert Small 1, Rob Jameson 2 Seismic Upgrade of the University Mound Reservoir North Basin included 542 micropiles with 1335 KN (300 kip) design capacity

More information

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. H A Y W A R D B A K E R I N C. RIGID INCLUSIONS Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. Above: HBI installed Rigid Inclusions on a congested downtown

More information

THE GREAT GUAM AND HANSHIN EARTHQUAKES PROFILES IN PORT DISASTERS

THE GREAT GUAM AND HANSHIN EARTHQUAKES PROFILES IN PORT DISASTERS ABSTRACT THE GREAT GUAM AND HANSHIN EARTHQUAKES PROFILES IN PORT DISASTERS FEROZE R. VAZIFDAR 1, M. ASCE PETER KALDVEER 2, M. ASCE Two recent earthquake events, several thousand miles apart, demonstrate

More information

SELECTIVE FLEXIBLE PAVEMENT REHABILITATION BASED ON FORENSIC INVESTIGATION AND DEFLECTION ANALYSIS: SEVENTEEN YEARS CASE STUDY IN VIRGINIA

SELECTIVE FLEXIBLE PAVEMENT REHABILITATION BASED ON FORENSIC INVESTIGATION AND DEFLECTION ANALYSIS: SEVENTEEN YEARS CASE STUDY IN VIRGINIA 0 0 0 0 SELECTIVE FLEXIBLE PAVEMENT REHABILITATION BASED ON FORENSIC INVESTIGATION AND DEFLECTION ANALYSIS: SEVENTEEN YEARS CASE STUDY IN VIRGINIA Mohamed Elfino, Ph.D., P.E. * Assistant State Materials

More information

Bid Form. To the Texas Department of Transportation hereinafter called the Agent.

Bid Form. To the Texas Department of Transportation hereinafter called the Agent. Bid Form TxDOT CSJ No. 1809HILLS Project: 2017 Airport Improvements Project Description: Schedule 1 Base Bid: Rehabilitate and mark RW 16-34, partial parallel TW, stub TWs including run-up areas, terminal

More information

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9 Table of Contents 1.0 Introduction...4 2.0 Description of Landfill...4 3.0 Review of Available Information...5 4.0 Inspection...5 4.1 Changes in Geometry since Last Inspection...5 4.2 Volume...5 4.3 Definitions

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

PARKING LOT AND ROADWAY MAINTENANCE

PARKING LOT AND ROADWAY MAINTENANCE Village of Vernon Hills Community Development Engineering Division Phone 847-367-3704 Fax 847-367-2541 PERMIT APPLICATION PROCESS PARKING LOT AND ROADWAY MAINTENANCE Removal and replacement, concrete and

More information

APPENDIX H. Capital Improvement Program Detail Project Costs NORTH PERRY AIRPORT MASTER PLAN UPDATE APPENDICES

APPENDIX H. Capital Improvement Program Detail Project Costs NORTH PERRY AIRPORT MASTER PLAN UPDATE APPENDICES MASTER PLAN UPDATE APPENDICES APPENDIX H Capital Improvement Program Detail Project Costs Montgomery Consulting Group August 11, 2009 Appendix H CAPITAL IMPROVEMENT PROGRAM Short Term (0-5 years) SUB-

More information

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method 3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed

More information

Low Mobility Grouting (LMG) and Compaction Grouting, "Application Review"

Low Mobility Grouting (LMG) and Compaction Grouting, Application Review Low Mobility Grouting (LMG) and Compaction Grouting, "Application Review" Sam Bandimere Abstract While the concept of using Low Mobility Grout (LMG) mix designs originated with the "Compaction Grouting"

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 11/21/2014 Project 140560 Addendum No. 2 PID No. 82972 HAM IR 275

More information

SECTION DUCTILE IRON PILES

SECTION DUCTILE IRON PILES SECTION 31 66 13 DUCTILE IRON PILES PART 1 - GENERAL 1.1 GENERAL REQUIREMENTS A. Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. B.

More information

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon Rock Fill Layer Management and Maintenance Plan 13 Highway 99 Prepared for: Half Moon LLC P.O. Box 25112 97402 PBS Project No. 51833.000 Rock Fill Layer Management and Maintenance Plan TABLE OF CONTENTS

More information

MANUAL OF PAVEMENT STRUCTURAL DESIGN ASG-19 (AK-68-12) MANUEL SUR LA CONCEPTION DES CHAUSSÉES

MANUAL OF PAVEMENT STRUCTURAL DESIGN ASG-19 (AK-68-12) MANUEL SUR LA CONCEPTION DES CHAUSSÉES MANUAL OF PAVEMENT STRUCTURAL DESIGN ASG-19 (AK-68-12) MANUEL SUR LA CONCEPTION DES CHAUSSÉES Public Works Canada Air Transportation Travaux Publics Canada Services d'architecture et de génie Tranports

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES

CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES SUMMARY AND INTENT OF PROJECT The City of Des Plaines Curb and Sidewalk Program is intended to repair hazardous sidewalk and

More information

C. Installers licensed by the Geopier Foundation Company, Inc. (www.geopier.com) will be accepted as approved installer.

C. Installers licensed by the Geopier Foundation Company, Inc. (www.geopier.com) will be accepted as approved installer. SPECIFICATION FOR RAMMED AGGREGATE PIER SYSTEMS AND RIGID INCLUSION FOUNDATION PART 1: GENERAL REQUIREMENTS 1.01 Description Work shall consist of designing, furnishing and installing Rammed Aggregate

More information

The URETEK Method for Roadways and Transportation Assets

The URETEK Method for Roadways and Transportation Assets The URETEK Method for Roadways and Transportation Assets A URETEK USA White Paper www.worldofuretek.com Introduction Since the inception of the National Highway Act in the 1950's, our interstate highway

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation. SECTION 312333 TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 SUMMARY A. Excavate trenches for new electric and telephone conduits, gas lines, and their appurtenances from at least 5 feet outside the building

More information

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH Presentation Outline General Introduction Part II Site Preparation & Earthwork Part III Base Courses

More information

Rehabilitation of Runway 9/27 at George Bush Intercontinental Airport, Houston, Texas

Rehabilitation of Runway 9/27 at George Bush Intercontinental Airport, Houston, Texas 99 Justin P. Jones Vice President / Business Sector Manager National Aviation Group Atkins North America Rehabilitation of Runway 9/27 at George Bush Intercontinental Airport, Houston, Texas William G.

More information

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS STANDARD SPECIFICATIONS SECTION 02950 PAVEMENT REQUIREMENTS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for removing, replacing and providing new paving for roads, driveways, parking

More information

BID # REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER

BID # REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER BID # 14-47 REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER Board of Trustees Middlesex County College 2600 Woodbridge Avenue P.O. Box 3050 Edison, New Jersey

More information

GEOTECHNICAL EXPLORATION

GEOTECHNICAL EXPLORATION GEOTECHNICAL EXPLORATION SAN MATEO COUNTY REPLACEMENT CORRECTIONAL FACILITY REDWOOD CITY, CALIFORNIA Submitted to: Mr. Sam Lin San Mateo County Sheriff s Office Jail Planning Unit 400 County Center, 3rd

More information

Recycling and Reclamation of Airfield Pavements

Recycling and Reclamation of Airfield Pavements Recycling and Reclamation of Airfield Pavements 35 th Airports Conference FAA Eastern Region, Hershey, PA April 4, 2012 Presented by: Mark D. McGuire, P.E. Items for Discussion Brief Introduction (Mark

More information

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation SECTION 33 40 00 STORM DRAINAGE UTILITIES 1. PART 1 GENERAL 1.1 RELATED WORK A. Section 31 23 00: Excavation and Fill B. Section 32 00 01: Site Restoration and Rehabilitation C. Special Conditions for

More information

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments Asphalt Pavement Preservation: Evaluation, Maintenance & Rehabilitation Maintenance & Rehabilitation Treatments Identification of Alternative Treatments Before selecting a treatment for a pavement, we

More information

Cost Considerations of Asphalt Rubber Hot Mix

Cost Considerations of Asphalt Rubber Hot Mix Cost Considerations of Asphalt Rubber Hot Mix Gene R. Morris, P.E. International Surfacing, Inc. Kent R. Hansen, P.E. International Surfacing Inc. MATERIAL DESCRIPTION AND PROPERTIES Asphalt-rubber (A-R)

More information

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt

More information