1 MEng year 1 Structural Engineering Project Structures/Structures with Management Bridge Msida Valley CVE 5101 CVE 5101: Structures CVE 5103: Structures with Management Design Workshop Workshop Co ordinator:. Tutors: Prof Dion Buhagiar,,,, Programme This workshop will have a eight week duration, commencing week 5 th October 2017 Submission dates: Concept design: Thursday 19 th October 2017 Structural appraisal of proposals: Thursday 16 th November 2017 Final Submission: Thursday 30th November 2017 Review date: To be announced Deliverables: Credits Assigned: Drawings + Small working model+ Preliminary calculations + report. 5 ECTS Method of assessment: Deliverables + Oral Presentation. 1 P age
2 Objectives The design brief The main objective of this workshop is to prepare a preliminary design for a bridge to spanning Msida Valley road as shown on the site plan. The proposed new bridge must have a clear span and cannot have any supports projecting down to the valley floor. The aim of the workshop will be to produce a number of conceptual bridge designs using various structural materials, preparing preliminary calculations for initial sizing, and producing general arrangement structural drawings, as well as detail drawings for a bridge spanning over the Msida Valley as shown in Figures 1 and 2. The project duration is 8 (eight) weeks and there will be intermediate reviews of your design work as indicated in the table at the end of this document. Figure 1: Proposed location of bridge 2 P age
3 Figure 2: Proposed location of bridge The design parameters Bridge loading: Load Model 1 (LM1) MSA EN Wind loading: 28 m/s Temperature: Temperature movements are to be taken into consideration. Basis for design (a) The foundations, abutments and piers should be preliminary design. The deck and other structural elements supporting the deck should be designed in detail. (b) The design should include deck bearings for articulation, expansion joints, parapet and deck drainage. (c) Foundations are assumed to be deep foundations. (d) Consideration should be given to all stages of erection when overall stability effects should be checked under nominal wind loads of 2kN/m2 applied over the projected surface area in elevation. Aerodynamic effects need not be considered. 3 P age
4 Learning outcomes for this project must demonstrate that you: Learning outcomes (a) Are capable of providing a number of reasoned innovative structural concept designs, based on sound engineering judgement, with a varied choice of structural materials. (b) Have an understanding of the principles of wind loading. (c) Have an understanding of bridge loading (MSA EN , & MSA EN ) (d) Have an appreciation for overall structural stability. (e) Have an understanding for the use of different structural materials, such as concrete, steel, timber, etc. (f) Have an appreciation of the use of approximate methods of calculation and rules of thumb, used in preliminary member sizing. (g) Possess good visual and verbal presentation skills. The project timeline CVE5101 & CVE5103 Design Workshops (Structural Engineering/Structural Engineering with Management) October 2017 Start Date: 5 th October 2017 End Date: 30 th November 2017 Task 1 Conceptual Design and design considerations Prof. D Buhagiar The following tasks involve Week 1 Week 2 Commencing: 5 th October 2017 Informal Review Task 1 Friday 20 th October 2017 You will prepare several concept designs for a bridge over Msida Valley. Your concepts are to be based on existing case studies; you are expected to explore the various types of bridge configurations that are typically used for this type of bridge. Structural solutions should seek to be innovative, elegant and structurally efficient. You are to consider solutions in different types of structural material. You will prepare preliminary sketches for your proposals. You will be required to indicate your choice of bridge design. You are not required to produce a formal submission, but you are to bring sufficient material to highlight your thought process. 4 P age
5 Task 2 Preliminary Structural Design Prof. D Buhagiar Dr Rebecca Dalli Gonzi Week 3 Week 6 Commencing: 19 th October 2017 Having chosen your structural configuration, you will be required to prepare preliminary calculations for initial sizing of the bridge. You will take into consideration load patterns as prescribed in EN 1991, as well as wind loading on your structure. The task involves producing preliminary structural design calculations for the bridge, taking into consideration loading patterns, wind loading etc; Due consideration is to be given to how your bridge will be built on site. Informal Review Task 2 Friday 17 th November 2017 This is not a formal review and no presentation material is to be prepared, but you will be required to show the work you have done, and to explain how you arrived at the size of your bridge components, and what were the main design decisions that influenced you final choice of design. You are also to highlight issues that you feel might affect your final design. Prof. D Buhagiar Dr Rebecca Dalli Gonzi Task 3 Week 7 Week 8 Commencing: 16 th November 2017 Final Structural Design, Calculation, Report and presentation During this phase, you will finalise your structural design, produce structural details and produce a report outlining the design process, the strategic decisions you made in arriving at your final design, and sufficient structural calculations to justify your proposal. Prof. D Buhagiar 5 P age
6 Formal Final Review Date to be announced Given your choice of structural solution, you are to take into consideration the location of the proposed site and to prepare the following: This is a formal presentation in front of a panel of people. You are to prepare 3 in No A1 boards that will include: (a) A Structural general arrangement plan view of the bridge (dimensioned and annotated). (b) A Structural general arrangement longitudinal section through the bridge showing the major components of your bridge, as well as the foundation layout. (c) A Structural general arrangement cross section through the bridge deck. (d) Details of a major connection (in consultation with your tutors). Your final submission shall include but not be limited to: (e) Sufficient preliminary structural calculations for the bridge. (f) A separate report (A4) highlighting: the main design constraints and design assumptions used, preliminary calculations, as well as future recommendations as to how to finalise the bridge design. A construction plan highlighting the erection sequence and site logistics. (g) A DVD of all the information submitted above in digital format. At the end of this phase there will be individual design reviews, you will be allotted 15 minutes to present your final design ( you may use a power point presentation if you feel it necessary). You will be stopped if you exceed the time limit for your presentation. A further 15 minutes for questions will be allotted to your review. 6 P age
STUDENT DESIGN COMPETITION - BRIDGES For further information visit: SteelConstruction.info/Student_awards
STUDENT DESIGN COMPETITION - BRIDGES 2014 For further information visit: SteelConstruction.info/Student_awards Foreword The Tata Steel / BCSA Students Awards - Bridge Design has been organised by The Steel
More information(Old examination format for reference only)
The Institution of Structural Engineers Associate-Membership Examination 11 APRIL 2003 INSTRUCTIONS TO CANDIDATE 1. The examination comprises two sessions separated by a lunch break of 1 2 hour, during
More informationAssociate-Membership Examination
Associate-Membership Examination 1 Associate-Membership Examination Friday 13 April 2012 Structural Engineering Design and Practice 09.30 13.00 and 13.30 17.00 (Discussion between individuals is not permitted
More informationPossible solution to past CM examination question. Question 3 - April Footbridge over a waterfall. by Saprava Bhattacharya
Possible solution to past CM examination question Question 3 - April 2013 Footbridge over a waterfall by Saprava Bhattacharya The information provided should be seen as an interpretation of the brief and
More informationThe HKIE Structural Examination Written Examination
The HKIE Structural Examination Written Examination Section 2: Design Questions (80% of the Written Examination) Date: 28 November 2014 (Friday) Time: 12:00 nn - 06:00 pm Answer ONE question only Question
More informationBridge articulation No. 1.04
Bridge articulation Scope This Guidance Note gives advice on the selection of the articulation arrangements, the choice of bearing types and dispositions of bearings, for bridges where relative movement
More informationThe HKIE Structural Examination Written Examination 2017
The HKIE Structural Examination Written Examination 2017 Section 2: Design Questions (80% of the Written Examination) Date: 5 December 2017 (Tuesday) Time: 12:00 nn 06:00 pm (Duration: 6 hours) Question
More informationEngineering Design Process: Structural Design
Engineering Design Process: Structural Design Introduction Structural engineering is the design of structural elements and their connections that work together to support loads and maintain stability within
More informationChartered Membership Examination Friday, 7 July 2017
Chartered Membership Examination Friday, 7 July 2017 Structural Engineering Design and Practice 09.30 13.00 and 13.30 17.00 (Discussion between individuals is not permitted during lunch period). A period
More informationPossible solution to past CM examination question. Question 3 - January Temporary pedestrian bridge. by Saprava Bhattacharya
Possible solution to past CM examination question Question 3 - January 2015 Temporary pedestrian bridge by Saprava Bhattacharya The information provided should be seen as an interpretation of the brief
More informationGEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY
GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY Introduction Authors Jarrod Hitchcox Associate Technical Director Arcadis Australia Pacific jarrod.hitchcox@arcadis.com
More informationMODEL CLAUSES FOR CIVIL ENGINEERING WORKS
MODEL CLAUSES FOR CIVIL ENGINEERING WORKS SECTION 70 GENERAL REQUIREMENTS FOR PILING NOTES TO SPECIFIER: These notes do not form part of the Specification. Generally 70.1 Sections 70-75 provide a specification
More informationDesign studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System
Design studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System Author: Dariusz Alterman Superviser: Dr. Tomasz Siwowski, Civ. Eng. Chairman of the examination committee:
More informationPattullo Bridge Replacement Project. Cost Report
Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...
More informationPossible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan
Possible solution to past CM exam question Question 2 July 2015 New city centre office block by Rajavel Inbarajan The information provided should be seen as an interpretation of the brief and a possible
More informationHollowcore Slabs. Hollowcore slabs are used mainly for flooring and roofing, but can also be used for wall purposes.
Hollowcore Slabs Hollowcore Slabs One of the most advanced precast products. Millions of square meters of hollowcore slabs are used every year in the building constructions all over the world (villas,
More informationMITRE 3 Building McLean VA
Executive Summary: The MITRE 3 building is an eight story office building. Its current frame is composed of A992 wide flange shapes. The lateral resisting system is a moment frame. This moment frame consists
More informationDESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.
DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change
More informationProject Management based on the Project Management book of knowledge
Project Management based on the Project Management book of knowledge Integration Check parts of your plan are co-ordinated. Make trade off between competing objectives Scope Ensure the project includes
More informationPOSITION DESCRIPTION DIRECTOR TECHNICAL & DEVELOPMENT SERVICES MANAGER ENGINEERING AND OPERATIONS
POSITION DESCRIPTION POSITION: DESIGN OFFICER CLASSIFICATION: BAND 4 DEPARTMENT: SECTION: OCCUPANT: TECHNICAL & DEVELOPMENT SERVICES ENGINEERING & OPERATIONS VACANT DATE: DECEMBER 2006 REVISED: AUGUST
More informationAGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.
Route 15/29 SBL Bridge Superstructure Replacement & Widening Existing Structure Scope Accelerated Procedure Staging (Superstructure) Preparatory Work (Substructure) NOVA District Questions EXISTING STRUCTURE
More informationRe: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy
Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy Presentation to Executive Committee September 21, 2015 1 Overview Project Background Procurement Options Analysis
More informationAl Islam Textile Ltd.
Al Islam Textile Ltd. 9 Kornopara,Savar,Dhaka-1340 (23.824207N, 90.256342E) 27 APRIL 2014 1 2 Observations Item 1 observation Column loads in excess of design loads Verify concrete strengths in columns
More informationCONSTRUCTION MANAGER
The South African Council for the Project and Construction Management Professions CONSTRUCTION MANAGER IDENTIFICATION OF WORK AND SCOPE OF SERVICES FOR CONSTRUCTION MANAGERS REGISTERED IN TERMS OF THE
More informationCountry Bridge Solutions
Country Bridge Solutions David K. Andrews, Senior Project Development Manager, Freight and Regional Program Office Roads and Maritime Services, NSW, Australia Adj Prof Wije Ariyaratne, Principal Engineer
More informationPRECAST CONCRETE GIRDER ERECTION
7.1 Precast Concrete Girder Erection - General Erection of precast concrete girders includes transporting the girders to the site, handling and temporary storage, installing anchor bolts, shear blocks
More informationUNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY, CITY OF MOORHEAD
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 14511 MSAS NO. 115 OVER THE RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY, CITY OF MOORHEAD PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY
More informationDimensionamento Estrutural de uma Ponte Canal. Structural Design of a Canal Bridge. Francisco Barbosa Alves de Moura. Introduction
Dimensionamento Estrutural de uma Ponte Canal Structural Design of a Canal Bridge Francisco Barbosa Alves de Moura IST, Technical University of Lisbon, Portugal Key Words: Structural Design, Canal Bridge,
More informationChartered Membership Examination
Chartered Membership Examination 1 Chartered Membership Examination Friday 9 January 2015 Structural Engineering Design and Practice 09.30 13.00 and 13.30 17.00 (Discussion between individuals is not permitted
More informationDesign and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway.
Design and Construction of the Nan-Tien Pedestrian Bridge, a Continuous Super-T Bridge over Princes Motorway. ABSTRACT James Nasr, Senior Bridge Engineer, Cardno The Nan-Tien Pedestrian Bridge project
More informationAPPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) RFP QUESTIONS AND ANSWERS-REVISION 2
Project: APPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) PROJECT: 0029-005-130, C501, B645 RFP QUESTIONS AND ANSWERS-REVISION 2 Date: 12/04/09 Approaches and Bridge over Tye River (Rte. 29 NBL) Subject:
More informationChartered Membership Examination Friday, 6 January 2017
Chartered Membership Examination Friday, 6 January 2017 Structural Engineering Design and Practice 09.30 13.00 and 13.30 17.00 (Discussion between individuals is not permitted during lunch period). A period
More informationThe HKIE Structural Examination Written Examination 2016
The HKIE Structural Examination Written Examination 2016 Section 2: Design Questions (80% of the Written Examination) Date: 2 December 2016 (Friday) Time: 12:00 nn - 06:00 pm Answer ONE question only Question
More informationPrestressed Hollowcore Slabs PRECAST CONCRETE SOLUTIONS.
PRECAST CONCRETE SOLUTIONS Prestressed Hollowcore Slabs HOLLOWCORE: THE CONCEPT Hollowcore slabs are prestressed concrete elements that have a constant cross section. They are manufactured using high tensile
More informationCABONNE COUNCIL DEVELOPMENT CONTROL PLAN NO. 15 RELOCATABLE AND TRANSPORTABLE HOMES
CABONNE COUNCIL DEVELOPMENT CONTROL PLAN NO. 15 RELOCATABLE AND TRANSPORTABLE HOMES As approved by Council at the meeting of 20 June 2005 Came into effect on 14 July 2005 I, G. L. P. Fleming, General Manager,
More informationA STRUCTURAL ASSESSMENT STUDY ON THE SUSTAINABILITY OF SULTAN ISKANDAR BRIDGE KUALA KANGSAR PERAK MALAYSIA
A STRUCTURAL ASSESSMENT STUDY ON THE SUSTAINABILITY OF SULTAN ISKANDAR BRIDGE KUALA KANGSAR PERAK MALAYSIA Lim Char Ching Public Works Department, Malaysia Email: cclim.jkr@1govuc.gov.my, Tel: 012-238
More informationDesign and construction of Hechang Bridge, Quanzhou, China
Design and construction of Hechang Bridge, Quanzhou, China G. Peng and B. Chen College of Civil Engineering, Fuzhou University, Fuzhou 302, China ABSTRACT: Hechang Bridge is a pedestrian bridge, located
More informationCVEN9000 Civil Engineering Design Practice
School of Civil and Environmental Engineering Semester 1, 2017 COURSE DETAILS Units of Credit 6 CVEN9000 Civil Engineering Design Practice Contact hours 4 hours per week Class Wednesdays, 9:00 11:00 Workshop
More informationCITY OF BATAVIA DECK CONSTRUCTION REQUIREMENTS
CITY OF BATAVIA DECK CONSTRUCTION REQUIREMENTS City of Batavia Building Division Community Development Department 100 North Island Avenue Batavia, Illinois 60510 Tel: (630) 454-2700 Fax: (630) 454-2775
More informationMatt Young Assistant Director - Park Operations and Planning City of Arlington, Texas. January 12 th, 2012
Matt Young Assistant Director - Park Operations and Planning City of Arlington, Texas January 12 th, 2012 Re: Design of City Wide Skatepark - Vandergriff Park Dear Mr. Young, Thank you for considering
More informationM2 THIS PAGE IS TO BE USED AS A M3 RECORD/PROOF OF SUBMISSION. D1 ENSURE EACH PIECE OF WORK SUBMITTED IS SIGNED FOR. D2
Diploma in Construction & the Built Environment / Civil Engineering YEAR 2014_15 QAN 500/7140/3 & 500/7137/3 (Btec Programmes: JW986 JW987 JW988) ASSIGNMENT BOOKLET (semester based) UNIT 14 STRUCTURAL
More informationReason for Acceptance or Rejection
Value Engineering Approval Form Project: 25th Avenue & Union Pacific Grade Separation #6 VE Study Date: January 28 through February 1, 2013 Form updated: 5/7/2013 (Final) FHWA Functional ENV 1 ROW 1 The
More informationwill be detrimental to your achievement M2 THIS PAGE IS TO BE USED AS A M3 RECORD/PROOF OF SUBMISSION. D1 ENSURE EACH PIECE OF WORK D2
Diploma in Construction & the Built Environment / Civil Engineering YEAR 2017_18 QAN 500/7140/3 & 500/7137/3 (Btec Programmes: JW986 JW987 JW988) ASSIGNMENT BOOKLET UNIT 14 STRUCTURAL MECHANICS Unit code:
More informationModular System Advantages
Modular System Advantages The Modular System advantages can be summarised as follows: Truly Modular Off-site build Competitive cost Multi-storey capability Fits any shape, any size Fast programme completions
More informationBALANCED CANTILEVER GIRDER BRIDGE OVER THE DANUBE-BLACK SEA CHANNEL
DOI: 10.1515/rjti-2015-0017 BALANCED CANTILEVER GIRDER BRIDGE OVER THE DANUBE-BLACK SEA CHANNEL Aldo Giordano, PH.D. Professor of Structural Engineering, ITALROM Inginerie Internationala, e-mail: a.giordano@italrominginerie.com
More informationStructural Eurocodes an overview
Structural Eurocodes an overview BS EN 1990, Eurocode Basis of Structural Design Structural safety, serviceability and durability BS EN 1991, Eurocode 1 Actions on Structures Actions on structures BS EN
More informationBridge Design, Construction & Maintenance Programme:
Bridge Design, Construction & Maintenance Programme: 4-12 February 2019, Dubai, UAE. 4th 12th March 2019, Cape Town, South Africa. 1st - 9th April, 2019 London, United Kingdom Course Objective 11111111
More informationConcrete Bridge Design and Construction series
40 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote excellence in the design, construction and management
More informationIntroduction to Engineering Design: EDGSN 100 Section 002
Design Project #1 Replacement of Vehicle Bridge over Spring Creek Centre County, PA Introduction to Engineering Design: EDGSN 100 Section 002 Team Ultra-Truss Design Team 5 Katherine Leahy, Bridget Johnson,
More informationModjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction
Introduction This memo presents a summary of a three dimensional (3D) analysis of the Organic concept for the proposed St. Croix River bridge project. The Organic concept has several attributes that are
More informationRESILIENT INFRASTRUCTURE June 1 4, 2016
RESILIENT INFRASTRUCTURE June 1 4, 2016 WESTMINSTER DRIVE UNDERPASS ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT Mark D Andrea, M.Sc., P.Eng. Stantec Consulting Ltd., Canada
More informationCHAPTER 3: Modern Methods of Construction (MMC)
CONTENTS 3.1.1 INTRODUCTION 3.1.2 SUITABILITY OF SYSTEMS AND COMPONENTS 3.1.3 TYPES OF MODERN METHODS OF CONSTRUCTION (MMC) 3.1.4 SUITABILITY OF SYSTEMS TO MEET WARRANTY REQUIREMENTS FUNCTIONAL REQUIREMENTS
More informationBRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)
SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART
More informationCONTENTS. Appendix D Guidance for the Production of Design & Check Certificates
CONTENTS Notes for Guidance for Applicants 1.0 Design Approval Page 1 2.0 Construction Stage Page 4 3.0 Information Required for Record Purposes.. Page 4 4.0 Planning Conditions.. Page 5 5.0 Provision
More informationOHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO
OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO 43216-0899 July 21, 2017 To: Users of the Bridge Design Manual From: Tim Keller, Administrator, Office of Structural
More informationShould be a Corporate Member of the Institution in the field of Civil Engineering and should register as a structural engineer of the IESL.
GUIDELINES FOR REGISTRATION AS A STRUCTURAL ENGINEER FOR THE DESIGN OF BUIDINGS WITH MORE THAN 4 FLOORS AS PER THE REQUIREMENTS OF THE URBAN DEVELOPMENT AUTHORITY FOR LISTING IN THE DIRECTORY OF STRUCTURAL
More informationLong Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables
Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables J. Manterola A. Martínez Carlos Fernández Casado S.L., Spain B. Martín J.A. Navarro M. A:
More informationExhibit A Mn/DOT Contract No
Exhibit A Mn/DOT Contract No. 98142 SCOPE OF WORK AND DELIVERABLES Preliminary Design Red Wing US 63 Bridge and Approach Roadways State Project (SP) 2515-21 SCOPE OVERVIEW... 2 SCHEDULE... 2 PROJECT TASK
More informationConcrete Bridge Design and Construction series
www.thestructuralengineer.org 41 CBDC series July 2014 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote
More informationSEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON STRUCTURAL EVALUATION FOR PREPARED BY PCS STRUCTURAL SOLUTIONS
STRUCTURAL EVALUATION FOR SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON PREPARED BY PCS STRUCTURAL SOLUTIONS NOVEMBER 1, 2017 17-733 TABLE OF CONTENTS Page I. PREFACE ii II. EXECUTIVE
More informationA-One Polar Ltd. Bhulta,Rupgonj,Narayangonj. ( , ) 27th April 2014
1 A-One Polar Ltd Bhulta,Rupgonj,Narayangonj. (23.754782,90545710) 27th April 2014 2 Observations Observations Knitting & Garments building Building 1 1 3 4 Observations Roof structure: no roof bracing
More information2018 SPECIFICATIONS The Timber Bridge
2018 SPECIFICATIONS The Timber Bridge APT Preservation Engineering Student Design-Build Competition Over the past 200 years of North American history, timber bridges have been used as quick, cost effective,
More informationFluid Viscous Dampers and Flat Surface Sliders for Seismic Isolation of the Bridge over Po River in Piacenza, Italy
Fluid Viscous Dampers and Flat Surface Sliders for Seismic Isolation of the Bridge over Po River in Piacenza, Italy M.G. Castellano, G.P. Colato, S. Infanti & A. Soffiato FIP Industriale SpA, Selvazzano
More informationBlaxland's Crossing Bridge, Wallacia NSW Bearing Replacement
Blaxland's Crossing Bridge, Wallacia NSW Bearing Replacement ABSTRACT Ken Maxwell, Arcadis Australia Pacific, Sydney, Australia The existing bridge (known as Blaxland s Crossing) carries Silverdale Road
More informationMASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK
MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 27510 CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY MAY 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.
More informationDesign and Rating of Steel Bridges
2014 Bentley Systems, Incorporated Parametric and Integrated Bridge Design LEAP Bridge Steel Steve Willoughby Design and Rating of Steel Bridges 2 WWW.BENTLEY.COM 2014 Bentley Systems, Incorporated 1 Discussion
More informationSTUDENT DESIGN COMPETITION - STRUCTURES For further information visit: tatasteelconstruction.com/sdc
STUDENT DESIGN COMPETITION - STRUCTURES 2013 For further information visit: tatasteelconstruction.com/sdc This page is intentionally blank. Document comprises 20 sheets in total, to allow for double-sided
More informationENTRY FORM. DVASE 2017 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2017 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings
More informationEmissions Reductions Alberta
Emissions Reductions Alberta Project Audit Expectations October 21, 2016 Emissions Reduction Alberta (ERA) is a legal trade name of the Climate Change and Emissions Management (CCEMC) Corporation. What
More informationSolutions for the Construction of steel bridges using the example of the Hochmoselübergang
Solutions for the Construction of steel bridges using the example of the Hochmoselübergang Dipl.-Ing. Michael Hagedorn, Eiffel Deutschland Dr.-Ing. Thomas Klähne, Klähne Ingenieure Dipl.-Ing. Uwe Heiland,
More informationCOMPARATIVE ANALYSIS OF SEISMIC ISOLATED SYSTEMS IN BRIDGES
COMPARATIVE ANALYSIS OF SEISMIC ISOLATED SYSTEMS IN BRIDGES APPLICATION TO A STUDY CASE João Tiago Ferreira Marques de Abreu Abstract This paper represents the resume of a study where is evaluated the
More informationSCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS
SCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS Each Technical Proposal (Volume A of Package 2 of the Proposal) should address each of the items and requests for information described in this
More informationPROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT
PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform
More informationChartered Membership Examination
The Institution of Structural Engineers Chartered Membership Examination Thursday 3 APRIL 2008 Structural Engineering Design and Practice 9.30a.m. 1p.m. and 1.30 5p.m. (Discussion between individuals is
More informationARCHITECTURAL TECHNOLOGY & DESIGN DESSIN ET TECHNOLOGIE ARCHITECTURALE POST-SECONDARY NIVEAU POSTSECONDAIRE
TEST PROJECT PROJET D ÉPREUVE ARCHITECTURAL TECHNOLOGY & DESIGN DESSIN ET TECHNOLOGIE ARCHITECTURALE POST-SECONDARY NIVEAU POSTSECONDAIRE Day 1 Competition Test & Appendix I Page 2 Day 1 (7 hours) REMEMBER
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 60019 MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS AUGUST 29, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF
More informationRESPONSE OF WOODEN FOOTBRIDGE TO THE DYNAMIC LOAD
RESPONSE OF WOODEN FOOTBRIDGE TO THE DYNAMIC LOAD Lenka Poništová, Roman Fojtík, David Mareček, Veronika Vašková and Antonín Lokaj Department of Civil Engineering, Ludvíka Podéště, VŠB - TU Ostrava, Ostrava
More informationThe Institution of Structural Engineers Chartered Membership Examination
The Institution of Structural Engineers Chartered Membership Examination 16th APRIL 2004 Structural Engineering Design and Practice 9.30 a.m. - 1 p.m. and 1.30-5 p.m. (Discussion between individuals is
More informationCertificate IV in Project Management Student Assessment Guide
Overview The assessment for the Certificate IV in Project Management comprises Team Assignment Development of a detailed Project Management Plan for chosen case study - 30% for blended classes Individual
More informationStructural Mechanics in Construction and Civil Engineering
Unit 14: Structural Mechanics in Construction and Civil Engineering NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract The study of the mechanics of structures is essential for engineers,
More informationREQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA
REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA GENERAL INFORMATION Greenwood School District 50 is
More informationQuestions Due: 12/11/14; Proposals Due 12/30/14: each by 2:00PM Central Standard Time
1. Q: Can you please confirm the Due Date? The Event Details on the webpage states 12/30/14, but when you click into Event Details in the Documents, it lists the Due Date as 12/5/14. A: Proposals are due
More informationICSS(4): A DESIGN APPLIED FOR A SUPER LONG MULTI-SPAN BRIDGE
ICSS(4): A DESIGN APPLIED FOR A SUPER LONG MULTI-SPAN BRIDGE D. Tsushima IHI Infrastrucure Systems Co., Ltd., Japan A. Igarashi Kyoto University, Japan H. Ouchi, T. Ueda & Y. Wada West Nippon Expressway
More informationProject Management: Project Justification and Planning
Higher National Unit Specification General information for centres Unit title: Project Management: Project Justification and Planning Unit code: DV5H 35 Unit purpose: This Unit is designed to provide the
More informationMyllysilta The Bridge Jouko Turto 07 September 2011
Myllysilta The Bridge Jouko Turto 07 September 2011 HISTORY OF THE BRIDGE The decision on constructing the Myllysilta Bridge was made in 1970 The technical personnel and City Board of Turku opposed the
More informationRt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening
Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction
More informationGet Involved Design Public Hearing
Get Involved Design Public Hearing VDOT representatives will review and evaluate Mail comments to Mr. Vicente Valeza at the address John G. Lewis Memorial Bridge any information received as a result of
More informationCE2401-DESIGN OF REINFORCED CONCRETE AND BRICK MASONRY QUESTION BANK
CE2401-DESIGN OF REINFORCED CONCRETE AND BRICK MASONRY QUESTION BANK UNIT-1 PART-A 1. What is a Retaining wall? 2. What are the disadvantages of gravity retaining walls? 3. What are the types of retaining
More informationSTRESS-RIBBON BRIDGES STIFFENED BY ARCHES OR CABLES
2nd Int. PhD Symposium in Civil Engineering 1998 Budapest STRESS-RIBBON BRIDGES STIFFENED BY ARCHES OR CABLES Tomas Kulhavy Technical University of Brno, Department of Concrete and Masonry Structures Udolni
More informationStructural Technical Report 1 Structural Concepts / Structural Existing Conditions Report
Michael A. Troxell Structural Option Advisor: Professor Parfitt College of Business Administration Oct. 5, 2005 Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report
More informationSystems Analysis and Design Methods Chapter 3: Information Systems Development
Systems Analysis and Design Methods Chapter 3: Information Systems Development Multiple Choice Questions 1. The act of drawing one or more graphical representations of a system is called. A. modeling B.
More information2016 ACEC/PA ANNUAL MEETING
2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA
More informationUNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - WILKIN COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 84505 CSAH NO. 14 OVER THE OTTER TAIL RIVER DISTRICT 4 - WILKIN COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.
More informationCompetency Category 1 Technical Competence Overall Level: 3
STRUCTURAL DISCIPLINE-SPECIFIC INDICATORS Competency Category 1 Technical Competence Overall Level: 3 Competencies 1.1 Demonstrate knowledge of regulations, codes, standards, and safety - this includes
More informationStructural Inspection
General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized
More informationNew Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia.
New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia. J. Manterola S. Fernández S. Fuente J. Muñoz-Rojas J. A. Navarro ABSTRACT The overall length of the new bridge over the River Magdalena
More informationBUILDERS TIMBER DECKING GUIDE TO
BUILDERS GUIDE TO TIMBER DECKING WWW.TDCA.ORG.UK 1 2 3 4 BUILDERS GUIDE TO TIMBER DECKING TIMBER DECKS CAN EITHER BE ATTACHED TO A PROPERTY OR FREE-STANDING. THE COMPLEXITY OF BUILD VARIES DEPENDING ON
More informationAhmedabad Gandhinagar Metro - MEGA, Ahmedabad. Construction of Helipad Building at V. S. Hospital, Ahmedabad
Birla Vishvakarma Mahavidyalaya Engineering College, V. V. Nagar 388120 A Report on Industrial/Site Visit Ahmedabad Gandhinagar Metro - MEGA, Ahmedabad Construction of Helipad Building at V. S. Hospital,
More information