A Primer Indianapolis, Indiana June 16, 2010

Size: px
Start display at page:

Download "A Primer Indianapolis, Indiana June 16, 2010"

Transcription

1 Alternative Project Delivery Methods A Primer Indianapolis, Indiana June 16, 2010 Michael Kenig, Holder Construction Company, Past chair of AGC of America s s Project Delivery Committee Jayne O Donnell, O General Manager, Turner s s Aviation Division

2 Overview of this Summit Definitions (Four Stops) Analysis of Options and Issues Identification of Best Practices Looking for Innovation

3 Industry Convergence Lean/ Economic Pressures You Are Here Building Information Modeling (BIM) Transparency in Public Bidding Labor, Tax and Funding Laws Project Delivery including IPD Threats and Risks Sustainability

4 Reference Materials Project Delivery Systems for Construction available though Associated General Contractors

5 Tailored (but dated) Reference Material Joint effort between ACI, ACC and AGC memberships Focused on airport owners Serves as an evolving, collaborative PDS guide Customizes key concepts in AGC PDS textbook

6 The Four Stops on the Road To Alternative Project Delivery 1. Ability to Use an Alternative Project Delivery 2. Definitions and establishing best options for your airport 3. Selecting best options for specific project needs and goals. 4. Implementing best practices and innovations to deliver the project. Baseline Metrics Lessons

7 Ability to Use Alternative Delivery Methods Airports have options: Design-Bid Bid-BuildBuild Construction Management at-risk Design /Build And although not yet implemented: FAA s s pilot program for PPP (private public partnerships)

8 Stop 2: Definitions Management Options Delivery Systems Procurement/Selection Contracting/Payment /Reimbursement

9 Defining Terms Management Options (in-house or out- sourced) Contracting/ Reimbursement (GMP, cost plus, lump sum, ) Delivery Methods (DBB, CMR, DB, Other) Procurement/Selection (low price/ best value / qualification based)

10 Defining Terms Management Options Delivery Methods Procurement/Selection Contracting/Payment /Reimbursement

11 Management Options 1. Use Owner s s Own Staff to manage the project 2. Hire Consultants to Assist in the management (Program Managers, Construction Managers or other staff augmentation)

12 Management Options vs Delivery Methods Owner & Owner Representatives Management Options: Who oversees the process Designer Builder Design- Bid -Build, Construction Management at-risk, Design/Build Delivery Methods: How design and construction is contracted by the Owner

13 Defining Terms Management Options Delivery Systems Procurement/ Selection Contracting/Payment /Reimbursement

14 Contracting/ Reimbursement Defined as: How the Owner wants to pay for the services provided (GMP, Cost plus, negotiated lump sum, lump sum)

15 Defining Terms Management Options Delivery Methods Procurement/Selection Contracting/Payment /Reimbursement

16 Phases of Project Development GOAL Traditional Linear Process Planning Design Bid Construction Occupancy Overlapping Phase Process Planning Design Construction Occupancy

17 Organizational Relationships Based on Delivery Methods How the owner and its consultants interact organizationally

18 Design-Bid Bid-BuildBuild Owner/ Owner Rep Two Separate Contracts for Design & Construction A / E Responsible for Design General Contractor Responsible for Construction Implementation

19 Construction Management at-risk Owner/ Owner Rep Two Separate Contracts for Design & Construction (CMR contracted to take cost and schedule risk) A / E Responsible for Design Construction Manager at Risk Responsible for Construction Implementation

20 Design/Build One Single Contract for Design & Construction Owner Bridging Consultant (optional) Design/Build Entity Responsible for Design and Construction Implementation

21 Optional Structures for Design/Build Entities Design/Build Entity Types Integrated Firm - All services in-house Contractor Led (design subcontracted) Joint Venture (architect-contractor j.v.) Architect Led (construction subcontracted)

22 What Characterizes Design-Bid-Build? Defining Characteristics - There are Separate Contracts for Design & Construction Contractor Selection is Based Entirely on Cost And Typically Design Documents are 100% complete

23 What Characterizes CM At-Risk? Defining Characteristics - There are separate contracts for design & construction Contractor selection is NOT based entirely on cost CMR contracts directly with trades and takes on performance risk (cost and schedule commitments) And Typically though not unique to CMR Schedule allows for overlapping design and construction Owner procures preconstruction services from the CMR Owner expects CMR to provide Guaranteed Maximum Price (GMP) and to commit to delivery schedule

24 What Characterizes Design/Build? Defining Characteristics - Single Point of Responsibility And Typically Schedule allows for overlapping design and construction Owner procures Preconstruction Services from the CMR Owner expects CMR to provide Guaranteed Maximum Price (GMP) and to commit to delivery schedule

25 Strengths of Each Delivery Type DBB -100% design complete CM at Risk bring builder in during design to improve design cost and accelerated schedule D/B single point of contact, fastest

26 Defining Terms Management Options Delivery Methods Procurement/ Selection Contracting/Payment /Reimbursement

27 Contracting Reimbursement What is The Project Cost? Cost of Construction + Contractor s s Fee & General Conditions + Contingencies /Allowances Total Construction Cost + Professional Services Fees + Design Contingencies + Permitting & Other Soft Costs +Owner Contingency Total Project Budget

28 Procurement /Selection Types 1. Low Bid Total Construction Cost, is the only selection criteria. (Total Construction weighted 100% ) 2A. Best Value Bid Total Construction Cost is a weighted selection criteria. (Total Construction Cost weighted between 0% & 100% ) 2B. Best Value Fees Fees and/or General Conditions are weighted; but Total Construction Cost is not a weighted selection criteria (Fees weighted between 0% & 100% ) 3. Qualifications Based Selection Price is not a selection criteria. (Price weighted 0% )

29 Typical Public Owner s Delivery Options SELECTION TYPES Price Definition Designer & Contractor 2 separate contracts Design- Builder 1 combined contract 1. Low Bid Total Construction Cost Professional Services Selected on Price Design/Builder Selected on Price 2A. 2B. Price and other Qualifications Total Construction Cost Fees, General Conditions, Contingencies Etc. Pre Qualified Bid Best Value Proposal Design/Build Pre-Qualified Bid Design/Build Best Value Proposal Qualifications ONLY 3. Based Selection None Professional Services based on Qualifications only Design-Build Services Based on Qualifications only

30 Examples of Airports Choices SELECTION TYPES Price Definition Designer & Contractor 2 separate contracts Design- Builder 1 combined contract 1. Low Bid Total Construction Cost John Wayne Airport, Washington Dulles - Contractor services Federal Contracts (FAA, DOT, COE)? 2A. 2B. Price and Other Qualifications Total Construction Cost Fees, General Conditions, Contingencies Etc. JetBlue Terminal 5, JFK Airport Most Common -PHX, SEA, FLL, Sacramento Airport* San Francisco Airport Qualifications ONLY 3. Based Selection None John Wayne Airport (PM/CM and A/E services) San Diego Airport

31 Delivery Methods Selection Options 1. Delivery Method / Selection Types Design-Bid-Build Low Bid Best Value Bid Best Value Fees Qualifications Based Selection (QBS) 2. CM at-risk (aka CM/GC) 3. Design-Build 4. Other

32 Another Way

33 Selection Process Summary SELECTION PROCESSES DELIVERY METHOD IFB 1 RFQ 2 RFP 3 Design-Bid-Build Design-Build, 1-Step Design-Build, 2-Step X X Const. Risk JOC, 1-Step JOC, 2-Step X X Notes: 1. Invitation for Bids, low bid process. 2. Request for Qualifications, a qualifications-based selection process with no element of price considered in the first step. 3. Request for Proposals, a process that combines qualifications, technical capabilities, and price in a Best Value process. X Engineering and Architectural Services Department 33 X X X

34 End of Definitions Next.. we continue to Stop 3 on the Road To Alternative Project Delivery 1. Ability to Use an Alternative Project Delivery 2. Definitions of the each of the Delivery Method Options 3. Selecting the appropriate Project Delivery Method 4. Implementing the chosen Project Delivery Method

35 Benefits and Results of Alternate Delivery Methods Airport Project Delivery Summit II Chicago, IL May 17, 2007 Wylie Bearup, City Engineer

36 APDM Project Summary Delivery Methods Total Projects Projects Awarded Projects Completed Contractors Selected Value ($M) Design-Build $436.9 Risk $2,484.6 Job Order Contracting $ $3,133.9 * Cumulative since passage of legislation in 2000 through December 2006 Engineering and Architectural Services Department 36

37 APDM Benefits Ability to pick Best Qualified contractor Better relationships among all project team members Contractor involvement throughout design phase: more control of budget through design phase true Value Engineering to ensure most costefficient systems enhanced project communications by selecting entire team early more time to plan construction activities better designs through constructability reviews Engineering and Architectural Services Department 37

38 APDM Benefits, con. Better quality from better subcontractors Smoother project close out Better contractor performance for repeat business Reduced completion time with fast tracking and long lead procurement Greater control of subcontractor selection Higher levels of M/W/SBE participation Ability to meet Green Building goals Engineering and Architectural Services Department 38

39 APDM Research Analyzed 59 completed projects: 33 DBB to serve as baseline 20 completed projects 6 completed DB projects Analysis compared results in 3 areas: Schedule Growth Cost Growth Delivery Speed Team perceptions: APDM projects on time, with better quality Engineering and Architectural Services Department 39

40 Schedule Growth 30.0% 25.0% 24.7% 20.0% 15.0% 10.0% 7.0% 5.0% 4.8% 0.0% Design-Bid-Build Design-Build Engineering and Architectural Services Department 40

41 Cost Growth 16.0% 15.2% 14.0% 12.0% 10.0% 8.0% 6.0% 4.7% 4.0% 2.0% 0.0% 0.7% Design-Bid-Build Design-Build Engineering and Architectural Services Department 41

42 Construction Speed 2,500 2,000 2,141 SF/month 1,500 1, , Design-Bid-Build Design-Build CM@Risk Engineering and Architectural Services Department 42

43 Conclusion Process is working very well Methods have provided significant benefits to the City City continues to utilize all of the tools in our tool box Engineering and Architectural Services Department 43

44 6 th Annual FMI/CMAA Survey of Owners

45 6th Annual FMI/CMAA Survey of Owners

46 6th Annual FMI/CMAA Survey of Owners

47 How to Choose the Best Delivery Method Airport Project Delivery Summit II Chicago, IL May 16, 2007 Wylie Bearup, City Engineer, City of Phoenix

48 NUMERICAL ANALYSIS 1. Select and rank criteria. 2. Rate Delivery Methods ability to deliver criteria. 3. Apply ratings to ranked criteria. 4. Sum scores for each method. 5. Highest scored method selected. Engineering and Architectural Services Department 48

49 Developing Criteria CRITERIA Low initial design and construction costs High aesthetics of design High quality project Short project schedule High City control of design Low risks to City Non-adversarial relationships Effective coordination of design and construction Maximum flexibility to revise scope Low cost growth Engineering and Architectural Services Department 49

50 Ranking Criteria CRITERIA RANK Low initial design and construction costs 3.5 High aesthetics of design 10 High quality project 8 Short project schedule 6 High City control of design 9 Low risks to City 1 Non-adversarial relationships 2 Effective coordination of design and construction 7 Maximum flexibility to revise scope 3.5 Low cost growth 5 10 = most important, 1 = least important Engineering and Architectural Services Department 50

51 Rating Delivery Methods CRITERIA DBB DB Low initial design and construction costs High aesthetics of design High quality project Short project schedule High City control of design Low risks to City Non-adversarial relationships Effective coordination of design and construction Maximum flexibility to revise scope Low cost growth = best able to deliver, 1 = worst able to deliver Engineering and Architectural Services Department 51

52 Weighted Criteria CRITERIA DBB DB Low initial design and construction costs High aesthetics of design High quality project Short project schedule High City control of design Low risks to City Non-adversarial relationships Effective coordination of design and construction Maximum Flexibility to revise scope Low cost growth TOTAL SCORE CM@R selected as Best Method Engineering and Architectural Services Department 52

53 PROS & CONS ANALYSIS CRITERIA DBB COMMENTS Contractor Selection Subcontractor Selection Design Input Quality Speed Relationships City selects Best Qualified contractor, based on demonstrated performance. Can select best Civic Plaza constructor in the country. DBB must select low bid, even if no experience or poor past performance. provides proposed subcontractors to City for approval. City can veto any poor performers or non-local firms. competes subcontracted work among prequalified, approved subs. DBB, low bid contractor brings own subs, no City control. selected during design process. Participates in design reviews. Provides true value engineering, constructability reviews. Validates design within budget throughout process. DBB, no design input, no constructor estimate until bid day. is selected on past performance. Has opportunity to work with designer, understand Owner s quality needs. Able to price construction cost proposal to satisfy quality requirements. Wants to provide high quality for future selections. DBB, quality reduces profit. CM@R can begin work as phases of design are completed; accelerates project. Can plan construction activities during design - site layout, circulation, etc. Is productive from 1st day on site. DBB, cannot start any work until entire design complete. CM@R, entire project team together throughout project. Able to establish relationships, communications processes up front. CM@R selected through professional process, similar to designer. DBB, contractor selected later, after City and designer working together. Engineering and Architectural Services Department 53

54 Pros & Cons Analysis, con FACTOR DBB COMMENTS Cost Growth Schedule Growth Initial Cost Cost Certainty Litigation Value involvement during design improves drawings and specs. More clearly understands design intent, helps eliminate ambiguities and deficiencies. Is motivated to limit change orders for future business. DBB, can exploit design deficiencies, no motivation to reduce. Prior planning during design makes more efficient, less surprises. Motivated to perform for future business. Paid lump sum for overhead, looses money if project delayed. DBB, negotiates extended General Conditions for changes, covers costs. requires fee to contractor during design, not required by DBB. receives construction phase fee, more visible than DBB. Research indicates can actually save money over project life. City doesn t have sufficient experience to evaluated total cost savings. CM@R gives City Guaranteed Maximum Price, absorbs cost if exceeded. Any savings realized during project returned to City. CM@R involvement during design reduces E&O change orders, cost growth. DBB, final project cost not known until negotiate final change order. Previous litigation used as negative factor in selection process. Improved relationships and communications reduces issues that lead to claims. Desire for repeat business compels CM@R to settle problems early. DBB not concerned about litigation, doesn t impact next low-bid selection. Fees paid to CM@R are investment in the project. Improves relationships, schedule, quality; reduces change orders and litigation. Research indicates CM@R is good value over project life. CM@R selected as Best Method Engineering and Architectural Services Department 54

55 SUMMARY Have applied Numerical Method on limited projects: Lake Pleasant Water Treatment Plant IGC/TGen Headquarters Convention Center Expansion Typically apply some form of Pros & Cons Analysis Engineering and Architectural Services Department 55

56 6 th Annual FMI/CMAA Survey of Owners Primary issues surveyed include role of A/E and C, collaboration, commissioning, sustainability, and delivery methods

57 Need more information?... Contact AGC of America Mike Stark:

58 RECAP: Defining Terms Management Options (in-house or out- sourced) Contracting/ Reimbursement (GMP, cost plus, lump sum, ) Delivery Methods (DBB, CMR, DB, other) Procurement/Selection (low bid / best value / qualification based)

59 From this session Management Options Delivery Systems Procurement/Selection Contracting/Payment /Reimbursement Consensus.

60 Agenda for Remainder of Summit Low Bid vs QBS GMP Contracting Funding Best Practices, a Case Study Design Level of Detail Innovations: BIM, Partnering, IPD

61 Alternative Delivery Methods, A Primer Michael Kenig, Holder Construction Company Phone: mkenig@holder.com Jayne O Donnell, O Turner Aviation Phone: JODonnell@tcco.com

62 End

1/4/2014. Alternative Project Delivery Methods 1. Agenda

1/4/2014. Alternative Project Delivery Methods 1. Agenda Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia

More information

DEFINING THE SPECTRUM OF PROJECT DELIVERY OPTIONS AND THEIR IMPLICATIONS FOR YOUR PROJECT 2017 Airport Construction Strategy Summit

DEFINING THE SPECTRUM OF PROJECT DELIVERY OPTIONS AND THEIR IMPLICATIONS FOR YOUR PROJECT 2017 Airport Construction Strategy Summit DEFINING THE SPECTRUM OF PROJECT DELIVERY OPTIONS AND THEIR IMPLICATIONS FOR YOUR PROJECT 2017 Special Thanks To: DEFINING THE SPECTRUM OF PROJECT DELIVERY OPTIONS AND THEIR IMPLICATIONS FOR YOUR PROJECT

More information

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from

More information

Airport Owners Guide to Project Delivery Systems White Paper Update

Airport Owners Guide to Project Delivery Systems White Paper Update Airport Owners Guide to Project Delivery Systems White Paper Update Steve Riano Chair, ACC Project Delivery Committee Bechtel Infrastructure Corporation Fall 2011 ACI-NA Operations & Technical Affairs

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide array of design, construction, construction administration,

More information

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Choosing a Project Delivery Method. A Design-Build Done Right Primer Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours)

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours) Session THREE Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: What type of tendering methods are there? What does qualification mean? Do you (the MC) bid for every job? Do you (the MC) price

More information

Design-Build (DB) and Construction Manager / General Contractor (CMGC)

Design-Build (DB) and Construction Manager / General Contractor (CMGC) Design-Build (DB) and Construction Manager / General Contractor (CMGC) IDOT and Industry Preliminary Joint Review for Proposed Legislation December 18, 2012 Welcome Introductions Agenda Purpose Definitions

More information

PROJECT DELIVERY METHODS

PROJECT DELIVERY METHODS Understanding the Construction Contract Project Delivery Methods ISBA April 7,2017 Copyright 2017 by K&L Gates LLP. All rights reserved. Design Bid Build Design Negotiate Build Construction Manager Advisor

More information

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018 SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018 Types of Public Construction Delivery Methods Available: Design-Bid-Build (DBB) under M.G.L Ch. 149 Overview Pros Cons Construction Management at Risk

More information

Progressive Design-Build Discussion

Progressive Design-Build Discussion Presentation for: Progressive Discussion February 4, 2011 1 Project Delivery Options Design-Bid-Build Construction Management at Risk Lump Sum Progressive DESIGNER BUILDER DESIGNER CM TRADITIONAL DELIVERY

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development

More information

DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS (SUPERPOWERS OPTIONAL!) FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors

DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS (SUPERPOWERS OPTIONAL!) FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS (SUPERPOWERS OPTIONAL!) FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors YOUR SUPERHERO TRAINERS TODAY ADAM NELSON Senior Architectural

More information

Construction Project Delivery Methods Overview and Comparison. Operations Division

Construction Project Delivery Methods Overview and Comparison. Operations Division Construction Project Delivery Methods Overview and Comparison Operations Division 1 Four Types of Delivery Methods Design/Bid/Build (CM Multi-Prime) CM at Risk Design/Build Lease/Leaseback 2 Considerations

More information

CMAA Owners Group Construction Delivery Methods

CMAA Owners Group Construction Delivery Methods CMAA Owners Group Construction Delivery Methods January 25, 2017 Today s Agenda Welcome Participants Introduce Themselves Goals for the Year Mission Statement Upcoming Events CMAA Membership CCM Certification

More information

Partnering for Alternative Delivery Projects

Partnering for Alternative Delivery Projects Partnering for Alternative Delivery Projects Presented by: Renee L. Hoekstra, CVS Managing Partner RHA, LLC Julie Kliewer, PhD, P.E. State Construction & Materials Engineer - ADOT Training Objectives Understanding

More information

Qualifications Based Selection of Contractors

Qualifications Based Selection of Contractors Qualifications Based Selection of Contractors AGC of America Project Delivery Committee QBS Working Group 1 Table of Contents QBS & The Industry: An Introduction Pages 3-4 Selection Criteria for QBS Page

More information

1/12/2015. Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach

1/12/2015. Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach DRAFT for AIA CCA Knowledge Community 2015 Dale Munhall, AIA not a sign of teamwork Director of Construction

More information

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA PROGRESSIVE DESIGN-BUILD Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA ADVANTAGES/DISADVANTAGES DESIGN BID BUILD (HARD BID) The traditional project delivery method, which customarily

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

Procurement Documents for Progressive Design-Build Projects

Procurement Documents for Progressive Design-Build Projects Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model

More information

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method Report on Effectiveness of the Construction Manager at Risk Project Delivery Method The project management plans described below, establish several elements or criteria for university project staff to

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

ALTERNATE FORMS OF PROJECT DELIVERY

ALTERNATE FORMS OF PROJECT DELIVERY ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors

More information

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be Thanks to our host CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be reported to RCEP at RCEP.net. A certificate

More information

Construction Project Delivery Methods

Construction Project Delivery Methods Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031

More information

Pioneering Alternative Project Delivery in Ohio

Pioneering Alternative Project Delivery in Ohio Pioneering Alternative Project Delivery in Ohio Ali Bahar, PE Principal Engineer Metropolitan Sewer District of Greater Cincinnati Tim Koch, PE, Vice President, Brown and Caldwell 1 Agenda Construction

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Project Delivery Methods Design-Bid-Build (DBB) Indefinite Delivery/Indefinite Quantity (ID/IQ) Construction Management at Risk

More information

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. Catalog. Updated Docs Inside ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits

More information

Project Delivery Systems

Project Delivery Systems Project Delivery Systems National Society of Professional Engineers Alaska Society of Professional Engineers 2011 Western and Pacific Region Annual Meeting and Conference Jeffrey Callahan April 1, 2011

More information

AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA

AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA PREFACE This document is an introductory guide for owners who face the choice of delivery methods for their

More information

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE Risks Associated with Alternative Delivery Methods Managing Expectations Presented by Dan Becker, CCM, PMP, CCE 1 3 Primary Methods for Delivering Projects in WA and OR Design/Bid/Build Design/Build CM

More information

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Jim Mallorey, P.E. Metro Wastewater Reclamation District Chris Harper - University of Colorado Boulder January 23, 2014 1

More information

Facility Basics for Bond Project Communications

Facility Basics for Bond Project Communications Facility Basics for Bond Project Communications TSPRA Annual Conference February 19, 2013 Presented by: Cathy Brandewie O Connell Robertson Architectural Teams can help with Evaluating / Assessing Facilities

More information

Construction Documents Education Program

Construction Documents Education Program PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected

More information

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K CONTRACTS CATALOG Updated Docs Inside ou Ah ead o f the Cur v e gy epin e K ... BUILDING A BETTER WAY! Whether working at the office, from the road or even at home, the platform provides instant access

More information

Fairfax County Government Construction Management At Risk (CMAR)

Fairfax County Government Construction Management At Risk (CMAR) Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of

More information

Stakeholders and project delivery methods

Stakeholders and project delivery methods Stakeholders and project delivery methods CIV-E.1040 Construction Management Lecture II 8 th November 2016 Antti Peltokorpi Assistant Professor Department of Civil Engineering, Aalto University antti.peltokorpi@aalto.fi

More information

PROFESSIONAL PRACTICE 544

PROFESSIONAL PRACTICE 544 PROFESSIONAL PRACTICE 544 April 20, 2015 Contracting Methods Alternative Project Delivery Methods Michael J. Hanahan, Esq. Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com

More information

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES Pueblo Urban Renewal Authority (PURA) Pueblo Convention Center Expansion &

More information

Construction Manager at Risk Delivery Method

Construction Manager at Risk Delivery Method County of Alameda Board of Supervisors Transportation and Planning Committee May 4, 2015 Caroline Judy, Acting Director Construction Manager at Risk Delivery Method Briefing and Discussion Purpose Briefing

More information

FACILITIES CONFERENCE

FACILITIES CONFERENCE FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity

More information

FACILITY PROJECT BIDDING OPTIONS OVERVIEW

FACILITY PROJECT BIDDING OPTIONS OVERVIEW FACILITY PROJECT BIDDING OPTIONS OVERVIEW A Presentation to the Board of Education Galt Joint Union High School District February 14, 2017 January 10, 2017 GHSD Measure E Bidding Options Overview 2 Overview

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Design-Build Data Sourcebook

Design-Build Data Sourcebook Design-Build Data Sourcebook What Is Design-Build? It s the fastest growing, most cost and time efficient method used to deliver construction projects in America. Design-build saves time and money by encouraging

More information

Professional Practice 544

Professional Practice 544 Spring Semester 2017 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights

More information

ALTERNATIVE CONTRACTING METHODS

ALTERNATIVE CONTRACTING METHODS ALTERNATIVE CONTRACTING METHODS Conventional Design-Bid-Build Design/Build Negotiated General Contractor By Jeff Warner, AIA, LEED AP Principal, ALSC Architects CONVENTIONAL DESIGN-BID-BUILD The most traditional

More information

Professional Practice 544

Professional Practice 544 Spring Semester 2018 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights

More information

Project Delivery Method

Project Delivery Method City Green - Project Delivery Method Roswell City Council Work Session September 14, 2016 Agenda Debrief on HPC Work Session Project Schedule Update Alternative Project Delivery Methods Discussion / Direction

More information

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD OWNER OWNER OWNER DESIGNER GC DESIGNER DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD Contracts Communications

More information

School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018

School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018 School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018 Who we are Presenters Rob Wilkinson, Partner, Ball Janik LLP Scott Rogers, CPPB, Senior Project Manager,

More information

Alternative Project Delivery Methods and Procurement

Alternative Project Delivery Methods and Procurement Alternative Project Delivery Methods and Procurement Board of Airport Commissioners Meeting 2 June 2014 Presented by: Roger A. Johnson, Deputy Executive Director Definitions Project Delivery Method o The

More information

Different Ways to Contract for Lean Project Delivery. Joel Darrington San Diego COP 3/27/19

Different Ways to Contract for Lean Project Delivery. Joel Darrington San Diego COP 3/27/19 Different Ways to Contract for Lean Project Delivery Joel Darrington San Diego COP 3/27/19 Relevance of Contracts? Increase alignment among parties Parameters for Lean behavior and activities First collaborative

More information

Alternate Project Delivery Experience at UOSA and PWCSA

Alternate Project Delivery Experience at UOSA and PWCSA Alternate Project Delivery Experience at UOSA and PWCSA Bob Angelotti, Director of Technical Services at UOSA Samer Beidas, Director of Engineering and Planning at PWCSA Presented at the VWEA 2015 Education

More information

A/E-LED INTEGRATED PROJECT DELIVERY

A/E-LED INTEGRATED PROJECT DELIVERY A/E-LED INTEGRATED PROJECT DELIVERY PRESENTED BY: Mark C. Friedlander Schiff Hardin LLP 233 South Wacker Drive Suite 6600 Chicago, Illinois 60606 (312) 258-5500/Fax: (312) 258-5600 mfriedla@schiffhardin.com

More information

DTX Project Delivery Methodology and Options. January 9, 2014

DTX Project Delivery Methodology and Options. January 9, 2014 DTX Project Delivery Methodology and Options January 9, 2014 1 Outline/Agenda Overview of Common Project Procurement and Delivery Methods Examples of Past Project Delivery Methods ( The Good, The Bad,

More information

Progressive Design-Build

Progressive Design-Build November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value

More information

UNIVERSITY OF CALIFORNIA, SAN DIEGO

UNIVERSITY OF CALIFORNIA, SAN DIEGO BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANT A BARBARA SANT A CRUZ OFFICE OF THE ASSOCIATE VICE CHANCELLOR CAPITAL PROGRAM MANAGEMENT TEL: (858) 534-2177 FAX: (858) 534-4363

More information

SCADA System Procurement Alternatives

SCADA System Procurement Alternatives SCADA System Procurement Alternatives 2017 Automation Committee Seminar August 24, 2017 Terry M. Draper, PE, PMP Discussion Topics SCADA Overview System Hardware / Software Procurement Additional System

More information

Alternative Delivery for Municipal Water & Wastewater Projects in 2012

Alternative Delivery for Municipal Water & Wastewater Projects in 2012 Alternative Delivery for Municipal Water & Wastewater Projects in 2012 a OWEA 2012 Making a Pass at Going Green Looking Towards the Future June 20, 2012 Dennis Tinkler, P.E. Agenda Ohio s Methods of Performing

More information

The Owner s Role in Successful Design-Build Project Delivery

The Owner s Role in Successful Design-Build Project Delivery The Owner s Role in Successful Design-Build Project Delivery Northwest Construction Consumer Council Tulalip Resort Casino & Conference Center October 23, 2013 presented by: Barbara Wagner Design-Build

More information

Alternative Delivery Methods in the Post-Davis World

Alternative Delivery Methods in the Post-Davis World CASBO 2017 Annual Conference April 2017 Alternative Delivery Methods in the Post-Davis World Alan Reising Long Beach Unified School District areising@lbschools.net Phil Henderson Orbach Huff Suarez & Henderson

More information

EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY

EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY Thomas O. Crowley, P.E. Carollo Engineers Southwest Section AWWA October 17, 2017 Agenda Project Delivery Overview Oklahoma Legislation Project Delivery Methods

More information

ICOC Procurement Briefing

ICOC Procurement Briefing ICOC Procurement Briefing How we acquire goods and services Overview Procurement of Professional Services Engineering, architecture, design build, construction manager Projects < $2 million use continuing

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee. Project Delivery Selection Approach

Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee. Project Delivery Selection Approach Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee Project Delivery Selection Approach Overview This document provides an approach for water and wastewater project delivery

More information

Continuing Education Credits

Continuing Education Credits Recent Developments in (IPD) for NECA Members October 14, 2013 9:00-9:50 AM Following this session, you will be able to: Explain the concept and structure of an IPD project. Identify the issues and risks

More information

ADDENDUM #2. Design/Build Contractor RFP Bid # for the. Joint-Use 21 st Century Post-Century Education Center.

ADDENDUM #2. Design/Build Contractor RFP Bid # for the. Joint-Use 21 st Century Post-Century Education Center. ADDENDUM #2 Design/Build Contractor RFP Bid #0606-14 for the Joint-Use 21 st Century Post-Century Education Center SJECCD California July 7, 2014 SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT 4750 San

More information

REQUEST FOR QUALIFICATIONS AND PROPOSALS

REQUEST FOR QUALIFICATIONS AND PROPOSALS REQUEST FOR QUALIFICATIONS AND PROPOSALS CONSTRUCTION MANAGER AT RISK SERVICES Preconstruction Phase Services and Construction Phase Services Sheridan Economic and Educational Development Authority Sheridan

More information

INTEGRATED PROJECT DELIVERY IN PUBLIC PROJECTS: LIMITATIONS AND OPPORTUNITY

INTEGRATED PROJECT DELIVERY IN PUBLIC PROJECTS: LIMITATIONS AND OPPORTUNITY Kim, Y., Rezquallah, K., Lee, H., and Angeley, J. (2016). Integrated Project Delivery in Public Projects: Limitations and Opportunity." In: Proc. 24 th Ann. Conf. of the Int l. Group for Lean Construction,

More information

Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers

Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers CBOC: Bond Update Since the Bond Passed Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers Bond Implementation Plan Considers

More information

PROVING OUR PROFESSIONALISM

PROVING OUR PROFESSIONALISM PROVING OUR PROFESSIONALISM 49 TH ANNUAL CONFERENCE MAY 22-25, 2016 ORLANDO, FLORIDA DESIGN-BUILD 101 Joanne Flick, CPPO, CPPB TODAY S TOPICS Project Delivery Overview Comparing Project Delivery Methods

More information

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for

More information

Welcome! Achieving Collaborative IPD-ish Delivery with basic D-B, P3 or CM contracts: Yes, there is a way

Welcome! Achieving Collaborative IPD-ish Delivery with basic D-B, P3 or CM contracts: Yes, there is a way Welcome! Achieving Collaborative IPD-ish Delivery with basic D-B, P3 or CM contracts: Yes, there is a way Wed, June 10, 2015 1:00 PM - 2:00 PM EDT Earn 1.0 AIA HSW LUs Moderator Jane Cameron, AIA, LEED

More information

Successful Use of Progressive Design-Build in California Community Colleges

Successful Use of Progressive Design-Build in California Community Colleges Successful Use of Progressive Design-Build in California Community Colleges The Panelists Bill Pate Devaney Pate Cameron & Morris LLP Chris Strugar-Fritsch San Mateo County Community College District Dennis

More information

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016 REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES For the renovation of existing apartment buildings August 15, 2016 INVITATION Bath Housing Development Corporation is soliciting proposals for

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

Strategic Management and Project Selection

Strategic Management and Project Selection Strategic Management and Project Selection Strategic Management and Project Selection Maturity of Project Management Overview Criteria for PS Models Nature of PS Models Types of PS Models Uncertainty Analysis

More information

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 AN OVERVIEW OF DESIGN-BUILD Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 Design-Build Not a New Concept In California: Multiple statutes govern design-build

More information

Legal Issues Related to Design Build

Legal Issues Related to Design Build Legal Issues Related to Design Build Presented by Aaron O. Martin CLARK, MIZE & LINVILLE, CHARTERED 129 S. 8 th, St. Salina, KS 67401 Telephone: (785) 823 6325 Facsimile: (785) 823 1868 aomartin@cml law.com

More information

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request

More information

SIXTH ANNUAL AIRPORT PROJECT DELIVERY SUMMIT

SIXTH ANNUAL AIRPORT PROJECT DELIVERY SUMMIT SIXTH ANNUAL AIRPORT PROJECT DELIVERY SUMMIT Terminal 1 In Line Baggage Screening Project June 8th & 9th, 2011 San José, CA Marc Gambrill, P.E, Director of Capital Improvement Program Fort Lauderdale-Hollywood

More information

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 2007 is a standard form of agreement between owner and contractor for

More information

SEPARATED PROJECT DELIVERY SYSTEMS

SEPARATED PROJECT DELIVERY SYSTEMS SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer

More information

General Session 2 Procurement Update. #AirportsTechnical

General Session 2 Procurement Update. #AirportsTechnical General Session 2 Procurement Update #AirportsTechnical Procurement Update Moderator: Jeff Kirby, Parish & Partners Mike Rottinghaus, FAA, Office of Airport Planning and Programming Jim Harris, Coffman

More information

Procurement Guidelines

Procurement Guidelines Reference 21 CM@Risk Procurement Guidelines Draft June 5, 2014 Purpose: These guidelines are intended to provide (1) assistance to those who may be responsible for implementation, processing and/or management

More information

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference JOB ORDER CONTRACTING United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference March, 2015 AGENDA Who is the Gordian Group Introduction to Job Order Contracting Explanation

More information

WhAt Are my OptIONs?

WhAt Are my OptIONs? ALTERNATIVE WAYS TO DESIGN AND CONSTRUCT BUILDING PROJECTS FOR POLITICAL SUBDIVISIONS IN NEBRASKA WhAt Are my OptIONs? Save Time and money with ReSouRceS from The nebraska design & construction industry

More information

Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective

Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective CMAA National Conference October 13, 2008 Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective Date Presenters Howard W. Ashcraft,