REQUEST FOR PROPOSAL DUGWAY WEST INTERCEPTOR RELIEF SEWER (DWIRS) WBS NO. CIP.CS.E March 2011

Size: px
Start display at page:

Download "REQUEST FOR PROPOSAL DUGWAY WEST INTERCEPTOR RELIEF SEWER (DWIRS) WBS NO. CIP.CS.E March 2011"

Transcription

1 REQUEST FOR PROPOSAL DUGWAY WEST INTERCEPTOR RELIEF SEWER (DWIRS) WBS NO. CIP.CS.E March 2011 This Request for Proposal (RFP) is being sent to interested engineering firms for predesign, design, bidding, construction and closeout engineering services for the Dugway West Interceptor Relief Sewer. Proposals for providing these services will be received until the close of business (4:30 P.M.) on April 15, All material submitted shall have a font size equivalent to Times New Roman 12 pt or larger. Proposals shall be no more than 100 printed pages and be printed on double-sided recycled paper. All pages will be counted unless indicated otherwise in Section 3.0, Proposal Content and Format. Pages that are 11 x17 shall be counted as two pages. Proposals are to be delivered to the following name and address: Julius Ciaccia, Executive Director Northeast Ohio Regional Sewer District 3900 Euclid Avenue Cleveland, OH Attn: Kellie Rotunno, Director of Engineering and Construction Late submittals will not be considered. A mandatory (for consultants that will submit as a prime) pre-proposal meeting will be held at 1 P.M. on March 18, 2011 in Conference Room B of the Northeast Ohio Regional Sewer District s Environmental Maintenance and Service Center (EMSC) located at 4747 East 49 th Street, Cuyahoga Heights, Ohio. Questions regarding this RFP shall be directed to Mr. Brian Page at the pre-proposal meeting or at other times by calling (216) , ext or ing to pageb@neorsd.org. The RFP is organized as follows: SECTION 1.0 SECTION 2.0 SECTION 3.0 SECTION 4.0 SECTION 5.0 INTRODUCTION SCOPE OF SERVICES PROPOSAL CONTENT AND FORMAT PROJECT SCHEDULE EVALUATION AND SELECTION PROCESS Page 1 of 48

2 SECTION 6.0 SUBMISSION OF PROPOSALS RFP list of Attachments The following attachments are included in this RFP. Attachment A Attachment B Attachment C Attachment D Attachment E Attachment F Attachment G Attachment H Attachment I Project Invoice Standards Project Data Standards & Requirements NEORSD SBE Policy District Equal Employment Opportunity Form Task and Hour Summary Form NEORSD Cost Summary Form NEORSD Non-Disclosure Agreement Standard Professional Agreement NEORSD SWP3 Format Template RFP list of Exhibits The following exhibits are provided for informational purposes: Exhibit A Exhibit B Exhibit C Exhibit D Exhibit E Exhibit F Exhibit G Exhibit H Exhibit I Dugway Interceptor Drawings Dugway West - Existing Regulator Information Dugway East Interceptor Relief Sewer Posted Contract Documents Dugway West Interceptor Relief Sewer Advanced Facility Plan Report Dugway West Interceptor Relief Sewer Advanced Facility Plan Drawings Dugway Storage Tunnel Advanced Facility Plan Report Dugway Storage Tunnel Advanced Facility Plan Drawings Doan Valley Storage Tunnel Advanced Facility Plan Report Doan Valley Storage Tunnel Advanced Facility Plan Drawings Page 2 of 48

3 1.1 PROJECT BACKGROUND 1.0 INTRODUCTION Description of the Existing Dugway Interceptor System The Dugway Interceptor system consists of two main service areas, the Dugway East and the Dugway West. The Dugway East includes the Main Branch, Eddy Branch, and Locke Branch. The Dugway West is comprised of Main Branch D and Main Branch E. Please see Figure 1-1 for the alignment of the sewers. Existing drawings and regulator information of these facilities are provided in Exhibits A and B. The existing Dugway Interceptor connects at the Easterly Interceptor near East 109 th Street. The interceptor (24-30 ) extends south paralleling the concrete culvert near Glenview Avenue. The sewers (18 on each side of the culvert) cross Dupont Avenue near East 107 th Street and proceed south crossing Elk Avenue near East 107 th Street, then crossing Glenville Avenue to East 106 th Street and then south on East 106 th Street and crossing St. Clair Avenue. The sewers parallel East 106 th Street, continue south, crossing Helena Avenue. At East 107 th Street, the sewers parallel Parkwood Drive southeast to Linn Drive near Kimberly Avenue. The sewers (15 on each side of the culvert) run down Linn Drive to Primrose Avenue. The interceptor sewers (12 on each side of the culvert) continue just south of Primrose Avenue and head southeast, crossing East 112 th, East 113 th, and East 114 th Streets. The sewer (12 ) then continues south between Carolina Road and Lakeview Roads to Superior Avenue. Page 3 of 48

4 Figure 1-1. Existing Dugway Interceptor General Description of the Easterly CSO Phase II Facilities Plan In 1998, the Northeast Ohio Regional Sewer District (NEORSD) undertook the Easterly CSO Phase II Facilities Plan (ECSO or ECSO Plan) to identify causes and develop solutions for the activation of combined sewer overflows (CSOs) in the Easterly service district. A system of conveyance and storage facilities were identified to capture combined sewage for treatment in accordance with the United States Environmental Protection Agency (EPA) CSO Policy and the Ohio EPA CSO Control Strategy. The first step taken by the District to implement the Easterly CSO plan was to advance the major CSO control systems to preliminary design. This effort, called the Easterly Advanced Facilities Plan (AFP), has the following components. Page 4 of 48

5 Connector Sewers and Interceptor Relief Storage Tunnels, including associated drop structures Easterly Tunnel Dewatering Pump Station Euclid Creek Pump Station Upgrade The Easterly storage tunnel system will consist of three tunnels Euclid Creek/Dugway (ECT/DST), Doan Valley (DVT) and Shoreline (SST). The Dugway Storage Tunnel (DST) segment of the ECT/DST is a 24-ft diameter rock tunnel that will capture and store CSO from the Dugway Brook areas, as well as a portion of the CSO originating from the Collinwood Interceptor service area. The Doan Valley Tunnel (DVT) is a 17-ft diameter dry-weather conveyance rock tunnel that will also have the capability to store CSO flows during storm events. After storms subside, the captured flows are released by gravity to the proposed Dugway West Interceptor Relief Sewer (DWIRS) system. The DWIRS will connect to the Dugway East Interceptor Relief Sewer (DEIRS) system and convey flow to the Easterly Interceptor for treatment at the Easterly Wastewater Treatment Plant (EWWTP). The DEIRS Posted Contract Documents are provided in Exhibit C. The shallower Shoreline Storage Tunnel (SST) is a 21-ft diameter soft ground tunnel that will capture CSO from the outfalls along the Lake Erie shoreline from downtown to the downstream shaft near Dugway Brook. The Euclid Creek Tunnel (ECT) is a 24-ft rock tunnel that will capture CSO from the balance of the Collinwood Interceptor. The DST and ECT are connected at their downstream shafts and their storage capacities are shared to control CSO outfalls from outer service areas. The downstream ends of DST and ECT are connected to the Easterly Tunnel Dewatering Pump Station (ETDPS) located at the Nine Mile Creek Site. After each storm event, when treatment capacity becomes available at the EWWTP, the pump station begins dewatering operations into the Easterly Interceptor for ultimate wastewater treatment at the plant. These tunnel projects, in conjunction with numerous diversion structures, conveyance conduits, drop shafts, and regulator modifications, all act in unison to provide the necessary CSO level of control for the Easterly drainage basin as established in the consent decree. The DWIRS is related to the ECT/DST in that flow diversion structures from these interceptor relief systems will divert flows to the tunnel system as depicted in the attached exhibits General Description of the Dugway West Interceptor Relief Sewer The DWIRS Advanced Facility Plan (Exhibits D & E) provides preliminary design information for the DWIRS system. The relief sewer addresses many wet weather conveyance needs. The DWIRS consolidates regulator structures. The Page 5 of 48

6 DWIRS also provides conveyance for the 5-year, 6-hour storm in the Dugway West service area as well as conveyance to the DST of combined sewage exceeding the capacity of the interceptor. The DWIRS also enables the DVT to empty dynamically during and after storm events by gravity optimizing the sizing of the DVT and eliminating the need to pump captured CSO. The main facilities included in the DWIRS system are illustrated in Figure 1-2, and consist of: A relief sewer with diameters of 66-inches to 108-inches Modifications to 44 existing regulators, and associated connector sewers to convey flow to the DWIRS system. Three diversion structures which redirect existing combined sewer overflows via new CSO conveyance conduits to the storage tunnel drop structures Three new regulating structures to provide wet weather relief overflows to the Dugway Brook West Branch Culvert One flow divider which splits flow between the DWIRS and a new Diversion Structure Page 6 of 48

7 Page 7 of 48

8 Table 1-1. Diversion, Regulator and Flow Divider Structure Functions ECSO AFP Name Location Function Name DW-1 DWD-1 East 110th Street north of Diversion Structure Glenview Avenue DW-2 DWF-1 East 109th Street and St. Clair Flow Divider Avenue DWD-2 St. Clair Avenue and Lakeview Diversion Structure Road DWR-1 Helena Avenue and East 107th Regulator Structure Street DWR-2 Linn Drive north of Willowmere Regulator Structure Avenue DW-3 DWD-3 Primrose Avenue and Linn Drive Diversion Structure DWR-3 Superior Avenue and East 120th Street Regulator Structure The upstream section of the DWIRS will commence at Tunnel Shaft DVT-1 where flows from Regulator Structure DWR-3 and the DVT will be diverted into a proposed 108-inch sewer. The DVT will release flows by gravity from its downstream shaft during and after a storm into the DWIRS. This configuration is beneficial because there is available capacity in the Easterly Main Interceptor at the downstream of the Dugway Interceptor system and the storage volume of the DVT can therefore be optimized to its current 17-foot diameter size. From Tunnel Shaft DVT-1, it will be necessary to tunnel the 108-inch sewer along Lakeview Road for a distance of 2,198 feet in rock to Manhole MH 37 located at the intersection of Lakeview Avenue and Primrose Avenue. A mining shaft will be located in an open lot at the northwest corner of this intersection, 67 feet beyond Manhole MH 37. The interim tunneled segment between MH 37 and the tunneling shaft will be abandoned after the construction of Manhole MH 37 is complete. Regulator Structure DWR-3 will be constructed on the existing 84-inch brick storm water outlet (SWO) from Regulator D-58 located at the intersection of Superior Avenue and East 120 th Street. The DWIRS runs in a northwesterly direction to Primrose, turning west on Primrose, Avenue, north on Linn Drive, continuing on East 109 th Street, continuing on Glenview Place, and alongside East 110 th Street to Junction Chamber No. 1 on the Dugway East Interceptor Relief Sewer. Page 8 of 48

9 The DWIRS will include the construction of seven new structures; three diversion structures, three regulator structures and one flow divider. Structure DWR-3 is the most upstream of the structures and DWD-1 is the furthest downstream. Diversion structure DWD-1 DWD-1, a proposed two-stage diversion structure, will be constructed on the DWIRS, with a 66-inch diameter dry weather outlet (DWO) and connections to the DST and the Dugway West Culvert. This structure will also receive flow from the 78-inch DWO of regulator D-61. The new 66-inch relief sewer will continue northeast to make a connection into the 5-foot diameter DEIRS. Flow divider DWF-1 A new flow divider will be constructed on the proposed DWIRS at the intersection of St. Clair Avenue and East 109th Street. DWF-1 will receive flows from the upsized DWO from regulator D-14 and the existing branches of the DWI. Flows up to CSO control will proceed north via the 66-inch DWO. Flows greater than this control level will be diverted east along St. Clair Avenue to DWD-2 through a 60-inch pipe. Diversion structure DWD-2 A diversion structure will be located on St. Clair Avenue, approximately 213 east of East 109th Street and designed to accept flow from DWF-1. This structure will have a 48-inch connection to the DST for flows up to CSO control, and a 60-inch connection to the Dugway East Culvert for flows greater than CSO control. Regulator structure DWR-1 This regulating structure will be constructed near the intersection of Helena Avenue and East 107th Street, at the existing location of regulator D-19. The current SWO of regulator D-16 and an upsized DWO from regulator D-17 will be utilized to deliver flows into this structure. Flows from the existing branches of the DWI as well as the flows from D-19 will be diverted into DWR-1. This structure will then convey flows up to CSO control to the DWIRS and have an overflow connection to the Dugway West Culvert. Page 9 of 48

10 Regulator structure DWR-2 DWR-2 will be constructed on the DWIRS on Linn Drive north of Willowmere Avenue and will receive flow from the existing branches of the DWI. Flows up to CSO control will proceed north through the 66-inch DWO. Flows higher than the level needed for CSO control will be diverted to the Dugway West Culvert. Diversion structure DWD-3 This diversion structure will be constructed on the DWIRS at the intersection of Primrose Avenue and Linn Road. Flows from the new Doan Relief Sewer as well as flows from regulators D-37, D-38, and D-39 will be diverted in to the new relief. Underflows will continue north on Linn Road through the 66-inch DWO. Higher flows, up to the CSO control level, will be diverted to a drop shaft on the DST system, located near the intersection of Primrose Avenue and Lakeview Road. Flows greater than the level required for CSO control will be diverted to the Dugway West Culvert. Regulator Structure DWR-3 Regulator structure DWR-3 will be constructed on the 84-inch brick SWO from Regulator D-58. This structure is located at the intersection of Superior Avenue and East 123rd Street. The DWO from Regulator D-58 will be bulkheaded, thus diverting all interceptor flow into the new sewer. The Dugway West Interceptor Relief Sewer Advanced Facility Plan Report (Exhibits D & E) is divided into nine additional technical sections, which includes the following: Section 2.0 provides a summary of the existing geological conditions, as identified in the Geologic Data Report (GDR) and evaluated in the Geotechnical Design Memorandum (GDM). Section 3.0 provides the hydraulics and operational issues of the DWIRS, including tributary area, capacity, sewer design data, and odor control. Section 4.0 provides the design issues for the diversion, regulator and flow divider structures, including hydraulic controls and design criteria. Section 5.0 presents a summary of required regulator modifications to divert flow to the DWIRS. Section 6.0 provides the design issues for the connecting conduits and relief sewers. A narrative description of each facility is also provided. Section 7.0 presents construction recommendations regarding work area requirements, impacts to existing utilities, traffic and the environment. The required property easements and acquisitions are also identified. Page 10 of 48

11 Section 8.0 presents a summary of the Engineer's estimate of probable cost. This section also identifies the assumptions made, the basis of cost, and specifically excluded items. Section 9.0 presents an outline of the specifications that may be required during final design. Section 10.0 provides requirements for final design and identifies various issues that need to be included in the final design of this project. The Dugway Storage Tunnel Advanced Facility Plan Report/Drawings (Exhibits F & G) and the Doan Valley Storage Tunnel Advanced Facility Plan Report/Drawings (Exhibits H & I) are all included with this RFP. The West Branch of the Dugway Interceptor sewershed consists of approximately 770 acres of tributary combined sewer system. The recommended DWIRS alternative consists of approximately 10,600 feet of relief conveyance sewer. Through modifications at 44 regulators, the construction of diversion structures and various new connector sewers, dry and wet weather flow will be introduced to the DWIRS. Table 1-2 lists the locations where flows are introduced to the DWIRS. Table 1-2. Flow Inputs to the DWIRS Connection Size Connection Origin (in.) Station Regulator D Elk Avenue Connector (Regulators 24 D-04, D-05, D-06, D-08, D-09) Regulator D-14, St. Clair Ave at 48 DWF Helena Avenue Connector 66 (Regulators D-16, D-17, D-19) at DWR Regulator D Interceptor Flow at DWR Regulator D Regulator D Regulator D Regulator D Regulator D Regulator D Interceptor flow at MH Regulator D Page 11 of 48

12 Regulator D-37 at DWD Regulators D-38 and D Connector at DWD Doan Relief Sewer at DWD East 112 th Connector (Regulator D ) East 113 th Connector (Regulator D ) Regulator D East 114 th Connector (Regulators D and D-43) Regulator D Regulator Structure DWR-3 54 Sanitary flows to the proposed DWIRS system were developed during the Easterly CSO Phase II Facilities Planning, and are based on collection system flow data used to calibrate the hydraulic model (Metcalf & Eddy, 1998). The calibrated flows were checked for reasonableness against the maximum population projections for the service area during the 20-year planning period. These wastewater flows generated by the hydraulic model were varied based on an hourly diurnal pattern typical of residential/light commercial areas. The final design shall evaluate dry weather flows to the DWIRS more extensively. The final design must provide adequate capacity to deliver wet weather flows to the Easterly Main Interceptor and the ECT/DST and also maintain minimum required flow velocities, as described later in this section. After the completion of the AFP, the NEORSD engaged in negotiations with the US Department of Justice, the Ohio EPA and the US EPA to finalize the long term CSO control plan through a consent decree. As part of these negotiations the control of the tunnels were modified to include delivery of the largest peak storm in a typical year, TY Storm 60, to the storage tunnels. This allowed the systems to control an additional overflow in a typical year, but also requires that the consolidation and drop systems have adequate capacity to deliver these flows. Therefore, the flows identified in Table 3.4 of the Dugway West Interceptor Relief Advanced Facilities Plan Report need to include Storm 60. This will be provided to the consultant when the models are updated and run to include this flow regime. This is expected to occur prior to the notice to proceed. The District is evaluating the use of green infrastructure as an alternative CSO control method in the Doan Valley sewershed, as well as the sewersheds in the Dugway and Euclid Creek storage tunnel systems. The evaluation will identify opportunities for reduction of stormwater entering the combined sewer system and subsequent reduction in the size and/or elimination of gray infrastructure. The tentative findings of this evaluation Page 12 of 48

13 and potential impacts to flow and infrastructure in the Doan Valley and Dugway Brook systems will be supplied to the selected consultant by July 15, Infiltration was also quantified for each metering basin during the Easterly CSO Phase II Facilities Planning Project (Metcalf & Eddy, 2002). The quantity of infiltration was estimated based on the flow monitoring data, and defined as being equivalent to approximately 90 percent of the minimum daily dry weather flow observed. An independent estimation of infiltration was performed by determining the total length of sewers, grouped by diameter, in the metering basin and applying an infiltration factor based on the type of pipe joints and age of the system. This independent analysis served as a check to determine, and confirm that the results obtained from the flow monitoring analysis were reasonable. Since the proposed DWIRS diverts flow from the existing interceptor system, this infiltration flow from the existing collection system was included in the basis of design of the proposed system. However, infiltration directly into the proposed sewer was not included in the basis of design. Since few pipe joints will be present in the new sewer, infiltration into the proposed system will likely be minimal and negligible in comparison to the wet weather flows present in the combined system. Total dry weather flow consists of both sanitary flow and dry weather infiltration. Table 1-3 presents a summary of average dry weather flows introduced to the DWIRS. Table 1-3. Average Dry Weather Flows Average Dry Connection Station Origin Weather Flow (cfs) Regulator D-61 at DWD Elk Avenue Connector 0.3 (Regulators D-04, D-05, D-08, D-09) Regulator D-14, St. Clair at 0.4 DWF Helena Avenue Connector 10 (Regulators D-16, D-17, D- 19) at DWR Regulator D Interceptor Flow at DWR Regulator D Regulator D Regulator D Regulator D Regulator D Regulator D Page 13 of 48

14 Interceptor Flow at MH Regulator D Regulator D-37 at DWD (est) Regulators D-38 and D Connector at DWD Doan Relief Sewer at DWD East 112th Connector 0.4 (Regulator D-40) East 113th Connector 0.1 (Regulator D-41) Regulator D East 114 th Connector 0.1 (Regulators D-42 and D-43) Regulator D Regulator Structure DWR-3 (Regulator D-58) AVAILABLE INFORMATION If the Consultants request to examine relevant documents not already provided as an exhibit to this RFP, they will be made available at the District s Administrative Office for examination upon request. To schedule an appointment to examine relevant District documents, contact Mr. Brian Page by calling Ext or ing at pageb@neorsd.org. Page 14 of 48

15 2.0 SCOPE OF SERVICES The scope of work for the DWIRS project shall consist of, but not be limited to, the tasks as outlined below. Upon completion of the design, the project will be advertised for construction as per Ohio Revised Code (ORC) requirements. The District will not entertain design-build for the completion of this work. The tasks as described are the preferred project organization of the District. The Consultant should base its proposal on the described tasks. The selected consultant shall provide all engineering services necessary to develop and produce a complete detailed design package that will culminate in a bidding package for the DWIRS. The Consultant shall work with Engineering & Construction Department and Operation & Maintenance Department personnel who will indicate system needs and assist in achieving the District s desired scope of work. The Consultant shall carefully consider the input by the District s staff, but based on the Consultant s own experience and ability, shall be solely responsible to provide a complete and workable design package in accordance with the requirements of the scope of work. The Consultant should be familiar with the exhibits discussed in Section 1.0 and included in this RFP. For the evaluation of options (Task 1 Pre-Design) for the DWIRS project, the Project Scope will include development of various alternatives as presented in the DWIRS AFP Report. Under the Project Scope, the Consultant shall include all considerations necessary for development. Considerations of alternatives that the Consultant would like to present in the proposal are to be presented as requested in Section 2.2 of this RFP, ALTERNATES TO THE PROJECT. 2.1 SCOPE OF SERVICES FOR PROJECT The scope of work for the DWIRS Project includes the following tasks Task 1: Pre-Design All Task 1 deliverables shall be submitted in the following formats and quantities: 5 hard copies bound and indexed appropriately 1 indexed PDF electronic copy 1 original electronic application format copy Page 15 of 48

16 Task 1A: Project Management Plan Within 30 days of the Notice-to-Proceed the Consultant shall provide a detailed Project Management Plan that includes critical processes and management activities that ensure compliance with the project design, schedule, and risk and budget requirements. Included in the management plan will be the following items: Team integration discuss the project management team responsibilities, assigning of activities, and integration of the design team to meet project objectives and program standards. Budget and schedule management include description of task tracking activities and critical path earned value scheduling format and systems. Submit monthly cash flow projections, including utilization and cash flow for sub-consultants and SBEs, in Primavera P6 cost loaded schedule, as required in Section of this RFP. Progress reporting include project management instructions for measuring performance and reporting completion status including a look back, look forward and critical issue resolutions. QA/QC description of the project quality assurance and quality control systems recommended to manage quality related problems and/or owner reviews of design deliverables and bid documents. Technical review board (TRB) include a description of need and cost/benefit for a TRB for a project of this complexity and magnitude and relative design discipline support to manage critical design decisions. SBE subcontracting plan include the process description for analyzing subcontracting work opportunities for small businesses once the design elements are defined to a point where these work activities can be defined. Cost estimates include confirmation that Consultant understands the cost estimating guidelines and identification of software systems and process to develop the estimates. Risk management - include a description of the consultant s risk management plan considering all project related risks and mitigation measures to alleviate those risks. This should include confirmation that Consultant understands program management risk register requirements Page 16 of 48

17 and method for developing and maintaining this register as a main design support tool Task 1B: Basis of Design Report The Consultant shall prepare a Basis of Design Report for the DWIRS that summarizes the Pre-Design work activities and critical design decisions to support advancement of the project into detailed design. The design parameters for the selected option shall be described in the Basis of Design Report. This document will also support the independent Value Engineering session to be held at the conclusion of the 30% Design subtask Task 1C: Route Identification Identify various routes for the DWIRS. For each route, identify the pick-up points, and the horizontal alignment of the DWIRS. For each potential route, identify and describe the surface features, underground utilities, underground structures, and topographic features through or around which the relocated interceptor will be constructed Task 1D: Construction Methods Identify the construction method(s) that will be suitable along the route associated with that alternative. If more than one construction method can be used for an alternative, break the alternative into multiple sub-alternatives Task 1E: Surveying For the Options Evaluation, perform surveying as necessary to determine the horizontal and vertical constraints of the selected alignment. Identify all existing utilities both vertically and horizontally. Obtain sufficient surface elevation data along the alignment to ascertain the required depths of excavation and available ground cover. Identify public and private property, bridges, buildings, other structures, and water bodies that will impact or be impacted by each alternative. For the Basis of Design Report, the Consultant shall survey to the extent described below: Locate critical elevations and establish a reference benchmark circuit for all construction. Page 17 of 48

18 Perform all research and procure all information necessary to establish existing right-of-way, property, and existing easement lines. Perform spot survey checks to verify the accuracy of the topographic mapping. Utility Tracking Form: In areas of expected excavation, the Consultant shall conduct an Ohio Utility Protection Service (OUPS) search and identify existing utility locations. The Consultant will be required to maintain a detailed utility tracking form to record and document all data collected with respect to line and grade conflicts. All locations/elevations are to be referenced to the State Plane Coordinate System Task 1F: Permits and Easements Identify permits and approvals required by public and private entities, including but not limited to the City of Cleveland, Army Corps of Engineers, Ohio EPA (Permit to Install, storm water construction, etc.), ODOT, and railroads. Also identify easements, rights of entry, license agreements and any other types of access agreements that will be required through public or private property. When developing schedules, take into account the time required to obtain such permits and property access rights Task 1G: Geotechnical Investigation Soil borings and rock cores shall be obtained along the proposed route as necessary to assess the suitability and cost of the construction methods associated with each alternative. The number of borings and cores is expected to be less than that required for final design. The Consultant may also utilize existing geotechnical data as appropriate. Consultant shall select and coordinate the services of a subcontractor to perform all soil borings, rock corings, and pavement corings; take all soil and rock samples; install any necessary instrumentation; and provide all testing services required for the development of geotechnical reports. It will be the responsibility of the Consultant to ensure that the boring subcontractor properly notifies all affected parties and secures any needed permits prior to commencing work, fills all bore holes with grout upon completion of boring work, and restores each site to a condition equal to or better than that which was originally encountered. All boring locations must be photographed prior to commencing Page 18 of 48

19 boring activities. Each photograph must be properly labeled with a minimum of the date, boring identification number, street address and city. Photographs shall be bound and presented to the District. Filled or final core boxes shall be photographed prior to removal from the boring site. Soil samples taken from the borings shall be properly stored and preserved to prevent or minimize moisture change and shall be delivered to the District for storage upon completion of all analysis. Consultant shall also select and coordinate the services of a sub-consultant who specializes in geotechnical consulting to prepare preliminary and final geotechnical reports. Should the lead consultant firm be able to perform these geotechnical duties in-house, a detailed resume of the individual(s) who will be involved will be required in the proposal, and the proposed individual(s) will need to be able to demonstrate sufficient expertise to be considered qualified. The geotechnical professionals and the lead firm shall mutually determine the parameters of a soil boring program for the project areas, including prescribing the necessary tests and evaluating the resulting data. The geotechnical professionals on the team shall designate the location for each boring, be present when it is being drilled and classify all samples. The geotechnical team members shall prepare interpretive geotechnical reports as necessary to address the criteria for the alternatives analysis and as necessary to support the design. Such reports may include, but are not necessarily limited to, evaluation of the subsurface materials discovered and the conditions which a construction contractor could expect to encounter; appropriate construction techniques; support requirements; slope stability analysis; and impact of surface and subsurface conditions on cost and risk. It will be the geotechnical professional s responsibility to assure the accuracy of the reports Task 1H: Hydraulic Analysis It is anticipated that hydraulic modifications may be needed due to DEIRS asbuilt conditions and potential consent decree changes. A hydraulic modeling specific allowance will be established during negotiations Task 1I: Green Opportunities Evaluation of the use of green infrastructure as a supplemental CSO control method for the DWIRS and the identification of opportunities for reduction of stormwater entering the combined sewer shall be considered throughout the design contract. Findings from the ongoing Green Infrastructure Study will be provided relative to any potential alternatives that may impact the hydraulics of the DWIRS system prior to July 15, Page 19 of 48

20 Task 1J: Schedule For the Options Evaluation, determine the duration of construction for each alternative. To the extent possible, outline the critical path for major design and construction tasks. For the Options Evaluation and the Basis of Design Report, identify the dependency on other factors for each alternative. Throughout the project, the Consultant must provide a critical path, cost-loaded project schedule that meets the milestone requirements described in Section 4.0 of this RFP Task 1K: Construction Cost Estimates In the Basis of Design Report, the Consultant shall include a Class 5 estimate in accordance with the Association for the Advancement of Cost Engineering (AACE) International Recommended Practice 18R-97 for each option Task 1L: Coordination with Other Entities Take into consideration all past, present and future work of other public and private entities. Some of the entities and projects for which coordination will be necessary are identified in Section 1.0 of this RFP; however, the Consultant shall assume that coordination will not be limited to those entities and projects Task 1M: Risk Analysis Perform a risk analysis for each alternative. Identify environmental risks, safety risks and economic risks. Identify short-term and long-term risks, including those risks associated with the period proceeding implementation of the alternatives, construction risks, and risks following implementation of the alternatives. Describe the consequences and likelihood of occurrence of each identified risk. Identify the means of mitigating the risks as well as the cost of mitigation. The risks and associated likelihood of occurrence as well as impact of occurrence will be summarized in a risk register. The risk register template will be provided by the District. Page 20 of 48

21 Task 1N: Community Impact Assessment The Consultant shall prepare a Community Impact Assessment, with the intent of identifying potential short-term impacts to the community during construction, and long-term impacts that arise as a result of the installed asset. Impacts are considered to be both positive and negative in nature. This project will require all components of the Level 1 and Level 2 Assessments as well as applicable components of the Level 3 Assessment. Level 1 Assessments: Typically underground repairs and improvements to existing assets, in existing easements and right-of-ways, does not expand the footprint of the existing asset to a significant extent and construction is shortterm (less than 6 months) in duration. Level 1 Assessments will typically focus on impacts to local residents (noise, dust, odors, loss of parking, access, inconvenience, etc.); impacts to businesses; places of worship; public agency (i.e. fire, police, schools, Rapid Transit Authority, refuse collection) services; vegetation, pedestrian and vehicular traffic patterns, etc. during construction. Level 2 Assessments: Repairs and improvements that significantly expand beyond the footprint of the original asset, or expand the easement or right-ofway to include community areas not previously impacted by the installation of the original asset. Will also include new aboveground structures and projects of longer term duration (greater than 6 months). Level 2 Assessments will typically include all Level 1 Assessment requirements; however, may also include aesthetic impacts from aboveground structures; potential economic impacts to local businesses; long-term changes to traffic patterns, road degradation, changes in land use, emergency response and other impacts due to long-term construction, and changes or additions to permanent aboveground structures. Level 3 Assessments: Typically new aboveground structures on green field sites where impacts to the community will be permanent from significantly altering the physical condition of the site. Level 3 Assessments may include requirements of Levels 1 and 2 Assessments as applicable; however, typically will include impacts to community socioeconomic conditions; alter future land use plans, land valuations, require future security plans, and other more permanent changes to the community. Page 21 of 48

22 Deliverables: The Consultant will provide a level of specificity in the Assessment (specific names of business impacted, type of impact, term of impact, residential addresses, agencies, community profiles and other community entities impacted), so that the Assessment can be developed into an actionable Community Relations and Communication Plan by the Owner in support of the project. The Assessment will provide a general description of the impacted area, specific areas of impact and evaluate the level of impact to each entity impacted. The assessment will also include maps, drawings, study information, supporting documentation and references in support of the Public Impact Assessment. The Consultant s Assessment will be provided to the Owner as a section within the 30%, 60% and 90% design phase submittals, as the Assessment evolves with additional site and public impact information. Elements of the Assessment may be included in the bid documents, at the Owner s discretion. Meetings: The consultant will be expected to attend both internal and external meetings in support of the project. These meetings may include; internal design reviews, contract reviews, Board meetings, internal informational meetings and public meetings Task 2: Design The Consultant shall develop drawings and specifications and integrate the District s Division 1 and Bid Booklet (including Instructions to Bidders, General Terms and Conditions, Special Conditions, Agreement) for the DWIRS project to produce a construction bid document suitable for competitive bidding purposes. The contract drawings will indicate the layout, plans, sections, and details of the DWIRS. All specifications shall be prepared with the CSI 2004 format. All drawings shall be prepared using AutoCAD All construction cost estimates shall be prepared according to the guidelines contained in the AACE International Recommended Practice No. 18R-97. Throughout the progress of the design, the geotechnical professionals on the project team shall continue to provide all geotechnical data and interpretation necessary to design the project. All Task 2 deliverables shall be submitted in the following formats and quantities: 10 hard copies bound and indexed appropriately 1 indexed PDF electronic copy Page 22 of 48

23 1 original electronic application format copy Task 2A: 30% Design The 30% percent design submittal will serve as the initial layout for review of the DWIRS to be advanced into further design levels. At this stage, the design shall incorporate major design concepts and shall be reflective of decisions made to date. The 30% submittal shall include, at a minimum, the following: Drawings including title sheet, drawing index, plan and section/profile drawings, flow diagrams, site plans, and other conceptual information using the District s sheet format and numbering system. Preliminary technical specifications of major equipment Revised basis of design Revised risk register Quality assurance report Construction cost estimate SBE analysis Value engineering services and report, including technical response by the Consulting recommending acceptance or rejection Design review meeting Quality Assurance/Quality Control Report The Consultant shall issue a QA/QC Report that includes the following: Summary of Consultant s internal design review comments, proposed responses and review staff documented on a review template provided by the District. Explanation of significant differences that may exist between the predesign basis of design report and the 30% basis of design report Construction Cost Estimate The Consultant shall issue along with the 30% design submittal an AACE Class 3 construction cost estimate. Three copies and one PDF electronic copy shall be submitted to the District s Project Manager. Page 23 of 48

24 SBE Analysis In concert with the development of the construction cost estimate, Consultant shall analyze areas where Small Business Enterprise contractors certified with the District can be utilized and recommend a SBE percentage goal for the construction project. A suggested template will be provided by the District for the Consultant s use Value Engineering Services The VE Study will be conducted when the design of the DWIRS is approximately 30% complete but prior to the 30% Design Review Meeting. A summary of the information discussed in the VE meeting shall be presented in the 30% Design Review Meeting. A firm that specializes in VE studies will conduct the VE Study. It is the responsibility of the Consultant to submit appropriate VE team members to the District for review and to schedule the VE meeting. The VE firm and team members will then be jointly selected by the Consultant and the District. A specific allowance in the amount of $100, will be included in Task 2A for the VE Consultant services, the Consultant s response services, and the Consultant s drawing revision services suggested by the VE Study and authorized by the District. The allowance funds contained in Task 2A will only be used with the written authorization of the Director of Engineering and Construction. The District will negotiate the actual scope of work and cost requirements for these services, on an as required basis Design Review Meeting The Consultant shall organize and lead a District attended 30% Design Review Meeting to explain their design as necessary and to receive and discuss comments regarding the design. The Consultant s Project Manager and key lead staff representing the various disciplines shall be in attendance for the review. All documents that comprise the 30% submittal shall be delivered to the District 10 working days in advance of the meeting. The Consultant shall submit an agenda containing critical issues for discussion three days prior to the meeting and shall prepare and submit meeting minutes to the District s Project Manager within four days after the meeting. The District shall provide written review comments on a District template. The Consultant shall record District comments made at the meeting and enter Page 24 of 48

25 them into the review template provided by the District. Within 10 working days of the review meeting the Consultant shall respond to the District comments contained on the review template, and the review template shall be submitted to the District Project Manager. The Consultant s QA/QC review staff shall be available by phone to answer any questions regarding their review Task 2B: 60% Design The 60% design submittal will serve as a detailed presentation of the design configurations and parameters established in the Pre-Design and 30% Design Tasks. The 60% submittal shall include, at a minimum, the following: Drawings including title sheet, drawing index, plan and section/profile drawings, flow diagrams, site plans, and other conceptual information using the District s sheet format and numbering system. Draft specifications for all equipment and major work items Revised basis of design Geotechnical Data Report Revised risk register Quality assurance report Construction cost estimate Revised SBE analysis Summary of VE recommendations incorporated by the Consultant into the contract documents Design review meeting Quality Assurance/Quality Control Report The Consultant shall issue a revised QA/QC Report that includes: Summary of Consultant s internal design review comments, proposed responses and review staff documented on a review template provided by the District. Summary of the Consultant s constructability review including inter and intra discipline coordination review Explanation of significant differences that may exist between the 30% basis of design report and the 60% basis of design report. Page 25 of 48

26 Construction Cost Estimate The Consultant shall issue along with the 60% design submittal an AACE Class 2 construction cost estimate Geotechnical Services The geotechnical program begun during the pre-design task shall be advanced during the design task, including all necessary borings, rock cores, testing, and analysis. The final boring logs shall be the result of the data gathered in the field and lab during the pre-design and design tasks. The logs shall be incorporated into a geotechnical data report Surveying The Consultant shall establish the baseline survey to which the DWIRS location and all geometrics will be referenced. This includes the following work: Locate critical existing utilities and pertinent property corners from the baseline survey. Field locate and identify topographic details within an agreed upon boundary for the project site. Provide services needed to fully describe and detail the planimetric drawings. Utility tracking form: Update the utility tracking form with any new or revised information obtained since the Basis of Design report was developed Permits and Easement Documents The consultant shall assist in preparation of permits required by public and private entities and coordination with those entities. If elements of work require temporary or permanent easements, the Consultant will be required to identify and coordinate these easements with the District. If required, the Consultant shall prepare legal descriptions, calculations and plats for all necessary permanent and temporary easements, which may be needed during construction. Preparation of these easement documents shall be included in the total negotiated price. This Page 26 of 48

27 includes surveying services in the event that it becomes necessary to field locate the proposed re-rerouted interceptor, appurtenances, easement limits, etc., and the time spent in meetings with property owners Maintenance of Traffic Plans Prepare maintenance of traffic plans to provide a safe work space for the contractor to perform the construction of the proposed project. The design shall meet the requirements of the local municipality and the Ohio Manual of Traffic Control Devices for Streets and Highways SWPPP Prepare a Storm Water Pollution Prevention Plan (SWPPP) using the District standard template form if more than one (1) acre is planned to be disturbed. The consultant shall prepare the Stormwater Pollution Prevention Plan and supporting documents as may be required to obtain a Notice of Intent permit from the Ohio EPA and local stormwater permitting regulations. The consultant shall provide all documentation pursuant to the standards as provided in the Ohio Department of Natural Resources Rainwater and Land Development Code ; latest edition. Please see Attachment I Task 2C: 90% Design The 90% percent design submittal will serve as the pre-final design submittal that details all aspects of the project decided during the previous submittal reviews and monthly meetings. The 90% submittal shall include, at a minimum, the following: All drawings checked for interdisciplinary coordination. Cross checked bid sheets, Division 1 and other Bid Booklet documents (provided by the District) coordinated with the bid package All technical specifications Revised basis of design Revised risk register Quality assurance report Construction cost estimate Revised SBE analysis Draft geotechnical baseline report Design review meeting Page 27 of 48

28 Quality Assurance/Quality Control Report The Consultant shall issue a revised QA/QC Report that includes: Summary of Consultant s internal design review comments, proposed responses and review staff documented on a review template provided by the District. Summary of the Consultant s final constructability review including inter and intra discipline coordination review Summary of Front end, Division 1 and technical specification coordination review. Explanation of significant differences that may exist between the 60% design basis of design report and the 90% basis of design report Construction Cost Estimate The Consultant shall issue along with the 90% design submittal an AACE class 2 construction cost estimate Geotechnical Baseline Report A draft geotechnical baseline report shall be prepared and included in the 90% design submittal. The draft report shall be a near final version of the report. Revisions to the report after the 90% submittal should consist only of changes necessary to correlate with revisions to the final design or changes due to reassessment of risk assignment. The final geotechnical baseline report shall contain the evaluation of the subsurface materials discovered and the conditions which the construction contractor can expect to encounter. In addition, the geotechnical baseline report shall include discussion of dewatering, appropriate construction techniques and support requirements necessary to properly construct this project. It will be the geotechnical professional s responsibility to assure the accuracy of the reports. Should the Consultant be able to perform these geotechnical duties in-house, a detailed resume of the individual(s) who will be involved are required in the Consultant s proposal. The proposed staff member(s) shall have a minimum five (5) years of recent geotechnical experience to be considered qualified Task 2D: Final Design The final design will be represented in the documents to be used for bidding purposes. This includes final drawings, specifications, cost estimates, and Page 28 of 48

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL CSO 049 and 050 RELOCATION (C49/50R) WBS NO. CIP.CL.E.1272 July 2011 This Request for Proposal (RFP) is being sent to interested engineering firms for predesign, design, bidding, construction

More information

REQUEST FOR PROPOSAL EASTERLY SECONDARY SYSTEM IMPROVEMENTS (ESSI) WBS NO. TP.E January, 2011

REQUEST FOR PROPOSAL EASTERLY SECONDARY SYSTEM IMPROVEMENTS (ESSI) WBS NO. TP.E January, 2011 REQUEST FOR PROPOSAL EASTERLY SECONDARY SYSTEM IMPROVEMENTS (ESSI) WBS NO. TP.E. 1255 January, 2011 This Request for Proposal (RFP) is being sent to interested engineering firms for predesign, design,

More information

Consent Decree Appendix 1. Control Measures and Performance Criteria

Consent Decree Appendix 1. Control Measures and Performance Criteria Case: 1:10-cv-02895-DCN Doc #: 2-2 Filed: 12/22/10 1 of 6. PageID #: 82 United States and State of Ohio v. Northeast Ohio Regional Sewer District Consent Decree Appendix 1 Control Measures and Performance

More information

Reducing Overflows using a Baffling Solution. OWEA AWWA 2014 Technical Conference & Expo August 28, 2014 Columbus, Ohio

Reducing Overflows using a Baffling Solution. OWEA AWWA 2014 Technical Conference & Expo August 28, 2014 Columbus, Ohio Reducing Overflows using a Baffling Solution OWEA AWWA 2014 Technical Conference & Expo August 28, 2014 Columbus, Ohio 1 Presented by: Steve Janosko, P.E. Project Manager Tony Margevicius, P.E. Vice President

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL SOUTHERLY WASTEWATER TREATMENT CENTER Maintenance Building Exterior Wall Panel Restoration (WPR-1) And Southerly WWTC Buildings Assessment Study WBS NO. CIP.TP.S.1187 October 2009

More information

LIMITED ENVIRONMENTAL REVIEW For. Northeast Ohio Regional Sewer District. Kingsbury Run Preliminary Engineering Early Action CSO CS

LIMITED ENVIRONMENTAL REVIEW For. Northeast Ohio Regional Sewer District. Kingsbury Run Preliminary Engineering Early Action CSO CS LIMITED ENVIRONMENTAL REVIEW For Kingsbury Run Preliminary Engineering Early Action CSO CS391430-0133 Applicant: Ms. Kyle Dreyfuss-Wells, Chief Executive Officer 3900 Euclid Avenue Cleveland, Ohio 44115

More information

REQUEST FOR PROPOSAL GRAVITY THICKENING IMPROVEMENTS (SFP-36-1) WBS NO. CIP.TP.S May 2011

REQUEST FOR PROPOSAL GRAVITY THICKENING IMPROVEMENTS (SFP-36-1) WBS NO. CIP.TP.S May 2011 REQUEST FOR PROPOSAL GRAVITY THICKENING IMPROVEMENTS (SFP-36-1) WBS NO. CIP.TP.S.1231 May 2011 This Request for Proposal (RFP) is being sent to interested engineering firms for predesign, design, bidding,

More information

Hydraulic Modeling of Deep Tunnel Provides Cost Savings

Hydraulic Modeling of Deep Tunnel Provides Cost Savings 5 Hydraulic Modeling of Deep Tunnel Provides Cost Savings Taymour El-Hosseiny, Karen Reinhart and M. P. Cherian In 2005, the City of Columbus, Ohio submitted a plan to the Ohio Environmental Protection

More information

REQUEST FOR PROPOSAL. Customer Inquiry Tracking Planning and Implementation Project Phase I March 25, 2014

REQUEST FOR PROPOSAL. Customer Inquiry Tracking Planning and Implementation Project Phase I March 25, 2014 REQUEST FOR PROPOSAL Customer Inquiry Tracking Planning and Implementation Project Phase I March 25, 2014 This Request for Proposal (RFP) is being sent to consulting firms to act as the Consultant in the

More information

Request for Proposals. 42nd Avenue Pump Station Rehabilitation. Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403

Request for Proposals. 42nd Avenue Pump Station Rehabilitation. Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 42nd Avenue Pump Station Rehabilitation Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 May 24, 2015 The City of San Mateo (City) is accepting proposals to select a qualified

More information

RECITALS TERMS AND CONDITIONS. The scope of work is contained in Exhibit A, attached hereto and incorporated herein.

RECITALS TERMS AND CONDITIONS. The scope of work is contained in Exhibit A, attached hereto and incorporated herein. FIFTH AMENDMENT TO MASTER CONTRACT FOR PROFESSIONAL SERVICES FOR WASTEWATER TREATMENT PLANT ENGINEERING FINAL DESIGN SERVICES FOR THE DURHAM ADVANCED WASTEWATER TREATMENT FACILITY PRIMARY TREATMENT AND

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Project Identification Project Name: Elyria East Side Relief Sewer Phase 1B South (CS390337-0018), Phase 1C (CS390337-0014), Phase 1D (CS390337-0017) Applicant: The Honorable Holly

More information

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES 1 PURPOSE... 3 2 PROJECT DESCRIPTION... 5 3 PROJECT COMMON AND PROJECT GENERAL TASKS... 6 4 ROADWAY

More information

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR DESIGN OF RECHARGE BASIN ON VICTORIA SITE General Provisions Western Municipal Water District (WMWD) requests a qualified Design Consultant

More information

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017 Attachment 1 Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017 Sanitary Sewer System Master Plan Summary Points - City s sanitary system

More information

Exhibit A Mn/DOT Contract No

Exhibit A Mn/DOT Contract No Exhibit A Mn/DOT Contract No. 98142 SCOPE OF WORK AND DELIVERABLES Preliminary Design Red Wing US 63 Bridge and Approach Roadways State Project (SP) 2515-21 SCOPE OVERVIEW... 2 SCHEDULE... 2 PROJECT TASK

More information

REQUEST FOR PROPOSAL. SOUTHERLY WASTEWATER TREATMENT CENTER PRIMARY TREATMENT IMPROVEMENTS (SFPI 2) WBS No.:CIP.TP.S.

REQUEST FOR PROPOSAL. SOUTHERLY WASTEWATER TREATMENT CENTER PRIMARY TREATMENT IMPROVEMENTS (SFPI 2) WBS No.:CIP.TP.S. REQUEST FOR PROPOSAL SOUTHERLY WASTEWATER TREATMENT CENTER PRIMARY TREATMENT IMPROVEMENTS (SFPI 2) WBS No.:CIP.TP.S.1227 January 2010 This Request for Proposal (RFP) is being sent to interested engineering

More information

Cost Estimating Framework

Cost Estimating Framework Cost Estimating Framework Water and Wastewater Master Study Prepared by: GM BluePlan Engineering for: Project No. 717022 TABLE OF CONTENTS 1 Introduction... 1 2 Cost Estimation Framework... 2 2.1 Approach

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions City Utilities operates the largest municipally-owned wastewater collection and treatment system in Indiana. The system serves 161 square miles and includes 1,014 miles of sanitary sewer lines, 365 miles

More information

Semi Annual Progress Report No. 6

Semi Annual Progress Report No. 6 Combined Sewer Overflow (CSO) Long Term Control Plan Consent Decree Case 1:10 CV 02895 DCN Semi Annual Progress Report No. 6 January 26, 2015 January 26, 2015 NEORSD Semi Annual Progress Report No. 6 Period

More information

SECTION TEMPORARY SEWER BYPASS PUMPING

SECTION TEMPORARY SEWER BYPASS PUMPING PART 1 GENERAL 1.1 DESCRIPTION A. The CONTRACTOR shall provide a complete sewer bypassing system including, but not limited to, the following: 1. Developing a sewer bypassing plan 2. Developing a spill

More information

Maximizing Your Investment

Maximizing Your Investment Maximizing Your Investment City of Lorain Collection System Optimization Eliminates SSOs Ohio Water Environment Association June 24, 2015 Mary Garza City of Lorain Laura McGinnis, P.E. ARCADIS Tim Ruggaber,

More information

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design Request for Proposals Hillsdale Pedestrian/Bicyclist Bridge Design Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 JUNE 13, 2013 The City of San Mateo (CITY) is accepting

More information

Technical Memorandum No. 1

Technical Memorandum No. 1 DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Serving the Public Protecting the Environment Technical Memorandum No. 1 Multi-Jurisdictional Use Facilities Capital Cost Allocation DRAFT April 17, 2013

More information

EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS June 27, 2017

EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS June 27, 2017 EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS 21-17 June 27, 2017 TO: RE: Invited Firms Request for Submittals to El Paso Water - Public Service Board (EPWater) Statement of Work Professional

More information

Northeast Ohio Regional Sewer District. Submittal Requirements for Connections to the Combined Sewer System

Northeast Ohio Regional Sewer District. Submittal Requirements for Connections to the Combined Sewer System Northeast Ohio Regional Sewer District Submittal Requirements for Connections to the Combined Sewer System Guidelines for Review and Approval Requests for connection approval are required for all new development

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Project Identification Project: Cleveland E. 185 th Street & Marcella Road Relief Sewer (Phase 1) Applicant: Robert L Davis, Director of Public Utilities City of Cleveland 12302

More information

Allegheny County Sanitary Authority (ALCOSAN)

Allegheny County Sanitary Authority (ALCOSAN) Allegheny County Sanitary Authority (ALCOSAN) REQUEST FOR QUALIFICATIONS for PROFESSIONAL SERVICES WET WEATHER PLANT EXPANSION CONSTRUCTION MANAGEMENT CAPITAL PROJECT NO. S 430 January 2018 1.0 INTRODUCTION

More information

Western Municipal Water District Request for Proposals (RFPs) Professional Services for La Sierra Pipeline Project

Western Municipal Water District Request for Proposals (RFPs) Professional Services for La Sierra Pipeline Project Page 1 of 11 Western Municipal Water District Request for Proposals (RFPs) Professional Services for La Sierra Pipeline Project Western Municipal Water District (WMWD) invites the submittal of written

More information

REQUEST FOR STATEMENT OF QUALIFICIATIONS FOR WATER SOURCE RAW WATER TRANSMISSION MAIN

REQUEST FOR STATEMENT OF QUALIFICIATIONS FOR WATER SOURCE RAW WATER TRANSMISSION MAIN REQUEST FOR STATEMENT OF QUALIFICIATIONS FOR WATER SOURCE RAW WATER TRANSMISSION MAIN FOR CITY OF SIDNEY SIDNEY, OHIO PROPOSALS TO BE RECEIVED AT THE OFFICE OF THE PUBLIC WORKS DIRECTOR 201 WEST POPLAR

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Highway / Utility Guide

Highway / Utility Guide Oregon Department of Transportation Highway Division Right of Way Section Highway / Utility Guide Railroad & Utilities Unit Right of Way Section STATEMENT OF PURPOSE It is important to understand that

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 2-1 Issue date: September 2012 1. General SITEWORK OVERVIEW This Directive outlines the Fund s requirements for the Consultant relative to the development, design and presentation of documents

More information

PROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing

PROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing Project Description PROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing The Siphon 1 River Crossing project consists of replacing an existing aerial pipe crossing

More information

APPENDIX A TECHNICAL SPECIFICATIONS. Engineering Services for the East Grid - Pump Station Upgrade Program DESCRIPTION OF SCOPE OF SERVICES

APPENDIX A TECHNICAL SPECIFICATIONS. Engineering Services for the East Grid - Pump Station Upgrade Program DESCRIPTION OF SCOPE OF SERVICES 159-18 APPENDIX A TECHNICAL SPECIFICATIONS Engineering Services for the East Grid - Pump Station Upgrade Program DESCRIPTION OF SCOPE OF SERVICES GENERAL CONSULTANT agrees to provide Engineering Services

More information

12 DRAINAGE General Administrative Requirements Standards

12 DRAINAGE General Administrative Requirements Standards 12 DRAINAGE 12.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with drainage, including culverts, bridge hydraulics, roadway ditches, and closed storm

More information

LIMITED ENVIRONMENTAL REVIEW. Northeast Ohio Regional Sewer District, Southerly Electrical Infrastructure Improvements SEII/1401A

LIMITED ENVIRONMENTAL REVIEW. Northeast Ohio Regional Sewer District, Southerly Electrical Infrastructure Improvements SEII/1401A LIMITED ENVIRONMENTAL REVIEW Project Identification Project: Applicant: Loan Number: Northeast Ohio Regional Sewer District, Southerly Electrical Infrastructure Improvements SEII/1401A Ms. Kyle Dreyfuss-Wells,

More information

DESIGN CRITERIA PACKAGE

DESIGN CRITERIA PACKAGE RFQ: 17-C-00002 DESIGN-BUILD SERVICES FOR THE Upper Peninsula Watershed Drainage Improvements Dale Mabry/Henderson Trunkline DESIGN CRITERIA PACKAGE PREPARED BY: JAMES E. JACKSON, AIA CITY ARCHITECT CONTRACT

More information

THE MUNICIPALITY OF SIOUX LOOKOUT

THE MUNICIPALITY OF SIOUX LOOKOUT THE MUNICIPALITY OF SIOUX LOOKOUT CONSULTANT TERMS OF REFERENCE TO PREPARE DETAILED DESIGN FOR PARK STREET LANE INFRASTRUCTURE UPGRADES IN URBAN SIOUX LOOKOUT RFP R013-2017 July 21, 2017 Terms of Reference

More information

Work Breakdown Structure Element Dictionary Preliminary Engineering

Work Breakdown Structure Element Dictionary Preliminary Engineering Element Name Initiation PE 3.1 Initiation includes the implementation of the project s funding and notification of the consultant or in-house design staff to commence work, the Kickoff Meeting with the

More information

PROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ)

PROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) PROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) MARCH 2018 INTRODUCTION AND BACKGROUND The City of Keller is in search of the most qualified firms to provide professional expertise and

More information

Design and Construction of Local Public and Private Sewers and Ancillary Facilities

Design and Construction of Local Public and Private Sewers and Ancillary Facilities Chapter 2 Design and Construction of Local Public and Private Sewers and Ancillary Facilities Subchapter I - General 2.101 Purpose...1 2.102 Applicability...1 2.103 Electronic data...1 2.104 Effect of

More information

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements 4.0 Introduction The requirements presented in this section shall be used to aid the design engineer or applicant in the preparation of drainage reports, drainage studies, and construction drawings for

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Final Design Guideline

Final Design Guideline Final Design Guideline May, 2016 July, 2011 Check the Capital Project Delivery website to ensure this is the current version Table of Contents Purpose... 1 Introduction... 1 FD Support... 1 Roadway and

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS Village of La Grange Phase II Design Engineering Services for Submission Deadline: No later than 10:00 am on October 19, 2018 Published on: October 5, 2018 on the Village of

More information

The South Hartford Conveyance and Storage Tunnel

The South Hartford Conveyance and Storage Tunnel The South Hartford Conveyance and Storage Tunnel South Hartford The Metropolitan District June 16 th -17 th, 2015 Purpose of This Public Meeting Communicate with Residents Directly Adjacent to the Project

More information

CRWP NERRS Science Collaborative Site Selection Criteria & Scoring System CHAGRIN RIVER WATERSHED PARTNERS, INC.

CRWP NERRS Science Collaborative Site Selection Criteria & Scoring System CHAGRIN RIVER WATERSHED PARTNERS, INC. CHAGRIN RIVER WATERSHED PARTNERS, INC. NATIONAL ESTUARINE RESEARCH RESERVE SYSTEM SCIENCE COLLABORATIVE GRANT Implementing Credits and Incentives for Innovative Stormwater Management REQUEST FOR PROPOSALS

More information

3.9 times the average 3.8 times the average 3.6 times the average

3.9 times the average 3.8 times the average 3.6 times the average ARTICLE VI DESIGN OF SANITARY SEWERS M'RSMIN. VOL.281 JA 2 4 2001 IMAGE; Section 601 Determination of the Amount of Sewage for Sanitary Sewers A. MSD Design Standards for estimating sanitary sewage flow

More information

Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River

Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River Sanitation District No. 1 of Northern Kentucky Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River Ohio WEA Collection Systems Workshop May 5, 2011 Sanitation District No. 1

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR: SE 9 TH STREET STORMWATER PUMP STATION Activity ID

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR: SE 9 TH STREET STORMWATER PUMP STATION Activity ID REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR: E 1 ST STREET & E MARKET STREET STORMWATER PUMP STATION Activity ID 01-2016-025 SE 9 TH STREET STORMWATER PUMP STATION Activity ID 01-2016-026 SE 1 ST STREET

More information

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves

More information

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

WEF Collection Systems Conference 2017

WEF Collection Systems Conference 2017 Davenport, Iowa 14th District Diversion Study Karol Giokas, P.E., RJN Group Tom Leabhart, P.E., Davenport, IA ABSTRACT The 14 th District sanitary sewer basin in Davenport, Iowa has high levels of inflow

More information

PROJECT UNDERSTANDING

PROJECT UNDERSTANDING Exhibit A 2012 Sewer Interceptor Condition Assessment Project Scope of Basic Services PROJECT UNDERSTANDING The City of Reno (City) has approximately 754 miles of Sanitary Sewer pipelines ranging from

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED METROPOLITAN COUNCIL ENVIRONMENTAL SERVICES ST. LOUIS

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS Floodplain Restoration and Wetland Creation 12/12/18 This Request for Qualifications (RFQ) is made available to interested consulting firms for professional design and implementation

More information

DRAFT SCOPE 1.0 General Requirements

DRAFT SCOPE 1.0 General Requirements DRAFT SCOPE 1.0 General Requirements This section outlines a general list of the responsibilities and requirements for the GEC. It is anticipated that the GEC will be used to support and supplement MnDOT

More information

CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS

CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS C-44 Reservoir/STA System Discharge Project RFB: 6000000620 Addendum No. 1 March 2014 CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS HDR Engineering, Inc. SECTION 02401 DEWATERING, COFFERDAM AND BYPASS

More information

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT:

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT: AGENDA HEADING: Unfinished Business AGENDA REQUEST COMMISSION MEETING DATE: June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell AGENDA ITEM NO: VI.2. Originating Department SUBJECT: Department

More information

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm

More information

STATE OF NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION DIVISION OF COASTAL ENGINEERING

STATE OF NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION DIVISION OF COASTAL ENGINEERING INDEX OF DRAWINGS SHEET NO. DESCRIPTION 1 TITLE SHEET AND LOCATION PLAN 2 GENERAL NOTES AND SITE ACCESS AND STAGING AREA LAYOUT 3 EXISTING CONDITIONS AND DEMOLITION PLAN 4 CONSTRUCTION PLAN AND PROFILE

More information

SCOPE 1.0 General Requirements

SCOPE 1.0 General Requirements SCOPE 1.0 General Requirements This section outlines a general list of the responsibilities and requirements for the GEC. It is anticipated that the GEC will be used to support and supplement MnDOT staff

More information

STATEMENT OF PRINCIPLE

STATEMENT OF PRINCIPLE 2011 STATEMENT OF PRINCIPLE It is important to understand that this Guide is a "baseline". Each organization should develop and utilize its own approach to the "baseline". The success of the Guide is predicated

More information

Any discussions or marketing activities related to this specific project.

Any discussions or marketing activities related to this specific project. 04-11-19 Posting Date South Sandusky Street Widening and Relocation PID No. Not Assigned City of Mount Vernon Response Due Date: 04-24-19 Communications Restrictions Please note the following policy concerning

More information

UNIT: ROAD MAINTENANCE & OPERATIONS

UNIT: ROAD MAINTENANCE & OPERATIONS COUNTY OF FRESNO PS&E/CONSTRUCTABILITY REVIEW CHECKLIST UNIT: ROAD MAINTENANCE & OPERATIONS I certify that a thorough and complete constructability review has been performed by my staff: Signature of Functional

More information

CHAPTER 4 SYSTEM DESIGN CRITERIA

CHAPTER 4 SYSTEM DESIGN CRITERIA INTRODUCTION CHAPTER 4 SYSTEM DESIGN CRITERIA Adequate design of the District s wastewater conveyance facilities requires the determination of the quantity of wastewater from contributing sources. The

More information

8. APPROVAL AND DEDICATION OF PROJECTS WITH PUBLIC SEWERS [Amended. See Section 16]

8. APPROVAL AND DEDICATION OF PROJECTS WITH PUBLIC SEWERS [Amended. See Section 16] 8. APPROVAL AND DEDICATION OF PROJECTS WITH PUBLIC SEWERS [Amended. See Section 16] 8.010 General The District will accept for dedication, all public sewers, pump stations and sewerage treatment facilities

More information

2018 Sanitary Sewer Overflow and Reduction Program (SSORP) Engineering Design Services Small Diameter

2018 Sanitary Sewer Overflow and Reduction Program (SSORP) Engineering Design Services Small Diameter 2018 Sanitary Sewer Overflow and Reduction Program (SSORP) Engineering Design Services Small Diameter Antonio Leyva, P.E. Engineering Manager Marisol V. Robles Manager SMWVB Program Stella Manzello Contract

More information

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac)

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac) Permit Application No.: 17-181 Rules: Erosion Control, Wetland Protection, and Waterbody Crossings & Structures Applicant: Hennepin County Received: 4/27/17 Project: CSAH 112 Phase II Complete: 9/5/17

More information

2. DEFINITIONS. American Association of State Highway and Transportation Officials.

2. DEFINITIONS. American Association of State Highway and Transportation Officials. 2. DEFINITIONS 2.010 Definitions [See Amendment 2] In addition to words and terms that may be defined elsewhere in this manual, the following words and terms shall have the meanings defined below: AASHTO:

More information

STORM DRAINAGE DESIGN MANUAL

STORM DRAINAGE DESIGN MANUAL Appendix I STORM DRAINAGE DESIGN MANUAL by: SUNGATE DESIGN GROUP, P.A. GEN ERAL DESIGN STAN DARDS AN D POLICIES 1. STREET AND LOCAL DRAINAGE Discharge estimates for specified design storms shall be calculated

More information

Chapter 3 Previous Studies

Chapter 3 Previous Studies Chapter 3 Previous Studies The Vista Grande stormwater conveyance system and watershed area has been evaluated in a number of reports and studies for the CCSF, the Daly City and San Mateo County over the

More information

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System INSTRUCTIONS: This form shall be completed and submitted (in duplicate)

More information

10.0 Storm Sewer Systems

10.0 Storm Sewer Systems October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and

More information

Long-Term CSO Control Plan for North Dorchester Bay and the Reserved Channel

Long-Term CSO Control Plan for North Dorchester Bay and the Reserved Channel Massachusetts Water Resources Authority Long-Term CSO Control Plan for North Dorchester Bay and the Reserved Channel Frederick A. Laskey Executive Director March 8, 2004 How Sewer Separation Works 2 How

More information

EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS February 5, 2019

EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS February 5, 2019 EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS 25-19 February 5, 2019 TO: RE: Invited Firms Request for Submittals to El Paso Water - Public Service Board (EPWater) Statement of Work Professional

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS DESIGN / ENGINEERING TEAM RIVERFRONT TOWN CENTER Town of Shallotte 106 Cheers Street, PO Box 2287 Shallotte, North Carolina 28459 Deadline for Submittal: February 9, 2018 at

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

Outfall at Lagoon between Lake of the Isles and Lake Calhoun

Outfall at Lagoon between Lake of the Isles and Lake Calhoun Outfall at Lagoon between Lake of the Isles and Lake Calhoun Prepared for City of Minneapolis April 17, 2013 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601

More information

S.O.P. No. HMD

S.O.P. No. HMD Page: 1 of 9 PURPOSE: To establish (SOP) for submission requirements, review process and approval of applications for Non-vehicular Access Permits for the purpose of connection or discharge to any MassDOT

More information

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN Financial Project ID: 417069-1-32-04 Work Program Item No.: N/A Federal Aid Project ID: County/Section No.:

More information

I. Project Overview and Limits. Project Goal

I. Project Overview and Limits. Project Goal Scope of Work and Deliverables for Subsurface Utility Engineering (SUE) for both Underground and Overhead Utilities on T.H. 10, and its Connecting Roads under S.P. 8001-40 I. Project Overview and Limits

More information

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY Project #08223 CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY PREPARED FOR: City of Crystal Lake 100 West Woodstock Street Crystal Lake, Illinois 60014 FEBRUARY 11, 2009 26575 W. COMMERCE DRIVE, SUITE 601,

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project

Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Bernie Ashyk 1, Christopher Lucie, P.E. 2, Jeffrey LeBlanc, P.E. 3 1 Shook Walbridge JV, Project Manager;

More information

Yorkton Rona Commercial and Industrial development. Concept Plan and Serviceability Report

Yorkton Rona Commercial and Industrial development. Concept Plan and Serviceability Report Yorkton Rona Commercial and Industrial development Concept Plan and Serviceability Report Prepared for: 101242326 Sask Ltd. Box Ft Quappelle, SK Canada S0G 1S0 Prepared by: Stantec Consulting Ltd. 302-1345

More information

Case 1:85-cv RGS Document 1792 Filed 12/16/13 Page 1 of 11. UNITED STATES DISTRICT COURT for the DISTRICT OF MASSACHUSETTS

Case 1:85-cv RGS Document 1792 Filed 12/16/13 Page 1 of 11. UNITED STATES DISTRICT COURT for the DISTRICT OF MASSACHUSETTS Case 1:85-cv-00489-RGS Document 1792 Filed 12/16/13 Page 1 of 11 UNITED STATES DISTRICT COURT for the DISTRICT OF MASSACHUSETTS UNITED STATES OF AMERICA, Plaintiff, CIVIL ACTION V. No. 85-0489-RGS METROPOLITAN

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

Items in this checklist identify the base requirements that are to be provided by the design professional.

Items in this checklist identify the base requirements that are to be provided by the design professional. The Project Manager or other Owner designee will serve as the Plan Reviewer. This checklist is to be completed by the Plan Reviewer on behalf of the Owner. The Plan Reviewer s role is to review the submitted

More information

Chapter 1 INTRODUCTION

Chapter 1 INTRODUCTION Chapter 1 Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 1.1 Introduction... 1 1.2 Preconstruction Division... 1 1.2.1 Regional Production Groups... 2 1.2.2 Preconstruction

More information

PEIRCE ISLAND WASTEWATER TREATMENT FACILITY UPGRADE

PEIRCE ISLAND WASTEWATER TREATMENT FACILITY UPGRADE REQUEST FOR QUALIFICATIONS CITY OF PORTSMOUTH NEW HAMPSHIRE Public Works Department ENGINEERING SERVICES PEIRCE ISLAND WASTEWATER TREATMENT FACILITY UPGRADE VALUE ENGINEERING REVIEW RFQ No. 59-14 City

More information

APPENDIX A TECHNICAL SPECIFICATIONS Engineering Services for the Twin Creeks RW Storage Tank and Booster Pump Station

APPENDIX A TECHNICAL SPECIFICATIONS Engineering Services for the Twin Creeks RW Storage Tank and Booster Pump Station APPENDIX A TECHNICAL SPECIFICATIONS 069-18 Engineering Services for the Twin Creeks RW Storage Tank and Booster Pump Station DESCRIPTION OF SCOPE OF SERVICES GENERAL The Twin Creeks project include the

More information

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP &

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP & TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP 4910-29 & 0504-14 Contract No. 1002252 Project Overview is in need of professional and technical assistance to provide detail design for State

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

DC Clean Rivers Project

DC Clean Rivers Project District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Briefing on: DC Clean Rivers Project Briefing for: Anacostia Watershed Restoration Partnership April 10, 2015 Agenda Background

More information

Assessing SWMM 5 Hydrologic Parameter Benefits for Model Calibration

Assessing SWMM 5 Hydrologic Parameter Benefits for Model Calibration Assessing SWMM 5 Hydrologic Parameter Benefits for Model Calibration Justin Siegrist, 1 Daniel Anderson, 2 Joseph Koran, 2 Mark Pribak, 3 Uzair M. (Sam) Shamsi 4 and Dave White 1 1 Wade Trim, Inc., Cincinnati,

More information

SCOPE OF WORK AND DELIVERABLES

SCOPE OF WORK AND DELIVERABLES 1.0 PROJECT OVERVIEW The State of Minnesota (State) has identified the need for the replacement of Bridge 5308, a railroad bridge that carries the Canadian Pacific Railroad (CP Rail) over Trunk Highway

More information

ATTACHMENT A STATEMENT OF WORK RAGGED MOUNTAIN DAM PROJECT

ATTACHMENT A STATEMENT OF WORK RAGGED MOUNTAIN DAM PROJECT PROEJECT UNDERSTANDING Background ATTACHMENT A STATEMENT OF WORK RAGGED MOUNTAIN DAM PROJECT The purpose of this work scope is to develop feasible alternatives for raising the existing Lower Ragged Mountain

More information