Fast and Furious Using 3D Design to Expedite Delivery of a New Brine Processing Facility
|
|
- Amos Pierce
- 5 years ago
- Views:
Transcription
1 Fast and Furious Using 3D Design to Expedite Delivery of a New Brine Processing Facility Prepared For AIPG EXPANDING WORLD OF UNCONVENTIONAL SHALE HYDROCARBON RESOURCES CONFERENCE Presented By Chad Roby, P.E. April 29, 2015
2 Agenda 3D Design What is 3D Design? 3D Platforms Advantages and Disadvantages Brine Processing Facility Project Overview Basis of Design Design Components 3D Design
3 What is 3D Design? 3D modeling is the process of developing a representation of any three-dimensional surface of an object using specialized software So what s Integrated 3D Design? Incorporating multiple engineering disciplines into one model o Process (piping, equipment, tanks, etc.) o Civil o Structural o Architectural o Mechanical o Electrical
4 BIM / 3D Platforms AutoDesk Plant 3D AutoDesk Revit Bentley AutoPlant
5 Benefits of using 3D Design Changes can be made in the model quickly and the 2D drawings readily updated, Enables conflicts to be identified and resolved more readily than in 2D. Industry experience has shown that 2D models are more prone to inter-discipline conflicts, Owner reviews are enhanced due to the ability to see what the final facility will look like, Project team coordination is reduced since the team can view everyone s design within a single platform, and 3D sections and layouts can be included in the plan set to give a comprehensive and detailed look at the design.
6 3D Design Disadvantages Trained Personnel Upfront time CAD Standard Compliance ours and owners
7 Treatment Tiers UIC Injection Well Reuse Zero Liquid Discharge
8 Confidential Client LLC formed by existing client Existing and permitted UIC Injection Well Schedule Nov 17, 2014 Notice to Proceed Nov 25, 2014 Survey Dec 01, 2015 Geotechnical Borings Two progress review meetings Jan 22, % Construction Documents
9 Process Mechanical Basis of Design 7,000 BBL/DAY Plan and allocate space for second well Total capacity of 14,000 BBL/DAY Flexibility to receive variety of fluids Environmental Compliance o Double Contained Pipeline o Containment wall with HDPE lining and leak detection o Air compliance o Records and Process Control
10 What s desired end result? TSS removal produces relatively clear water Coming In Going out Tier I Going out Tier II
11 Process Flow Diagram Oxidizer Oxidizer Truck Coarse Screens Settling / Flow Equalization Tanks Gunbarrel Tanks Storage Tanks Oil Recovery Anti-Scalant Sand Filters Bag Filters Cartridge Filters Injection Well Pumps UIC Well
12 Process Mechanical Truck Receiving Station with Canopy x 3 lanes Settling Tanks x 5 Gunbarrel Tanks x 2 Skim Oil Tank x 1 Storage Tanks x 2 5,600 SF Treatment Building Process Pumps Desander Multi-media filters Bag Filters Cartridge Filters High Pressure Injection Well Pumps
13 Process Mechanical Air Compliance Flame Arresters Vents of all tanks connected Detonation Arrester Flame Arrester Detonation Arrester
14 Process Mechanical Records and Process Control Meters Automation and Control Database Coriolis Mass Flow Meter
15 Survey and Geotechnical Survey Typical survey of site Tied into existing LiDAR topo from State Geotechnical Root fibers and organic material were noted throughout the fill materials, in addition to construction debris which included asphalt, brick, concrete, cardboard, plastic bags, rubber, rock, slag and wood fragments. Over-excavation or Drilled Shafts
16 Civil/Site Civil/Site Over-excavate Footers below or near approximate location of suitable fill Set tank farm and building at same elevation Incorporated radiation detection
17 Civil/Site FLEX Steel Pipeline Rated for 2,250 psi (ANSI 900) Reduced installation costs compared to API high pressure pipe 1,805 feet spools (4 ) splice sections together
18 Structural Truck Unloading Area Concrete Containment Wall Building Slab, Footers, and Stub wall Tank Foundations and Pad Considered Foam Tank Pads
19 3D Design
20 3D Design
21 3D Isometric
22 Plan, Section, and Isometric Views
23 Owner Reviews with 3D Vital tool during progress review meetings Used through-out detailed review meeting (plan set page turn)
24 Prefabricated Metal Building
25 Roy Stanley with a desander Tank Farm Plunger pump for injection Bag filter and cartridge filter
26 Roy Stanley UIC well Leak Detection Truck off load Screen readout for system
27 Questions? Chad Roby, P.E. PROJECT MANAGER / PROCESS ENGINEER CROBY@CECINC.COM
Permian & Anadarko Basin Produced Water Recycling: Keys to Success
Permian & Anadarko Basin Produced Water Recycling: Keys to Success J. Daniel Arthur, P.E., SPEC; David Alleman, Mark Faucher, Steve Tipton, P.E. Presented at: Ground Water Protection Council UIC Conference,
More informationCHAPTER 7 Building Information Modeling
CHAPTER 7 Building Information Modeling Dr Nabil Elsawalhi Associate Professor of Construction Management 1 Information and Communication Technology/ Building Information Modeling New approaches to construction
More informationInfiltration Guidelines
Appendix E Infiltration Guidelines As a stormwater management method, infiltration means retaining or detaining water within soils to reduce runoff. Infiltration can be a cost-effective method to manage
More informationWater Issues Relating to Unconventional Oil and Gas Production
Water Issues Relating to Unconventional Oil and Gas Production John Veil 410 212 0950 john@veilenvironmental.com www.veilenvironmental.com National Research Council Workshop on the Development of Unconventional
More informationWell Pad Automation Improves Capital Efficiency and Reduces Fiscal Risk Michael Machuca* Emerson Process Management
URTeC: 1874921 Well Pad Automation Improves Capital Efficiency and Reduces Fiscal Risk Michael Machuca* Emerson Process Management Copyright 2014, Unconventional Resources Technology Conference (URTeC)
More informationQuality management system. Environmental management system. Occupational health and safety management system.
Company Profile Gulf Rock Engineering Group was started in 1975 as a specialist blasting sub-contractor and has since developed into one of the Gulf regions leading earthworks and underground construction
More informationThermoflex Tubing! Reinforced Thermoplastic Gathering, Disposal and Injection Lines! Overview and Case Studies!!! December 17, 2009!
Thermoflex Tubing! Reinforced Thermoplastic Gathering, Disposal and Injection Lines! Overview and Case Studies!!! December 17, 2009!! Why Use Thermoflex Tubing! Corrosion Resistance/ Hydrocarbon Resistance!
More informationChoosing The Correct Flow Meters For Hydraulic Fracturing
WHITE PAPER Choosing The Correct Flow Meters For Hydraulic Fracturing INTRODUCTION Hydraulic Fracturing requires accurate and durable flow meters to monitor several processes during a fracking treatment.
More informationSweet Creek Road Retaining Wall Replacement. Mapleton, OR
Sweet Creek Road Retaining Wall Replacement Mapleton, OR Technical Information Project Completion Date: April 30, 2013 Project Location: Mapleton, OR Size of Project: 15,000 SF, 870 CY Concrete Strength
More informationCONDITIONAL USE APPLICATION Grand County Courthouse: 125 E. Center St. Moab, UT 84532; Phone: (435)
COMMUNITY DEVELOPMENT ENGINEERING & PLANNING CONDITIONAL USE APPLICATION Grand County Courthouse: 125 E. Center St. Moab, UT 84532; Phone: (435)259-1371 FOR OFFICE USE ONLY Date of Submittal: Conditional
More informationHolds a B. Sc. in Mechanical Power Engineering and has more than 12 years hands-on experience working in construction, maintenance and operation.
102762-MEC-CMO-E-2004 Team Leader Construction Engineer Holds a B. Sc. in Mechanical Power Engineering and has more than 12 years hands-on experience working in construction, maintenance and operation.
More informationA White Paper February System for piping global management
A White Paper February 2004 System for piping global management Page blank Table of contents Summary... 4 Modules... 5 Piping Classes... 6 Data Dictionaries 6 Tables 6 Piping Classes 7 Branch Tables 7
More informationREMTECH 2014 CONFERENCE TERVITA. Implementing Fully Integrated Waste Management Solutions Direct At Source in Oil Sands Operations.
REMTECH 2014 CONFERENCE TERVITA Implementing Fully Integrated Waste Management Solutions Direct At Source in Oil Sands Operations. 2014 AGENDA Tervita Integrated solutions for oil sands operations Waste
More informationImpoundments for Cost-Effective Recycling of Produced Water for Hydraulic Fracturing
Impoundments for Cost-Effective Recycling of Produced Water for Hydraulic Fracturing D. Steven Tipton, PE J. Daniel Arthur, PE, SPEC, and Gavin James, PE November 8-10, 2016 23 rd International Petroleum
More informationQUESTIONS & ANSWERS ITB HELEN MCCALL PARK IMPROVEMENTS
QUESTIONS & ANSWERS ITB 017-030 HELEN MCCALL PARK IMPROVEMENTS QUESTION: Site Lighting. The prints show that the existing site lighting structures are to be relocated on site. Is this the only site lighting
More informationWater Sourcing and Recycling in Oil & Gas Operations. Michael Sims, P.E. Technical Permitting, Oil &Gas Division Main Line:
Railroad Commission of Texas Water Sourcing and Recycling in Oil & Gas Operations Michael Sims, P.E. Technical Permitting, Oil &Gas Division Main Line: 512.463.3840 RRC Background Founded in 1891 to regulate
More informationPlaceholder for photo
Placeholder for photo Consultancy and Construction Firm 7500 staff worldwide, 1800 staff UK Water and Energy Bringing Our Global Unconventional Experience to the UK Hydrocarbon Strategy and Water/Brine
More informationMason s Training Programme on Onsite Treatment Systems
Mason s Training Programme on Onsite Treatment Systems Session: 2 Design of septic tank Do s & Don ts November 18, 2016 TECHNICAL SUPPORT UNIT: IN ASSOCIATION WITH: Groundwater table is high Which onsite
More informationMain Page The Company The Technology Safety Locks Electric Lifts. Air Lifts
Incorporated date: 1985 Location: Walled Lake, Michigan Lot size: Approximately 3 acres Building: Approximately 33,000 square feet Military Application Employees: 40 Strengths: ISO certified Long Term
More informationWARNING DO NOT BID ON THIS PROJECT
WARNING DO NOT BID ON THIS PROJECT Nick H. Strater, P.G., Associate, Brierley Associates, Bedford, NH Brian C. Dorwart, P.E., P.G., Sr. Consultant, Brierley Associates, Bedford, NH For projects advertised
More informationPOLLUTANT STORAGE CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
POLLUTANT STORAGE CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Revised September 14 The General Trade Knowledge portion of the examination is administered daily in Computer Based
More information659 VAN METER STREET CINCINNATI, OH Phone: Fax: Website:
659 VAN METER STREET CINCINNATI, OH 45202 Phone: 513. 241. 1230 Fax: 513. 241. 1287 Website: www.hixson-inc.com Email: info@hixson-inc.com IN-HOUSE EXPERTISE At Hixson, it is not enough to offer only a
More informationAttachment D-1: Civil/Structural Scope of Work
Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,
More informationImproved Fueling Platforms: Increased Velocity with Less Risk
Improved Fueling Platforms: Increased Velocity with Less Risk Gene Schubel Director Engineering Services BNSF Railway Company 4515 Kansas Avenue Kansas City, KS 66106-1199 913/551-4435 Mike Herzog Manager
More informationLIFE+ PROJECT - SEKRET LIFE12 ENV/IT/ "Sediment ElectroKinetic REmediation Technology for heavy metal pollution removal"
LIFE+ PROJECT - SEKRET LIFE12 ENV/IT/000442 "Sediment ElectroKinetic REmediation Technology for heavy metal pollution removal" DELIVERABLE ACTION B3 Validation report on installed plant VALIDATION REPORT
More informationHigh Density Polyethylene (HDPE) Lined Evaporation Ponds
High Density Polyethylene (HDPE) Lined Evaporation Ponds Presented by: Neil Nowak, PE Phone: 303-221-1719 Email: nnowak@scsengineers.com Website: scsengineers.com TOPIC OF PRESENTATION: Use of High Density
More informationEPA Greenhouse Gas Mandatory Reporting Rule. Onshore Petroleum & Natural Gas Production
EPA Greenhouse Gas Mandatory Reporting Rule Onshore Petroleum & Natural Gas Production Onshore Petroleum & Natural Gas Production Agenda 1.Applicability 2.Source Categories 3.BAMM Time Line 4.BAMM Request
More informationVapor Extraction / Groundwater Extraction (VE/GE) System Initial Report
Vapor Extraction / Groundwater Extraction (VE/GE) System Initial Report Gasoline Fueling Station Royal Farms #96 500 Mechanics Valley Road North East, MD 21901 MDE OCP Case No. 2011-0729-CE Facility ID
More informationSTANDARD SPECIFICATION Section Auger-Grout Injected Piles Civil Engineering Group Revised: August, 2000
DIVISION 2: SITE WORK SECTION 02320 AUGER-GROUT INJECTED PILES STANDARD SPECIFICATION PART 1 GENERAL 1.0 DESCRIPTION OF WORK This work shall include all excavation, concrete, equipment and accessories
More informationCase Histories. Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc.
Case Histories Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc. Cap Grouting Capping the top of the rock surface with grout to provide a barrier
More informationDivision Mandates. Supervise the drilling, operation, and maintenance of wells to prevent damage to life, health, property, and natural resources.
Division Mandates Supervise the drilling, operation, and maintenance of wells to prevent damage to life, health, property, and natural resources. Supervise and permit the owners/operators to utilize all
More informationSECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)
SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density
More informationOpportunities for Methane Emissions Reductions in Natural Gas Production. Technology Transfer Workshop. April 25, 2006 Villahermosa, Mexico
Opportunities for Methane Emissions Reductions in Natural Gas Production Technology Transfer Workshop PEMEX & Environmental Protection Agency, USA April 25, 2006 Villahermosa, Mexico Agenda Reduced Emissions
More informationClass II Saltwater Disposal Wells in Ohio: Understanding the Avenue to Success
Class II Saltwater Disposal Wells in Ohio: Understanding the Avenue to Success Authors: J. Daniel Arthur, P.E., SPEC, ALL Consulting Tom Tomastik, Geologist, ALL Consulting David Overstreet, Vice-President,
More informationCERTIFICATE OF APPROVED REGISTRATION J. T. BAKER CHEMICAL COMPANY. Sanitary Landfill. Harmony Township. Warren 2110B
State of New Jersey SOLID WASTE ADMINISTRATION BEATRICE S. TYLUTKI CERTIFICATE OF APPROVED REGISTRATION Under the provisions of N.J.S.A. 13:lE n as the Solid Waste Management Act, this registration is
More informationEnvironmental and Economic Considerations for Marcellus Natural Gas Development. Presented by Tom Murphy and Dave Yoxtheimer
Environmental and Economic Considerations for Marcellus Natural Gas Development Presented by Tom Murphy and Dave Yoxtheimer 1 Presentation Topics Marcellus Geology Water Management Hydrofracturing Process
More informationSummary of Advances: Frac Water Treatment and Hydrocarbon Recovery from Oil-Based Drilling Fluids
Summary of Advances: Frac Water Treatment and Hydrocarbon Recovery from Oil-Based Drilling Fluids Randy D. Horsak, PE Carl L. Brassow, PE JD KlarTek, LLC Houston, Texas USA Presented at Texas Association
More informationELLIOTT WAY IMPROVEMENTS
OWNER: THE VILLAGE OF CROTON-ON-HUDSON CROTON-ON-HUDSON TOWN HALL 1 VAN WYCK STREET CROTON-ON-HUDSON, NY 1050 ACTING VILLAGE MANAGER: JANINE KING LOCATION MAP SITE * COMMISSIONER OF PUBLIC WORKS: MARCO
More informationA tank filtration and settling system set up to dewater groundwater for excavation work near the Upper Truckee River.
4.5.1.3 DEWATERING DESCRIPTION Dewatering techniques are methods of addressing extracted ground or surface water encountered during construction. This temporary BMP addresses the installation and maintenance
More informationMeasurement Schematics & Facility Delineation Requirements Required by September 11, 2014
Alberta Energy Regulator (AER) Directive 017 - Measurement Requirements for Oil and Gas Operations Version - September 2012 Measurement Schematics & Facility Delineation Requirements Required by September
More informationFLOOR PANEL LAYOUT. The Ultimate Prefabricated Floor Panelling Software for Revit
FLOOR PANEL LAYOUT The Ultimate Prefabricated Floor Panelling Software for Revit OVERVIEW Floor Panel Layout Floor Panel Layout Floor Panel Layout a powerful product for planning floor panels and splitting
More informationGrouting Bilfinger Spezialtiefbau GmbH
Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com
More informationDesign And Construction Standards Manual Hilton
Design And Standards Manual Hilton Free PDF ebook Download: Design And Standards Manual Hilton Download or Read Online ebook design and construction standards manual hilton in PDF Format From The Best
More informationStanford University Global Climate & Energy Project. Methane Leakages from Completion of Unconventional Wells
Stanford University Global Climate & Energy Project Energy Supply with Negative Carbon Emissions GCEP Workshop Taku Ide June 15 th, 2012 Methane Leakages from Completion of Unconventional Wells 1 CH 4
More informationMUD ROTARY TECHNIQUES. MUD Rotary Drilling Method 12/11/2017. Roger E. Renner, MGWC MUD ROTARY DRILLING. Rotary Well Rig
Roger E. Renner, MGWC MUD ROTARY TECHNIQUES Presenter: Roger E. Renner Master Groundwater Contractor President of E.H. RENNER & SONS, INC. Past President of NGWA 2001 Past President of Minnesota Water
More informationDecreasing the Environmental Impact of Treating Slurry Waste Onsite by Mechanical Separation
Decreasing the Environmental Impact of Treating Slurry Waste Onsite by Mechanical Separation Craig Jones Applications Engineer Peter Bradshaw Account Manager Agenda BOS Solutions Overview Equipment Overview
More informationExperts in tunneling with Tunnel Boring Machines
www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution
More informationSECTION WASTEWATER FORCE MAINS
SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.
More informationLNG Terminal in Świnoujście. Mutual Joint Visit Workshop for Seveso Inspections 26 September 2017, Nicosia, Cyprus
LNG Terminal in Świnoujście Mutual Joint Visit Workshop for Seveso Inspections 26 September 2017, Nicosia, Cyprus Contents 1. Polskie LNG COMPANY PRESENTATION 2. LNG supply chain 3. Key technical parameters
More information703 - DRILLED SHAFTS SECTION 703 DRILLED SHAFTS
SECTION 703 DRILLED SHAFTS 703.1 DESCRIPTION Construct drilled shafts by the cased or uncased method depending upon site conditions and Contract Document requirements. BID ITEMS Drilled Shaft (*) (**)
More informationBackground. AEM Tier 2 Worksheet Farmstead Water Supply Evaluation. AEM Principle: Glossary
AEM Tier 2 Worksheet Glossary Casing: Steel or plastic pipe installed while drilling a well, to prevent collapse of the well bore hole and the entrance of contaminants, and to allow placement of a pump
More informationASPHALT CAPABILITIES & EXPERIENCE
ASPHALT CAPABILITIES & EXPERIENCE Portland, OR І Los Angeles, CA І Houston, TX І Denver, CO Norwest Engineering, a national-level engineering firm, has been providing consulting engineering and related
More informationNatural Gas STAR Methane Challenge Program: Supplementary Technical Information for ONE Future Commitment Option
Natural Gas STAR Methane Challenge Program: Supplementary Technical Information for ONE Future Commitment Option 1 Contents Introduction... 4 Methane Challenge Program Reporting... 4 Emission Sources...
More informationAquatech Energy Services
Aquatech Energy Services Upstream Oil & Gas Water Management Services Total Water Management Total Water Management For Oil & Gas Producers More Than 30 Years Experience Serving The Oil & Gas Industry
More informationSANKO GEOTHERMAL POWER PROJECT EFFLUENT MANAGEMENT PLAN
Draft A.0 January 10, 2018 Version Revision Date SANKO GEOTHERMAL POWER PROJECT Prepared by Checked by Approved by Muhsin Dervişoğulları Environmental Manager Project Manager General Manager of Geothermal
More informationAdvancing Technology in Well Completions & Stimulations
A N A D A R K O P E T R O L E U M C O R P O R A T I O N Advancing Technology in Well Completions & Stimulations Megan Starr-Powell Senior Reservoir Engineer 2-25-16 1 Anadarko s Mission & Values Anadarko
More informationEROSION CONTROL GENERAL NOTES EC JAN 2017 C.B.
EROSION CONTROL GENERAL NOTES EC - 000 EROSION CONTROL GENERAL NOTES EC - 001 INSTALL TEMPORARY DRIVEWAY CULVERT IF THERE IS A ROADSIDE DITCH PRESENT EXISTING PAVEMENT OR APPROVED ACCESS POINT OR AS PRACTICABLE
More informationLNG Terminal Equipment. Juan Manuel Martín Ordax
LNG Terminal Equipment Juan Manuel Martín Ordax Terminal equipment. General aspects The aspects considered are: o Main equipment used for cargo transfer are loading arms or hard arms, which are jetty based.
More informationMRI Chiller Installation Guidelines
MRI Chiller Installation Guidelines *These Items are the responsibility of the installing contractor to complete prior to the startup of the MRI Chiller.* **Please refer to DTS chiller manual for further
More informationABC Oil and Gas August 15th, 2016 Report No: SMP-0003 ABC Wellsite Chemical Injection Addition Powered by Solaris-MCI
ABC Oil and Gas August 15th, 2016 Report No: SMP-0003 ABC 08-16 Wellsite Chemical Injection Addition Powered by Solaris-MCI Contents Executive Summary 3 1.0 Assumptions 3 1.1. Napkin Assumptions 3 1.2.
More informationnalcofabtech.com A Nalco Champion Company
nalcofabtech.com A Nalco Champion Company 2 CONTENTS Goal Zero - Safety Culture...4 About Us...6 Capabilities...8 Services...24 Equipment and Facilities... 36 3 4 At Nalco FabTech, our programs ensure
More informationBIM Competency Delivers Competitive Advantages
Volume 9, Number 2 Summer 2014 The official publication of the PHCC Wisconsin Association and Master Plumbers/Heating & Cooling Contractors of Wisconsin BIM Competency Delivers Competitive Advantages INSIDE:
More informationFounded in 1996, Summit Industrial Construction, LLC is a merit shop, heavy industrial contractor. Summit
ABOUT US Founded in 1996, Summit Industrial Construction, LLC is a merit shop, heavy industrial contractor. Summit is licensed to perform industrial construction nationwide and holds R, S and U stamps
More informationArnfield and Godley WTW s are located in Tameside, south east of Manchester and form part of the Longdendale
Arnfield and Godley WTW water quality improvements scheme for United Utilities by Martin Clark Arnfield and Godley WTW s are located in Tameside, south east of Manchester and form part of the Longdendale
More informationFIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF
ARCHITECTURE & BUILDING ENGINEERING AEC COLLECTION EBOOK FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF Get started > 01 02 03 04 05 DELIVER HIGHER- QUALITY WORK OPERATE MORE EFFICIENTLY EXPAND YOUR BILLABLE
More information11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...
Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3
More informationYour defined goals and objectives:
About us GECO GmbH was founded in 1977 as a private owned business by Josef Schlusche ( 2005). The company headquarters are located in Ketsch near Heidelberg. HOME Our customers: Administrative building
More informationSECTION WASTEWATER FORCE MAINS
SECTION 02732 WASTEWATER FORCE MAINS PART 1 GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.
More informationNEMC Challenges of Managing Water in the Marcellus Play. Nick Inkenhaus Water Resources Engineer
NEMC Challenges of Managing Water in the Marcellus Play August 5, 2013 December 22, 2011 Nick Inkenhaus Water Resources Engineer Water Requirements for Marcellus Shale Completion typically requires 3-5
More informationPlunger pumps are used in a wide variety of
Kelly Eberle and Cajetan Ijeomah, Wood Group, Canada, outline a case study of vibration-induced cracks in a plunger pump piping system. Plunger pumps are used in a wide variety of applications, such as
More informationEnvironmental Plans and Procedures
ACC CULPEPER Environmental Plans and Procedures OMM and SWPPP Permit # VAG110315 16273 Allied Way Culpeper, Va. 22701 Contents OMM... 2 O&M practices for wastewater treatment... 2 Chemical and material
More informationThe experience in applying of static load and O-cell pile testing geotechnologies in problematical soil conditions of Astana
Japanese Geotechnical Society Special Publication International Mini Symposium CHUBU (IMS-CHUBU) The experience in applying of static load and O-cell pile testing geotechnologies in problematical soil
More informationLegacy Environmental Process, LLC 1445 Ashville Road, Suite 103 Leeds, Alabama In USA Fax:
Legacy Environmental Process, LLC 1445 Ashville Road, Suite 103 Leeds, Alabama 35094 In USA 1-205-640-1035 Fax: 1-205-640-1039 www.legacyenvpro.com Pre-Plant Delivery And Installation Manual For Project
More informationIRISH CEMENT PLATIN INVESTING IN OUR FUTURE
IRISH CEMENT PLATIN INVESTING IN OUR FUTURE INTRODUCTION Investing in our future. The next phase of investment in Platin will see further energy efficiency improvements with on site electricity generation
More informationBaker Hughes. The Eco-Centre. Heather Thomas Baker Hughes Incorporated. All Rights Reserved.
Baker Hughes The Eco-Centre Heather Thomas FES Service Portfolio Containment Solids Control CRI Filtration Drilling Waste Centrifuges Slurry Units Filter Presses Cuttings Shakers Tanks Cartridge Units
More informationUNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2015
Sheet 1 of 9 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2015 Delete SECTION 703 and replace with the following: SECTION 703 DRILLED SHAFTS 703.1 DESCRIPTION
More informationNon-intrusive wellhead surveillance to support brownfield production optimisation recent case studies
Non-intrusive wellhead surveillance to support brownfield production optimisation recent case studies Agenda Introduction Produce the Technical Limit Typical Sonar Applications Sonar Technology Case Studies
More informationSECTION NATURAL GAS DISTRIBUTION
SECTION 33 51 00 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph
More informationDesign Considerations for Full-Cycle Water Management Systems
Design Considerations for Full-Cycle Water Management Systems Ken Fairchild, PE Director Water Logistics Basic Energy Services Permian Basin Water in Energy Conference 22-Feb-2018 Preface - Responsible
More informationSection 4 - Design and Construction Overview
Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First
More informationWater Resource Management for Shale Energy Development
Water Resource Management for Shale Energy Development Presented by Dave Yoxtheimer, P.G. February 19, 2014 Bakken Shale Energy: A Global Play Well Site in Operation U.S. Natural Gas Production is Increasing
More informationMRI Chiller Installation Guidelines
MRI Chiller Installation Guidelines *These Items are the responsibility of the installing contractor to complete prior to the startup of the MRI Chiller.* **Please refer to DTS chiller manual for further
More informationCHAPTER IX RULES AND REGULATIONS FOR GRINDER PUMPS. A. "Department" means Concord Township Sewer Department.
CHAPTER IX RULES AND REGULATIONS FOR GRINDER PUMPS SECTION 1. DEFINITIONS OF TERMS USED IN THIS CHAPTER IX A. "Department" means Concord Township Sewer Department. B. "Engineer" means a licensed professional
More informationProject Name: Melut Basin Oil Development. Client Name: PDOC, Petrolium. Development Oman Company. EPC: Dodsal. Consultant: Mott MacDonald
Produced Water Treatment Project Profile Project Name: Melut Basin Oil Development Client Name: PDOC, Petrolium EPC: Dodsal Consultant: Mott MacDonald Plant Location: Adar/ Agordeed Field Scope: Design,
More informationChanges for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details
Changes for the 2017 TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details The following changes are made to the existing standards and details to clarify or improve existing information.
More information17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS
17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS 17.1 Description The work covered by this section of the specifications consists of furnishing all labor, the construction and installation of open storm drain
More informationThe U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study
Creative Construction Conference 2015 The U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study Miranda Griffin, Scott W. Kramer, Ph.D.* 118 M. Miller Gorrie Center, Auburn
More informationPLUMBING BUILDING SCOPE OF WORK
PLUMBING BUILDING SCOPE OF WORK 1. The Contractor shall furnish all supervision, materials, labor, equipment, tools, supplies, incidental items, including construction cleanup, etc for accomplishing the
More informationPAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV
NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435
More informationgeoexchange as an alternative energy source DESIGN APPROACHES
geoexchange as an alternative energy source DESIGN APPROACHES GEOEXCHANGE AN ALTERNATIVE ENERGY SOURCE T The earth provides the perfect heat exchange medium: harnessing constant, year-round temperatures
More informationLynx Products Overview and Application Manual
Lynx Products Overview and Application Manual Lynx Products are Designed and Manufactured by Clearflow Group inc. is a solution based organization, which has grown its core capabilities around the unique
More informationErrata for the 2003 Uniform Plumbing Code Study Guide (5th Printing)
Errata for the 2003 Uniform Plumbing Code Study Guide (5th Printing) The following is a list of changes that we found after the fifth printing of the 2003 Uniform Plumbing Code Study Guide. These changes
More informationSustainability in Shale Development EDSGN 100 Design Project, Fall 2016
Sustainability in Shale Development EDSGN 100 Design Project, Fall 2016 Project Objective Keeping sustainability and stewardship of the environment in mind, as well as the need to remain a safe and profitable
More informationIntroduction to Brownfields: Site Assessment and Cleanup
consulting engineers and scientists Introduction to Brownfields: Site Assessment and Cleanup Presented by: Barry Giroux, P.E., LEP, Senior Project Manager TAB Technical Assistance for Brownfields Team
More informationKORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No
000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20
More informationReport of Exploratory Test Pits
Report of Exploratory Test Pits UNF Transportation Projects Stockpile Investigation Osprey Ridge Road Extension Jacksonville, Florida CSI Geo Project No.: 71-17-135-20 Arcadis Project No.: JK017002.0001
More informationFracturing Overview: Fact vs. Fiction Andy Bond, Subsurface Manager December 8,
Fracturing Overview: Fact vs. Fiction Andy Bond, Subsurface Manager December 8, 2016 www.caelusenergy.com Agenda Brief History of Hydraulic Fracturing Why is Hydraulic Fracturing Used? Alaska Regulations
More information