Sweet Creek Road Retaining Wall Replacement. Mapleton, OR
|
|
- Abigayle Hall
- 5 years ago
- Views:
Transcription
1 Sweet Creek Road Retaining Wall Replacement Mapleton, OR
2 Technical Information Project Completion Date: April 30, 2013 Project Location: Mapleton, OR Size of Project: 15,000 SF, 870 CY Concrete Strength Requirements: (cu. yds., sq. ft., etc.) : The 15 span, 1130 foot bridge, was constructed using 105, four-foot wide by 30 inch thick precast, pre-stressed concrete slabs, varying in length from 50 to 81 feet and totaling 7,902 linear feet. Each span is made up of 7 slabs. The slabs rest on a total of 16 reinforced concrete caps ranging from 3 to 4 foot wide by 4 foot deep. 240 yards of concrete was used for bridge cap construction. Each cap sets on four concrete-filled steel pipe piles drilled 15 feet into bedrock. A total of 64 steel pipe piles support the length of the structure. The 64 pipe piles are encased in a total of 121 yards of concrete. Water/Cement Ratios: : Reinforced Bridge Caps and End Panels: 0.45 (Standard) / 0.35 (Early Strength); Concrete in Bridge Pipe
3 Unique or High Volume Admixtures: Four primary concrete mix designs were used on the project. Admixtures were needed to slow the set time of the concrete for transportation and also to keep the concrete fluid like for placement by pump operation. 1. Drilled Shaft Concrete 2. Exterior Structural Concrete 3. Exterior Structural Concrete 4. Type F Bridge Rail - Slip Form Total LEED points attributed to concrete construction: This project is credited with two LEED points for the respective sections: Water Quantity (6.1) and Water Quality (6.2). Describe unique mix designs: The most unique concrete mix design used on this project was the 5,000 psi Structural High-Early mix used in bent cap construction. Describe placement challenges or unique techniques: Given the immediate proximity of the Siuslaw River, the narrow roadbed and work area, the adjacent steep rock bluffs, and the needs of motorists, this project presented numerous placement challenges which inevitably drove a completely new design.
4 Sweet Creek Road is located near the community of Mapleton, Oregon, approximately 15 miles east of the Pacific Ocean, and is a vital transportation link between State Route 126 and large tracts of public and private forest lands. The road provides the only all-season access route to 68 rural residences. Particular sections of the roadway had been constant maintenance challenges due to settling pavement, sunken grades and failing retaining walls. Maintenance issues were compounded by a 22 foot wide roadway, bordered by a sheer rock bluff and steep banks of the Siuslaw River. In January 2011, one lane of the roadway sunk severely, resulting in a huge crack, leaving the westbound lane impassable.
5 The Sweet Creek Road Retaining Wall Replacement Project was designed to replace the failing retaining walls as viewed from the adjacent Siuslaw River and rebuild both lanes of the roadway by constructing two tieback retaining walls totaling 900 feet, connected by a 240 foot long pre-stressed bridge.
6 The contractor could only work during the hours of 8:00 a.m. to 4:00 p.m., Monday through Friday, allowing traffic to pass through the work zone every hour for a period of five minutes. Full road closures were permitted during the hours of 8:00 p.m. to 6:00 a.m. as on-site discoveries forced a completely different design and construction approach.
7 Prior to beginning construction, the contractor presented Lane County with a Value Engineering Plan (VEP) which proposed replacing the deepest sections of the retaining wall with additional bridge spans. The contractor had difficulty designing a shoring plan that would allow deep excavations for double tieback retaining wall construction while maintaining traffic flow on half of the existing roadway.
8 The VEP served as the foundation for extensive design changes. It eliminated all double tieback sections of the wall and it changed the project from a single, 240-foot, three-span bridge with two tieback retaining walls into two bridges having a total of 11 spans connected by a 180-foot tieback retaining wall.
9 As soldier piles were being drilled and installed for the remaining retaining walls, a second issue presented itself. In some locations bedrock was being encountered at depths greater than those estimated on the plans. These soldier piles were so deep they would require a double tieback.
10 It was further discovered during the initial drilling for the retaining wall soldier piles, that the rock encountered, which was thought to be bedrock, was actually large boulders. As a result, some soldier piles were installed with inadequate embedment into bedrock.
11 The project team eliminated all but 40 feet of retaining wall and added additional spans which tied the two concrete bridge structures into a single bridge. The result was the construction of one, continuous 15-span concrete bridge structure totaling 1,130 feet.
12 The construction limitations initially imposed by the river, the rock bluff and the narrow and heavily utilized roadway were compounded by differing soil and bedrock conditions discovered during construction.
13 This project was unique in that it began its life primarily as a retaining wall replacement project, but quickly morphed into a bridge construction project. In spite of these dramatic changes, the project team through a close partnership was able to retain the project s original scope, schedule and budget.
ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company
James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2
More informationMOA Project # Golden View Drive Intersection & Safety Upgrades
Appropriate transitions can include extending the insulation beyond the roadway improvements, reducing the insulation thickness, or angling the insulation downward. Use of a frost tolerant section, an
More informationTilikum Crossing Transit Bridge. Portland, OR
Tilikum Crossing Transit Bridge Portland, OR Technical Information Size of Project: The Tilikum Crossing Transit Bridge is 1,720 ft. long and required 24,000 cy total concrete Strength Requirements: The
More informationSandy High School. Sandy, OR
Sandy, OR Technical Information Project Completion Date: August 31 2013 Project Location: 37400 Bell Street, Sandy, OR Size of Project: 310,000 sq. ft., 8,500 cu. yds. Concrete Strength Requirements: 4,000
More informationDESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION
DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationOR99E: Clackamas River Bridge Dunes Drive. Oregon City, OR
Oregon City, OR Technical Information Project Completion Date: March 5, 2015 Project Location: Oregon City, OR Size of Project: 7,015 linear feet of curb; 35,083 square feet of sidewalk and driveways;
More informationBonner Bridge Replacement Update:
Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationSafe, innovative, quality construction since Riding on the Strength
Safe, innovative, quality construction since 1880 Riding on the Strength of EXPERIENCE The Expertise The Experience The People The Equipment The Work Ethic The quality To get your job done safely, on time
More informationFinal Estimates Level 2
Florida Department of TRANSPORTATION Final Estimates Level 2 Module 6: Structures 11/1/2017 FDOT Final Estimates Level 2 Release 11, Module 6 1 6-1 Module Content Concrete Structures Bridges Substructure
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationAbo Canyon Second Main Track
Abo Canyon Second Main Track Thomas Schmidt Director Engineering Services BNSF Railway David Miller Manager Engineering BNSF Railway Abo Canyon Second Main Track Building 5 miles of a second track through
More informationTraffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center
Traffic Management Guide to Concrete Overlay Solutions December 5, 2014 ACPA Annual Meeting Dale S. Harrington P.E. Representing CP Tech Center Traffic Management- Concrete Overlays Traffic Management
More informationTABULATION OF TOTAL QUANTITIES - CR 44H (BUCKHORN ROAD) (1 OF 2)
TABULATION OF TOTAL QUANTITIES - CR 44H (BUCKHORN ROAD) (1 OF 2) CONTRACT ITEM NO. CONTRACT ITEM UNIT BUCKHORN ROAD UPPER SECTION BUCKHORN ROAD LOWER SECTION PROJECT TOTALS PLAN AS CONST. PLAN AS CONST.
More informationWell Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.
Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990
KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 90P-270 Sheet 1 of 5 SECTION PAVEMENT PATCHING Page 591, Section. Delete the Section and replace with
More informationODOT Design & Construction Requirements for MSE Walls
ODOT Design & Construction Requirements for MSE Walls Peter Narsavage, P.E. Foundation Engineering Coordinator Ohio Department of Transportation Office of Structural Engineering 2006 Ohio Transportation
More informationANSWERS TO QUESTIONS RECEIVED THROUGH 1:00 PM ON MAY 24, 2018:
ADDENDUM NO. 3 PROJECT NO. 43805 (PART A & B) PAGE 2 ANSWERS TO QUESTIONS RECEIVED THROUGH :00 PM ON MAY 24, 208: Q#32 Addendum # answered Question #7 indicating that an average depth of 3 feet for the
More informationIronton Russell Bridge Project
Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September
More informationCase Histories. Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc.
Case Histories Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc. Cap Grouting Capping the top of the rock surface with grout to provide a barrier
More informationPlatform District at Orenco. Hillsboro, OR
Hillsboro, OR Technical Information Project Completion Date: September 15, 2015 Project Location: Hillsboro, OR Size of Project: 23,000 cubic yards; 171,930 square feet of slab-on-grade; 348,942 square
More informationSOUTH MEDFORD INTERCHANGE BRIDGES
Eleven bridges were required for the project THe I-5 south medford Interchange by Keith Kaufman, Knife River Corporation Northwest and Daniel J. McIntier, formerly with H.W. Lochner Inc. Interstate 5 is
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More information10:00 AM, Wednesday, May 6, Peters Creek Sanitary Sewer Rehabilitation Project
NOTICE OF MANDATORY PRE-BID CONFERENCE WILL BE HELD AT 10:00 AM, Wednesday, May 6, 2015 IN ROOM 16, CITY HALL BUILDING, 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA The purpose of this conference
More informationENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2014 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings
More informationVT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017
VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident
More informationUNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 66532 227 th STREET (TWP 45) OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY SEPTEMBER 12, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationA. Section includes temporary excavation support and protection systems.
SECTION 31 50 00 - EXCAVATION SUPPORT AND PROTECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationExcavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.
Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet
More informationJANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25
General Info Number: PROJECT NO. 43-17-03 Description: BRIDGE DECK REPAIR AND REHABILITATION, ARLINGTON ROAD OVER OHIO TURNPIKE M.P. 122.3, JOPPA ROAD OVER OHIO TURNPIKE M.P. 128.5, DEAN ROAD OVER OHIO
More information6 th STREET VIADUCT SIESMIC IMPROVEMENT PROJECT
6 th STREET VIADUCT SIESMIC IMPROVEMENT PROJECT Project Location The 6 th Street Viaduct (Bridge No. 53C-1880) and Sixth Street Overcrossing (Bridge No. 53-0595) comprise a single structure, which spans
More informationIngenuity Offers a Solution to an Anomaly in a Bridge Support
Ingenuity Offers a Solution to an Anomaly in a Bridge Support CSDA Contractor Member Part of the Most Expensive Public Works Project in California History Walkway to the congested work platform. San Francisco
More informationSTRUCTURES INSPECTION CERTIFICATION TRAINING COURSE
STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE Code Pre/Route AFE Function Part 0 1000 7116 1174 N Hadley Eisenbeisz Bridge Construction Engineer Rick Brandner Mitchell Area Darrell utter Assistant
More informationESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA
ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationKicking Horse Cantilever Structure. Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd.
Kicking Horse Cantilever Structure Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd. Brian Borton, P. Eng., Klohn Crippen Berger Ltd. Paper prepared for
More informationSPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006
Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable
More informationSR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA
ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN
More informationSPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006
Michigan Department Of Transportation 3703B (11/06) 1 Materials SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Page 1 of 5 1.1 Pipe - Pipe used in this method includes an external steel
More informationThis drawing. is preliminary. and not for. construction or. implementation. purposes. project number 170 END VIEW DESIGN STRENGTHS: PLAN
project number 70 Reference Line 2-0" Reference 3 -" 6-0" 6-0" 3 -" Line Box Culvert Roadway Finished Channel -0" -0" E VIEW 20-0" Riprap 0-0" Riprap Outlet Invert El 87.0 Sta 233+00.00 Inlet Invert El
More informationOhio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director
Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 6/2/2014 Project 140353 Addendum No. 1 PID No. 86675 MOT IR 75 11.75/11.80
More informationEconomical Design / Case Studies
Economical Design / Case Studies Alabama Technology Transfer Center Workshop Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation Competitiveness of
More informationIronton Russell Bridge Project
Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place
More informationClear Creek Road (PM 1.82 & 0.25) Bridge Replacement Projects. Public Meeting, Wednesday, November 20, 2013 Pleasant Valley Middle School
Clear Creek Road (PM 1.82 & 0.25) Bridge Replacement Projects Public Meeting, Wednesday, November 20, 2013 Pleasant Valley Middle School Presented By: County of El Dorado Community Development Agency Transportation
More informationFoundation Innovations Ensure Successful Bridge Replacement
COVER STORY Foundation Innovations Ensure Successful Bridge Replacement Rhode Island s new $163.7 million, 2,265 ft (690 m) long, fourlane Sakonnet River Bridge sits just south of the existing bridge in
More informationCivil and Structural Engineering CONSTRUCTION OF BRIDGE STRUCTURES SHALL BE IN ACCORDANCE WITH THE FOLLOWING SPECIFICATIONS, LISTED IN ORDER OF PRECEDENCE: 1. CDOT STANDARD SPECIFICATIONS FOR ROAD AND
More informationtwenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013
ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013 lecture twenty six concrete construction: www.tamu.edu foundation design Foundations 1 Foundation the engineered
More informationLecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts...
Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts... LECTURE 13 May 17, 2005 May 17, 2005 1 Where we have been Basics Allowable Stress Ultimate Strength Shear Camber
More informationSTANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation
STANDARDIZED CONCRETE BRIDGES IN TEXAS John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation ABSTRACT Standardized concrete bridge plans are used extensively
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationPHASING CONSIDERATIONS FOR BRIDGES
PHASING CONSIDERATIONS FOR BRIDGES Christopher Miller, P.E. 6/11/18 Table of contents 1 What Not to Do 3 2 Span Arrangement 4-9 3 4 5 6 Superstructure Geometric Considerations Superstructure Structural
More informationTraffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))
11060 White Rock Road, Suite 200 Rancho Cordova, CA 95670 Phone: (916) 363-4210 Fax: (916) 363-4230 M e m o r a n d u m To: Reena Gohil, Environmental Planner Date: May 30, 2017 California Department of
More informationStevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets
Stevens & Associates, Inc. Tunnel Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Massachusetts Water Resources Authority
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES
Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle
More informationHALLS RIVER BRIDGE REPLACEMENT
HALLS RIVER BRIDGE REPLACEMENT FDOT District 7 Structures Design Office Cristina Kay Suarez Mamunur Siddiqui, P.E. David Pelham Structures Designer Structures Design Engineer - SEOR Senior Structures Designer
More informationDSNY/DDC Spring Street Salt Shed
DSNY/DDC Spring Street Salt Shed PRESENTED TO Delaware Valley Association of Structural Engineers PRESENTED BY Burns Engineering, Inc. April 4, 2017 Anthony LoCicero, PE, LEED AP Photo : Scott Beale /
More informationTake Me to the Other Side:
Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional
More informationCHEF MENTEUR BRIDGE REPLACEMENT
CHEF MENTEUR BRIDGE REPLACEMENT Gumbo Engineers, Inc. Lucy Farrar, Travis Honore, Jeremy Vezina, Thomas Harrison PRELIMINARY DESIGN Fall 2016 Semester CE 4750 Professional Issues Mr. Miles Williams INTRODUCTION
More informationContinuously Reinforced Concrete Pavement California Practices
Continuously Reinforced Concrete Pavement California Practices Mehdi Parvini, PhD., P.E., Sr. Pavement Engineer California Department of Transportation 2012 CRCP California Workshop Why Continuously Reinforced
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS
Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...
More informationWELCOME TO THE PILE DRIVING INSPECTOR COURSE
Lesson 1 WELCOME TO THE PILE DRIVING INSPECTOR COURSE 1-1 Welcome to the Pile Driving Inspector Course. This is a course designed to assist students to understand the specifications and inspection practices
More informationtwenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design
ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SRING 2017 lecture twenty seven Foundation the engineered interface between the earth and the structure it supports that transmits
More informationWest Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation
West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre 10.26.2016 HNTB Corporation Outline Overview of WV TPK Ghent NB Bridge Existing Conditions ABC Deck Replacement Alternatives
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationPresented by: Taya Retterer BRG Webinar July 30, 2012
Presented by: Taya Retterer BRG Webinar July 30, 2012 PHASED CONSTRUCTION RECOMMENDATIONS FOR BRIDGES Will be posted to the TxDOT Website http://www.dot.state.tx.us/business/contractors_consultants/bridge/default.htm
More informationMisan University - College of Engineering Civil Engineering Department
CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s
More informationHalls River Bridge Update
2018 FTBA Construction Conference February 8 & 9, 2018 Orlando, FL 2017 FTBA Construction Conference Registration February 2 & 3, 2017 Orlando, FL Halls River Bridge Update Antonio Nanni, U. Miami, nanni@miami.edu
More informationCOVER FEATURE. Micropile. Design Minimizes. California Edison Project
COVER FEATURE Micropile Foundation Design Minimizes Environmental Impact for Southern California Edison Project by Chih-Hung Chen, P.E., Burns & McDonnell, and Nick Salisbury, Crux Subsurface, Inc. Micropiles
More information9 Concrete Pavement Patching
9 Concrete Pavement Patching Materials Concrete Mix Design Concrete Mix Criteria Trial Batch Demonstration of CMD Acceptance Removal of Concrete Partial Depth Patches Full Depth Patched Placement of Patching
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationUpon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that:
As part of our analyses, we have considered the design and construction of the cantilever retaining wall that will be located along the north side of Lucks Lane, between Falling Creek and Gladstone Glen
More informationLessons Learned Meeting Notes
EXTERNAL MEMORANDUM Lessons Learned Meeting Notes Distribution Date: April 24, 2017 Date of Meeting: April 19, 2017 Project: Sacramento Wash Crossing at Oatman Highway TRACS No. T0021 01D Federal Project
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationtwenty four foundations and retaining walls Foundation Structural vs. Foundation Design Structural vs. Foundation Design
ALIED ARCHITECTURAL STRUCTURES: STRUCTURAL ANALYSIS AND SYSTEMS DR. ANNE NICHOLS SRING 2018 lecture twenty four Foundation the engineered interface between the earth and the structure it supports that
More informationDeep Foundations Institute Fall 2004 Fall 2004
Fall 2004 Treviicos/Rodio JV using Wirth Reverse Circulation Drill Rig to install Secant Wall Piles for Walter F. George Dam Deep Cut-Off Fall 2004 DEEP FOUNDATIONS 5 The Deep Cut-Off at the Walter F.
More informationFlood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013
United States Department of Agriculture Natural Resources Conservation Service Denver Federal Center Building 56, Room 2604 P.O. Box 25426 Denver, CO 80225 720-544-2818-OFFICE alton.albin@co.usda.gov Flood
More informationProposal. Revised The Residences Anne Arundel County, Maryland. 1/14/2011 Faculty Advisor - Dr. Richard A. Behr Ryan English - Structural Option
Proposal Revised The Residences Anne Arundel County, Maryland 1/14/2011 Faculty Advisor - Ryan English - Structural Option Table of Contents Executive Summary... 3 Introduction... 4 Structural System...
More informationConverting square ft to cubic yards concrete
Converting square ft to cubic yards concrete Search Cubic Yards Calculator. Area Shape:. Where ( ft 2) = square foot, ( ft 3) = cubic foot, (yd 3) = cubic yard; Cubic Yards Formulas and Images for Different
More informationUsing Load Testing to Save Money and Time on the I-35W Bridge Project
Using Load Testing to Save Money and Time on the I-35W Bridge Project MATTHEW GLISSON, PE, M.ASCE, Braun Intertec Corporation, St. Louis, MO; MORGAN RACE, PH.D., PE, M.ASCE, Braun Intertec Corporation,
More informationHANt>LtNC WORK AND MtN 171
HANt>LtNC WORK AND MtN 171 shell bucket to lift the gravel to the mixer. By handling the work in the manner described above, it was unnecessary to build falsewotk and the results indicate that the work
More informationTechnical Report #2. Matthew R Peyton
Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study
More informationSpecification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010
Specification Changes and Their Effect on Plans Bridge Construction Issues BRG VTC April, 2010 Brian D. Merrill, P.E. BRG Construction & Maintenance Branch Also: Common Plan Review Items Revised Specifications
More informationSPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006
Michigan Department Of Transportation 3703F (11/06) SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Page 1 of 5 1 Materials 1.1 Pipe (a) Pipe shall be specifically designed and certified for microtunneling
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationJOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106.
JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106. There are notes in the plans regarding driving the test pile without the use of a follower. The
More informationCUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE CITY OF BRECKSVILLE,
CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE FOR THE CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS RQ# 41677 BIDS DUE ON: May 1, 2018, at 2:00 p.m. ADDENDUM NUMBER 1, April 25, 2018, Page
More informationDIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012
2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include
More informationSt. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer
St. Anthony Falls I-35W Bridge Replacement ASHE National Conference June 13, 2014 Dustin Thomas, P.E. I-35W Bridge Construction Engineer The Former Bridge - 9340 Opened to traffic in 1967 Steel truss bridge
More informationITEM QUANTITY UNITS UNIT PRICE AMOUNT. Contractor Construction Staking 1.0 Lump Sum
KTA Contract No. 5677 KANSAS TURNPIKE AUTHORITY ALT 1 Schedule of Prices Contract No. 5677 County Leavenworth Type of Work: Remove and reconstruct Bridge 221.542 (120'-170'-170'-120' Weathering Steel Spans).
More informationPerformance of Ultra-Thin Whitetopping District 58. Neal West, P.E.
Performance of Ultra-Thin Whitetopping District 58 Neal West, P.E. District 58 State Project 026-03-0036 FERRIDAY - RED GUM ROUTE US 65 CONCORDIA PARISH Contractors Prime Contractor: D&J Construction Co.,
More informationPerformance Verification Packet. Supervisor
Performance Verification Packet Supervisor This performance verification is designed as one method to evaluate job skills and safe work habits of a participant. The performance of the participant must
More informationUS-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer
US-131 Over the Muskegon River Corey Rogers, P.E. Bridge Construction Engineer NB and SB US-131 Each bridge is a three-span, 580 foot long, cast-in-place, post-tensioned concrete box girder structure resting
More informationCity of Mesquite General Design Standards Revision Date:
SCREENING WALLS (Public and Private) Page 1 of 6 Section 1 General Design & Notes 1.1 Standards 1.1.1 All screening walls in the City of Mesquite and within its Extraterritorial Jurisdiction (ETJ), both
More informationJohn James Audubon Bridge. Introduction
John James Audubon Bridge Introduction The Project Why build the bridge? The bridge--proposed to be the longest cable-stayed bridge in America--will replace an existing ferry between the communities of
More informationNorfolk Southern s Online Rebuild of the Coosa River Bridge
Norfolk Southern s Online Rebuild of the Coosa River Bridge Author: Harold Hal E. Lewis, PE, Vice President, HDR Engineering, Inc. 200 West Forsyth Street, Suite 800, Jacksonville, Florida 32202 Telephone:
More information