Sodom and Shearer Dam Removal Effectiveness Monitoring

Size: px
Start display at page:

Download "Sodom and Shearer Dam Removal Effectiveness Monitoring"

Transcription

1 Sodom Dam Site: pre-removal Shearer Dam ( Sodom and Shearer Dam Removal Effectiveness Monitoring Sodom Dam Site: post-removal Final Report: OWEB Grant # February 1, 2013 Shearer Dam Site: pre-removal Prepared by: Desiree Tullos, Ph.D., PE Matt Cox Cara Walter Biological and Ecological Engineering Oregon State University 116 Gilmore Hall Corvallis, OR Shearer Dam Site: post-removal

2 Table of Contents List of Figures Introduction and Project Objectives Background and project objectives General site descriptions Methods Dispersed Sites Fish Habitat Temperature Intensive Sites Sodom Dam Shearer Dam Streamflow gauging Summary of Results Dispersed sites Temperature Temperature monitoring was used, in part, to investigate effects of potential ecological impacts of changes in the flow split. Lower flow in a reach may lead to warming due to lower volume of water Longitudinal temperature trends in Sodom Channel: Pre- and post-removal Fish Fish Cover Canopy cover Sreambank conditions Longitudinal profiles Vegetation Historical Calapooia In-channel wood Intensive sites

3 4.2.1 Sodom Dam Shearer Dam Discharge and flow splits Summary and future work Literature Cited Appendix A: Discharge gaging... Error! Bookmark not defined. Appendix B: Intensive site cross sections... Error! Bookmark not defined. Sodom Dam site... Error! Bookmark not defined. Shearer Dam site... Error! Bookmark not defined. Appendix C: Photo points... Error! Bookmark not defined. Appendix D: Visual Inspection Checklist Appendix E: Temperature monitoring locations on the Sodom Channel and Calapooia River. 84 3

4 List of Figures Figure 1: Site map, including extents of intensive monitoring sites and locations of dispersed sites. S1 and S2 sites are located in the Sodom channel and C1-C5 sites are all located on this historical Calapooia River. C0 and C6 is located on the mainstem Calapooia River Figure 2: The Sodom 1 dispersed site (map on left, photo on right). Site is located to the north of Linn West Drive, 2.5 km north of the bifurcation Figure 3: The Sodom 2 dispersed site (map on left, photo on right). Site is located directly to the north of Boston Mill Rd, 6.4 km north of the bifurcation... 9 Figure 4: The Calapooia 1 dispersed site (map on left, photo on right). Site is located east of I-5, 2.8 km downstream of the bifurcation Figure 5: The Calapooia 2 dispersed site (map on left, photo on right). Site is located alongside Roberts Rd, 6.35 km downstream of the bifurcation Figure 6: The Calapooia 3 dispersed site (map on left, photo on right). Site is downstream of the former location of Shearer Dam, 9.25 km downstream of the bifurcation Figure 7: The Calapooia 4 dispersed site (map on left, photo on right). The site is located just upstream of the confluence between the Calapooia and the millrace at Thompson s Mill State Historical Park, 12.2 km downstream of the bifurcation. The two red locations are approximate (GPS waypoints not taken due to lack of signal under dense vegetation) Figure 8: The Calapooia 5 dispersed site (map on left, photo on right). Site is located downstream of Thompson s Mill, km downstream of the bifurcation Figure 9: Pre-removal daily maximum temperatures collected in two Sodom Channel locations, 0.55km and 2.5km below the bifurcation in Sodom 1 corresponds to S1 in Figure Figure 10: Post removal daily maximum temperatures collected in 3 Sodom Channel dispersed site locations located at 0.55km, 2.5km and 6.4km below the bifurcation in Figure 11: Pre removal daily maximum temperatures observed at 5 dispersed sites in the Calapooia River in Calapooia 1- Calapooia 5 correspond to C1-C5 in Figure Figure 12: Post removal daily maximum temperatures observed at 2 dispersed sites and 1 winter temperature monitoring site in the Calapooia River after the removal of Sodom and Shearer Dams in These sites are located 4.1km, 6.35km and 12.2km downstream of the bifurcation Figure 13: The percent of native fish during the sampling period in 2010 and Figure 14: Breakdown of fish species, by location Figure 15: Fish cover changes in the Sodom Channel, 2010 to Figure 16: Fish cover changes in the Calapooia River, 2010 to Figure 17: Canopy cover measured at five units per site, on two dispersed sites along the Sodom Channel Figure 18: Canopy cover measured at five units per site, on five dispersed sites along the historical Calapooia River Figure 19: Channel longitudinal profiles at dispersed sites (S1 and S2) on the Sodom Channel.27 4

5 Figure 20: Channel longitudinal profiles measured in 2010 and 2012 at dispersed sites (C1-C5) on the Calapooia River Figure 22: Riparian vegetation observed at the Sodom 1 dispersed site in 2010 and Figure 23: Riparian vegetation observed at the Sodom 2 dispersed site in 2010 and Figure 24: Riparian vegetation observed at the Calapooia 1 dispersed site in 2010 and Figure 25: Riparian vegetation observed at the Calapooia 2 dispersed site in 2010 and Figure 26: Riparian vegetation observed at the Calapooia 3 dispersed site in 2010 and Figure 27: Riparian vegetation observed at the Calapooia 4 dispersed site in 2010 and Figure 28: Riparian vegetation observed at the Calapooia 5 dispersed site in 2010 and Figure 29: Volume of wood measured in Sodom Channel dispersed sites Figure 30: Volume of wood measured in Calapooia River dispersed sites. Note that the y axes vary in size, so that columns representing wood volume are not obscured due to scaling effects Figure 31: Longitudinal profile for Sodom Figure 32: Net change in area at cross sections in the area around Sodom Dam Figure 33: Longitudinal profile for the Calapooia River at Shearer Dam Figure 34: Net change in cross sectional area from as-built to 2012 for cross sections in the former Shearer Dam reservoir and downstream Figure 35: Calculated and measured discharge on the Calapooia River at Brownsville, the Calapooia River at Linn West Drive, and Sodom Channel at Linn West Drive Figure 36: Calculated discharge on the Calapooia River at Brownsville and Sodom Channel at Linn West Drive with the ratio of discharges for Sodom Channel at Linn West Drive and the Calapooia River at Linn West Drive relative to the Calapooia River at Brownsville Figure 37: Discharge on the Calapooia River at Brownsville Bridge... Error! Bookmark not defined. Figure 38: Rating Curve for the Calapooia River at Brownsville Error! Bookmark not defined. Figure 39: Discharge on Sodom Channel at Linn West Drive... Error! Bookmark not defined. Figure 40: Rating Curve for Sodom Channel at Linn West DriveError! Bookmark not defined. 5

6 1. Introduction and Project Objectives 1.1.Background and project objectives This report presents the results of geomorphic and biological monitoring around the removal of Sodom and Shearer dams on the Calapooia River and Sodom Channel. The overarching objectives od this effort were to 1) evaluate the effectiveness of the project in meeting objectives to inform maintenance and modification, and 2) investigate the spatial and temporal effects of the split flows, sediment dynamics, and channel reconfiguration associated with removing Sodom and Shearer Dams on habitat and fish of the Calapooia River. All data are disseminated via the project website : 2. General site descriptions The Calapooia River travels 121 km from its source in the Western Cascades before meeting the Willamette River near Albany, Oregon. Its drainage area of 947 km 2 consists of steep terrain managed for forestry in the upper watershed transitioning to low gradient agricultural and rural residential lands below the community of Holley (Runyon et. al 2004). The Calapooia is a winter rain-dominated system, with majority of annual runoff occurring from November to April. Average monthly flows at the Holley gauge (records from 1936 to 1990) ranged from 24.3 m 3 /s in January to 1.2 m 3 /s in August. The Sodom Channel was created in the 19 th century to divert flow for milling and to reduce flooding impacts in the lower Calapooia basin. The Channel leaves the main channel of Calapooia just downstream of RM 19, and carries the majority of the annual flow of the river. Sodom Dam was originally constructed in 1890 because the Channel had diverted the entire volume of the river. The most recent (concrete) Sodom Dam was constructed in the 1950s near the upstream end of the Sodom Channel in order to maintain flow in the historical Calapooia channel for use at Thompson s Mill (OPRD 2006). The dam measured 3.4m high and 25.9m wide (Calapooia Watershed Council, 2013). The pool behind Sodom Dam contained approximately 4600m 3 of sediment (Tetra Tech, 2008). Sodom Dam was removed in July of Various structures have historically been in place to divert water from the historical Calapooia channel near RM 23 into the millrace used by Thompson s Mill. The most recent concrete structure at Shearer Dam was built in 1956 at a location about 46 m below the millrace. This structure measured 2.2m high and 12.2m wide. Shearer Dam was removed in August of

7 Table 1: Characteristics of dispersed sites in the Sodom Channel (S1, S2) and Calapooia River (C1-C5). Site Name Dist DS of bifurcation (km) Low Flow Wetted Width (m) Top of Bank Width (m) Water Surface Slope S % S % C % C % C % C % C % 3. Methods Study design included both intensive monitoring at the sites of dam removal and at dispersed sites (Figure 1). Seven dispersed sites (2 in the Sodom Channel and 5 in the historical Calapooia) were selected to represent a sample of the entire system for detailed study of bank characteristics, habitat features and temperature (Figures 2-8). Goals and methods varied between the intensive and dispersed sites, as described in the following sections. 7

8 Figure 1: Site map, including extents of intensive monitoring sites and locations of dispersed sites. S1 and S2 sites are located in the Sodom channel and C1-C5 sites are all located on this historical Calapooia River. C0 and C6 is located on the mainstem Calapooia River. 8

9 Figure 2: The Sodom 1 dispersed site (map on left, photo on right). Site is located to the north of Linn West Drive, 2.5 km north of the bifurcation. Figure 3: The Sodom 2 dispersed site (map on left, photo on right). Site is located directly to the north of Boston Mill Rd, 6.4 km north of the bifurcation. 9

10 Figure 4: The Calapooia 1 dispersed site (map on left, photo on right). Site is located east of I-5, 2.8 km downstream of the bifurcation. Figure 5: The Calapooia 2 dispersed site (map on left, photo on right). Site is located alongside Roberts Rd, 6.35 km downstream of the bifurcation. 10

11 Figure 6: The Calapooia 3 dispersed site (map on left, photo on right). Site is downstream of the former location of Shearer Dam, 9.25 km downstream of the bifurcation. Figure 7: The Calapooia 4 dispersed site (map on left, photo on right). The site is located just upstream of the confluence between the Calapooia and the millrace at Thompson s Mill State Historical Park, 12.2 km downstream of the bifurcation. The two red locations are approximate (GPS waypoints not taken due to lack of signal under dense vegetation). 11

12 Figure 8: The Calapooia 5 dispersed site (map on left, photo on right). Site is located downstream of Thompson s Mill, km downstream of the bifurcation. 3.1 Dispersed Sites Fish Consistent with the surveys collected for pre-removal characterization and with USEPA s protocols for wadeable streams (Peck et al. 2006), fish sampling was performed by a contractor for this study using a backpack electroshocker and hand nets. Four of the dispersed sites were sampled annually (Figure 1): S2) Sodom Channel downstream of Boston Mill Road; C2) Calapooia River upstream of the mill, Shearer and Spillway Dams but downstream of I5; C4) Calapooia River upstream of the mill but downstream of Shearer and Spillway Dams; and C5) Calapooia River downstream of the mill but upstream of the confluence with Sodom Channel. This sampling supplements fish sampling being performed by the USEPA for a wider study upstream of Sodom Dam on the Calapooia River, and downstream of the Sodom Channel and Calapooia River confluence Habitat We evaluated changes in habitat at the seven dispersed sites on the Calapooia River and Sodom Channel. Each site consists of five contiguous transects, each of which are four activechannel widths long, as determined at the downstream end of the each site. Sites were sampled downstream to upstream. We modified USEPA s EMAP procedure (Kaufmann et al. 1999), as described below, to measure in-stream wood, canopy density, fish cover, thalweg depth, bed sediment, water surface velocity, channel width, slope, shade angle, and bank vegetation either along the transect or at cross sections situated at the midpoint of the transects. Along the transects, we sampled the following features: 12

13 Wood - All pieces in the active channel greater than 5 feet long or 0.5 feet in diameter were tallied. The positioning (in or out of water), stability (fixed or loose), and racking (individual or part of an accumulation) was documented for each piece of wood. In the case of larger accumulations, we estimated the overall dimensions and porosity (e.g. streamwise length, width, height, and volume filled with wood) as well as whether or not the accumulation was channel spanning or the dominant side of the channel if not channel-spanning. Vegetation Each bank was evaluated in two parts: downstream of the cross section and upstream of the cross section. For each part of the bank evaluated, the species or class of vegetation (vine, shrub, grass, mature tree) and percent of the bank covered by vegetation class were recorded. Bed slope and water depth - Water depth was measured with a stadia rod in the thalweg at an interval equal to the section length divided by 12. Bed slope was determined with a hand level and stadia rod for either half of each section or the whole section, depending on visibility. Substrate - Substrate was measured visually or with the bottom of the stadia rod (to differentiate sand and silt/clay) on the left, center and right of the wetted channel at four streamwise locations within each section: 1) the start; 2) ¼ of the length; 3) ½ of the length (at the cross section); 4) ¾ of the length. Percent embedded was visually estimated for substrate determined to be gravel and larger. At cross sections, we sampled the following features: Bank parameters - Bank slope in percent was determined by laying the stadia rod down with the clinometer on top of it for all discrete slopes (e.g. toe, bench, to terrace) along each bank. Bank material was identified as the dominant material and determined by pinching for fines or visual assessment for gravels or larger. Bank height was defined as the height above the water surface. Channel parameters - Velocity was estimated three times by extending the stadia rod to 13 feet, laying it streamwise on the surface of the water, and timing a dogwood leaf floating the length next to the rod. Channel width was measured from top-of-bank to topof-bank. Bottom width was measured as the wetted width. Shade angle was measured from the middle of the active channel looking up to the top of the vegetation on each side with the clinometer. Canopy Canopy density was measured four times at each cross section facing downstream, upstream, river right (oriented looking downstream), and river left using a densitometer with 17 intersections showing on the densiometer. The densiometer was 13

14 held level approximately one foot above the water surface, and each intersection that covered by vegetation was counted. Fish cover Perfect aerial coverage of ten types of potential fish cover was assessed in each unit of each site : Macrophytes, Large and small wood, live trees/roots, overhanging vegetation, undercut banks, boulders, artificial structures and bryophytes. We found no artificial structures or bryophytes at any of the dispersed sites. 3.2 Temperature Temperature was measured hourly at dispersed and intensive monitoring sites using ibutton sensors (model DS1921G). According to the manufacturer, these sensors are accurate to +/- 1 C and water resistant (IP 56). Additional water resistance was gained by placing the ibutton within two plastic layers and then within a sealed, galvanized pipe housing. The original sampling design called for three sensors at each dispersed site, placed at various depths to examine possible temperature stratification and locations of thermal refugia. In addition, sensors were placed above and below the intensive monitoring sites in order to understand the magnitude of heating enabled by the impoundment of flow behind the both dams. In the winter, a single sensor at each site was left in place, and in some cases moved to location that is accessible year round (e.g a nearby bridge abutment). Our experience with these particular sensors has been that they are very unreliable (Appendix F, Tables F1 and F2) when placed in a submerged environment for extended amounts of time. Even with a well-sealed case, water vapor caused unit failures in well over 60% of our placements overall. Thus, we were unable to complete the temperature analysis as originally envisioned. Longitudinal trends where simultaneous measurements do exist are presented here. 3.3 Intensive Sites Sodom Dam Spatial extent for the intensive monitoring near Sodom Dam is approximately 300 feet upstream of the bifurcation (River Design Group-RDG station 22+00) to 200 feet downstream on the historical Calapooia and 2000 feet downstream on Sodom Channel (RDG station 42+00). A combination of RTK GPS and total station field surveys were conducted annually at low water. Surveys were conducted as a longitudinal profile and cross sections at a) each engineered riffle crest, b) each pool that occurred between the engineered riffle structures, c) upstream of the bifurcation to Station 22+00, d) at the bifurcation, Station 26+00, e) downstream of the bifurcation in the historical Calapooia River (approximately 200 ). Additional survey points were collected in areas that greatly deviated from design both during the low flow survey, and soon after changes in the channel. Surveys at the completion of dam removal and channel construction, hereafter referred to as as-built surveys, were conducted by River Design Group (RDG). Subsequent surveys were conducted by the River lab at Oregon State University (OSU). 14

15 During summer baseflows, we completed a visual inspection checklist, developed by OPRD (See example, Appendix E), and field surveys of the following locations: engineered riffles, engineered log jams, vegetated soil lifts, channel reconstruction, specifically noting areas of erosion or deposition, and the bifurcation. Surveys and inspections specifically noted areas of sediment accumulation, discontinuous flow through coarse sediment that could lead to fish passage barriers, and lack of flow into either of the downstream channels. We revisited photo points during summer baseflow and for 1-2 storm events to document the performance of the structures during higher flows. Photos were taken at multiple angles per point. Locations established based on Federal Energy Regulatory Commission (FERC) permit requirements for effectiveness evaluation of the structures include: 2 photo points per engineered riffle: 1 looking upstream, 1 looking downstream 1 photo point per engineered log jam 1 photo point per vegetated soil lift at each associate engineered structure 5 Representative photo points for vegetative plantings 3 photo points at the bifurcation: 1) Looking downstream, 2) Looking upstream from Calapooia River below the bifurcation, and 3) Looking upstream from Sodom Channel below the bifurcation Shearer Dam Intensive monitoring around Shearer Dam extended from approximately 250 feet upstream of the Shearer Dam to 250 feet downstream. A combination of RTK GPS and total station field surveys were conducted at low water documenting the longitudinal profile and cross sections upstream and downstream of the Shearer Dam site. Surveys at the completion of dam removal and channel construction, hereafter referred to as as-built surveys, were conducted by RDG. Subsequent surveys were conducted by the River lab at Oregon State University (OSU). Photo points were established prior to dam removal at points of interest and were revisited during summer baseflow. 3.4 Streamflow gauging For the purpose of monitoring flow allocation between the two channels, two gages were utilized: 1. An existing OSU gauging station on the Calapooia River upstream of the bifurcation near Brownsville. Effort for this gage was focused on continuing to develop the rating curve, and downloading and processing flow data. 15

16 2. A new OSU gauging station on Sodom Channel at the Linn West Drive bridge. Effort for this telemetry-based gauging station was focused on extending the rating curve and providing hourly water level and discharge measurements to interested parties through a website. Discharge measurements on the Sodom Channel were subtracted from discharge on the Calapooia River to estimate flows through the historical Calapooia channel. On a time available basis, discharge measurements were also taken on the Calapooia River at Linn West Drive. All discharge measurements were taken according to USGS protocols (Rantz et al. 1982, Mueller et al. 2009) with a Price AA current meter either wading or using a crane from a bridge, or with a Teledyne RD Instruments StreamPro. Rating curves were developed using USGS protocols (Rantz et al. 1982, Kennedy et al. 1983, Kennedy et al. 1984). All data were published online at the project website: Rating curves and equations are presented in Appendix A. 4. Summary of Results 4.1 Dispersed sites Temperature Temperature monitoring was used, in part, to investigate effects of potential ecological impacts of changes in the flow split. Lower flow in a reach may lead to warming due to lower volume of water. Longitudinal temperature trends in Sodom Channel: Pre- and post-removal. Longitudinal trends are represented as the difference in maximum daily temperature between two sensors located in Sodom Channel. Due to damaged sensors, no pre-removal data is available from S2, which is located 6.4 km downstream of the bifurcation, but was functioning in 2012 for post-removal analysis. In addition, the upstream temperature sensor for the upstream Sodom Intensive site also failed. Thus, for the pre-removal condition, we compare (Figure 9) temperature from the sensors installed a) in the Sodom Intensive site, located 0.55 km downstream of the former dam site, to b) at the S1 dispersed site, located at Linn-West in the Sodom Channel, 2.5km downstream of the former dam site. From these data, we see no evidence of longitudinal trend in maximum daily temperature between the downstream Sodom Intensive monitoring site and S1 between early June and early July of

17 Figure 9: Pre-removal daily maximum temperatures collected in two Sodom Channel locations, 0.55km and 2.5km below the bifurcation in Sodom 1 corresponds to S1 in Figure 1. Comparing post removal temperature trends (Figure 10), daily maximum temperatures remain similar at the Sodom DS intensive and S1 sites. No evidence is seen of a longitudinal trend between the Sodom DS intensive and S1 sites, similar to pre removal observations. The daily maximum temperatures at the Sodom 2 site are occasionally cooler, but the relationships between the sites become less predictable after July 1 st. 17

18 Figure 10: Post removal daily maximum temperatures collected in 3 Sodom Channel dispersed site locations located at 0.55km, 2.5km and 6.4km below the bifurcation in Longitudinal temperature trends in the historical Calapooia River: Pre- and post-removal For the pre-removal condition (Figure 11), we compare daily maximum temperatures at 5 dispersed locations: 1) C1, located 2.8 km downstream of the bifurcation 2) C2, located 6.35 km downstream of the bifurcation 3) C3, located 9.3 km downstream of the bifurcation 4) C4, located 12.2 km downstream of the bifurcation, and 5) C5, located 13.3 km downstream of the bifurcation. Daily maximum temperatures do not show a consistent downstream warming pattern during this time period. In fact, maximum temperatures are generally cooler farther downstream from the bifurcation after June 15th. This may in part be due to the dense riparian shading in the historical Calapooia channel. It also appears that warmer water in the upstream of portion of this channel (e.g. C1) takes about one day to travel the 10.5 km to the farthest DS site (C5). This is most clearly apparent in the maximum on July 6 th, where temperature peaks at 23 C for the C1 location, but peaks at 21 C on July 7 th at C5. 18

19 Figure 11: Pre removal daily maximum temperatures observed at 5 dispersed sites in the Calapooia River in Calapooia 1- Calapooia 5 correspond to C1-C5 in Figure 1. For the post-removal condition (Figure 12), we examine daily maximum temperatures at three locations in the historical Calapooia channel. Due to sensor loss, data at C1, C3 and C5 are not available. However, data from a winter temperature monitoring location (Calapooia River at Linn West Drive 4.1km downstream of the bifurcation) were available and are included. Downstream cooling is observed in daily maximum temperature values between April 1 st and early June. One pattern observed is the reduction in daily maximum temperatures in the downstream direction. This pattern, observed post removal, is similar to the pattern observed prior to removal in

20 Figure 12: Post removal daily maximum temperatures observed at 2 dispersed sites and 1 winter temperature monitoring site in the Calapooia River after the removal of Sodom and Shearer Dams in These sites are located 4.1km, 6.35km and 12.2km downstream of the bifurcation. In summary, we conclude that effects of daily maximum temperature patterns from either changes in flow regime or changes in riparian condition are small and likely beyond our ability to detect with this dataset Fish Results of fish monitoring are presented as percent natives and community composition by sampling location. Nearly 100% of the fish observed in the dispersed sites were native in both survey periods for all sites (Figure 13). Species composition was dominated by torrent sculpin, reticulate sculpin, redside shiner and speckled dace (Figure 14). Smallmouth bass (a non-native species) were observed both in the historical Calapooia and the Sodom Channel. From these limited surveys, we see no evidence of impact on species distribution or % natives associated with the dam removals. 20

21 Figure 13: The percent of native fish during the sampling period in 2010 and 2012 Figure 14: Breakdown of fish species, by location. 21

22 4.1.3 Fish Cover Fish cover in the Sodom Channel underwent little change over the study period, with the exception of a reduction in overhanging vegetation observed at the S2 site. Filamentous algae declined in four of five historical Calapooia sites in Small woody debris also decreased at the same four sites. These changes likely represent the effects of increased flow in the historical Calapooia. No clear trends were observed in the presence of large woody debris or live trees in the channel. Figure 15: Fish cover changes in the Sodom Channel, 2010 to

23 Figure 16: Fish cover changes in the Calapooia River, 2010 to Canopy cover Along the Sodom Channel (Figure 17), canopy cover increased in four of the five units at the S1 site. Slight changes within units were observed at the S2 site, but overall, canopy cover was similar in 2010 and On the historical Calapooia channel, canopy cover (Figure 18) either remained similar (C2 and C3) or increased slightly (C1, C4, C5). Riparian disturbances large enough to reduce canopy cover were not observed at any of the dispersed sites. Figure 17: Canopy cover measured at five units per site, on two dispersed sites along the Sodom Channel. 23

24 Figure 18: Canopy cover measured at five units per site, on five dispersed sites along the historical Calapooia River. 24

25 4.1.5 Sreambank conditions Bank slopes changes were grouped into five discrete categories (Table 2). The accuracy of the clinometers is /- 5, so any change less than this is considered not measureable. Bank slope values were averaged when more than one measurement existed on the same bank. Channel width values were measured from the top of one bank to the top of the opposing bank. Table 2: Changes in bank slope, bank height, channel width following dam removal. Results are presented for individual cross sections in dispersed sites between 2010 and Slope change categories are represented as follows: >+15%(++), +5% to +15%(+), +5% to -5% (n.c. no change), -5% to -15%(-), >-15%(--). Channel width in the table represents the difference in top-of-bank width. Site Name Bank Slope Changes Average Change in Average Change in Channel Width at Top of Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Bank Height (m) Bank (m) S1 LB ++ n.c RB n.c S2 C1 LB LB n.c RB RB n.c n.c. n.c C2 LB n.c RB - -- n.c C3 LB RB n.c C4 LB ++ n.c RB n.c C5 LB n.c RB n.c Across the period (September 27 to October 15) of the 2010 survey, the estimated stage and discharge in the Sodom Channel were 0.4 m (1.3 ft) and 3.3 cms (115 cfs), respectively. On the historical Calapooia, estimated stage and discharge were 0.3 m (0.9 ft) and 1.5 cms (53 cfs), respectively. In 2012, our survey dates spanned fewer days (September 12-14) and flows were very different. Stage and discharge were both much lower, 0.3 ft (0.1 m) and 0.3 cms (9 cfs) respectively, in the Sodom Channel. In contrast, stage and discharge in the historical Calapooia were both higher that pre-project conditions, 0.4 m (1.3 ft) and 3.3 cms (115 cfs), respectively. In the Sodom Channel, channels appear to have mostly steepened, narrowed, and lowered between 2010 and The only exceptions to this trend are the right banks of S2, where slopes flattened by S1 and S2 sites are located 2.5 and 6.4 m, respectively downstream of the sites. However, without analysis of the streambank stability, we are unable to confirm that the extensive changes in bank width are associated with dam removal. For example, it is possible that some of the estimated changes in top widths are unreliable due to difficulty in identifying the top of bank in the heavily vegetated channels under different flow conditions. Analysis of 25

26 streambank stability across the study periods, to be completed, will provide addition insight into the reliability of these observations and the mechanisms for changes in streambank geometry. Along the historical Calapooia River, units both narrowed (C1, C2, and C5) and widened (C3, C4). Change in bank height was low for most units. Patterns in bank steepening are mixed; both C1 and C2 steepened on the left bank while the slope steepened on the right bank, suggesting erosion on the left bank. Most of the left and right banks at C3 either steepen or become flatten simultaneously. Most banks steepen at site C4, where the channel width increases substantially. The change in channel width and slope at C4 corresponds with an increase in wood volume (Figure 30). Alternating banks steepen and become less steep at site C Longitudinal profiles Along the Sodom Channel, the locations of pools dramatically shift between the two periods for both S1 and S2 sites (Figure 19). Because these sites are so far downstream (Table 1), it is unlikely that these changes are associated with the dam removal. Without additional information on the background, natural variability of the bed profile, we also cannot conclude whether changes are associated with the changes in winter flows (See Section 4.3, Table 3, and Figure 36 for pre- and post-project flow splits between the historical Calapooia and Sodom Channel). Thus, based on maximum GPS error (+/- 3m) in reoccupying former survey locations, we can only conclude that these large shifts in the locations of these pools on the Sodom Channel are not surveying artifacts but are legitimate channel changes that occurred across the study period. 26

27 Figure 19: Channel longitudinal profiles at dispersed sites (S1 and S2) on the Sodom Channel. Patterns of incision and aggradation varied across the dispersed sites on the historical Calapooia between the two study periods (Figure 20). One site (C1) incised, two sites aggraded (C3, C5), and two sites (C2, C4) experienced local erosion and deposition. It is possible that channel changes are a result of the flow split (See Section 4.3 for pre- and post-project flow splits between the historical Calapooia and Sodom Channel), but again, without some evidence of baseline variability at these sites, conclusions cannot be drawn. 27

28 28

29 Figure 20: Channel longitudinal profiles measured in 2010 and 2012 at dispersed sites on the Calapooia River. 29

30 4.1.7 Vegetation For the purposes of this report, vegetation data has been lumped into four broad categories (woody, shrubs, grass/forbs and bare). In general, grass and forbs were most prevalent in locations where small bank failures had recently exposed sediment to plant colonization. In reaches with more mature vegetation, the understory was so dense that very few areas of grass/forbs were observed. The most commonly observed wood species in our vegetation surveys were red osier dogwood (Cornus Stolonifera) and Oregon ash (Fraxinus Latifolia). The most commonly observed shrub species included Himalayan blackberry (Rubus Discolor), snowberry (Symphoricarpus Albus), and red flowering currant (Ribes Sanguineum). By far the most commonly occurring plant in the forb/grass category was reed canary grass (Phalaris Arundinacea). Along the Sodom Channel, the presence of forbs decreased between 2010 and 2012 (Figure 22) for most units in S1 and S2. More woody vegetation was observed on the left bank at S1, while less was observed on the right bank, where woody vegetation was replaced primarily by shrubs. At S2, woody vegetation comprised more of the bank vegetation in 2012 than in Percent of the bank with no vegetation was lower in 2012 that 2010 for nearly all units in S1 and S2, replaced by a mixture of woody and shrubby vegetation. Figure 21: Riparian vegetation observed at the S1 dispersed site. 30

31 Figure 22: Riparian vegetation observed at the S2 dispersed site. Historical Calapooia Across most of the dispersed sites on the historical Calapooia, bare areas observed in 2010 were not present in 2012 (Figures 23-27). Grass and forbs were also reduced, with a few exceptions (C1, Unit 1, right bank; C5, Unit 1, right bank; C5, Unit 5, left bank). For these units where grasses and forbs were not lower in 2012, the opposite bank became much less steep and the bank where the grass/forbs were observed became steeper. This is consistent with initial observations in these units that area of bank failure tended to be colonized with reed canary grass. For many areas in C3, C4 and C5 (Figures 25-27), it appears that woody vegetation was replaced by shrubs in However, we do not believe this shift actually occurred. Instead, we believe the difference may be related to a classification discrepancy; Field technicians classified red osier dogwood as woody in 2010 and as a shrub in The banks of these sites are heavily overgrown, with very little undergrowth. 31

32 Figure 23: Riparian vegetation observed at the C1 dispersed site. Figure 24: Riparian vegetation observed at the C2 dispersed site. 32

33 Figure 25: Riparian vegetation observed at the C3 dispersed site. Figure 26: Riparian vegetation observed at the C4 dispersed site. 33

34 Figure 27: Riparian vegetation observed at the C5 dispersed site In-channel wood Very little wood was present at either of the dispersed sites on the Sodom Channel in 2010 and 2012 (Figure 28). At S2, one somewhat large accumulation (10 m 3 in Unit 4 of was associated with one large fallen tree. Figure 28: Volume of wood measured in Sodom Channel dispersed sites. Much more wood was observed in the historical Calapooia (Figure 29) than in the Sodom Channel, and the volume of wood varied more in the historical Calapooia than in the Sodom Channel between the two study periods. Both the import of smaller pieces of wood and the 34

35 export of both large individual pieces of wood and accumulations account for the differences between study periods, and indicate that wood movement was active in the historical Calapooia channel post dam removal. For example, several sites (C1, C3 and C5) had greater accumulation of wood in 2012 than in with 2010 (Figure 29). This increase in wood volume consisted mainly of numerous smaller pieces of wood. Both C2 and C4 lost wood between 2010 and 2012: Site C2 had a single large single piece of wood present in 2010 that was not present in 2012, while a large wood accumulation present in C4 in 2010 was not observed in However, wood volumes in the other units of C2 were similar or lower in 2012 than in 2010, while wood volume in C4 increased wood volume in the remaining four units by Figure 29: Volume of wood measured in Calapooia River dispersed sites. Note that the scales on the y-axes are not consistent. 35

36 4.2 Intensive sites Sodom Dam As can be seen from the longitudinal profile (Figure 30), change in channel area (Figure 31), and cross sections (Appendix C), the Sodom Channel above, within, and downstream of the influence of Sodom Dam greatly changed as a result of the channel reconstruction (pre-removal June 2011 to as-built November 2011), and from the changes in flows during the 2012 water year (as-built to post-removal June/July 2012). A maximum of approximately 10 feet of erosion occurred between the as-built and the June/July 2012 surveys for the pool (3300 m) above the former dam site. In contrast, the historical Calapooia River underwent few changes at the cross section 200 feet downstream of the bifurcation (Figure 31). There was little net change for cross sections outside of the reconstructed area, although the most upstream cross section at station changed in shape with a ~50 shift toward river right of a mid-channel bar (Appendix C). In cross-section, there were dramatic changes upstream of and within the middle riffle of the reconstructed area, starting at cross sections at and continuing through (Appendix C). At its maximum, the river right bank retreated 60 feet and the bed lowered up to 15 feet, resulting in erosion of a total volume of approximately 5,000 cubic yards of material. There were also moderate changes in the river left bank within the most upstream riffle between cross sections at and 30+40, including creation of a backwater channel and natural log jam. At the cross section at within the upstream riffle, the backwater channel visible in the 2012 survey appears to be a reversion to the pre-removal bed elevation for that cross section. In addition to the changes highlighted from the channel surveys, we identified several changes in 2012 relative to the as-built condition from the visual inspection (Appendix E) of the engineered riffles, log jams, and vegetated soil lifts. The primary change visually noted at the engineered riffles was the exposure of the large blocks of rocks making up the ribs for each riffle. The ribs were exposed for all three riffles: primarily on the banks for the middle and downstream riffles, and across the entire channel for the most upstream riffle. For the engineered log jams, all structures remained largely intact. We observed small amounts of upstream sediment accumulation at the most downstream river left and most upstream river right jams. Moderate amounts of erosion occurred upstream and adjacent to the other two river left jams and the river right jam immediately upstream of the bank failure, between and cross sections. Finally, five of the nine vegetated soil lift were completely intact and growing. Approximately 1/3 to all of the structure s length washed away from the remaining four lifts. 36

37 Figure 30: Longitudinal profile for Sodom Channel. Figure 31: Change in area at cross sections in the area around Sodom Dam. Positive values represent deposition and negative values represent erosion. 37

38 4.2.2 Shearer Dam There were few changes in the bed and banks of the former Shearer Dam reservoir area and immediately downstream between the as-builts and 2012 surveys (Figure 32, Appendix C). The largest changes in cross sectional area were on the river left bank of cross sections at and directly adjacent to the former dam location (Figure 33). Figure 32: Longitudinal profile for the Calapooia River at Shearer Dam Figure 33: Net change in cross sectional area from as-built to 2012 for cross sections in the former Shearer Dam reservoir and downstream 38

39 4.3 Discharge and flow splits The project sites experienced several moderately-sized storm events over the study period (Figure 35). Unfortunately, the range of the pressure transducer installed at Sodom Channel at Linn West Drive was insufficient to capture the peak for several storms as indicated by the dashed line in Figure 34. Thus, discharges above the dashed gray line was estimated based on relationships with nearby USGS-gaged streams (Mohawk River near Springfield: , South Santiam below Cascadia: ). However, we also note that peaks above the range of the pressure transducer were primarily those that overtopped banks upstream and downstream of the gaging station and therefore difficult to accurately capture anyway. Prior to project implementation, the gaging station at Sodom Channel at Linn West Drive captured several storm events, including the annual peak. We estimate that this event has a recurrence interval of 1.6 to 3.4 years. After the project, similarly sized and larger events occurred. The largest event in January of 2012, with a recurrence interval estimated to be between 1.8 and 5.6 years. The split of flow between the historical Calapooia River and Sodom Channel was highly unequal prior to the dam removal and did not appear to vary with discharge (Table 3, Figure 36). Post-project ratios varied more with discharge, such that more flow was conveyed down the historical Calapooia during moderate discharges (e.g. 12/22/11) and less flow was conveyed down the historical as discharge increased (Table 2). Thus, more higher flow events were conveyed down the historical Calapooia in 2012, both because 2012 was a wetter year and because the historical Calapooia conveys relatively more of the moderate flows than pre-project. Table 3. Percent of Brownsville flows that are conveyed down historical Calapooia River. Note that ratios are relative; At higher flows, more tributaries are activated and thus the flows at the Brownsville gage become less representative of flows just above the bifurcation. Results are sorted in increasing values of flow at Brownsville. Date Historical Calapooia at Linn West (cfs) Brownsville (cfs) Percent of Brownsville flow in historical Calapooia 2/8/ /8/ /7/ /18/ /16/ /22/ /4/ /24/ /22/ /22/

40 Figure 34: Calculated and measured discharge on the Calapooia River at Brownsville, the Calapooia River at Linn West Drive, and Sodom Channel at Linn West Drive. 40

41 Figure 35: Calculated discharge on the Calapooia River at Brownsville and Sodom Channel at Linn West Drive. The ratio of discharges for Sodom Channel at Linn West Drive and the Calapooia River at Linn West Drive relative to the Calapooia River at Brownsville are presented on the secondary y-axis. 5. Summary and future work The removal of Sodom and Shearer dams appears to have limited effects on the channel morphology or ecological of the Calapooia River system. The most obvious effects are those on the flow split; more of the low and moderate flows are conveyed through the historical Calapooia River (Figure 36, Table 3). Some morphological changes were observed, including variability in the longitudinal profiles (Figures 19 and 20) and streambank conditions (Table 2), but could not be conclusively linked to the dam removals or changes in flow splits. No clear evidence of effect from the projects on temperature, vegetation, fish, or various features of the channel habitat was observed. Further analysis, underway, is needed to a) link streambank changes to veg changes, and b) characterize streambank stability, using the USDA s Bank Stability and Toe Erosion Model (BSTEM) model, to identify mechanisms for observed changes in streambank geometry. 41

42 6. Literature Cited Calapooia Watershed Council Sodom Shearer Dams Fish Passage Improvement and Flow Management. Accessed January 17, Kaufmann, P.R, P. Levine, E.G. Robison, C. Seeliger, and D.V. Peck Quantifying Physical Habitat in Wadeable Streams. EPA/620/R-99/003. U.S. Environmental Protection Agency, Washington, D.C. Kennedy, E. J Computation of Continuous Records of streamflow. Techniques of Water- Resources Investigations of the United States Geological Society Chapter A13. Kennedy, E. J Discharge Ratings at Gaging Stations. Techniques of Water-Resources Investigations of the United States Geological Society Chapter A10. Mueller, David S., and Wagner, Chad R Measuring Discharge with Acoustic Doppler Current Profilers from a Moving Boat. U.S. Geological Survey Techniques and Methods 3A- 22. Oregon Parks and Recreation Department (OPRD) Thompson s Mills State Heritage Site, Master Plan. Peck, D. V., A. T. Herlihy, B. H. Hill, R. M. Hughes, P. R. Kaufmann, D. J. Klemm, J. M. Lazorchak, F. H. Mc Cormick, S. A. Peterson, P. L. Ringold, T. Magee, and M. R. Cappaert Environmental Monitoring and Assessment Program: Surface Waters Western Pilot Study-field operations manual for wadeable streams. EPA 620/R-06/003. US Environmental Protection Agency, Washington, DC. Rantz, S.E. and others, Measurement and Computation of Streamflow: Volume 1. Measurement of Stage and Discharge. Geological Survey Water Supply Paper Runyon J, Andrus C, Schwindt R Calapooia River Watershed Assessment. Calapooia Watershed Council: Brownsville, OR. Tetra Tech Preliminary Assessment and Conceptual Site Model: Sodom Dam Conversion Project, Calapooia River/Sodom Channel. Linn Country, OR. Prepared for Oregon Parks and Recreation Department and the Army Corps of Engineers. 42

Appendix E: Methods of Collecting Macroinvertebrates in Streams

Appendix E: Methods of Collecting Macroinvertebrates in Streams Quality Assurance Project Plan DuPage-Salt Creek Assessment Revision 1.0 July 1, 2006 Appendix E Appendix E: Methods of Collecting Macroinvertebrates in Streams 1 Methods of Collecting Macroinvertebrates

More information

Mill Creek Restoration in Lower Merion Township. PH (610) ; FAX (610) ;

Mill Creek Restoration in Lower Merion Township. PH (610) ; FAX (610) ; Mill Creek Restoration in Lower Merion Township Vincent L. Sortman 1 and Robert M. Lambert 2 1 Biohabitats, Inc., 15 W. Aylesbury Road, Timonium, MD 21093; PH (410) 337-3659; FAX (410) 583-5678; email:

More information

Old Mill School Stream Restoration

Old Mill School Stream Restoration Project Overview This conceptual plan restores and stabilizes two consecutive reaches of a highly incised and unstable stream and reconnects them with the floodplain. The restoration reaches are part of

More information

The Influence of LWD and Tributary Confluences on the Local Grain Size Distributions of the H.J. Andrews Stream Network

The Influence of LWD and Tributary Confluences on the Local Grain Size Distributions of the H.J. Andrews Stream Network The Influence of LWD and Tributary Confluences on the Local Grain Size Distributions of the H.J. Andrews Stream Network Brent Davis Abstract The influence of Large Woody Debris (LWD) and tributary confluences

More information

Developing a multi-metric habitat index for wadeable streams in Illinois (T-25-P-001).

Developing a multi-metric habitat index for wadeable streams in Illinois (T-25-P-001). T E C H N I C A L R E P O R T Developing a multi-metric habitat index for wadeable streams in Illinois (T-25-P-001). Annual Segment Report to the Illinois Department of Natural Resources. Leon C. Hinz

More information

Freight Street Development Strategy

Freight Street Development Strategy Freight Street Development Strategy Appendix B: Naugatuck River Floodplain Analysis Freight Street Development Strategy DECEMBER 2017 Page B-1 1.0 NAUGATUCK RIVER FLOODPLAIN AT FREIGHT STREET 1.1 Watershed

More information

Case Study 15. Moonlight Crossing Concrete Box Vented Ford

Case Study 15. Moonlight Crossing Concrete Box Vented Ford Appendix A Case Study 15 Case Study 15. Moonlight Crossing Concrete Box Vented Ford Location Northeastern California. Plumas National Forest. On Lights Creek, 8 miles north of Taylorsville, CA., Forest

More information

Watershed Hydrology: Go with the flow. Greg Jennings, PhD, PE

Watershed Hydrology: Go with the flow. Greg Jennings, PhD, PE Watershed Hydrology: Go with the flow Greg Jennings, PhD, PE jenningsenv@gmail.com Streams What are your CHALLENGES? Hydrology too much water Pollutants upstream and on-site Vegetation wrong plants, wrong

More information

INTERMEDIATE BMI ASSESSMENT TIER 2 FIELD SHEET

INTERMEDIATE BMI ASSESSMENT TIER 2 FIELD SHEET INTERMEDIATE BMI ASSESSMENT TIER 2 FIELD SHEET PHYSICAL PARAMETERS ASSESSMENT FIELD SHEET ALL TIERS NAME: DATE: TIME: STREAM OR RIVER NAME: WATERSHED NAME: TOWN: WEATHER PRESENT PAST 48 HOURS SITE DESCRIPTION

More information

Case Study 19. Mill Creek Embedded Box Culvert Vented Ford

Case Study 19. Mill Creek Embedded Box Culvert Vented Ford Case Study. Mill Creek Embedded Box Culvert Vented Ford Location Southeast Missouri. Mark Twain National Forest; Houston-Rolla Ranger District. Southeast of Rolla, south of Interstate 44, off of State

More information

Stream Restoration in the Urban Environment Concepts and Considerations

Stream Restoration in the Urban Environment Concepts and Considerations Stream Restoration in the Urban Environment Concepts and Considerations The Restoration of Our Rivers; October 5, 2012 Matthew A. Van Eps, PE & Sandi J. Formica: Watershed Conservation Resource Center

More information

ODFW AQUATIC INVENTORY PROJECT RESTORATION MONITORING STREAM HABITAT REPORT

ODFW AQUATIC INVENTORY PROJECT RESTORATION MONITORING STREAM HABITAT REPORT ODFW AQUATIC INVENTORY PROJECT RESTORATION MONITORING STREAM HABITAT REPORT STREAM: GCG: 5-SC SITE ID: 466 BASIN: ROGUE TREATMENT DATE: 2 SURVEY DATE: 7/29/23 SURVEY CREW: USGS MAPS: ECOREGION: REPORT

More information

Summary of Flow and Water Quality Conditions Willamette Basin Science Review February 4-6, 2014

Summary of Flow and Water Quality Conditions Willamette Basin Science Review February 4-6, 2014 Summary of Flow and Water Quality Conditions Willamette Basin Science Review February 4-6, 2014 Prepared by: U.S. Army Corps of Engineers, Portland District, January 2014 The following document summarizes

More information

Chapter 3 Stream Discharge

Chapter 3 Stream Discharge Chapter 3 Stream Discharge - Introductory Level Volunteer Water Quality Monitoring Training Notebook - What is Discharge (Flow)? Discharge, also called flow, is the amount of water that flows past a given

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Ongoing and Completed Studies

Ongoing and Completed Studies Attachment 2 Ongoing and Completed Studies 2014 Monitoring and Analysis Plan November 2013 Attachment 2 Ongoing and Completed Studies 1 Introduction In 2013, the small interdisciplinary study groups for

More information

Appendix A. Location of Transects, Study Sections, Instream Structures and U.S. Geological Survey Gage Stations -Russian River and Lower Dry Creek

Appendix A. Location of Transects, Study Sections, Instream Structures and U.S. Geological Survey Gage Stations -Russian River and Lower Dry Creek scanned for KRIS Appendix A Location of Transects, Study Sections, Instream Structures and U.S. Geological Survey Gage Stations -Russian River and Lower Dry Creek Symbols used are defined in the following

More information

Developing a multi-metric habitat index for wadeable streams in Illinois (T-25-P-001).

Developing a multi-metric habitat index for wadeable streams in Illinois (T-25-P-001). T E C H N I C A L R E P O R T Developing a multi-metric habitat index for wadeable streams in Illinois (T-25-P-001). Annual Segment Report to the Illinois Department of Natural Resources. Laura L. Sass,

More information

Measurement of Stream Discharge. Using Weirs and Flumes

Measurement of Stream Discharge. Using Weirs and Flumes Maine Geologic Facts and Localities March, 2012 Using Weirs and Flumes Text by Daniel B. Locke, Department of Agriculture, Conservation & Forestry 1 Introduction Hydrologists, hydrogeologists, engineers,

More information

FORM B: DAMMING AND DIVERSION OF WATER

FORM B: DAMMING AND DIVERSION OF WATER APPLICATION FOR RESOURCE CONSENT FORM B: DAMMING AND DIVERSION OF WATER NOTES Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan

More information

Forest Practices Technical Note Number 5. Determining the 50-Year Peak Flow and Stream Crossing Structure Size for New and Replacement Crossings

Forest Practices Technical Note Number 5. Determining the 50-Year Peak Flow and Stream Crossing Structure Size for New and Replacement Crossings Forest Practices Technical Note Number 5 Determining the 50-Year Peak Flow and Stream Crossing Structure Size for New and Replacement Crossings Introduction Version 1.0: Effective May 10, 2002 The objective

More information

Case Study 12. Grubbs Concrete Slab Vented Ford

Case Study 12. Grubbs Concrete Slab Vented Ford Appendix A Case Study Case Study. Grubbs Concrete Slab Vented Ford Location North central California. Plumas National Forest. Mount Hough Ranger District. Grizzly Creek. 3 miles west of Bucks Lake, CA.

More information

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013 United States Department of Agriculture Natural Resources Conservation Service Denver Federal Center Building 56, Room 2604 P.O. Box 25426 Denver, CO 80225 720-544-2818-OFFICE alton.albin@co.usda.gov Flood

More information

RIPARIAN CORRIDOR STUDY FINAL PARLEYS CREEK MANAGEMENT PLAN TABLE OF CONTENTS

RIPARIAN CORRIDOR STUDY FINAL PARLEYS CREEK MANAGEMENT PLAN TABLE OF CONTENTS TABLE OF CONTENTS 1.0 INTRODUCTION... 1-1 Riparian Corridor Study and Management Plan Goals... 1-1 Study Area... 1-2 Importance and Functions of Riparian Corridors... 1-2 Habitat for Mammals, Birds, and

More information

Riparian Ecology Station OBJECTIVES

Riparian Ecology Station OBJECTIVES Riparian Ecology Station OBJECTIVES Students learn The basic definition of a riparian area. The condition of any riparian area greatly affects the water quality and aquatic habitat of the water body it

More information

Public Notice. Public Notice No. Date: April 8, 2016 CENAP-PL-E Comment Period Closes: May 9, 2016

Public Notice. Public Notice No. Date: April 8, 2016 CENAP-PL-E Comment Period Closes: May 9, 2016 Public Notice Public Notice No. Date: April 8, 2016 CENAP-PL-E-16-02 Comment Period Closes: May 9, 2016 USACE Philadelphia District: http://www.nap.usace.army.mil COBBS CREEK FISH PASSAGE PROJECT SECTION

More information

Appendix H: Stream Habitat Assessment

Appendix H: Stream Habitat Assessment Appendix H: Stream Habitat Assessment H CH2MHill and Greenways Incorporated conducted Stream Habitat Assessments on several streams throughout Wake County to determine the affect of development density

More information

Ithaca Creek Habitat Monitoring

Ithaca Creek Habitat Monitoring Ithaca Creek Habitat Monitoring My name is: Class: Date: Ithaca Creek is part of the Catchment. Today when I was walking at the creek I decided that I wanted to investigate how healthy my waterway was.

More information

LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C

LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C90593066 PARTNERS Alabama Department of Environmental Management Cawaco

More information

Use of WARSSS in Stream Restoration and Watershed Planning. Michigan Aquatic Restoration Conference 2015

Use of WARSSS in Stream Restoration and Watershed Planning. Michigan Aquatic Restoration Conference 2015 Use of WARSSS in Stream Restoration and Watershed Planning Michigan Aquatic Restoration Conference 2015 October 22, 2015 Use of WARSSS in Stream Restoration and Watershed Planning 1. Watershed Management

More information

WQPBWMSSOP-03 Rev# 01 03/15/2010 FIELD METHODOLOGY FOR THE ASSESSMENT OF TMDL SEDIMENT AND HABITAT IMPAIRMENTS

WQPBWMSSOP-03 Rev# 01 03/15/2010 FIELD METHODOLOGY FOR THE ASSESSMENT OF TMDL SEDIMENT AND HABITAT IMPAIRMENTS WQPBWMSSOP-03 Rev# 01 03/15/2010 FIELD METHODOLOGY FOR THE ASSESSMENT OF TMDL SEDIMENT AND HABITAT IMPAIRMENTS Montana Department of Environmental Quality 1520 East Sixth Avenue Helena, Montana 59620 March

More information

Stream Restoration Raccoon Creek A Case Study

Stream Restoration Raccoon Creek A Case Study Stream Restoration Raccoon Creek A Case Study Restoration of a Degraded Stream System Steven Glickauf Presentation Overview Stream Restoration Raccoon Creek Restoration Site Case Study Existing Conditions

More information

General Construction

General Construction General Construction Terms and Conditions: 1. Flagging sensitive areas. The action area will be flagged to identify sensitive resource areas, such as the extent of herbicide buffers, areas below ordinary

More information

Appendix H. Fish Habitat Survey Data Sheets

Appendix H. Fish Habitat Survey Data Sheets Appendix H Fish Habitat Survey Data Sheets 06-00 DNR&E / DFO - NEW BRUNSWICK 1 of 3 STREA SURVEY and HABITAT ASSESSENT River: Winter Creek Start Point: End Point : Stream/River No. Personnel: SC Date:

More information

Klamath Hydroelectric Settlement Agreement Interim Measure 7 J.C. Boyle Gravel Monitoring Report 2012

Klamath Hydroelectric Settlement Agreement Interim Measure 7 J.C. Boyle Gravel Monitoring Report 2012 Klamath Hydroelectric Project FERC Project No. 2082 Klamath Hydroelectric Settlement Agreement Interim Measure 7 J.C. Boyle Gravel Monitoring Report 2012 Prepared by Prepared for July 2013 KLAMATH HYDROELECTERIC

More information

Application for resource consent Form B Damming and diversion of water

Application for resource consent Form B Damming and diversion of water Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or

More information

CIP-01: Stream Channel Stabilization, Silver Creek

CIP-01: Stream Channel Stabilization, Silver Creek CIP-01 CIP-01: Stream Channel Stabilization, Silver Creek HIGHEST PRIORITY This project consists of stream channel stabilization to address channel incision and the replacement of two cross-culverts. Preferred

More information

PROJECT SCREENING MATRIX: A User s Guide

PROJECT SCREENING MATRIX: A User s Guide Version 2.0 Page 1 of 7 November 9, 2010 PROJECT SCREENING MATRIX: A User s Guide BACKGROUND The Project Screening Matrix (Screening Matrix) is one of several tools that comprise the River Restoration

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

TABLE OF CONTENTS. TOC-i

TABLE OF CONTENTS. TOC-i TOC-i TABLE OF CONTENTS 1.0 INTRODUCTION... 1-1 Riparian Corridor Study and Management Plan Goals... 1-1 Study Area... 1-2 Importance and Functions of Riparian Corridors... 1-2 Habitat for Mammals, Birds,

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

STREAM INVENTORY REPORT PUDDING CREEK

STREAM INVENTORY REPORT PUDDING CREEK STREAM INVENTORY REPORT PUDDING CREEK WATERSHED OVERVIEW Pudding Creek is a tributary to the Pacific Ocean (Figure 1). Elevations range from sea level at the mouth of the creek to 1,600 feet in the headwater

More information

Hydrology Attribute 1/15/2016. California Rapid Assessment Method for Wetlands. Hydrology. Precipitation Increases the Extent of Wetlands

Hydrology Attribute 1/15/2016. California Rapid Assessment Method for Wetlands. Hydrology. Precipitation Increases the Extent of Wetlands California Rapid Assessment Method for Wetlands Hydrology Attribute Hydrology Determines existence of wetlands, drives primary physical and ecological processes: Establishment of reducing conditions Nutrient

More information

Social, Economic, and Environmental impacts of Brownsville Dam Removal

Social, Economic, and Environmental impacts of Brownsville Dam Removal Social, Economic, and Environmental impacts of Brownsville Dam Removal Desiree Tullos, PhD Denise Lach, PhD Jack Zunka Trent Carmichael Cara Walter http://home.netcom.com/~horse/digitarium.html Who we

More information

IMPROVING OUTCOMES FOR STREAM ALTERATION PROJECTS

IMPROVING OUTCOMES FOR STREAM ALTERATION PROJECTS IMPROVING OUTCOMES FOR STREAM ALTERATION PROJECTS Bethany Matousek Inland Lakes and Streams Program Coordinator Wetlands, Lakes and Streams Unit DEQ Water Resources Division MatousekB@Michigan.gov 517-243-6421

More information

Calapooia River Fish Passage Analysis and Culvert Removal Proposal

Calapooia River Fish Passage Analysis and Culvert Removal Proposal Calapooia River Fish Passage Analysis and Culvert Removal Proposal Submitted to: Calapooia Watershed Council P.O. Box 844 Brownsville, OR 97327 Prepared by: Oregon State University Department of Biological

More information

REMAP approach produce unbiased estimates of conditions Random site selection Measure fish and macroinvertebrate populations, chemistries (water,

REMAP approach produce unbiased estimates of conditions Random site selection Measure fish and macroinvertebrate populations, chemistries (water, REMAP approach produce unbiased estimates of conditions Random site selection Measure fish and macroinvertebrate populations, chemistries (water, sediment, fish tissue) and habitat (instream, steam banks,

More information

BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas

BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas The Executive Council of the Chesapeake Bay Program defines a Riparian Forest Buffer as "an area of trees, usually accompanied by shrubs and other vegetation,

More information

Constructed Wetland Channel T-9

Constructed Wetland Channel T-9 Description A constructed wetland channel is a conveyance BMP that is built, in part, to enhance stormwater quality. Constructed wetland channels use dense vegetation to slow down runoff and allow time

More information

Case Study 5. Willow Creek Concrete Plank Ford

Case Study 5. Willow Creek Concrete Plank Ford Appendix A Case Study Case Study. Willow Creek Concrete Plank Ford Location Northeastern California. Plumas National Forest. Willow Creek. miles northwest of Portola, CA, on Spur Road 23N97Y off Forest

More information

THE EFFECTS OF URBANIZATION ON THE MINGO CREEK WATERSHED

THE EFFECTS OF URBANIZATION ON THE MINGO CREEK WATERSHED THE EFFECTS OF URBANIZATION ON THE MINGO CREEK WATERSHED by Tim Marshall (presented at the Sixth Conference on Hydrometeorology in Indianapolis, IN, 1984) 1. INTRODUCTION Urbanization of flood plains presents

More information

Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring

Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring Prepared for: Urban Drainage and Flood Control District 2480 W. 26 th Avenue Suite 156-B Denver, CO 80211 May 19, 2006 (Rev

More information

MONTEREY PENINSULA WATER MANAGEMENT DISTRICT PROJECT DESCRIPTION FOR SELECTIVE VEGETATION MANAGEMENT AND BANK RESTORATION (RANCHO SAN CARLOS AREA)

MONTEREY PENINSULA WATER MANAGEMENT DISTRICT PROJECT DESCRIPTION FOR SELECTIVE VEGETATION MANAGEMENT AND BANK RESTORATION (RANCHO SAN CARLOS AREA) MONTEREY PENINSULA WATER MANAGEMENT DISTRICT PROJECT DESCRIPTION FOR SELECTIVE VEGETATION MANAGEMENT AND BANK RESTORATION (RANCHO SAN CARLOS AREA) IN THE CARMEL RIVER CHANNEL, SUMMER AND FALL 2014 SELECTIVE

More information

Environmental Assessment Form Part 1 Resource Identification Enclosure C Description of Aquatic Habitat

Environmental Assessment Form Part 1 Resource Identification Enclosure C Description of Aquatic Habitat Environmental Assessment Form Part 1 Resource Identification Enclosure C Description of Aquatic Habitat 8. Provide a written narrative, identified and labeled as Enclosure C Description of Aquatic Habitat,

More information

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment

More information

2012 Mill Creek Watershed Habitat Assessment Level 3 Project Study Plan Results

2012 Mill Creek Watershed Habitat Assessment Level 3 Project Study Plan Results 2012 Mill Creek Watershed Habitat Assessment Level 3 Project Study Plan Results Cranberry Run This project study plan was financed through a Sub-grant from the Ohio EPA with funds from the State of Ohio.

More information

Green CCR Landfill. Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2016 Annual Inspection Report

Green CCR Landfill. Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2016 Annual Inspection Report Green CCR Landfill Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2016 Annual Inspection Report January 10, 2017 Prepared By: Project ID: 160122B Big Rivers

More information

RIPARIAN CORRIDOR STUDY FINAL CITY CREEK MANAGEMENT PLAN TABLE OF CONTENTS

RIPARIAN CORRIDOR STUDY FINAL CITY CREEK MANAGEMENT PLAN TABLE OF CONTENTS TABLE OF CONTENTS 1.0 INTRODUCTION... 1-1 Riparian Corridor Study and Management Plan Goals... 1-1 Study Area... 1-2 Importance and Functions of Riparian Corridors... 1-2 Habitat for Mammals, Birds, and

More information

4. Present Activities and Roles

4. Present Activities and Roles 4. Present Activities and Roles The present missions, authorities, activities and roles of the various agencies involved with flood protection, floodplain management and flood-damage reduction are identified

More information

Section 6: Stormwater Improvements

Section 6: Stormwater Improvements Section 6: Stormwater Improvements A major objective of this study was to identify opportunities for improvements to address the widespread water quality impairments caused by stormwater runoff in the

More information

APPENDIX 8. NORTHERN GROUND ELECTRODE LINE WATERCOURSE CROSSING ASSESSMENT BOOKLETS

APPENDIX 8. NORTHERN GROUND ELECTRODE LINE WATERCOURSE CROSSING ASSESSMENT BOOKLETS APPENDIX 8. NORTHERN GROUND ELECTRODE LINE WATERCOURSE CROSSING ASSESSMENT BOOKLETS Aquatic Environment November 2011 Bipole III Transmission Project Construction Camp CC1 Location Datum: NAD 83 UTM: Zone:

More information

Lessons Learned from the Jocko River Demonstration Project

Lessons Learned from the Jocko River Demonstration Project Lessons Learned from the Jocko River Demonstration Project Applied Adaptive Management Matt Daniels, P.E. Presentation Objectives Provide a brief overview of the project context. Describe the monitoring

More information

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat S.R. 4007, Section 14B PADEP Environmental Assessment Form Description of Aquatic Habitat Cresheim Creek is the only water resource that exists within the project area. No jurisdictional wetlands were

More information

COTTON CREEK CULVERT REPLACMENT

COTTON CREEK CULVERT REPLACMENT COTTON CREEK CULVERT REPLACMENT Integrating Mobility with Environmental Innovation Located along a scenic section of Highway 3/95 in British Columbia, Moyie Bluffs, a 6.5 km stretch of inland highway had

More information

CHAPTER 1. Ecological Integrity

CHAPTER 1. Ecological Integrity CHAPTER 1 Ecological Integrity RIPARIAN RESTORATION ECOLOGICAL INTEGRITY This chapter suggests a broad interpretation of the riparian ecosystem and its influences. Often riparian ecosystems are described

More information

Section 4. Mono Basin Tributaries: Lee Vining, Rush, Walker, and Parker Creeks. Monitoring Results and Analysis For Runoff Season

Section 4. Mono Basin Tributaries: Lee Vining, Rush, Walker, and Parker Creeks. Monitoring Results and Analysis For Runoff Season Section 4 Mono Basin Tributaries: Lee Vining, Rush, Walker, and Parker Creeks Monitoring Results and Analysis For Runoff Season 2009-10 Mono Basin Tributaries: Lee Vining, Rush, Walker, and Parker Creeks

More information

WRPI: Water Resources and Policy Initiatives Final Report. Stream Condition Inventory Cottonwood Campground Lake Elizabeth Canyon Stream, CA

WRPI: Water Resources and Policy Initiatives Final Report. Stream Condition Inventory Cottonwood Campground Lake Elizabeth Canyon Stream, CA WRPI: Water Resources and Policy Initiatives Final Report Stream Condition Inventory Cottonwood Campground Lake Elizabeth Canyon Stream, CA Jonathan I. Tejeda California State University, Northridge June

More information

The Science Behind Forest Riparian Protection in the Pacific Northwest States By George Ice, Summer 2004

The Science Behind Forest Riparian Protection in the Pacific Northwest States By George Ice, Summer 2004 The Science Behind Forest Riparian Protection in the Pacific Northwest States By George Ice, Summer 2004 Riparian buffers, streamside management zones, and similar measures are essential parts of forest

More information

Prepared by: PacifiCorp 825 NE Multnomah Street Portland, OR 97232

Prepared by: PacifiCorp 825 NE Multnomah Street Portland, OR 97232 Wallowa Falls Hydroelectric Project (FERC No. P-308) Grande Ronde River Basin Wallowa County, Oregon June 2, 2017 Prepared by: PacifiCorp 825 NE Multnomah Street Portland, OR 97232 Table of Contents 1.0

More information

Jacobi, Toombs, and Lanz, Inc.

Jacobi, Toombs, and Lanz, Inc. Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations

More information

Logan River at Rendezvous Park, Channel and Floodplain Restoration: Crack Willow (Salix fragilis) Issues and Management Strategies

Logan River at Rendezvous Park, Channel and Floodplain Restoration: Crack Willow (Salix fragilis) Issues and Management Strategies Logan River at Rendezvous Park, Channel and Floodplain Restoration: Crack Willow (Salix fragilis) Issues and Management Strategies Prepared May 2, 2017 by Darren Olsen, BIO-WEST, Inc. Issues Crack willow

More information

The Status of Rainbow Trout (Oncorhynchus mykiss) in the Stanislaus River Summary report of 2015 snorkel surveys

The Status of Rainbow Trout (Oncorhynchus mykiss) in the Stanislaus River Summary report of 2015 snorkel surveys The Status of Rainbow Trout (Oncorhynchus mykiss) in the Stanislaus River Summary report of 2015 snorkel surveys Prepared By: Matt Peterson Jason Guignard Andrea Fuller Doug Demko FISHBIO 1617 S. Yosemite

More information

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc. ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975 Source: Hey and Associates, Inc. DEFINITION A bridge or culvert crossing installed across a stream or watercourse for short-term

More information

Development of a Stage-Discharge Rating for Site Van Bibber Creek at Route 93

Development of a Stage-Discharge Rating for Site Van Bibber Creek at Route 93 Development of a Stage-Discharge Rating for Site 330 - Van Bibber Creek at Route 93 Prepared for: Urban Drainage and Flood Control District 2480 W. 26 th Avenue Suite 156-B Denver, CO 80211 May 19, 2006

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Stream Watch Visual Survey Instructions

Stream Watch Visual Survey Instructions Stream Watch Visual Survey Instructions The Stream Watch Visual Survey is based on assessment parameters from the EPA's Rapid Bioassessment Protocol Habitat Assessment, Georgia Adopt a Stream Visual Survey,

More information

Fish Passage Design for Roughened Channels. Pre-Presentation Note

Fish Passage Design for Roughened Channels. Pre-Presentation Note NOAA 9/23/2010 Science, Service, Stewardship Aaron Beavers Hydraulic Engineer Fish Passage Design for Roughened Channels Northwest Region E.I.T. M.S.C.E. NOAA FISHERIES SERVICE Pre-Presentation Note The

More information

A modelling framework to predict relative effects of forest management strategies on coastal stream channel morphology and fish habitat

A modelling framework to predict relative effects of forest management strategies on coastal stream channel morphology and fish habitat A modelling framework to predict relative effects of forest management strategies on coastal stream channel morphology and fish habitat by FRANK STEFAN PETER HEINZELMANN A THESIS SUBMITTED IN PARTIAL FULFILLMENT

More information

Context of Extreme Alberta Floods

Context of Extreme Alberta Floods Context of Extreme Alberta Floods Introduction Design of water management and stream crossing infrastructure requires determination of hydrotechnical design parameters. These parameters often consist of

More information

DRAFT MONITORING REPORT LELAND-DOUGLAS HABITAT RESTORATION PROJECT

DRAFT MONITORING REPORT LELAND-DOUGLAS HABITAT RESTORATION PROJECT DRAFT MONITORING REPORT LELAND-DOUGLAS HABITAT RESTORATION PROJECT Prepared for Stillaguamish Tribe of Indians Prepared by Anchor QEA, LLC 1605 Cornwall Avenue Bellingham, Washington 98225 October 2013

More information

Chapter 2 Site Selection

Chapter 2 Site Selection Chapter 2 Site Selection Before you start monitoring water quality, you must first select a site to monitor. This chapter will explore many factors for selecting an appropriate stream site to monitor.

More information

Temporary Stream Crossing

Temporary Stream Crossing Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Temporary Stream Crossing

Temporary Stream Crossing Temporary Stream Crossing NS-4 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution

More information

Tucannon Restoration Science Workshop Field Tour Booklet (May 24 th 2018)

Tucannon Restoration Science Workshop Field Tour Booklet (May 24 th 2018) Tucannon Restoration Science Workshop Field Tour Booklet (May 24 th 2018) Field Tour Agenda: 8:20 am Meet at the SRSRB office We will meet at the SRSRB office to load the bus and ride to the Last Resort

More information

SWAP Risk Informed Methods for Stormwater Assessment and Prioritization

SWAP Risk Informed Methods for Stormwater Assessment and Prioritization SWAP Risk Informed Methods for Stormwater Assessment and Prioritization Sara Hillegas Woida, Hydraulic Engineer US Army Corps of Engineers, Pittsburgh Thomas Maier, Biologist/Planner US Army Corps of Engineers,

More information

SUMMARY OF INDIAN MILL CREEK WATERSHED ASSESSMENT KENT, MICHIGAN

SUMMARY OF INDIAN MILL CREEK WATERSHED ASSESSMENT KENT, MICHIGAN SUMMARY OF INDIAN MILL CREEK WATERSHED ASSESSMENT KENT, MICHIGAN INTRODUCTION BY: MARY SIEVERT, STUDENT ASSISTANT AND JANICE TOMPKINS, SENIOR WATER QUALITY ANALYST FIELD OPERATION SECTION WATER DIVISION

More information

CLAY STREET BRIDGE REPLACEMENT

CLAY STREET BRIDGE REPLACEMENT HYDROLOGY /HYDRAULICS REPORT. EL DORADO COUNTY CLAY STREET BRIDGE REPLACEMENT Prepared by: Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762

More information

Calapooia River Fish Passage

Calapooia River Fish Passage Calapooia River Fish Passage Engineering Design Report Spring, 2013 Image credit: Chris Gifford-Miears Contents 1 Background and Existing Conditions... 2 1.1 Location... 2 1.2 Project Goals... 3 1.3 Watershed

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

Enhancing Straightened River Channels

Enhancing Straightened River Channels .6 Creating a sinuous low flow channel in an over-widened river River Dearne Location - Mexborough, West of Doncaster, South Yorkshire SE484012 Date of construction - Summer 1995 Length - 500m Cost - 4,000

More information

Designing roads for fish, floods and foxes

Designing roads for fish, floods and foxes Designing roads for fish, floods and foxes Calculations 9 Swimming Plunging Flow & Leaping Occupied Velocity Prolonged > Capability Yes Swim in Burst Total Time in Burst Time to > Exhaustion Yes Barrier

More information

City of River Falls North Kinnickinnic River Monitoring Project Summary. Report prepared by SEH Inc., for the

City of River Falls North Kinnickinnic River Monitoring Project Summary. Report prepared by SEH Inc., for the City of River Falls North Kinnickinnic River Monitoring Project 2012 Summary Report prepared by SEH Inc., for the City of River Falls Engineering Department December 2012 Project Introduction: City of

More information

MILL CREEK FISH PASSAGE CONCEPTUAL DESIGNS FINAL REPORT

MILL CREEK FISH PASSAGE CONCEPTUAL DESIGNS FINAL REPORT MILL CREEK FISH PASSAGE CONCEPTUAL DESIGNS FINAL REPORT Prepared for Tri State Steelheaders Contact: Brian Burns 216 N. Roosevelt, PO Box 1375 Walla Walla, WA 99362 Prepared by Waterfall Engineering, L.L.C.

More information

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR 257.82 EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part 257 and Part

More information

Assessing Fish Passage at Culverts the method, its metrics and preliminary findings from over 4,000 assessments.

Assessing Fish Passage at Culverts the method, its metrics and preliminary findings from over 4,000 assessments. Assessing Fish Passage at Culverts the method, its metrics and preliminary findings from over 4,000 assessments. Richard Thompson, Ministry of Environment, Richard.Thompson@gov.bc.ca ABSTRACT There has

More information

Keller and Tally (1979), in a study of the role of woody debris in

Keller and Tally (1979), in a study of the role of woody debris in Persistence of Historical Logging Impacts on Channel Form in Mainstem North Fork Caspar Creek Michael B. Napolitano Abstract: The old-growth redwood forest of North Fork Caspar Creek was clearcut logged

More information

Chehalis Basin Strategy Programmatic SEPA Draft EIS

Chehalis Basin Strategy Programmatic SEPA Draft EIS Chehalis Basin Strategy Programmatic SEPA Draft EIS History of Flooding I-5 closed in 1990, 1996, 2007, 2009 Five largest flood events occurred since 1986 2 History of Habitat Degradation Harvest has been

More information

Towards. Sustainable Forest Management

Towards. Sustainable Forest Management PLUMPER CREEK WATERSHED Towards Sustainable Forest Management Prepared for Nootka Contract March 2004 Prepared for: Reporting by: Shawn Hamilton and Associates Plumper Creek Sustainable Forest Management

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Rascal Goose. Reach 1. Rascal Goose. Reach 2. å å å. Main Goose Pit. Stream Reach 3. Main Goose Pit. Stream Reach 7

Rascal Goose. Reach 1. Rascal Goose. Reach 2. å å å. Main Goose Pit. Stream Reach 3. Main Goose Pit. Stream Reach 7 434000 March 16 2014 434200 434400 ± 434600 434800 435000 Goose Lake 7269800 WRSA B 7269800 7270000 433800 GIS # BAC-06-180a 7270000 PROJECT # 0234411-0005 Rascal Goose Reach 1 Main Goose Pit Stream Reach

More information