Jacobi, Toombs, and Lanz, Inc.

Size: px
Start display at page:

Download "Jacobi, Toombs, and Lanz, Inc."

Transcription

1 Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations for improving storm water management in Area 5 for the Town of Clarksville, Indiana. December 2008

2 AREA 5: BLACKISTON MILL ROAD AT DEADMAN S HOLLOW JTL Consulting Engineers Project Area Overview This report summarizes the project team s assessment and recommendations for Area 5, Blackiston Mill Road at Dead Man s Hollow, which has historically presented maintenance issues and flood hazards for the Town of Clarksville. The existing drainage conduit in this area suffered partial failure and has been slip-lined two times since its original construction. These activities have decreased the effective opening size from a 48-inch x 60-inch concrete box culvert (20.0 ft 2 cross-sectional area) to a 30-inch diameter PVC pipe (4.9 ft 2 cross-sectional area). During rainfall events of significant intensity, the existing 30-inch pipe under Blackiston Mill Road lacks the conveyance capacity to prevent backwater conditions upstream of the road embankment. At times, these high water surface elevations upstream of the structure have led to the overtopping of the roadway and presented public safety hazards and caused road closures. In addition, these conditions present significant challenges to the drainage and roadway maintenance activities of the Clarksville Street Department. The project team comprised of Stantec Consulting Services, Inc. (Stantec) and Jacobi, Toombs and Lanz, Inc. (JTL) conducted physical surveys and performed hydrologic and hydraulic assessments of the project area to determine the nature and extent of the problems and evaluate alternatives for improving drainage and reducing the risk of flooding at this location. Two solutions have been developed and are detailed in this report. These solutions include an in-kind replacement of the existing structure or a structure replacement with roadway improvements. The anticipated costs for improvements to this existing structure under Blackiston Mill Road are estimated to be 425,000. In addition, the anticipated cost for structure replacement and improvements to the roadway alignment is 685,000. E.1

3 AREA 5: BLACKISTON MILL ROAD AT DEADMAN S HOLLOW JTL Consulting Engineers Table of Contents PROJECT AREA OVERVIEW E INTRODUCTION BACKGROUND FLOODING PROBLEMS PROBLEM ASSESSMENT STUDY METHODOLOGY EXISTING CONDITIONS ANALYSIS PROPOSED SOLUTIONS ALTERNATIVE 1: BOX CULVERT ALTERNATIVE 2: BOX CULVERT WITH ROAD IMPROVEMENTS CONCLUSIONS i

4 AREA 5: BLACKISTON MILL ROAD AT DEADMAN S HOLLOW JTL Consulting Engineers 1.0 Introduction This report examines two conceptual alternatives to improve motorist safety and minimize maintenance requirements by reducing the flooding risk along Blackiston Mill Road at Dead Man s Hollow. The project team comprised of Stantec Consulting Services, Inc. (Stantec) and Jacobi, Toombs and Lanz, Inc. (JTL) conducted physical surveys and completed hydrologic and hydraulic assessments to identify the problems in the area and develop alternatives in the project area. Flooding problems in the area of Blackiston Mill Road at Dead Man s Hollow have increased in recent years because of the increased volume and intensity of stormwater runoff. This increased runoff is due to extensive developments in the watershed and degradation and partial failure of the existing structure under Blackiston Mill Road. 1.1 BACKGROUND The project area is located in the central and western portion of the Town of Clarksville, situated between the major intersections of Blackiston Mill Road with Gutford Road and Potters Lane. The existing outfall structure on Blackiston Mill Road is located approximately 600 feet east of Silver Creek. Silver Creek water surface elevations and backwater conditions were considered and incorporated into this design. The structure under Blackiston Mill Road is located in a steeply incised stream valley. The elevation difference from the centerline of the road to the invert of the current structure is approximately 24 feet. This project area is located in the Silver Creek Plum Run HUC14 watershed. According to the Natural Resources Conservation Service (NRCS), soils in this area are composed primarily of hydrologic soil group (HSG) C with some smaller areas containing HSG B. The majority of the area is composed of clayey stratum and silty loams which indicate poor soil infiltration capacity, which often leads to standing stormwater in poorly graded areas or regions with little drainage relief. Only very small regions contain soils which permit moderate infiltration abilities. The 451 acre watershed draining to this structure is composed primarily of residential properties in the lower subcatchments and heavy commercial properties located in the upper subcatchments. The watershed is relatively flat, ranging from 466 feet above sea level (FASL) to 474 FASL. The only area of significant elevation relief is immediately adjacent to the steeply incised ditch. Upstream of Blackiston Mill Road, the central open channel begins at the outlet of a 12-foot x 3-foot concrete box culvert that drains a heavy commercial area along Greentree Boulevard. The existing terrain creates a deep channel with steep slopes on both the upstream and downstream side of Blackiston Mill Road. The significant elevation difference between the channel bed and roadway surface results in a significant amount of storage upstream of the structure prior to flow overtopping the roadway. This causes high flow velocities through the culvert and scour downstream. 1.1

5 AREA 5: BLACKISTON MILL ROAD AT DEADMAN S HOLLOW JTL Consulting Engineers 2.0 Flooding Problems 2.1 PROBLEM ASSESSMENT The drainage structure at Dead Man s Hollow is believed to have originally been a 48-inch x 60- inch box culvert; however, due to structural deterioration, the existing structure was slip-lined with a 42-inch galvanized corrugated metal pipe. Due to further complications, the pipe was slip-lined again with a 30-inch, schedule 35 PVC pipe. These repairs have decreased the effective opening size from a 48-inch x 60-inch (20.0 ft 2 ) box culvert to a 30-inch PVC pipe (4.9 ft 2 ). During large rainfall events, the existing culvert cannot convey enough stormwater to prevent ponding along the upstream embankment of Blackiston Mill Road. Additionally, woody debris and trash accumulate at the structure opening and further reduce the flow capacity. This is a regular maintenance issue for the Clarksville Street Department. Additionally, this inadequate structure has regularly caused backups which overtop the roadway. When this overtopping occurs, it causes hazardous conditions for motorists, and requires immediate action by the Clarksville Street Department to close the roadway to traffic. During these events where overtopping occurs, erosion regularly takes place on the downstream side of the embankment. This also requires regular maintenance by the street department. High entrance and exit velocities occur at this structure due to the elevation of ponded water upstream of the structure. Erosion also occurs when stormwater overtops the roadway and flows down the steep embankment on the downstream side of the roadway. These two erosion problems require regular maintenance from the Clarksville Street Department. 3.0 Study Methodology Hydrologic (HEC-HMS) and hydraulic models (HEC-RAS) were developed to assess the drainage and flooding dynamics of Blackiston Mill Road at Dead Man s Hollow. Soil information from the Natural Resources Conservation Service (NRCS) and land use determined from aerial imagery were used to estimate runoff potential for the subwatersheds in the study area. Peak discharges for 24-hour storm events were estimated using the SCS method. Representative cross sections upstream and downstream of Blackiston Mill Road were surveyed by field crews, and used in the hydraulic model to compute peak water surface elevations. 3.2

6 AREA 5: BLACKISTON MILL ROAD AT DEADMAN S HOLLOW JTL Consulting Engineers 4.0 Existing Conditions Analysis A model representing the downstream portions of the watershed and Silver Creek was developed during this assessment. This model validated observations that the area downstream of Blackiston Mill Road is susceptible to backwater flooding from Silver Creek during a 100-year storm event. Consequently, the proposed improvements will only allow increased stormwater discharges underneath Blackiston Mill Road until the backwater conditions from the Silver Creek reach the same elevation as the proposed box culvert. Refer to Appendix 5A for a map of the watershed draining this area. 5.0 Proposed Solutions 5.1 ALTERNATIVE 1: BOX CULVERT Based upon the hydrologic and hydraulic (H & H) analysis, it was determined that an 8-foot x 10-foot box culvert would control the stormwater in a manner that would allow sufficient flow through the culvert while minimizing backwater conditions and controlling the rate of discharge to a sufficient degree to minimize the potential for downstream flooding. Refer to Appendix 5B for the HEC-HMS and Appendix 5C HEC-RAS results of this assessment. See Appendix 5D for the preliminary construction plan for this structure replacement. The estimated cost for the proposed 8 x10 box culvert is 425,000. A detailed breakdown of the engineer s estimate can be found in Appendix 5E. 5.2 ALTERNATIVE 2: BOX CULVERT WITH ROAD IMPROVEMENTS In addition to the proposed 8-foot x 10-foot box culvert recommended above, further improvements to the grade and alignment of Blackiston Mill Road could be implemented during the installation of the culvert to increase the height of the road and further minimize the potential for overtopping. This would further minimize road closures caused by backwater from Silver Creek. These modifications would also improve the traffic conditions and visibility through this portion of Blackiston Mill Road. The general layout and improved vertical roadway alignment can be found in Appendix 5D. The estimated cost of the proposed box culvert with additional road improvements is 685,000. An engineer s estimate of the proposed stormwater and roadway improvements can be found in Appendix 5F. 5.3

7 AREA 5: BLACKISTON MILL ROAD AT DEADMAN S HOLLOW JTL Consulting Engineers 6.0 Conclusions Blackiston Mill Road at Dead Man s Hollow has historically presented maintenance issues for the Clarksville Street Department and regular flood hazards for motorists. The existing drainage conduit in this area suffered partial failure and has been slip-lined two times since its original construction. These activities have decreased the effective opening of the structure to the point that its ability to sufficiently convey stormwater is no longer adequate, which results in high backwater developing. At times, these high water surface elevations upstream of the structure have led to the overtopping of the roadway and presented public safety hazards and caused road closures. The project team conducted physical surveys and developed hydrologic and hydraulic models to determine the nature and extent of the problems and evaluate alternatives for improving drainage and reducing the risk of flooding at this location. The anticipated costs for improvements to this existing structure under Blackiston Mill Road are estimated to be 425,000. In addition, the anticipated cost for structure replacement and improvements to the roadway alignment is 685,000. It is recommended that Alternative 2 is selected due to the increased roadway elevation. This increased elevation will not only further minimize flooding of Blackiston Mill at Deadman s Hollow, it will also serve to improve roadway geometry, reducing traffic safety hazards during both wet and dry weather. 6.4

8 Appendices

9 Appendix A

10

11 Appendix B

12 Simulation Run Area 5 Blackiston Mill - Existing Culvert Backwater Elevation Q Total (cfs) Min Ch El (ft) W.S. Elev (ft) Crit W.S. (ft) E.G. Elev (ft) Slope (ft/ft) Vel Chnl (ft/s) 24 Hour 1 Year Hour 2 Year Hour 5 Year Hour 10 Year Hour 25 Year Hour 50 Year Hour 100 Year Simulation Run Area 5 Blackiston Mill - Proposed Culvert Backwater Elevation Q Total (cfs) Min Ch El (ft) W.S. Elev (ft) Crit W.S. (ft) E.G. Elev (ft) Slope (ft/ft) Vel Chnl (ft/s) 24 Hour 1 Year Hour 2 Year Hour 5 Year Hour 10 Year Hour 25 Year Hour 50 Year Hour 100 Year

13 Culvert_Analysis Plan: Existing 4/3/2008 River Reach Legend WS 100 Year WS 50 Year WS 25 Year WS 10 Year WS 5 Year WS 2 Year WS 1 Year Ground 450 Elevation (ft) Main Channel Distance (ft)

14 Culvert_Analysis Plan: Proposed Culvert 4/3/2008 River Reach Legend WS 100 Year WS 50 Year WS 25 Year WS 10 Year WS 5 Year WS 2 Year WS 1 Year Ground 450 Elevation (ft) Main Channel Distance (ft)

15 Appendix C

16 Simulation Run Area 5 Blackiston Mill - Existing Conditions HEC-HMS Results Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) 24 Hour 1 Year Subbasin Jan2008, 00: Hour 2 Year Subbasin Jan2008, 00: Hour 5 Year Subbasin Jan2008, 00: Hour 10 Year Subbasin Jan2008, 00: Hour 25 Year Subbasin Jan2008, 00: Hour 50 Year Subbasin Jan2008, 00: Hour 100 Year Subbasin Jan2008, 00:

17 Project: DeadMan Simulation Run: 24 Hour 1 Year Start of Run: 01Jan2008, 12:00 Basin Model: Basin 1 End of Run: 03Jan2008, 12:00 Meteorologic Model: 24Hr-1Yr Compute Time: 02Apr2008, 13:22:24 Control Specifications: Control 1 Volume Units: IN Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) Subbasin Jan2008, 00:

18 Project: DeadMan Simulation Run: 24 Hour 2 Year Start of Run: 01Jan2008, 12:00 Basin Model: Basin 1 End of Run: 03Jan2008, 12:00 Meteorologic Model: 24Hr-2Yr Compute Time: 02Apr2008, 13:23:17 Control Specifications: Control 1 Volume Units: IN Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) Subbasin Jan2008, 00:

19 Project: DeadMan Simulation Run: 24 Hour 5 Year Start of Run: 01Jan2008, 12:00 Basin Model: Basin 1 End of Run: 03Jan2008, 12:00 Meteorologic Model: 24Hr-5Yr Compute Time: 02Apr2008, 13:11:15 Control Specifications: Control 1 Volume Units: IN Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) Subbasin Jan2008, 00:

20 Project: DeadMan Simulation Run: 24 Hour 10 Year Start of Run: 01Jan2008, 12:00 Basin Model: Basin 1 End of Run: 03Jan2008, 12:00 Meteorologic Model: 24Hr-10Yr Compute Time: 02Apr2008, 13:21:56 Control Specifications: Control 1 Volume Units: IN Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) Subbasin Jan2008, 00:

21 Project: DeadMan Simulation Run: 24 Hour 25 Year Start of Run: 01Jan2008, 12:00 Basin Model: Basin 1 End of Run: 03Jan2008, 12:00 Meteorologic Model: 24Hr-25Yr Compute Time: 02Apr2008, 13:22:52 Control Specifications: Control 1 Volume Units: IN Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) Subbasin Jan2008, 00:

22 Project: DeadMan Simulation Run: 24 Hour 50 Year Start of Run: 01Jan2008, 12:00 Basin Model: Basin 1 End of Run: 03Jan2008, 12:00 Meteorologic Model: 24Hr-50Yr Compute Time: 02Apr2008, 13:23:44 Control Specifications: Control 1 Volume Units: IN Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) Subbasin Jan2008, 00:

23 Project: DeadMan Simulation Run: 24 Hour 100 Year Start of Run: 01Jan2008, 12:00 Basin Model: Basin 1 End of Run: 03Jan2008, 12:00 Meteorologic Model: 24Hr-100Yr Compute Time: 02Apr2008, 13:21:29 Control Specifications: Control 1 Volume Units: IN Hydrologic Element Drainage Area (MI2) Peak Discharge (CFS) Time of Peak Volume (IN) Subbasin Jan2008, 00:

24 Appendix D

25

26 Appendix E

27 Clarksville Stormwater Improvements BY HLH CHECKED JIL Area 5 Blackiston Mill Road Preliminary Cost Estimate - ALT #1 DATE 11/28/2008 JOB NO ITEM QUANTITY UNIT ENGINEER'S ESTIMATED UNIT COST EXTENSION Mobilization & Demobilization 1 LS 10, , Common Excavation 6800 CY , Borrow 8252 CY , HMA Surface, Type B 18 Ton , HMA Intermediate, Type B 36 Ton , HMA Base, Type B 53 Ton , Compacted Aggregate, No Ton , Clearing and Grubbing 1 LS 7, , Revetment Riprap 44 Ton , Seed and Straw Pavement Markings Guardrail, Remove Guardrail, W-beam 6'-3" spacing Traffic Maintenance Erosion Control Remove Existing Culvert SY LS LF LF LS LS LS , , , , , , , , , , , Construction Subtotal 334, % Contingency 33, % Engineering, Surveying, & Inspection 55, Total Estimated Construction Cost 422, USE 425,000

28 Appendix F

29 Clarksville Stormwater Improvements BY HLH CHECKED JIL Area 5 Blackiston Mill Road Preliminary Cost Estimate - ALT #2 DATE 11/28/2008 JOB NO ITEM QUANTITY UNIT ENGINEER'S ESTIMATED UNIT COST EXTENSION Mobilization & Demobilization 1 LS 10, , Common Excavation 6800 CY , Borrow CY , HMA Surface, Type B 106 Ton , HMA Intermediate, Type B 213 Ton , HMA Base, Type B 319 Ton , Compacted Aggregate, No Ton , Clearing and Grubbing 1 LS 10, , Demo Existing Road Surface 1660 SY , Modify Existing Lift Station 1 LS 10, , Revetment Riprap 44 Ton , Seed and Straw Pavement Markings Guardrail, Remove Guardrail, W-beam 6'-3" spacing Traffic Maintenance Erosion Control Remove Existing Culvert SY LS LF LF LS LS LS , , , , , , , , , , , Construction Subtotal 540, % Contingency 54, % Engineering, Surveying, & Inspection 89, Total Estimated Construction Cost 683, USE 685,000

30 Area 6: Adams Drive Drainage Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations for improving storm water management in Area 6 for the Town of Clarksville, Indiana. December 2008

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

Old Mill School Stream Restoration

Old Mill School Stream Restoration Project Overview This conceptual plan restores and stabilizes two consecutive reaches of a highly incised and unstable stream and reconnects them with the floodplain. The restoration reaches are part of

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any

More information

III. INVENTORY OF EXISTING FACILITIES

III. INVENTORY OF EXISTING FACILITIES III. INVENTORY OF EXISTING FACILITIES Within the Growth Management Boundary, the existing storm drainage facilities are largely associated with development that has historically occurred in the ten drainage

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Chapter 11 Culverts and Bridges

Chapter 11 Culverts and Bridges Chapter 11 Culverts and Bridges Contents 1.0 Introduction... 1 2.0 General Design... 1 2.1 Design Criteria... 1 2.2 Design Flows... 1 2.3 Permitting and Regulations... 1 2.4 Aesthetics and Safety... 2

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

V. DRAINAGE IMPROVEMENTS

V. DRAINAGE IMPROVEMENTS V. DRAINAGE IMPROVEMENTS 5.1 Formulation of Drainage Improvements As indicated in Chapter 4, following the completion of the hydrologic analysis associated with future land use conditions, drainage improvements

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

FINDINGS: Olsson used a three-step analysis strategy to develop a benefit cost ratio that would indicate the relative feasibility of this project.

FINDINGS: Olsson used a three-step analysis strategy to develop a benefit cost ratio that would indicate the relative feasibility of this project. EXECUTIVE SUMMARY FINDINGS: Based on the results of this feasibility study, the Platte Republican Diversion Project would be cost-effective. With minimal improvements to the channel, and the existing bridge

More information

Preliminary Drainage Analysis

Preliminary Drainage Analysis Preliminary Drainage Analysis Tanimura and Antle Employee Housing Town of Spreckels County of Monterey, California LIB150205 May 29, 2015 Prepared For: Tanimura and Antle Produce Prepared By: 9699 Blue

More information

4.1 Browns Canal Introduction Sub-basin Information

4.1 Browns Canal Introduction Sub-basin Information Section 4 Withlacoochee Basin 4.1 Browns Canal 4.1.1 Introduction The information presented in this sub-basin plan for Browns Canal is intended to provide the reader with information necessary to understand

More information

APPENDIX G HYDRAULIC GRADE LINE

APPENDIX G HYDRAULIC GRADE LINE Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Appendix G Preliminary Hydrology Study

Appendix G Preliminary Hydrology Study Appendix G Preliminary Hydrology Study Preliminary Hydrology Study VESTING TTM 72608 Long Beach, CA Prepared for: The Long Beach Project, LLC 888 San Clemente, Suite 100 New Port Beach, CA May 28, 2014

More information

Chapter 8. Inlets. 8.0 Introduction. 8.1 General

Chapter 8. Inlets. 8.0 Introduction. 8.1 General . Introduction This chapter provides criteria and design guides for evaluating and designing storm sewer inlets in the City of Centennial. The review of all planning submittals will be based on the criteria

More information

10.0 Storm Sewer Systems

10.0 Storm Sewer Systems October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and

More information

Appendix D - Evaluation of Interim Solutions

Appendix D - Evaluation of Interim Solutions Appendix D - Evaluation of Interim Solutions D.1 Introduction The implementation of long-term improvements is projected to take 5 to 8 years. To reduce the number of years of flooding impacts, the partner

More information

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

DRAINAGE & DESIGN OF DRAINAGE SYSTEM Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means

More information

GRASS-LINED CHANNEL (acre) CODE 840

GRASS-LINED CHANNEL (acre) CODE 840 NATURAL RESOURCES CONSERVATION SERVICE ILLINOIS URBAN MANUAL PRACTICE STANDARD GRASS-LINED CHANNEL (acre) CODE 840 (Source: NC Erosion and Sediment Control Field Manual) DEFINITION A natural or constructed

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability

More information

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

Chapter 3 Dispersion BMPs

Chapter 3 Dispersion BMPs Chapter 3 Dispersion BMPs 3.1 BMP L611 Concentrated Flow Dispersion 3.1.1 Purpose and Definition Dispersion of concentrated flows from driveways or other pavement through a vegetated pervious area attenuates

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Bremo Power Station CCR Surface Impoundment: North Ash Pond Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

ARTICLE V: STORMWATER MANAGEMENT AND DRAINAGE SYSTEMS

ARTICLE V: STORMWATER MANAGEMENT AND DRAINAGE SYSTEMS ARTICLE V: STORMWATER MANAGEMENT AND DRAINAGE SYSTEMS Section 501: Purpose An adequate drainage system including necessary ditches, pipes, culverts, drains, inlets, bridges, detention ponds, etc. shall

More information

Hydrologic Study Report for Single Lot Detention Basin Analysis

Hydrologic Study Report for Single Lot Detention Basin Analysis Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page

More information

Sediment Basin. Fe= (Depends on soil type)

Sediment Basin. Fe= (Depends on soil type) 3.9 Sediment Control Description: A sediment basin is an embankment with a controlled outlet that detains stormwater runoff, resulting in the settling of suspended sediment. The basin provides treatment

More information

Location Drainage Study

Location Drainage Study Location Drainage Study PROJECT ROUTE: LIMITS: MUNICIPALITY/COUNTY: JOB NUMBER: IL 47 at Burlington Road 750ft NW to 750ft SE of IL 47(Burlington), & 1000ft S to 1000ft N of Burlington (IL47) Kane County

More information

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification 7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street

More information

HYDROLOGIC-HYDRAULIC STUDY BAYAMON SOUTH COMMERCIAL CENTER BAYAMON, PUERTO RICO. Casiano Ancalle, P.E. August, 2006 I.

HYDROLOGIC-HYDRAULIC STUDY BAYAMON SOUTH COMMERCIAL CENTER BAYAMON, PUERTO RICO. Casiano Ancalle, P.E. August, 2006 I. HYDROLOGIC-HYDRAULIC STUDY BAYAMON SOUTH COMMERCIAL CENTER BAYAMON, PUERTO RICO Casiano Ancalle, P.E. August, 2006 I. INTRODUCTION A commercial development project named Bayamon South Commercial Center

More information

Camp Creek: Tackling Erosion and Improving Water Quality in a Recreational Playground Mitchellville, Iowa

Camp Creek: Tackling Erosion and Improving Water Quality in a Recreational Playground Mitchellville, Iowa Camp Creek: Tackling Erosion and Improving Water Quality in a Recreational Playground Mitchellville, Iowa Rachel Conrad, PE, CFM IAFSM March 10 th, 2016 Outline Project Background and Goals Modeling Results

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials. I. Drainage Report A. Executive Summary - Brief Overview of Project Drainage Design B. Project Description 1. Existing Conditions 2. Proposed Project Conditions 3. Project Justification Narrative - Basin

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements 4.0 Introduction The requirements presented in this section shall be used to aid the design engineer or applicant in the preparation of drainage reports, drainage studies, and construction drawings for

More information

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall 6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures

More information

CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS

CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS APRIL 2011 APRIL 2011 Page 1 Chapter Table of Contents 12.1 Policy... 12-3 12.1.1 Table 1... 12-3

More information

MnDOT Flash Flood Vulnerability and Adaptation Assessment Pilot Project DISTRICT 1 SILVER CREEK CASE STUDY

MnDOT Flash Flood Vulnerability and Adaptation Assessment Pilot Project DISTRICT 1 SILVER CREEK CASE STUDY MnDOT Flash Flood Vulnerability and Adaptation Assessment Pilot Project DISTRICT 1 SILVER CREEK CASE STUDY NOVEMBER 2014 This document is part of a series of short reports based on the full Flash Flood

More information

Cokato Lake (86-263) Wright County. Hydrologic Investigation

Cokato Lake (86-263) Wright County. Hydrologic Investigation Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005 Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005 Problem Statement In recent years, heavy rainfall has

More information

CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS

CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

Project Drainage Report

Project Drainage Report Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater

More information

Hydrologic Calibration:

Hydrologic Calibration: Hydrologic Calibration: UPDATE OF EFFECTIVE HYDROLOGY FOR MARYS CREEK October 2010 Agenda Background Hydrologic model Calibrated rainfall Hydrologic calibration 100 year discharges, Existing Conditions

More information

DRAFT. Jacob Torres, P.E.; Nick Fang, Ph.D., P.E.

DRAFT. Jacob Torres, P.E.; Nick Fang, Ph.D., P.E. \ Memorandum SSPEED Center at Rice University Department of Civil & Environmental Engineering 6100 Main MS-317 Houston, Texas 77005-1827 sspeed.rice.edu tel: 713-348-4977 To Andy Yung, P.E. CFM; Lane Lease,

More information

City of Saint John. Storm Drainage Design Criteria Manual

City of Saint John. Storm Drainage Design Criteria Manual Storm Drainage Design Criteria Manual March 7, 2016 LIST OF 2016 REVISIONS PAGES SECTION TITLE iii, iv, v, vi All Table of Contents 31-35 3 SUBMISSION REQUIREMENTS March 7, 2016 Page i DISCLAIMER The material

More information

Master Plan of Storm Drainage for East Garden Grove Wintersburg Channel Tributary Area

Master Plan of Storm Drainage for East Garden Grove Wintersburg Channel Tributary Area CITY OF ANAHEIM Master Plan of Storm Drainage for East Garden Grove Wintersburg Channel Tributary Area JANUARY 2006 VOLUME 1 Table of Contents VOLUME 1 1. Executive Summary... 1 1.1 General... 1 1.2

More information

Hydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated)

Hydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated) Hydrology Study Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated) Prepared for San Mateo Real Estate & Construction March 9, 21 Rev. 1 11-8-211 Rev.

More information

December 7, Dr. Christine Pomeroy University of Utah Civil and Environmental Engineering MCE Salt Lake City, UT. Dear Dr.

December 7, Dr. Christine Pomeroy University of Utah Civil and Environmental Engineering MCE Salt Lake City, UT. Dear Dr. December 7, 2012 Dr. Christine Pomeroy University of Utah Civil and Environmental Engineering MCE 2042 Salt Lake City, UT 84112 Dear Dr. Pomeroy, The following document is the final report of the Red Butte

More information

Stantec Consulting Services Inc Lebanon Road, Cincinnati, OH 45241

Stantec Consulting Services Inc Lebanon Road, Cincinnati, OH 45241 Stantec Consulting Services Inc. 11687 Lebanon Road, Cincinnati, OH 45241 File: 175534017 Revision 0 Ohio Valley Electric Corporation 3932 U.S. Route 23 P.O. Box 468 Piketon, Ohio 45661 RE: Run-on and

More information

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1 CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1

More information

Considerations In Estimating Tailwater Elevations

Considerations In Estimating Tailwater Elevations Considerations In Estimating Tailwater Elevations by Alphonse (Al) J. Stewart, P.E., President www.suncam.com Page 1 of 39 ************************************************************************ This

More information

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed

More information

Diversion Dikes. Fe=0.95

Diversion Dikes. Fe=0.95 2.2 Diversion Dike Erosion Control Description: A diversion dike is a compacted soil mound, which redirects runoff to a desired location. The dike is typically stabilized with natural grass for low velocities

More information

STORM AND SURFACE WATER 4-1 GENERAL...4-1

STORM AND SURFACE WATER 4-1 GENERAL...4-1 SECTION 4 STORM AND SURFACE WATER SECTION DESCRIPTION PAGE 4-1 GENERAL...4-1 4-2 STORM DRAINAGE CONVEYANCE SYSTEM DESIGN CRITERIA...4-1 4-2.1 Overview...4-1 4-2.2 Design Flow and Route Requirements...4-2

More information

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 Phasing of Meetings April Meeting May Meeting October Review of Tax Day Storm Event and Immediate Actions Taken By City Review of Coordination

More information

Gwinnett County Stormwater System Assessment Program

Gwinnett County Stormwater System Assessment Program Gwinnett County Stormwater System Assessment Program Jonathan Semerjian, PE Dept. of Water Resources Stormwater Management Sam Fleming, PE Dewberry Presentation Overview Project Background Drivers Enhanced

More information

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01 Stormwater Management Studies PDS Engineering Services Division Revised Date: 2/28/08 INTRODUCTION The City of Overland Park requires submission of a stormwater management study as part of the development

More information

Volume 2, Chapter 10 - Storage

Volume 2, Chapter 10 - Storage Volume 2, Chapter 10 - Storage Users Guidance: If a UDFCD Section number in this chapter is skipped: It was adopted as is; please refer to that Section in the corresponding UDFCD Manual, Volume, Chapter

More information

CCR Certification: Initial Inflow Design Flood Control System Plan for the

CCR Certification: Initial Inflow Design Flood Control System Plan for the Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 4778 Submitted by AECOM 94 Amberglen Boulevard Austin, Texas 78729 October

More information

HYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006

HYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006 HYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006 RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT TABLE OF CONTENTS

More information

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Project Authorization USDA's Small Watershed Program is carried out under the

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Cherokee Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado

More information

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall SWM MD-378 Pond Checklist Training 10/17/07 Ken Wolfe Warren Johnson USDA, NRCS Frederick, Maryland ROLES AND RESPONSIBILITIES Small Pond Approval MDE, WMA, Dam Safety Division Authority (COMAR 26.17.04.03)

More information

New Castle County, DE. Floodplain Regulations

New Castle County, DE. Floodplain Regulations New Castle County, DE Floodplain Regulations John J. Gysling, PE CFM Department of Land Use New Castle County, DE February 26, 2009 Today s Presentation Floodplain Protection and Uses Terms and Definitions

More information

SECTION 2 DESIGN CRITERIA

SECTION 2 DESIGN CRITERIA SECTION 2 DESIGN CRITERIA 2.1 GENERAL The following criteria will be utilized by the District Engineer, and/or a consultant, in the review of development plans for recommending approval of the proposed

More information

FLAGSTAFF FAMILY FOOD BANK FLOOD REMEDIATION PROJECT

FLAGSTAFF FAMILY FOOD BANK FLOOD REMEDIATION PROJECT FLAGSTAFF FAMILY FOOD BANK FLOOD REMEDIATION PROJECT Final Design Report 5/12/2016 Erik Henricksen, Elena Smith, Garrett Ribas, Meshal Alotaibi Table of Contents Acknowledgments... 3 1.0 Project Description...

More information

The City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater.

The City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater. Background The City of rth Las Vegas strives to provide the development community with adequate information to ensure the successful completion of any project in the City. To aid in the submittal of a

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What

More information

Summary of Detention Pond Calculation Canyon Estates American Canyon, California

Summary of Detention Pond Calculation Canyon Estates American Canyon, California July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i

More information

City Plaza Residential (TPM ) Preliminary Hydrology Report

City Plaza Residential (TPM ) Preliminary Hydrology Report Hydrology Study City Plaza Residential (TPM 2016-127) Preliminary Hydrology Report Orange, Orange County, California Prepared For: Greenlaw Partners 18301 Von Karman Avenue, Suite 250 Irvine, CA 92612

More information

Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan

Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan TR-20 is a computer program for the simulation of runoff occurring from a single storm event. The program develops flood hydrographs from runoff and routes

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Valmont Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado

More information

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan) A. B. Brown History of Construction 40 CFR 257.73 (c) (i.) (ii.) (iii.) Owner Name: Southern Indiana Gas and Electric Company dba Vectren Power Supply Owner Address: One Vectren Square, PO Box 209, Evansville,

More information

Article 20: Erosion Control and Stormwater Management

Article 20: Erosion Control and Stormwater Management Article 20: Erosion Control and Stormwater Management Section 360: Purpose, Scope of Authority, Performance Guarantee and Approvals A. Purpose. The purpose of this document is to set forth minimum requirements

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose STANDARD FOR GRASSED WATERWAYS Definition A natural or constructed watercourse shaped or graded in earth materials and stabilized with suitable vegetation for the safe conveyance of runoff water. Purpose

More information

HYDROLOGY STUDY LA MIRADA BOULEVARD La Mirada, California

HYDROLOGY STUDY LA MIRADA BOULEVARD La Mirada, California HYDROLOGY STUDY 12000 LA MIRADA BOULEVARD La Mirada, California TTM 73119 Prepared for: The Olson Company 3010 Old Ranch Parkway, Suite 100 Seal Beach, CA 90740 Contact: Mr. Aaron Orenstein (562) 370-9531

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

STORM DRAINAGE DESIGN CRITERIA

STORM DRAINAGE DESIGN CRITERIA BWM Orig. 01/01/05 Revised 01/01/10 LUCAS COUNTY ENGINEERS OFFICE STORM DRAINAGE DESIGN CRITERIA Drainage The design of storm sewer systems will be based upon the Rational Method using the equation Q=CiA

More information

Appendix J Hydrology and Hydraulics

Appendix J Hydrology and Hydraulics Appendix J Hydrology and Hydraulics Marsh Lake Dam Ecosystems Restoration Feasibility Study Hydraulics & Hydrology Appendix January 2011 Contents List of Figures iii List of Tables iii I. General 1 II.

More information

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # CW2-3 Priority Ranking Med Locator Information/GPS Lat: Long: Impact Rating 3 Start Project Development: Clearwater 2 Risk Rating

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

Applying landforming to reclamation: A case study in Central Appalachia

Applying landforming to reclamation: A case study in Central Appalachia Applying landforming to reclamation: A case study in Central Appalachia Leslie Hopkinson, John Quaranta April 12, 2017 Department of Civil and Environmental Engineering West Virginia University WEST VIRGINIA

More information

VALLEY MEADOWS PARK IMPROVEMENTS REPORT

VALLEY MEADOWS PARK IMPROVEMENTS REPORT VALLEY MEADOWS PARK IMPROVEMENTS REPORT for The Borough of Carlisle CUMBERLAND COUNTY, PENNSYLVANIA Prepared by: FREDERICK, SEIBERT & ASSOCIATES, INC. www.fsa-md.com CIVIL ENGINEERS SURVEYORS LANDSCAPE

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

Appendix J: Storm Conveyance Design Parameters

Appendix J: Storm Conveyance Design Parameters Appendix J: Storm Conveyance Design Parameters Drain Commissioner 39 February 2005 STORM DRAINAGE DESIGN CRITERIA A. STORM SEWERS 1. The required discharge capacity shall be determined by the Rational

More information