4.0 Coordination and Consultation 4.0 Coordination and Consultation

Size: px
Start display at page:

Download "4.0 Coordination and Consultation 4.0 Coordination and Consultation"

Transcription

1 4.0 Coordination and Consultation 4.0 Coordination and Consultation DART RAIL TO ROWLETT Connecting Communities

2

3 4.0 COORDINATION AND CONSULTATION This Chapter provides an overview of the public involvement and agency coordination efforts that have been carried out as a part of the proposed project development process. It is anticipated that agency coordination will continue through final design. In addition, DART will work closely with the affected property owners as well as the appropriate agencies to finalize mitigation treatments and resolve any outstanding issues. 4.1 Public Involvement The public involvement program for the proposed has been designed to utilize a variety of methods to reach a range of affected parties and stakeholders, from city officials to project area residents. These methods have included a series of newsletters, many formal meetings with community and agency groups and several special meetings. A series of three four-page newsletters, each were produced throughout the duration of the study to communicate with the general public about the progress of the project. These newsletters included text and graphics, and provided information in both English and Spanish. The newsletters were distributed to the corridor mailing list, which included adjacent property owners, meeting attendees, and work group participants. Anyone requesting project information was added to the mailing list. Newsletters were distributed on the following dates: Volume 1 June 2005 Volume 2 August 2005 Volume 3 July 2006 The DART Community Affairs Department has maintained the corridor mailing list. The list has been used to send notifications regarding public and work group meetings, as well as project progress. Meetings were held to obtain input, communicate information, or obtain approval of the study alternatives and conclusions. These meetings included general public meetings, meetings with the formal CWG and TWG, a series of meetings to address specific issues related to the proposed project such as crossing the KCS, briefings to elected and appointed officials, and individual meetings with the appropriate City of Garland and City of Rowlett staff. Table 4-1 provides a chronologically ordered summary of the public and agency coordination efforts to date. 4-1

4 Table 4-1: Public and Agency Meetings Event Date Location Alternatives Analysis Meeting 04/27/2005 DART Public Meeting #1 05/12/2005 Rowlett City Hall Alternatives Analysis Meeting 05/25/2005 DART TWG Meeting #1 06/16/2005 Granville Arts Center CWG Meeting #1 07/14/2005 Rowlett City Hall Alternatives Analysis Meeting 08/16/2005 DART Alternatives Analysis Meeting 08/30/2005 DART DART Planning Committee 09/20/2005 DART Public Meeting #2 09/22/2005 Station Design Meeting #1 10/03/2005 DART Station Design Meeting #2 10/18/2005 DART Station Design Meeting #3 11/08/2005 DART TWG Meeting #2 11/17/2005 Austin Academy for Excellence Rowlett Community Centre DGNO Meeting #1 01/10/2006 DART CWG Meeting #2 01/25/2006 Granville Arts Center Station Design Meeting #4 02/13/2006 DART Station Design Meeting #5 02/20/2006 Rowlett City Hall Station Design Meeting #6 02/20/2006 City of Garland TWG Meeting #3 06/14/2006 Rowlett City Hall TWG Meeting #3 06/15/2006 Garland City Hall Event Date Location GP&L Meeting 06/21/2006 Garland City Hall Public Meeting #3 06/29/2006 Rowlett City Hall Public Meeting #4 12/14/06 Rowlett City Hall Source: LOPEZGARCIA GROUP, 2007 A series of four public meetings were held over the course of the study to involve the community in project design, EA alternatives, and station area planning. An informational brochure was distributed prior to each public meeting which provided project progress, meeting date, and location. These brochures were placed on DART bus and rail lines, as well as in public facilities within the project area. The first public meeting, held on May 12, 2005, was attended by over 50 members of the community. An introduction to the study and several key issues were presented, including: Crossing KCS tracks east of downtown Garland Rowlett Creek and floodplain issues Noise and vibration issues Historical issues 4-2

5 Coordination efforts with downtown Garland planning initiatives and the City of Rowlett Main Street Improvement project In addition to the key issues noted, residents in the Study Area requested information regarding ROW acquisition along the corridor, which had not been determined at the time. Meeting attendees also asked about plans to expand the corridor beyond the City of Rowlett. Since noise impacts were a main concern for residents, noise and vibration issues were closely examined during the LEA process. A second public meeting was held in the City of Garland on September 22, Issues presented were associated with data collection efforts and station development. Residents in attendance were mainly concerned with noise and vibration impacts to residential areas. Members of the community also provided input regarding bridge aesthetics and double track construction. The third public meeting was held on June 29, 2006 in the City of Rowlett and was attended by 26 members of the community. The presentation included the preliminary results from the DART Rail to Rowlett LEA, proposed DART Downtown Rowlett LRT Station concept design, and an update on key issues. Following the presentation, residents in attendance were able to provide questions or comments regarding the project, the majority of which were concerned with real estate acquisitions and visual aesthetics within the downtown Rowlett area. The final public meeting was conducted on December 14, 2006, following the completion of the Draft LEA. The meeting, held at Rowlett City Hall, reported the results included in the draft document. Several presentation boards with the proposed DART Downtown Rowlett LRT Station concepts and the general corridor overview were on display prior to the meeting. Questions asked following the presentation included noise impacts to Dexham Estates, future extension to Lake Ray Hubbard, parking expansion at the DART Downtown Garland LRT Station and current and future train capacity. DART also worked closely with community leaders and city officials and employees to identify issues of concern and solicit recommendations. A CWG was formed and briefed periodically on study progress prior to public meetings and asked to present their ideas to community members and associations. A TWG including representatives from affected agencies, local cities and utility companies was formed and members were divided into break-out sessions according to city affiliation. The organization of the TWG allowed the project team to focus on specific issues of concern for each city. On July 14, 2005, the first CWG meeting was held in the City of Rowlett. The group was comprised of representatives from organized interest groups, politicians, and other stakeholders in the corridor. The project background was provided and key project issues were presented, including the DART Downtown Garland LRT Station alternatives, potential wetlands/floodplain issues, potential historic structures, and noise/vibration sensitive areas. Members of the community in attendance expressed concern with regard to noise and safety, suggesting noise walls and fencing along the ROW. Many questions were related to the future of the DART System Plan, including new member cities and possible expansion. 4-3

6 The second CWG meeting was held on January 25, 2006 in Garland. The issues presented in this meeting included: The crossing of the light rail over the KCS alignment, just east of the DART Downtown Garland LRT Station Bridge structure appearance for the new line Design and development of the proposed DART Downtown Rowlett LRT Station Environmental issues including noise and vibration Attendees requested information regarding the effects of construction on current service, as well as noise and vibration impacts to the community college. The first TWG meeting was held on June 16, The TWG was composed of staff from local, state and federal implementation agencies and authorities, local jurisdictions, utility companies, affected resource agencies, and other interested agencies. A presentation of the study and evaluation of alternatives was given, followed by discussions within break-out groups composed of individuals concerned with either the DART Downtown Garland LRT Station or proposed DART Downtown Rowlett LRT Stations. The break-out sessions provided an opportunity for TWG members to share comments and suggestions regarding the study. Some of the issues introduced included: The DART Downtown Garland LRT Station s role in downtown redevelopment GP&L transmission line and substation Concern with the look of possible aerial structures Proposed DART Downtown Rowlett LRT Station design with regard to downtown plan During this meeting, the City of Garland expressed the importance of redeveloping the downtown area with regard to the placement of the new Dallas County Community College District education center, referred to as the Richland College Northeast Campus, scheduled to open in The college would be located at 5th Street, Walnut Street and Glenbrook Drive, to the west of the current DART bus transfer facility and north of the DART Downtown Garland LRT Station. GP&L representatives in attendance noted issues related to the substation and transmission lines located adjacent to the proposed alignment. Members of the Rowlett breakout group discussed plans for the new station in accordance with the City of Rowlett Downtown Revitalization Plan. The second TWG meeting was held on November 17, 2005 in the City of Rowlett and addressed data collection efforts, KCS crossing alternatives, and proposed DART Downtown Rowlett LRT Station design. Members of the TWG discussed KCS crossing efforts with regard to the transmission line limitations and possible relocations. Obstacles include uninterrupted electric service and the project budget constraints. During the proposed DART Downtown Rowlett LRT Station discussions, parking concerns were expressed. Suggestions included building a parking structure to accommodate increased ridership. The importance of maintaining the theme of downtown Rowlett was discussed. 4-4

7 The final TWG meeting was divided into separate meetings for each city. The first meeting was held in the City of Rowlett on June 14, 2006 in order to discuss station design and ROW issues. Members in attendance commented on ROW acquisition through residential developments. Potential ROW acquisitions, to accommodate the station, and the historical significance of the cotton gin were also concerns. The TWG meeting held in the City of Garland included key issues relating to the preliminary LEA results, ROW acquisition, drainage design, noise impacts, the Texas Municipal Power Agency (TMPA) interface, and GP&L substation and transmission lines. City of Garland representatives commented on the need for bridge aesthetic efforts. This meeting was predominantly attended by GP&L employees and a follow-up meeting was scheduled in order to address the concerns related to the substation and transmission line issues. In addition to these formal group meetings, a series of meetings was held to address specific issues relating to the proposed DART Downtown Rowlett LRT Station design and the KCS crossing alternatives. During the proposed DART Downtown Rowlett LRT Station design meetings, the conceptual layout was discussed, including TOD and parking. Automobile, bus, and pedestrian circulation were analyzed, along with the proposed extension of Martin Street. These meetings focused on incorporating the new station into the City of Rowlett Downtown Master Plan. During the KCS crossing alternatives analysis meetings, options for crossing the KCS freight tracks immediately east of the Garland Station were analyzed. These meetings included detailed analysis of the GP&L transmission lines and clearance requirements for the KCS railroad. Options involving the relocation of the existing DART Downtown Garland LRT Station were eliminated. 4-5

Environmental Assessment May Table 3-21: Existing Aerial Transmission Lines Crossing DART Trackway

Environmental Assessment May Table 3-21: Existing Aerial Transmission Lines Crossing DART Trackway Table 3-21: Existing Aerial Transmission s Crossing DART Trackway Utility Guideway Description Owner NB Station Crossing Type 345 kv Electric Transmission TMPA 961+50 Elevated Track 138 kv Electric Transmission

More information

Cotton Belt Corridor. Area Focus Group (AFG) DFW Airport/Coppell/Cypress Water May 4, John Hoppie, Capital Planning

Cotton Belt Corridor. Area Focus Group (AFG) DFW Airport/Coppell/Cypress Water May 4, John Hoppie, Capital Planning Cotton Belt Corridor Area Focus Group (AFG) DFW Airport/Coppell/Cypress Water May 4, 2017 John Hoppie, Capital Planning 0 Agenda Introductions Area Focus Group (AFG) Purpose Project Background Project

More information

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY? WHAT IS AN INTERMODAL TRANSIT FACILITY? An intermodal transit facility gathers many modes of transportation together and is strategically located to increase destination alternatives. Intermodal facilities

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

PLANNING FOR TRANSIT ORIENTED DEVELOPMENT IN CARROLLTON

PLANNING FOR TRANSIT ORIENTED DEVELOPMENT IN CARROLLTON PLANNING FOR TRANSIT ORIENTED DEVELOPMENT IN CARROLLTON Townscape Inc Angelou Economic Advisors Newman Jackson Bieberstein Parsons Transportation Group Bridgefarmer & Associates Carrollton Renaissance

More information

Green Line extension Project Fall 2009

Green Line extension Project Fall 2009 Introduction The Massachusetts Department of Transportation (MassDOT) is proposing to extend the Green Line to improve transit service, mobility, and regional access for residents and visitors of Cambridge,

More information

Appendix C Scoping Meeting Materials

Appendix C Scoping Meeting Materials Appendix C Scoping Meeting Materials Appendix C - Contents Sign-in Sheet for Agency Scoping Meeting Sign-in Sheet for Public Scoping Meeting Scoping Information Booklet Scoping Presentation Scoping Brochure/Comment

More information

Media Briefing. February 7, 2011

Media Briefing. February 7, 2011 1 Media Briefing February 7, 2011 2 3 4 NEPA Process NOTICE OF INTENT Start of Federal Process for an EIS SCOPING Define the Range of Alternatives We are Here DRAFT ENVIRONMENTAL IMPACT STATEMENT (DEIS)

More information

Blacklands Corridor Feasibility Study

Blacklands Corridor Feasibility Study Blacklands Corridor Feasibility Study Public Meeting May 13, 2014 The Atrium at the Granville Arts Center 300 N. Fifth Street, Garland, Texas 1 Overview Welcome and Public Involvement Efforts Amanda Wilson

More information

Cotton Belt Corridor Regional Rail Project Final Environmental Impact Statement. Appendix H. DART Cotton Belt Public Involvement Plan

Cotton Belt Corridor Regional Rail Project Final Environmental Impact Statement. Appendix H. DART Cotton Belt Public Involvement Plan Final Environmental Impact Statement Appendix H DART Cotton Belt Public Involvement Plan Cotton Belt Corridor Regional Rail Public Involvement Plan FINAL Dallas, Texas March 13, 2017 THIS PAGE INTENTIONALLY

More information

Environmental Assessment May 2007

Environmental Assessment May 2007 jurisdictional waters. It is assumed that, at a minimum, a USACE Section 404 Nationwide Permit would be necessary to construct these features. The impacts of the fill into the floodplain cannot be fully

More information

11 Joint Development Regulatory Context and Methodology

11 Joint Development Regulatory Context and Methodology 11 Joint Development This chapter describes the long-term direct and potential indirect impacts, and short-term direct and potential indirect impacts, of the proposed METRO Blue Line Light Rail Transit

More information

Technical Advisory Committee Meeting #1. December 13, 2011 MARTA Headquarters

Technical Advisory Committee Meeting #1. December 13, 2011 MARTA Headquarters Technical Advisory Committee Meeting #1 December 13, 2011 MARTA Headquarters Meeting Agenda Project Purpose Project Schedule TAC s Roles and Responsibilities Study Area Previous Studies Big Themes from

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY Purpose of tonight s meeting A Notice of Project Change (NPC) has been published for a possible extension of the Green Line from College Avenue to Mystic

More information

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services

More information

I-20 East Transit Initiative

I-20 East Transit Initiative I-20 East Transit Initiative Open Houses Monday, June 24 6 7 PM: Open House 7 8 PM: Presentation & Q/A City of Atlanta Old Council Chambers Atlanta City Hall 55 Trinity Avenue Atlanta, GA 30303 Tuesday,

More information

West Seattle and Ballard Link Extensions. Stakeholder Advisory Group March 14, 2018

West Seattle and Ballard Link Extensions. Stakeholder Advisory Group March 14, 2018 West Seattle and Ballard Link Extensions Stakeholder Advisory Group March 14, 2018 Agenda Introductions What we heard during early scoping Alternatives evaluation framework Neighborhood Forums Next steps

More information

Capital Cost Estimating Methodology Technical Memorandum

Capital Cost Estimating Methodology Technical Memorandum Memo Date: November 7, 2018 Project: To: From: DART Cotton Belt Regional Rail Project DFW International Airport to Shiloh Road Chad Edwards, DART Assistant Vice President Capital Planning John Hoppie,

More information

Environmental Assessment May 2007

Environmental Assessment May 2007 Based on the above assessment and the proposed construction activity within the Proposed corridor, the following recommendations would be incorporated as mitigation treatments during the final design and

More information

Appendix B. Technical Memoranda and Reports

Appendix B. Technical Memoranda and Reports Cotton Belt Corridor Regional Rail Project Draft Environmental Impact Statement Appendix B Technical Memoranda and Reports Technical memoranda and reports were prepared as independent documents to support

More information

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

SOUTHWEST LRT (METRO GREEN LINE EXTENSION) 8 Evaluation of Alternatives This chapter evaluates the effectiveness of the No Build Alternative and the Southwest Light Rail Transit (LRT) Project (the Project) based on the information contained in

More information

Blacklands Corridor Feasibility Study. Public Meeting March 20, 2014 Fletcher Warren Civic Center Greenville, TX

Blacklands Corridor Feasibility Study. Public Meeting March 20, 2014 Fletcher Warren Civic Center Greenville, TX Blacklands Corridor Feasibility Study Public Meeting March 20, 2014 Fletcher Warren Civic Center Greenville, TX 1 Overview Welcome, Overview, and Progress to Date Michael Morris Growth and Traffic Martin

More information

PROJECT PLAN December 2010

PROJECT PLAN December 2010 FINAL PROJECT PLAN December 2010 Tax Increment Financing Reinvestment Zone No. 1 City of Denton, Texas George R. Schrader Larry D. Cline 4800 Broadway, Ste A Addison, TX 75001 972-661-1973 schcli@swbell.net

More information

Cotton Belt Corridor. Open House Meetings September 2017

Cotton Belt Corridor. Open House Meetings September 2017 Cotton Belt Corridor Open House Meetings September 2017 0 Welcome Open House format with break for brief presentation and Question/Answer Allows for one-on-one discussions with staff Brief presentation

More information

6.0 Indirect Effects and Cumulative Impacts

6.0 Indirect Effects and Cumulative Impacts 6.0 Effects and Impacts 6.1 Introduction This chapter of the Draft EIS addresses potential indirect and cumulative impacts of the Bottineau Transitway project. effects are those that are caused by the

More information

Overview of City of Dallas and DART Interlocal Agreements

Overview of City of Dallas and DART Interlocal Agreements Overview of City of Dallas and DART Interlocal Agreements Council Transportation and Environment Committee Prepared by Transportation Programs Public Works and Transportation March 24, 2008 Purpose of

More information

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences

Final Land Use and Development Opportunities Report 5.0 Environmental Impact/Environmental Consequences Figure 5-6. Century City 1/4-Mile Station Area August 16, 2010 Page 5-14 Figure 5-7. Wilshire/Westwood 1/4-Mile Station Area August 16, 2010 Page 5-15 Alternative 1 would be constructed underneath existing

More information

Chapter 1. Introduction

Chapter 1. Introduction Chapter 1. Introduction 1.1 Purpose of the Supplemental Environmental Impact Report (EIR) The California Environmental Quality Act (CEQA) requires preparation of an Environmental Impact Report (EIR) when

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 11, 2018

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 11, 2018 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF APRIL 11, 2018 Item 9, Report No. 14, of the Committee of the Whole, which was adopted, as amended, by the Council of the City of Vaughan on April

More information

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017 Palo Alto Rail Committee Meeting November 29, 2017 Slide 1 Project Area Millbrae Station City Limits Existing Railroad Crossing at Broadway Caltrain Operational Constraint Major Constraints Millbrae Station

More information

Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE

Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE The purpose of this annotated outline is to focus the content of the Environmental Impact Statement (EIS)

More information

Project Scope and Timetable

Project Scope and Timetable 2 PROPOSED SCOPE OF WORK The timetable enclosed in this proposal presents the schedule for completing all of the work items identified within a six-month timeframe from receipt of a signed professional

More information

Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation

Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation Table of Contents Acronyms and Abbreviations Secretary s Certificate on the EENF Executive Summary 1 Introduction and Background... 1-1 1.1 Introduction... 1-1 1.2 Project Summary... 1-2 1.3 Permits and

More information

I-20 East Transit Initiative

I-20 East Transit Initiative I-20 East Transit Initiative Technical Advisory Committee (TAC) Meeting June 11 th, 2013 Introductions Purpose of Today s Meeting Project Review Preliminary Environmental Findings Next Steps Project Status

More information

Status Report on the 3 Rail Priorities

Status Report on the 3 Rail Priorities Status Report on the 3 Rail Priorities Presented to the Fort Worth City Council November 16, 2010 1 Review In August/September, the Mayor appointed the Rail Funding Strategies Committee to: Formulate funding

More information

Community Vision and Core Values DRAFT SEPTEMBER 2013

Community Vision and Core Values DRAFT SEPTEMBER 2013 Community Vision and Core Values DRAFT SEPTEMBER 2013 Introduction Plan Rapid City is the effort to update the Rapid City Comprehensive Plan, a long-range planning strategy that will provide a blueprint

More information

FINANCE PLAN December 2010

FINANCE PLAN December 2010 FINANCE PLAN December 2010 Tax Increment Financing Reinvestment Zone No. 1 City of Denton, Texas George R. Schrader Larry D. Cline December 2010 4800 Broadway, Ste A Addison, TX 75001 972-661-1973 schcli@swbell.net

More information

Final Design Guideline

Final Design Guideline Final Design Guideline May, 2016 July, 2011 Check the Capital Project Delivery website to ensure this is the current version Table of Contents Purpose... 1 Introduction... 1 FD Support... 1 Roadway and

More information

Project Steering Committee April 14, 2015

Project Steering Committee April 14, 2015 Project Steering Committee April 14, 2015 Agenda Project Background and Schedule Agency Coordination Project Need and Purpose Alternatives Under Consideration Resources Stakeholder and Public Involvement

More information

Final Quiet Zone Work Plan

Final Quiet Zone Work Plan Executive Summary Recognizing the impacts of commuter train horns on the communities they serve, RTD will assist and facilitate the local jurisdictions Quiet Zone applications along the Gold Line, Northwest

More information

APPENDIX B. ECONOMIC DEVELOPMENT TECHNICAL MEMORANDUM

APPENDIX B. ECONOMIC DEVELOPMENT TECHNICAL MEMORANDUM APPENDIX B. ECONOMIC DEVELOPMENT TECHNICAL MEMORANDUM Environmental Assessment May 2016 South Central Light Rail Extension This page is intentionally left blank. Environmental Assessment May 2016 South

More information

SELF-EVALUATION FORMS. A tool for Michigan communities seeking RRC certification

SELF-EVALUATION FORMS. A tool for Michigan communities seeking RRC certification SELF-EVALUATION FORMS A tool for Michigan communities seeking RRC certification The Redevelopment Ready Communities (RRC) best practices self-evaluations are a tool for communities seeking RRC certification.

More information

Contents. S. Executive Summary... ES Overview of Purpose & Need

Contents. S. Executive Summary... ES Overview of Purpose & Need Contents S. Executive Summary... ES-1 S.1 Introduction... ES-1 S.2 Purpose of this Study... ES-3 S.3 Background... ES-6 S.4 Purpose and Need for Transit Investment... ES-10 S.5 Community Input Process...

More information

Section 3.11 Land Use

Section 3.11 Land Use Chapter 3 Affected Environment, Environmental Consequences, and Mitigation Measures Section 3.11 Land Use Introduction This section discusses the effect of the proposed alternatives on existing land use,

More information

Federal Way Transit Center to Tacoma Dome Light Rail

Federal Way Transit Center to Tacoma Dome Light Rail Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 9.7 miles Date Last Modified July 1, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project

More information

Frequently Asked Questions Connecting Palo Alto

Frequently Asked Questions Connecting Palo Alto Frequently Asked Questions Connecting Palo Alto www.cityofpaloalto.org/connectingpaloalto General Project Questions Q1: What is Connecting Palo Alto? A1: Connecting Palo Alto (formerly the Palo Alto Rail

More information

DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL)

DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL) DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL) Background On June 25, 2014, the Federal Railroad Administration (FRA) issued a Notice of Intent to Prepare an Environmental

More information

Light Rail Operations and Maintenance Facilities

Light Rail Operations and Maintenance Facilities Subarea All Primary Mode Light Rail Facility Type Length Date Last Modified July 1, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project would construct two new light rail

More information

SH 34 Corridor Study & Environmental Assessment:

SH 34 Corridor Study & Environmental Assessment: SH & Environmental Page 1 SH & Environmental : from Kaufman (SH 243) to Terrell (north of IH 20) Third Series TxDOT 80 557 80 The SH Corridor 20 20 175 SH Study Area Boundary 243 175 SH & Environmental

More information

NEW OPPORTUNITY FOR MIDDLESEX COUNTY

NEW OPPORTUNITY FOR MIDDLESEX COUNTY Source: http://www.flickr.com/photos/scraparcs/3259040067/sizes/l/in/photostream/ RARITAN RIVER LIGHT RAIL NEW OPPORTUNITY FOR MIDDLESEX COUNTY This report studies the viability of a new transit line connecting

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 19, 2014 SUBJECT: TPAP AMENDMENT FOR TRAIN STORAGE FACILITY YONGE SUBWAY EXTENSION ACTION ITEM RECOMMENDATION It is recommended

More information

Restoration of Historic Streetcar Service in Downtown Los Angeles

Restoration of Historic Streetcar Service in Downtown Los Angeles Restoration of Historic Streetcar Service in Downtown Los Angeles Environmental Scoping Meeting January 23, 2013 Agenda 1. Welcome 2. Purpose of Scoping Meeting 3. Project Background and Description 4.

More information

CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MAY 3, 2017

CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MAY 3, 2017 TO: FROM: CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICY COMMITTEE MEETING ON MAY 3, 2017 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER SUBJECT:

More information

U.S. Department of Transportation Federal Transit Administration and Metropolitan Atlanta Rapid Transit Authority

U.S. Department of Transportation Federal Transit Administration and Metropolitan Atlanta Rapid Transit Authority ATLANTA BELTLINE CITY OF ATLANTA, FULTON COUNTY, GA TIER 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT/ SECTION 4(F) EVALUATION U.S. Department of Transportation Federal Transit Administration and Metropolitan

More information

Business Advisory Committee. July 12, 2016

Business Advisory Committee. July 12, 2016 Business Advisory Committee July 12, 2016 1 Today s Topics Approval of Meeting Minutes Cost Participation Adjusted Project Scope and Cost Estimate Recommendation Environmental Update 2 3 Cost Participation

More information

SELF-EVALUATION FORMS. A tool for Michigan communities seeking RRC certification

SELF-EVALUATION FORMS. A tool for Michigan communities seeking RRC certification SELF-EVALUATION FORMS A tool for Michigan communities seeking RRC certification The Redevelopment Ready Communities (RRC) best practices self-evaluations are a tool for communities seeking RRC certification.

More information

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

Northern Branch Corridor CLC Meeting. June 30, 2008

Northern Branch Corridor CLC Meeting. June 30, 2008 Northern Branch Corridor CLC Meeting June 30, 2008 Agenda Introductions Project Status Environmental Process Technical Findings Capital Costs Next Steps Break Out Areas Introductions Project Status Preliminary

More information

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.1 INTRODUCTION A preliminary environmental review was performed on the proposed freeway improvements that form Concept C, which encompasses the three freeway corridors

More information

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!

More information

Public Meeting. January 26, 2012 Fulton County North Service Center

Public Meeting. January 26, 2012 Fulton County North Service Center Public Meeting January 26, 2012 Fulton County North Service Center Today s Meeting Purpose 2 Why is the GA 400 Corridor Project Study Needed? Key Themes from Existing Conditions Your Input! o o Draft Purpose

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275 C-034-001 Thank you for your comments describing the cultural importance of the Latvian Evangelical Lutheran Church. See Section 2.5.1 for a description of the refined Segment A alternatives that avoid

More information

Research Initiatives at TxDOT Related to Utilities and Right of Way

Research Initiatives at TxDOT Related to Utilities and Right of Way Research Initiatives at TxDOT Related to Utilities and Right of Way Transportation Research Board Workshop on Transportation Law, New Orleans, LA July 17, 2012 Overview 2 TxDOT utility/right of way research

More information

CHAPTER 2 DESIGN REFINEMENTS

CHAPTER 2 DESIGN REFINEMENTS CHAPTER 2 DESIGN REFINEMENTS 2.1 INTRODUCTION Since publication of the Draft 2 nd Supplemental Environmental Impact Report (SEIR-2), additional design refinements have been identified. Some of these refinements

More information

State Road (S.R.) 12 (Florida Arts Trail PD&E)

State Road (S.R.) 12 (Florida Arts Trail PD&E) State Road (S.R.) 12 (Florida Arts Trail PD&E) from North Corry Street to S.R. 63 (U.S. 27) Gadsden County, Florida FPID Number: 433380-1-32-01 CRTPA Briefing September 2015 Today s Presentation Evolution

More information

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS B203 Sacramento,

More information

APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED

APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal

More information

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices DRFT ppendices MIS 8-05 - ppendices ppendices ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK] DRFT ppendix Tier Detailed Evaluation Tables MIS 8-05 - ppendix ppendix ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK]

More information

Los Gatos Creek Bridge Replacement / South Terminal Phase III Project

Los Gatos Creek Bridge Replacement / South Terminal Phase III Project Los Gatos Creek Bridge Replacement / South Terminal Phase III Project Board Meeting February 6, 2014 Presentation Topics Overview Location and Scope Environmental Review Project Construction Schedule Community

More information

South Sounder Capital Improvements Program

South Sounder Capital Improvements Program Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Date Last Modified July 1, 2016 PROJECT AREA AND REP RESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION

More information

14.0 TRANSPORTATION PLANNING RULE COMPLIANCE

14.0 TRANSPORTATION PLANNING RULE COMPLIANCE 14.0 TRANSPORTATION PLANNING RULE COMPLIANCE As stated earlier in this plan, the Oregon Department of Land Conservation and Development (DLCD), with concurrence from ODOT, adopted Transportation Planning

More information

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Environmental Analysis, Chapter 4 Consequences, and Mitigation Environmental Analysis, Chapter 4 Table 4.17-3. Summary of Adverse Environmental Justice Impacts Topic No Build TSM At-Grade Emphasis LRT Underground Emphasis LRT Locally Preferred Alternative Transit

More information

Table 2: Recommended Improvement Projects - Northeast Area Transit Evaluation. Plan

Table 2: Recommended Improvement Projects - Northeast Area Transit Evaluation. Plan Table 2: Recommended Improvement Projects - Northeast Area Transit Evaluation Project Location/Type Description Document Source US 85 US 85 interchange/baseline (WCR 2) Single-point diamond interchange

More information

CROWS LANDING CORRIDOR PLAN

CROWS LANDING CORRIDOR PLAN ATTACHMENT 1: SCOPE OF WORK CROWS LANDING CORRIDOR PLAN INTRODUCTION: StanCOG proposes the Crows Landing Corridor Plan (Plan), which is needed to determine the feasibility of inter-jurisdictional transportation

More information

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study Village of Forest Park Council Meeting Presented by Carole Morey, CTA Chief Planning Officer October 13, 2015 Slide 2: Purpose and Study

More information

Bonnie Doon Grade Separation

Bonnie Doon Grade Separation 6. 2 Bonnie Doon Grade Separation Recommendation: That the April 18, 2017, Integrated Infrastructure Services report CR_4461, be received for information. Report Summary This report provides information

More information

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012 2030 Transportation Policy Plan SUMMARY PRESENTATION Land Use Advisory Committee November 15, 2012 Today s Topics Transportation Policy Plan (TPP) Requirements and Background Current TPP Policies, Issues

More information

Chapter 4: Transportation and Land Use

Chapter 4: Transportation and Land Use Chapter 4: Transportation and Land Use Transportation and land use together make possible the wide range of destination opportunities in the region. Transportation provides the connections, and, in turn,

More information

Special Use Permit Application Martin Street Property

Special Use Permit Application Martin Street Property Special Use Permit Application Martin Street Property Submitted to City of Reno February 08, 2016 Prepared for PCD Asset Group 2760 Camino Diablo Walnut Creek, CA 94597 Prepared by Martin Street Property

More information

Chapter 9 UTILITIES ELEMENT

Chapter 9 UTILITIES ELEMENT Chapter 9 UTILITIES ELEMENT Introduction The state of Washington Growth Management requires that local governments developing or updating Comprehensive Plans under the Act to include an element within

More information

Florida Department of Transportation. Lane Elimination

Florida Department of Transportation. Lane Elimination Florida Department of Transportation Lane Elimination FDOT D6 Lane Elimination Review and Approval Process Developed to assure consistency in FDOT D6 s handling of the Lane Elimination Review and Approval

More information

RECOMMENDATION. (b) that the Shift Communications Plan, attached hereto as Appendix B, BE RECEIVED;

RECOMMENDATION. (b) that the Shift Communications Plan, attached hereto as Appendix B, BE RECEIVED; TO: FROM: SUBJECT: CHAIR AND MEMBERS STRATEGIC PRIORITIES AND POLICIES COMMITTEE MEETING ON SEPTEMBER 18, 2017 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR ENVIRONMENTAL & ENGINEERING SERVICES AND

More information

Cumulative and Secondary Impacts

Cumulative and Secondary Impacts Chapter 14: Cumulative and Secondary Impacts A. INTRODUCTION SEQRA regulations require the consideration of the Proposed Project s potential to result in cumulative impacts (6 NYCRR 617.9(b)(5)(a)) and

More information

SR 50 PD&E Study

SR 50 PD&E Study SR50 Project Development & Environment Study Public Hearing November 1, 2011 SR 50 PD&E Study 427056-1-22-01 1 Purpose of the Public Hearing Afford persons the opportunity to express their views about

More information

Cotton Belt Corridor. Area Focus Group (AFG) North Dallas May 9, John Hoppie, Capital Planning

Cotton Belt Corridor. Area Focus Group (AFG) North Dallas May 9, John Hoppie, Capital Planning Cotton Belt Corridor Area Focus Group (AFG) North Dallas May 9, 2017 John Hoppie, Capital Planning 0 Agenda Introductions Area Focus Group (AFG) Purpose Project Scope North Dallas Focus Area AFG input

More information

S-16: Sounder Rail Extension from Puyallup to Orting

S-16: Sounder Rail Extension from Puyallup to Orting Project Number S-16 Subarea Pierce Primary Mode Commuter Rail Facility Type Corridor Length 5.7 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT

More information

Riverview Corridor Pre-Project Development Study

Riverview Corridor Pre-Project Development Study Riverview Corridor Pre-Project Development Study American Society of Civil Engineers - Minnesota May 25, 2016 Work in Progress; Subject to Change 1 History 2000: Major Investment Study (MIS) offered several

More information

Intent to Prepare a Supplemental Draft Environmental Impact Statement for the Capitol

Intent to Prepare a Supplemental Draft Environmental Impact Statement for the Capitol Federal Register DEPARTMENT OF TRANSPORTATION Federal Transit Administration Intent to Prepare a Supplemental Draft Environmental Impact Statement for the Capitol Expressway Light Rail Project in the City

More information

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA This report was prepared to present development information (Utility availability, Development Regulations, Flood Plain information,

More information

Cotton Belt Corridor. Area Focus Group (AFG) North Dallas September 11, John Hoppie, Capital Planning

Cotton Belt Corridor. Area Focus Group (AFG) North Dallas September 11, John Hoppie, Capital Planning Cotton Belt Corridor Area Focus Group (AFG) North Dallas September 11, 2017 John Hoppie, Capital Planning 0 Agenda AFG Concerns Design Update Alignment/Cross-section/Stations Environmental Update Documentation

More information

BUS RAPID TRANSIT CORRIDOR

BUS RAPID TRANSIT CORRIDOR DOWNTOWN UPTOWN OAKLAND EAST END BUS RAPID TRANSIT CORRIDOR Scoping Booklet for National Environmental Policy Act Review City of Pittsburgh Port Authority of Allegheny County Uptown/Downtown Scoping Meeting

More information

3 Documentation of Alternatives

3 Documentation of Alternatives Sacramento Intermodal Transportation Facility TR #9 SITF Alternatives 3 Documentation of Alternatives This section documents the four alternative concept plans for the Sacramento Intermodal Transportation

More information

BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION

BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION Perform Master Plan Implementation Consulting: $50,000 Perform Post Office Site Evaluation (if necessary): $50,000 11 Agenda Packet

More information

FINAL ENVIRONMENTAL IMPACT STATEMENT/RECORD OF DECISION AND SECTION 4(F) EVALUATION

FINAL ENVIRONMENTAL IMPACT STATEMENT/RECORD OF DECISION AND SECTION 4(F) EVALUATION FINAL ENVIRONMENTAL IMPACT STATEMENT/RECORD OF DECISION AND SECTION 4(F) EVALUATION MARCH 2018 Federal Transit Administration and Northern Indiana Commuter Transportation District In cooperation with the

More information

Cypress Waters TIF District Final Plan and Phase I Development Agreement

Cypress Waters TIF District Final Plan and Phase I Development Agreement Final Plan and Phase I Development Agreement Economic Development Committee May 16, 2011 1 Overview was created December 8, 2010. It is located north and east of the intersection of LBJ Freeway (I-635)

More information

Transit Oriented Development Study Addendum

Transit Oriented Development Study Addendum Federal Way Link Extension Transit Oriented Development Study Addendum Table of Contents Introduction and Purpose... 2 FWLE Preferred Alternative... 2 Original TOD Potential Methodology (April 2015)...

More information

KRM COMMUTER RAIL RATES HIGH WITH PUBLIC INSIDE THE KENOSHA-RACINE-MILWAUKEE COMMUTER LINK

KRM COMMUTER RAIL RATES HIGH WITH PUBLIC INSIDE THE KENOSHA-RACINE-MILWAUKEE COMMUTER LINK KRM THE KENOSHA-RACINE-MILWAUKEE COMMUTER LINK COMMUTER RAIL RATES HIGH WITH PUBLIC Earlier this year, the initial series of public informational scoping meetings for this phase of the KRM project was

More information