1 Shingle Creek Watershed Management Commission Wetland 639W Outlet Modifications Summary Feasibility Report The proposed project is the modification of the outlet of Wetland W to reduce phosphorus export from the wetland to Upper Twin Lake, an Impaired Water that exceeds the state standard for total phosphorus concentration. The proposed modification consists of the construction of a sheet pile weir just upstream of the outlet to increase storage in the wetland, and the construction of an upstream outlet structure and high flow overflow channel. Wetland 639W is shown in Figure 1. Project Background A network of storm sewers and a channel known locally as Twin Creek conveys stormwater from approximately 1,010 acres of fully developed mixed use land in the cities of Crystal, Brooklyn Center, Brooklyn Park, and New Hope to Wetland 639W (Figure 2). In addition, approximately 324 acres of land on the Crystal Airport drains overland to the wetland, which is located on property owned by the Metropolitan Airports Commission (MAC). Drainage is conveyed by sheet flow across the main basin of the wetland, and is discharged from the basin by Twin Creek to Upper Twin Lake. Monitoring performed by the Shingle Creek Watershed Management Commission (SCWMC) in Twin Creek upstream and downstream of the wetland has found that total phosphorus concentration in the water discharged from the wetland is significantly greater than the concentration at the inlet, indicating that the wetland is discharging phosphorus. The phosphorus load discharged from the wetland into Upper Twin Lake is an estimated 40 percent of the total load of phosphorus to Upper Twin Lake, and a Total Maximum Daily Load (TMDL) study prepared for the lake concluded that this phosphorus load contributes significantly to its impairment. Because Upper Twin is connected to Middle Twin by a channel, the nutrient-rich water from Upper Twin flows directly to that lake and contributes to its Impaired Waters status. Reducing phosphorus load exported from Wetland 639W is the highest-priority action in the EPA-approved TMDL and MPCA-approved Twin and Ryan Lakes Nutrient TMDL Implementation Plan. The SCWMC and the cities of Brooklyn Center and Crystal have for a number of years investigated ways to improve the Twin Lake chain. Modeling of the lake s watershed and water quality testing at outfalls into the lake in 1999 suggested that the part of the watershed that outlets through Wetland 639W was exporting more phosphorus to the lake than would be expected for the land uses in the watershed. More detailed monitoring upstream and downstream of the wetland conducted in 2002 confirmed that the wetland was the likely source of the excess phosphorus, but the exact mechanism causing that export was not known. Options Analysis Prior to undertaking this Feasibility Study, the Commission hypothesized that one or more of the following conditions were causing the export of phosphorus from the wetland. 1

2 Figure 1. Wetland 639W. 2

3 Figure 2. Drainage area to wetland 639W. 3

4 1. Stormwater is conveyed through the upper wetland in a channel. At the wetland midpoint, just above the central wetland basin, the channel disappears and the flow diffuses into sheet flow. This sheet flow moves more slowly across the wetland basin, and becomes deoxygenated as vegetation and soils capture and use the dissolved oxygen. Anoxia at the soil-water interface across the wetland breaks electrochemical bonds and releases phosphorus from the mineral soils. 2. The wetland vegetation and soil dries out in summer, becoming friable. Periodic large events mobilize and flush organic material and detached soil particles out of the wetland and into the lake. 3. The wetland soils have reduced ability to bind phosphorus due to the transport of sediment and nutrients to the wetland from historic agricultural and current urban stormwater. In 2008, as the first phase of this Feasibility Study the SCWMC undertook additional monitoring, replicating the 2002 stream monitoring but also tracking groundwater levels in and near the wetland and analyzing soil cores taken from the wetland. A detailed analysis of the monitoring data and observation of conditions suggests that the primary reason phosphorus is released from the wetland is that the central basin dries out significantly during the summer. This drying out has two effects. First, the soil becomes mineralized faster than it would were it saturated, releasing phosphorus. Second, the soil becomes more friable, and stormwater sheet flowing across the wetland then mobilizes these mineralized soil particles and conveys them and the associated phosphorus load downstream to Upper Twin Lake. The groundwater elevation monitoring in 2008 suggests that groundwater movement in the immediate vicinity is generally from all directions toward the central basin of the wetland, which is vegetated with dense cattail growth. Cattails have a high evapotranspiration crop coefficient, meaning they use a lot of water. During periods of lower precipitation and runoff, when there is little to no standing surface water, cattails rely on groundwater for the water necessary for photosynthesis was a very low precipitation year, and piezometers measured a 2-3 foot drop in surficial groundwater over the summer growing season. The main basin of the wetland experienced extended periods of soil dryness, so then when rain events did occur, pulses of phosphorus were discharged from the wetland to the lake. These pulses were high in orthophosphate, which is the form of phosphorus that is most readily available for plant uptake and which fuels lake algal blooms. The Commission and the Technical Advisory Committee (TAC) considered several options to reduce the phosphorus export from the wetland. Some of these were identified but not pursued further as they were considered infeasible for cost, maintenance, or regulatory reasons as described in Table 1. Table 1. Options to reduce phosphorus export from wetland 639W. Option Implementation Considerations 1. Bypass all flow around the wetland Option would eliminate all surface water inputs from the upper watershed, leaving only direct runoff from the surrounding watershed, groundwater inputs, and precipitation. This would significantly affect the wetland s hydroperiod and change the wetland type, likely requiring wetland mitigation. May be difficult to obtain a permit. 2. Bypass high flows allowing low flows Would eliminate the most damaging high flows but allow low flows to to pass continue, reducing the impact to the wetland hydroperiod. 3. Modify wetland outlet to retain water Needs to be carefully designed to avoid creating areas of permanent in the wetland open water that would be attractive to waterfowl and other aviation nuisances. 4

5 Option Implementation Considerations 4. Divert channel flow into storage cells Would create areas of permanent open water that would be attractive to in the wetland to slow rate of flow waterfowl and other aviation nuisances. 5. Soil amendment Does not address the cause of soil mineralization problem, would have to be reapplied periodically. 6. Remove cattails and excavate mineralized soils Expensive, would change wetland type, likely requiring wetland mitigation. Would lower wetland surface elevation creating areas of permanent open water. 7. Chemical treatment of effluent Expensive, an ongoing cost for operations, needs a flocculation basin that would periodically have to be dredged and the material disposed. 8. Chemical treatment within the wetland Alum columns, limestone berms, etc. Would have to be widely dispersed to be effective given the volume of water passing through. 9. Reduce peak rates from upper watershed Very long term, also needs to be done carefully to avoid creating openwater habitat. Preferred Option The most promising options, options 2 and 3, were studied in more detail. The preferred option is a combination of the two approaches. Limiting outflow from the wetland would help the wetland stay as wet as possible, reducing the periods of soil dryness that lead to soil mineralization and export of friable material. This could be accomplished through the construction of a sheet pile weir along the bottom of the wetland. This weir would be set at elevation 856.0, approximately two feet above the ground elevation. Figure 3 shows a schematic drawing of the proposed modified outlet. A new outlet set at elevation would be constructed at a point upstream of the central wetland basin. Three options were considered for this new outlet: a new channel to be constructed at the edge of the upland wooded area adjacent to the wetland; a piped outlet following the chip trail corridor; and a combination pipe and channel to the east into a wetland in Brooklyn Center. Brooklyn Center expressed concern about the unknown impacts of discharging into its wetland, so that scenario was not pursued. The piped outlet as discussed below was estimated to be considerably more expensive than the open channel. The preferred option, the open channel, would outlet through an existing swale downstream of the sheet pile weir. Figure 4 shows the general location of the new channel. Water would be stored in the wetland until the elevation exceeds 855.5, at which point the upper outlet would begin to discharge into the channel. Hydrologic and hydraulic modeling indicate that channel discharge and storage in the wetland between elevations and can accommodate up to a 1.5 inch event. When the basin is full (i.e., at elevation 855.5), events smaller than 1.5 inches will be retained in the wetland. Larger events would be discharged both through the channel and over the top of the sheet pile weir. Modeling is discussed in more detail below. Figure 3. Conceptual cross section of proposed sheet pile weir and new outlet. 5

6 Figure 4. Proposed Wetland 639W outlet modification. Storage and Potential for Open Water Installation of the sheet pile weir will increase runoff storage in the central basin. Because of the proximity to the Crystal Airport, it is of prime importance to prevent the creation of open water that would attract waterfowl. The central basin of the wetland is currently vegetated mainly with dense cattails several feet in height interspersed with higher elevation areas of scrub shrubs and trees. There are some pockets vegetated with grasses and less dense cattail growth. During large events lower elevation areas of the basin may for up to several days contain a foot to 18 inches of standing water, compared to field observations that the wetland currently rarely contains more than six inches of standing water. It is unlikely that any significant new permanent open water will be created in the main basin as the height of the standing cattails in the low areas exceeds the potential standing water depth. However, there is a possibility that small permanent pockets of open water may be created in the lower basin immediately adjacent to the sheet pile weir. This area is a foot lower in elevation from the central basin, and may contain one to two feet of standing water on a continuing basis. This may cause changes in vegetation that might result in patches of open water. However, these low areas are small in size and are surrounded by higher ground that could be expected to remain vegetated with cattails, grasses, and scrub shrubs, limiting the attractiveness to waterfowl. 6

7 Hydrologic and Hydraulic Modeling Hydrologic and hydraulic modeling were completed to assess the impact of various improvement scenarios on flow through the wetland and on wetland elevations. The P8 model prepared for the Twin and Ryan Lakes Nutrient TMDL and the Shingle Creek Watershed Management Commission s watershed SWMM model were used in this analysis. The SWMM model hydrology is well-calibrated to watershed runoff measured at various locations throughout the watershed during the development of the Shingle Creek chloride TMDL. P8 hydrology was calibrated to the SWMM model and the pollutant loading was calibrated to Twin Creek water quality data collected in 2002 and Once the models were calibrated the proposed new sheet pile weir, outlet structure, and outlet channel were added. The models were then used to optimize the design details of the weirs and evaluate the impact of the revised outlets on wetland hydrology. Figures 5 and 6 below show the hydrographs for the 2-year event and the 100-year event respectively assuming the basin is full (i.e., at 855.5) as a starting condition. The hydrographs show the elevation of water in the basin at Node SW-2, which is the downstream sheet pile weir. The 2-year event hydrograph shows that the wetland very slightly overtops the weir, and then the basin is drawn down through the outlet channel to the starting conditions in a few days. The 100- year event hydrograph shows the weir overtopped and flowing for about one day, and then drawing down the second day. A ten year precipitation record was run through the SWMM model. The wettest year in this period was 2002, where the model predicts the sheet pile weir would have been overtopped five times. However, even during that wet year there were periods when the wetland elevation would have fallen below the outlet elevation and there would have been no flow in the channel. The average bounce, or change in wetland elevation due to a precipitation event, is estimated to be less than one foot during this period of record. The lower areas adjacent to the downstream weir might experience a bounce of up to two feet. In 2008, a very dry year, the model predicts that water elevation in the wetland would never have reached the level where the outlet weir would be overtopped. In an average year, the weir would likely be overtopped two to three times. Even in wet years, the model predicts that overflow through the channel would likely be flowing only for short periods. 7

8 Start Day 2 Day 3 Day 4 Day 5 Figure 5. Hydrograph, 2- year event at Node SW-2, the sheet pile weir. Flow just overtops the downstream weir set at

9 Start Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Figure 6. Hydrograph, 100-year event for Node SW-2, the sheet pile weir. Flow overtops the downstream weir for approximately one day and then is drawn down by the next day. 9

10 10

11 Cost and Performance Previous study and the Twin and Ryan Lakes Nutrient TMDL estimated that wetland 639W exports between pounds of total phosphorus annually, depending on the amount of precipitation received. The goal of this project is to reduce phosphorus export by an average 300 pounds per year. This would accomplish a significant fraction of the approximately 750 pound annual total phosphorus wasteload reduction required to Upper Twin Lake. Because Middle Twin Lake is connected to Upper Twin Lake through a short channel, improving Upper Twin Lake will have a beneficial effect on Middle Twin. Table 2 below is summary of construction cost (excluding engineering and other costs), and an estimated cost per pound of phosphorus removed. Table 3 below shows the detailed performance calculations indicating the preferred option, Option 3, meets the removal goal of 300 pounds per year. Table 2. Estimated costs, load reductions, and cost per pound removed for wetland 639W design options. Estimated Cost Load Reduction (lbs) and Cost per Pound Wet Year Dry Year Average 1. No build $0 $0 $0 $0 2. Sheet pile weir only $325,000 $1,555 $1,633 $1, Bypass + sheet pile weir To east $590,000 $855 $1,616 $1,150 To west (pipe) $890,000 $1,290 $2,438 $1,735 To west (channel) To south (pipe) $410,000 $770,000 $ $1,116 $1, $2,110 $ $1,501 Table 3. Estimated phosphorus export load reductions for each of the three Wetland 639W options. Monitored Avg Annual Load Annual Load Annual Load P8 Volume TP Wetland Year Option Reduction Reduction (af-yr) Concentration Outflow (kg/yr) (lb/yr) (mg/l) (kg/yr) 1. No build 1, Wet Year 43.8 precip 2008 Dry Year 22.7 precip 2. SP weir only Bypass + weir Bypass Flow over weir No build SP weir only Bypass + weir Bypass Flow over weir

12 Year Option P8 Volume (af-yr) Monitored Avg TP Concentration (mg/l) Annual Load Wetland Outflow (kg/yr) Annual Load Reduction (kg/yr) Annual Load Reduction (lb/yr) 1. No build SP weir only Average 3. Bypass + weir Bypass weir Note: Concentrations used for 2002 and 2008 are the monitored summer average concentration; for the average the concentration is the average of the 2002 and 2008 monitoring results. The No build, SP weir only, and flow over weir option concentrations are at the outlet of the wetland. Concentrations used for the bypass option are the summer average at the midpoint of the wetland, near where the bypass weir would be located. Ongoing Operations and Maintenance The City of Crystal has agreed to take on responsibility for ongoing operations and maintenance of the weirs and channel. These activities are expected to include but not be limited to: Routine inspection of weirs, outfalls, and the channel. Removal of debris accumulated on the weirs or blocking the outfalls. Removal of trees, woody debris, sediment deltas, and other blockages in the outlet channel. Maintenance, repair, and replacement as necessary of weirs, outfalls, and the channel. Estimated Cost and Funding The following is a summary of the estimated costs and funding sources for this project. The MPCA Section 319 construction grant extends through August 29, The benefitting cities include Brooklyn Center, Brooklyn Park, Crystal, and New Hope. Those cities have not yet reached an agreement on cost sharing between the partners. Because the project is located mostly in Crystal, Crystal has agreed to be the lead agency and to manage the construction project if approved. Costs Construction $410,000 Contingency 85,000 Final Design and Construction Engineering 50,000 Followup Monitoring and Reporting 25,000 Total $570,000 Funding MPCA Section 319 Grant $300,000 Shingle Creek WMC 142,500 Cities 127,500 Total $570,000 12

Final Report Section 319 and Clean Water Partnership Projects

Final Report Section 319 and Clean Water Partnership Projects Grant Project Summary Final Report Section 319 and Clean Water Partnership Projects Project title: Wetland 639W Nutrient Export Reduction Organization (Grantee): Shingle Creek Watershed Management Commission

More information

11. Public Utilities. Key Terminology: OVERVIEW STORMWATER MANAGEMENT WATERSHED MANAGEMENT ORGANIZATIONS AND COMMISSIONS. Inventory and Analysis

11. Public Utilities. Key Terminology: OVERVIEW STORMWATER MANAGEMENT WATERSHED MANAGEMENT ORGANIZATIONS AND COMMISSIONS. Inventory and Analysis Inventory and Analysis 11. Public Utilities Urbanized (drainage): Defined as an area where natural soils, waterways, and environmental functions are replaced with impervious surfaces (roads, parking lots,

More information

Hydrology 101. Impacts of the Urban Environment. Nokomis Knolls Pond Summer June 2008

Hydrology 101. Impacts of the Urban Environment. Nokomis Knolls Pond Summer June 2008 Hydrology 101 Nokomis Knolls Pond Summer 2002 Impacts of the Urban Environment Hydrologic Cycle; What is it? Geography, Topography, Geology, Land Cover and Climate determine the Amount and Behavior of

More information

Project Priority List scoring worksheet - stormwater Guidance document

Project Priority List scoring worksheet - stormwater Guidance document www.pca.state.mn.us Project Priority List scoring worksheet - stormwater Guidance document PLEASE NOTE: THE MINNESOTA STATE FISCAL YEAR IS FROM JULY 1 JUNE 30 The first step towards receiving either a

More information

BUREAU OF CLEAN WATER

BUREAU OF CLEAN WATER COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF CLEAN WATER NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) STORMWATER DISCHARGES FROM SMALL MUNICIPAL SEPARATE STORM

More information

Natural and Engineered Wetlands for Stormwater Management

Natural and Engineered Wetlands for Stormwater Management Natural and Engineered Wetlands for Stormwater Management Dan Hitchcock, Ph.D., P. E. Baruch Institute of Coastal Ecology and Forest Science Clemson University Georgetown, SC Prominence and Diversity of

More information

Appendix D Monitoring Program

Appendix D Monitoring Program Appendix D Monitoring Program [This page left intentionally blank.] Shingle Creek and West Mississippi Watershed Management Commissions Third Generation Watershed Management Plan Monitoring Program Minnesota

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW

COON CREEK WATERSHED DISTRICT PERMIT REVIEW 16-054 Woodland Creek Wetland Banking Restoration Project, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 11 FILE NUMBER: 16-054 ITEM: Woodland Creek

More information

Common Pitfalls in BMP Selection and Implementation. 19 th Annual Southeastern Lakes Management Conference Winston-Salem, NC

Common Pitfalls in BMP Selection and Implementation. 19 th Annual Southeastern Lakes Management Conference Winston-Salem, NC Common Pitfalls in BMP Selection and Implementation 19 th Annual Southeastern Lakes Management Conference Winston-Salem, NC Harvey H. Harper, Ph.D., P.E. Environmental Research & Design, Inc. Introduction

More information

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY Project #08223 CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY PREPARED FOR: City of Crystal Lake 100 West Woodstock Street Crystal Lake, Illinois 60014 FEBRUARY 11, 2009 26575 W. COMMERCE DRIVE, SUITE 601,

More information

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges Detention Pond Design Considering Varying Design Storms Land Development Results in Increased Peak Flow Rates and Runoff Volumes Developed area Robert Pitt Department of Civil, Construction and Environmental

More information

Lauren Striegl City of Madison Engineering UPDATE ON CITY OF MADISON S SPECIAL TREATMENT PROJECTS

Lauren Striegl City of Madison Engineering UPDATE ON CITY OF MADISON S SPECIAL TREATMENT PROJECTS Lauren Striegl City of Madison Engineering UPDATE ON CITY OF MADISON S SPECIAL TREATMENT PROJECTS March 15, 2018 Starkweather Creek Stormwater Treatment System Removing Phosphorus from Stormwater Runoff

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW Mississippi Dr Coon Rapids, MN SQ FT Residence on 0.64 Acre Lot

COON CREEK WATERSHED DISTRICT PERMIT REVIEW Mississippi Dr Coon Rapids, MN SQ FT Residence on 0.64 Acre Lot 17-082 Van Sloun Residence, Page 1 of 5 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: May 8, 2017 AGENDA NUMBER: 17 FILE NUMBER: 17-082 ITEM: Van Sloun Residence RECOMMENDATION: Approve with

More information

Appendix X: Non-Point Source Pollution

Appendix X: Non-Point Source Pollution Appendix X: Non-Point Source Pollution Sources Nonpoint source of pollution, unlike pollution from industrial and sewage treatment plants, comes from many different sources. Nonpoint source pollution is

More information

Hydrology: Sources of Water and Nutrients

Hydrology: Sources of Water and Nutrients Hydrology: Sources of Water and Nutrients 37 Hydrology: Sources of Water and Nutrients Study results indicate that Silver Lake is colimited by both phosphorus and nitrogen, at the time when the bioassay

More information

Final TMDL Implementation Plan. Prepared for Minnesota Pollution Control Agency

Final TMDL Implementation Plan. Prepared for Minnesota Pollution Control Agency Wirth Lake Final TMDL Implementation Plan Prepared for Minnesota Pollution Control Agency September 2010 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601 wq-iw11-03c

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

Constructed Wetland Pond T-8

Constructed Wetland Pond T-8 Constructed Wetland Pond T-8 Description A constructed wetlands pond is a shallow retention pond designed to permit the growth of wetland plants such as rushes, willows, and cattails. Constructed wetlands

More information

San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons and

San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons and San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons 2011-12 and 2012-13 Project Overview San Francisco State University (SFSU) has implemented several green

More information

Chapter 3 Previous Studies

Chapter 3 Previous Studies Chapter 3 Previous Studies The Vista Grande stormwater conveyance system and watershed area has been evaluated in a number of reports and studies for the CCSF, the Daly City and San Mateo County over the

More information

The Borough of Penbrook 150 South 28th Street Penbrook, PA NPDES MS4 Permit PAG DRAFT for Public Review: July 21, 2017

The Borough of Penbrook 150 South 28th Street Penbrook, PA NPDES MS4 Permit PAG DRAFT for Public Review: July 21, 2017 POLLUTANT REDUCTION PLAN FOR IMPAIRED WATERS OF THE COMMONWEALTH AND THE CHESAPEAKE BAY, AND TMDL PLAN TO PAXTON CREEK PENBROOK BOROUGH, DAUPHIN COUNTY, PA The Borough of Penbrook 150 South 28th Street

More information

4.12. Detention Basins

4.12. Detention Basins 4.12. Detention Basins Detention Basins can be a cost effective method to provide temporary storage, conveyance, and treatment of runoff when used within the context of Low Impact Development (LID) strategies.

More information

Wakefield Lake TMDL Public Meeting 3/17/2014. Jen Koehler, PE Barr Engineering

Wakefield Lake TMDL Public Meeting 3/17/2014. Jen Koehler, PE Barr Engineering Wakefield Lake TMDL Public Meeting 3/17/2014 Jen Koehler, PE Barr Engineering Outline Project Contacts Introduction to Wakefield Lake Thoughts/Questions/Concerns About TMDL Studies Lake Water Quality and

More information

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac)

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac) Permit Application No.: 17-181 Rules: Erosion Control, Wetland Protection, and Waterbody Crossings & Structures Applicant: Hennepin County Received: 4/27/17 Project: CSAH 112 Phase II Complete: 9/5/17

More information

Rainwater Harvesting at Stillwater Country Club

Rainwater Harvesting at Stillwater Country Club technical memo Project Name BCWD Community Demonstration BMP Projects Date 12/05/2018 / Contact info Cc / Contact info From / Contact info Regarding BCWD Board of Managers Karen Kill, District Administrator

More information

Section 6: Stormwater Improvements

Section 6: Stormwater Improvements Section 6: Stormwater Improvements A major objective of this study was to identify opportunities for improvements to address the widespread water quality impairments caused by stormwater runoff in the

More information

Design of Stormwater Wetlands

Design of Stormwater Wetlands Hydraulic & Hydrologic Stormwater Engineering Design of Stormwater Wetlands Jon Hathaway, EI Extension Associate NCSU Bio. And Ag. Engineering 6 Step Process 1. Watershed Analysis (Runoff Volume and Peak

More information

BCWMC Capital Improvement Program (Approved with Minor Plan Amendment July 2017)

BCWMC Capital Improvement Program (Approved with Minor Plan Amendment July 2017) BCWMC Capital Improvement Program 2019 2023 (Approved with Minor Plan Amendment July 2017) Project Name City Number 2016 2017 2018 2019 2020 2021 2022 2023 Totals Honeywell Pond Expansion, Main Stem Watershed

More information

RETENTION BASIN EXAMPLE

RETENTION BASIN EXAMPLE -7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary

More information

SILVER SPRINGS/RIVER POLLUTION REDUCTION PROJECT IMPROVING THE WATER QUALITY OF THE SILVER SPRINGS ECOSYSTEM

SILVER SPRINGS/RIVER POLLUTION REDUCTION PROJECT IMPROVING THE WATER QUALITY OF THE SILVER SPRINGS ECOSYSTEM SILVER SPRINGS/RIVER POLLUTION REDUCTION PROJECT IMPROVING THE WATER QUALITY OF THE SILVER SPRINGS ECOSYSTEM Jonathan Steflik, PE JEA (Formerly Black & Veatch) Bruce Phillips, PE PLS, Tom Young, PE City

More information

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines Pennsylvania Stormwater Best Management Practices Manual Chapter 3 Stormwater Management Principles and Recommended Control Guidelines 363-0300-002 / December 30, 2006 Chapter 3 Stormwater Management Principles

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.) Module 2: Selection of Controls and Site Planning for Construction Site Erosion Prevention Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa,

More information

Sunset Circle Vegetated Swale and Infiltration Basin System Monitoring Report: Rainy Seasons and

Sunset Circle Vegetated Swale and Infiltration Basin System Monitoring Report: Rainy Seasons and Sunset Circle Vegetated Swale and Infiltration asin System Monitoring Report: Rainy Seasons 2012-13 and 2013-14 bstract Site Summary Project Features Sunset Circle Vegetated swales and infiltration basins

More information

Multipurpose Wetland Creation and Restoration to Improve Water Quality and Wildlife Habitat in Coastal Urban Bayous

Multipurpose Wetland Creation and Restoration to Improve Water Quality and Wildlife Habitat in Coastal Urban Bayous Multipurpose Wetland Creation and Restoration to Improve Water Quality and Wildlife Habitat in Coastal Urban Bayous CEER 2014 New Orleans, LA George Guillen, Misty Shepard, K. Vale and J. Oakley Environmental

More information

Nutrient Management in. A presentation to the West Metro Water Alliance

Nutrient Management in. A presentation to the West Metro Water Alliance Nutrient Management in Developing and Agricultural Areas A presentation to the West Metro Water Alliance Chris Meehan, P.E. May 25, 2011 Agenda Physical Improvements Planning Improvements How to get it

More information

Water Resources Management Plan

Water Resources Management Plan P L Y M O U T H M I N N E S O T A Appendix D: The developed a to analyze and minimize the impact of existing and future development on the City s natural resources. It is important to the City to have

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

2016 Monitoring Report; Mississippi River Tributaries

2016 Monitoring Report; Mississippi River Tributaries 2016 Monitoring Report; Mississippi River Tributaries SWWD s East Mississippi watershed (Map 1) is named after the former East Mississippi Watershed Management Organization which managed the area prior

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or

More information

Cedar Island, Pike, and Eagle Lakes Nutrient TMDL Implementation Plan

Cedar Island, Pike, and Eagle Lakes Nutrient TMDL Implementation Plan Cedar Island, Pike, and Eagle Lakes Nutrient TMDL Implementation Plan Wenck File #1240-76 Prepared for: SHINGLE CREEK WATERSHED MANAGEMENT COMMISSION MINNESOTA POLLUTION CONTROL AGENCY Prepared by: May

More information

Shingle Creek and West Mississippi Watershed Management Commissions Iron- and Biochar-Enhanced Sand Filters Project

Shingle Creek and West Mississippi Watershed Management Commissions Iron- and Biochar-Enhanced Sand Filters Project Urban stormwater conveys bacteria such as E. coli to receiving waters, where contact can be a human health risk. Shingle Creek, the Upper Mississippi River, and many other urban and rural streams in Minnesota

More information

Jason R. Vogel, Ph.D., P.E. Biosystems and Agricultural Engineering Oklahoma State University

Jason R. Vogel, Ph.D., P.E. Biosystems and Agricultural Engineering Oklahoma State University Stormwater 101 OKLAHOMA STATE UNIVERSITY Biosystems and Agricultural Engineering Department Jason R. Vogel, Ph.D., P.E. Biosystems and Agricultural Engineering Oklahoma State University Stormwater is excess

More information

SECTION 10: WETLANDS PROTECTION

SECTION 10: WETLANDS PROTECTION SECTION 10: WETLANDS PROTECTION 10-1 INTENT AND PURPOSE A. Intent 1. The City finds that wetlands serve a variety of beneficial functions. Wetlands maintain water quality, reduce flooding and erosion,

More information

Stormwater Infrastructure Funding Study Public Education Session May 27, :00 9:00 pm City Hall, Multi-Purpose Room Level 100

Stormwater Infrastructure Funding Study Public Education Session May 27, :00 9:00 pm City Hall, Multi-Purpose Room Level 100 Stormwater Infrastructure Funding Study Public Education Session May 27, 2015 7:00 9:00 pm City Hall, Multi-Purpose Room Level 100 What is the Stormwater Infrastructure funding study? Purpose of the Stormwater

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

Lake Creek Watershed Management Plan Public Meeting. Arrowhead Lake May 3, :00 PM

Lake Creek Watershed Management Plan Public Meeting. Arrowhead Lake May 3, :00 PM Lake Creek Watershed Management Plan Public Meeting Arrowhead Lake May 3, 2018 6:00 PM Agenda I. Welcome and Introductions II. III. IV. Watershed Basics Overview of Lake Creek Watershed Elements of a Successful

More information

Constructed Wetland Use in Nonpoint Source Control

Constructed Wetland Use in Nonpoint Source Control Constructed Wetland Use in Nonpoint Source Control Description Constructed wetlands are excavated basins with irregular perimeters and undulating bottom contours into which wetland vegetation is purposely

More information

Hey and Associates, Inc.

Hey and Associates, Inc. Hey and Associates, Inc. Table 1: 100-Year Study Existing Conditions Discharges and Elevations vs. FIS Results Location Existing FIS Q (cfs) Existing FIS Elevation Existing XP- SWMM Q (cfs) Existing XP-SWMM

More information

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until

More information

Appendix A Stormwater Site Plan Report Short Form

Appendix A Stormwater Site Plan Report Short Form Appendix A Stormwater Site Plan Report Short Form The Stormwater Site Plan Report Short Form may be used for projects that trigger only Minimum Requirements #1-#5. These projects typically fall within

More information

5G. Consider Approval of 50% Plans for Northwood Lake Improvement Project (NL-1), New Hope

5G. Consider Approval of 50% Plans for Northwood Lake Improvement Project (NL-1), New Hope Memorandum To: Bassett Creek Watershed Management Commission Subject: Item 5G. Consider Approval of 50% Plans for Northwood Lake Improvement Project (NL- 1), New Hope BCWMC September 17, 2015 Meeting Agenda

More information

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1 To: From: The City of Virginia Beach Lewis White and Rachael Johnson on behalf of WSP Date: June 6, 2017 Subject: s Drainage Alternatives Analysis This memorandum represents the summary of findings from

More information

Hydromodification Management Measures

Hydromodification Management Measures Chapter 7 Hydromodification Management Measures This Chapter summarizes the requirements for controlling erosive flows from development projects. 7.1 Why Require Hydromodification Management? Changes in

More information

Hydromodification Management Measures

Hydromodification Management Measures Chapter 7 Hydromodification Management Measures This Chapter summarizes the requirements for controlling erosive flows from development projects. 7.1 Why Require Hydromodification Management? Changes in

More information

WQ-06 SAND FILTER. 1.0 Sand Filter. Greenville County Technical Specification for: 1.1 Description

WQ-06 SAND FILTER. 1.0 Sand Filter. Greenville County Technical Specification for: 1.1 Description Greenville County Technical Specification for: WQ-06 SAND FILTER 1.0 Sand Filter 1.1 Description Sand Filters remove pollutants through sedimentation and filtration within the sand. The primary components

More information

BCWMC Capital Improvement Program (approved April 19, 2018; pending minor Plan amendment)

BCWMC Capital Improvement Program (approved April 19, 2018; pending minor Plan amendment) BCWMC Capital Improvement Program 2020 2024 (approved April 19, 2018; pending minor Plan amendment) Project Name City Number 2019 2020 2021 2022 2023 2024 2025 Totals Medicine Lake Rd and Winnetka Ave

More information

Inlet Protection. Fe= (Depends on soil type)

Inlet Protection. Fe= (Depends on soil type) 3.4 DESIGN CRITERIA: KEY CONSIDERATIONS Evaluate drainage patterns to ensure inlet protection will not cause flooding of roadway, property or structures Never block entire inlet opening Size according

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW th Lane NE East Bethel, MN 55005

COON CREEK WATERSHED DISTRICT PERMIT REVIEW th Lane NE East Bethel, MN 55005 18-115 South Terrace Cove, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: July 23, 2018 AGENDA NUMBER: 8 FILE NUMBER: 18-115 ITEM: South Terrace Cove RECOMMENDATION: Approve with

More information

Old Mill School Stream Restoration

Old Mill School Stream Restoration Project Overview This conceptual plan restores and stabilizes two consecutive reaches of a highly incised and unstable stream and reconnects them with the floodplain. The restoration reaches are part of

More information

4. Ponds and infiltration BMPs can achieve 60 to 100% removal efficiencies for sediment.

4. Ponds and infiltration BMPs can achieve 60 to 100% removal efficiencies for sediment. Landscape BMPs For the purposes of this project, preventive measures have been categorized into two categories: landscape BMPs and source prevention BMPs. Landscape BMPs includes both vegetative practices

More information

4.4.6 Underground Detention

4.4.6 Underground Detention 4.4.6 Underground Detention Limited Application Water Quality BMP Description: Detention storage located in underground pipe systems or vaults designed to provide water quantity control through detention

More information

Outfall at Lagoon between Lake of the Isles and Lake Calhoun

Outfall at Lagoon between Lake of the Isles and Lake Calhoun Outfall at Lagoon between Lake of the Isles and Lake Calhoun Prepared for City of Minneapolis April 17, 2013 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601

More information

Constructed Wetland Channel T-9

Constructed Wetland Channel T-9 Description A constructed wetland channel is a conveyance BMP that is built, in part, to enhance stormwater quality. Constructed wetland channels use dense vegetation to slow down runoff and allow time

More information

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission

More information

Best Management Practice Fact Sheet 10: Dry Swale

Best Management Practice Fact Sheet 10: Dry Swale Publication 426-129 Best Management Practice Fact Sheet 10: Dry Swale David J. Sample, Assistant Professor and Extension Specialist, Biological Systems Engineering, Virginia Tech Lia Doumar, Undergraduate

More information

Level 1 One-Box Steady-State Model of Jennings Bay

Level 1 One-Box Steady-State Model of Jennings Bay D R A F T Modeling Three levels of lake modeling are discussed below as they relate to management of water quality in Jennings Bay and Lake Minnetonka in general. Specific data requirements vary, but are

More information

Drainage Report. New Braunfels Municipal Airport. Master Plan Update 2005

Drainage Report. New Braunfels Municipal Airport. Master Plan Update 2005 Drainage Report Master Plan Update 2005 General The Texas Department of Transportation (TxDOT), Aviation Division, retained the consulting engineering team of Parkhill, Smith & Cooper, Inc. (PSC), to prepare

More information

2014 Annual Water Quality Report

2014 Annual Water Quality Report WENCK File #B1240-0155 May 2015 2014 Annual Water Quality Report Prepared for: Shingle Creek and West Mississippi Watershed Management Commissions 3235 Fernbrook Lane Plymouth, MN 55447 shinglecreek.org

More information

Skogman Fannie Elms Florence Lakes Chain Stormwater Retrofit Analysis

Skogman Fannie Elms Florence Lakes Chain Stormwater Retrofit Analysis Skogman Fannie Elms Florence Lakes Chain Stormwater Retrofit Analysis Prepared for the ISANTI COUNTY SOIL AND WATER CONSERVATION DISTRICT By Funding provided in part by the Clean Water Fund of the Clean

More information

Addressing Water Quality in the East Fork Watershed: A Collaborative Effort

Addressing Water Quality in the East Fork Watershed: A Collaborative Effort Addressing Water Quality in the East Fork Watershed: A Collaborative Effort John McManus and Jake Hahn Clermont (OH) Soil & Water Conservation District OKI Annual Meeting Cincinnati Nature Center March

More information

5.15 Wetlands and Other Waters of the U.S.

5.15 Wetlands and Other Waters of the U.S. I-70 East Final EIS 5.15 Wetlands and Other Waters of the U.S. 5.15 Wetlands and Other Waters of the U.S. This section discusses wetlands, open waters, and other waters of the U.S. in the study area and

More information

6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff

6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff October 2003, Revised February 2005 Chapter 6.0, Runoff Page 1 6.1 Introduction 6.0 Runoff The timing, peak rates of discharge, and volume of stormwater runoff are the primary considerations in the design

More information

HYDROLOGIC CONSIDERATIONS. 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY

HYDROLOGIC CONSIDERATIONS. 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY LOW IMPACT DEVELOPMENT HYDROLOGIC CONSIDERATIONS 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY May 18, 2011 PRESENTATION AGENDA Introduction Definitions Discuss Impacts to Hydrologic

More information

3.10 Hydrology and Water Quality. Environmental Setting

3.10 Hydrology and Water Quality. Environmental Setting 3.10 Hydrology and Water Quality This section describes the potential hydrology and water quality impacts associated with the proposed changes to the approved project. Environmental Setting This section

More information

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What

More information

ORDINANCE # 854. Stormwater Management / Operation and Maintenance Requirements

ORDINANCE # 854. Stormwater Management / Operation and Maintenance Requirements ORDINANCE # 854 Stormwater Management / Operation and Maintenance Requirements Section 1. Purpose and Authority In accordance with the provisions of Chapters 98, 124, 126, 440, 444, and 446h of the General

More information

Presentation Overview

Presentation Overview Little Dry Creek Restoration Deep River Flood Risk Management Final Presentation to LCRBDC June 10, 2015 Presentation Overview Project Overview & Background Information Data Collection Model Development

More information

Fort Leonard Wood, Missouri. September 2013

Fort Leonard Wood, Missouri. September 2013 Fort Leonard Wood, Missouri September 2013 1 Presenters Shannon Kelly, Physical Scientist Clean Water Act Program Manager Directorate of Public Works Environmental Division Environmental Compliance Branch

More information

DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection. Design Criteria - Wetlands Replacement/Monitoring

DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection. Design Criteria - Wetlands Replacement/Monitoring DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection DOCUMENT NUMBER: 363-0300-001 TITLE: Design Criteria - Wetlands Replacement/Monitoring EFFECTIVE DATE: February 11, 1997 AUTHORITY:

More information

Infiltration Basin Description Applicability

Infiltration Basin Description Applicability Infiltration Basin Description An infiltration basin is a shallow impoundment which is designed to infiltrate storm water into the ground water. This practice is believed to have a high pollutant removal

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. KTJ 314, LLC Blaine, MN 55449

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. KTJ 314, LLC Blaine, MN 55449 18-118 ABRA Auto Body, Page 1 of 8 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 13, 2018 AGENDA NUMBER: 14 FILE NUMBER: 18-118 ITEM: ABRA Auto Body RECOMMENDATION: Approve with 6 Stipulations

More information

Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No.

Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No. Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates 2005 VNH File No. 35317-210-21 Table of Contents Introduction... 3 Goals... 3 Storm water Discussion...

More information

Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations

Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations drainage. The easement could potentially be used to site a surface water quality treatment facility for the flow. The design

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

PRELIMINARY DRAINAGE STUDY

PRELIMINARY DRAINAGE STUDY PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,

More information

The Town of Chester Stormwater Mapping Report

The Town of Chester Stormwater Mapping Report The Town of Chester Stormwater Mapping Report Prepared by the Warren County Soil & Water Conservation District December 2013 Table of Contents Introduction and Location 3 Stormwater Runoff 3 Assessment

More information

Hydrologic Study Report for Single Lot Detention Basin Analysis

Hydrologic Study Report for Single Lot Detention Basin Analysis Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page

More information

BMP #: Infiltration Basin

BMP #: Infiltration Basin Structural BMP Criteria BMP #: Infiltration Basin An Infiltration Basin is a shallow impoundment that stores and infiltrates runoff over a level, subtle, uncompacted, (preferably undisturbed area) with

More information

Comfort Lake-Forest Lake Watershed District Six Lakes Total Maximum Daily Load Implementation Plan

Comfort Lake-Forest Lake Watershed District Six Lakes Total Maximum Daily Load Implementation Plan Prepared by: for the Comfort Lake-Forest Lake Watershed District and the Minnesota Pollution Control Agency Comfort Lake-Forest Lake Watershed District Six Lakes Total Maximum Daily Load February 16, 2010

More information

TOWN LINE BROOK URBAN WATERSHED STUDY MODELING INCREMENTAL IMPROVEMENTS

TOWN LINE BROOK URBAN WATERSHED STUDY MODELING INCREMENTAL IMPROVEMENTS TOWN LINE BROOK URBAN WATERSHED STUDY MODELING INCREMENTAL IMPROVEMENTS Marcus M. Quigley, P.E., Project Engineer, GeoSyntec Consultants Steven P. Roy, Associate, GeoSyntec Consultants Lawrence Gil, North

More information

Memo. To: From: cc: For further assistance please contact Ben Ruzowicz, GSWCC Technical Specialist at (706)

Memo. To: From: cc: For further assistance please contact Ben Ruzowicz, GSWCC Technical Specialist at (706) Memo To: From: cc: Local Issuing Authorities, Design Professionals, Plan Reviewers and Other Interested Parties The Georgia Soil and Water Conservation Commission and the Georgia Environmental Protection

More information

3F. Hydrology and Water Quality

3F. Hydrology and Water Quality This section provides an analysis of potential hydrological and water quality impacts associated with implementation of the proposed project. The section also evaluates and describes the potential impacts

More information

Design Features of Constructed Wetlands for Nonpoint Source Treatment. September 1995

Design Features of Constructed Wetlands for Nonpoint Source Treatment. September 1995 Design Features of Constructed Wetlands for Nonpoint Source Treatment September 1995 Brochure written by William W. Jones, School of Public and Environmental Affairs, Indiana University, Bloomington, Indiana.

More information

City of Fairmont Storm Water Pollution Prevention Plan Annual Public Meeting. June 11, 2018

City of Fairmont Storm Water Pollution Prevention Plan Annual Public Meeting. June 11, 2018 City of Fairmont Storm Water Pollution Prevention Plan Annual Public Meeting June 11, 2018 Why is Water Quality Important? Water has always been important to Minnesota and is a key part of our history,

More information

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) Activity: Infiltration Systems PLANNING CONSIDERATIONS: Design Life: Short IS Acreage

More information

MnRAM Guidance on Selected Questions

MnRAM Guidance on Selected Questions MnRAM Guidance on Selected Questions 1 1 Formula: Vegetative Integrity/Diversity There are four ways to report this function: Individual Community Scores: maintain raw data as recorded. Highest Quality

More information

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond)

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Chapter 10 Design Examples Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Example 2: Filter Design in a commercial development

More information