AESO Considerations and Experiences with Development of Wind Facility Interconnection

Size: px
Start display at page:

Download "AESO Considerations and Experiences with Development of Wind Facility Interconnection"

Transcription

1 AESO Considerations and Experiences with Development of Wind Facility Interconnection John H. Kehler, Senior Technical Specialist BC Focused Wind Workshop January 25-26, 2005

2 Topics Background on Alberta and AESO Considerations for Wind Interconnection Existing and Future Development Modeling and representation of wind facilities Technical requirement development for Reliability and System Operations Standard Development and Continued Work Experiences Voltage Regulation, Power Quality, Operations

3 Background Alberta Existing Generation Capacity Generating Capacity (MW) 8% 2% 1% Coal 5,999 Gas 4,738 Hydro 917 Wind 279 Biomass 153 Fuel Oil 8 Total 12,094 Interconnections: British Columbia Saskatchewan % 50%

4 Industry Structure (June 2003) Electric Utilities Act Minister of Energy Appoints Board members, MSA & EUB Chair Balancing Pool Wholesale Energy Market Alberta Electric System Operator Load Settlement Alberta Energy & Utilities Board (EUB) Regulates AESO s Transmission business Market Surveillance Administrator (MSA) Transmission DFO s Real-time Alberta Electric System Operator TFO s

5 Concerns with Integration of Wind Power Wind Power Industry concerns Voltage Behavior Low voltage tripping Voltage Regulation Operations impact as a result of wind power variability Previous AESO standard inadequate for wind development No requirements for low voltage ride through capability No ability to manage power from facility

6 To Natal B -1S C o lem a n 79 9S Lu nd b re ck 51 3S Cowley Ridge S 4 1 M W L C a stle R iver S 4 0 M W Shell W aterton 37 9S Shell Waterton S 53 F t. M a c le o d Oldman Hydro 3 2 M W P in ch e r C re e k S Y a rrow 99 5 S D ryw o od S N 17 0L To Janet 7 4 S P e ig a n 5 9 S S ta vely S 5 5 G le n w o o d To Blackie 25 3S G le n w o o d S E. S ta ve ly 92 8 S F t. M a cle o d 1 5 S L S p ring C o u lee 38 5S L Le th b ridg e S S R iverb e n d S Taylor Chute 13 M W To Milo Junctio n N. Le thb rid g e S M ag ra th S S S L a ke vie w S T e m p e st S R a ym o n d 2 1 M W C o a lda le S Chin Chute 1 1 M W S tirlin g 6 7 S 185L 164L 863L 66L 180L 911L T o C ra n b ro ok L T o L a n gd o n 10 2S S u m m e rvie w 131 MW (Total) Kettles Hill 6 3 M W W a te rto n M W L/1 62 L L M a cleod F la ts 6 0 M W 17 0 L S o d e rgle n 71 M W McBride Lake 7 5 M W M ag ra th 3 0 M W 22 5 L 92 4L L 1201L L L T a y lor 3.4 M W Irric an H y dro 7 M W L W a rne r S To Taber 25 4S Southwest Alberta Existing wind generation 279 MW Proposed wind generation 560 MW Monarch 492S 725AL 820L 6 9 k V kv 2 40 kv kv Planned Custom er Interconnection P lan ts E x is tin g F u tu re H ydro W in d P ro po s ed Lin e

7 Southeast Alberta Proposed wind generation 200 MW To Oyen 767S To Langdon 102S Brooks To Queens Town 504S 935L 923L Enchant 447S Bassano 431S 853L W. Brooks 28S 763AL To Anderson 801S 763L Ware Junction 132S 814L 827L Duchess 339S Cutting Lake 227S Brooks 121S 795L 951L 944L Tilley 498S 100L Wardlow 223S Jenner 275S N Empress Suffield 895S 100L 945L Empress Liquids 164S Sandy Point 204S Empress 394S 760AL 869L 760L 163S 830L 9LS1M Sask Power McNeill Interconnection Convertor Station 840S Sand Hills 341S 760L 871L 7L760/760L Amoco Empress Monarch 492S 725L Lethbridge 674S Riverbend 618S 924L 923L Coaldale 254S To Peigan 59S 172L To Ft. Macleod 820L 15S N. Lethbridge 370S 207L To Peigan 59S 111S 241S 146S 863L 725AL 734L 813L 823L Lakeview 593S 172L Lethbridge 824L Vauxhall 158S Taber 83S Chin Chute IPP 11MW Tempest 403S 66L To Stirling 67S 821L Fincastle 336S 172AL Conrad 135S Hays 421S Vauxhall Purple Springs 80MW Burdett 368S 722L Westfield 107S 172L Medicine Hat Bullshead 523S Seven Persons 120MW 172L Medicine Hat 41S To City of Medicine Hat Peace Butte 404S Chappice L. 649S To Magrath 225S 138 kv 240 kv 138 kv - New Capacitor banks Thermal Plant Future W ind Farm

8 Summary of AESO actions to address concerns New Standard Voltage Ride Through and Voltage Regulation requirements TFO must have ability to trip wind farm facility, in emergencies. Small wind farms exempt from certain requirements. Further Studies and Consultation Initiated wind power variability study with support provided by wind developers. Continue to consult with industry in the development of wind power technical requirements.

9 Intent of the Wind Power Facility Standard Treat wind farms similar to other generators, while recognizing differences in technologies. Interconnection requirements are not intended to exclude particular wind power technologies. Standards contribute to maintaining AIES reliability. New standards are not intended to be applied retroactively. Technical standards to be consistent with North American practices, under similar circumstances, and evolving standards. Stakeholder consultation throughout the initiative.

10 Considerations for Wind Interconnections Existing and Future Development

11 Forecast Wind Capacity as a Percentage of Total Alberta Generation 8% % % Alberta Calif. PJM New York ERCOT

12 Considerations for Wind Interconnections Modeling and Representation of Wind Facilities

13 Dynamic Models NEW MODEL OLD MODEL 15% Accurate models are required for dynamic studies LVRT at 15% did not mitigate multiple wind facility trips with the original model used in the studies.

14 Wind Facility Modeling Standard Development WTGs < 690v kv Transmission Voltage External Voltage Regulation / Reactive Power System WIND POWER FACILITY REPRESENTATION

15 Wind Facility Modeling Actual Facilities Depending on the nature of the study the AESO may use; single turbine representation Example: Network studies full detailed representation Example: Dynamic simulation for testing and validation

16 Considerations for Wind Interconnections Technical Requirement Development for Reliability and System Operations

17 AESO Voltage Ride Through standard is to; mitigate multiple wind facility tripping identified in studies, satisfy operating requirements, and specified at the transmission voltage of the wind facility. temporary consideration until Jan

18 AESO Voltage Regulation standard is to; accommodate unique differences and advanced technology for wind facilities. provide options to satisfy voltage and reactive power requirements. Installation at transmission voltage levels or within wind facility. Static, dynamic and overload capabilities. Facilities must be capable of voltage set-point adjustment of +/- 5% from rated.

19 AESO Power Management standard; Operational requirements of wind facilities will be determined following the variability study. Power management is optional at this time and will be assessed after the variability study. Permits self-control of Wind facilities. Ability to start, stop and change load without operator intervention. Coarse Control Remote trip only of a wind facility by a TFO during emergencies.

20 Wind Facility Monitoring Normal SCADA requirements plus wind speed and wind direction. Dynamic system monitoring equipment to record wind facility voltage, reactive power and real-power behavior to system disturbances Testing and Validation Voltage Regulation and Reactive Power capability

21 Experiences Voltage Regulation, Power Quality, Operations

22 Voltage Regulation The AESO requires testing and validation of the automatic voltage regulation controls. A Phasor Measurement Unit monitors the collector feeders into the low side of the system step-up transformer. Validation is performed with GE PSLF or PTI PSS/E.

23 Voltage Quality Wind facility measurement Alberta Voltage Flicker Curve Wind facility measurement well within compliance.

24 Total Wind Power During December 2004 Alberta Total Wind (Dec 2004) MW Time - 1 Day Per Division

25 Deviation in % of Capacity Dec MINUTE 30 MINUTE VARIABILITY- 10 MIN AVERAGES VARIABILITY- 30 MIN AVERAGES 20 VARIABILITY- MINUTE 20 AVERAGES 60 MINUTE VARIABILITY- 60MIN AVERAGES Where 1 = 100%

26 Questions? Web Site: John Kehler, ,

27

ALBERTA POWER MARKET

ALBERTA POWER MARKET ALBERTA POWER MARKET www.canaxenergy.com Generating Capacity Generating Capacity [MW] Coal 5,840 Gas 4,434 Hydro 900 Wind 522 Biomass 184 Fuel Oil 13 Subtotal 11,892 Interconnections British Columbia 750

More information

Technologies to Enable Wind Power Integration. John Kehler Technical Lead System Performance

Technologies to Enable Wind Power Integration. John Kehler Technical Lead System Performance Technologies to Enable Wind Power Integration John Kehler Technical Lead System Performance Presentation Outline The AESO Overview of Wind Development in Alberta Technologies Wind Power Forecasting System

More information

Calculation of the Grid Emission Intensity Factor for Alberta

Calculation of the Grid Emission Intensity Factor for Alberta Calculation of the Grid Emission Intensity Factor for Alberta Using the Wind Energy Working Group s Proposed Methodology Disclaimer The information and data provided in this report has been obtained or

More information

Alberta s Irrigation A Strategy for the Future

Alberta s Irrigation A Strategy for the Future Government Alberta s Irrigation A Strategy for the Future 2016/17 Strategy Measures Alberta's Irrigation Strategy for the Future Alberta's Irrigation - a Strategy for the Future 2016/17 Strategy Measures

More information

Preliminary Report to Alberta Electric System Operator. Transmission Costs. April 19, 2006

Preliminary Report to Alberta Electric System Operator. Transmission Costs. April 19, 2006 Preliminary Report to Alberta Electric System Operator Transmission Costs April 19, 2006 PS Technologies Arnie Reimer, P. Eng. Table of Contents 1. Overview...2 2. Bulk System Coincidence...3 2.1 Alberta

More information

Alberta s Irrigation Infrastructure

Alberta s Irrigation Infrastructure Alberta s Irrigation Infrastructure Reservoir Diversion structure Dam Spillway River Reservoirs store and control primary water supplies for irrigation. In Alberta, most of the stored water is from spring

More information

Transmission System Long-term View Alberta Power Industry Consortium

Transmission System Long-term View Alberta Power Industry Consortium Transmission System Long-term View Alberta Power Industry Consortium Jerry Mossing Vice-President Transmission Planning and Performance November 6, 2013 Power Industry Structure in Alberta Minister of

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

Understanding Bill 50

Understanding Bill 50 1 Understanding Bill 50 Major Players: Energy Utilities Board (EUB): Prior to 2008, the EUB was the governing body responsible for regulating the entire energy industry in Alberta, including transmission

More information

Wind Farm Performance on the Grid: Perception and Reality

Wind Farm Performance on the Grid: Perception and Reality Wind Farm Performance on the Grid: Perception and Reality WindVAR and LVRT Data and Graphs provided by Nicholas W. Miller GE Energy, Energy Consulting 1 GE Energy Wind Energy Grid Performance: A Perception

More information

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement Your guide to the SOUTHERN ALBERTA Transmission Reinforcement OUR TRANSMISSION LINES TRANSPORT THE POWER YOU USE EVERY DAY. Edmonton Red Deer Calgary Lethbridge 85% AltaLink s transmission system efficiently

More information

Alberta Transmission System Transmission Cost Causation Update. September 15, Prepared for the. Alberta Electric System Operator (AESO)

Alberta Transmission System Transmission Cost Causation Update. September 15, Prepared for the. Alberta Electric System Operator (AESO) Alberta Transmission System 2006 Transmission Cost Causation Update September 15, 2006 Prepared for the Alberta Electric System Operator (AESO) PS Technologies Inc. Arnie Reimer, P. Eng. Table of Contents

More information

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation Observations and Information Sharing Date: June, 2015 Prepared by: AESO Table of Contents Executive Summary...

More information

Wind Generation Part I Planning, Design & Operations

Wind Generation Part I Planning, Design & Operations Wind Generation Part I Planning, Design & Operations Jack Hochheimer, FPL Energy, LLC Providing Safe, Reliable Power for 75 Years FPL Group one of the nation s largest providers of electricity-related

More information

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator Energy Storage Integration in Alberta s Energy Only Market Kevin Dawson Director, Market Design Alberta Electric System Operator Outline The AESO and Alberta s Wholesale Electricity Market About the AESO

More information

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study Point to Point US to BC, BC to Alberta and wheel through US to Alberta System Impact Study Report No. SPA 2007-85 November 2007 Transmission System Planning British Columbia Transmission Corporation British

More information

BPA Wind Voltage Control Requirements

BPA Wind Voltage Control Requirements BPA Wind Voltage Control Requirements PJM Conference Dmitry Kosterev Bonneville Power Administration Many of BPA Paths are Stability-Limited Cross-Cascades North Montana - Northwest Cross-Cascades South

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April 28 2016 Renewable Energy Systems (RES) In Canada for more than 12 years Family-owned company

More information

DECISIONS on operating transfer limits and transmission

DECISIONS on operating transfer limits and transmission 1144 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 2, MAY 2004 Hydro Turbine-Governor Model Validation in Pacific Northwest Dmitry Kosterev Abstract This paper presents an approach for generator model

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement September 8, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-126: Needs Identification Document

More information

Improving Customer Service

Improving Customer Service May 2013 In this issue Improving customer service: Navigating the transmission process Connecting with AltaLink a customer s perspective Direct connecting customer survey Feature stories An update on industry

More information

Ancillary Services from Wind and Solar. Power Plants. CanWEA O&M Workshop January 30, 2018 Toronto, Ontario. J. Charles Smith Executive Director UVIG

Ancillary Services from Wind and Solar. Power Plants. CanWEA O&M Workshop January 30, 2018 Toronto, Ontario. J. Charles Smith Executive Director UVIG Ancillary Services from Wind and Solar CanWEA O&M Workshop January 30, 2018 Toronto, Ontario J. Charles Smith Executive Director UVIG Power Plants Toronto, CA Jan 2018 -- 2 Background Outline of Topics

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC 006 RFC 01 3. Purpose: To establish ReliabilityFirst requirements for automatic Load shedding (UFLS) to support

More information

Technical considerations for integration of distributed renewables on the grid

Technical considerations for integration of distributed renewables on the grid Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services

More information

Approaches to Generation Dispatch in Transmission Planning

Approaches to Generation Dispatch in Transmission Planning 21, rue d Artois, F-75008 PARIS Paper 135 GUILIN 2009 Approaches to Generation Dispatch in Transmission Planning P. J. PALERMO KEMA, Inc. USA SUMMARY A critical factor affecting transmission system development

More information

Interconnection System Feasibility Study

Interconnection System Feasibility Study Interconnection System Feasibility Study Zonnebeke Wind Project Report No: T&S Planning 2015-053 November 2015 FINAL British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Wind Power Forecasting Process Development

Wind Power Forecasting Process Development Wind Power Forecasting Process Development Data Management Working Group (DMWG) Generation and Transmission Valley Forge, PA Thursday, August 20, 2009 Sanjay Patil PJM Interconnection Table of Contents

More information

Virtual power Plant Concept in Electrical Networks

Virtual power Plant Concept in Electrical Networks Virtual power Plant Concept in Electrical Networks J. Corera Iberdrola Distribution on behalf of a step towards the future of a step towards the future of electricity networks 1 Introduction to the VPP

More information

GOLDEN VALLEY ELECTRIC ASSOCIATION

GOLDEN VALLEY ELECTRIC ASSOCIATION October 13, 2008 GOLDEN VALLEY ELECTRIC ASSOCIATION Eva Creek Wind Farm-Limited Study Doubly Fed Asynchronous Generators Power Flow, Reactive Compensation, Transient Stability Revision 0 PROJECT NUMBER:

More information

Decision Cenovus FCCL Ltd.

Decision Cenovus FCCL Ltd. Decision 2012-196 Construct and Operate a 95-MW Cogeneration Power Plant, Construct and Operate Sunday Creek 539S Substation, Industrial System Designation and Interconnection of the Christina Lake Industrial

More information

YOUR LOCAL DEVELOPER

YOUR LOCAL DEVELOPER YOUR LOCAL DEVELOPER ABOUT Alberta Wind Energy Corporation ( AWEC ) was formed in 2003 to develop independent wind farm projects. The Company is currently focused on developing several sites, taking a

More information

Renewable Energy Impact to Distribution Network Performance and Reliability. ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO

Renewable Energy Impact to Distribution Network Performance and Reliability. ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO Renewable Energy Impact to Distribution Network Performance and Reliability ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO Presentation Outline 1. RE Integration and changes in the Electric

More information

2017 Long-term Outlook. Information Session July 25, 2017

2017 Long-term Outlook. Information Session July 25, 2017 2017 Long-term Outlook Information Session July 25, 2017 0 Welcome Overview of 2017 Long-term Outlook (2017 LTO) Questions will be answered at the end of the presentation Please use microphone when asking

More information

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE CHENNAI INDIAN WIND GRID CODE Rajesh Katyal Unit Chief, R&D Centre for Wind Energy Technology OVERVIEW NEED FOR INDIAN WIND GRID CODE Wind energy constitutes 6% of the installed capacity in the power scenario

More information

Assessment of Water Quality in Alberta s Irrigation Districts

Assessment of Water Quality in Alberta s Irrigation Districts Assessment of Water Quality in Alberta s Irrigation Districts Summary Second Edition November 2010 Government of Alberta Assessment of Water Quality in Alberta s Irrigation Districts Second Edition Acknowledgements

More information

Consolidated Authoritative Document Glossary

Consolidated Authoritative Document Glossary Consolidated Authoritative Document Glossary Term "10 minute clock period" Definition means any one of the following six (6) ten (10) minute periods in any hour: ME:01 to ME:10; ME:11 to ME:20; ME21 to

More information

Recent US Wind Interconnection Experience

Recent US Wind Interconnection Experience Wind Energy and Grid Integration Recent US Wind Interconnection Experience J. Charles Smith Nexgen Energy LLC Utility Wind Integration Group January 24-25, 2006 Madrid, Spain Outline of Topics Background

More information

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403 AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination

More information

Lesson learned about the integration of large amount of volatile Renewable Energy Resources

Lesson learned about the integration of large amount of volatile Renewable Energy Resources Francesco Rizzo, Area Manager America & Iberia III BIREGIONAL FORUM WEC N.A. AND LAC- Cancun, Dec. 6-7, 2012 How to Satisfy the Energy Demand of the Americas in a World with Greater Environmental and Financial

More information

Introduction to the PJM Markets

Introduction to the PJM Markets Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility

More information

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013 NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC 006 RFC 01 3. Purpose: To establish ReliabilityFirst requirements for automatic underfrequency Load shedding

More information

Grid Interconnection Issues for Wind Generation

Grid Interconnection Issues for Wind Generation Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical

More information

Information Document Protection System Information ID# R

Information Document Protection System Information ID# R Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between the Information Document and the related authoritative document(s)

More information

LONG TERM PLANNING, PRINCIPLES & PRACTICAL ANALYSES TURKISH ELECTRICITY TRANSMISSION CORPORATION

LONG TERM PLANNING, PRINCIPLES & PRACTICAL ANALYSES TURKISH ELECTRICITY TRANSMISSION CORPORATION LONG TERM PLANNING, PRINCIPLES & PRACTICAL ANALYSES TURKISH ELECTRICITY TRANSMISSION CORPORATION www.teias.gov.tr CONTENT Overview of Turkish Transmission System Load and Generation Forecasts Preparing

More information

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection Feasibility Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy February / 2015 Introduction

More information

Alberta Intertie Restoration Initiative Discussion Paper

Alberta Intertie Restoration Initiative Discussion Paper Alberta Intertie Restoration Initiative Discussion Paper March 25, 2010 Table of Contents 1.0 Executive Summary... 2 2.0 Intertie Capacity Restoration Policy Background... 3 2.1 Obligation to Restore Intertie

More information

MON TANA M EAN S BU SINE SS MONTANA TRANSMISSION FOR AMERICA CLEAN ENERGY AND TRANSMISSION DEVELOPMENT IN MONTANA AND THE WEST

MON TANA M EAN S BU SINE SS MONTANA TRANSMISSION FOR AMERICA CLEAN ENERGY AND TRANSMISSION DEVELOPMENT IN MONTANA AND THE WEST MON TANA M EAN S BU SINE SS MONTANA TRANSMISSION FOR AMERICA CLEAN ENERGY AND TRANSMISSION DEVELOPMENT IN MONTANA AND THE WEST MONTANA CLEAN ENERGY AND TRANSMISSION DEVELOPMENT Montana is energy country.

More information

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm SYNOPSIS OF THE THESIS Enhanced Power Quality Management of Grid Connected Wind Farm INTRODUCTION OF THE THESIS Faster depletion of fossil fuels and environmental damage has resulted into increased use

More information

Renewable and Alternative Energy - Alberta. National Renewable Energy Forum April Susan Carlisle Director, Alternative Energy

Renewable and Alternative Energy - Alberta. National Renewable Energy Forum April Susan Carlisle Director, Alternative Energy Renewable and Alternative Energy - Alberta National Renewable Energy Forum April 2 2013 Susan Carlisle Director, Alternative Energy What is Driving Alberta Today? Market Access Infrastructure Social License

More information

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017 FALL 2017 PROJECT OVERVIEW EDF EN Canada is proposing to develop, construct, and operate the Cypress Wind Power Project with 243.6 megawatts (MW) of generating capacity. The Project is south of Dunmore,

More information

Key Issues and Consideration in Market Design, Operational and Oversight

Key Issues and Consideration in Market Design, Operational and Oversight Key Issues and Consideration in Market Design, Operational and Oversight Patrick Donlon Amanda Gordon Kathryn Sophy Kenneth Villwock Public Utilities Commission of Ohio & Pennsylvania Public Utilities

More information

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015 EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be

More information

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL Case s 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality s FINAL Introduction Powerflow and dynamics cases are the foundation of virtually all power system studies. Calculations

More information

Summary of the Tutorial on Fundamentals of Wind Energy IEEE PES 2010 T&D Conference New Orleans, Louisana

Summary of the Tutorial on Fundamentals of Wind Energy IEEE PES 2010 T&D Conference New Orleans, Louisana Summary of the Tutorial on Fundamentals of Wind Energy IEEE PES 2010 T&D Conference New Orleans, Louisana Sponsorship This tutorial is sponsored by (WPCC). Cosponsors include PSDP Committee, T&D Committee,

More information

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM Wholesale Markets Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM RTO Functions Grid Operation Non-discriminatory treatment Monitoring transmission system Reliability

More information

Alberta s Irrigation Water Management Challenges

Alberta s Irrigation Water Management Challenges Alberta s Irrigation Water Management Challenges - The Need For Water Measurement - 2010 Water Measurement Workshop July 14-15, 2010 Lethbridge, Alberta Alberta s Water Challenges Increasing public pressure

More information

Information Document Regulating Reserve ID # R

Information Document Regulating Reserve ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

Collaborative Approach for Wind Power Plant Model Data and Validation

Collaborative Approach for Wind Power Plant Model Data and Validation Collaborative Approach for Wind Power Plant Model Data and Validation Dmitry Kosterev, Steve Yang and Gordon Kawaley, BPA WECC MVWG October 5, 2017 1 Regulatory Landscape NERC MOD-032 Data for Power System

More information

Modeling DER in Transmission Planning CAISO Experience

Modeling DER in Transmission Planning CAISO Experience Modeling DER in Transmission Planning CAISO Experience Irina Green Regional Transmission Senior Advisor, California ISO NERC Load Modeling Task Force Meeting April 18-19 2017 DER Types (NERC Reliability

More information

Renewable Energy in Power Systems

Renewable Energy in Power Systems Renewable Energy in Power Systems Leon Freris Centre for Renewable Energy Systems Technology (CREST), Loughborough University, UK David Infield Institute of Energy and Environment, University of Strathclyde,

More information

Peak West-wide System Model Validation Activities

Peak West-wide System Model Validation Activities Peak West-wide System Model Validation Activities 10/24/2016 Brett Wangen Hongming Zhang Gareth Lim Purpose of This Discussion Provide West-wide System Model (WSM) overview Give insight into ongoing model

More information

Intertie Capacity Value for Alberta

Intertie Capacity Value for Alberta Intertie Capacity Value for Alberta PREPARED FOR PREPARED BY Johannes Pfeifenberger Judy Chang Kathleen Spees Yingxia Yang David Luke Oates Colin McIntyre November 1 st, 2017 This report was prepared for

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction

More information

Conseptualizing Flexibility In Power Systems

Conseptualizing Flexibility In Power Systems Conseptualizing Flexibility In Power Systems 21 st Century Power Partnership: An Initiative of the Clean Energy Ministerial Dr. Douglas Arent National Renewable Energy Laboratory Operating Agent for the

More information

Western Wind & Solar Integration Studies

Western Wind & Solar Integration Studies Western Wind & Solar Integration Studies Kara Clark, Greg Brinkman, NREL Nick Miller, Miaolei Shao, Slobodan Pajic, Rob D Aquila, Bruno Leonardi, GE 3/22/17 NREL is a national laboratory of the U.S. Department

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Ditni Yoh Green Energy April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY

More information

Quality Wind Project. Operations Workshop Clean Energy BC, October 2014

Quality Wind Project. Operations Workshop Clean Energy BC, October 2014 Quality Wind Project Operations Workshop Clean Energy BC, October 2014 1 North American footprint Ownership interest in 14 facilities with more than 2,600 MW (1) Operating Plants Under Construction Natural

More information

Regional Impact of Renewables: ERCOT

Regional Impact of Renewables: ERCOT Regional Impact of Renewables: ERCOT Kenan Ögelman VP, Commercial Operations, ERCOT February 1, 2018 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external connections

More information

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation. Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Grid Integration in Sri Lanka

Grid Integration in Sri Lanka Auf in neue Märkte! Exportinitiative Energie MIDIGASPE SAMITHA 05.09.2017 Chief Engineer (Renewable Energy Projects) Ceylon Electricity Board Sri Lanka Grid Integration in Sri Lanka Overview Country Overview

More information

Limon 100 MW Wind Farm System Interconnection Study

Limon 100 MW Wind Farm System Interconnection Study Limon 100 MW Wind Farm System Interconnection Study October 27, 2004 Studies Conducted By: Garrett Durland Limon Wind Farm Impact Study I. Introduction In April 2004, Western Area Power Administration

More information

Power Plant Model Verification using PMUs

Power Plant Model Verification using PMUs Power Plant Model Verification using PMUs Ryan D. Quint, PhD, PE NASPI Work Group Meeting March 2016 Importance of Accurate Models 2 Verifying Power Plant Component Models 3 MOD-026-1 & MOD-027-1: Verification

More information

Decision Criteria from Estimated Financial Impacts IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005

Decision Criteria from Estimated Financial Impacts IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005 Decision Criteria from Estimated Financial Impacts 2005 IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005 Resource Option Workshops 1st meeting (Dec 7) Introduction / Process of input / feedback

More information

ATC Ten-Year Transmission System Assessment. ATC Transmission Briefing October 29, 2008

ATC Ten-Year Transmission System Assessment. ATC Transmission Briefing October 29, 2008 ATC Ten-Year Transmission System Assessment ATC Transmission Briefing October 29, 2008 Transmission Planning Process Build Transmission System Models Identify Transmission System Needs Develop Solutions

More information

Power and Energy Systems Engineering

Power and Energy Systems Engineering Engineering Planning Project Management Operations Support Provided By J. J. Bergeron & Company, Inc. 1900 Veterans Memorial Blvd. Suite 205 Metairie, La. 70005 Power and Energy Systems Engineering Services

More information

Eastern Wind Integration and Transmission Study

Eastern Wind Integration and Transmission Study Eastern Wind Integration and Transmission Study Great Lakes Regional Wind Energy Workshop March 1, 2010 Dave Corbus National Renewable Energy Lab 1 EWITS Analysis - What is Needed to Integrate 20% Wind

More information

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011 Draft 2011 Long-term Transmission Plan Stakeholder Session June 20, 2011 Agenda Highlights of draft 2011 Long-term Transmission Plan Discussion of project costs and rate impact Impact of transmission constraints

More information

Operational Characteristics of Wind Windfarms

Operational Characteristics of Wind Windfarms Operational Characteristics of Wind Windfarms Panel sponsored by Energy Development and Power Generation Committee PES General Meeting, Montreal, Canada June 19, 2006 Badrul H. Chowdhury (Panel Chair)

More information

WWSIS - 3: Western Frequency Response and Transient Stability Study

WWSIS - 3: Western Frequency Response and Transient Stability Study WWSIS - 3: Western Frequency Response and Transient Stability Study GE Energy Nicholas W. Miller (PM) Miaolei Shao Slobodan Pajic Rob D Aquila NREL Kara Clark (PM) NERC ERSTF Briefing Atlanta December

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas 2012 NCTPC PJM Joint Interregional Reliability Study PJM Interconnection Duke Energy Carolinas Progress Energy Carolinas January 2013 1 Executive Summary The joint study consisted of a reliability analysis

More information

2011/2012 RPM Base Residual Auction Results

2011/2012 RPM Base Residual Auction Results Executive Summary The 2011/12 Reliability Pricing Model (RPM) Base Residual Auction (BRA) cleared 132,221.5 MW of unforced capacity in the RTO at a uniform Resource Clearing Price of $110.00/MW-day. This

More information

Renewable Integration at ERCOT

Renewable Integration at ERCOT Renewable Integration at ERCOT Dan Woodfin Director of System Operations ERCOT CIGRE Chile September 12, 2016 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external

More information

What makes a Wind Plant Grid Friendly?

What makes a Wind Plant Grid Friendly? Stable Renewable Plant Voltage and Reactive Power Control NERC ERSTF June 11-12, 2014 Sebastian Achilles Nicholas Miller Einar Larsen Jason MacDowell GE Energy Consulting 1 / Topics Features of modern

More information

Advances in VG Integration

Advances in VG Integration Advances in VG Integration Southeastern Wind Coalition Georgia Power Headquarters Atlanta, GA March 30, 2016 J. Charles Smith Executive Director UVIG Atlanta, March 2016 -- 2 What is UVIG? Non-profit corporation

More information

Centralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011

Centralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011 Centralia Power Plant Closure Study Initial Study Results DRAFT March 17, 2011 Conditions Studied 5 and 10-year Winter and Summer Peak 5-year Light Autumn High Transfers to and from British Columbia Additional

More information

Managing Director Transmission Operations

Managing Director Transmission Operations Managing Director Transmission Operations Responsible for the safe, reliable, cost-effective, and profitable operational management of AEP's transmission assets including: 1) directs and manages AEP's

More information

The Impact of Wind Generation on System Services in Ireland

The Impact of Wind Generation on System Services in Ireland The Impact of Wind Generation on System Services in Ireland Renewable Energies, an Opportunity and Challenge for Electricity Systems October 8th 2009 Dr Ivan Dudurych, EirGrid 4000 600 3600 480 Load, MW

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2014-126 South and West Edmonton Area Transmission System Reinforcement Needs Identification Document May 5, 2014 The Alberta Utilities Commission Decision 2014-126: South and West Edmonton Area

More information

LOW POWER FACTOR AT WINGHAM TS ASSESSMENT

LOW POWER FACTOR AT WINGHAM TS ASSESSMENT LOW POWER FACTOR AT WINGHAM TS ASSESSMENT Date: October 18 th, 2016 Prepared and Reviewed by: Sacha Constantinescu, P.Eng Transmission Planner System Planning Jerry Vo Distribution Planner Distribution

More information

Investigating Power System Primary and Secondary Reserve Interaction under High Wind Power Penetration Using Frequency Response Model

Investigating Power System Primary and Secondary Reserve Interaction under High Wind Power Penetration Using Frequency Response Model 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium Investigating Power System Primary and Secondary Reserve Interaction under High Wind

More information

PAULA ZARNETT. She has performed assignments for clients in North America, China, Ghana, and Barbados.

PAULA ZARNETT. She has performed assignments for clients in North America, China, Ghana, and Barbados. Paula Zarnett has more than 25 years broadly based experience specializing in regulatory compliance, regulated tariffs and pricing issues for electricity and gas utilities. She has been responsible for

More information

Integrating DER in PJM Transmission Operations and Planning

Integrating DER in PJM Transmission Operations and Planning Integrating DER in PJM Transmission Operations and Planning NRRI Webinar: Case Studies in Utility Integrated Distributed Resources Planning and Doing October 11, 2017 Andrew Levitt Senior Market Strategist

More information