1 Sawalkote HEP Kirthai Stage-II Baglihar Stage-II Kirthai Stage-I 390

Size: px
Start display at page:

Download "1 Sawalkote HEP Kirthai Stage-II Baglihar Stage-II Kirthai Stage-I 390"

Transcription

1 POWER SCENARIO IN J&K The J & K State is endowed with huge and vast water resources in the form of permanent glaciers & ice bodies, inland water bodies viz. lakes & river systems. These are being utilized for water resource development projects. To tap water resources for hydropower development, the capacity that can be developed on the major river systems and its tributaries has been estimated as about 20,000 MW. The hydropower scenario has been examined based on latest information of projects implemented, proposed and under construction in the state. Based on these studies it is established that: i. Most of the State s Hydro power Projects are run-off the river type; ii. The present installed generating capacity in the State is only MW (just about 12%) against the Hydropower potential of 20,000 MW in the state; iii. The power shortage is less in summer months and far greater in winter months when river discharges dwindle down to the barest minimum. The position becomes alarming in Kashmir Valley during winter, when the entire mountainous region is snow bound and in the grip of extreme cold with higher energy requirement; iv. The state Government has installed Gas Turbines in the valley to generate 175 MW of Power and thus provide some immediate relief to the people; v. In order to make the state self-sufficient in power sector and to harness the western rivers of Indus Basin without disturbing the Indus Waters Treaty, the J&K Govt. has approved the IPP Policy to develop power potential in the State wherein investors, both national and international, have been asked to come forward and invest. J & K State has accorded top priority to harness the huge hydro power potential and has prioritized following nine projects for immediate execution :- S. No. H.E. Projects at various stages of clearance Capacity in MW 1 Sawalkote HEP Kirthai Stage-II Baglihar Stage-II Kirthai Stage-I 390 Page 1 of 20

2 5 New Ganderbal HEP Lower Kalnai Parnai Dah Hanu 9.0 JKSPDC had vide letter dated had submitted the applications as per the prescribed form to the CDM Executive Board for prior consideration of these projects. Applications were also submitted to the National Designated Authority. CDM team of UNFCCC secretariat has published the included these projects in the list of the projects for Prior Consideration of the CDM at: on 9th of August MW Sawalkote HEP in J & K 1.1 Introduction The Sawalkote Hydro-electric project with an envisaged installed capacity 1856 MW (800 MW for main generating units +56 dam toe for eco flow) is proposed on the left bank of River Chenab in Districts of Ramban and Udhampur of Jammu & Kashmir State in India. 1.2 Project Location The project is located 40Km from District Head Quarter of Ramban. The dam and Power House are located at longitude ʹ E and Latitude ʹ N. The project will utilize the potential between the existing downstream 690 MW Salal HEP and the upstream 900 MW Baglihar HE Project (Stage I of 450 MW of Baglihar HEP has been commissioned in 2009 and the Stage II also of 450 MW is being constructed). The Chenab River crosses the border to Pakistan 80 Kms downstream from the proposed Dam site. 1.3 General information The Sawalkot HEP will be essentially a run-off-river plant. Total catchment area of the project upstream of the dam is Sqkms. It envisages construction of a roller compacted concrete dam with maximum height of 192 m from the deepest river foundation level. It shall have free over-flow gated spillway chute.. Page 2 of 20

3 The reservoir thus created shall have submergence area of Sqkm which includes 2.50 Sqkm of river area. The capacity of the reservoir shall be 530 million M 3 at Full Reservoir Level (FRL), 550 million M 3 at Max. water level and million M 3 at Minimum Draw Down Level (MDDL). The operational volume shall be of the order of million M 3. The maximum regulated water level will be 697 m amsl. During construction of the river works, the river flow shall be diverted through two No. diversion tunnels of 1080M and 690M lengths each having cross sectional area of 234 M 2. The tunnels shall be sufficient to divert a 25 years flood of 8900 M 3 /Sec. The design discharge for generating 1856MW is 1293 Cumecs at a net head of m. The project envisages construction of three to four head race tunnels 200 to 210 m in length and underground power house and transformer hall and tail race tunnels. Indus Waters Treaty 1960 shall strictly govern the development of the Project. Due to the project activities, about 629 houses in the river stretch of 40Km shall be affected. The design energy of the project in a 90% dependable year shall be 8015 GWh. The construction period of the project shall be 7½ years besides one year preconstruction activities. 1.4 Present status Earlier DPR with an installed capacity of 1200MW was submitted to CEA for techno economic clearance. CEA advised to enhance the installed capacity to 1856MW to ensure optimum hydrological utilization. CEA has cleared the updated hydrology, flood studies and power potential of the project. Dam design is under appraisal of CEA. Full version of the revised DPR for installed capacity of 1856MW shall be submitted to CEA by March Technoeconomic Clearance (TEC) of Central Electricity Authority (CEA) is expected to become available by June Project execution is expected to start by Nov with commencement of the preconstruction/infrastructure activities. Identification of the land requirement and the detailed survey of the project affected people is under progress. Page 3 of 20

4 MoEF on has approved the ToR for carrying out the EIA studies. M/s RS Envirolink Technologies Pvt. Limited, accredited by the Quality council of India- National Accreditation Board of Education & Training (QCI-NABET), has been engaged for carrying out the studies. First season report has already been submitted by the Consultant. The studies are under progress and are targeted to be completed in a time bound manner so as to get the clearance from MOEF by the end of MW Kirthai HEP Stage II 2.1 General Kirthai H.E. Project stage II, a run-of-the river project on river Chenab, has been conceived as 121 m high concrete dam with a total potential of 990MW. The main Power house shall be underground and a small dam toe power house shall be constructed for eco-flow. 2.2 Location The Project is proposed to be located at Kidur 16 km downstream of Gulabgarh in Kishtwar District of J&K. At the project Site, the river flows in a very deep gorge having mean elevation of 1650 m. The river is about 85 m wide and both the abutments are steep sloping. Rocks are exposed on both the banks. The coordinates of the Main Dam are:- Longitude : ' - 37" E; Latitude: ' - 41" N The Project site of Kirthai H.E. Project Stage II is approachable through Kishtwar, Galhar Sansari Road. Nearest town Kishtwar is located at about 80 km from project site and connected to Jammu by National Highway 1A & 1B. Nearest Rail head is Udhampur Railway Station and nearest Airport is Jammu. 2.3 General information Catchment area of the river upto the dam site is 9987 Sq.Km having Average Annual Yield of M cum. Minimum Mean Discharge is 53.9 Cumecs. The design flood shall be 7440 cum. The project envisages construction of a 165m high (Height above the deepest foundation level) concrete gravity dam having dam top length of m. Spillway having width of 85m has been designed to discharge flood of 7440 cum. To facilitate construction of the Dam, a 10.5m diameter and m long diversion tunnel shall be provided. Full Reservoir Level shall be m, with a reservoir area of Sq. Km and gross Capacity of MCM. Minimum Draw Down Level shall be m Page 4 of 20

5 with reservoir area1.028 sq.km with capacity of Mcm. Maximum live storage shall be17 Mcm. The project envisages construction of one no. Head Race Tunnel Km in length and diameter m to carry a design discharge of 485 cumecs. 3 No. pressure shaft each of 5.60 m dia. shall be provided. Each pressure shaft shall be bifurcated into 3.75m dia. steel lined penstocks to feed two units. There will be an underground Power House complex having machine hall Cavern 187 X 22m X in size to accommodate 6 vertical shafts Francis type turbine driven generating units. Size of the Transformer Cavern shall be 191m X 18m X 27m. The Tail Race Tunnel shall be of Pressure Flow type having length of m with dia. of m This scheme is governed by the provisions of Indus Waters Treaty. MoEF has approved the ToR for conducting the EIA studies of the project. The Studies are currently underway. A construction period of seven years has been considered for completion of the project. The basic infra-structural development, pre-construction surveys and investigations, preparation of design/specifications and tender documents shall be completed within the first year. The work on other infra-structural facilities like colonies, roads, workshops etc. will also start in the first year. The construction of all civil structures shall be completed in six years. The project shall generate GWH of energy in a 90% dependable year. 2.4 Present Status The DPR of project was prepared by CWC in March It was submitted to Central Electricity Authority (CEA) by JKSPDC in April, 2011 for accord of Techno Economic Clearance (TEC). Hydrology as well as the Power Potential studies (estimated at 990 MW) stand approved by CEA/CWC. Even the observations of the GSI have also been replied. The appraisal process in underway and TEC is expected to become available by Dec Requisite clearances are under process. The project is being implemented by Jammu & Kashmir State Power Corporation, JKSPDC, through EPC mode. Two stage bidding process shall be Page 5 of 20

6 adopted to award the project. RfQ shall be floated in the month of October The project is targeted sto be awarded by July MW Baglihar HEP Stage II 3.1 General The Baglihar Hydro-Electric Project Stage-I and Stage-II, each of 450MW installed capacity were envisaged as run-of-the river schemes, governed by the Indus Waters Treaty to exploit the hydro power potential of River Chenab at village Baglihar, near Ramban. Baglihar Hydro-Electric Project Stage-I works comprise of m high concrete dam on Chenab river, near Baglihar village, Intake works for both Stage-I and Stage-II project located on right bank of river, Head Race Tunnels of about 2081m long for Stage-I and 50m long for Stage-II, 27.5 m dia. Surge Shaft, Three Steel Lined Pressure Shafts, an Underground Power House (3x150 MW), D/S Surge Chamber and 130 m long Tail Race Tunnel with its outlet works. The works of Baglihar Hydro-Electric Project Stage-I have been completed and its Power House is under commercial operation since April While designing the structures of Stage-I works, the requirements of proposed Stage-II works were also kept in view. Accordingly the underground works for Stage-I were so located that Stage-II works can also be accommodated on the hill side on the right bank of river Chenab. The reservoir levels, pond levels, inlet levels etc. were also fixed keeping in view the peaking capacity requirement for both Stage-I and Stage-II Power Stations. 3.2 Location The projects are located in the Ramban Tehsil of Distt. Ramban of Jammu Province of Jammu & Kashmir state. (Longitude: 75 18'10" ' East; Latitude: 33 9'30" ' North). The project is about 140Km from Jammu near the Jammu Srinagar National Highway (NH1A). 3.3 General information BHEP stage-ii Power House cavern is 180m u/s of stage-i Power House Caverns. The Power Intake for Stage-II project has been constructed along with the intake of Stage-I, as it would not have been practical to construct the same at later stage without stopping the Stage-I Power house. The inlet to the intake consists of two rectangular openings 10m x 7.5 m with a 5m thick intermediate pier. Page 6 of 20

7 The project comprises construction of about m (including the length of already constructed part of HRT-II with stage-i works) long Head Race Tunnel of 10.15m finished diameter designed to carry 430 Cumecs of water. A restricted orifice type Surge Shaft of 27.5m diameter has been proposed at the d/s end of HRT with the top of surge shaft at EL m and bottom of Surge Shaft is proposed at EL m. Three nos. individual steel lined Pressure Shafts (inner dia 5.5m) for each machine are taking off from the surge shaft. It is proposed to provide gates for each pressure shaft at junction of Surge Shaft and pressure shafts. Machine Hall Cavern will be of size 121 m (L) x 24 m (W) x 51.8 m (H) and would have 3 Nos. generating units m (L) x 15 m (W) x 24.5 m (H) Transformer Hall Cavern will run parallel to power house machine hall cavern and will be located 30 m away from the downstream wall of Machine Hall. The transformer hall cavern will have two floors. The bottom floor at El m will house the 10 single-phase power transformers (3 3 and one spare), and upper floor at El m will house 400 kv G.I.S. equipment. A Collection Gallery has been provided on the downstream of the power house to help stabilize the pressure level caused by load fluctuations. This gallery also acts as collection chamber for the discharge from draft tube tunnels. The gallery is 95 m long, 14 m wide and m high. The water level of Chenab river at outfall of Stage-II has been taken at EL m corresponding to flood discharge of 8500 cumec. 3 Nos. Vertical Shafts (one for each draft tube) of size 12 m (L) x 14 m (W) rise from overt of Collection Gallery upto El. 736 (i.e. invert of top gallery). The top of vertical shafts have been kept above the max. surge level in D/S surge chamber. A m long Tail Race Tunnel will carry the turbine discharge to the river Chenab. The tail race tunnel will have the same cross-section as the head race tunnel (10.15m dia circular) and will rise from El m at the collection chamber to El m at the outlet structure at a constant slope of 1 in The Outlet Structure of the Tail Race Tunnel has been proposed in the shape of a diffuser with two bays of 5.0 m width x 8.1 m height each. The project shall generate 1302MUs of energy in a 90% dependable year. Page 7 of 20

8 3.4 Present Status Contracts for the project have been awarded in March Civil and hydro mechanical works shall be executed by M/s Jai Prakash Associates Limited and the Electro mechanical works by M/s Voith Hydro- Andritz Hydro Germany/India. All the three units of the project are targeted to be commissioned by August MW Kirthai HEP Stage I 4.1 Introduction The project is a run-of-the river scheme envisaging construction of a 165m high concrete dam above the deepest foundation level to be located on river Chenab with underground power house just downstream of dam axis on left bank and diversion tunnel on right bank. 4.2 Location The dam and power house site is located in village Gulabgarh in Paddar Tehsil of Kishtwar District of Jammu and Kashmir, about 315 km away from Jammu which is approachable through NH-1A National Highway upto Batote and beyond Batote upto Kishtwar there exist an all weather road. The Coordinates of the Main Dam are Longitude: E; Latitude: N 4.3 General information The drainage area of Chenab River up to dam site of Kirthai I H E Project is 8530 Sq km, out of which 4608 Sq km is snow fed and rest 3922 Sq km is rain fed. Total length of dam at top (at El 1900) is m. Standard Ogee Type spillway and shaft spillway will be provided to pass design flood of 7400 cumecs. For diverting the flow during construction period a 10.5 m dia diversion tunnel has been provided on right bank with designed carrying capacity of 1200 cumecs. An underground power house with four units of Francis Turbines has been envisaged with total installed capacity of 380 MW under designed head of m. A surface power house on right bank with one unit of Francis turbine has been envisaged with 10 MW installed capacity for eco-flow of 9.5 cumecs Energy generation in a 90% dependable year shall be MUs. Page 8 of 20

9 Intake tunnel shall be 10.5 m diameter, m long. The tunnel will end in 10.5 m diameter vertical pressure shaft. Pressure shaft will converge in to manifold in to four penstocks near the power house to feed the units. Design Discharge shall be Cumecs. The underground power house complex comprises of machine hall cavern (116.4m x 20m x 45.54m), the transformer cavern (102m x 14m x 23.30m). There shall be one Concrete Lined tail race tunnel of diameter m and m length. In addition, there shall be access tunnels to power house and transformer cavern and construction adit to top of power house, top of transformer cavern and bottom of vertical pressure shaft Gross Capacity of the reservoir at the FRL of 1895 m shall be M Cum with a Reservoir Area of Hactare. Gross Capacity at the Minimum Draw Down Level of m shall be M Cum. Maximum available live storage shall be 13 M- Cum. The project is planned with pondage for peaking operation, as per the provisions of the Indus Waters Treary. Completion time for all construction activities for the project as a whole i.e. commissioning of all the units is 60 months. 4.4 Present status JKSPDC has floated the Request for Qualification on for implementation of the project on Engineering, Procurement and Construction (EPC) basis. The project is targeted to be awarded by June JKSPDC has conducted the EIA studies of the project as per the ToR approved by MoEF. EIA/EMP studies report has been submitted to MOEF for accord of the clearance. 5. New Ganderbal Hydro Electric Project (93 MW) 5.1 General 93MW New Ganderbal Hydro Electric Project (NGHEP) is envisaged as a run-ofthe river multipurpose scheme, between Preng and Ganderbal along left bank of the Nallah Sindh, a tributary of River Jhelum in Jammu & Kashmir India. Besides power generation, the project envisages to provide drinking water facilities to Srinagar city and irrigation to the local command area. Page 9 of 20

10 5.2 Location The Project area is located in the Ganderbal district of Jammu and Kashmir State with headworks at Preng having latitude of N and longitude of E. The headworks can be approached by National Highway 1- D (Srinagar-Leh National Highway NH 1D) and is at a distance of 40 Km from Srinagar. The powerhouse site is also to be approached through NH-1D and is about 20 km from Srinagar. 5.3 General information The Nallah Sindh drains off catchment area of 1352 sq. km at the proposed barrage site. The design flood (1 in 100 year) and SPF have been assessed as 1800 cumecs and 2600 Cumecs respectively. The diversion flood is 225 cumecs. An installation of 93 MW comprising 3 generating units of 31 MW each has been assessed. The Design energy of the project in 90% dependable year is GWh. The project envisages construction of a barrage of m length and 11 m height across the Nallah Sindh at Preng village. The barrage has 7 Nos. spillway bays (including 1 undersluice) with gates mechanically operated. Each spillway bay is 8 m wide totalling a waterway of 56 m. River diversion works are proposed to be undertaken through a diversion channel, located on the left bank of Nallah. The channel shall be capable of carrying a diversion flood of 225 cumecs with upstream and downstream cofferdams. Water Conductor System envisages construction of one no. 5.5 m diameter and m long horse shoe shaped concrete lined head race tunnel to carry a discharge of cumecs (72.38 cumec for power generation and 6 cumecs for drinking water supply). An adit-cum water Supply tunnel (6m dia D shaped) having length of 739 m shall be provided to deliver the drinking water to the treatment plant at Rangil. A twin chamber hopper type desilting basin of size 34 m (W) X 70 m (L) X 7 m (H) each has been proposed on the left abutment of barrage upstream of barrage axis. The power intake is located in the collection chamber of basin. The intake structure is proposed at the end of the collection chamber provided at the termination of the Desilting basin. The gated Power Intake is designed for discharge of m³/s. Page 10 of 20

11 One number underground surge shaft of 20 m diameter and 58 m height in RCC is proposed at the end of HRT. One pressure shaft of 4.3 m diameter from the Surge shaft is envisaged leading to the Valve House after trifurcation to 2.5 m dia shafts, where it will be connected to butterfly valve of 2.5 m diameter. Three numbers of penstocks of 2.5 m diameter each having a length of 265 m are proposed to connect valve house to power house. Surface powerhouse (69.65 m X m X 34 m) is proposed on the left bank of the Nallah Sindh to house 3 Francis units of 31 MW each with MIV control on the upstream. 245 families belonging to four villages will be losing their land due to acquisition of 9.5 ha and 14.5 ha land in Ganderbal and Preng village panchayats respectively. EIA studies of the project, based on the ToR approved by the MoEF have been conducted and the report submitted to the MOEF for accord of clearance. On the basis of the primary and secondary data collected in respect of the project affected families, a draft R & R Plan was formulated in consonance with the principles enunciated in the National Resettlement and Rehabilitation Policy, 2007, notified by Government of India. Besides meeting the mandatory requirement, certain works relating to social welfare and community development are also considered in consultation with local authorities and representatives of affected families, to make the R&R Plan for the proposed project so that a greater degree of acceptability for implementation of the plan is achieved. The total execution period for the entire works of the project including testing and commissioning is planned to be 57 months. The construction is assumed to start from March 2013 and get completed by November Present Status:- Being a multi-purpose project, its DPR has been submitted to CWC for clearance. CWC/CEA have already cleared the hydrology, floods studies and power potential of the project. Appraisal is expected to be completed within three months i.e. by Dec Two stage bidding has been adopted for this project for implementation of the project through EPC mode. 9 bids have been received against RfQ floated. The bids have been evaluated. RfP is being issued shortly among the qualified bidders. Page 11 of 20

12 6. 48MW Lower Kalnai HEP 6.1 General The Lower Kalnai Hydel Project in Jammu and Kashmir State is a run of the river Hydropower project. The project envisages diversion of Upper Kalnai and Kaguneged Nallah, about 200 m downstream of their confluence at Dunadi by constructing a concrete dam of 49 m height (above the deepest foundation) across the Lower Kalnai River, small tributary of river Chenab. 6.2 Location Project area is located in district Doda of Jammu and Kashmir State with headworks at Dunadi having latitude 33º (N) longitude 75º (E). The project site can be approached by National Highway I-A (Jammu to Batote) and National Highway I-B (Batote to Thathri) having a distance of 200 Km. Further the head works can be approached through 7km long link road from Thathri to Dunadi. 6.3 General information 48MW (2 X 24) Lower Kalnai Hydro Electric Project is proposed utilizing the stream flows of the Lower Kalnai River, a tributary of the Chenab River, in Kistwar district of Jammu & Kashmir with a gross head of m and Net Head of m. The project envisages construction of a 49 m high dam (above the deepest foundation level of EL m) on the Lower Kalnai River near Dunadi village with a gross storage capacity of 1.86 Mcum at FRL 1135 m. The annual yield from the catchment area of 958 sq.km works out to be MCM. River diversion works comprising one (1) no. 7 m diameter D- shaped diversion tunnel on the right bank with upstream and downstream cofferdams on the river, which will be finally plugged with a Bulkhead gate of 7mx7m size before reservoir filling. The 49 m high (above deepest foundation level of EL m) Concrete Gravity Dam shall have 4 bays of Surface Spillway with crest at El m. Control shall be with Radial Gates of size 10m X 15m operated by Hydraulic Hoists. Storage at FRL of m shall be 1.86 MCUM. A Power Intake Structure is proposed on the left bank of Lower Kalnai River just upstream of the Dam. The Intake is provided with two bell-mouth openings each having an Intake gate of 2.0m (W) x 3.0m (H) size. Page 12 of 20

13 Water is proposed to be diverted through a Water Conductor System (WCS) of 4.56 km (including 3.96 Km long Head Race Tunnel) with a Surge shaft proposed at the HRT. A Power House is proposed on the left bank of Lower Kalnai River about 200 m upstream of its confluence with Chenab River. The Desilting arrangement comprises two underground chambers 60 m (L) x 12 m (W) x 9.8 m (D) each having four nos. tapering hoppers at the bottom. Two numbers feeder tunnels take off from the Power Intake structure provided with separate intake gate for each of them. These feeder tunnels are of 3m dia D-shaped section and are 425m and 464m long, respectively. Each of the feeder tunnels join the two chambers of Desilting Chamber. Two more small length 3m dia D-Shaped tunnels (55m each) take off from the outlet ends of each desilting chambers to carry clear desilted waters from the Desilting Chamber. A 3.96 Km long Head Race Tunnel (HRT) of 4.0 m finished diameter has been proposed to carry the silt free waters from the Desilting Chamber. This D-shaped tunnel, proposed on the left bank of river has been designed for a discharge of 30 m 3 /s. One number intermediate adit located downstream of the desilting chamber, after the two short tunnels join into a single tunnel of 4 m diameter, has been proposed for construction of headrace tunnel, feeder tunnels and the Desilting Chamber. The Head Race Tunnel would terminate at an underground Surge Shaft of 14 m dia and 39.0 m height. This restricted orifice type shaft shall have a 4m diameter and 5.0 m high vertical riser at its bottom to connect the Surge Shaft to the HRT at its tail end and the Pressure Shaft at it u/s end. One number Pressure Shaft of 3.0m dia and 45 m length is proposed to take off at the bottom of vertical riser of Surge Shaft, to carry flows further to the Powerhouse. This Pressure Shaft bifurcates into two branches of 2m dia of surface penstocks, just u/s of a Valve House proposed to control flow into any or both of the branch penstocks. After the Valve House, the branch Penstocks would run as inclined penstocks for about 220m length after which these shall run as Pressure Shafts for 80.0m upto the Powerhouse. A Surface Powerhouse of size 55 m long x m wide x 32.4 m high has been proposed on the left bank of river Lower Kalnai about 200m upstream of its confluence with River Chenab at Thathri. The Powerhouse will house 2 Francis turbines driven generating units of 24 MW each in the machine hall along with MIV for each of them. A132 KV switch yard of 63m x 40m size has been located adjacent to power house on the left bank of the Lower Kalnai River, where the transformers are also located. Power shall be evacuated through a 3 km long, double circuit 132 kv, Page 13 of 20

14 transmission line from the switchyard to the existing pooling station at Thathri. 132 kv Pooling Station near the power house is connected to the Grid. The design energy of the project shall be Gwh. The IWT clearance has been obtained. State level Environmental Impact Assessment Authority has accorded clearance. Land acquisition is under process. Clearance has also been obtained from State Pollution Control Board, Power Development, wildlife, tourism., fisheries and irrigation departments. Construction methodology and equipment selection has been formulated and planned in such way as to commission the project in a total period of 48 months including infrastructure works. 6.4 Present Status The project is being implemented by Jammu & Kashmir State Power Corporation, JKSPDC, through EPC mode. Single drop two cover tendering procedure has been adopted for award of the contract on EPC basis. Nit has been floated on The project is targeted to be awarded for execution by December MW Parnai HEP 7.1 General Parnai Hydro-electric Project is a run of the river project. The project envisages diversion of designed discharge of cumecs of water of Suran River downstream of the confluence of Parnai and Chang nallah, at Bafliaz through a tunnel across Jaranwali ridge for generating 37.5 MW of hydro power near Bata Durian village and dropping tail waters into Mendhar nallah. Parnai and Mendhar nallah are both tributaries of Suran / Poonch river, which, in itself, is a tributary of river Jhelum. 7.2 Location The entire project area is well connected by a network of pucca roads. Diversion site at Bafliaz is approachable from Jammu-Poonch road via two passes namely, Bimber Gali and Dera Gali Pass. Bafliaz is at a distance of 212 km. from Jammu via Dera Gali and 224 km from Jammu via Bimber Gali pass. Since Dera Gali pass remains covered by snow for a greater part of the year, the main connection for the purpose of project work is via Bimber Gali. Geographical Coordinates are as under:- Longitude: 74⁰21'08" E to 74⁰15'30 E Page 14 of 20

15 Latitude: 33⁰36'34" N to 35⁰35'15 N 7.3 General information Parnai Hydro-electric Project envisages utilization of Suran River waters for power generation to the tune of 37.5 MW. Suran is a tributary of river Jhelum. Diversion of water upto a maximum discharge of cumec is envisaged by constructing a barrage across the river at Bafliaz-just downstream of the confluence of Parnai and Chung nallahs. The proposed water conductor is 8.90 km long tunnel across Aran-wali-Galli with inlet portal at Bafliaz and exit portal at Bata Durian where fore bay site has been proposed. Power house shall be constructed on upstream of the confluence of two drainages flanking the Kallar Mehra ridge on Mandhar side, below Bata Durian village. Tail waters shall be fed into Mandher Nallah where it is shall be used for irrigation purposes. The annual yield from the catchment area of 372 sq.km works out to be MCM. The Pond level at the headworks shall be m, with M.D.D.L. of m Major project components are:- A Barrage 107 m long with 2 numbers of undersluice bays and 7 numbers of spillway bays; One desilting basin with two chambers of 90m x 7m each with average depth of 5m 3.2m dia finished D-shaped Head Race Tunnel about 8.90 km long with Design Discharge of cumecs An approach channel to forebay of 300m length; A forebay tank of40m x 10m x 5.5m A 2.0 m dia steel lined pressure penstock with three 1.15m Dia penstock branches off taking from it for feeding the turbines; 71m X 16.6m X 22m Surface Powerhouse with three vertical shaft Pelton wheel Units of 12.5 MW each with Gross Head of m and Net Head of m A tail race with 5 m x 5 m collection chamber and Trapezoidal shape with base width 4.0 m and height as 2.25 m RCC channel shall be provided. An open to sky, restricted orifice type 4.0 m dia, 69 m high surge shaft has been provided to take care of the surge in case of load fluctuation/throw Off Page 15 of 20

16 A steel lined Pressure Shaft of 2.0 m dia. and 1733 m long which shall be trifurcated into three No. Penstocks each of 1.15 m dia. and 70 m long The annual Design energy of the project is computed as MU. The project is targeted to be construction in 48 months. A provision for two numbers 132 kv outgoing feeders bays has been made for evacuation of power generated from the project. An 8 km long 132 kv double circuit transmission line from the project switchyard up to the nearest 132 kv grid substation of JKPDD at Draba is proposed to be laid for power evacuation which a part of Parnai project. Environment Impact Assessment (EIA studies/emp) have been conducted and adequate provision for Catchment area treatment and other environmental up gradation stand, kept in the DPR. Environmental clearance in respect of the Project has been accorded by State Level Environment Impact Authority Govt. of J&K vide their letter no dated As per the findings of the socio-economic survey of the affected families due to this project, the details are as under: (i) Total number of families being affected 66 (ii) Total number of families losing land (fully affected) 1 (iii) Total number of families losing land only (partly affected) 1 (iv) Number of villages affected Present Status The IWT clearance has been obtained. State level EIAA has accorded clearance. Land acquisition is under process. Clearance has also been obtained from State Pollution Control Board and wildlife deptt. Tenders were invited for implementation of the through EPC mode. Process has been completed. Contract is being shortly awarded to the successful bidder/lowest bidder. 8. Dah Hydro Electric Project (9 MW) 8.1 General 9MW (3X3) Dah Hydro Power Project has been envisaged as a run of-the river scheme to utilize the hydro power potential of perennial discharge available in Dah nala, a tributary of Indus River. Page 16 of 20

17 8.2 Location Dah Small hydro power project is located on the Dah nala near Dah villages in Leh district of J & K. The site is well connected by road to all major towns of Ladakh region. The project site is located by the side of Kargil- Leh road via Batalik at a distance of about 735 Km from Jammu and 170 km from Leh. Diversion site is having longitude of and latitude of General information The annual yield from the catchment area of 161 sq.km works out to be MCM. Dah HEP is essentially a run-of-river scheme with little pondage, utilizing inflows of Dah Nala for power generation with a surface power house on the bank of Indus. The scheme can be operated as a base station with firm power of installed capacity of 9MW for 6 months and for the remaining six months the availability varies from 9MW to 4.68MW. Installed capacity of the project has been proposed as 9 MW comprising 3 units of 3MW each Pelton turbines.the annual energy generation is million units and the Design discharge is 3.54 m 3 The power generated will be stepped up to 133 kv through 3 No kva, 6.6 kv/133 kv step up transformer and shall be delivered to nearby 133 kv grid substation at Khaltsi which is at a distance of 30 km from generating station. Double circuit 133 kv line has been proposed and the cost included in the report. The power shall be generated between EL m and confluence with Indus El m, with a net head of m. The nala bed has an average slope of 1 in 20 at diversion weir site and its minimum average discharge is 1.83 cumecs. The high flood discharge of this nala at the location of the diversion weir is estimated to be 135 cumec. The total length of the water conductor system up to Power House of the project is about 3489 meters. The principle components of the project are as follows: a. A weir of 3.5 m high with 16m water way and 2.0 wide under sluice. b. Cut & Cover Feeder Channel of 65m length 1.6m bed width and 1.85m over all depth. c. Desilting Tank of 45 m length including transition and 6m width. Page 17 of 20

18 d. Cut & Cover Power Channel of 2751 m length and of size 1.4m wide and 1.85m deep. e. Forebay of 22 m length and 8 m wide with pondage depth of 2.5m. f. Surface Penstock of 1.25 m dia and 606 m length. g. Surface Power House of size m (length) x 19 m (Wide) x 18 m (high). h. Tailrace Channel of 113 m length and size of 1.5m (wide) and 1.85 m (deep). The total execution period for the entire works of the project including testing and commissioning shall be 48 months. The locations of all the components is so selected that it requires about 4.5 m wide strip of land for the Power Channel along hill slope in about 2751 m length, 450 Sq m at forebay and about 1500 Sq m area for Power House. It does not cause any environmental and ecological imbalance of the area. No resettlement is involved. 8.4 Present Status The project was tendered out for implementation on EPC basis. All requirements as per the tender documents have been completed. The project is being awarded to the successful/lowest bidder. All the necessary clearances including the Indus Waters Treaty clearance, Pollution Control Board clearance, clearance from irrigation Deptt. are available. Power purchase agreement has also been signed. Land is available and its acquisition is under progress. 9. Hanu Hydro Electric Project (9 MW) 9.1 General 9MW (3X3) Dah Hydro Power Project has been envisaged as a run of-the river scheme to utilize the hydro power potential of perennial discharge available in Hanu nala, a tributary of Indus River. 9.2 Location Hanu HEP is located on the Hanu nala near Hanu villages in Leh district of J & K. The site is well connected by road to all major towns of Ladakh region. The project site is located by the side of Kargil- Leh road via Batalik at a distance of about 705Km from Jammu and 145 km from Leh. Diversion site is having longitude of and latitude of General information Page 18 of 20

19 The annual yield from the catchment area of 372 sq.km works out to be MCM. Hanu Small Hydro Project is essentially a run-of-river scheme with small pondage, utilizing inflows of Hanu Nala for power generation with a surface power house on the bank of Indus. The scheme can be operated as a base station with firm power of installed capacity of 9MW for 6 months and for the remaining six months the availability varies from 9MW to 2.63MW. Installed capacity of the project has been proposed as 9 MW comprising 3 units of 3MW each Pelton turbines with a net head of m.The annual energy generation is million units. The power generated will be stepped up to 133 kv through 3 No kva, 6.6 kv/133 kv step up transformer and shall be delivered to nearby 133 kv grid substation at Khaltsi which is at a distance of 30 km from generating station. Double circuit 133 kv line has been proposed and the cost included in the report. The locations of all the components is so selected that it requires about 4.5 m wide strip of land for the Power Channel along hill slope in about 3574 m length, 450 Sq m at forebay and about 1500 Sq m area for Power House. It does not cause any environmental and ecological imbalance of the area. No resettlement is involved. The total length of the water conductor system up to Power House is about 4300 meters. The principle components of the project are as follows: a) A weir of 3.5 m high with 16m water way and 2.0 wide under sluice. b) Cut & Cover Feeder Channel of 49.5m length 1.8m bed width and 1.9m over all depth. c) Desilting Tank of 56.4 m length including transition and 10m width d) Cut & Cover Power Channel of 3574 m length and of size 1.6m wide and 1.85m deep. e) Forebay of 23 m length and 10 m wide with pandage depth of 2.5m f) Surface Penstock of 1.25 m dia and 608 m length g) Surface Power House of size m (length) x 19 m (Wide) x 18 m (high) h) Tailrace Channel of 140 m length and size of 2m(wide) and 1.85 m (deep) The total execution period for the entire works of the project including testing and commissioning is planned to be 48 months. Page 19 of 20

20 9.4 Present Status The project was tendered out for implementation on EPC basis. All requirements as per the tender documents have been completed. The project is being awarded to the successful/lowest bidder. All the necessary clearances including the Indus Waters Treaty clearance, Pollution Control Board clearance, clearance from irrigation Deptt. are available. Power purchase agreement has also been signed. Land is available and its acquisition is under progress. Page 20 of 20

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

UJH MULTIPURPOSE PROJECT JAMMU & KASHMIR

UJH MULTIPURPOSE PROJECT JAMMU & KASHMIR Annexure-V Annexure-V UJH MULTIPURPOSE PROJECT JAMMU & KASHMIR PRE FEASIBILITY REPORT 1 J&K State Power Development Corporation, Sector-3 Extension, 2 Table of Content EXECUTIVE SUMMARY...5 Chapter 1:

More information

INTRODUCTION & PROJECT DESCRIPTION

INTRODUCTION & PROJECT DESCRIPTION 1 INTRODUCTION & PROJECT DESCRIPTION 1.1 GENERAL Hirong Hydro Electrical Project is proposed to be developed as run-off the river scheme to harness the potential of river Siyom (a tributary of river Siang).

More information

Hydropower and Water Resources

Hydropower and Water Resources Hydropower and Water Resources Hydropower and Water Resources The development, planning, design, and construction of hydropower as well as large-scale irrigation schemes and special hydraulic structures

More information

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling Dr. Ing. Meg B. Bishwakarma General Manager, Hydro Lab Pvt. Ltd., Nepal ABSTRACT: The

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

POWER POTENTIAL STUDIES A CASE STUDY OF KULSI MUTLTIPURPOSE PROJECT

POWER POTENTIAL STUDIES A CASE STUDY OF KULSI MUTLTIPURPOSE PROJECT POWER POTENTIAL STUDIES A CASE STUDY OF KULSI MUTLTIPURPOSE PROJECT G.k.Hazarika B.E (civil) Asstt Executive Engineer Brahmaputra Board Dilip Goswami B.E (civil) Executive Engineer Brahmaputra Board The

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

STAGES IN SETTING UP A MINI/MICRO HYDEL PROJECT. Village Electrification through Sustainable use of Renewable Energy (VE-SuRE) TARA

STAGES IN SETTING UP A MINI/MICRO HYDEL PROJECT. Village Electrification through Sustainable use of Renewable Energy (VE-SuRE) TARA STAGES IN SETTING UP A MINI/MICRO HYDEL PROJECT Village Electrification through Sustainable use of Renewable Energy (VE-SuRE) TARA Contributors Dr. Andre Pittet, Swiss Agency for Development and Cooperation,

More information

Design of Small Hydro Power Project on Main Tirhut Canal, Champaran, Bihar, India

Design of Small Hydro Power Project on Main Tirhut Canal, Champaran, Bihar, India OPEN ACCESS Int. Res. J. of Science & Engineering, 2015; Vol. 3 (3): 125-130 ISSN: 2322-0015 RESEARCH REPORT Design of Small Hydro Power Project on Main Tirhut Canal, Champaran, Bihar, India Kumar Manish

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

A VISIT REPORT ON SARDAR SAROVAR DAM. CIVIL 4 th SEM PREPARED BY: MISS. D.A.DAVE MR. H.A.MAULVI CIVIL ENGINEERING DEPARTMENT

A VISIT REPORT ON SARDAR SAROVAR DAM. CIVIL 4 th SEM PREPARED BY: MISS. D.A.DAVE MR. H.A.MAULVI CIVIL ENGINEERING DEPARTMENT A VISIT REPORT ON SARDAR SAROVAR DAM CIVIL 4 th SEM PREPARED BY: MISS. D.A.DAVE MR. H.A.MAULVI CIVIL ENGINEERING DEPARTMENT A.Y.DADABHAI TECHNICAL INSTITUTE-KOSAMBA 1 The Narmada River Narmada means ever-delightful,

More information

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

COMPARATIVE SALIENT FEATURES

COMPARATIVE SALIENT FEATURES COMPARATIVE SALIENT FEATURES Raigam HEP 126 MW 195 MW LOCATION OF THE PROJECT State Arunachal Pradesh Arunachal Pradesh District Anjaw Anjaw Tehsil Hayuliang (100 km from Tezu) Brahmaputra, Sub-basin Lohit

More information

DAM BREAK ANALYSIS & DISASTER MANAGEMENT PLAN

DAM BREAK ANALYSIS & DISASTER MANAGEMENT PLAN 11 DAM BREAK ANALYSIS & DISASTER MANAGEMENT PLAN 11.1 INTRODUCTION 11.1.1 Dam Break Phenomenon The construction of dams in rivers can provide considerable benefits such as the supply of drinking and irrigation

More information

Voith s StreamDiver solution for decentralized low head hydropower plant operations

Voith s StreamDiver solution for decentralized low head hydropower plant operations Voith s StreamDiver solution for decentralized low head hydropower plant operations Stefan Reich Joerg Lochschmidt, Mandar Pachegaokar Voith Hydro Holding GmbH & Co. KG Voith Hydro Holding GmbH & Co. Voith

More information

CHAPTER-4 WATER RESOURCES

CHAPTER-4 WATER RESOURCES CHAPTER-4 WATER RESOURCES 4.1 GENERAL Dibang Multipurpose project is proposed across river Dibang, a major tributary of river Brahmaputra, near Munli village in Lower Dibang Valley District of Arunachal

More information

PROJECT HISTORY. * Under Fiscal Incentives through promotion policies - 200MW

PROJECT HISTORY. * Under Fiscal Incentives through promotion policies - 200MW PROJECT HISTORY Planning commission has recognized the need for harnessing small hydro for meeting the rural areas energy need in an environmentally benign manner. The Govt. of India have entrusted Ministry

More information

CASE STUDY OF INGULA AND LIMA PUMPED STORAGE SCHEMES

CASE STUDY OF INGULA AND LIMA PUMPED STORAGE SCHEMES CASE STUDY OF INGULA AND LIMA PUMPED STORAGE SCHEMES Frans Louwinger Engineering Department (Hydro), Eskom Enterprises Division, PO Box 1091, Johannesburg, 2000 SOUTH AFRICA, frans.louwinger@eskom.co.za

More information

Water Balance Assessment of the Roseires Reservoir

Water Balance Assessment of the Roseires Reservoir Kamalddin E. Bashar 1 and Mohanad O. Mustafa 2 1 UNESCO-Chair in Water Resources, Khartoum, Sudan 2 Ministry of Irrigation and Water Resources, Sudan Abstract Roseires Reservoir on the Blue Nile River

More information

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Campbell River System Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Generation Resource Management Nov 21, 2012 v6 Campbell River System Water Use Plan Page i Table of Contents

More information

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India

Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India World Bank Water Week February 17, 2009 Pyush Dogra (Environmental Specialists) & Daryl Fields (Senior Water

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

level control gates Waterman Industries of Egypt WATERMAN

level control gates Waterman Industries of Egypt WATERMAN Automatic level control gates WATERMAN DOWNSTREAM LEVEL CONTROL Waterman Types "A" and "B" Automatic gates provide constant downstream water level control regardless of upstream level conditions or downstream

More information

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants Head Office Augustaanlage 62-64 D-68165 Mannheim Germany Reinhold Metzler Project manager Tel: +49-7531 3620 882 email: metzler@enerm.de RAIFFEISEN BANK SH.A. ALBANIA entecag Consulting & Engineering Bahnhofstr.

More information

PAKISTAN BALOCHISTAN SMALL SCALE IRRIGATION PROJECT (SSIP) PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB1661 Project Name

PAKISTAN BALOCHISTAN SMALL SCALE IRRIGATION PROJECT (SSIP) PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB1661 Project Name PAKISTAN BALOCHISTAN SMALL SCALE IRRIGATION PROJECT (SSIP) PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB1661 Project Name Balochistan Small Scale Irrigation Project Region SOUTH ASIA

More information

Three Gorges Project. A Project with Tremendous Benefits and in Favour of Environmental Improvement. By Cao Guangjing May 22, 2004

Three Gorges Project. A Project with Tremendous Benefits and in Favour of Environmental Improvement. By Cao Guangjing May 22, 2004 Three Gorges Project A Project with Tremendous Benefits and in Favour of Environmental Improvement By Cao Guangjing May 22, 2004 Contents 1. Brief Introduction 2. Why Should TGP Be Built? 3. Investment

More information

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View

Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View J. Mayrhuber and P. Stering VERBUND Austrian Hydro Power AG, Am Hof 6a, A-1010 Wien, Austria

More information

Pump storage hydro power plant (PSKW) Reißeck

Pump storage hydro power plant (PSKW) Reißeck Roland Schorn Short description The new pump storage power plant (PSKW) Reißeck II represents an expansion of the already existing group of power plants, Malta and Reißeck/Kreuzeck in Carinthia. The new

More information

North and South Dams Project Overview

North and South Dams Project Overview North and South Dams Project Overview Construction performed by Barnard Pennecon LP Mobilized in late-2015 Anticipated Completion in mid-2019 Major Features of Our Contract Include: Diversion of Churchill

More information

JOBS AROUND THE WORLD

JOBS AROUND THE WORLD PILE DRIVERS AND THE U.S. SUPREME COURT: A STORIED FOUNDATION OF CONSTRUCTION LAW EST. 1984 THE INTERNATIONAL PILE DRIVERS, DEEP FOUNDATIONS & MARINE CONTRACTOR S MAGAZINE PILE BUCK PRESENTS 2013 VOLUME

More information

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP Darial Energy LLC Dariali Hydro Power Plant Construction and Operation Project Environmental and Social Plan, Dariali HPP Tbilisi 2014 Dariali Energy JSC, the Sponsor, is planning construction and operation

More information

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA Overview Romania has built 2,617 dams out of which 246 are large and medium dams and 1260 are small dams, as per

More information

A STUDY OF WATER SUPPLY FOR ISLAMABAD / RAWALPINDI

A STUDY OF WATER SUPPLY FOR ISLAMABAD / RAWALPINDI A STUDY OF WATER SUPPLY FOR ISLAMABAD / RAWALPINDI By Engr. Muhammad Jabbar 1 and Azhar Masood Panni 2 The present major source of water supply to Islamabad / Rawalpindi, some industrial units and irrigation

More information

KEMBAR DAM N u s a T e n g g a r a B a r a t

KEMBAR DAM N u s a T e n g g a r a B a r a t I N V E N T O R Y S T U D Y O N D E V E L O P M E N T P O T E N T I A L F O R R U R A L E L E C T R I F I C A T I O N I N I N D O N E S I A KEMBAR DAM N u s a T e n g g a r a B a r a t Bandung, October

More information

Torpa Small Hydro Power Project

Torpa Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

RATLE HYDRO ELECTRIC PROJECT (850 MW) BIDDING DOCUMENT FOR "APPOINTMENT OF OWNER S ENGINEER

RATLE HYDRO ELECTRIC PROJECT (850 MW) BIDDING DOCUMENT FOR APPOINTMENT OF OWNER S ENGINEER GVK RATLE HYDRO ELECTRIC PROJECT PRIVATE LIMITED RATLE HYDRO ELECTRIC PROJECT (850 MW) BIDDING DOCUMENT FOR "APPOINTMENT OF OWNER S ENGINEER (This document is meant for the exclusive purpose of bidding

More information

Water Balance and Regulation Alternative Analysis for Kajakai Reservoir using HEC-ResSim

Water Balance and Regulation Alternative Analysis for Kajakai Reservoir using HEC-ResSim US Army Corps of Engineers Hydrologic Engineering Center Water Balance and Regulation Alternative Analysis for Kajakai Reservoir using HEC-ResSim Phase I and II Final Report December 2007 Approved for

More information

THE ANTAS RIVER HYDROPOWER COMPLEX - CERAN

THE ANTAS RIVER HYDROPOWER COMPLEX - CERAN THE ANTAS RIVER HYDROPOWER COMPLEX - CERAN 14 DE JULHO HPP MONTE CLARO HPP CASTRO ALVES HPP Authors: Marco Aurélio Fernandes, Vendolino Fischer and Marcelo Wood Chiarello THE ANTAS RIVER HYDROPOWER COMPLEX

More information

Environmental and Social Impact Assessment: 192 MW Hydroelectric Power Project, Tehsil Manali, District Kullu, Himachal Pradesh

Environmental and Social Impact Assessment: 192 MW Hydroelectric Power Project, Tehsil Manali, District Kullu, Himachal Pradesh Environmental and Social Impact Assessment: 192 MW Hydroelectric Power Project, Tehsil Manali, District Kullu, Himachal Pradesh AD Hydro Power Limited Revised and Updated Report February 2009 www.erm.com

More information

KERIO VALLEY DEVELOPMENT AUTHORITY INVITATION TO TENDER

KERIO VALLEY DEVELOPMENT AUTHORITY INVITATION TO TENDER KERIO VALLEY DEVELOPMENT AUTHORITY KVDA REPUBLIC OF KENYA MINISTRY OF ENVIRONMENT, WATER AND NATURAL RESOURCES INVITATION TO TENDER Introduction Kerio Valley Development Authority (KVDA) is a Parastatal

More information

Lower Mattagami River Project

Lower Mattagami River Project Lower Mattagami River Project 2016 Canadian Consulting Engineering Awards Project summary Ontario Power Generation s (OPG) Lower Mattagami River (LMR) project, its largest hydro project in 40 years, added

More information

Impact of Indus Water Treaty on J&K State: with Special Reference to Hydro Power Potential

Impact of Indus Water Treaty on J&K State: with Special Reference to Hydro Power Potential Journal of Recent Advances in Agriculture Impact of Indus Water Treaty on J&K State: with Special Reference to Hydro Power Potential Nazakat R. and Nengroo A. J Rec Adv Agri 2012, 1(4): 157-163 Online

More information

Rehabilitation of Kidatu Power Plant Project Presentation

Rehabilitation of Kidatu Power Plant Project Presentation Rehabilitation of Kidatu Power Plant Project Presentation Norconsult The 200 MW Kidatu power plant is located on the Great Ruaha River in the region of Morogoro in central Tanzania about 280 km west of

More information

Introduction. General Description

Introduction. General Description Introduction General Description The 3-Gorges project is a vitally important and backbone project in the development and harnessing of the Yangtze River (Changjiang River). The dam site is situated at

More information

Module 4. Hydraulic structures for flow diversion and storage. Version 2 CE IIT, Kharagpur

Module 4. Hydraulic structures for flow diversion and storage. Version 2 CE IIT, Kharagpur Module 4 Hydraulic structures for flow diversion and storage Lesson 1 Structures for Flow Diversion Investigation Planning and Layout Instructional objectives On completion of this lesson, the student

More information

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47 John Hart Generating Station Replacement Project May 2017 Community Construction Update Report #47 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT 1.2 and 2.1 General / Civil Works Planning and Layouts Sponsor: Ministry of New and Renewable Energy Govt. of India Lead Organization: Alternate

More information

PROJECT BRIEF for the John Hart Generating Station Replacement Project

PROJECT BRIEF for the John Hart Generating Station Replacement Project PROJECT BRIEF for the John Hart Generating Station Replacement Project Issue Date: March 13, 2012 TABLE OF CONTENTS John Hart Generating Station Replacement Project Page ii of 17 1. INTRODUCTION... 3 1.1

More information

CHAPTER - 1 TYPE OF HYDRO ELECTRIC DEVELOPMENT AND ENVIRONMENTAL IMPACT ASSESSMENT

CHAPTER - 1 TYPE OF HYDRO ELECTRIC DEVELOPMENT AND ENVIRONMENTAL IMPACT ASSESSMENT CHAPTER - 1 TYPE OF HYDRO ELECTRIC DEVELOPMENT AND ENVIRONMENTAL IMPACT ASSESSMENT 1.1 General Selection of Equipment, their Characteristics and Specifications for design of hydro power station depends

More information

3- Hydropower. Energy conversion and hydropower principles

3- Hydropower. Energy conversion and hydropower principles 3- Hydropower The hydraulic power is one of the oldest energy sources of the mankind, namely for irrigation and industry. Nowadays, small hydro is one of the most valuable answers to the question of how

More information

Brief Introduction of SH/MH Components and Civil Engineering aspects of SH/MH

Brief Introduction of SH/MH Components and Civil Engineering aspects of SH/MH Brief Introduction of SH/MH Components and Civil Engineering aspects of SH/MH Janak Das Koirala Treasurer - Nepal Micro Hydro Power Development Association (NMHDA) Executive Director - AG Power Company

More information

1 Small Hydro Power Plants Wetzmann

1 Small Hydro Power Plants Wetzmann 5 th Bulgarian-Austrian Seminar SMALL DAMS AND HPP 30 March 2012, Sofia R.9 REFURBISHMENT OF TWO SMALL HYDRO POWER PLANTS IN AUSTRIA P. Tschernutter Abstract: A weir at the River Gail, which was used for

More information

Installation, Operation and Maintenance Manual

Installation, Operation and Maintenance Manual Installation, Operation and Maintenance Manual for Multipurpose Power Unit (MPPU) at Munar Prepered for TIFAC-DST Sponsored Project Development of Standard Water Mills in Uttaranchal Submitted to TIFAC

More information

Hydropower & Dams Services

Hydropower & Dams Services Hydropower & Dams Services We represent a world-class concentration of hydropower and dam expertise. Since 1920, we have designed hundreds of new hydropower and dams globally, producing clean reliable

More information

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001)

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001) IE0311133-22-RP-0001, Issue A 17/10/2013 Attachment 12 Stage 1 Flood Risk Assessment (IE0311133-30-RP-0001) IE0311133-22-RP-0001_A_02.DOC Flood Risk Assessment Celebrating 40 Years in Business Jazz Pharmaceuticals

More information

MRC SEA FOR HYDROPOWER ON THE MEKONG MAINSTREAM INCEPTION REPORT VOL II MAINSTREAM PROJECT PROFILE SUMMARIES 23 OCTOBER 2009

MRC SEA FOR HYDROPOWER ON THE MEKONG MAINSTREAM INCEPTION REPORT VOL II MAINSTREAM PROJECT PROFILE SUMMARIES 23 OCTOBER 2009 II MRC SEA FOR HYDROPOWER ON THE MEKONG MAINSTREAM INCEPTION REPORT VOL II MAINSTREAM PROJECT PROFILE SUMMARIES 23 OCTOBER 2009 The MRC SEA of Hydropower on the Mekong mainstream comprises 4 main phases:

More information

Gulpur Hydropower Project. Assessment of Cumulative Impacts and Management. February, Vaqar Zakaria

Gulpur Hydropower Project. Assessment of Cumulative Impacts and Management. February, Vaqar Zakaria Gulpur Hydropower Project Assessment of Cumulative Impacts and Management February, 2016 Vaqar Zakaria The Project 2/26/2016 2/26/2016 Diversion Tunnels Powerhouse Intake Cofferdam Weir and Spillway

More information

Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014

Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014 Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014 Western Power Company Western Power Company (WPC) is a Zambian Independent Power Producer which is working for the development

More information

ABOUT US HISTORY PRODUCTS -1-

ABOUT US HISTORY PRODUCTS -1- ABOUT US HISTORY PRODUCTS Waterman Industries of Egypt's product line covers several types of gates and valves in standard sizes for use in potable water, irrigation canals and wastewater treatment plants.

More information

The dam authority of Saxony (LTV) is responsible

The dam authority of Saxony (LTV) is responsible Three innovative dam rehabilitation schemes in Saxony U. Müller, Landestalsperrenverwaltung des Freistaates Sachsen, Germany Three recent rehabilitation schemes in Saxony involved a number of innovative

More information

Bridge River Power Development Water Use Plan. Revised for Acceptance for the Comptroller of Water Rights

Bridge River Power Development Water Use Plan. Revised for Acceptance for the Comptroller of Water Rights Bridge River Power Development Water Use Plan Revised for Acceptance for the Comptroller of Water Rights March 17, 2011 Bridge River WUP March 17, 2011 Page i Bridge River Power Development Water Use Plan

More information

EXPERIMENTAL STUDY OF EFFECT OF END SILL ON STILLING BASIN PERFORMANCE

EXPERIMENTAL STUDY OF EFFECT OF END SILL ON STILLING BASIN PERFORMANCE EXPERIMENTAL STUDY OF EFFECT OF END SILL ON STILLING BASIN PERFORMANCE H.L.Tiwari Department of Civil Engineering, Maulana Azad National Institute of Technology, Bhopal, Madhya Pradesh INDIA Arun Goel

More information

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL SLI Doc. No. 505573-3000-40EC-0003 01 5-Dec-2013 ii TABLE OF CONTENTS Page No. 1 INTRODUCTION... 1 2 CREST ELEVATIONS... 2 2.1 Cofferdams... 2 2.2 North Spur... 3 3 STABILITY ANALYSIS LOADING CASES AND

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

Uri Hydroelectric Project The State of Jammu & Kashmir, India

Uri Hydroelectric Project The State of Jammu & Kashmir, India IEA Hydropower Implementing Agreement Annex VIII Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 07-03: Resettlement Uri Hydroelectric Project, india Key Issues: 7-Resettlement

More information

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC JANUARY 2013 PARR Relicensing Project PARR AND FAIRFIELD LOCATIONS FFPS PARR

More information

Regional Rusumo Falls Hydroelectric Project. Terms of Reference for the Project Manager

Regional Rusumo Falls Hydroelectric Project. Terms of Reference for the Project Manager 1 Nile Equatorial Lakes Subsidiary Action Program Coordination Unit Regional Rusumo Falls Hydroelectric Project Terms of Reference for the Project Manager May 2017 Page 1 of 8 2 1 Background and Description

More information

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station City of St. Joseph, Missouri Hydraulic Analysis and Effluent Pump Station By Work Order No. 09-001 B&V Project 163509 May 20, 2010 Table of Contents 1.0 Executive Summary...1 2.0 Purpose of Study...2 3.0

More information

Bishunpur Small Hydro Power Project

Bishunpur Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

Flow Measuring Structures

Flow Measuring Structures Flow Measuring Structures Flow measurement structures are required in irrigation canals in order to facilitate the distribution of water through out the system and to keep account for seepage losses, etc.

More information

KALABAGH - A SUPERIOR DAM DESIGNERS VIEW POINT

KALABAGH - A SUPERIOR DAM DESIGNERS VIEW POINT Paper No. 688 KALABAGH - A SUPERIOR DESIGNERS VIEW POINT Engr. Barkat Ali Luna, Engr. Muhammad Jabbar 288 Luna, Jabbar Pakistan Engineering Congress, 71st Annual Session Proceedings 289 KALABAGH - A SUPERIOR

More information

Chenab Valley Power Projects (P) Ltd

Chenab Valley Power Projects (P) Ltd (A Joint Venture of NHPC (A Govt of India Enterprise, JKSPDC (A Govt of J&K Undertaking) & PTC India Ltd) Pakal Dul Hydro Electric Project Ph No. 01995-260661 Chenab Nagar - II, Kishtwar, (J&K) -182206

More information

Implementing Party & Period - Project: Oslo Lysverker (Preparation and Application), (Construction), (in Operation)

Implementing Party & Period - Project: Oslo Lysverker (Preparation and Application), (Construction), (in Operation) IEA Hydropower Implementing Agreement Annex VIII Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 10-04: Landscape and Cultural Heritage Aurland Hydropower Development,

More information

Dam Safety Instrumentation with Case Study

Dam Safety Instrumentation with Case Study Dam Safety Instrumentation with Case Study Dr. Rajbal Singh Joint Director Rock Mechanics Discipline Central Soil and Materials Research Station (CSMRS), New Delhi Dam Instrumentation Safety of Dam Construction

More information

INVITATION FOR EXPRESSION OF INTEREST

INVITATION FOR EXPRESSION OF INTEREST INVITATION FOR EXPRESSION OF INTEREST Consulting Services for Hydropower Deadline: 15.05.2014 at 12.00 hours (noon) India Time Country: India Ref.-No: KfW Project Number: 31510 Prequalification Ref.: International,

More information

Some aspects of the sediment transit on the Mekong river in relation with hydropower development

Some aspects of the sediment transit on the Mekong river in relation with hydropower development Some aspects of the sediment transit on the Mekong river in relation with hydropower development Daniel Loudière Société Hydrotechnique de France A presentation in three parts - the situation when starting

More information

Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping

Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping County, Hebei, P. R. China. Tel : 0086-318-7752001 7531068

More information

SITE VISITS REPORT: EXISTING

SITE VISITS REPORT: EXISTING Small Hydro Resource Mapping in Tanzania SITE VISITS REPORT: EXISTING April 2015 This report was prepared by SHER Ingénieurs-Conseils s.a. in association with Mhylab, under contract to The World Bank.

More information

Long Lake Small Hydro Project

Long Lake Small Hydro Project Long Lake Small Hydro Project Minerals North 2005 29 April 2005 Presented by David Carter Regional Power Inc. Stuart Croft - Summit Power Group Project Location 25 km north of Stewart, in northwest B.C.

More information

SMALL HYDRO PROGRAMME IN INDIA

SMALL HYDRO PROGRAMME IN INDIA SMALL HYDRO PROGRAMME IN INDIA Bhuwanesh Kumar Bhatt Ministry of New and Renewable Energy Hydropower represents use of water resources towards inflation free energy due to absence of fuel cost with mature

More information

TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS

TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS Introduction E. Dean 1, M. ASCE Bethel Herrold 2 George Robbins 3, M. ASCE James C. Carter 4 The Southwestern

More information

Application for resource consent Form B Damming and diversion of water

Application for resource consent Form B Damming and diversion of water Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or

More information

Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France

Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France Christophe PETEUIL Compagnie Nationale du Rhone Engineering Department, River Systems and

More information

Hydro Electric Power (Hydel Power)

Hydro Electric Power (Hydel Power) Operating Principle Hydro Electric Power (Hydel Power) Hydro-electric power is generated by the flow of water through turbine, turning the blades of the turbine. A generator shaft connected to this turbine

More information

Sediment Basin. Fe= (Depends on soil type)

Sediment Basin. Fe= (Depends on soil type) 3.9 Sediment Control Description: A sediment basin is an embankment with a controlled outlet that detains stormwater runoff, resulting in the settling of suspended sediment. The basin provides treatment

More information

Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel

Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel 5 Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel M. P. Cherian, Ari Pandian, Karen Ridgway and Gregory Barden The City of Columbus, Ohio, submitted a wet weather management plan

More information

consulting engineers hydraulic steel structures

consulting engineers hydraulic steel structures consulting engineers hydraulic steel structures Floating Sector Gate at Yeonsang Front cover Five of the seven rising sector gates at the Gangchon bridge and weir at Yeoju on the Han River in central Korea.

More information

Guidelines for Construction of Pipe Distribution Network (PDN) for Irrigation

Guidelines for Construction of Pipe Distribution Network (PDN) for Irrigation Guidelines for Construction of Pipe Distribution Network (PDN) for Irrigation Mr. Sandesh B. Kulavmode 1, Dr.S.S.Valunjkar 2 1P.G. Student, Dept. of Civil Engineering, Government College of Engineering,

More information

Screening, Definition: The unit involved is called a screen.

Screening, Definition: The unit involved is called a screen. Screening, Definition: Screening is a unit operation that separates materials in and/or on water (found in different sizes) from water and from entering water treatment facilities and mains. The unit involved

More information

Water. Power. HYDROMATRIX

Water. Power. HYDROMATRIX Water. Power. HYDROMATRIX HYDROMATRIX An innovative way to hydropower generation Conventional HYDROMATRIX Ø 6+ m Ø 1.3+ m An array ( Matrix ) of small turbines instead of conventional sized turbines Best

More information

Alouette Project Water Use Plan (April 15, 2009) Revised for Acceptance for the Comptroller of Water Rights

Alouette Project Water Use Plan (April 15, 2009) Revised for Acceptance for the Comptroller of Water Rights Alouette Project Water Use Plan (April 15, 29) Revised for Acceptance for the Comptroller of Water Rights Alouette Project - Water Use Plan Alouette Project Water Use Plan (April 15, 29) Revised for Acceptance

More information

Thethaitangar Small Hydro Power Project

Thethaitangar Small Hydro Power Project 1.0 INTRODUCTION 1.1 General The state of Jharkhand almost comprises hilly terrain mostly of Chhotanagpur plateau and 30% of total area (79,714 sq km) is covered with forest. The normal annual rainfall

More information

Discharge Measurement in Small Hydropower Stations using Acoustic Doppler Current Profiler

Discharge Measurement in Small Hydropower Stations using Acoustic Doppler Current Profiler Discharge Measurement in Small Hydropower Stations using Acoustic Doppler Current Profiler B.K. Gandhi 1, H.K. Verma 2 and S.S. Patnaik 3 1) Department of Mechanical & Industrial Engineering, Indian Institute

More information

Dr. S. K. Sharma Ground Water Expert

Dr. S. K. Sharma Ground Water Expert Dr. S. K. Sharma Ground Water Expert CONCEPT OF ARTIFICIAL RECHARGE Recharging practices began in 19 th century in Europe. Traditional water harvesting in India dates back to Indus Valley Civilization

More information

PUMPED STORAGE PLANTS

PUMPED STORAGE PLANTS PUMPED STORAGE PLANTS Shaping our world A company of PUMPED STORAGE PLANTS Why Pumped Storage? Benefits and Advantages With the Paris agreement in effect, the global aim is to reduce the emission of greenhouse

More information

APPENDIX E: West Creek Hydro Technical Review

APPENDIX E: West Creek Hydro Technical Review APPENDIX E: West Creek Hydro Technical Review # 3 Calcite Business Centre, 151 Industrial Road Whitehorse, Yukon Y1A 2V3 Phone (867) 668 6463 Fax (867) 633 4882 www.accessconsulting.ca Memorandum To: From:

More information

USE OF PERCOLATION WATER IN TRACTEBEL ENERGIA HYDROELECTRIC PLANTS REPLACING WATER TREATMENT STATIONS

USE OF PERCOLATION WATER IN TRACTEBEL ENERGIA HYDROELECTRIC PLANTS REPLACING WATER TREATMENT STATIONS USE OF PERCOLATION WATER IN TRACTEBEL ENERGIA HYDROELECTRIC PLANTS REPLACING WATER TREATMENT STATIONS Tractebel Energia S.A. GDF SUEZ 1 Contents Introduction 3 Objectives 5 Development 6 Methodology 8

More information

STUDY OF FLOOD AT SURAT CITY AND ITS REMSDIAL MEASURES

STUDY OF FLOOD AT SURAT CITY AND ITS REMSDIAL MEASURES STUDY OF FLOOD AT SURAT CITY AND ITS REMSDIAL MEASURES PRASIT G. AGNIHOTRI, LECTURER AND PH. D. SCHOLAR DR. JAYANTILAL N. PATEL, PROFESSOR Civil Engineering Department S.V. National Institute of Technology

More information