WATER QUALITY PROTECTION AND MONITORING PLAN PORT OF VANCOUVER, USA TERMINAL 5 BULK POTASH HANDLING FACILITY

Size: px
Start display at page:

Download "WATER QUALITY PROTECTION AND MONITORING PLAN PORT OF VANCOUVER, USA TERMINAL 5 BULK POTASH HANDLING FACILITY"

Transcription

1 WATER QUALITY PROTECTION AND MONITORING PLAN PORT OF VANCOUVER, USA TERMINAL 5 BULK POTASH HANDLING FACILITY Prepared for Port of Vancouver, USA BHP Billiton Canada, Inc. Prepared by Anchor QEA, LLC 6650 SW Redwood Lane, Suite 333 Portland, OR October 2011

2 WATER QUALITY PROTECTION AND MONITORING PLAN PORT OF VANCOUVER USA TERMINAL 5 BULK POTASH HANDLING FACILITY Prepared for Port of Vancouver, USA BHP Billiton Canada Inc. Prepared by Anchor QEA, LLC 6650 SW Redwood Lane, Suite 333 Portland, OR October 2011

3 TABLE OF CONTENTS 1 INTRODUCTION Project Description Water Quality Criteria WATER QUALITY PROTECTION MEASURES General Water Quality Protection Measures Stormwater Outfall Replacement Pile Installation in Riprap Armor Pile Removal General Over-water Construction Work General Concrete Work Nearshore Stone Column Installation WATER QUALITY MONITORING PLAN Visual Monitoring Monitoring Parameters Monitoring Schedule Monitoring Locations Instrumented Monitoring Monitoring Parameters Monitoring Schedule Monitoring Locations Monitoring Depths Record Keeping CONTINGENCY RESPONSE AND NOTIFICATION PLAN Contingency Measures Visible Turbidity Plume Instrument Field Monitoring Construction Debris in Water Distressed or Dying Fish Discharge of Oil, Fuel, or Chemicals Notification...18 Water Quality Protection and Monitoring Plan i

4 5 REFERENCES List of Tables Table 1 Water Quality Standards for Class A Water... 3 List of Figures Figure 1 Vicinity Map Figure 2 Monitored Construction Activities Water Quality Protection and Monitoring Plan ii

5 LIST OF ACRONYMS AND ABBREVIATIONS BHP Billiton BMP CRD Ecology MTPA NOAA NPDES NGVD NTU OHWM Port Q2 RM WAC WQPMP BHP Billiton Canada Inc or an affiliate of the BHP Billiton Group best management practice Columbia River Datum Washington State Department of Ecology million tonnes per annum National Oceanic and Atmospheric Administration National Pollutant Discharge Elimination System National Geodetic Vertical Datum Nephelometric Turbidity Unit Ordinary High Water Mark Port of Vancouver second quarter river mile Washington Administrative Code Water Quality Protection and Monitoring Plan Water Quality Protection and Monitoring Plan iii

6 1 INTRODUCTION This document presents the Water Quality Protection and Monitoring Plan (WQPMP) for construction activities associated with the Terminal 5 Bulk Potash Handling Facility at the Port of Vancouver, USA (Port). The site is located at 5701 Northwest Lower River Road in Vancouver, Washington, on the north bank of the Columbia River at approximately River Mile (RM) 103. The objective of the WQPMP is to monitor and control releases of turbidity, suspended sediment, concrete, and other construction-related materials that may be generated during the removal or filling of material in, over, or near the water, and to ensure compliance with Section 401 of the Clean Water Act, for which Ecology is the delegated regulatory authority, and the Washington State Surface Water Quality Standards ( A Washington Administrative Code [WAC]). In addition, earthwork performed on the shoreline of the site will be conducted in accordance with the terms and conditions of the Environmental Restrictive Covenant entered March 26, 2009, or any successor covenant that restricts this work. This document describes water quality protection measures; monitoring parameters, methods, and evaluation criteria; and contingency response and notification procedures in the event a water quality criterion is exceeded during construction activities. 1.1 Project Description BHP Billiton Canada, Inc., or an affiliate of the BHP Billiton Group (BHP Billiton), is proposing to lease part of Terminal 5 located at the Port for the purpose of establishing a bulk handling export facility to allow shipping of approximately 8 million tonnes per annum (MTPA) of potash to global markets (Figure 1). The facility will accept potash shipped by rail from potash mines located in Saskatchewan, Canada. On-site infrastructure is proposed to enable the unloading of rail cars into on-site storage, and the conveyance of potash to vessels at a new berth to be constructed on the Columbia River adjacent to the facility. The berth will contain a dual-quadrant shiploader system to receive and service various classes of cargo vessels, including Panamax Class vessels. The berth is anticipated to consist of shiploaders, support beams and pivot supports, berthing dolphins, mooring dolphins, a central maintenance trestle, and a berth structure (Figure 2). Other on-site infrastructure components will include a dedicated rail track for BHP Billiton, materials handling equipment, storage structures, utilities, on-site access roads, and related ancillary infrastructure. Water Quality Protection and Monitoring Plan

7 Introduction This WQPMP concerns work conducted below the ordinary high water mark (OHWM) under the jurisdiction of Section 401 of the Clean Water Act. The OHWM is defined as feet Columbia River Datum (CRD) (+16.7 feet National Geodetic Vertical Datum [NGVD] 29) in this reach of the Columbia River. Work performed above the OHWM will be regulated by the project s National Pollutant Discharge Elimination System (NPDES) construction stormwater permit, which will be secured under a separate permitting action. The following construction activities may involve removal or filling of material below the OHWM, and are the focus of this WQPMP: Construction of a replacement stormwater outfall on the bank of the terminal Installation of piles to support the new shiploader structure Removal of piles for habitat mitigation at the project site as well as at Terminal 2 General over-water work associated with construction of the shiploader structure General over-water or in-water concrete work, potentially including concrete filling of steel piles and casting of concrete pile caps and decking Installation of stone columns in nearshore areas for ground stabilization While not all of these activities include removal or filling of material below OHWM, as regulated under Section 401 of the Clean Water Act, they are included for completeness and to ensure State water quality standards are met during all construction work over or near the water as well as in the water. The location of these construction activities is shown on Figure 2. The activities are described further in Section Water Quality Criteria The Columbia River at the Port of Vancouver is designated as a Class A water body by the State of Washington ( A WAC). Characteristic uses include commerce and navigation, recreation, and support of aquatic life (including salmonids) and wildlife habitat. In consideration of the site construction activities (general earthwork and concrete work), turbidity and ph are the primary water quality parameters of concern. Table 1 presents the water quality standards for Class A water for turbidity and ph. Water Quality Protection and Monitoring Plan

8 Introduction Table 1 Water Quality Standards for Class A Water Monitoring Parameter Turbidity If less than 50 NTU: If greater than 50 NTU: Water Quality Criterion Background Turbidity plus 5 NTU Background Turbidity plus 10 percent ph ph shall be within the range of 6.5 to 8.5 with a human caused variation within the above range of less than 0.5 unit. Note: NTU = Nephelometric Turbidity Unit The water quality standards in Table 1 will need to be met at the compliance boundary at the edge of an authorized mixing zone. The mixing zone boundary is assumed to extend 300 feet (91.4 meters) downstream from the point of construction, as specified in WAC A- 100(7)(i), or as otherwise authorized in the Water Quality Certification for this project. The critical monitoring location will typically be directly downstream (i.e., west-northwest) from the point of construction, although tidal reversals are possible during flood tide conditions, which could shift the critical location upstream. In addition to the numerical criteria in Table 1, the project must also comply with narrative water quality standards, including the following: No visible petroleum sheen on water observed at the construction site No distressed or dying fish observed at the construction site and attributed to site activities Unlike the numerical criteria in Table 1, these narrative criteria are not subject to a mixing zone and therefore must be met immediately adjacent to the construction activity with no allowance for dilution. Water Quality Protection and Monitoring Plan

9 2 WATER QUALITY PROTECTION MEASURES This section describes the construction activities covered by this WQPMP and the protection measures or best management practices (BMPs) that will be implemented to minimize impacts to water quality. In addition to implementing the protection measures described in this WQPMP, water quality monitoring will also be performed during construction to ensure that the protection measures are effective, as described in Section 3. General and activityspecific water quality protection measures are described below. 2.1 General Water Quality Protection Measures Water quality protection measures that will be generally implemented on a project-wide basis during all work in or near the water include the following: All in-water work performed in the wet will be completed within the designated in-water work window to protect sensitive fisheries and aquatic resources. The inwater work window is between November 1 and February 28 or as otherwise authorized in project permits. Other work elements may be performed in the dry and will be completely removed or isolated from direct contact with the river; such activities are therefore proposed to be conducted outside the designated in-water work window. All equipment will be maintained in good proper running order to prevent leaking or spilling of potentially hazardous or toxic substances, including but not limited to hydraulic fluid, diesel, gasoline and other petroleum products. Equipment used in or over the water will use biodegradable hydraulic fluids to the extent practicable. Storage of fuels and petroleum products will comply with safe operating procedures, including containment facilities in case of a spill. Pile cut-offs, waste or any miscellaneous unused materials will be recovered for either disposal in a designated facility or placed in storage. No material will enter the Columbia River. Contractors will have emergency spill equipment available whenever working in or near the water. Contractors will position their water borne equipment in a manner that will minimize damage to existing habitat. Water Quality Protection and Monitoring Plan

10 Water Quality Protection Measures 2.2 Stormwater Outfall Replacement Description. The Port s stormwater outfall servicing Terminal 5 will be upgraded and relocated approximately 150 feet downstream from its current location (Figure 2). The new 36- to 60-inch diameter (91- to 152-cm diameter) stormwater pipe will be trenched into the subsurface through the shoreline berm and will daylight at approximately +10 feet NGVD29. The lower portion of the outfall, including the portion exposed above the river bed, will be supported on pile and beam structures similar to the existing outfall. Beneath the outfall, a splash pad consisting of a 2-foot-thick (0.61-meter) layer of riprap will be placed between approximately -5 feet and +5 feet NGVD29 to provide energy dissipation. The splash pad will be approximately 40 feet (12.2 meters) in diameter. The existing outfall will be abandoned by cutting the supporting timber piles below the mudline, cutting and capping the outfall pipe just above the mudline, and filling the pipe with grout. The Port is also evaluating an option to replace and/or rehabilitate the stormwater outfall at its current location which would further minimize construction impacts to the shoreline area. Invasive earthwork will be necessary to lay the new pipe in a trench through the shoreline berm and to remove sediment beneath the riprap apron in order to balance cut and fill and restore existing contours. The shoreline earthwork above the OHWM will be conducted in accordance with the terms and conditions of the Environmental Restrictive Covenant entered March 26, 2009, or any successor covenant that restricts this work. The earthwork necessary to build the subsurface pipe trench through the berm is planned to be completed in the dry during the seasonal low water level (September and October 2012) and before the in-water work window. Pile installation, excavation and placement of the splash pad, securing of the pipe to the support piles, and abandonment of the existing outfall will occur during the in-water work window (November 1, 2012 through February 28, 2013). A sheet pile coffer dam or equivalent may be installed to allow excavation of the splash pad in the dry; alternatively, the excavation of the splash pad may proceed carefully in the wet in conjunction with more rigorous water quality monitoring requirements (see Section 3). If a coffer dam is installed, the area behind the dam would be dewatered, and the dewatering water would be clarified in an upland settling basin or through an in-line filter before being returned to the river. Water Quality Protection and Monitoring Plan

11 Water Quality Protection Measures Water Quality Protection Measures. The following BMPs will be implemented to protect water quality during construction of the upgraded stormwater outfall: Trenching of the outfall pipe through the shoreline berm will be conducted entirely in the dry during seasonal low water. In addition, the following temporary erosion and sediment control measures will be implemented during trenching activities: Vertical shoring will be used in the trench to minimize the footprint of the trench, as well as the temporary stockpile volumes. Perimeter controls (i.e., straw wattles and/or silt fencing), stockpile covers, and gravel construction entrances will be employed. Because the outfall will daylight in an area of heavy riprap armor, it is not expected that slope stabilization measures will be necessary on the river bank. A coffer dam may be used to allow excavation of the splash pad foundation in the dry. Dewatering water behind the coffer dam would be clarified in an upland settling basin or through an in-line filter before discharging back to the river. Alternatively, excavation of the splash pad foundation may be performed in the wet. If this option is selected, instrumented turbidity monitoring would be required during excavation as described in Section 3. In addition, operational BMPs would be employed to minimize turbidity at the excavation site, including the following: Bottom or beach stockpiling of sediment will be prohibited. Overfilling of the excavator bucket shall be avoided. If necessary, the excavator bucket will be paused at the bottom before hoisting it through the water column. If necessary, the ascent velocity will be reduced as the loaded bucket is raised through the water column. In general, careful operational controls, such as those listed above, are expected to provide more effective turbidity control than a silt curtain, especially in a tidally influenced river environment. 2.3 Pile Installation in Riprap Armor Description. Approximately 100 concrete-filled steel piles will be installed below OHWM to support the new shiploader structure and the associated mooring and berthing dolphins. A Water Quality Protection and Monitoring Plan

12 Water Quality Protection Measures large majority of these piles will be placed in unobstructed deep water locations using standard vibratory methods to the extent possible, augmented by impact methods where necessary. However, a small number of piles (approximately 5) will be installed in shallower bank areas armored with riprap; in particular, to support the East Pivot structure (Figure 2). To allow pile installation, the existing riprap will be pulled aside, either manually or with the assistance of a small backhoe. It will then be replaced to original contours after the piles are installed. Pile installation at the East Pivot structure will occur between September 2012 and June 2013; the work will be conducted in the dry and therefore will not be constrained by the in-water work window. Water Quality Protection Measures. The following BMPs will be implemented during temporary riprap removal and replacement to facilitate pile installation on the upper bank: Work will be isolated from the river and conducted entirely in the dry. Because the piles will be installed in an area of heavy riprap armor, it is not expected that slope stabilization measures will be necessary on the river bank. 2.4 Pile Removal Description. Pile removal will be conducted at the project site as well as the Port s Terminal 2 as a part of the habitat mitigation requirements for the project. Piles will be removed using vibratory extraction or by pulling them with a crane mounted on a barge. If a pile is unable to be completely removed using vibratory or pulling methods, the pile will be cut off at or below the mudline using a pneumatic underwater chainsaw or pushed into the sediment. Water Quality Protection Measures. The following BMPs will be implemented during pile removal: When creosote-treated piles are being removed, a containment boom will surround the work area to contain and collect any floating debris and sheen. Any debris will be retrieved and properly disposed. The piles will be dislodged with a vibratory hammer, when possible, and will not be intentionally broken by twisting or bending. If a pile breaks above the mudline, it will be cut off at or below the mudline or pushed into the sediment. The piles will be removed in a single, slow, and continuous motion so as to minimize Water Quality Protection and Monitoring Plan

13 Water Quality Protection Measures sediment disturbance and turbidity in the water column. Removed piles, stubs, and associated sediment (if any) will be contained on a barge. The barge scuppers and any unprotected perimeter areas will be controlled using hay bales covered with filter fabric. All creosote-treated material, pile stubs, and associated sediments (if any) will be disposed of in a landfill approved to accept these types of materials. 2.5 General Over water Construction Work Description. Construction of the shiploader structure will likely require over-water welding, cutting, and other general over-water construction work. The over-water work associated with construction of the shiploader pivots, beams, trestles, walkways, and berthing structures is projected to occur between the second quarter (Q2) of 2013 and Q Because this work will occur out of the river, it will not be constrained by the in-water work window. Water Quality Protection Measures. The following BMPs will be implemented to minimize effects to water quality during over-water construction work: The contractor s Spill Prevention, Control, and Countermeasures Plan for marine operations will be implemented. All construction equipment will be clean and inspected daily before use to ensure that the equipment has no fluid leaks. Should a leak develop during use, the leaking equipment shall be removed from the project site immediately and will not be used again until it has been adequately repaired. At no time will fuels or oils be allowed to enter the river. Debris booms will be placed around the work areas to contain any materials or litter that may inadvertently drop into the water. Any materials dropped into the water would immediately be picked up by the contractor. 2.6 General Concrete Work Description. The existing outfall will be abandoned by cutting it back to the bank, capping the end, and filling the remaining section with grout. This is projected to occur in January through February Water Quality Protection and Monitoring Plan

14 Water Quality Protection Measures Approximately 100 piles will be installed to support the shiploader structure (pivots, beams, trestles, walkways) and associated mooring and berthing dolphins. Depending on the results of ongoing structural design work, some or all of these piles may be filled with concrete. Pile installation below the water line will occur during the in-water work window between November 2012 and February After the piles are installed, the over-water elements of the shiploader structure will be built. Concrete components of the shiploader include pile caps and trestle decking; these may be installed as pre-cast components, or cast in place. This work will generally occur between Q and Q Water Quality Protection Measures. During concrete and grout work in, over, or near the water, the following BMPs will be implemented: Wet concrete will be isolated from contact with surface water. Water-tight forms will be used to prevent leakage. Curing concrete will not be watered. Forms will be kept in place until curing is completed. Grouting of the abandoned outfall will be performed entirely in the dry ; a spill control basin may be placed below the abandoned outfall during grouting for secondary containment of any leakage. Once piles are driven to refusal and cutoff at their design elevation, the water inside will be pumped out. This water should be clean of oil and debris; however, the water will be pumped to a tank and visually inspected prior to release back to the river. Concrete will be injected into the piles from the bottom up; however, some water or infiltrate is expected in the piles and will rise with, and on top of the concrete. This contaminated water will be collected using a universal close-fitting tubular collar fabricated specifically for this project. A 6- to 10-foot apron will be welded around the exterior circumference of the pile for limited secondary containment prior to concrete injection. As the water rises to the top, it will drain through a port in the sidewall (located approximately one foot from the top of the collar), then into a tank on a barge for offsite disposal. The entire operation will be carefully and continuously monitored in order to prevent overfill and release of any contaminated water to the Columbia River. Water Quality Protection and Monitoring Plan

15 Water Quality Protection Measures 2.7 Nearshore Stone Column Installation Description. To improve the seismic stability of the terminal area, ground improvement work will be performed by installing stone columns in potential liquefaction areas. In particular, a field of approximately 1,900 stone columns are proposed in the nearshore area behind the shiploader structure, as shown on Figure 2. Stone columns are a ground improvement technique that combines soil densification and partial replacement of unstable material with crushed rock. The operation involves injecting and compacting aggregate at the base of a vibrating steel probe with the aid of compressed air. Stone column installation is planned to occur between Q through Q Based on WSDOT s recent experience with stone column installation projects, the subsurface ground vibration and injection of high-pressure air may percolate into open-water areas up to 75 feet (22.9 meters) away from the activity (Ecology 2010), potentially causing resuspension of sediment and organic matter and increased turbidity. The nearshore field of stone columns behind the shiploader structure ranges from 30 to 190 feet (9.1 to 57.9 meters) inland from OHWM, and is about 30 to 40 feet (9.1 to 12.2 meters) farther from the river during seasonal low water conditions. The stone columns in the southeast (upstream) quadrant of this ground improvement area are closest to the water and therefore most susceptible to turbidity generation. It should be noted that stone columns are also proposed to help stabilize the ground behind the Railcar Dumper Building and beneath the Storage Building, but these ground improvement areas are several hundred feet from the river and well beyond the range of potential impacts. Water Quality Protection Measures. Proposed water quality protection measures are consistent with the recommendations in Ecology s Guidance on Controlling Turbidity in Nearby Waters from Ground Improvement Work for Seismic Events (Ecology 2010). During nearshore stone column installation, the following BMPs will be implemented: Air injection methods will be used rather than water injection methods to minimize the potential for turbidity impacts. Visual monitoring of adjacent shoreline areas will be conducted during stone column installation within 75 feet of the river. If a turbidity plume is observed in the river as a result of ground improvement work on the adjacent uplands, instrumented Water Quality Protection and Monitoring Plan

16 Water Quality Protection Measures monitoring will be initiated to better quantify turbidity impacts at the compliance boundary (see Section 3.2). As necessary, other approved operational or engineering control measures would be implemented. Water Quality Protection and Monitoring Plan

17 3 WATER QUALITY MONITORING PLAN The primary monitoring method proposed for this project is visual monitoring, supported as necessary with contingent real-time instrumented monitoring of water quality parameters using a hydroprobe with ph and turbidity sensors. To the extent the construction work can be fully removed or isolated from the water and completed in the dry, visual monitoring will be performed. Instrumented monitoring will be performed if in-water earthwork is necessary; for example, if the foundation for the splash pad of the replacement outfall is excavated in the water and without use of a coffer dam. Instrumented monitoring may also be implemented if a significant turbidity plume is observed during visual monitoring, to better assess compliance with water quality standards and the effectiveness of any supplemental BMPs that may be implemented to control turbidity. In the event that an exceedance of water quality standards is indicated by either visual or instrumented monitoring, contingency response actions and agency notifications will be triggered. The contingency response and notification plan is provided in Section Visual Monitoring Visual monitoring will be performed during all construction activities that are removed or isolated from the water or performed in the dry. Specifically, visual monitoring will be performed during the following construction activities: Trench work in the dry to lay the replacement stormwater outfall Excavation of the splash pad foundation if the excavation area is isolated from the water column by a coffer dam Grouting to abandon the existing stormwater outfall Pile removal Over-water construction work on the shiploader structure Over-water casting of concrete pile caps and trestle decking on the shiploader structure Concrete filling of steel piles Water Quality Protection and Monitoring Plan

18 Water Quality Monitoring Plan The monitoring and inspection procedures outlined in the following subsections will be implemented during visual monitoring Monitoring Parameters The following parameters will be assessed during visual monitoring: Turbidity Sheen Construction debris in the water Operation and effectiveness of BMPs Monitoring Schedule The frequency of visual monitoring will be as follows: Ongoing monitoring by Contractor during construction operations Twice daily monitoring by the Project Engineer or Environmental Manager Immediate monitoring if notified by the Contractor of a potential water quality exceedance, followed by ongoing monitoring until water quality returns to acceptable conditions Monitoring Locations Visual monitoring will be performed at the following locations: For BMP performance, at the location of the active operation For turbidity, within 300 feet downstream of any relevant construction activities For visible sheen, at the point of discharge to the river For construction debris, including wet concrete, at the point of discharge to the river Note that multiple activities requiring monitoring may be occurring simultaneously. 3.2 Instrumented Monitoring Instrumented monitoring will be performed during the following construction activities: Any in-water earthwork activities that are in direct contact with the water column; Water Quality Protection and Monitoring Plan

19 Water Quality Monitoring Plan for example, excavation of the splash pad foundation, if such work is performed without use of a coffer dam, or any other ground-disturbing activities that must be performed in the water due to unusually high water levels, scheduling constraints, or other field contingencies As a possible contingency measure in response to a visual observation of a significant turbidity plume, to better assess compliance with water quality standards and the effectiveness of any supplemental BMPs that may be implemented to control turbidity The monitoring procedures outlined in the following subsections will be implemented during instrumented monitoring Monitoring Parameters Real-time field measurements of the following water quality parameters will be collected during instrumented monitoring: Turbidity (in NTU) ph (in standard units) Monitoring Schedule If instrumented monitoring is required, it will consist of two rounds of measurements each day. If any exceedances of water quality criteria are observed at any time during the monitoring program and it is determined that the exceedance is caused by construction activities rather than an ambient background condition, then the contingency response and notification procedures will be initiated as described in Section Monitoring Locations During each monitoring event, turbidity and ph will be measured at three stations: 1. The Compliance Station is at the edge of the mixing zone 300 feet (91.4 meters) downstream from the construction activity. Compliance with water quality criteria will be evaluated at this station. Water Quality Protection and Monitoring Plan

20 Water Quality Monitoring Plan 2. The Early Warning Station is at the mid-point of the mixing zone, 150 feet (45.7 meters) downstream from the construction activity. The objective of the Early Warning Station is to become quickly aware of possible water quality excursions at the construction site and to be able to adjust construction operations and BMPs before an exceedance occurs at the Compliance Station. 3. The Background Station will be positioned approximately 500 feet (152 meters) upstream of the project site and beyond the influence of construction activities. The Background Station should be located along a part of shoreline with comparable water depth and other physical characteristics, including riprap armor. This station will be monitored during every event because the turbidity criterion is based on an acceptably small increase above ambient background levels in the river Monitoring Depths At each monitoring station, measurements of turbidity and ph will be made at three depths in the water column: 1. Surface: Within 3 feet (approx. 1 meter) of the water surface. 2. Middle: At the mid-depth of the water column. 3. Bottom: Within 6 feet (approx. 2 meters) of the river bed. 3.3 Record Keeping The Project Engineer or Environmental Manager will keep a written record of twice-daily monitoring activities and inspections during both visual and instrumented monitoring. These records will be maintained in project files and provided to the Washington State Department of Ecology (Ecology) if requested. Water Quality Protection and Monitoring Plan

21 4 CONTINGENCY RESPONSE AND NOTIFICATION PLAN 4.1 Contingency Measures In the event of an exceedance of water quality standards as observed during visual or instrumented monitoring, personnel will immediately stop work and attempt to assess the source of the impact or exceedance. Once the source has been identified, personnel will implement control measures to prevent further occurrences and limit additional environmental impact. Monitoring will continue to confirm that the control measures are effective and the observed water quality exceedances have been mitigated Visible Turbidity Plume In the event a significant turbidity plume is observed during visual monitoring, construction operations and BMPs will be thoroughly inspected to identify the source of the turbidity exceedance, and appropriate operational controls, engineering controls, or enhanced BMPs will be implemented to reduce turbidity to acceptable levels. A significant plume will extend the entire length of the mixing zone and remain visible 300 feet (91.4 meters) from the construction activity. Based on the shape and extent of the turbidity plume, it should be evident that the plume is sourced from a site construction activity rather than an anomalous background condition. If a visible turbidity plume is evident at the compliance boundary, follow-up instrumented turbidity monitoring may be initiated to better assess compliance with water quality standards and to track the effectiveness of any supplemental controls or BMPs that may be implemented. Instrumented monitoring is described in the next section Instrument Field Monitoring Contingent instrumented monitoring for turbidity and ph may be implemented in certain conditions, as described in Section 3.2. Field parameter measurements will be compared with the water quality criteria specified in Table 1 (see Section 1.2). Compliance with water quality criteria will be determined at the Compliance Station. If there is an exceedance of water quality criteria at the Compliance Station, the following sequence of events will be initiated: Water Quality Protection and Monitoring Plan

22 Contingency Response and Notification Plan 1. Evaluate the concurrent measurements at the Background Station to determine whether the exceedance is caused by ambient river conditions versus site-related construction activities. 2. Re-take field measurements 5 minutes later at the Compliance Station to confirm (or not confirm) the exceedance. 3. If the exceedance is confirmed and is attributed to construction activities, immediately notify the Contractor and Project Engineer. The Contractor will be directed to immediately modify operations and/or implement additional BMPs to mitigate the exceedance. 4. Re-take field measurements at the Compliance Boundary 30 minutes later, after additional BMPs and/or operational modifications are implemented. 5. Notify Ecology of the exceedance, actions taken to mitigate the exceedance, and the results of the follow-up measurements. If the water quality exceedance continues to persist, even with additional BMPs and/or operational modifications, a path forward will be discussed with Ecology. The path forward could include some or all of the following: a. Implement more aggressive BMPs or operational modifications. b. Implement more intensive monitoring to better track the growth or dissipation of the plume. c. If options (a) or (b) are not successful at controlling the water quality exceedance, it may be necessary to stop work to further assess the source of the exceedance, identify effective mitigation measures, and allow the water column to recover Construction Debris in Water In the event of an observed release to the water of deleterious construction debris, the Contractor will cease operations and recover the debris. Repairs to equipment, containment measures, and/or modification to work practices will be made prior to resuming work. Once the source has been identified and addressed, work may proceed. If the debris is environmentally innocuous (e.g., old concrete, steel, etc.), work may proceed simultaneously with recovery efforts. Water Quality Protection and Monitoring Plan

23 Contingency Response and Notification Plan Distressed or Dying Fish In the event distressed or dying fish are observed at the construction site and are attributed to site activities, work will immediately stop and Ecology, the Washington Department of Fish and Wildlife, and the National Marine Fisheries Service will be contacted. The condition of the fish (dead, dying, erratic behavior, etc.); an estimate of the number, species, and size of fish in each condition; and the location of fish relative to construction operations will be noted. If any dead listed species are present, samples will be frozen for possible agency inspection. Additional fish and/or water sampling may be conducted at the direction of the resource agencies Discharge of Oil, Fuel, or Chemicals In the event of a discharge of oil, fuel, or chemicals (including wet concrete) into state waters, containment and cleanup efforts shall begin immediately and be completed as soon as possible. Cleanup includes appropriate disposal of any spilled material and cleanup material. The following agencies will be immediately notified: Ecology s Spill Response Office at (360) Washington State Emergency Mangement at (800) National Response Center at (800) Notification For any work that is out of compliance with water quality standards, personnel will immediately stop work and notify the Project Engineer or Environmental Manager, who will notify Lori Ochoa, Federal Permit Manager, Ecology Southwest Regional Office at (360) A detailed written report will be submitted to Ecology within 5 days or as otherwise specified in the Section 401 Water Quality Certification for this project. The report will include the following information: Nature and extent of the water quality exceedance, including detailed visual observations and, if appropriate, field parameter measurements Identification of the likely cause of the exceedance Description of control measures or BMPs implemented to mitigate the exceedance Notifications to agency, including timing and names of agency personnel contacted Water Quality Protection and Monitoring Plan

24 Contingency Response and Notification Plan Documentation that control measures were effective at mitigating the water quality exceedance, thereby allowing construction work to resume Water Quality Protection and Monitoring Plan

25 5 REFERENCES Washington State Department of Ecology (Ecology) Guidance on Controlling Turbidity in Nearby Waters from Ground Improvement Work for Seismic Events. Memorandum from K. Carroll, WSDOT Liaison, to K. Susewind, Ecology, July 13, Water Quality Protection and Monitoring Plan

26 FIGURES

27

28

PROGRAMMATIC ENDANGERED SPECIES ACT CONSULTATION Piling Replacement List of Requirements Version: May 3, 2017

PROGRAMMATIC ENDANGERED SPECIES ACT CONSULTATION Piling Replacement List of Requirements Version: May 3, 2017 PROGRAMMATIC ENDANGERED SPECIES ACT CONSULTATION Piling Replacement List of Requirements Version: May 3, 2017 Programmatic Endangered Species Act (ESA) Consultations [U.S. Fish and Wildlife Service (USFWS)

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate Project Overview Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate a natural gas-tomethanol production plant and storage facilities, and a new marine terminal, in the

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements:

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements: TNC Fisher Slough Final Design and Permitting Subject: Inverted Siphon Construction Feasibility To: From: Jenny Baker (TNC) Dave Olson (DD3) Brian Olson (DD17) Bob Boudinot Skagit County David Cline (Tetra

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

Attachment D-1: Civil/Structural Scope of Work

Attachment D-1: Civil/Structural Scope of Work Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,

More information

General Permit No.: OHR Page 53 of 146

General Permit No.: OHR Page 53 of 146 Page 53 of 146 Part 8 Sector-Specific Requirements for Industrial Activity Subpart J Sector J Non-Metallic Mineral Mining and Dressing. You shall comply with Part 8 sector-specific requirements associated

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0 PROTOCOL 15 FOR CONTAMINATED SITES Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil Version 1.0 Prepared pursuant to Section 64 of the Environmental Management

More information

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR All the documents shown today are in the MN Stormwater Manual on the page titled 2018 Construction Stormwater Permit Public Notice and Public Informational

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Appendix D. Stormwater Pollution Prevention Plan

Appendix D. Stormwater Pollution Prevention Plan Appendix D Memorandum AECOM 3292 Production Way, Floor 4 604 444 6400 tel Burnaby, BC, Canada V5A 4R4 604 294 8597 fax www.aecom.com To Joan Liu, Metro Vancouver Page 1 CC Subject Conveyance for the NSWWTP

More information

Greenfield Pond B Rehabilitation

Greenfield Pond B Rehabilitation Preliminary Investigation Report Centennial, Colorado November 15, 2011 Prepared for: Liverpool Metropolitan District Prepared by: Stantec Consulting Services, Inc. Table of Contents Executive Summary...

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN 32-00042 OCTOBER 12, 2016 LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT

More information

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation. SECTION 312333 TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 SUMMARY A. Excavate trenches for new electric and telephone conduits, gas lines, and their appurtenances from at least 5 feet outside the building

More information

STORM WATER PLAN (SWP) GUIDANCE TEMPLATE

STORM WATER PLAN (SWP) GUIDANCE TEMPLATE STORM WATER PLAN (SWP) GUIDANCE TEMPLATE Name of Facility: Address: Phone Number: Date: INTRODUCTION This Storm Water Plan (SWP) is written in accordance with the State of Delaware Regulations Governing

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

Joint Public Notice. LOCATION: In Salmon Bay, Lake Washington Ship Canal, at Seattle, Washington.

Joint Public Notice. LOCATION: In Salmon Bay, Lake Washington Ship Canal, at Seattle, Washington. US Army Corps of Engineers Seattle District Joint Public Notice Application for a Department of the Army Permit and a Washington Department of Ecology Water Quality Certification and/or Coastal Zone Management

More information

The Good, The Bad, and The Ugly

The Good, The Bad, and The Ugly Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information

CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY

CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY File No. 0506-013-07 Contaminated Media Management Plan Midland

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

Installation and Maintenance of Erosion Control BMPs

Installation and Maintenance of Erosion Control BMPs Installation and Maintenance of Erosion Control BMPs Or Common BMPs Applications Specifications Installation Problems Maintenance Utility Design Professionals Clarifications, proactive problem solving

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014 1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment,

More information

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands SOUTH FLORIDA WATER MANAGEMENT DISTRICT Question 13: Wetlands 1. The wetland responses and topographical data provided in the ADA for the 520- acre project site are conceptual in nature. The referenced

More information

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO.

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. 11-91360-001 ADVERTISED: November 5, 2010 MANDATORY PRE-BID MEETING:

More information

Admiralty Inlet Pilot Tidal Project FERC No Appendix D. Water Quality Monitoring Plan

Admiralty Inlet Pilot Tidal Project FERC No Appendix D. Water Quality Monitoring Plan Appendix D Water Quality Monitoring Plan ADMIRALTY INLET PILOT TIDAL PROJECT FERC PROJECT NO. 12690 WATER QUALITY MONITORING PLAN (submitted with the Final Application for a New Pilot Project License)

More information

PUBLIC WORKS SKAGIT COUNTY SAMISH ISLAND ROAD SAMISH ISLAND ROAD SLIDE REPAIR

PUBLIC WORKS SKAGIT COUNTY SAMISH ISLAND ROAD SAMISH ISLAND ROAD SLIDE REPAIR EASEMENT NOTES:. EASEMENT LIMIT SHOWN AS PROVIDED BY. TESC NOTES:. CONTRACTOR SHALL DEVELOP TEMPORARY EROSION AND SEDIMENT CONTROL PLAN AND PROVIDE ONSITE CERTIFIED EROSION AND SEDIMENT CONTROL LEAD (CESCL)

More information

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control Inspecting Construction Site BMPs Kristin Kerr EOA, Inc. Outline of Presentation Back to Basics Erosion and Sediment Control Good Site Non-Stormwater Run-on and Run-off Control Construction Inspection

More information

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards

More information

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

SECTION RIPRAP, BOULDERS, AND BEDDING

SECTION RIPRAP, BOULDERS, AND BEDDING SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

Design Specifications & Requirements Manual

Design Specifications & Requirements Manual Design Specifications & Requirements Manual 10 SEDIMENT AND EROSION CONTROL 10.1 INTRODUCTION... 1 10.2 REFERENCE... 1 10.3 GENERAL INFORMATION REQUIREMENTS... 1 10.3.1 ESC Plan... 1 10.3.2 Servicing Drawings...

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

JEFFERSON COUNTY STORM WATER MANAGEMENT

JEFFERSON COUNTY STORM WATER MANAGEMENT JEFFERSON COUNTY STORM WATER MANAGEMENT B-210 Courthouse, Birmingham, Alabama 35203 Telephone: (205) 325-8741 Erosion and Sedimentation Control Measures for Commercial Projects (Plans Requirements) -All

More information

EROSION & SEDIMENT CONTROL/STORMWATER CERTIFICATION: (Rev ) SP1 G180

EROSION & SEDIMENT CONTROL/STORMWATER CERTIFICATION: (Rev ) SP1 G180 EROSION & SEDIMENT CONTROL/STORMWATER CERTIFICATION: 1-16-07 (Rev 1-15-08) SP1 G180 General Schedule and conduct construction activities in a manner that will minimize soil erosion and the resulting sedimentation

More information

Appendix A: Project Characteristics

Appendix A: Project Characteristics Gorgon Fourth Train Expansion Proposal Appendix A: Project Characteristics Appendices Project Characteristics A Key Characteristics table has been prepared to describe the elements of the Foundation Project

More information

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP)

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP) Elements of the Storm Water Management Plan Storm Water Pollution Prevention Plan (SWPPP) Small Construction Site Storm Water Management Rodney Hendrick Water Quality Specialist LSU Ag Center Plan Requirements

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission

More information

APPENDIX F. SECTION 404(B)(1) EVALUATION SHORT VERSION. Herbert Hoover Dike Dam Safety Modification Study

APPENDIX F. SECTION 404(B)(1) EVALUATION SHORT VERSION. Herbert Hoover Dike Dam Safety Modification Study Appendix F Section 404(b)(1) APPENDI F. SECTION 404(B)(1) EVALUATION SHORT VERSION Herbert Hoover Dike Dam Safety Modification Study HHD Dam Safety Modification Study EIS June 2016 E i Appendix F Section

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance

More information

KDOT TEMPORARY EROSION - CONTROL MANUAL

KDOT TEMPORARY EROSION - CONTROL MANUAL KDOT TEMPORARY EROSION - CONTROL MANUAL A Guide for the Design, Installation, Inspection, and Maintenance of Temporary Erosion-Control Measures in Kansas January 2007 PURPOSE & USE OF THE MANUAL PURPOSE

More information

7/17/2017 Page 1 of 5

7/17/2017 Page 1 of 5 HORIZONTAL DIRECTIONAL DRILLING AND BORING PART 1.0 GENERAL 1.1 DESCRIPTION This section covers the work necessary for the installation of conduit duct banks by directionally controlled horizontal drilling

More information

Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study. Presented by John Laplante, Carl Stivers, and Clay Patmont

Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study. Presented by John Laplante, Carl Stivers, and Clay Patmont Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study Presented by John Laplante, Carl Stivers, and Clay Patmont October 24, 2012 Presentation Outline Engineered Barriers Best

More information

City of Bozeman. Construction Site Management Program

City of Bozeman. Construction Site Management Program City of Bozeman Construction Site Management Program Best Management Practice (BMP) Manual for Construction Sites Version 6 June 30, 2017 Blank Page 2 Section 1 - Overview Table of Contents Manual Introduction

More information

Annex I Lyons Ferry Hatchery Modification Plan

Annex I Lyons Ferry Hatchery Modification Plan Annex I Lyons Ferry Hatchery Modification Plan Table I1 Figure I1 Figure I2 Figure I3 Figure I4 Figure I5 Well Characteristics Lyons Ferry Hatchery Vicinity Map Lyons Ferry Hatchery Site Plan Water Supply

More information

U.S. ARMY CORPS OF ENGINEERS. Little Rock District

U.S. ARMY CORPS OF ENGINEERS. Little Rock District U.S. ARMY CORPS OF ENGINEERS Little Rock District SEDIMENT AND EROSION CONTROL GUIDELINES FOR PIPELINE PROJECTS Table of Contents 1.0 INTRODUCTION... - 1-2.0 PROJECTS IN WATERS OF THE UNITED STATES...

More information

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011 Introduction to Sediment Remediation Presented to: Lower Passaic River Community Advisory Group July 14, 2011 Overview Feasibility Considerations Conceptual Site Model Dredging / Capping Dredged Material

More information

Alberta Transportation. Environmental Protection Plan for the Planning and Construction of Water and Transportation Projects

Alberta Transportation. Environmental Protection Plan for the Planning and Construction of Water and Transportation Projects Alberta Transportation Environmental Protection Plan for the Planning and Construction of Water and Transportation Projects January 9, 2009 INFTRA Table of Contents Page Table of Contents... i 1.0 INTRODUCTION...1

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Builder s enviro guide

Builder s enviro guide BC3337 Builder s enviro guide Preventing pollution from your building project Find out more: phone Auckland Council on 09 301 0101 or visit aucklandcouncil.govt.nz Contents Why compliance matters 2 The

More information

Mr. Paul Dunlap, California Department of Water Resources

Mr. Paul Dunlap, California Department of Water Resources Memorandum To: From: Mr. Paul Dunlap, California Department of Water Resources Oroville Dam Spillway Incident Independent Forensic Team Date: September 5, 2017 Re: Interim Status Memorandum Introduction

More information

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division

More information

15-MM & 16-MA NOI and SWPPP Overview

15-MM & 16-MA NOI and SWPPP Overview Maryland Department of the Environment 15-MM & 16-MA NOI and SWPPP Overview General Permit for Mineral Mines, Concrete and Asphalt Plants (15MM / NPDES MDG49) and General Permit for Marinas (16MA / NPDES

More information

Constructed Wetland Use in Nonpoint Source Control

Constructed Wetland Use in Nonpoint Source Control Constructed Wetland Use in Nonpoint Source Control Description Constructed wetlands are excavated basins with irregular perimeters and undulating bottom contours into which wetland vegetation is purposely

More information

5.5 NAVIGABLE WATERWAYS AND COASTAL ZONE

5.5 NAVIGABLE WATERWAYS AND COASTAL ZONE 5.5 NAVIGABLE WATERWAYS AND COASTAL ZONE This section discusses the effect of the Proposed Action on navigable waterways, and the Proposed Action s consistency with coastal zone policies. 5.5.1 Navigable

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

Mitigating Environmental Impacts in the Offshore Oil and Gas Industry

Mitigating Environmental Impacts in the Offshore Oil and Gas Industry Mitigating Environmental Impacts in the Offshore Oil and Gas Industry Paul Barnes, Manager - Atlantic Canada & Arctic NOTES 2015 St. John s, NL April 27, 2015 Overview Who is CAPP? Oil and Gas Lifecycle

More information

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems Anchorplex retaining wall construction guide Building Anchorplex Retaining Wall Systems Table of Contents and ow to Use This Guide table of contents ow to Use This Guide. 2 About the Anchorplex System.

More information

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY Phong Vo, Manager - Engineering/Gypsum, Mosaic Fertilizer, LLC. 13830 Circa Crossing Drive Lithia, Florida 33547, USA and Ashraf H. Riad, Ph.D., P.E.,

More information

Department of the Army Permit Application

Department of the Army Permit Application Department of the Army Permit Application DA File Number U.S. Army Corps of Engineers Honolulu District Date Received by CEPOH-RO Send Completed Application to: Honolulu District, U.S. Army Corps of Engineers

More information

Dredging and Dredged Material Disposal Overview

Dredging and Dredged Material Disposal Overview Dredging and Dredged Material Disposal Overview Tim Welp Timothy.L.Welp@usace.army.mil 601.634.2083 The process of dredging consists of the following stages: - Excavation (loosening or dislodging) of the

More information

Division 02 - Site Work Section

Division 02 - Site Work Section NWIT-11-26 Page 1 1 GENERAL 1.1 REQUIREMENTS INCLUDED.1 Furnish all labour, material, services and equipment necessary to carry out and complete excavation work and shoring, as indicated on the drawings

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum LOUISIANA URBAN STORMWATER COALITION EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum SWPPP NOTIFICATION SIGN Post sign at entrance of site or areas where the public can easily access.

More information

Development of the SP-SSA International Terminal, Vietnam Christopher B. Cornell, MASCE, PE, SE; 1 Morgan McArthur, MASCE; 2 and David Michou 3

Development of the SP-SSA International Terminal, Vietnam Christopher B. Cornell, MASCE, PE, SE; 1 Morgan McArthur, MASCE; 2 and David Michou 3 Development of the SP-SSA International Terminal, Vietnam Christopher B. Cornell, MASCE, PE, SE; 1 Morgan McArthur, MASCE; 2 and David Michou 3 1 Project Manager, BergerABAM, 33301 Ninth Avenue South,

More information

SECTION 11: REGULATORY FLOODWAYS

SECTION 11: REGULATORY FLOODWAYS SECTION 11: REGULATORY FLOODWAYS Contents 11.1. The Floodway... 11-2 11.1.1. The floodway concept... 11-2 11.1.2. Floodway map... 11-2 11.1.3. Floodway permitting... 11-3 11.1.4. Changing the floodway...

More information

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown

More information

GUIDELINES FOR INSTALLATION OF ABOVEGROUND DIESEL FUEL TANKS

GUIDELINES FOR INSTALLATION OF ABOVEGROUND DIESEL FUEL TANKS GUIDELINES FOR INSTALLATION OF ABOVEGROUND DIESEL FUEL TANKS Revised 1/1/17 Authority cited: California Fire Code; National Fire Protection Association 30 (NFPA) Flammable and Combustible Liquids Code

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Project Review Application Form

Project Review Application Form Project Review Application Form Information supplied in this application may be made public during consultation with adjacent municipalities, First Nations groups and other interested parties, as well

More information

Current Trends in Marina Planning and Design

Current Trends in Marina Planning and Design ASSOCIATION OF PACIFIC PORTS 101 st Annual Conference, July 2014 Current Trends in Marina Planning and Design, PE, LEED AP, Reid Middleton Outline Introduction Market & Demand Planning Environmental Design

More information

Sediment Basin. Fe= (Depends on soil type)

Sediment Basin. Fe= (Depends on soil type) 3.9 Sediment Control Description: A sediment basin is an embankment with a controlled outlet that detains stormwater runoff, resulting in the settling of suspended sediment. The basin provides treatment

More information

SECTION GRAVEL PACKED WATER WELL

SECTION GRAVEL PACKED WATER WELL SECTION 02520 GRAVEL PACKED WATER WELL PART 1 GENERAL 1.01 SECTION INCLUDES A. Gravel packed water well includes drilling, installing, cleaning, developing, testing, videoing, abandoning, and site clean

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information