EVALUATION OF ODOR EMISSIONS AND THEIR CONTROL AT THE CHIQUITA WATER RECLAMATION PLANT, AND SAN JUAN AND ORTEGA LIFT STATIONS

Size: px
Start display at page:

Download "EVALUATION OF ODOR EMISSIONS AND THEIR CONTROL AT THE CHIQUITA WATER RECLAMATION PLANT, AND SAN JUAN AND ORTEGA LIFT STATIONS"

Transcription

1 EVALUATION OF ODOR EMISSIONS AND THEIR CONTROL AT THE CHIQUITA WATER RECLAMATION PLANT, AND SAN JUAN AND ORTEGA LIFT STATIONS Prepared for: RANCHO MISSION VIEJO Ortega Highway San Juan Capistrano, CA by: BOWKER & ASSOCIATES, INC. CONSULTING ENGINEERS 477 Congress Street, Suite 1004 Portland, ME May, 2013 i

2 EXECUTIVE SUMMARY INTRODUCTION The Ranch Plan prepared by Rancho Mission Viejo was approved in 2004 by the County Board of Supervisors. A portion of the proposed development is in relatively close proximity to the Chiquita Water Reclamation Plant (CWRP) in the unincorporated County of Orange, CA. The sewage treatment plant currently has no neighbors, but the location of the proposed development has raised concerns with regard to the potential for odors to be detected by the residents and other occupants. Also, the San Juan and Ortega Lift Stations are sources of odors that could potentially impact the development. The purpose of this study is: 1. To determine the extent to which CWRP odors will be detected by future residents in Planning Area Determine the adequacy of existing odor control systems to meet target odor levels in the proposed development. 3. Evaluate needed improvements at the treatment plant and lift stations to prevent odor complaints. 4. Make recommendations to upgrade, expand, or replace odor control systems to ensure that odor impacts on the community are minimized. DESCRIPTION OF FACILITIES Chiquita Water Reclamation Plant The Chiquita Water Reclamation Plant (CWRP) is a 9 million gallon per day (mgd) wastewater treatment plant owned and operated by the Santa Margarita Water District (SMWD). It is located in Chiquita Canyon. The original Phase I facility came on-line in 1987 using the trickling filter-solids contact process for wastewater treatment. The plant currently treats approximately 5 mgd through a conventional activated sludge process with tertiary filtration, producing reclaimed water suitable for landscape irrigation and agriculture. An additional 1 mgd is treated through the original trickling filter solids contact process. The plant appears to be well operated and maintained, and was in a clean and orderly condition at the time of the visits. The CWRP was constructed with four odor control systems having a total combined air treatment capacity of 58,000 cubic feet per minute (cfm). Since the plant has no current neighbors, the odor control systems were installed to meet permit requirements only for hydrogen sulfide. Apparently, the SMWD was able to demonstrate that the permit requirements ii

3 are met without operating the chemical feed systems, and only the fans are operated to provide adequate ventilation of the enclosed spaces. In 2009, a Master Plan was developed for SMWD by AECOM to evaluate the need for additional capacity and plant upgrades. Recommendations for the Phase 4 expansion included increasing liquid treatment and solids handling capacity, replacement of sludge dewatering systems, adding a thermal sludge drying system, and installing a new central biofilter odor control system. San Juan and Ortega Lift Stations The San Juan Lift Station was constructed in 2001, and houses four pumps, each rated at 2,000 gpm. It is located east of Antonio Parkway and north of San Juan Creek. The pumps discharge into a 16 force main approximately 7,000 ft. long. Current wastewater flows through the San Juan Lift Station are approximately 2 mgd. Peak capacity is 8 to 9 mgd. The San Juan LS receives the discharge from the Horno LS, which serves the community of Ladera Ranch. The Horno LS currently pumps about 2 mgd through 9,500 ft of 16-inch force main. The Ortega Lift Station Lift Station was built in 1991, and has three pumps, each capable of 1,600 to 1,700 gpm. It is located north of Ortega Highway near its intersection with a private road (Christianito Rd). The pumps discharge into a 16-inch force main approximately 17,000 ft. long. Current flows through the station are about 0.7 mgd. Peak capacity is 4 to 5 mgd. The Ortega Lift Station receives the discharge from the Talega Lift Station, which pumps approximately 0.7 mgd through a 10-inch diameter, 12,000 ft long force main, which transitions to a 16-inch force main for the remaining 8,000 ft. The District has installed a system at the Talega LS to inject oxygen and ozone into the force main to prevent sulfide generation. The Ortega LS also has a 300 cfm Biocube biofilter system to treat the air from the wet well. SAMPLING PROGRAM A sampling program was developed for the Chiquita Water Reclamation Plant (CWRP) and the San Juan and Ortega Lift Stations. The purpose of the sampling program was to quantify the odor emissions from the facilities, and understand the conditions under which the odors are generated and released. The sampling program consisted of the following elements: 1. Collection of air samples from major odor sources for laboratory odor panel analysis 2. On-site measurement of hydrogen sulfide (H 2 S) at all sample locations 3. Installation of datalogging H 2 S analyzers (Odalogs) 4. Collection and field analysis of wastewater grab samples iii

4 ODOR DISPERSION MODELING Odor dispersion modeling was used to predict off-site odor impacts from odor sources at CWRP to evaluate odor mitigation alternatives. The software used to complete the modeling was Breeze AERMOD developed by Trinity Consultants Inc. AERMOD is the preferred U.S. Environmental Protection Agency model for simulating the impacts of emissions from a variety of sources. The information input into the model for this study was the Odor Emission Rates (OER) for each odor source, location and discharge height of source, local meteorological conditions from the Costa Mesa and Mission Viejo weather stations operated by the South Coast Air Quality Management District, and digital terrain data. The OER is the odor concentration or Dilutions to Threshold (D/T) multiplied by the air flow rate. The model output predicts the highest D/T level, estimated over the area of analysis. The resulting peak D/T levels are shown graphically on odor contour plots. In addition, the model output provides a plot of odor frequency, that is, the number of hours per year that the odor concentration exceeds a pre-selected target level of nearly non-detectable odor. The target parameters used in the modeling were a peak odor concentration of 7 D/T or less, and an odor detection frequency of less than 100 hours/year. The following scenarios were evaluated using the model: 1. Existing conditions with odor control systems operating. 2. With improved performance of upgraded odor control systems 3. With improved scrubber performance; primary clarifier and sludge transfer scrubbers upgraded to achieve 99% odor reduction. CONCLUSIONS AND RECOMMENDATIONS Conclusions Chiquita WRP 1. The Chiquita Water Reclamation Plant (CRWP) and the lift stations that contribute wastewater flow are well operated and maintained facilities, and poor maintenance is not a factor contributing to odor emissions. 2. Based on sampling of the odor emissions from various processes, the discharge of the chemical scrubber serving the primary clarifiers had the highest odor concentrations and the highest odor emission rate. 3. The existing chemical scrubbers were designed only for hydrogen sulfide removal using sodium hydroxide, and are only partially effective at controlling odor emissions, with odor removal efficiencies of zero to 70 percent. iv

5 4. The second largest odor contributor based on odor emission rate was the chemical scrubber serving the sludge thickening and holding processes. Odors from these sources tend to be strong, and sulfur compounds other than H 2 S typically contribute to the strong odor. 5. The trickling filters were estimated to be the third largest odor emission source. 6. Odor dispersion modeling using AERMOD showed significant predicted downwind odor impacts from the CWRP on the area slated for development (Planning Area 2). Predicted peak odor levels were as high as 1,000 D/T, compared to target levels of 7 D/T. 7. The scrubbers serving the primary clarifier and sludge transfer processes were responsible for almost 98% of the total plant odor emissions, with the primary clarifier scrubber accounting for 90 percent of the plant odor emissions. 8. The existing chemical scrubbers serving the CWRP appear to be capable of being upgraded to use sodium hypochlorite (bleach) which will greatly enhance performance. 9. Even with the assumption of 90% odor reduction through upgraded chemical scrubbers, dispersion modeling still shows an odor impact on the proposed Planning Area 2. This impact is largely due to the primary clarifier scrubber. Predicted peak odor levels were as high as 200 to 300 D/T near the plant fence-line compared to target levels of 7 D/T. 10. With 99% odor reduction assumed for the primary clarifier scrubber and sludge transfer scrubber, predicted odor impacts closely approach the target range for acceptable odor concentrations and detection frequency (less than 7 D/T peak odor concentration; less than 100 hr/yr above 7 D/T). 11. Under the scenario of 99% odor reduction in the primary clarifier scrubber and sludge transfer scrubber, the trickling filters become a more significant source of odor. 12. The remaining odor sources, including the aeration tanks, dewatering building, sludge loading operation, and grit storage are relatively minor and do not appear to be capable of off-site detection. Ortega and San Juan Lift Stations 1. The Ortega Lift Station experienced significant spikes in H 2 S of over 350 ppm during morning hours. The remainder of the day, H 2 S concentrations were zero. 2. The biofilter serving the Ortega LS is not providing effective treatment due to overloading and the need to replace the organic media. 3. The San Juan Lift Station showed a relatively high odor concentration in the wet well air. Due to a steeply-sloped influent sewer, the sewer is conveying large volumes of air to the wet well. This causes the air to become pressurized and escape around seams on hatches, pipe or conduit penetrations, etc. Recommendations Chiquita WRP 1. The primary clarifier scrubber should be upgraded to achieve outlet odor concentrations of 300 D/T or less. The cost of rehabilitating the scrubber and adding a second chemical (bleach) is estimated to be $196, Additional sampling should be conducted on the primary clarifier scrubber to verify the high inlet loading and to measure performance using bleach. v

6 3. The chemical scrubber serving the Chiquita influent pump station should be replaced with a larger, 5,000 cfm biological odor control system such as a biofilter or bioscrubber. The estimated cost of a pre-engineered biofilter system is $362, The sludge transfer scrubber should be rehabilitated and upgraded to use bleach, and the activated carbon in the downstream carbon adsorber should be replaced. Estimated cost of odor control system improvements for the sludge transfer processes is $285, Bowker & Associates concurs with a choice of a central biofilter system to handle odorous air from an expanded Chiquita WRP in accordance with the 2009 Master Plan. If space is not available for a large biofilter, biotrickling filters (aka bioscrubbers) should be evaluated. Ortega and San Juan Lift Stations 1. The San Juan LS should be fitted with a 1,000 cfm (conservative) activated carbon adsorber to treat odorous air from the wet well. This will ensure no off-site odors even if upstream chemical treatment is compromised. Estimated cost of this system is $112, Oxygen injection rate at the Talega LS should be increased to eliminate spikes of H 2 S at the downstream Ortega LS. 3. The media in the Ortega LS biofilter should be replaced. 4. The Santa Margarita Water District should continue their effort to control sulfide in the collection system using cost-effective control technologies such as oxygen injection. Oxygen injection is likely to be more cost-effective and reliable compared to the existing chemical (nitrate) addition system at the Horno LS, even though the current system may be effective.. SUMMARY OF ODOR CONTROL RECOMMENDATIONS Recommendation Est. Capital Cost, $ 1. Install activated carbon adsorber at San Juan LS $112, Upgrade primary clarifier scrubber $196, Upgrade sludge transfer scrubber $285, Install biofilter at influent pump station $362, Replace media in Ortega LS biofilter $ 10, Increase oxygen injection at Talega LS $ 0 vi

7 TABLE OF CONTENTS Page No. EXECUTIVE SUMMARY... i 1. INTRODUCTION DESCRIPTION OF FACILITIES Chiquita Water Reclamation Plant San Juan and Ortega Lift Stations SAMPLING PROGRAM Methodology Results Odor and H 2 S Measurements Continuous H 2 S Dataloggers Wastewater Grab Samples ODOR DISPERSION MODELING Odor Emission Rates Description of Dispersion Model General Description Dispersion Model Output Modeling Protocol Description of Modeling Scenarios Modeling Results EVALUATION OF ODOR CONTROL ALTERNATIVES San Juan and Ortega Lift Stations Chiquita Water Reclamation Plant Interim Odor Control Measures Long-Term Odor Control CONCLUSIONS AND RECOMMENDATIONS Conclusions Recommendations vii

8 LIST OF TABLES Page No. Table 1 Table 2 Table 3 Table 4 Table 5 Table 6 Table 7 Table 8 Odor Control Systems at the Chiquita WRP...5 Summary of Odor and H2s Data from Air Sampling Program Chiquita Water Reclamation Plant Liquid Stream Sampling Data Santa Margarita Water District...20 Ranking of Existing Odor Sources by Odor Emission Rate Chiquita Water Reclamation Plant...22 Estimated Cost of 1,000 cfm Activated Carbon Odor Control System for San Juan Lift Station...36 Estimated Cost of Primary Clarifier Scrubber Upgrade...39 Estimated Cost of Sludge Transfer Scrubber And Carbon Adsorber Upgrade...41 Estimated Cost of 5,000 cfm Pre-Engineered Biofilter for Chiquita Influent Pump Station...42 viii

9 LIST OF FIGURES Page No. Figure 1 Chiquita WRP and Planning Area No. 2 Map...2 Figure 2 Site Plan of Existing Chiquita WRP...6 Figure 3 Diagram of Flux Chamber Sampling System...10 Figure 4 H 2 S Concentration vs. Time Ortega LS Wet Well March 9-13, Figure 5 H 2 S Concentrations vs. Time San Juan LS Wet Well Figure 6 March 9-13, H 2 S Concentration vs. Time Chiquita WRP Influent PS Wet Well March 9-13, Figure 7 Predicted Peak Odor Levels - Existing Conditions (Costa Mesa Met Data)...26 Figure 8 Predicted Odor Detection Frequency - Existing Conditions (Costa Mesa Met Data)...27 Figure 9 Predicted Peak Odor Levels - Existing Conditions (Mission Viejo Met Data)...28 Figure 10 Predicted Odor Detection Frequency - Existing Conditions (Mission Viejo Met Data)...29 Figure 11 Predicted Peak Odor Levels - 90% Control in Scrubbers...31 Figure 12 Predicted Odor Detection Frequency - 90% Control in Scrubbers...32 Figure 13 Predicted Peak Odor Levels - 99% Control in Primary Clarifier and Sludge Transfer Scrubbers...33 Figure 14 Predicted Odor Detection Frequency - 99% Control in Primary Clarifier and Sludge Transfer Scrubbers...34 ix

10 1. INTRODUCTION The Ranch Plan developed by Rancho Mission Viejo was approved in 2004 by the County Board of Supervisors. A portion of the proposed development is in relatively close proximity to the Chiquita Water Reclamation Plant (CWRP) in the unincorporated County of Orange, CA. The sewage treatment plant currently is surrounded by ranching and farming operations. The location of the proposed development has raised concerns with regard to the potential for odors to be detected by residents and other occupants. Also, the San Juan and Ortega Lift Stations are sources of odors that could potentially impact the development. A map showing the location of the Chiquita WRP and Planning Areas 2 and 3 are shown in Figure 1. The closest residence may be as little as 1,000 feet from the wastewater treatment plant. In addition, there are two lift stations (San Juan and Ortega) that are odor sources that could impact future residents. The purpose of this study is: 1. To determine the extent to which CWRP odors will be detected by future residents in Planning Area Determine the adequacy of existing odor control systems to meet target odor levels in the proposed development. 3. Evaluate needed improvements at the treatment plant and lift stations to prevent odor complaints. 4. Make recommendations to upgrade, expand, or replace odor control systems to ensure that odor impacts on the community are minimized. 1

11 FIGURE 1 VICINITY MAP SHOWING SMWD FACILITIES AND RANCH PLAN 2

12 2. DESCRIPTION OF FACILITIES 2.1 Chiquita Water Reclamation Plant The Chiquita Water Reclamation Plant (CWRP) is a 9 million gallon per day (mgd) wastewater treatment plant owned and operated by the Santa Margarita Water District (SMWD). It is located in Chiquita Canyon (see Figure 1). The original Phase I facility came on-line in 1987 using the trickling filter-solids contact process for wastewater treatment. The plant currently treats approximately 5 mgd through a conventional activated sludge process with tertiary filtration, producing reclaimed water suitable for landscape irrigation and agriculture. An additional 1 mgd is treated through the original trickling filter solids contact process. The plant appears to be well operated and maintained, and was in a clean and orderly condition at the time of the visit. Unit liquid stream processes at the facility include: 1. Influent screening and pumping 2. Vortex grit removal system 3. Primary clarification 4. Activated sludge or trickling filter solids contact 5. Final clarification 6. Tertiary filtration 7. Disinfection Solids handling processes include: 1. Gravity thickening 2. Mechanical disk thickening 3. Anaerobic digestion 4. Sludge holding 5. Belt filter press dewatering 6. Off-site disposal of dewatered biosolids 3

13 Digester gas is burned in boilers to heat the digesters, and excess gas is burned to generate electricity via micro turbines. Ferric chloride is added to the digesters to control hydrogen sulfide. The CWRP was constructed with four odor control systems having a total combined air treatment capacity of 58,000 cubic feet per minute (cfm). Since the plant has no current neighbors, the odor control systems were installed to meet permit requirements for only hydrogen sulfide. Apparently, the SMWD was able to demonstrate that the permit requirements are met without operating the chemical feed systems, and only the fans are operated to provide adequate ventilation of the enclosed spaces. Table 1 provides a summary of the available information on the odor control systems. Figure 2 shows a site plan of the existing Chiquita WRP. In 2009, a Master Plan was developed for SMWD by AECOM to evaluate the need for additional capacity and plant upgrades. Recommendations for the Phase 4 expansion include: 1. Increasing influent pumping capacity 2. Constructing a new 3 million gallon emergency raw sewage holding basin 3. Installing new screens at influent lift station, and adding one new vortex grit chamber 4. Constructing one new primary clarifier 5. Constructing two new aeration tanks and two secondary clarifiers 6. Installing new 1.5 million gallon (secondary) flow equalization basin 7. Constructing additional filter and chlorine contact tank 8. Installing additional disc thickener 9. Constructing new anaerobic digester and sludge holding tank 10. Replacing the belt filter presses with centrifuges 11. Constructing a 39 wet-ton-per-day thermal sludge drying system 12. Installing 3 new micro turbines 4

14 TABLE 1 ODOR CONTROL SYSTEMS AT THE CHIQUITA WRP Odor Control System Processes Served Air Flow Capacity, cfm Type 1. Influent Lift Station Screen room, old wet well 4,000 Cross-flow, caustic-only chemical scrubber; approx. 5.5 ft of horizontal media 2. Primary Clarifiers Grit chambers, primary clarifiers 24,000 Vertical, counter-current packed tower scrubber, causticonly; 8 ft. diam., 9 ft. packing depth 3. Dewatering Building Biosolids dewatering room 22,000 Vertical, counter-current packed tower scrubber, causticonly; 8 ft. diam,, 9 ft. packing depth 4. Sludge Transfer Building Sludge thickening, holding 8,000 Cross-flow caustic-only scrubber followed by 12 ft. diam. activated carbon adsorber 5

15 FIGURE 2 6

16 13. Installing new 4-cell central biofilter for odor control at the treatment plant, as well as a new odor control system for the influent pump station (capacities not provided). 2.2 San Juan and Ortega Lift Stations San Juan Lift Station The San Juan Lift Station was constructed in 2001, and houses four pumps, each rated at 2,000 gpm. It is located east of Antonio Parkway and north of San Juan Creek (see Figure 1). The wet well is 6 W x 45 L x 20 H. The pumps discharge into a 16 force main approximately 7,000 ft. long. Current wastewater flows through the San Juan Lift Station are approximately 2 mgd. Peak pumping capacity is 8 to 9 mgd. The San Juan LS receives the discharge from the Horno LS, which serves the community of Ladera Ranch. The Horno LS currently pumps about 2 mgd through 9,500 ft of 16-inch force main. From there, the flow transitions to gravity for approximately 1 mile before reaching the San Juan LS. Ortega Lift Station The Ortega Lift Station was built in 1991, and has three pumps, each capable of 1,600 to 1,700 gpm. It is located north of Ortega Highway near its intersection with a private road (Christianito Rd) as shown in Figure 1. The wet well is 6 W x 22 L x 20 H. The pumps discharge into a 16- inch force main approximately 17,000 ft. long. Current flows through the station are about 0.7 mgd. Peak pumping capacity is 4 to 5 mgd. The Ortega Lift Station receives the discharge from the Talega Lift Station, in San Clemente, which pumps approximately 0.7 mgd through a 10-inch diameter, 12,000 ft long force main, which transitions to a 16-inch force main for the remaining 8,000 ft. With the long detention times in these force mains, there is high potential for sulfide generation. The SMWD has installed a system at the Talega LS to inject oxygen and ozone into the force main to prevent sulfide generation. At the time of the sampling, oxygen was being injected at a rate of 150 L/min. The system can inject up to 280 L/min of oxygen. 7

17 The Ortega LS has a 300 cfm Biocube biofilter system to treat the air from the wet well. The system is designed to handle 150 ppm of H 2 S over a 24-hour period, with a max 1-hr peak of 300 ppm. 3. SAMPLING PROGRAM A sampling program was developed for the Chiquita Water Reclamation Plant (CWRP) and the San Juan and Ortega Lift Stations. The purpose of the sampling program was to quantify the odor emissions from the facilities, and understand the conditions under which the odors are generated and released. 3.1 Methodology The sampling program consisted of the following elements: 1. Collection of air samples from major odor sources for laboratory odor panel analysis 2. On-site measurement of hydrogen sulfide (H 2 S) at all sample locations 3. Installation of datalogging H 2 S analyzers (Odalogs) 4. Collection and field analysis of wastewater grab samples Although the odor control systems at the CWRP have not been operated for many years, they were brought into services and operated long enough to collect air samples from the inlet and outlet ductwork. Air samples were collected from the following locations: 1. Inlet and outlet of scrubber serving CWRP influent LS 2. Inlet and outlet of scrubber serving primary clarifiers and grit chambers 3. Inlet and outlet of scrubber serving dewatering building 4. Inlet and outlet of scrubber serving sludge transfer processes 5. Surface of trickling filters 6. Surface of aeration tanks 7. Surface of solids contact tank 8

18 8. Surface of grit piles in container 9. Surface of dewatered sludge cake in biosolids trailer 10. Inlet and outlet of biofilter odor control system at Ortega LS 11. Wet well of San Juan LS Samples were collected on March 11, 12, and 13, The air sampling procedure involved use of the EPA surface isolation chamber or flux chamber that is placed over an area odor source such as the primary clarifier. After a 20-minute equilibration period, a sample was withdrawn from the chamber at 3 liters/minute using Teflon tubing, a vacuum chamber, and air sampling pump. The sampling pump induced a vacuum in the vacuum chamber containing a 10L Tedlar bag. This allowed sample air to flow directly into the Tedlar bag without potential contamination from the sampling pump. A diagram of the sampling apparatus is shown in Figure 3. Air samples were shipped by overnight carrier to St. Croix Sensory in Stillwater, Minnesota for determination of odor concentration in accordance with ASTM E-679. The samples were analyzed within 24 hours of collection. This laboratory test measures the odor strength in dilutions to threshold, which is the number of times that the sample must be diluted with equal volumes of odor-free air before it is no longer detectable by 50% of a trained 6-member odor panel. The dilutions of the sample and the presentation of the air to the odor panelists was accomplished using a forced-choice dynamic triangle olfactometer having a presentation rate of 20 liters/minute. In addition to the odor testing, hydrogen sulfide concentrations were measured at each sample location using an Interscan 4170 H 2 S analyzer with a range of 0.1 to 200 ppm. To measure the diurnal variation in hydrogen sulfide levels with time, datalogging H 2 S analyzers (Odalogs) were installed in the wet wells of the Ortega LS, the San Juan LS, and the Chiquita WRP influent lift station. The devices recorded H 2 S concentrations every five minutes from March 8 until March 13,

19 Regulator Teflon "sweep air" line Stainless steel dome Teflon sample line Tedlar bag Flowmeter "Ultra Zero" compressed air Flotation collar 16" Vacuum chamber Sampling pump FIGURE 3. DIAGRAM OF FLUX CHAMBER SAMPLING SYSTEM Bowker & Associates, Inc. 10

20 Single grab samples of wastewater were collected from the Ortega LS, the San Juan LS, and the Chiquita WRP plant influent. The ph, temperature and oxidation-reduction potential were measured in the field using a Myron L Model 3P analyzer. Total sulfide was measured in the field using a Chemetrics Sulfide Test Kit with a range of 0 to 10 mg/l. 3.2 Results Odor and H 2 S Measurements Table 2 summarizes the results of the air sampling program, which are discussed below in the order shown on the table. The aeration tank odor emissions were relatively low as expected (Samples 1 and 5), with odor concentrations of 140 and 80 dilutions to threshold, and low H 2 S of 0.1 ppm. The trickling filters exhibited a higher odor concentration of 2,400 D/T, but with low H 2 S levels of 0.1 to 0.2 ppm. (Samples 2 and 6). Air samples from the surface of the open sludge cake trailer showed odor levels of 1,100 D/T from freshly-deposited biosolids (Sample 4), and lower odor concentration of 320 D/T from partially dried material (Sample 8). H 2 S levels were 2.7 to 4.4 ppm. The solids contact tank exhibited odor concentrations of 360 D/T and 830 D/T, with low H 2 S of 0.2 ppm (Samples 3 and 7). Samples were collected from the inlet an outlet of the four chemical scrubber systems. All scrubbers were put into service for the sampling, and the ph of the scrubbant solution was adjusted to achieve a minimum ph of 10. The large scrubber serving the grit chambers and primary clarifiers had the highest odor concentration of any of the samples collected. Inlet and outlet odor concentrations were reported as 29,000 and 28,000 D/T, respectively (Samples 11 and 12). Although the H 2 S concentrations were reduced by about 55% through the caustic scrubber, the odor data did not show a similar decrease. The influent pump station scrubber did 11

21 TABLE 2 SUMMARY OF ODOR AND H 2 S DATA FROM AIR SAMPLING PROGRAM CHIQUITA WATER RECLAMATION PLANT March 11, 2013 Sample No. Location Time Odor Concentration (D/T) H 2 S Concentration (ppm) 1 Aeration Tank #1 9:40 AM Trickling Filter #3 10:20 AM 2, Solids contact tank 11:15 AM Sludge cake trailer, fresh 12:00 PM 1, Aeration Tank #2 1:20 PM Trickling Filter #1 2:05 PM 2, Solids contact tank 2:35 PM Sludge cake trailer, dried 3:10 PM

22 TABLE 2 (cont d) SUMMARY OF ODOR AND H 2 S DATA FROM AIR SAMPLING PROGRAM CHIQUITA WATER RECLAMATION PLANT March 12, 2013 Sample No. Location Time Odor Concentration (D/T) H 2 S Concentration (ppm) 9 Influent PS Scrubber Outlet 10 Influent PS Scrubber Inlet 11 Primary Clarifier Scrubber Outlet 12 Primary Clarifier Scrubber Inlet 13 Dewatering Scrubber Outlet 14 Dewatering Scrubber Inlet 15 Sludge Transfer Scrubber Outlet 16 Sludge Transfer Scrubber Inlet 9:20 AM 1, :40 AM 6, :10 AM 28, :25 AM 29, :20 AM :40 AM :55 AM 8, :10 AM 6,

23 TABLE 2 (cont d) SUMMARY OF ODOR AND H 2 S DATA FROM AIR SAMPLING PROGRAM CHIQUITA WATER RECLAMATION PLANT March 13, 2013 Sample No. Location Time Odor Concentration (D/T) H 2 S Concentration (ppm) 17 Ortega LS Biofilter Outlet 18 Ortega LS Biofilter Inlet 19 San Juan LS Wet Well 20 Chiquita WRP Grit Dumpster 9:20 AM 6, :50 AM 9, :30 AM 8, :30 PM 3,

24 show greater than 70% odor and H 2 S reduction, reducing the odor concentration from 6,000 to 1,600 D/T (Samples 9 and 10). Odors in the sludge dewatering room were mild at the time of the sampling. Inlet and outlet odor concentrations from the dewatering room scrubber were only 80 and 50 D/T respectively (Samples 13 and 14). No H 2 S was detected. The low odor and H 2 S concentrations may be due to the addition of ferric chloride to the anaerobic digester, which binds up the hydrogen sulfide. The air entering the sludge transfer scrubber has a relatively high odor concentration of 6,900 and an H 2 S of 2.8 ppm. Much of the odor is likely due to non-h 2 S reduced sulfur compounds. Although the scrubber showed some H 2 S reduction, the outlet odor sample showed a similar odor concentration to the inlet (Samples 15 and 16). The biofilter serving the Ortega LS was sampled (Samples 17 and 18). The system was receiving a relatively high odor loading of 9,700 D/T but odor reduction through the system was only about 30 percent. Inlet H 2 S was only 0.5 ppm, which is much lower than the peaks recorded by the dataloggers (see next section). The organic media in the system is approximately 5 years old and has reached the end of its useful life, which is typically 2 to 5 years. The air sample from the San Juan LS (Sample 19) wet well showed a similar odor concentration of 8,500 D/T and an H 2 S of 1.2 ppm. Peak values may be higher based on datalogger results. Finally, the sample collected from the surface of the grit dumpster at the CWRP showed an odor concentration of 3,700 D/T and H 2 S concentration of 6.5 ppm (Sample 20) Continuous H 2 S Dataloggers Figures 4, 5 and 6 show approximately five days of H 2 S data from March 8 to March 13 for the Ortega LS, San Juan LS, and CWRP influent LS, respectively. The Odalog devices were hung in 15

25 Mar, 8 Mar, 9 Mar, 10 Mar, 11 Mar, 12 Mar, 13 13:50 17:50 21:50 1:50 5:50 9:50 13:50 17:50 21:50 1:50 5:50 9:50 13:50 17:50 21:50 1:50 5:50 9:50 13:50 17:50 21:50 1:50 5:50 9:50 13:50 17:50 21:50 1:50 5:50 H 2 S, Concentration ppm Temperature, F 1000 FIGURE 4 H 2 S Concentration vs. Time Ortega LS Wet Well March 9-13, Temperature; Avg. = 69 F H 2 S; Avg. = 15 ppm Date/Time 16

26 Mar. 8 Mar. 9 Mar. 10 Mar. 11 Mar. 12 Mar :52 18:52 22:52 2:52 6:52 10:52 14:52 18:52 22:52 2:52 6:52 10:52 14:52 18:52 22:52 2:52 6:52 10:52 14:52 18:52 22:52 2:52 6:52 10:52 14:52 18:52 22:52 2:52 6:52 H 2 S Concentration, ppm Temperature, F 7 FIGURE 5 H 2 S Concentrations vs. Time San Juan LS Wet Well March 9-13, Temperature Avg. = 72 F H 2 S; Avg. = 0 ppm Date/Time 17

27 Mar. 8 Mar. 9 Mar. 10 Mar. 11 Mar. 12 Mar :37 19:04 21:31 23:58 2:25 4:52 7:19 9:46 12:13 14:40 17:07 19:34 22:01 0:28 2:55 5:22 7:49 10:16 12:43 15:10 17:37 20:04 22:31 0:58 3:25 5:52 8:19 10:46 13:13 15:40 18:07 20:34 23:01 1:28 3:55 6:22 8:49 11:16 13:43 16:10 18:37 21:04 23:31 1:58 4:25 6:52 9:19 H 2 S Concentration, ppm Temperature, F 11 FIGURE 6 H 2 S Concentration vs. Time Chiquita WRP Influent PS Wet Well March 9-13, Temperature; Avg. = 61 F H 2 S; Avg. = 0 ppm Date/Time 18

28 the wet wells of the Ortega and San Juan LS and in the influent channel upstream of the screens at the CWRP lift station. At the Ortega LS (Figure 4) significant spikes of H 2 S were detected in the morning hours between 6 AM and 10 AM. Peaks of 200 to over 350 ppm were recorded. Smaller spikes were twice detected between 5PM and 6PM. Much of the flow entering this lift station is pumped from the Talega LS, where oxygen/ozone are injected into the force main to control sulfide generation. It would appear that not enough oxygen is being added to prevent sulfide generation during low-flow periods during late evening/early morning hours. At the San Juan LS (Figure 5), average H 2 S concentration was 0 ppm, with only an occasional spike of H 2 S. This lift station receives flow from the Horno LS, where a nitrate product is injected to control hydrogen sulfide generation. The influent pump station for the Chiquita WRP showed low H 2 S concentrations, but with occasional spikes of 8 up to 10 ppm (Figure 6) Wastewater Grab Samples Single grab samples of wastewater were collected from the Ortega LS, the San Juan LS, and the Chiquita influent LS and analyzed in the field for ph, oxidation-reduction potential (ORP), temperature, and total sulfide. ORP is a measure of the relative septicity of the wastewater. Positive values indicate aerobic conditions with presence of dissolved oxygen, while negative values indicate septic or anaerobic conditions conducive to sulfide generation. Results from the wastewater testing are shown in Table 3. Samples collected from the Ortega and San Juan LS wet wells showed no sulfide, with a positive ORP. The sample of the Chiquita WRP influent, on the other hand, exhibited a sulfide concentration of 0.8 mg/l and a highly negative ORP of -240 mv. 19

29 TABLE 3 LIQUID STREAM SAMPLING DATA SANTA MARGARITA WATER DISTRICT March 13, 2013 Location Time ph, s.u. ORP, mv Temp, C Total Sulfide mg/l Ortega LS wet well San Juan LS wet well 8:55 AM :40 AM Chiquita Inf. PS 11:15 AM

30 4. ODOR DISPERSION MODELING 4.1 Odor Emission Rates A key input into the odor dispersion model is the odor emission rate for each odor source. Odor emission rate is the product of the odor concentration and the air flow rate. This provides an estimate of the mass of odor being released from each odor source. Table 4 shows the ranking of the odor sources at the Chiquita Water Reclamation Plant (CWRP) by odor emission rate. This shows that the scrubber serving the grit chamber and primary clarifiers dominates the emissions, accounting for nearly 90 percent of the total measured odor emissions. The second highest odor contributor is the sludge transfer scrubber (9% of total emissions). The trickling filters account for about one percent of the total odor emissions, followed by the influent pump station scrubber and dewatering room scrubber. The aeration tanks, grit dumpsters, solids contact tank, and sludge cake trailers are relatively minor sources that collectively account for less than one percent of total plant odor emissions. 4.2 Description of Dispersion Model General Description Odor dispersion modeling has been used as a reliable and cost-effective approach for predicting offsite odor impacts from odor sources and evaluating odor mitigation alternatives. The odor dispersion model is a computer program designed to predict what impact an odor source, or group of odor sources, will have on an area based on a number of factors that are input into the program. The primary inputs include: Odor emission rates from individual odor sources Odor source dimensions and characteristics Historic meteorological data Local terrain data 21

31 Source TABLE 4 RANKING OF EXISTING ODOR SOURCES BY ODOR EMISSION RATE Chiquita Water Reclamation Plant Odor Concentration (D/T) Estimated Air Flow, cfm Odor Emission Rate D/T x cfm 1. Primary clarifier scrubber 28,000 24, x Sludge transfer scrubber 8,500 8, x Trickling filters (2 in service) 2,400 3, x Influent PS scrubber 1,600 4, x Dewatering bldg. scrubber , x Aeration tanks (2) 140 3, x Grit dumpsters (2) 3, x Solids contact tank x Sludge cake trailers (2) x 10 6 TOTAL X

32 The software used to complete the modeling is Breeze AERMOD v developed by Trinity Consultants Inc. AERMOD is the preferred U.S. Environmental Protection Agency model for simulating the impacts of emissions from a variety of sources where a near field (less than 50 km) condition exists. AERMOD is a comprehensive, steady state Gaussian plume dispersion model that is commonly used for odor assessments as it assumes direct transport from a source to a receptor for every hour of meteorological data, which is designed to yield a conservative result in terms of odor impacts in the community surrounding the facility. The model was be used to predict and simulate the dilution of odors from the sources, measured in terms of Dilutions to Threshold (D/T) for the maximum hourly value of the year throughout the study area. AERMOD uses the pre-processor program AERMET which processes meteorological data for input to AERMOD. The modeling in this study used actual meteorological data obtained from the South Coast Air Quality Management District s monitoring stations in Costa Mesa and Mission Viejo. The data includes the actual hourly meteorological data (wind speed, wind direction, temperature, and cloud cover, ceiling height, and mixing height) from every hour of the year. The information input into the model for this study was Odor Emission Rates (OER) for each point source (sources with stacks &/or exhaust fans); Odor Emission Rate per square foot for each area source (open surfaces and tanks); odor source locations, discharge heights and size; local meteorological conditions from the Costa Mesa and Mission Viejo weather stations, and digital terrain data. The OER is the Detection Threshold (D/T) at the source multiplied by the air flow rate Dispersion Model Output The model output predicts the highest D/T level, estimated over the area of analysis. The resulting peak D/T levels are shown graphically on odor contour plots. In this study, the hourly average D/T levels at particular receptor points were converted to peak one-minute D/T levels by applying a multiplier to account for short exposure to odors. The peak D/T is more relevant for odors, since the odor plume meanders and is very transient. Perceived odor complaints are generally related to peak odor levels, as opposed to an hourly average odor level. 23

33 plant. In other words, it predicts the number of times per year odors may be detectable for a oneminute period at any point in the study area. For example, a person standing at a point where a frequency of 100 is predicted would be expected to experience an odor that exceeds the selected odor detection threshold 100 times (or during 100 hours) per year. In this study, an odor detection threshold of seven (7) D/T has been selected. An odor with a detection threshold of seven dilutions or less may not be detected because it could be overwhelmed by other natural odors in the area such as grass, trees, soil and flowers, or it may not be detectable at all Modeling Protocol The modeling scenarios were completed with the following modeling protocol settings: Peak-to-mean multiplier of: (Averaging Period / Peak Duration) 0.5 = (60 min / 60 sec) 0.5 = 7.75, based on one hour averaging period, one minute average peak duration, and 0.5 power factor. Elevated terrain option Digital local terrain data 2011 surface and mixing height meteorological data, upper air data collected from the Costa Mesa and Mission Viejo meteorological stations operated by the South Coast Air Quality Management District. Threshold of 7 D/T used for the odor frequency modeling Description of Modeling Scenarios Three modeling scenarios were evaluated in this odor evaluation. Following is a description of each of the modeling scenarios. 24

34 Current 2013 Conditions This scenario simulates the odor impact of all significant existing processes at the Chiquita Water Reclamation Plant (CWRP) as tested on March 10-12, All significant existing plant processes are simulated in this modeling scenario, and the odor control systems were operating in accordance with their design. 90% Odor Control Scenario This scenario simulates the odor impact of all significant plant processes, assuming that the existing odor control systems have been upgraded to provide 90 percent odor reduction. 99% Odor Control Scenario This scenario assumes upgrade of the primary clarifier and sludge transfer scrubber to achieve 99% odor reduction, with the remaining two scrubbers operating at 90% control. 4.3 Modeling Results Current 2013 Conditions Figures 7 and 8 show the Peak D/T and Odor Frequency contour maps for the current conditions scenario with odor control systems operating as designed. These model results use meteorological data from the Costa Mesa station based on recommendations from the South Coast Air Quality Management District. Figures 9 and 10 shows the model output using the meteorological data from the Mission Viejo station. Figures 7-10 clearly show a significant predicted odor impact on areas surrounding the CWRP. Not only are the predicted odor concentrations well above the target of 7 D/T, but the frequency of detectable odors is above the target of 100 hours per year. Comparison of the model outputs using 25

35 FIGURE 7 Predicted Peak Odor Levels Existing Conditions (Costa Mesa Met Data) 26

36 FIGURE 8 Predicted Odor Detection Frequency Existing Conditions (Costa Mesa Met Data) 27

37 FIGURE 9 Predicted Peak Odor Levels - Existing Conditions (Mission Viejo Met Data) 28

38 FIGURE 10 Predicted Odor Detection Frequency- Existing Conditions (Mission Viejo Met Data) 29

39 Costa Mesa meteorological data (Figures 7 and 8) vs. Mission Viejo data (Figures 9 and 10) shows only a minor difference in predicted odor impacts, with the Costa Mesa meteorological data having a slightly greater impact. The Costa Mesa data was used in all subsequent modeling. Figures 11 and 12 show the predicted odor impacts from the CWRP assuming that all four chemical scrubbers are upgraded to achieve 90% odor removal efficiency. This is well within the capabilities of packed tower scrubbers that use a combination of sodium hypochlorite (bleach) and sodium hydroxide (caustic soda). The exception to the 90% removal efficiency was the dewatering building scrubber, which is currently receiving such dilute odors that the outlet D/T was assumed to be 100. Even with improved performance of the scrubbers, predicted odor levels beyond the Chiquita WRP properly line still exceed the target 7 D/T in all locations. The odor impact from this scenario is again due largely to the primary clarifier scrubber that showed a measured inlet odor concentration of 29,000 D/T. Assuming 90 percent removal, the outlet odor remains a relatively high 2,900 D/T. Combined with the high air flow rate of 24,000 cfm, the odor emission rate is still greater than from all other sources combined. Figures 13 and 14 represent a scenario in which the primary clarifier scrubber is upgraded to achieve 99% odor reduction, and the sludge transfer scrubber exhaust is polished by the existing activated carbon adsorber. This would produce an outlet odor concentration of about 300 D/T from the primary clarifier scrubber, which is achievable by many chemical scrubber systems treating odor sources that are comprised mostly of hydrogen sulfide. It is difficult to predict whether this outlet odor level is achievable in the existing scrubber without adding a second polishing stage. The outlet from the combined scrubber-carbon system serving the sludge transfer processes is assumed to be 85 D/T, which is achievable. This scenario represents over 95% reduction in total odor emissions from the CWRP. Under this scenario, the odor impacts on Planning Area 2 are greatly reduced, and for the most part meet the target peak odor concentration of 7 D/T (Figure 13) and target odor detection frequency of <100 hours per year (Figure 14). Although there are still limited areas on the east and south borders of the plant where predicted peak odor levels exceed the target of 7 D/T, the frequency that these peak odors would be detectable is very low. With the assumption of very efficient odor control in the primary clarifier scrubber, the trickling filters become a more significant source of odor. 30

40 FIGURE 11 Predicted Peak Odor Levels - 90% Control in Scrubbers 31

41 FIGURE 12 Predicted Odor Detection Frequency- 90% Control in Scrubbers 32

42 FIGURE 13 Predicted Peak Odor Levels 99% Control in Primary Clarifier and Sludge Transfer Scrubbers 33

43 FIGURE 14 Predicted Odor Detection Frequency 99% Control in Primary Clarifier and Sludge Transfer Scrubbers 34

44 5. EVALUATION OF ODOR CONTROL ALTERNATIVES 5.1 San Juan and Ortega Lift Stations Because of the proximity of the lift stations to the first phase of development of Planning Area 1, as well as other Rancho Mission Viejo property, they are considered to be high priority for evaluation and control. San Juan LS This lift station is near the south entrance to Planning Area 1. Currently, the only odor control is upstream chemical addition (nitrate) at the Horno LS. Very little H 2 S was detected in the wet well of the San Juan LS during the March, 2013 monitoring. However, odor concentration was still quite high, and odorous air can escape around hatches, pipe penetrations, etc. The steeply-sloped 18-inch HDPE sewer approaching the lift station is contributing to the pressurization of the wet well headspace and the escape of odorous air. Under worst-case conditions, this pipe could contribute as much as 700 cfm of air to the wet well. This is due to the friction between the flowing wastewater and the air above it that drags the air down the pipe. Average velocity of the air is typically about one third the velocity of the sewage. Escape of odorous air can be prevented by evacuating enough air to maintain a slight negative pressure in the wet well. This air would require treatment prior to release to the atmosphere. Based on the low H 2 S levels, an activated carbon adsorber would be an appropriate odor control technology for this application. The process is very simple and reliable, and with the low H 2 S loadings, a media life of at least two years is anticipated. A biofilter is also feasible, but will have greater capital and O & M costs. Performance would be equivalent. A carbon adsorber has been conservatively sized for an air flow rate of 1,000 cfm. This estimate accounts for the contribution of air from the inlet sewer. Table 5 provides a breakdown of estimated 35

45 TABLE 5 ESTIMATED COST OF 1,000 CFM ACTIVATED CARBON ODOR CONTROL SYSTEM FOR SAN JUAN LIFT STATION Item Estimated Cost 1. 6 ft diam adsorber with fan, carbon media, control panel $46, Sound enclosure for fan 8, Pre-filter 5, Ductwork 15,000 Subtotal $64,000 30% 19,200 $83,200 Engineering & 35% 29,100 TOTAL $112,300 36

46 costs for an activated carbon odor control system to treat the air from the San Juan LS wet well. The SMWD is considering an oxygen injection system at the Horno LS to replace the chemical addition system. In the experience of Bowker & Associates, a properly designed oxygen injection system will provide more reliable and consistent control of hydrogen sulfide, and will provide long-term economic benefits in reduced O & M costs. Ortega LS The Ortega LS has historically been a source of odors, due largely to the long force main from the Talega LS. Although a 300 cfm biofilter was installed at Ortega to treat the air from the wet well, the organic media is exhausted and needs to be replaced. H 2 S data collected by the Odalog datalogger showed several significant spikes of H 2 S (> 300 ppm) during morning hours, with no H 2 S detected during the vast majority of the day. This may indicate that the upstream oxygenation system is not providing enough oxygen to prevent sulfide generation during low-flow periods when detention times in the force main can exceed 12 hours. However, the current injection rate is approximately 150 L/min, and the capacity is reported to be 280 L/min. Thus, it would appear that the system has sufficient capacity to bring H 2 S levels down to zero during all times of the day. With the optimization of the upstream oxygen injection system to consistently control sulfide, and the change-out of the biofilter media, odors from the Ortega LS should be adequately controlled. 5.2 Chiquita Water Reclamation Plant In order to prevent odors from the Chiquita WRP from impacting new development planned for east and north of the facility, it will be necessary to either upgrade the existing chemical scrubbers to achieve higher odor removal efficiency, or replace the scrubbers with new, more operator-friendly odor control systems. Given the age of the existing scrubbers, upgrading the scrubbers to use sodium hypochlorite (bleach) to improve performance is considered an interim solution until the odor control recommendations in the 2009 Master Plan are implemented. The schedule for 37

Corrosion and Odor Control in Wastewater Systems

Corrosion and Odor Control in Wastewater Systems Corrosion and Odor Control in Wastewater Systems Topics to be covered Hydrogen Sulfide Formation and Consequences What has changed since the Clean Water Act Corrosion in Wastewater systems Liquid Phase

More information

The Latest in Odor Control Issues and Solutions

The Latest in Odor Control Issues and Solutions The Latest in Odor Control Issues and Solutions FWEA Air Quality Seminar Feb 2017 Philip Wolstenholme, P.E. 1 Agenda Vapor Phase Technologies Comparison of Technologies Collect before Treating Dispersion

More information

Chapter 2: Description of Treatment Facilities

Chapter 2: Description of Treatment Facilities 2020 Facilities Plan Treatment Report 2.1 Introduction Chapter 2: Description of Treatment Facilities This chapter defines the Milwaukee Metropolitan Sewerage District (MMSD) service area. It also describes

More information

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W Facility Overview The recently upgraded and expanded Henry N. Wochholz Regional Water Reclamation Facility (WRWRF) treats domestic wastewater generated from the Yucaipa-Calimesa service area. The WRWRF

More information

Odor Threshold Emission Factors for Common WWTP Processes

Odor Threshold Emission Factors for Common WWTP Processes Odor Threshold Emission Factors for Common WWTP Processes Authored by: Michael A. McGinley, P.E. St. Croix Sensory, Inc. And Charles M. McGinley, P.E. St. Croix Sensory, Inc. Presented at Water Environment

More information

Comparison of Methods Used to Measure Odour at Wastewater Treatment Plant Fencelines

Comparison of Methods Used to Measure Odour at Wastewater Treatment Plant Fencelines Comparison of Methods Used to Measure Odour at Wastewater Treatment Plant Fencelines Jay R. Witherspoon and Jennifer L. Barnes CH2M HILL, Inc. 777 108 th Avenue NE, Suite 800 Bellevue, WA, USA 98004-5118

More information

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND Brett T. Messner, PE, Tetra Tech, Inc., 201 E Pine St, Suite 1000, Orlando, FL 32801 Brett.Messner@tetratech.com, Ph: 239-851-1225 Fred

More information

West County Treatment Plant Noise and Odor Control Project Update. June 29, 2004

West County Treatment Plant Noise and Odor Control Project Update. June 29, 2004 West County Treatment Plant Noise and Odor Control Project Update June 29, 2004 West County Meeting Purpose 1. Brief history of odor and noise control project 2. Describe odor and noise control systems

More information

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Wastewater Treatment Plant Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Water Utility March 22, 2016 WWTP Service Area Overview Population: 110,000 Service

More information

CHAPTER 1 - WASTEWATER SYSTEM DESCRIPTION

CHAPTER 1 - WASTEWATER SYSTEM DESCRIPTION CHAPTER 1 - WASTEWATER SYSTEM DESCRIPTION 1.1 Introduction The GWA provides wastewater services for Guam s general population and for Andersen Air Force Base. The wastewater system is made up of seven

More information

Providing Infrastructure Redundancy at the Rocky River WWTP. Timothy McCann AECOM Keith Bovard Rocky River WWTP

Providing Infrastructure Redundancy at the Rocky River WWTP. Timothy McCann AECOM Keith Bovard Rocky River WWTP Timothy McCann AECOM Keith Bovard Rocky River WWTP WWTP Infrastructure Redundancy Redundancy As NASA Would Say: A Backup Plan for the Backup Plan Nuclear Power Plant Wastewater Treatment Plant Page 3 Infrastructure

More information

Primary Clarifier Odor Control Replacing Nitrates with D.O. Kevin Jacobs, P.E. ECO Oxygen Technologies

Primary Clarifier Odor Control Replacing Nitrates with D.O. Kevin Jacobs, P.E. ECO Oxygen Technologies Primary Clarifier Odor Control Replacing Nitrates with D.O. Kevin Jacobs, P.E. ECO Oxygen Technologies Presentation Outline Primary Clarifier Odor Challenges Odor Treatment Options Case Study Anson-Madison

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY

FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY Ahmed El-Zayat, Environmental Engineering Group, Egypt Emaill: ahmed_el_zayat@yahoo.com Introduction This case study focuses on three

More information

CITY OF FORT MYERS CENTRAL ADVANCED WASTEWATER TREATMENT FACILITY

CITY OF FORT MYERS CENTRAL ADVANCED WASTEWATER TREATMENT FACILITY CITY OF FORT MYERS CENTRAL ADVANCED WASTEWATER TREATMENT FACILITY RAW SEWAGE Raw sewage is the water that flows into a wastewater treatment facility. It is made up of waste from toilets, sinks, garbage

More information

November 28, Dear Mr. Bechtold:

November 28, Dear Mr. Bechtold: 4000 Hollywood Boulevard Seventh Floor, North Tower Hollywood, Florida 33021 (954) 987-0066 Fax: (954) 987-2949 November 28, 2012 Wastewater Compliance and Enforcement Section FLORIDA DEPARTMENT OF ENVIRONMENTAL

More information

WWTF Capacity Assessment Project

WWTF Capacity Assessment Project Wastewater Treatment Facility Evaluation The Richland WWTF was constructed in 1985 to provide primary and secondary treatment for the City's wastewater. Section 3 includes a general description of the

More information

CEDAR CREEK Wastewater Treatment Facility

CEDAR CREEK Wastewater Treatment Facility CEDAR CREEK Wastewater Treatment Facility Where does the waste originate Private homes Businesses from? Condominium complexes Nursing homes Apartments ANY DWELING THAT USES WATER AND IS CONNECTED TO THE

More information

A COMPARISON OF ODOR AND HYDROGEN SULFIDE EMISSIONS FROM TWO METROPOLITAN WASTEWATER TREATMENT PLANTS

A COMPARISON OF ODOR AND HYDROGEN SULFIDE EMISSIONS FROM TWO METROPOLITAN WASTEWATER TREATMENT PLANTS A COMPARISON OF ODOR AND HYDROGEN SULFIDE EMISSIONS FROM TWO METROPOLITAN WASTEWATER TREATMENT PLANTS Chester M. Morton, P.E., BCEE, Phyllis Diosey QEP, Richard J. Pope, P.E., BCEE, Malcolm Pirnie, Inc.

More information

HYDROGEN SULFIDE INDUCED CONCRETE CORROSION

HYDROGEN SULFIDE INDUCED CONCRETE CORROSION HYDROGEN SULFIDE INDUCED CONCRETE CORROSION Presented by Tim Matheis Monday, October 19, 2015 2014 Evoqua Water Technologies LLC Outline Background Objectives Methods Data Results 2014 Evoqua Water Technologies

More information

USE OF CHEMICALS TO CONTROL ODORS AND CORROSION IN WASTEWATER SYSTEMS

USE OF CHEMICALS TO CONTROL ODORS AND CORROSION IN WASTEWATER SYSTEMS USE OF CHEMICALS TO CONTROL ODORS AND CORROSION IN WASTEWATER SYSTEMS By Robert P.G. Bowker, P.E. Bowker & Associates, Inc. Portland, Maine Florida Water Environment Association Air Quality Workshop February

More information

Polishing Ponds. Biosolids Storage. Ammonia Removal. Digesters. Thickeners. Pretreatment. Final Clarifiers. Primary Clarifiers.

Polishing Ponds. Biosolids Storage. Ammonia Removal. Digesters. Thickeners. Pretreatment. Final Clarifiers. Primary Clarifiers. Wastewater Treatment Facility (2012) Polishing Ponds Biosolids Storage Ammonia Removal Digesters Thickeners Pretreatment Primary Clarifiers Activated Sludge Final Clarifiers OVERVIEW Whenever a home, business,

More information

Norwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation. Subject: Task 3 Existing Grit Removal System Assessment

Norwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation. Subject: Task 3 Existing Grit Removal System Assessment A Technical Memorandum Date: Project: Norwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation Subject: Task 3 Existing Grit Removal System Assessment This memorandum presents

More information

Thornton Sewer Plant Operations Manual -DRAFT-

Thornton Sewer Plant Operations Manual -DRAFT- Thornton Sewer Plant Operations Manual -DRAFT- February 2014 Prepared for: HOUSING AUTHORITY OF THE COUNTY OF SAN JOAQUIN P.O. BOX 447 421 S. EL DORADO STREET STOCKTON, CA 95203 Prepared by: BLACK WATER

More information

Wastewater Treatment Processes

Wastewater Treatment Processes Wastewater Treatment Processes CEL212 Environmental Engineering (2 nd Semester 2010-2011) Dr. Arun Kumar (arunku@civil.iitd.ac.in) Department of Civil Engineering Indian Institute of Technology (Delhi)

More information

Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project

Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project Prepared By: Curt Czarnecki, P.E. Kenosha Water Utility Presented By: Joseph Hughes, P.E. Centrisys Corporation MIWEA June

More information

Appendix D JWPCP Background and NDN

Appendix D JWPCP Background and NDN Appendix D JWPCP Background and NDN JWPCP Background JWPCP Water Quality Primary Clarifiers HPO Reactors Final Clarifiers Unit Influent Primary Effluent Secondary Effluent BOD mg/l 460 240

More information

Anaerobic Digester Optimization with Bio-Organic Catalyst. NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08

Anaerobic Digester Optimization with Bio-Organic Catalyst. NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08 Anaerobic Digester Optimization with Bio-Organic Catalyst NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08 Municipal Anaerobic Digester Optimization Program Index! Overview

More information

New York State Department of Environmental Conservation

New York State Department of Environmental Conservation May 2012 New York State Department of Environmental Conservation Award Submission for Environmental Excellence Awards Port Washington Water Pollution Control District (PWWPCD) Submitted by D&B Engineers

More information

Minnesota Pollution Control Agency

Minnesota Pollution Control Agency Minnesota Pollution Control Agency STATE OF MINNESOTA Minnesota Pollution Control Agency MUNICIPAL DIVISION PUBLIC NOTICE OF INTENT TO REISSUE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES)/ STATE

More information

Is Oxygen Injection the Solution for Your Collection System Odors and Corrosion?

Is Oxygen Injection the Solution for Your Collection System Odors and Corrosion? Is Oxygen Injection the Solution for Your Collection System Odors and Corrosion? An Investigation into Current Applications and Industry Trends of Oxygen Injection for a Central Texas Municipality. Melissa

More information

CHAPTER 10 PRELIMINARY TREATMENT

CHAPTER 10 PRELIMINARY TREATMENT CHAPTER 10 PRELIMINARY TREATMENT TM 5-814-3/AFM 88-11, Volume III 10-1. General considerations. Preliminary treatment of wastewater includes screening, grinding, grit removal, flotation, equilization,

More information

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100 MEMO To: Jeff Pelz (West Yost) Kathryn Gies (West Yost) Copies: Mark Hildebrand (NCA) ARCADIS U.S., Inc. 200 Harvard Mills Square Suite 430 Wakefield Massachusetts 01880 Tel 781 224 4488 Fax 781 224 3033

More information

Comparison of Two Dispersion Models: A Bulk Petroleum Storage Terminal Case Study

Comparison of Two Dispersion Models: A Bulk Petroleum Storage Terminal Case Study Comparison of Two Dispersion Models: A Bulk Petroleum Storage Terminal Case Study Prepared By: Anthony J. Schroeder BREEZE SOFTWARE 12770 Merit Drive Suite 900 Dallas, TX 75251 +1 (972) 661-8881 breeze-software.com

More information

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017 Dealing with Unexpected Wastewater Treatment Plant Disruptions February 16, 2017 Location Map WPCP History Original WPCP constructed on this site in 1928 consisting of primary treatment and chlorination;

More information

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS:

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS: FACILITY: City of Redlands Wastewater Treatment Plant LOCATION: Redlands, CA GEO. AREA: Southern California STATUS 07/14: Operational CONSTRUCTION: ENGINEERING: Carollo Engineers; CH2M HILL MBR MANUFACTURER:

More information

Your Guide to the. Budd Inlet Treatment Plant

Your Guide to the. Budd Inlet Treatment Plant Your Guide to the Budd Inlet Treatment Plant How does LOTT know the plant is working correctly? All activity within the treatment plant is monitored 24 hours a day, 7 days a week. A highly trained team

More information

Need-to-Know Criteria Wastewater Treatment Operator Class III

Need-to-Know Criteria Wastewater Treatment Operator Class III 2017 Need-to-Know Criteria Wastewater Treatment Operator Class III A Need-to-Know Guide when preparing for the ABC Wastewater Treatment Operator Class III Certification Exam Before You Dive In What is

More information

Definition separation of unstable and destabilized suspended solids from a suspension by the force of gravity

Definition separation of unstable and destabilized suspended solids from a suspension by the force of gravity SEDIMENTATION-1 TEKNOLOGI PENGOLAHAN LIMBAH Definition separation of unstable and destabilized suspended solids from a suspension by the force of gravity 1 Applications in Wastewater Treatment grit removal

More information

Sanitary and Environmental Engineering I (4 th Year Civil)

Sanitary and Environmental Engineering I (4 th Year Civil) Sanitary and Environmental Engineering I (4 th Year Civil) Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University Wastewater Flow

More information

A H. Marcela Velázquez-Carrillo Consultant to Mountain Systems Inc. on the application of Proficy for Water Treatment

A H. Marcela Velázquez-Carrillo Consultant to Mountain Systems Inc. on the application of Proficy for Water Treatment WASTEWATER TREATMENT IINORMATIION TECHNOLOGY SUEZ, parent company of United Water ONDEO, is one of the largest water and wastewater treatment firms in the world. On January 5 th, 1998, United Water Milwaukee

More information

ATTACHMENT 1 GENERAL FACILITY INFORMATION. BOD5 mg/l mg/l TSS mg/l mg/l NH3-N mg/l mg/l

ATTACHMENT 1 GENERAL FACILITY INFORMATION. BOD5 mg/l mg/l TSS mg/l mg/l NH3-N mg/l mg/l ATTACHMENT 1 GENERAL FACILITY INFORMATION 1. Facility Name: 2. Type of Facility: 3. Population Served: Present: Design: 4. Flow: Average Maximum Peak 5. Water Quality: Present Design Assumed Actual Source:

More information

Watertown Wastewater Facility Plan. August 11, 2015

Watertown Wastewater Facility Plan. August 11, 2015 Watertown Wastewater Facility Plan August 11, 2015 Watertown Wastewater Wastewater Treatment Facility History Comprehensive Planning Wastewater Concerns Capacity Condition Permitting Requirements Watertown

More information

SPILL ESTIMATION. Not Just A Guess Anymore

SPILL ESTIMATION. Not Just A Guess Anymore SPILL ESTIMATION Not Just A Guess Anymore SPILL ESTIMATION Under current regulations accurate spill estimation has become critical to the operation and maintenance of a sanitary collection system Reporting

More information

AIR POLLUTION AND ENVIRONMENTAL CONSULTANCY

AIR POLLUTION AND ENVIRONMENTAL CONSULTANCY APPENDIX 5.5.2 ODOUR IMPACT OF EMISSIONS FROM THE WASTEWATER TREATMENT PLANT ---------- NEWMARKET CO-OPERATIVE CREAMERIES LTD. SCARTEEN LWR, NEWMARKET CO. CORK ---------- AIR POLLUTION AND ENVIRONMENTAL

More information

Calculating Aeration Flow and Pressure Requirements

Calculating Aeration Flow and Pressure Requirements Calculating Aeration Flow and Pressure Requirements Brought to you by: For your free subscription, please visit www.blowervacuumbestpractices.com/magazine/subscription. All rights are reserved. The contents

More information

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment OWEA 2013 Annual Conference June 19, 2013 Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment Jeff Lamson, Superintendent, WPCC Robert Hrusovsky,

More information

Need-to-Know Criteria Wastewater Treatment Operator Class II

Need-to-Know Criteria Wastewater Treatment Operator Class II 2017 Need-to-Know Criteria Wastewater Treatment Operator Class II A Need-to-Know Guide when preparing for the ABC Wastewater Treatment Operator Class II Certification Exam Before You Dive In What is ABC

More information

Biosolids EMS Internal Audit Report

Biosolids EMS Internal Audit Report Biosolids EMS Internal Audit Report Camden County Municipal Utilities Authority Camden, New Jersey Audit Report Date: January 14, 2014 Audit Conducted by: Douglas Burns, Chief Accountant, CCMUA Chris Waldron,

More information

CITY OF ALBANY BIOSOLIDS MANAGEMENT PROGRAM DEQ/EPA ANNUAL REPORT 2009

CITY OF ALBANY BIOSOLIDS MANAGEMENT PROGRAM DEQ/EPA ANNUAL REPORT 2009 CITY OF ALBANY BIOSOLIDS MANAGEMENT PROGRAM DEQ/EPA ANNUAL REPORT 2009 I. Background/General A. Facility: Albany-Millersburg Water Reclamation Facility 405 Davidson Street, NE Albany, OR 97321 NPDES Permit

More information

Need-to-Know Criteria Wastewater Treatment Operator Class IV

Need-to-Know Criteria Wastewater Treatment Operator Class IV 2017 Need-to-Know Criteria Wastewater Treatment Operator Class IV A Need-to-Know Guide when preparing for the ABC Wastewater Treatment Operator Class IV Certification Exam Before You Dive In What is ABC

More information

Minnesota Pollution Control Agency

Minnesota Pollution Control Agency Minnesota Pollution Control Agency STATE OF MINNESOTA Minnesota Pollution Control Agency MUNICIPAL DIVISION PUBLIC NOTICE OF INTENT TO REISSUE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES)/ STATE

More information

AS-H Iso-Disc Cloth Media Filter

AS-H Iso-Disc Cloth Media Filter AS-H Iso-Disc Cloth Media Filter Tertiary filtration and final polishing of wastewaters in municipal and industrial applications Toby.Sedgwick@AlfaLaval.com Slide 2 Typical Performance Range Influent Average

More information

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier Bruce R. Johnson 1 *, Jennifer Phillips 2, Tim Bauer 3, Greg Smith 4, George Smith 5, John Sherlock 6

More information

The Use of Magnesium Hydroxide Slurry as a Safe and Cost Effective Solution for H 2 S Odor, Corrosion, and FOG in Sanitary Sewer Systems

The Use of Magnesium Hydroxide Slurry as a Safe and Cost Effective Solution for H 2 S Odor, Corrosion, and FOG in Sanitary Sewer Systems The Use of Magnesium Hydroxide Slurry as a Safe and Cost Effective Solution for H 2 S Odor, Corrosion, and FOG in Sanitary Sewer Systems Aileen Gibson, Product Development Manager, Martin Marietta Magnesia

More information

Lagoons Operation and Management in New Brunswick

Lagoons Operation and Management in New Brunswick Lagoons Operation and Management in New Brunswick Lagoons Provide secondary treatment to domestic wastewater by the action of bacteria stabilizing the organic matter in the wastewater. Benefits of lagoons:

More information

Chlorine Scrubbing: Conversion from Batch to Continuous. Brent Hardman, P.E. Powell Fabrication & Mfg., Inc.

Chlorine Scrubbing: Conversion from Batch to Continuous. Brent Hardman, P.E. Powell Fabrication & Mfg., Inc. Chlorine Scrubbing: Conversion from Batch to Continuous Brent Hardman, P.E. Powell Fabrication & Mfg., Inc. Powell Fabrication & Mfg., Inc. Since 1964 Sodium Hypochlorite production, Chlorine Scrubbing

More information

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT Matthew Valade, P.E. July 25, 2014 Barboe.pptx Presentation Outline Project Background Why Dewater Croton Residuals Offsite?

More information

INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS

INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS INTERIM GUIDE CRITERIA FOR AEROBIC BACTERIAL GENERATOR FOR INSERT INTO SEPTIC TANKS, GREASE INTERCEPTORS AND GREASE TRAPS IAPMO IGC 180-20023

More information

DELTA WASTEWATER TREATMENT PLANT UPGRADES

DELTA WASTEWATER TREATMENT PLANT UPGRADES Delta, Ohio Environmental and Electrical Engineering, Grant Administration Cost $2.6 million $3.2 million OWDA Loan 1,100 SF Admin Building Addition 0.725 MGD Average Daily Flow 1.5 MGD Peak Capacity Professional

More information

GHG Inventory Report February 2018 KENT COUNTY REGIONAL RESOURCE RECOVERY FACILITY 2017 GREENHOUSE GAS (GHG) EMISSION INVENTORY

GHG Inventory Report February 2018 KENT COUNTY REGIONAL RESOURCE RECOVERY FACILITY 2017 GREENHOUSE GAS (GHG) EMISSION INVENTORY KENT COUNTY REGIONAL RESOURCE RECOVERY FACILITY 2017 GREENHOUSE GAS (GHG) EMISSION INVENTORY FEBRUARY 2018 1 INTRODUCTION Greenhouse gases (GHG) are believed to contribute to the global warming phenomenon

More information

Brian Reed Brent Hayes

Brian Reed Brent Hayes Sewer Odor Control Dosing Station Tiffany Pump Station Assessment City of Garden Grove Sanitary District / Orange County Sanitation District Brian Reed Brent Hayes OCSD Collection Odor and Corrosion Control

More information

WATER POLLUTION CONTROL PLANT

WATER POLLUTION CONTROL PLANT WATER POLLUTION CONTROL PLANT Welcome to the Sunnyvale Water Pollution Control Plant For 60 years, Sunnyvale s Water Pollution Control Plant has worked tirelessly 24 hours a day and 7 days a week. Rain

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information

Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project

Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project Presented August 29 th, 2016 Function of IMKWWTP Treatment Facility History Reasons for Proposed Project Why Now? Modest

More information

Water Reclamation Facility Master Plan. Community Workshop November 14, 2016

Water Reclamation Facility Master Plan. Community Workshop November 14, 2016 Water Reclamation Facility Master Plan Community Workshop November 14, 2016 Presentation Overview Introduction Project Goals Project Background Recent and Upcoming Schedule WRF Program Overview Big Picture

More information

CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT

CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT FEBRUARY 2014 SUMMARY This annual report is in response

More information

EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION

EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION Jody B. Barksdale, P.E MWH; Juan R. Oquendo, P.E. MWH; Bruce A. Petrik, P.E. - MWH ABSTRACT. The threshold

More information

Sulaibiya world s largest membrane water reuse project

Sulaibiya world s largest membrane water reuse project Water Technologies & Solutions technical paper Sulaibiya world s largest membrane water reuse project background In May 2001, a consortium including Mohammed Abdulmohsin Al-Kharafi and Sons (The Kharafi

More information

Biofiltration is. The average odor. Treating Odor Emissions from Buildings Biofilters

Biofiltration is. The average odor. Treating Odor Emissions from Buildings Biofilters Biofiltration is an air-cleaning technology that uses microorganisms to break down gaseous contaminants and produce non-odorous end products. It is used successfully around the world for treating a wide

More information

Lowering The Total Cost Of Operation

Lowering The Total Cost Of Operation Lowering The Total Cost Of Operation The system removes more solids than conventional clarification, so filters can run longer between backwash cycles. Fewer backwash cycles means less backwash water,

More information

Liquid Phase Collection System Odor Control 101

Liquid Phase Collection System Odor Control 101 Liquid Phase Collection System Odor Control 101 Presented by Richard Finger Presentation Outline General System Considerations Treatment Technologies Air and Pure Oxygen Injection Oxidants Chlorine and

More information

p2m berlin GmbH Tubli Water Pollution Control Centre Expansion of Sewage Treatment Plant with First Sludge to Energy Concept in the Middle East

p2m berlin GmbH Tubli Water Pollution Control Centre Expansion of Sewage Treatment Plant with First Sludge to Energy Concept in the Middle East p2m berlin GmbH Tubli Water Pollution Control Centre Expansion of Sewage Treatment Plant with First Sludge to Energy Concept in the Middle East Berliner Wasserbetriebe Water Supply and Waste Water Disposal

More information

CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA

CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA A. EXISTING FACILITIES 1. Westtown-Chester Creek Plant Westtown Township acquired the Westtown-Chester Creek Treatment Plant (WCC Plant)

More information

Grit Collection & Classification Case Studies

Grit Collection & Classification Case Studies Grit Collection & Classification Case Studies OWEA 2010 Specialty Biosolids Specialty Workshop Brian F. McNamara, HRSD Definition of Grit Metcalf & Eddy 2 nd Edition 1979 grit, consisting of sand, gravel,

More information

Water and Wastewater Impact Fee Analysis Capital Improvement Plan City of Lockhart February 2017

Water and Wastewater Impact Fee Analysis Capital Improvement Plan City of Lockhart February 2017 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 ANALYSIS OF WATER & WASTEWATER SYSTEMS... 1 2.1 Present Water Demands... 1 2.2 Water Supply... 3 2.3 Water Treatment Plant... 4 2.4 Storage, High-Service Pumps,

More information

APPENDIX E: EXISTING FACILITIES DESCRIPTIONS AND DESIGN CRITERIA

APPENDIX E: EXISTING FACILITIES DESCRIPTIONS AND DESIGN CRITERIA Wastewater Treatment Plant Master Plan APPENDIX E: EXISTING FACILITIES DESCRIPTIONS AND DESIGN CRITERIA E THIS PAGE INTENTIONALLY LEFT BLANK. APPENDIX E - EXISTING FACILITIES DESCRIPTION AND DESIGN CRITERIA

More information

a) Biological Oxygen Demand b) Biology Oxygen Demand c) Biochemical Oxygen Demand d) Biomicrobics Oxygen Demand

a) Biological Oxygen Demand b) Biology Oxygen Demand c) Biochemical Oxygen Demand d) Biomicrobics Oxygen Demand Onsite Domestic Wastewater Treatment, Dispersal and Reuse Biosystems Engineering 532 Final Exam Fall 2008 Due by 4:00 p.m. Monday December 8, 2008 (either by email or hardcopy) Name Instructions: This

More information

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station City of St. Joseph, Missouri Hydraulic Analysis and Effluent Pump Station By Work Order No. 09-001 B&V Project 163509 May 20, 2010 Table of Contents 1.0 Executive Summary...1 2.0 Purpose of Study...2 3.0

More information

Pilot Testing and Evaluation of Three Filtration Technologies for the Eugene / Springfield Wastewater Treatment Plant

Pilot Testing and Evaluation of Three Filtration Technologies for the Eugene / Springfield Wastewater Treatment Plant Pilot Testing and Evaluation of Three Filtration Technologies for the Eugene / Springfield Wastewater Treatment Plant 2009 PNCWA Annual Conference Boise, ID September 15, 2009 By: Bill Bennett and Yan

More information

The City of Houston s Approach to Odor and Corrosion Management

The City of Houston s Approach to Odor and Corrosion Management The City of Houston s Approach to Odor and Corrosion Management August 5, 2015 Presented By: Jason A. Iken, Senior Assistant Director Introduction Houston at a Glance Wastewater Infrastructure Biosolids

More information

Screening, Definition: The unit involved is called a screen.

Screening, Definition: The unit involved is called a screen. Screening, Definition: Screening is a unit operation that separates materials in and/or on water (found in different sizes) from water and from entering water treatment facilities and mains. The unit involved

More information

Ellis Creek Water Recycling Facility, City of Petaluma

Ellis Creek Water Recycling Facility, City of Petaluma Ellis Creek Water Recycling Facility, City of Petaluma Historical Timeline Facility Treatment Processes / Flow Schematics Challenges of Wetlands Dechlorination Mode of Operation Benefits of Natural Dechlorination

More information

West Hernando County Sewer Master Plan SECTION 7.0 RECLAIMED WATER

West Hernando County Sewer Master Plan SECTION 7.0 RECLAIMED WATER SECTION 7.0 RECLAIMED WATER 7.1 Introduction The use of highly treated wastewater effluent, or reclaimed water, has expanded greatly in Florida over the past several decades. In particular, the use of

More information

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan 4 Capacity Analysis The capacity analysis used the calibrated dry weather and wet weather wastewater collection system model to evaluate

More information

Water Utility Science Water Math and Hydraulics 050. Name: Date:

Water Utility Science Water Math and Hydraulics 050. Name: Date: Water Utility Science Water Math and Hydraulics 050 Name: Date: Note: Please show all of your calculations for each problem no matter how simple the problem may seem. Please use the accompanying pieces

More information

SSO Reduction Program. WWTP Effluent Violation Corrective Actions

SSO Reduction Program. WWTP Effluent Violation Corrective Actions SSO Reduction Program WWTP Effluent Violation Corrective Actions Report to United States Environmental Protection Agency: SSO Reduction Program This page intentionally left blank i WWTP Effluent Violation

More information

Guide to the Santa Margarita Water District Records. No online items

Guide to the Santa Margarita Water District Records.  No online items http://oac.cdlib.org/findaid/ark:/13030/kt0n39q6rg No online items Processed by Cyndi Shein; machine-readable finding aid created by Cyndi Shein Special Collections and Archives The UCI Libraries P.O.

More information

Carbon Canyon Water Recycling Facility Title 22 Engineering Report

Carbon Canyon Water Recycling Facility Title 22 Engineering Report Carbon Canyon Water Recycling Facility Title 22 Engineering Report April 2014 Introduction Regulatory Requirements Inland Empire Utilities Agency Carbon Canyon Water Recycling Facility Title 22 Engineering

More information

City of Staples, Minnesota

City of Staples, Minnesota Wastewater Treatment Facility Plan November 2012 City of Staples, Minnesota Bolton & Menk kproject No. W13.104619 104619 TABLE OF CONTENTS SECTION 1 INTRODUCTION... 1-1 A. Purpose... 1-1 B. Background...

More information

PRODUCT BULLETIN DRUM SCRUBBER 100

PRODUCT BULLETIN DRUM SCRUBBER 100 DRUM SCRUBBER 100 The Purafil Drum Scrubber 100 (DS-100) is ideal for removal of odorous gases found at pump stations, lift stations, wet wells, force mains, and wastewater treatment plants. Recommended

More information

Wastewater Treatment Works... The Basics

Wastewater Treatment Works... The Basics United States EPA 833-F-98-002 Environmental Protection May 1998 Agency Office of Water (4204) Wastewater Treatment Works... The Basics O ne of the most common forms of pollution control in the United

More information

Air Lift Pumps (Grit Pump) ST-027

Air Lift Pumps (Grit Pump) ST-027 Air Lift Pumps (Grit Pump) ST-027 I. Grit removal facilities at Gilroy/Morgan Hill Plant. a. Aerated grit chambers and appurtenant equipment. 1. 2 grit tanks 2. Effective volume 47,713 Gal each. 3. Aeration

More information

OPERATOR CERTIFICATION EXAMINATION REGISTRATION PA Certification to Operate Water or Wastewater Systems PRINT CLEARLY

OPERATOR CERTIFICATION EXAMINATION REGISTRATION PA Certification to Operate Water or Wastewater Systems PRINT CLEARLY 3900-FM-BSDW0109 9/2012 COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION STATE BOARD FOR CERTIFICATION OF WATER AND WASTEWATER SYSTEMS OPERATORS OPERATOR CERTIFICATION EXAMINATION REGISTRATION

More information

MEASUREMENT OF ODOUR EMISSIONS FROM HOG OPERATIONS IN MANITOBA

MEASUREMENT OF ODOUR EMISSIONS FROM HOG OPERATIONS IN MANITOBA MEASUREMENT OF ODOUR EMISSIONS FROM HOG OPERATIONS IN MANITOBA Final Report Submitted to Manitoba Livestock Manure Management Initiative Inc. and Triple S Hog Manure Management Initiative by Q. Zhang 1

More information

Integrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant

Integrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant Integrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant City of Columbus Division of Water: Matt Steele CH2M HILL: Enoch Nicholson DRWP Source Water and Treatment DRWP Overview Current

More information

COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL

COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL Alvin C. Firmin CDM Jefferson Mill, 670 North Commercial Street Suite 201 Manchester, New Hampshire 03101 ABSTRACT Sequencing

More information

Liquid Stream Fundamentals: Grit Removal

Liquid Stream Fundamentals: Grit Removal FACT SHEET Liquid Stream Fundamentals: Grit Removal Grit removal is an essential component of the wastewater treatment process. Not only does the removal of grit help protect downstream equipment from

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING Question Bank CE2354 - ENVIRONMENTAL ENGINEERING - II Prepared By: Year: 3rd year Semester: 6th Semester R.THENMOZHI / A.P.Civil J.SHANMUGAPRIYA

More information