Project Update. Gas to Great Island Power Station

Size: px
Start display at page:

Download "Project Update. Gas to Great Island Power Station"

Transcription

1 Project Update Gas to Great Island Power Station

2 Introduction The Transmission System Operator, Gaslink, on behalf of Endesa Ireland Ltd., has requested Bord Gáis Networks to design for a new gas supply to the proposed Combined Cycle Gas Turbine (CCGT) Electricity Generating Plant at Great Island, County Wexford. This pipeline will comprise of a 46 kilometre spur line from the Cork Dublin Pipeline on the existing gas transmission network in County Kilkenny to a new Above Ground Installation (AGI) at Great Island Power Station in County Wexford with an intermediate AGI located centrally along the route. The aim of this brochure is to provide our stakeholders with an overview of the project, the expected timeframe, the environment and the construction/reinstatement methodologies. The Pipeline Routes The starting point of the proposed natural gas pipeline will be at an existing Bord Gáis Networks facility at Baunlusk approximately 6km south of Kilkenny City. This facility, known as an Above Ground Installation (AGI), is where the pipeline is brought to ground to facilitate operation and maintenance. At the outset, three route corridor options were identified and assessed. Figure 1 illustrates the route corridor options considered. Following in-depth routing studies and environmental investigations, Route Corridor B has been selected as the preferred option and a proposed route has been established within this corridor. Route B begins at Baunlusk AGI and travels southeast, primarily through agricultural land. It crosses the River Barrow Estuary and then runs southeast to the Great Island Power Station. As the route involves crossing the River Barrow, a suitable crossing point has been identified and thoroughly investigated. This will be subject to further investigations and an Environmental Appraisal. Of the three routes considered, Route Option B minimises risk to the environment during the construction phase and also represents the lowest risk option in terms of safety during pipeline construction. The pipeline will be constructed using 400mm diameter high-grade steel pipe, buried to a minimum depth of 1.2m below ground level. The main impact of the proposed pipeline will be during the construction phase; however this will be relatively short term. The only above ground development will occur at the three AGI sites. These will be landscaped to blend in with the surrounding environment. Figure 1. LIMERICK KILKENNY Baunlusk C B A Clonmel Carrick-on-Suir WATERFORD New Ross Great Island CORK Kinsale Head Gas Field ROUTE OPTIONS IDENTIFIED Route B (Preferred Option) Routes A and C Existing Pipelines

3 Consultation and Construction Community and Environment Public Consultation Prior to finalising the routes of any pipeline, Bord Gáis Networks undertakes a public consultation programme. This includes consultation with any stakeholders potentially affected by a pipeline project. In this case, stakeholders include individual landowners, agricultural groups, statutory bodies, environmental organisations, heritage groups and others. Developing and maintaining good relationships are necessary to the success of any Bord Gáis Networks project. Our aim is to be open and transparent in all our communications with the local communities located along the route of a pipeline. We act in a responsible manner and engage with those who may be impacted at each stage of the process so that concerns can be incorporated into our strategy, wherever possible. Bord Gáis Networks is committed to ensuring all works will be undertaken in a safe and environmentally responsible manner, in co-operation with the local community. Public Information Evenings were advertised in local media and held in October 2010 to give all stakeholders the opportunity to examine the route and discuss the scope of the proposed pipeline with the project team. If you require any further information,we have a dedicated Community Liaison Team who will be able to respond to any concerns of the local community. Environmental Protection As with all Bord Gáis Networks pipeline projects, a detailed Environmental Impact Assessment of the construction and maintenance of the pipeline will be carried out by consultants to assess potential impacts of the Great Island project. Any resulting mitigation measures will be implemented as required and every effort will be made to avoid any areas that are of particular environmental interest. Bord Gáis Networks is fully committed to environmental conservation and the protection of Irish heritage. An environmental engineer will be employed to oversee activities during the construction of the pipeline. Archaeology Bord Gáis Networks employs a team of archaeologists as part of all pipeline construction projects. A licensed archaeologist will monitor all topsoil stripping and potential areas of archaeological interest. Construction Activities The construction of the Gas to Great Island Power Station pipeline is expected to commence in Summer The pipeline is scheduled for completion in October 2013 with all major construction activities taking place in the Spring and Summer months. It should be noted that at certain locations along the route of the pipeline, the construction programme will be dictated by the need to minimise the environmental impact. Pipeline construction activities will be carried out by a suitably qualified contractor appointed by Bord Gáis Networks. The latest and least intrusive engineering methods will be used and the pipelines will be built, operated and maintained to the highest national and international safety standards. In general, the pipeline will be constructed using a spread technique. Prior to the commencement of construction, a surveyor will set out the centreline of the pipeline and stock-proof fencing will be erected on either side of the 36 metre working width. The removal of hedges, walls and fences at field boundaries will be kept to a minimum and flume pipes will be inserted in drains/ditches to avoid disrupting the water flow. An archaeologist will supervise topsoil stripping, which will be carried out using tracked machines and bulldozers.

4 Construction and Reinstatement The linepipe required for the pipeline will be stored at intervals along the route before being strung out along the spread. In order to minimise the amount of excavation required, the pipes will be bent or formed to suit the ground profile. The pipe sections will then be clamped together and welded. Once each weld has been radiographed and meets the specified standards, it will be coated with a polyethylene sleeve to prevent corrosion. The pipe sections are then lowered into the pre-excavated trench. The trench is then backfilled to subsoil level reusing the excavated material with compaction taking place at set intervals. Before bringing the pipeline into service, the pipe and components are subjected to rigorous testing in the field. Each stage of the construction process is overseen by qualified inspectors to ensure compliance with the engineering plans, codes, permit conditions, landowner agreements, and regulatory requirements. We would also like to emphasise that safety is our priority at all stages of pipeline construction. The construction process typically involves the following: Pre-Construction Construction Post-Construction - Environmental Impact Statement (EIS) - On-Farm Site Investigations - Liaising with Landowners - Wayleave Acquisitions - Identification of all stakeholders on the project - Communications in the form of meetings, brochures, public information meetings - Statutory Approvals - Fencing Off the Working Width - Top-Soil Stripping - Pipe Preparation - Trenching and Backfilling - Road and River Crossings - Drainage and Reinstatement - Pipeline Safety - Continued Liaison with Landowners and the Community Reinstatement Post construction, Bord Gáis Networks will retain a 14 metre wide permanent wayleave along the route of the pipeline. This will be monitored by regular helicopter fly-overs and occasional foot patrols. All ditch crossings will have a protective slab placed over the pipe. Following completion of the main pipe laying activities, all drains are fully replaced and reinstated. The working width is also fully reinstated, this includes picking stones, levelling the topsoil, spreading, tilling and sowing the topsoil. Once reinstatement is completed there should be little or no evidence to show that the pipeline passed through.

5 Pipeline Statistics Pipeline Length: Pipeline Diameter: 46 km 400mm (16 inch) Construction Timeline: Construction to commence during Summer 2012 Planned completion in October 2013 (Omitting the Winter Season) Pipeline Material: Pipeline Design Pressure: Numbers Employed: Number of Wayleaves Along Route Number of Crossings* 400mm (16 inch) Steel to EN bar G Approximately 150 during peak construction season 140 approximately 50 in Total: 3 national roads or motorway 31 minor roads 3 rail 13 rivers and water courses Land Reinstatement: Scheduled for 2012/2013 (this can be dependent on weather conditions) Organisations Consulted Include: Kilkenny County Council Wexford County Council Environmental Protection Agency Farming Organisations Waterford and New Ross Ports National Parks & Wildlife Service Heritage Council Inland Fisheries Ireland * Based on the preferred route corridor

6 Further Information There is a dedicated phone line and address for queries or comments about the proposed construction works. If the query cannot be answered straight away, then a member of the project team will get back to you as quickly as possible. Bord Gáis Networks is committed to ensuring all works will be undertaken in a safe and environmentally responsible manner, in co-operation with the local community. Our Community Liaison Team are there to respond to any concerns of the local community. Phone: Post: (9am 5pm) greatislandccgt@bge.ie Community Liaison Officer, Gas to Great Island Project, Bord Gáis Networks, Gasworks Road, Cork Website: 100% 25724/9/2011

Code of Practice between Bord Gáis Éireann and The Minister for Arts, Heritage, Gaeltacht and the Islands

Code of Practice between Bord Gáis Éireann and The Minister for Arts, Heritage, Gaeltacht and the Islands bord gais english pdf 10/5/02 1:11 pm Page 1 Code of Practice between Bord Gáis Éireann and The Minister for Arts, Heritage, Gaeltacht and the Islands bord gais english pdf 10/5/02 1:11 pm Page 2 1 Foreword

More information

Factors in Infrastructural Planning / Implementation. Evening lecture for Project Management Society

Factors in Infrastructural Planning / Implementation. Evening lecture for Project Management Society Evening lecture for Project Management Society Developing Sensitive Infrastructural Projects while Managing Media and Stakeholder Issues Thursday, 10 th January, 2008 Presented by P. J. Rudden B.E., Eur.

More information

Construction of Dariali HEPP. Reinstatement Plan

Construction of Dariali HEPP. Reinstatement Plan Construction of Dariali HEPP Reinstatement Plan 2016 Table of Content 1. Introduction... 3 2. Site Clean-up... 4 3. Headwork Site Reinstatement... 4 4. Reinstatement Of The Pipeline Corridor.9 5. Cable

More information

Stage 4 Geotechnical Investigations Information Sheet

Stage 4 Geotechnical Investigations Information Sheet Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical

More information

Abstract. Environmental Impact Statement (EIS) Scoping Report

Abstract. Environmental Impact Statement (EIS) Scoping Report Abstract On 1 st January 2014, Irish Water assumed responsibility for managing Ireland s water and wastewater investment and maintenance programmes. On that date, Irish Water also took over the management

More information

Project Information Note The Gas Pipeline

Project Information Note The Gas Pipeline Knottingley Power Project Project Information ote The Gas Pipeline Introduction The CCGT power plant will be fuelled by a supply of natural gas. The supply of natural gas will be taken from a new underground

More information

Mustang Pipeline. Project Overview

Mustang Pipeline. Project Overview Project Overview New Pipeline Being Constructed in Your Area Overview Tulsa-based ONEOK Partners, a subsidiary of ONEOK, Inc., is constructing a $33 million, approximately 22-mile natural gas pipeline

More information

Water Supply Project Eastern and Midlands Region. Preliminary Options Appraisal Report (POAR) Non Technical Summary

Water Supply Project Eastern and Midlands Region. Preliminary Options Appraisal Report (POAR) Non Technical Summary Water Supply Project Eastern and Midlands Region Preliminary Options Appraisal Report (POAR) Non Technical Summary November 2015 Background Irish Water s remit includes the delivery of a sustainable and

More information

The West East Link Main is a 125 million pipeline project that will carry water across the North West of England

The West East Link Main is a 125 million pipeline project that will carry water across the North West of England West East Link Main 55km pipeline, carrying 100 million litres, is one of the largest ever undertaken by a water company by Jon Higham The West East Link Main is a 125 million pipeline project that will

More information

Roadrunner Gas Transmission Pipeline. Project Overview

Roadrunner Gas Transmission Pipeline. Project Overview Roadrunner Gas Transmission Pipeline Project Overview New Pipeline Being Constructed in Your Area Overview Tulsa-based ONEOK Partners has entered into a 50-50 joint venture with a subsidiary of Fermaca

More information

PRESS KIT MEDIA CONTACT. Chris Stockton Office Number: Cell Number:

PRESS KIT MEDIA CONTACT. Chris Stockton   Office Number: Cell Number: PRESS KIT MEDIA CONTACT Chris Stockton Email: Christopher.L.Stockton@williams.com Office Number: 713-215-2010 Cell Number: 713-562-2939 ABOUT WILLIAMS Williams is a nearly 110-year-old energy company that

More information

Imperial s Sarnia Products Pipeline

Imperial s Sarnia Products Pipeline Imperial s Sarnia Products Pipeline Waterdown to Finch Project Community Information Session Imperial s Waterdown to Finch Project Important infrastructure to the Greater Toronto and Hamilton Area (GTHA).

More information

Pavement Asset Management Guidance Section 7: Reinstatements

Pavement Asset Management Guidance Section 7: Reinstatements Pavement Asset Management Guidance Section 7: Reinstatements December 2014 Document Information Title Author Description, Paul Hardy, exp consulting This section recommends that records should be kept

More information

Technical Standard for the Design of Forest Entrances from Public Roads

Technical Standard for the Design of Forest Entrances from Public Roads Technical Standard for the Design of Forest Entrances from Public Roads Contents Acknowledgements... 3 1) Introduction... 4 2) Forest Entrances from National Primary and National Secondary Routes... 5

More information

Chapter 13 Management and Monitoring

Chapter 13 Management and Monitoring Chapter 13 Management and Monitoring TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Construction Phase Roles and Responsibilities... 13-1 13.2.1 BP... 13-1 13.2.2

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

Chapter 13 Management and Implementation

Chapter 13 Management and Implementation Chapter 13 Management and Implementation TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Overview of AGT Region Operating Management System... 13-1 13.3 Construction

More information

Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity & Crossing Permit. Design and Construction Guidelines

Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity & Crossing Permit. Design and Construction Guidelines Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity & Crossing Permit Design and Construction Guidelines A Guide to Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity

More information

Welcome to the Lyrenacarriga Wind Farm public information event

Welcome to the Lyrenacarriga Wind Farm public information event Welcome to the Lyrenacarriga Wind Farm public information event Innogy Renewables Ireland Ltd (innogy) is investigating the potential for developing Lyrenacarriga Wind Farm in the vicinity of Lyrencarriga

More information

Gas to the West project update

Gas to the West project update Gas to the West project update Agenda Introductions Paddy Larkin The story so far Planning permission HP construction what s involved HP Construction Programme IP construction what s involved Danny O Malley

More information

Report on Archaeological Testing of Luas Line A1 Belgard to Saggart, Co.Dublin.

Report on Archaeological Testing of Luas Line A1 Belgard to Saggart, Co.Dublin. Project code: RPLT08 Client: Railway Procurement Agency Date: October, 2008. Report on Archaeological Testing of Luas Line A1 Belgard to Saggart, Co.Dublin. Director: Liam Hackett. Author : Liam Hackett.

More information

Reducing Third Party Damage to High. Policy Manager, Transmission

Reducing Third Party Damage to High. Policy Manager, Transmission Reducing Third Party Damage to High Pressure e Pipelines es Neil Jackson Policy Manager, Transmission Introduction Background Current measures to prevent third party interference What more can pipeline

More information

Mayo - Galway Gas Pipeline

Mayo - Galway Gas Pipeline Mayo - Galway Gas Pipeline Environmental Impact Statement Volume 1 - Main Text May2001 Job No. C689/10 EPA Export 13-02-2015:23:04:50 EPA Export 13-02-2015:23:04:50 TABLE OF CONTENTS (VOLUME 1) NON TECHNICAL

More information

Auckland Unitary Plan Operative in part 1

Auckland Unitary Plan Operative in part 1 Designation Schedule - New Zealand Refining Company Number Purpose 6500 Operation, maintenance and repair, upgrade and renewal of the existing petroleum transmission pipeline and ancillary facilities...

More information

THIRD ENERGY & MOORLAND CONSULTATION EVENT

THIRD ENERGY & MOORLAND CONSULTATION EVENT THIRD ENERGY & MOORLAND CONSULTATION EVENT WELCOME Welcome to the Third Energy & Moorland consultation event. This exhibition outlines our plans and proposals to install a pipeline to connect the existing

More information

MOUNTAINEER XPRESS. Columbia Pipeline Group

MOUNTAINEER XPRESS. Columbia Pipeline Group MOUNTAINEER XPRESS Columbia Pipeline Group C169566.indd 1 TABLE OF CONTENTS CPG AT A GLANCE THE PLAN/PROJECT COMPONENTS COMMITMENT TO KEEPING YOU INFORMED PROJECT BENEFITS SAFETY FREQUENTLY ASKED QUESTIONS

More information

SemCAMS Area Project Description

SemCAMS Area Project Description REGULATORY The Redwillow Pipeline Project involves crossing a provincial boundary, and therefore, approval for it will require the preparation of an application to the NEB. plans to proceed with the regulatory

More information

For inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:33:57

For inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:33:57 EPA Export 11-02-2014:23:33:57 P03/3343 CORRIB GAS FIELD DEVELOPMENT Prepared in respect of the proposed Bellanaboy Bridge Gas Terminal and associated Srahmore Peat Deposition Site RESPONSE TO REQUEST

More information

Corrib Onshore Pipeline

Corrib Onshore Pipeline Case Study: Corrib Onshore Pipeline Ciarán Butler Engineers Ireland Permitting of Energy Projects Seminar Engineers Ireland Permitting of Energy Projects Seminar 20 th October, 2014 20 th October, 2014

More information

Engineers Ireland. Permitting of Energy Projects. Shannon LNG

Engineers Ireland. Permitting of Energy Projects. Shannon LNG Engineers Ireland Permitting of Energy Projects Shannon LNG October 2014 Martin Ahern 0 What is LNG LNG is natural gas that has been cooled to -160 o C at which point it condenses to a liquid LNG s volume

More information

Mercia EnviRecover PROPOSED DEVELOPMENT OF A RENEWABLE ENERGY PLANT ON LAND AT HARTLEBURY TRADING ESTATE, HARTLEBURY, WORCESTERSHIRE

Mercia EnviRecover PROPOSED DEVELOPMENT OF A RENEWABLE ENERGY PLANT ON LAND AT HARTLEBURY TRADING ESTATE, HARTLEBURY, WORCESTERSHIRE Mercia EnviRecover PROPOSED DEVELOPMENT OF A RENEWABLE ENERGY PLANT ON LAND AT HARTLEBURY TRADING ESTATE, HARTLEBURY, WORCESTERSHIRE Environmental Statement Regulation 19 Submission (3a) Other Information

More information

City of Green Construction Update

City of Green Construction Update NEXUS Gas Transmission City of Green Construction Update February 16, 2018 Project Overview Nexus Market Connections Project Summary: Design Capacity: 1.5 Bcf/d New: 257 miles of 36 pipe and 4 compressor

More information

SPECIAL STUDY AREA PLAN (SSAP) 1: FIRTH OF FORTH SPA

SPECIAL STUDY AREA PLAN (SSAP) 1: FIRTH OF FORTH SPA SPECIAL STUDY AREA PLAN (SSAP) 1: FIRTH OF FORTH SPA 1 INTRODUCTION The Firth of Forth is classified as a Special Protection Area (SPA) because it qualifies under Article 4.1 of the Birds Directive by

More information

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION HIGH SPEED TWO INFORMATION PAPER E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION This paper outlines the framework for the control and management of traffic associated with the construction of the Proposed

More information

Canadian Solar Developers Ltd.

Canadian Solar Developers Ltd. Canadian Solar Developers Ltd. Type of Document Draft Report Project Name Proposed Ground Mount Solar Facility L.P #5 8338 Scotchmere Drive, Strathroy, ON OPA FIT Program: FIT-FL67GB5 Project Number V00002250-00

More information

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT Welcome Eggborough Power Ltd (EPL) is proposing to develop a new gas-fired power station on the site of its existing coal-fired

More information

Appendix D Construction Phase ESMMP Amendments

Appendix D Construction Phase ESMMP Amendments Appendix D Construction Phase ESMMP Amendments TABLE OF CONTENTS SCP Expansion Project, Azerbaijan 1 INTRODUCTION... 1 2 AMENDMENTS TO THE MANAGEMENT PLANS... 2 Tables Table 1: SCPX ESMMP Amendment Register...

More information

Kobe Pumping Plant and Pipeline Project Narrative UPDATED 6/28/13

Kobe Pumping Plant and Pipeline Project Narrative UPDATED 6/28/13 Kobe Pumping Plant and Pipeline Project Narrative UPDATED 6/28/13 Introduction/Background The Kobe Pumping Plant and Pipeline (the Project ) is located in Mesa and Garfield Counties near DeBeque, Colorado.

More information

Consent of copyright owner required for any other use. For inspection purposes only.

Consent of copyright owner required for any other use. For inspection purposes only. 12.0 WASTE MANAGEMENT EU Legislation such as: This section addresses the subject of waste management for the proposed installation of a new dryer and evaporator at Lakeland Dairies Co-operative Society

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

Draft Noise Action Plan Consultation Issue Aug 09

Draft Noise Action Plan Consultation Issue Aug 09 Draft Noise Action Plan 2008 Consultation Issue Aug 09 KILKENNY COUNTY COUNCIL COUNTY HALL JOHN STREET KILKENNY KILKENNY BOROUGH COUNCIL CITY HALL HIGH STREET KILKENNY EXECUTIVE SUMMARY...v 1 Introduction...6

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

Keeping your water flowing How we maintain our mains network

Keeping your water flowing How we maintain our mains network Keeping your water flowing How we maintain our mains network Keeping your water flowing Planning for mains Maintenance and replacement of our water supply network can cause disruption to our customers

More information

5. The role of the Project Archaeologist and the Code of Practice Ken Hanley

5. The role of the Project Archaeologist and the Code of Practice Ken Hanley 5. The role of the Project Archaeologist and the Code of Practice Ken Hanley Aerial view of extensive test trenching on the N22 Ballincollig Bypass (Cork County Council National Roads Design Office) Introduction

More information

COMBINED CONCRETE SIDEWALK AND RETAINING WALL. Comply with Division 1 - General Provisions and Covenants, as well as the following:

COMBINED CONCRETE SIDEWALK AND RETAINING WALL. Comply with Division 1 - General Provisions and Covenants, as well as the following: SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9072 - Combined Concrete Sidewalk and Retaining Wall PART 1 - GENERAL 1.01 SECTION INCLUDES COMBINED CONCRETE SIDEWALK AND RETAINING

More information

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2 Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2 PARTICULAR SPECIFICATIONS FOR THE CONSTRUCITON OF STORM WATER DRAINAGE NETWORK March 2018 BUREAU TECHNIQUE POUR LE DEVELOPPEMENT P.O.B

More information

Special Provision No. 405F03 March 2005

Special Provision No. 405F03 March 2005 PIPE SUBDRAINS - Item No. VIDEO CAMERA INSPECTION Item No. Special Provision No. 405F03 March 2005 OPSS 405, February 1990, Construction Specification for Pipe Subdrains is deleted in its entirety and

More information

Imperial s Sarnia Products Pipeline. Waterdown to Finch Project

Imperial s Sarnia Products Pipeline. Waterdown to Finch Project Imperial s Sarnia Products Pipeline Waterdown to Finch Project Safety and reliability: pipeline replacement from Waterdown to Finch Imperial s Sarnia Products Pipeline is important infrastructure that

More information

Installation Guide BLUE904 PEX MUNICIPAL WATER SERVICE TUBING. We Build Tough Products for Tough Environments

Installation Guide BLUE904 PEX MUNICIPAL WATER SERVICE TUBING. We Build Tough Products for Tough Environments Installation Guide BLUE904 PEX MUNICIPAL WATER SERVICE TUBING W A T E R S E R V I C E T U B I N G We Build Tough Products for Tough Environments Blue904 Installation Guide 1 TABLE OF CONTENTS Introduction...................................2

More information

WASTEWATER REVIEW CHECKLIST. Project Number: Reviewed By: Telephone:

WASTEWATER REVIEW CHECKLIST. Project Number: Reviewed By: Telephone: The City of East Point DEPARTMENT OF WATER AND SEWER 1526 East Forrest Ave. Suite 400 East Point, Georgia 30344 FAX (404) 270-7215 www.eastpointcity.org WASTEWATER REVIEW CHECKLIST Project Name: Tax ID

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

GREATER DUBLIN DRAINAGE PROJECT: PUBLIC CONSULTATION REPORT ON THE ISSUES TO BE CONSIDERED IN THE ENVIRONMENTAL IMPACT STATEMENT

GREATER DUBLIN DRAINAGE PROJECT: PUBLIC CONSULTATION REPORT ON THE ISSUES TO BE CONSIDERED IN THE ENVIRONMENTAL IMPACT STATEMENT GREATER DUBLIN DRAINAGE PROJECT: PUBLIC CONSULTATION REPORT ON THE ISSUES TO BE CONSIDERED IN THE ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY DECEMBER 2013 EXECUTIVE SUMMARY 1. PROJECT BACKGROUND

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GETCO/E/TS LUC058/R1

More information

C231 Subsoil and Foundation Drains

C231 Subsoil and Foundation Drains CONSTRUCTION SPECIFICATION FOR DEVELOPMENTS AND SUBDIVISIONS C231 Subsoil and Foundation Drains Tamworth Regional Council Page :1 TABLE OF CONTENTS CLAUSE CONTENTS PAGE ORIGIN OF DOCUMENT, COPYRIGHT...

More information

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction 2.7 Generic Mitigation Measures 2.7.1 Avifauna CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction Vehicles and machinery can impact on natural vegetation

More information

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE 378-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION 378 - POND I. SCOPE The work shall consist of constructing an earthfill embankment and appurtenances to the lines, grades,

More information

Route Selection and Alternatives Considered

Route Selection and Alternatives Considered Route Selection and Ciarán Butler BE, MEngSc, CEng, MIEI 1. My name is Ciarán Butler and I am a Technical Director in RPS Consulting Engineers. I have been with RPS since 1996 and I manage the Energy Section

More information

Development & Delivery of a Pilot Training Programme for Construction Operatives to NVQ Level 2 Standard

Development & Delivery of a Pilot Training Programme for Construction Operatives to NVQ Level 2 Standard Development & Delivery of a Pilot Training Programme for Construction Operatives to NVQ Level 2 Standard 1. Introduction CITB NI intends to deliver a Pilot Programme to train General Construction Operatives

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02315-1 PART 1 GENERAL 1.1 Description of Work.1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. 1.2 Related

More information

Native Title Act 1993

Native Title Act 1993 APPENDIX A2: Regulatory approvals Table 1: Regulatory approvals Approval / permit type Commonwealth approvals Permission to intervene in matters where traditional cultural heritage interests are considered

More information

MAKING THE MOST OF WATER RESOURCES AS FEATURED IN AUSTRALIAN CONSTRUCTION FOCUS - JUNE 2012 EDITION

MAKING THE MOST OF WATER RESOURCES AS FEATURED IN AUSTRALIAN CONSTRUCTION FOCUS - JUNE 2012 EDITION MAKING THE MOST OF WATER RESOURCES AS FEATURED IN AUSTRALIAN CONSTRUCTION FOCUS - JUNE 2012 EDITION 2 JUNE ISSUE 2012 AUSTRALIAN CONSTRUCTION FOCUS 3 Making The Most Of Water Resources Mitchell Water Conserving

More information

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and TECHNICAL STANDARDS & SAFETY AUTHORITY 14 th Floor, Centre Tower 3300 Bloor Street West Toronto, Ontario Canada M8X 2X4 IN THE MATTER OF: THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16

More information

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES CITY OF SANTA MONICA Department of Public Works Civil Engineering Division 1685 Main, Room 116 Santa Monica, CA 90401 Tel: (310) 458-2240 or (310) 458-8737 EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL

More information

Charging Arrangements for New Connection Services

Charging Arrangements for New Connection Services Charging Arrangements for New Connection Services 2018-2019 About South East Water Developer Services Developer Services Department For any new connections requests or issues please contact our Developer

More information

CITY OF GARDEN PLAIN, KANSAS STANDARDS AND SPECIFICATIONS FOR GAS YARD LINES & METER SETS

CITY OF GARDEN PLAIN, KANSAS STANDARDS AND SPECIFICATIONS FOR GAS YARD LINES & METER SETS All gas yard lines shall be installed, repaired or replaced in accordance with the standards and specifications herein and in accordance with the rules and regulations as set forth in the city s OQ, and

More information

REVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL

REVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL 623.01 SUMMARY: GENERAL Section Includes: Landscape irrigation system as shown on the drawings for complete coverage to landscape areas. Furnish design for layout, pipe sizing, valving and head types and

More information

Chapter 10. Pipeline Installation

Chapter 10. Pipeline Installation Chapter 10 CHAPTER 10 STOCKWATER PIPELINE INSTALLATION TABLE OF CONTENTS PART 10.1 TRENCHING 10-1 10.1.1 Backhoe Constructed Trench 10-1 10.1.2 Trencher Constructed Trench 10-1 10.1.3 Backfilling and Maintenance

More information

SECTION 1208 CHAIN LINK FENCING DESCRIPTION

SECTION 1208 CHAIN LINK FENCING DESCRIPTION SECTION 1208 CHAIN LINK FENCING 1208-1 DESCRIPTION This item covers the requirements for furnishing materials and constructing new chain link fences and gates in accordance with the details included herein

More information

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate.

The compliance monitors are responsible for reviewing NEXUS s construction and documenting compliance with the FERC Certificate. FEDERAL ENERGY REGULATORY COMMISSION ENVIRONMENTAL COMPLIANCE MONITORING PROGRAM WEEKLY SUMMARY REPORT NEXUS GAS TRANSMISSION PROJECT DOCKET NO.: CP16-22-000 FOR THE PERIOD: NOVEMBER 13 THROUGH NOVEMBER

More information

Piceance Basin Lateral Extension. Project Overview May 2008

Piceance Basin Lateral Extension. Project Overview May 2008 Piceance Basin Lateral Extension Project Overview May 2008 Overview Overland Pass Pipeline Company, L.L.C. is a joint-venture company owned 99 percent by ONEOK Partners and 1 percent by Williams Field

More information

SANKO GEOTHERMAL POWER PROJECT TRAFFIC MANAGEMENT PLAN

SANKO GEOTHERMAL POWER PROJECT TRAFFIC MANAGEMENT PLAN Draft A.0 January 10, 2018 Version Revision Date SANKO GEOTHERMAL POWER PROJECT Prepared by Checked by Approved by Muhsin Dervişoğulları Environmental Manager Project Manager General Manager of Geothermal

More information

HOW YOU NEED TO PLAN AND PREPARE FOR A SUCCESSFUL DEMOLITION PROJECT

HOW YOU NEED TO PLAN AND PREPARE FOR A SUCCESSFUL DEMOLITION PROJECT HOW YOU NEED TO PLAN AND PREPARE FOR A SUCCESSFUL DEMOLITION PROJECT GUIDANCE BRIEF FOR CLIENTS & ADMINSTRATORS CONSTRUCTION (DESIGN & MANAGEMENT) REGULATIONS 2007 This document has been produced to guide

More information

Lines of Communication. Our New Approach to Consultation - Have Your Say

Lines of Communication. Our New Approach to Consultation - Have Your Say Lines of Communication Our New Approach to Consultation - Have Your Say Who are EirGrid - and what do we do? What is this guide for? EirGrid is responsible for a safe, secure and reliable supply of electricity:

More information

GWINNETT COUNTY STORM SEWER PIPE STANDARDS

GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.0 Standard Specifications GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.1 Unless otherwise specifically set forth herein or in the Gwinnett County Standard Drawings, all of the materials, methods of the

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

NOVEMBER 2016 GRANDWALL. retaining walls installation guide NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining

More information

Following the November 2009 flood event Galway County Council and the OPW have been working together on the Ballinasloe flooding situation.

Following the November 2009 flood event Galway County Council and the OPW have been working together on the Ballinasloe flooding situation. Derrymullan, Ballinasloe Flood Defence Wall, Report October 2011 Following the November 2009 flood event Galway County Council and the OPW have been working together on the Ballinasloe flooding situation.

More information

THE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR RESTORATION

THE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR RESTORATION THE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR RESTORATION Standard Specifications for Restoration INDEX PAGE R.1 GENERAL...1 R.2 SCOPE...1 R.3 MATERIALS...1 R.4 CONSTRUCTION...2 R.4.1 General...2

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN CORRIB GAS PIPELINE ENVIRONMENTAL MANAGEMENT PLAN Status: Draft Date: July 2011 Document Reference : COR-14-OP-SH-0000 SHELL E & P IRELAND LTD Shell E&P Ireland Limited Environmental Management Plan TABLE

More information

COMPETITION NOTICE and JOB DESCRIPTION PLEASE READ CAREFULLY. OPEN Recruitment Competition for Fixed-Term (including Seasonal) positions as

COMPETITION NOTICE and JOB DESCRIPTION PLEASE READ CAREFULLY. OPEN Recruitment Competition for Fixed-Term (including Seasonal) positions as COMPETITION NOTICE and JOB DESCRIPTION PLEASE READ CAREFULLY OPEN Recruitment Competition for Fixed-Term (including Seasonal) positions as General Operative Band 2 / 360 0 Excavator Driver in the Office

More information

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS TABLE OF CONTENTS 11.01 SCOPE OF WORK... 1 11.02 REFERENCES... 1 11.03 MATERIALS... 2 11.04 GRANULAR & NATIVE BACKFILL... 2 11.05 CONSTRUCTION... 2 11.06 MEASUREMENT FOR PAYMENT... 5 11.07 BASIS OF PAYMENT...

More information

Cork Lower Harbour Main Drainage Project March 2017

Cork Lower Harbour Main Drainage Project March 2017 IW/BK/CLH/V3/0317 Cork Lower Harbour Main Drainage Project March 2017 If you have any questions or wish to register for updates you can contact the project team in the following ways: Post: Web: Email:

More information

Fiji Electricity Authority Transmission Unit 2 Marlow Street, Suva

Fiji Electricity Authority Transmission Unit 2 Marlow Street, Suva Access Roads Upgrade to 132kV Transmission Towers in Navala and Koro areas TENDER SPECIFICATION The (FEA) invites bids from reputable contractors for the upgrade of existing Access Roads to its Transmission

More information

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE Project Background As part of the Seaterra Program, Clover A new conveyance pipe (forcemain) Pump Station will be upgraded and will run

More information

Response to a Bridge Strike over the Railway

Response to a Bridge Strike over the Railway Response to a Bridge Strike over the Railway A Protocol for Highway and Road Managers, Police and Bridge Owners NR/GPG/CIV/007 Note This protocol has been produced for the benefit of Network Rail staff

More information

PLATIN PEAKER PLANT PROPOSAL

PLATIN PEAKER PLANT PROPOSAL PLATIN PEAKER PLANT PROPOSAL PUBLIC INFORMATION EVENT - 25 SEPTEMBER 2018 Thank you for coming to our information evening for SSE s proposed new peaker power generation plant at Platin, Carranstown, Duleek,

More information

Ag obair i gcomhpháirtíocht Irish Water

Ag obair i gcomhpháirtíocht Irish Water Irish Water All of our customers should receive a safe and reliable supply of drinking water and have their wastewater collected and safely returned to the environment. We will protect the environment

More information

National Highways Sector Schemes for Quality Management in Highway Works

National Highways Sector Schemes for Quality Management in Highway Works National Highways Sector Schemes for Quality Management in Highway Works SCHEME 0 GUIDE TO THE IDENTIFICATION, DEVELOPMENT, MANAGEMENT AND CERTIFICATION OF NATIONAL HIGHWAY SECTOR SCHEMES PART 1 INTRODUCTION

More information

Grant County Wind: Revised Decommissioning Plan

Grant County Wind: Revised Decommissioning Plan Grant County Wind: Revised Decommissioning Plan Roseville Township - Grant County, MN Initially Prepared by: Mr. Jeff Bendel Vice President of Construction, Juhl Wind August 1, 2010 Revised April 14, 2014

More information

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10.1 Objective The main objective is to confirm the implementation of mitigation measures recommended in

More information

Inveraray to Crossaig Overhead Line Reinforcement

Inveraray to Crossaig Overhead Line Reinforcement About Scottish Hydro Electric (SHE) Transmission plc Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the electricity networks in

More information

The PennEast Pipeline Project

The PennEast Pipeline Project The Project About the Project AGL Resources; NJR Pipeline Company; PSEG Power; South Jersey Industries; Spectra Energy and UGI Energy Services (UGIES) comprise Company, LLC. Over $1 billion investment

More information

The PennEast Pipeline Project

The PennEast Pipeline Project The Project About the Project AGL Resources; NJR Pipeline Company; PSEG Power; South Jersey Industries; Spectra Energy and UGI Energy Services (UGIES) comprise Company, LLC. Nearly $1 billion investment

More information

Cork Lower Harbour Main Drainage Project

Cork Lower Harbour Main Drainage Project Obair i gcomhpháirtíocht Working in partnership Cork Lower Harbour Main Drainage Project IW/CP/CLH/B/0414 1011337 IW-Cork-Drainage-Booklet-v7.indd 1 02/05/2014 16:14 If you have any questions or require

More information

The London to Fishguard Trunk Road (East of Magor to Castleton) Order 201-

The London to Fishguard Trunk Road (East of Magor to Castleton) Order 201- Proof of Evidence Construction Adran yr Economi a r Seilwaith Department for Economy and Infrastructure The M4 Motorway (Junction 23 (East of Magor) to West of Junction 29 (Castleton) and Connecting Roads)

More information