Annex 4. Technical Guideline

Size: px
Start display at page:

Download "Annex 4. Technical Guideline"

Transcription

1 Annex 4 Technical Guideline 1

2 Contents 1. Purpose of Technical Guideline 2. Scope of Feasibility Study 3. Socio-economic and social/natural environments survey 4. Topographical survey 4.1 Collection of existing topographical maps 4.2 Topographical survey and mapping for preliminary design 4.3 Longitudinal river profile survey 4.4 River cross-section survey 5. Meteorological/hydrological survey and analysis 5.1 Collection of existing meteorological/hydrological data 5.2 Meteorological/hydrological survey 5.3 Length of rainfall and river runoff data 5.4 Rationale and validation of selected rainfall and runoff data 5.5 Low flow analysis 5.6 Flood analysis 5.7 Backwater analysis of the reservoir during flood time 5.8 Hydraulic analysis during flood discharge and power discharge 5.9 Hydraulic analysis against landslide effect to reservoir 5.10 Reservoir evaporation 5.11 Reservoir sedimentation 6. Geological, seismic and Construction Material Survey 6.1 Geologic survey and analysis Geological maps Aerial photo interpretation Geologic surface reconnaissance Geophysical prospecting Drilling investigation Laboratory rock test Other investigations 6.2 Seismic survey and analysis 6.3 Construction material survey Material for concrete dam and other concrete structures Material for embankment dam 7. Recommended Project 7.1 Project description 7.2 Preliminary Design 7.3 Construction Plan and Implementation Schedule 7.4 Project Cost 2

3 Technical Guideline on Feasibility Study 1. Purpose of Technical Guideline This Technical Guideline present the detail contents, requirement and recommended methodologies for Feasibility Study of hydropower project to be conducted by the Project Developer. 2. Scope of Technical Guideline This Technical Guideline is applicable for all the hydropower projects developed by IPP investors, EDL, EDL-GEN and PDEM. 3. Socio-economic and social/natural environments survey The Project Developer shall prepare, in accordance with the results of socio-economic survey and social/natural environmental survey, explanatory plan(s) on topographical maps of more than 1/50,000 scale showing both existing and future activities such as land utilizations, local development plans and other water resource development plans as well as hydropower projects for the purpose of sustainable integrated water resource and watershed management. 4. Topographical survey 4.1 Collection of existing topographical maps The Project Developer shall collect existing topographical maps of 1/100,000 and 1/50,000-scale covering the hydropower facilities of dam, waterways, powerhouse and transmission lines as well as drainage areas and temporary facilities such as access roads, camp facilities, borrow areas, quarry sites and resettlement areas. The above topographical maps of 1/100,000 and 1/50,000-scale are used only for identification of the locations of project facilities including temporary facilities. Detailed topographical maps are required for preparing preliminary designs as stated in Topographical survey and mapping for preliminary design The Project Developer shall prepare the following topographic maps required for both planning study and preliminary design. 1/5,000 map to cover the project facilities including dam, waterways, and powerhouse, access roads, and camp facilities, quarry sites, borrow areas and resettlement areas. 1/10,000 map to cover inundated areas by dam and/or weir, and transmission line 1/500-1/1,000 map to cover the above-ground structures of power facilities such as dam, weir, open channel, head tank and powerhouse 4.3 Longitudinal river profile survey The Project Developer shall conduct a longitudinal river profile survey by measuring river bed elevations covering the most upstream end of the inundated area by dams or weir and the powerhouse outlet location. The Project Developer shall also investigate and study the river profile, i.e. river-bed slope, with topographical maps of more than 1/50,000 scale in order to verify that potential heads of the river are effectively utilized by both existing and planned hydropower projects, and then shall prepare the river profile of main river and its tributaries indicating locations of existing and planned hydropower projects. 4.4 River cross-section survey The Project Developer shall conduct a river cross section survey at power outlet sites in order to study the tailrace water levels of various power discharges. In case some downstream areas of the dam or the powerhouse/outlet will be inundated during power discharges or flood discharges, the Project 3

4 Developer shall conduct river cross section surveys for the downstream areas at appropriate intervals in order to identify the inundated area due to the hydropower project. 4.5 Catchment area and reservoir volume The Project Developer shall measure the catchment area of the main dam and/or intake weirs by 1/50,000 or 1/10,000 topographical map, and also calculate the reservoir volume of the project by using appropriate topographical maps in two different methods of altitudinal and cross-section ones. 5. Meteorological/hydrological survey and analysis 5.1 Collection of existing meteorological/hydrological data The Project Developer shall collect existing meteorological/hydrological data as below in and near the project area. These data are utilized as bases for hydropower development planning, preliminary design and construction schedule. A location map showing existing meteorological/hydrological stations and the project shall be prepared. Rainfall (daily, monthly, annual) Temperature (daily average, daily minimum, daily maximum, monthly average) Wind velocity and direction (daily average, daily minimum, daily maximum, monthly average) River runoff (daily, monthly, annual) Flood records (hourly river discharge records during floods, or flood marks at river banks or trees or bridges) Evaporation (monthly, annual) Suspended load records during dry and rainy seasons together with river discharges Sediment records of existing dams 5.2 Meteorological/hydrological survey When the above existing data is not enough nor reliable for FS, the Project Developer shall set up gaging stations and conduct surveys to collect sufficient and reliable meteorological/hydrological data for the period of at least 1 year. It is advisable to measure river discharges at an appropriate location of the project as well as rainfalls during FS. In case of small hydropower development of run-of-river type, it is advisable to measure river discharges at a minimum 3-10 times a year including dry season in order to prepare runoff duration curve, followed by the determination of installed capacity(kw), annual energy production(kwh) and guaranteed capacity(kw) during dry season. 5.3 Length of rainfall and river runoff data The length of rainfall and river runoff data series to be collected by the Project Developer shall be greater than or equal to 10 years, and years of river runoff data series are preferable for sound and reliable hydropower planning. 5.4 Rationale and validation of selected rainfall and runoff data The Project Developer shall establish rationales of the selected meteorological/hydrological stations to be used for FS in terms of their locations, record lengths and their reliabilities. Prior to the use of measured rainfall and runoff data for FS, the Project Developer shall validate the consistency and reliability of the measured data through statistical approaches. If they are found to be inappropriate, the Project Developer shall identify the reasons of inappropriateness and eliminate them from the data series or correct them by reasonable methods. 5.5 River flow analysis When the length of river runoff data series is less than 10 years, the Project Developer shall conduct low flow analysis in order to prepare a river runoff data series at main dam site and/or intake dam/weir 4

5 sites for not less than 10 years, preferably years, through the following methods and their combinations of hydrological analysis. (1) Ratio of catchment areas between dam and gauging station (s) in the same river basin on condition that their drainage areas have similar rainfall patterns and amounts through a year Qg1 AB Qd Ag1 It is noted that the ratio of catchment area of dam site to that of gauging station is preferably several times. (2) Ratio of catchment areas considering the weight of the rainfall When the dam site and the gauging station are located separately, and rainfall amounts at the two sites are different, the runoff at the dam site is calculated by using a ratio of the catchment areas considering the weight of rainfall. The average rainfall in the catchment area is estimated by using isohyetal map or Thiessen method. Flow Qd at the dam site is expressed by the following equation; 1 Qg2 AB Ag 2 2 Ad AB1 AB Qd: runoff at dam site (m 3 /sec) Qg l : runoff at No. 1 gauging station (m 3 /sec) Qg 2 : runoff at No. 2 gauging station m 3 /sec) Ad: catchment area of dam site (km 2 ) Ag l : catchment area of No. 1 gauging station (km 2 ) Ag 2 : catchment area of No. 2 gauging station (km 2 ) AB l : catchment area of No. 1 tributary (km 2 ) AB 2 : catchment area of No. 2 tributary (km 2 ) 2 Qd=Qg Rd Ad Rg Ag Qd: runoff at dam site (m 3 /sec) Qg: runoff at gauging station (m 3 /sec) Rd: average rainfall at dam site (mm) Rg: average rainfall at gauging station (mm) Ad: catchment area of dam site (km 2 ) Ag: catchment area of gauging station (km 2 ) (3) Correlation between runoff data of gauging stations When the length of the runoff data at the dam site is not long enough, less than 10 years, and there exists other gauging station nearby with long-enough runoff data more than 10 years, the runoff data of the dam site can be extended for a longer period through a regression analysis with least-square method. Correlation coefficient of more than 0.7 is generally accepted (4) Data generation method of mathematical models When the length of the runoff data at the dam site is not long enough, less than 10 years, and there exists rainfall station nearby with long-enough runoff data of more than 10 years, the runoff data of the dam site can be generated by using mathematical models such as tank model, distributed runoff model and so on. The Project Developer shall process the monthly, weekly or daily runoff data at the main dam site or intake weir site and prepare a flow duration curve for run-of-river development project or a mass curve for reservoir development project. 5

6 5.6 Flood analysis Flood analysis is carried out to estimate flood flows at a proposed dam site. These flood estimates are required for the design of dam/spillways and diversion facilities. The inflow design flood shall be carefully determined through various approaches and considerations. Dam failure might cause tremendous damage against downstream area such as loss of life and economic loss. Inflow Design Flood for dam and spillway is specified in Article 17 of LEPTS as below taking care of hazard potential against downstream area of the dam. On the other hand, design flood at dam site during construction is determined by the Project Developer based on probable flood discharge for T- year returns period in consideration of dam type, construction plan and schedule, river diversion method and construction cost. The Project Developer shall estimate Probable Maximum Flood (PMF) and Probable Floods for various return periods up to 10,000 year by using available measured meteorological and hydrologic data, and MEM shall determine Inflow Design Flood for dam and spillway according to the dam classification specified in Article 17 of LEPTS. Dam classification Loss of life Impact on economy, society & environment Inflow design flood High Large increase Excessive increase PMF Significant Some increase Substantial increase Between PMF & 1000-year flood Low No increase Low increase Between PMF & 100-year flood (1) Probable Maximum Flood (PMF) PMF is defined as theoretically anticipated flood in the worst meteorological and hydrological conditions of the concerned area. Hydrograph Analysis is generally employed to estimate the PMF. The outline of work flow for the PMF is described in the chart below. Select rain gauge station DAD analysis of rainfall (Depth-Area-Duration) Estimate PMP (Probable Maximum Precipitation) Determine area reduction factor & hourly distribution Design PMP hyeto-graph Construct Unit Hydrograph PMF Hydrograph 6

7 The Project Developer shall identify rainfall gauging stations in/around the concerned river basin and select the stations of which records are used for Depth-Area analysis to obtain the area reduction factor for estimating a mean rainfall over the river basin. In general, the relation between point rainfall depth and basin mean rainfall depth is expressed by an exponential equation below, known as Horton s equation. P b = P 0 * exp[-kan] P b : mean rainfall depth over an area A (mm) P 0 : maximum point rainfall at a storm center (mm) A: concerned area (km 2 ) k,n: constant for a given area The Project Developer shall carry out Depth-Duration analysis by collecting hourly rainfall records during storms and estimating the hourly rainfall hyet-graph of heavy rainfall storm. When there are no hourly rainfall records in/around the river basin, the Project Developer shall install a self-recording rain gauge in the river basin and collect the hourly rainfall records. The Project Developer shall estimate the PMP through appropriate methods by using available data. The following methods are generally used for hydropower projects. It is advisable to estimate the PMP by more than two (2) methods. Theoretical approach in terms of the physically maximum moisture content by using temperature, humidity, dew points and wind velocity/direction Statistical approach which was developed by Hershfield and standardized by WMO in 1986 Historical approach by examining historical maximum rainfall storms ever occurred in the concerned area U.S. Weather Bureau method for the Lower Mekong River Basin to estimate generalized PMP with little meteorological and hydrological data The Project Developer shall construct unit hydrograph(s) by an appropriate methods including SCS 1 dimensionless unit hydrograph method, construct the PMP hydrograph(s) and estimate the peak discharge of PMF. (2) Probable floods for various return periods Probable flood discharge for T- year returns period is calculated by using a data series of annual maximum peak river discharges at gauging station(s). Hourly or daily discharge records depending on the size of drainage area are used for the estimation of probable flood discharges. The number of observed annual peak discharges is required for at least 10 years, preferably years. When daily discharges are used for the estimation, it is advisable that peak discharges are calculated by multiplying observed daily discharges by a reasonable conversion coefficient. A most fitted frequency curve for observed annual peak discharges is selected from probability density functions such as Gumbel s distribution, Pearson distribution, log normal distribution, log Pearson type III distribution. 1 SCS: Soil Conservation Service (USA), now Natural Resources Conservation Center (NRCS) 7

8 5.7 Backwater analysis of the reservoir during flood time The Project Developer shall carry out a backwater analysis of the reservoir during inflow design flood in order to access impacts of the reservoir water level rising in the upstream area including local villages, cultivated lands and existing structures like bridges and roads. In case serious impacts are anticipated during inflow design flood, the Project Developer shall prepare safe-guard plans to mitigate and alleviate those impacts. 5.8 Hydraulic analysis during flood discharge and power discharge The Project Developer shall carry out hydraulic analysis in the downstream area during both the normal power operation and the flood discharging through the spillway and then prepare a hazard map to indicate downstream inundated areas on topographical maps in order to examine impacts of the power discharge or flood waters over local villages, cultivated lands and existing structures like bridges and roads. 5.9 Hydraulic analysis against landslide effect to reservoir In case a large-scale landslide occurs in the reservoir area of the hydropower project, it causes huge shock waves in the reservoir which might overtop the dam crest. When the Project Developer identifies high potential locations of large-scale landslides, he shall conduct hydraulic calculations to simulate its disaster and confirm whether the dam will be overtopped or not Reservoir evaporation When the evaporation loss from the reservoir surface will not be negligible compared with river inflow into the reservoir, the Project Developer shall estimate the monthly amount of the evaporation from the reservoir by using measured data of evaporation pans. Evaporation loss from the reservoir surface is estimated by the equation below. E Loss = E open P, when E open > P E Loss = 0.0, when P > E open E Loss : monthly evaporation loss from reservoir surface E open : monthly evaporation from open water (measured value) P: monthly rainfall at reservoir surface 5.11 Reservoir sedimentation The Project Developer shall investigate and analyze suspended loads and river water quality in order to 1) estimate sedimentation volume of the reservoir, 2) design the settling basin, 3) design the sand flushing gate, and 4) ensure the durability of turbines. Sediment phenomena progresses and it reduces effective storage capacity between HWL and LWL as shown below. It is assumed that the sediment is deposited horizontally under the LWL. The LWL is determined in consideration of sediment volume and the sedimentation level and required water depth for the intake under the LWL. When the huge amount of reservoir sediment is estimated and power generation might be effected in spite of appropriate countermeasures, the Project Developer shall simulate a sediment configuration in the reservoir through mathematical analysis in order to estimate an actual sediment profile. 8

9 The Project Developer shall estimate the sediment volume deposited during 100 years after the dam completion through the two (2) different methods below. (1) Estimation by measured data of suspended load The work flow of estimation of sediment volume for 100 years is shown in the chart below. Collect measured data of suspended load Calculate annual suspended load & bed load Trap efficiency of the reservoir Calculate the average density of the sediment deposited in 100 years Estimate sediment volume for 100 years (2) Estimation by actual sediment records of existing dams When dams already exists near the proposed dam site and their sedimentation records are available, the sediment volume of the proposed dam site is estimated from the specific sediment yield, which is the sediment volume delivered to the reservoir from catchment area of 1 km 2 in a year (unit: m 3 /km 2 /year). If the condition such as climate, geology, topography and scale of reservoir are resemble in the proposed project site, the nearby sedimentation record can contribute to estimate the sediment volume with high reliability. 9

10 6. Geological, seismic and Construction Material Survey The Project Developer shall collect data and information on geology, seismicity and construction material covering the project area in order to 1) figure out geological conditions of the drainage area, dam site and waterway route, 2) study the reservoir water-tightness, 3) to identify possible landslide areas, 4) identify possibility of earthquakes and 5) study the availability of construction material such as dam embankment, concrete and aggregates. 6.1 Geologic survey and analysis Geological maps The Project Developer shall prepare the following geological maps, but not limited to, after the geologic surveys described in /5,000 geologic maps: the project area including dam, waterway, powerhouse, access roads for construction, quarry sites, borrow areas, temporary facilities and resettlement areas. 1/5,000-1/10,000 geologic plan: dam and reservoir area 1/5,000-1/10,000 geologic profile: dam and reservoir area 1/1,000-1/2,000 geologic plan and sections: dam and other power structures 1/5,000 geologic sections: quarry sites and borrow areas Aerial photo interpretation The Project Developer will be able to use aerial photos, if necessary for FS, not only for preparing topographical maps but also for a supplementary means of geologic survey through aerial photo interpretation Geologic surface reconnaissance Following literature survey and morphologic interpretation by both aerial photos and topographical maps, the Project Developer shall carry out the geologic surface reconnaissance with topographic maps below. 1/5,000 1/25,000 topographic maps: reservoir area and waterway route 1/1,000 1/2,000 topographic maps: dam, powerhouse and other structures Geologic surface reconnaissance shall observe and identify geologic and morphologic features on geological outcrops, overburdens and morphology as below; Geological outcrops Lithofacies including type of bedrocks, distribution of the stratum, joint pattern, characteristics of bedding and schistose planes and geologic ages Lithologic characters including hardness of bedrocks, conditions of weathering and alteration, conditions of crack/joint and remarkable phenomena such as secondary deposit and cavity Geologic structure including folding structure, faults, surface water and underground water Overburden Type of deposit, genesis, characteristics, distribution and vegetation Morphology Valley configuration Flat surface configuration Particular or unusual topography as karst, landslide and fault valley 10

11 6.1.4 Geophysical prospecting The Project Developer shall conduct geophysical prospecting such as seismic prospecting, electric prospecting, gravity prospecting and magnetic prospecting in order to identify the underground geologic and hydrologic structures. Seismic prospecting is a most generally method used for hydroelectric power projects. The length of prospecting lines shall be at least five (5) times longer than the depth to be prospected. Prospecting results shall be compared with drilled cores collected from drillholes located at intersecting points of prospecting lines and/or along the lines Drilling investigation The Project Developer shall conduct drilling investigation when the geologic surface reconnaissance and geologic prospecting are insufficient to get geologic and subsurface hydrologic conditions at dam, powerhouse and other structures. The Project Developer shall keep utmost technical efforts for full core recovery and store the recovered cores into specified core boxes. Through the drilled core observation, the Project Developer shall prepare drillholes logs to describe the following items. Geologic name (rock name, stratum name and surface deposit) Rock color with water-saturated Weathering, hardness, joint, solubility, swelling by water Drilling records (drilling speed and supply/drain water rate) Depending on actual geologic and topographic conditions, the number of drillholes at dam site is generally as below. Dam height 50 m : Total 5 drillholes including 3 holes at river bed & 2 holes at both river banks 50m < Dam height 100m : Total 7 drillholes including 5 holes at river bed & 2 holes at both river banks 100m < Dam height : Total 9 drillholes including 7 holes at river bed & 2 holes at both river banks The depth of drillholes at dam site is generally the same as dam height, depending on actual geological condition. The Project Developer will carry out permeability tests, seismic prospecting and horizontal loading test by using drilled holes. When seasonal ground water levels in dry and rainy seasons are key factors for the design of dam and other structures, the Project Developer shall monitor groundwater levels in the drillholes through a year Laboratory rock test The Project Developer will carry out laboratory rock tests according to international standards such as ASTM, BS, JIS and others using rock samples collected from drillholes. The following tests are generally conducted for FS of hydropower projects. 11

12 Specific gravity/absorption test, ultra-sonic wave test Unconfined compression test, Splitting tensile strength test, tri-axial compression test Other investigations In case 1) extremely high pervious layer or zone exists in the reservoir, 2) groundwater levels at river banks of dam site is lower than river water level, 3) there might be potential large leakage from the reservoir or dam abutment through limestone and/or karst zone, the Project Developer will carry out the following investigations on groundwater flows in order to secure the water-tightness of the reservoir or the dam safety. Simultaneous measurement of river discharges at multiple locations in the river Water quality measurement of river at multiple locations in a river to estimate flow routes of groundwater Tracing investigation of river flow with a colored material 6.2 Seismic survey and analysis The Project Developer shall collect and analyze historical seismic records, reports and information on seismic activities, geological formation and existence of faults in/around the project area, and then he shall determine the seismic design coefficient considering seismic activity level at the project area, geologic conditions of the structures foundation, existence of geologic faults and type of dam. When possible earthquakes might significantly affect the safety and stability of power facilities, the Project Developer shall further study dynamic seismic analysis for power facilities. 6.3 Construction material survey The Project Developer shall carry out construction material survey described below in order to 1) select the dam type such as RCC dam, concrete dam or embankment dam, 2) prepare preliminary designs for power structures and 3) prepare the construction planning and schedule Material for concrete dam and other concrete structures The Project Developer shall investigate the availability of ready-mixed concrete and concrete materials including cement, concrete aggregates and fly ash in terms of quantity and quality. For example, the concrete aggregates will be procured from quarries, river bed gravels, excavated rocks, and existing concrete plants, followed by quality tests such as specific gravity test, water absorption test, grain size distribution, Los Angeles test and alkali-aggregate-reaction test to confirm whether the materials to be procured will possess the required qualities for concrete aggregates as below. Sufficient hardness, strength and durability Adequate gravel diameter and size distribution Less than permissible levels of deleterious materials The Project Developer shall confirm whether fly ash used for RCC dam and other concrete structures will satisfy required qualities. If not, unsatisfied qualities of the fly ash shall be improved or modified through appropriate measures. The Project Developer shall investigate potential quantities at candidate quarry sites by geological maps, geologic surface reconnaissance, seismic prospecting and drillholes in order to confirm whether they have enough volumes of aggregates required for the project Material for embankment dam The Project Developer shall carry out the following tests for embankment materials to confirm whether the materials possess required qualities as well as their quantities. 12

13 Pervious and semi-pervious material: specific gravity test, water absorption test, grain size distribution test, uniaxial compression test Impervious material: natural water content, specific gravity test, liquidity/inelastic limit, grain size distribution test, compaction permeability test, triaxial compression test 7. Recommended Project 7.1 Project description The Project Developer shall provide detail features and descriptions on a recommended project scheme in accordance with the results of alternative study and optimization study. Required items of project descriptions are listed below. (1) Reservoir: catchment area (km 2), annual basin rainfall (mm), annual mean runoff (million m 3 ), reservoir surface area (km 2 ) at HWL, High Water Level (EL.m), Low Water Level (EL.m), gross reservoir capacity (million m 3 ), effective reservoir capacity (million m 3 ), available draw-down depth (m) (2) Main dam: dam type, dam height (m), dam crest length (m), dam width (m), dam volume (m 3 ) (3) Auxiliary dam: dam type, dam height (m), dam crest length (m), dam width (m), dam volume (m 3 ) (4) Intake dam/weir: catchment area (km 2 ), annual basin rainfall (mm), annual mean runoff (million m 3 ), intake water level (EL.m), dam type, dam height (m), dam crest length (m), dam width (m), dam volume (m 3 ) (5) Spillway: inflow design flood (m3/sec), type of spillway gate, number and size of spillway gates (6) Power intake: location and type of power intake, type of intake gate, number and size of intake gate (7) Headrace/Tailrace tunnel: number of tunnels, length and diameter of tunnels (m) (8) Headrace/Tailrace channel: number of channels, length and size of channels (m) (9) Head tank/surge tank: type of tank, size of tank (m) (10) Penstock: number of penstocks, type of penstocks (tunnel or exposed), material of penstocks, length and diameter of penstocks (m) (11) Power plant: design power discharge (m 3 /sec), rated head (m), plant capacity (MW), power supply for domestic use and/or export (MW), annual power generation (Gwh), type of powerhouse (open or underground), size of power house (m) (12) Turbine: type of turbines, number of turbines, rated output (MW)/rated head (m)/rated speed (rpm) of turbines (13) Generator: type of generators, number of generators, rated output (MVA)/rated speed (rpm) of generators, power factor of generators (14)Transformer: type of transformers, number of transformers, voltage ratio (kv), rated capacity 13

14 (MVA) of transformers (15) Transmission line: type and length (km) of transmission line (16) Substation: type of substation, size of substation (m) (17) Access road/bridge: length and width of permanent access road/bridges (m) (18) Resettlement/relocation: number of villages, number of households, number of people, relocation of existing road or bridge (19) Environmental/ecological flow: flow discharge (m 3 /sec), discharge method, length of recession area of the river (km) (20) Economy: total project cost (million USD), unit cost (USD/kw), EIRR, FIRR 7.2 Preliminary Design Hydropower civil engineering facilities According to Chapter 2 of LEPTS the Project Developer shall design hydropower civil engineering facilities for the recommended project in the following manners and prepare design drawings of plans, profiles and typical sections for dam/intake weir, intake, headrace, head tank/surge tank, penstock, powerhouse and outlet/tailrace. The Project Developer will prepare and submit structural calculation reports and/or stability calculation reports of dam, spillway and other key structures, if requested by MEM or PDEM. To use topographical maps of 1/1000-1/2000, To base on the results of hydrological survey and analysis, To decide physical/geotechnical properties of rocks and construction materials by accessing results of geotechnical investigation, various tests and literature survey To set up design criteria including design loads and safety coefficients for assumed design conditions, When the hydropower project is planned to locate its dam at the Mekong mainstream in the Lower Mekong Basin, this preliminary design shall be in compliance with the document Preliminary Design Guidance for proposed mainstream Dams in the Lower Mekong Basin (Mekong River Committee, 2009 August) in order to prevent any social and environmental impacts or other potential risks in the four MRC member countries. The impacts and risks are particularly with respect to navigation, fisheries, sediment transport and river morphology, water quality and aquatic ecology, and safety of dams. For the preliminary design the Project Developer shall study the following points for respective facilities, but not limited to. Main dam and auxiliary dams: its location in topographical and geological/geotechnical points of view, alternatives of dam types, availability of dam body materials, foundation treatment including gallery and grouting, method of river diversion, floods during construction, instrumentation during construction and after completion Intake dam/weir: its location for placing intake and settling basin, geological/geotechnical condition, access for maintenance 14

15 Spillway: its location and types, cavitation during discharging, operation rule of spillway gates during floods, downstream effects during discharging, Intake: its location and alignment not to breathe air or flow in whirls, flow capacity and velocity, structure types, geological and geotechnical conditions Headrace/Tailrace: its alignment, flow capacity and velocity, structure types, geological and geotechnical conditions for tunnel, lining pattern for tunnel, landslides and/or flush floods for headrace, maintenance after completion Head Tank/Surge Tank: its location, structure types, tank capacity, geological and geotechnical conditions, access for maintenance Penstock: its alignment, materials of penstock pipes, flow capacity and velocity, structure types, geological and geotechnical conditions, installation method of penstock pipes, access for maintenance, instrumentation after completion Powerhouse: its location, geological and geotechnical conditions, safety against floods during construction and after completion, cavern stability and supporting design of underground powerhouse, installation method of turbine and generators, regulating pond/dam downstream, warning system at the time of power discharging Reservoir: flood management system including rainfall/inflow monitoring method, discharge process and measures from spillway, warning system to downstream communities, environmental discharge, reservoir operation rule, water sharing rules between power, irrigation, industrial water, navigation and tourism Others: capacities of disposal areas and its utilization after completion, utilization plan of temporary facilities areas after completion, utilization and plantation plans of borrow areas and quarries, resettlement plans, tree trimming plan in the reservoir area before impounding the reservoir Hydro-mechanical facilities According to Chapter 2 of LEPTS the Project Developer shall design hydraulic gates, high pressure valves and trash-racks such as spillway gate, intake gate, sediment flush gate, draft gate, outlet gate, fish-way gate, navigation lock gate, conduit valve, outlet valve, etc. in the following manners. To select the type, shape, size and number of hydraulic gates and valves To select the type of hoisting device of hydraulic gates To determine operating conditions of hydraulic gates and valves in normal and emergency cases Electro-mechanical facilities The Project Developer shall determine the type, number and specification of turbine, generator and other electrical facilities in consideration of design power discharge with planned monthly available output and effective heads with water volume. According to Chapter 3 of LEPTS the Project Developer shall design turbines, generators, main transformers and their auxiliary facilities, followed by the preparation of drawings presenting layout plans of electrical facilities at power station and substation. Environmental conditions shall be carefully studied and adequate countermeasure shall be provided. Major items to be concerned are as follows; 15

16 Vibration and noise from turbine/generator and transformers. Oil/water separation system for turbine/ generator and transformer. Firefighting system for the necessary place, Indoor type Vacuum Circuit Breaker (VCB) for medium voltage, The Project Developer shall prepare general arrangement and single line diagram for the power station in view of technical, economical, energy conservation and reliable points as below: Applicable standard: IEC and/or LEPTS Number and capacity of generators Synchronous generator [kva], [V], [SCR] with pf=0.8 Selection of transmission line voltage Communication method of Remote Terminal Unit (RTU) for SCADA with Load Dispatching Center (LDC) Building code or standards of Lao PDR for powerhouse? Safe and easy operation and maintenance? Transmission line The Project Developer shall study and determine an optimal route of transmission line with right of way and connection point to the existing substation. Sectional view and river crossing if any, shall be provided by using 1/5,000 topographical maps in consideration of meteorological data. Highest point of the transmission line shall be indicated. Following certificate and agreement shall be concluded by the end of feasibility study. Environmental certificate issued by MONRE Agreement on transmission line issued by EDL. According to Chapter 3 of LEPTS, the Project Developer shall design transmission system including substation and connection point to the existing substation with their auxiliary facilities, and then prepare drawings presenting layout plans of electrical facilities. Control and protection relay panel related to the existing substation may be provided. Environmental conditions shall be carefully studied. Major items to be concerned are as follows; Number of resettlement households Legal restrictions of land uses No passage to the environmental protected area Height of overhead conductors Crossing points to the existing 22/115/230/500kV lines Oil/water separation system for transformer with fire-fighting system Indoor type VCB for medium voltage and outdoor type SF6 CB for 115, 230 or 500kV system Optical fiber overhead ground wire (OPGW) The Project Developer shall prepare general route map, detail route map with right of way, details of crossing section at the river and road. Technical items to be concerned are as follows; Local development plans and future project such as road, other public facilities Short circuit current and other system requirement Communication method of RTU for SCADA with LDC Protection and insulation coordination to the existing facility? Alternative transmission line route and connection point? Seismic zone map Requirement of Lao Grid Code? 16

17 Safe and easy operation and maintenance? According to Section 3-5 Transmission Lines of LEPTS, the Project Developer shall select overhead conductors, supporting structures, etc. considering design manual of transmission system of EDL. In case the hydropower project will be linked to the national grid of Lao or neighboring countries, the PD shall conduct the power system analysis in order to confirm reliability, power flow and short circuit current List of Drawings of Preliminary Design General layout covering dam, reservoir, waterways, powerhouse, transmission line, access roads, temporary facilities, disposal areas, borrow areas and quarries General plan of dam, auxiliary dam, intake dam/weir Upstream and downstream view of dam, auxiliary dam, intake dam/weir Typical sections of dam, auxiliary dam, intake dam/weir Foundation treatment plan of dam River diversion method Plan and profiles of spillway section and stilling basin/energy dissipator including spillway gates Plan and profiles of power intake including intake gates Plan and profiles of sediment settling basin Plan and profiles of headrace tunnel or headrace channel Plan and profiles of head tank or surge tank Plan and profiles of penstocks Plan, profiles and floor plans of powerhouse Plan and profiles of tailrace and outlet Floor arrangement plans and profiles of electro-mechanical equipment including turbines, generators and auxiliary equipment Plan and profiles of switchyard including arrangement of electrical equipment Overall single line diagram including transmission and substation to be connected Single diagram of power station Route map of transmission line with right of way Highest point of transmission line Profiles of transmission tower including foundation bases Sectional views of transmission line at river crossing points, if any Plan and profile of disposal areas Plan and profiles of borrow areas and quarries General layout plan of temporary facilities including camps, concrete plant, turbid water treatment plant, steel processing yard, parking lots for construction equipment, warehouses, and other facilities 7.3 Construction Plan and Implementation Schedule 7.3.1Basic data for construction plan and schedule The Project Developer shall collect the following data and information prior to preparation of construction planning and schedule. Meteorological data including temperature, rainfall, number of rainy days, etc. Hydrologic data including flood discharge, frequency of floods, etc. River water properties including temperature, quality, turbidity, ph Topographical and geological maps of 1/5,000 covering project facilities and temporary facilities Site conditions including geographical location of the project and living conditions in its vicinity Construction conditions including availability of construction machines, materials and labors 17

18 Transportation conditions of roads and bridges near the project area Electricity for construction including availability of existing power transmission lines near the project area Construction plan and schedule The Project Developer shall prepare construction/installation plans and schedules of the following works in consideration of local meteorological/hydrological conditions, transportation/shipping conditions and availabilities of construction materials/machine and workers. Preparatory works including access roads, temporary bridges and distribution lines for the construction Temporary facilities including camps, concrete plant, turbid water treatment plant, steel processing yard, parking lots for construction equipment, warehouses, and other facilities Civil works of dam, waterway, powerhouse, etc. Electro-mechanical works of turbines, generators, transformers and auxiliary equipment Hydro-mechanical works of gates, valves and steel penstocks Transmission line works Resettlement works Environmental mitigation works and safe-guard measures works All main milestones and risks shall be clearly identified and addressed; in addition, the critical path shall be indicated in the construction schedule. Main milestones are summarized below, but not limited to. Completion of dam excavation Commencement of river diversion Commencement of initial reservoir pounding Commencement of dry test of electro-mechanical equipment Commencement of wet test of electro-mechanical equipment Commencement of commercial operation 7.4 Project Cost The Project Developer shall estimate the project cost by local currency (LAK) and foreign currency (US$), present the total construction cost in US$ by changing the cost for local currency (LAK) to foreign currency (US$), and prepare a summary of the project cost shown in the following table as well as Bill of Quantity sheets by work items. Bill of Quantity sheets for respective work items shall indicate lengths, number, volume and weight of concrete, excavation, steel bars, and other construction materials. When work items such as hydro-electrical equipment cannot be expressed as above, their lump sum prices are accepted. The Project Developer shall describe clearly 1) how the above respective cost items are estimated and 2) how the unit costs are derived,. The Project Developer shall also prepare the disbursement schedule of the project cost according to the construction schedule stated in Construction Plan and Schedule. 18

19 Cost Item Work Item 1. Base Cost 1.1 Development cost Feasibility study, Basic design & Detail design prior to construction 1.2 Preparation works & temporary facilities Access roads, temporary bridges, distribution lines for the construction, camps, concrete plant, turbid water treatment plant, steel processing yard, parking lots for construction equipment, warehouses, and other faciliti 1.3 Land acquisition & compensation Cost for land acquisition, land lease and compensation for local villages and local people during construction as well as during operation 1.4 Safeguarding works Environmental mitigation works to safeguard the environment to be affected by the project 1.5 Civil works Main dam, auxiliary dam, spillway, intake weir/dam, sediment settling basin, intake, headrace tunnel/channel, surge tank/head tank, penstock, powerhouse, tailrace tunnel/channel, outlet 1.6 Hydro-mechanical equipment Hydraulic gates, high pressure valves and trash-racks such as spillway gate, intake gate, sediment flush gate, draft gate, outlet gate, fish-way gate, navigation lock gate, conduit valve, outlet valve, trash-racks, steel penstocks 1.7 Electro-mechanical equipment Turbines, generators, transformers and auxiliary equipment 1.8 Transmission and distribution line works Transmission line, distribution line, steel tower structures, electricity concrete poles 1.9 Administration cost Administration cost for headquarter and site office 1.10 Engineering service cost Construction drawings and construction supervision 1.11 Physical Contingency Unexpected increase of work volume/quantities Sub-total Total of Basic Cost 2. Price contingency Unexpected increase of unit cost 3. Taxes & Royalties 4. Interest during construction Total Total of 1, 2, 3 and 4 19

10 Project Cost Estimation

10 Project Cost Estimation 10 Project Cost Estimation Contents 10 Project Cost Estimation... 1 10.1 Project Overview... 1 10.2 Principles of Project Cost Estimation... 2 10.3 Data Basis and Assumptions for Project Cost Estimation...

More information

FEASIBILITY STUDY GUIDELINES

FEASIBILITY STUDY GUIDELINES FEASIBILITY STUDY GUIDELINES Pakhtunkhwa Energy Development Organization (PEDO) Energy and Power Department, KP Prepared by Pakhtunkhwa Energy Development Organization Feasibility Study Guidelines Volume

More information

2 FINDING OF THE POTENTIAL SITES

2 FINDING OF THE POTENTIAL SITES EXECUTIVE SUMMARY 1 Background S-1 2 User of Manual S-1 3 Applicable Range of Micro-hydro power in the Indonesia S-2 4 How to use this Manual S-2 Chapter 1 INTRODUCTION 1-1 1.1 Purpose of the Manual

More information

Reclamation Manual Design Data Collection Guidelines Chapter 5 Typical Design Data Package Template

Reclamation Manual Design Data Collection Guidelines Chapter 5 Typical Design Data Package Template Reclamation Manual The Introduction (Chapter 1) for these design data collection guidelines contains additional information concerning: preparing a design data collection request, design data collection

More information

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant The power plant is located in southern Tolima, in the municipality of Chaparral, approximately 150 km from Ibague. It has an installed capacity of 80

More information

MIEL I Hydroelectric Power Plant

MIEL I Hydroelectric Power Plant MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Xayaburi Hydroelectric Power Project

Xayaburi Hydroelectric Power Project The MRC Regional Workshop on Discharge and Sediment Monitoring and Geomorphological Tool for the Lower- Mekong Basin, 21-22 22 October 2008 Xayaburi Hydroelectric Power Project TEAM Consulting Engineering

More information

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Ministry of Infrastructure and Transport PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Prepared by : Department of Energy August, 2013 [DOE] 1 Table of Contents Summary... 3 1. Geographical

More information

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw. 11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration

More information

NEPAL ELECTRICITY AUTHORITY ENGINEERING SERVICES PROJECT DEVELOPMENT DEPARTMENT

NEPAL ELECTRICITY AUTHORITY ENGINEERING SERVICES PROJECT DEVELOPMENT DEPARTMENT JAPAN INTERNATIONAL COOPERATION AGENCY NEPAL ELECTRICITY AUTHORITY ENGINEERING SERVICES PROJECT DEVELOPMENT DEPARTMENT THE UPGRADING FEASIBILITY STUDY ON THE DEVELOPMENT OF THE KULEKHANI III HYDROPOWER

More information

UPGRADING FEASIBILITY STUDY UPPER SETI (DAMAULI) STORAGE HYDROELECTRIC PROJECT NEPAL FINAL REPORT. Nepal Electricity Authority Nepal.

UPGRADING FEASIBILITY STUDY UPPER SETI (DAMAULI) STORAGE HYDROELECTRIC PROJECT NEPAL FINAL REPORT. Nepal Electricity Authority Nepal. No. Nepal Electricity Authority Nepal UPGRADING FEASIBILITY STUDY ON UPPER SETI (DAMAULI) STORAGE HYDROELECTRIC PROJECT IN NEPAL FINAL REPORT June 2007 JAPAN INTERNATIONAL COOPERATION AGENCY ELECTRIC POWER

More information

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng. HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the

More information

2. SCOPE OF WORK Evolution of Plan of Study Hydrology ALASKA ENERGY AUTHORITY AEA ENGINEERING FEASIBILITY REPORT

2. SCOPE OF WORK Evolution of Plan of Study Hydrology ALASKA ENERGY AUTHORITY AEA ENGINEERING FEASIBILITY REPORT 2. SCOPE OF WORK 2.1. Evolution of Plan of Study The purpose of this feasibility study is to define all aspects of the Project in sufficient detail to support the State s decision process regarding project

More information

Small Hydro based energy generation

Small Hydro based energy generation Workshop on Capacity Development Program for Afghan Women (Clean Energy Access) Small Hydro based energy generation G Anil Head Small Hydro Power Dn., Energy Management Centre, Trivandrum 695017, Kerala,

More information

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1 Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...

More information

Small Hydropower Projects (SHPP) Training Workshop Project Documentation for Project Assessment. Yerevan, 12./

Small Hydropower Projects (SHPP) Training Workshop Project Documentation for Project Assessment. Yerevan, 12./ Consulting Services for the Programme for the Promotion of Renewable Energies: German-Armenian Renewable Energy Fund (GAF-RE) Phase II, BMZ ID 2009.70.285 Small Hydropower Projects (SHPP) Training Workshop

More information

Phase II Report: Project Definition Options

Phase II Report: Project Definition Options OSHPC BARKI TOJIK Phase II Report: Project Definition Options Implementation Studies PHASE 2 Consultations Implementation studies 2014 07 08 2 Objectives of the implementation studies Establish detailed

More information

USE OF GABIONS IN SMALL HYDRAULIC WORKS

USE OF GABIONS IN SMALL HYDRAULIC WORKS USE OF GABIONS IN SMALL HYDRAULIC WORKS SECTION 1 SITE SELECTION FOR SMALL DAMS Table of Contents 1.1 CLASSIFICATION ACCORDING TO USE... 2 1.2 CLASSIFICATION BY HYDRAULIC DESIGN (site and basin requirements)...2

More information

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

CASE STUDY OKUYOSHINO, JAPAN

CASE STUDY OKUYOSHINO, JAPAN SEDIMENT MANAGEMENT CASE STUDY OKUYOSHINO, JAPAN Key project features Name: Okuyoshino Country: Japan Category: bypass channel/tunnel Reservoir volume (original): 15.47 Mm 3 Installed capacity: 1,206 MW

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

Amina Reservoir Project Report

Amina Reservoir Project Report Amina Reservoir Project Report Prepared for Instituto Nacional de Recursos Hidráulicos, Dominican Republic Rob Sowby, Sam García, and Erik McCarthy Civil and Environmental Engineering Brigham Young University

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL

More information

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank. Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge

More information

4. Present Activities and Roles

4. Present Activities and Roles 4. Present Activities and Roles The present missions, authorities, activities and roles of the various agencies involved with flood protection, floodplain management and flood-damage reduction are identified

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment

More information

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement Keeyask Generation Project Environmental Impact Statement Supporting Volume Physical Environment June 2012 KEEYASK GENERATION PROJECT SUPPORTING VOLUME EFFECTS OF THE ENVIRONMENT ON THE PROJECT June 2012

More information

Successful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam

Successful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam Successful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam David M. Robison, P.G. Geotechnical and Dam Safety Section, Louisville District, U.S. Army Corps of Engineers

More information

Overview of the IWAYA Dam project. Specifications

Overview of the IWAYA Dam project. Specifications Overview of the IWAYA Dam project Specifications The Iwaya dam, as a comprehensive development project, plays an important role on flood control in Kisogawa River system, as well as is used for irrigation,

More information

Some aspects of the sediment transit on the Mekong river in relation with hydropower development

Some aspects of the sediment transit on the Mekong river in relation with hydropower development Some aspects of the sediment transit on the Mekong river in relation with hydropower development Daniel Loudière Société Hydrotechnique de France A presentation in three parts - the situation when starting

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : January,

More information

Hydropower and Water Resources

Hydropower and Water Resources Hydropower and Water Resources Hydropower and Water Resources The development, planning, design, and construction of hydropower as well as large-scale irrigation schemes and special hydraulic structures

More information

Module 2 Measurement and Processing of Hydrologic Data

Module 2 Measurement and Processing of Hydrologic Data Module 2 Measurement and Processing of Hydrologic Data 2.1 Introduction 2.1.1 Methods of Collection of Hydrologic Data 2.2 Classification of Hydrologic Data 2.2.1 Time-Oriented Data 2.2.2 Space-Oriented

More information

PRELIMINARY DESIGN OF THE HYDRAULIC STRUCTURES DAM IN THE PISÃO RIVER

PRELIMINARY DESIGN OF THE HYDRAULIC STRUCTURES DAM IN THE PISÃO RIVER PRELIMINARY DESIGN OF THE HYDRAULIC STRUCTURES DAM IN THE PISÃO RIVER Margarida Isabel Godinho Sobral Department of Civil Engineering and Architecture, Instituto Superior Técnico - Lisbon, Portugal SUMMARY

More information

Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin: A Case Study

Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin: A Case Study Arab J Sci Eng (2013) 38:1359 1367 DOI 10.1007/s13369-013-0590-5 RESEARCH ARTICLE - CIVIL ENGINEERING Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin: A Case Study M. Cihat

More information

2.16 NAM POT HYDROPOWER PROJECT

2.16 NAM POT HYDROPOWER PROJECT 2.16 NAM POT HYDROPOWER PROJECT Nam Pot is a hydropower project of around 20 to 25 MW located in Xiangkhouang Province. Due to its size, location and economics, Nam Pot project is best suited to a domestic

More information

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation Client: Budhi Gandaki Hydroelectric Project Development Committee General Presentation 1. Background and objectives 2. Project location 3. Project information/features 4. Project performances 5. Environmental

More information

ONE DIMENSIONAL DAM BREAK FLOOD ANALYSIS FOR KAMENG HYDRO ELECTRIC PROJECT, INDIA

ONE DIMENSIONAL DAM BREAK FLOOD ANALYSIS FOR KAMENG HYDRO ELECTRIC PROJECT, INDIA ONE DIMENSIONAL DAM BREAK FLOOD ANALYSIS FOR KAMENG HYDRO ELECTRIC PROJECT, INDIA S. Masood Husain Nitya Nand Rai Director Assistant Director Foundation Engineering & Special Analysis Directorate Central

More information

Hydrology and Water Resources Engineering

Hydrology and Water Resources Engineering Hydrology and Water Resources Engineering SUB GSttingen 214 868 613 K.C. Patra 't'v Mai Narosa Publishing House New Delhi Chennai Mumbai Calcutta CONTENTS Preface vii 1. Introduction 1 1.1 General 1 1.2

More information

HPP CEBREN. Prepared by: Development and Investments Department

HPP CEBREN. Prepared by: Development and Investments Department HPP CEBREN Prepared by: Development and Investments Department Skopje, 2017 The partition place Cebren is located at the River Crna Reka, 81 km upstream from its inflow in the River Vardar, near the village

More information

5 Muskrat Falls Project

5 Muskrat Falls Project 5 Muskrat Falls Project Report by: P. Rae, P. Eng. 5.1 Introduction The Muskrat Falls Project comprises the hydropower generation facility proposed on the Lower Churchill River. The main project elements

More information

Hydropower retrofitted onto existing water infrastructure assets

Hydropower retrofitted onto existing water infrastructure assets Hydropower retrofitted onto existing water infrastructure assets Marco van Dijk Lecturer and Principal Researcher University of Pretoria / Water Research Commission South Africa Presentation Layout How

More information

Application for a Dam Permit Ash Basin No. 1

Application for a Dam Permit Ash Basin No. 1 Application for a Dam Permit Ash Basin No. 1 for the Sunbury Generating Station Shamokin Dam, Pennsylvania submitted to Commonwealth of Pennsylvania Department of Environmental Protection Bureau of Waterways

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France

Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France Christophe PETEUIL Compagnie Nationale du Rhone Engineering Department, River Systems and

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Hydrology and Water Management. Dr. Mujahid Khan, UET Peshawar

Hydrology and Water Management. Dr. Mujahid Khan, UET Peshawar Hydrology and Water Management Dr. Mujahid Khan, UET Peshawar Course Outline Hydrologic Cycle and its Processes Water Balance Approach Estimation and Analysis of Precipitation Data Infiltration and Runoff

More information

2.29 XE KONG 5 HYDROPOWER PROJECT

2.29 XE KONG 5 HYDROPOWER PROJECT 2.29 XE KONG 5 HYDROPOWER PROJECT The Xe Kong 5 Hydropower Project is located in Kaleum District, Xe Kong Province on the upper reaches of the Xe Kong, immediately upstream of the proposed Xe Kong 4 Hydropower

More information

Tangible benefits of technological prospection and prefeasibility studies in SHP projects Ing. Sergio Armando Trelles Jasso

Tangible benefits of technological prospection and prefeasibility studies in SHP projects Ing. Sergio Armando Trelles Jasso 5 th and 6 th December 2012, Panama City, Panama Tangible benefits of technological prospection and prefeasibility studies in SHP projects Ing. Sergio Armando Trelles Jasso Agenda Artisanal vs Technological

More information

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No ) Snettisham Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No. 017020) Authorization Flood Control Act, 23 October 1962 (House Doc. 40, 87th Congress, 1st Session) as adopted, provides

More information

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options)

(1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Sub-sector Guideline: (1) Bridge, Road and Railway (Adaptation Project) (2) Bridge, Road and Railway (BAU Development with Adaptation Options) Basic Concept A. General Concept Climate change will increase

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part 257.82 PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part

More information

WELCOME TO POND 101 OREGON WATER RESOURCES DAM SAFETY SECTION. John Falk, PE

WELCOME TO POND 101 OREGON WATER RESOURCES DAM SAFETY SECTION. John Falk, PE WELCOME TO POND 101 OREGON WATER RESOURCES DAM SAFETY SECTION John Falk, PE MISCONCEPTION 101 This is my own property..so I guess it s really none of your %*&^`!# business if I want to build a pond. R

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report February 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development

More information

HYDROPOWER AND WATER RESOURCES

HYDROPOWER AND WATER RESOURCES HYDROPOWER AND WATER RESOURCES Shaping our world A company of D-ZM-14137-01-00 Head of Certification body OUR EXPERTISE Hydropower and Water Resources The development, planning, design, and construction

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Structure of Presentation Outline of the Project Development Phases Key Attributes of the Project Environmental Considerations Scheme Layout

More information

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Distribution Restriction Statement Approved for public release; distribution is unlimited. CECW-EH-Y Regulation No. 1110-2-1464 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design HYDROLOGIC ANALYSIS OF WATERSHED RUNOFF Distribution Restriction

More information

Water Development Plan Template

Water Development Plan Template Water Development Plan Template (Updated September 2005) Water Development Plan Template Note: For any application with a proposed diversion rate of over 25,000 gallons a day, a development plan must be

More information

UPSC ESE/IES Civil Engineering Syllabus

UPSC ESE/IES Civil Engineering Syllabus 1 UPSC ESE/IES Civil Engineering Syllabus PAPER I 1. Building Materials: Stone, Lime, Glass, Plastics, Steel, FRP, Ceramics, Aluminum, Fly Ash, Basic Admixtures, Timber, Bricks and Aggregates: Classification,

More information

Text Andrew Tanner. Sixtus Tohlang.

Text Andrew Tanner. Sixtus Tohlang. Text Andrew Tanner C4 SEED JV Project Manager andrew.tanner@af.aurecongroup.com Sixtus Tohlang Chief Delegate LHWC Lesotho (GOL) mabesa@lhwc.org.ls Peter Van Niekerk Head: Delegation Study Management Committee

More information

Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014

Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014 Study on Economic Partnership Projects in Developing Countries in FY2013 Study on the small hydro power project in the province of Lam Dong in Socialist Republic of Vietnam Final Report SUMMARY February

More information

DAMS AND OTHER HYDRAULIC STRUCTURES

DAMS AND OTHER HYDRAULIC STRUCTURES GAP.2.9.1 A Publication of Global Asset Protection Services LLC DAMS AND OTHER HYDRAULIC STRUCTURES INTRODUCTION The purpose of a dam evaluation is to review the design, construction and performance history

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116 (i) Site Name and Ownership Information: HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY Site Name: Site Location: Site Address: Owner: Owner Address:

More information

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS Table of Contents APPENDIX SECTION HEADINGS 3-G.1.0 INTRODUCTION 3-G-2 3-G.1.1 Construction Inspections 3-G-2 3-G.1.2. As-Built Survey and Plan 3-G-2 3-G.1.2.1

More information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information Table of Contents Section Page 5.1 GENERAL... 5.1-1 5.1.1 Overview... 5.1-1 5.1.2 Investigation and Engineering Information... 5.1-2 5.2 PRELIMINARY GEOTECHNCIAL REPORTS... 5.2-1 5.2.1 Preliminary Geotechnical

More information

McElroy s Run Impoundment Structural Stability Assessment Report

McElroy s Run Impoundment Structural Stability Assessment Report Allegheny Energy Supply Company, LLC A FirstEnergy Company Pleasants Power Station Pleasants County, West Virginia October 2016 Prepared for: Allegheny Energy Supply Company, LLC A FirstEnergy Company

More information

Earth Brickwork Concrete Plain Radial Drum Roller Flap. fixed. Weirs Barrages. mobile. rockfills. Gravity butress Arch Arch-gravuty Cupola.

Earth Brickwork Concrete Plain Radial Drum Roller Flap. fixed. Weirs Barrages. mobile. rockfills. Gravity butress Arch Arch-gravuty Cupola. Dams type 1 Weirs Barrages fixed mobile Earth Brickwork Concrete Plain Radial Drum Roller Flap embankment Earthfills rockfills Dams Concrete gravity Arch Gravity butress Arch Arch-gravuty Cupola 2 Dams

More information

Stream Reaches and Hydrologic Units

Stream Reaches and Hydrologic Units Chapter United States 6 Department of Agriculture Natural Resources Conservation Service Chapter 6 Stream Reaches and Hydrologic Units Rain clouds Cloud formation Precipitation Surface runoff Evaporation

More information

Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams

Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams Blank line 11 pt Blank line 11 pt M. Wieland Chairman, Committee on Seismic Aspects of Dam Design,

More information

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

WASTEWATER & STORM WATER COLLECTION AND REMOVAL CVE 471 WATER RESOURCES ENGINEERING WASTEWATER & STORM WATER COLLECTION AND REMOVAL Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE

More information

John Hart Generating Station Replacement Project. December 2017 Community Construction Update Report #54

John Hart Generating Station Replacement Project. December 2017 Community Construction Update Report #54 John Hart Generating Station Replacement Project December 2017 Community Construction Update Report #54 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Annex 5 - Hydropower Model Vakhsh

Annex 5 - Hydropower Model Vakhsh Annex 5 - Hydropower Model Vakhsh 1. The Vakhsh Cascade The construction of dams on the Vakhsh River started in the late 1950s with the construction of the Perepadnaya diversion and power station. Until

More information

Takatz Lake Project - Alaska

Takatz Lake Project - Alaska BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT SUBMITTED BY: City and Borough of Sitka Electric Department 105 Jarvis Street Sitka, Alaska 99835 June, 2008 Initial Statement

More information

Flood control and safety evaluation of Banqiao reservoir

Flood control and safety evaluation of Banqiao reservoir Available online at www.sciencedirect.com Procedia Engineering 8 (01) 368 375 01 International Conference on Modern Hydraulic Engineering Flood control and safety evaluation of Banqiao reservoir GUAN Tie-sheng

More information

The Texas A&M University and U.S. Bureau of Reclamation Hydrologic Modeling Inventory (HMI) Questionnaire

The Texas A&M University and U.S. Bureau of Reclamation Hydrologic Modeling Inventory (HMI) Questionnaire The Texas A&M University and U.S. Bureau of Reclamation Hydrologic Modeling Inventory (HMI) Questionnaire May 4, 2010 Name of Model, Date, Version Number Dynamic Watershed Simulation Model (DWSM) 2002

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Modernization of High Hazard Dams in Austin, Texas. TFMA Spring Conference May 23, 2007

Modernization of High Hazard Dams in Austin, Texas. TFMA Spring Conference May 23, 2007 Modernization of High Hazard Dams in Austin, Texas TFMA Spring Conference May 23, 2007 Modernization of High Hazard Dams in Austin, Texas City of Austin Glen Taffinder, P.E. Stormwater Pond Dam Safety

More information

More Creek Hydroelectric Project Prefeasibility Study

More Creek Hydroelectric Project Prefeasibility Study Alaska Hydro Corporation More Creek Hydroelectric Project March 2018 E6348 SIGMA ENGINEERING LTD 1444 Alberni Street, 4th Floor, Vancouver, BC, Canada V6G 2Z4 Phone: (604) 688-8271 Fax: (604) 688-1286

More information

CE Hydraulics. Andrew Kennedy 168 Fitzpatrick

CE Hydraulics. Andrew Kennedy 168 Fitzpatrick CE 40450 Hydraulics Andrew Kennedy 168 Fitzpatrick Andrew.kennedy@nd.edu Final Exam, 8AM May 7, Will cover entire course 155 Fitzpatrick Around half on material since last midterm Like 1.5 midterms in

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs Project: Sorang Hydro Electric Project - 100 MW Overview: M/s.Himachal Sorang Pvt.Ltd., Hyderabad, is developing the Run of the River Sorang Hydro Electric Project (100MW) in Kinnaur District of Himachal

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Progress Report January 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development & Consulting

More information

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project

More information

CE 2031 WATER RESOURCES ENGINEERING L T P C

CE 2031 WATER RESOURCES ENGINEERING L T P C CE 2031 WATER RESOURCES ENGINEERING L T P C 3 0 0 3 QUESTION BANK PART - A UNIT I GENERAL 1. Write short notes on Water Resources Survey. 2. How do you calculate Average Annual Runoff depth? 3. Write short

More information

Saluda Hydro Operations. William R. Argentieri, P.E. Fossil & Hydro Technical Services

Saluda Hydro Operations. William R. Argentieri, P.E. Fossil & Hydro Technical Services Saluda Hydro Operations William R. Argentieri, P.E. Fossil & Hydro Technical Services Hydropower Basics Hydroelectric plants convert potential energy of water into kinetic energy to drive a generator.

More information

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC SEPTEMBER 19, 2012 PARR AND FAIRFIELD LOCATIONS Lockhart Neal Shoals Monticello

More information

Power Summit Presentation

Power Summit Presentation Government Of Nepal Ministry of Energy Power Summit Presentation 1st June 2016 Presented by: Moti Bahadur Kunwar Executive Director Web: www.nhpdc.gov.np Email: info@nhpdc.gov.np GON has Constituted Nalsing

More information

Hydropower. See the notes in Compedu Source: Marianne KTH

Hydropower. See the notes in Compedu   Source: Marianne KTH Hydropower See the notes in Compedu http://www.energy.kth.se/compedu/webcompedu/index.html Source: Marianne Salomon @ KTH Global Renewable Energy Source: IEA Worldwide Hydropower Source: IEA Hydropower

More information

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR 257.82 EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part 257 and Part

More information

Xayaburi Hydropower Project

Xayaburi Hydropower Project The 5 th Regional Stakeholder Forum Basin Planning and Environmental Management 20-21 September 2018 Landmark Hotel, Vientiane, Lao PDR Review of the Design Changes made for the Xayaburi Hydropower Project

More information

Managed Aquifer Recharge (MAR) Practical Techniques for the Caribbean

Managed Aquifer Recharge (MAR) Practical Techniques for the Caribbean Managed Aquifer Recharge (MAR) Practical Techniques for the Caribbean Scope of Presentation What is MAR? Antigua and Barbuda water resources issues Why promote MAR? MAR: Techniques MAR: Design criteria

More information

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE Greater Mekong Subregion Nam Ngum 3 Hydropower Project (RRP LAO 41385) Supplementary Appendix 5 TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE Strengthening Biodiversity

More information

PHYSICAL ENVIRONMENT MONITORING P LAN DRAFT

PHYSICAL ENVIRONMENT MONITORING P LAN DRAFT Aquatic Effects Monitoring Plan PHYSICAL ENVIRONMENT MONITORING P LAN DRAFT October 2012 POINTE DU BOIS SPILLWAY REPLACEMENT PROJECT Physical Environment Monitoring Plan DRAFT Report Prepared for October

More information