1 9 Before and After Study Plan A Before and After Study Plan has been prepared, describing how the Massachusetts Bay Transportation Authority (MBTA), in cooperation with the Massachusetts Department of Transportation (MassDOT), will collect and report information about the Green Line Extension project. As described in the plan that follows, the MBTA will assemble information on: Project scope; Transit service levels; Capital costs; Operating and maintenance costs; and Ridership patterns and revenues. This information will be provided throughout project planning, development, and design, and continu e until two years after revenue operation begins. The Before and After Study Plan for the Green Line Extension project will build on data collection, preservation, and reporting efforts alread y established for the existing Green Line currently in operation. This plan will be updated as the project moves through engineering and design, and annual reports of th is key data will be provided throughout those design phases. Existing conditions data for the study area was used as the Before cond ition for the Green Line Extension d ata collection and reporting effort. Before and After Study Plan /23/2011

2 9.1 Before and After Data Preservation and Collection Plan This section summarizes the status of the Green Line Extension project development process, the scope of the Proposed Action, the need for and anticipated outcomes of Green Line Extension project implementation, and the data collection and preservation plan for key project characteristics, includ ing d ata sources as part of the Federal Transit Administration s (FTA) Before and After Study Plan requirements Introduction The FTA s Final Rule on Major Capital Investment Projects (December 7, 2000) requires that New Start project proponents collect data on key project characteristics generated 1) during planning and project development, 2) immediately before implementation of the project, and 3) for two years after the project opens for service. The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) amended Section 5309(g)(2)(c) to codify this regulatory requirement. Project sponsors, as a condition of receiving a Full Fund ing Grant Agreement (FFGA), must assemble information on: Project scope; Transit service levels; Capital costs; Operating and maintenance costs; and Ridership patterns and revenues. This information is provided throughout project planning, development, and design, and continues until two years after revenue operation begins. SAFETEA-LU additionally requires the FTA to summarize the information provid ed by project sponsors on these key project characteristics in a Report to Congress on the results of any Before and After studies completed during that year Green Line Extension Project Planning and Development Status Since 2003, continuous planning and development efforts have been coordinated for the Green Line Extension project. A Major Investment Study/ Alternatives Analysis (MIS/ AA) was completed for the project in In 2006, MassDOT submitted an Expanded Environmental Notification Form (EENF) to the Secretary of the Executive Office of Energy and Environmental Affairs (EEA), after which the Secretary of EEA issued a certificate requiring the preparation of an Environmental Impact Report (EIR). A Draft Environmental Impact Report/ Environmental Assessment (DEIR/ EA) Before and After Study Plan /23/2011

3 was filed October 15, During the project process, MassDOT has continuously coordinated with the FTA and submitted several items related to the Green Line Extension New Starts package prior to this submittal. It is anticipated that further coordination efforts would continue throughout the New Starts application review process, and all upd ates will be documented accordingly. The MBTA will assume lead responsibility for managing the project beginning with the preliminary engineering phase of the project. As the operating agency and ultimate owner of the Green Line Extension, the MBTA will manage, with support from MassDOT, the preliminary engineering, final design and construction phases of the project. See Attachment 1A for the list of prior FTA submittals for this project Project Description The purpose of the Green Line Extension is to imp rove corridor mobility, boost transit ridership, improve air quality, ensure equitable distribution of transit services, and support opportunities for smart growth initiatives and sustainable development in the project study area which includes Cambridge, Somerville, and Medford. The Green Line Extension offers tremendous benefits to the area, in that the project would: Focus regional transportation investment in established environmental justice communities, connecting currently-underserved resid ents to jobs and services in Boston and Cambrid ge and strengthening business and residential districts in the corridor. Improve transit travel times within the project stud y area by approximately 13 to 17 minutes (compared to the No-Build Alternative) from Lechmere Station to Union Square or Medford Hillside, respectively. Offer a one-seat ride from the project study area into d owntown Boston, eliminating the bus/ rail transfer that occurs at Lechmere Station, or at other stations, to the MBTA s Orange and Red rap id transit lines. Generate daily ridership at the project s seven stations of approximately 44,800 by 2030, with approximately 92 percent of these trips to take place in the project s opening year of As per FTA instruction, this number reflects the daily inbound boardings and outbound alightings at these new GLX stations (including New Lechmere). The Green Line as a whole would also see an increase of 25,970 boardings, and the entire MBTA system would see an increase of 7,500 new d aily linked transit trips as a result of the extension of Green Line service. Of the projected new transit trips, approximately 25 and 45 percent of these riders are projected to switch from using their automobiles to using transit within the study area and the Green Line system, respectively. Before and After Study Plan /23/2011

4 Substantially improve mobility and service quality for transit-dependent riders, with improved access (i.e. service, travel time savings) to jobs, schools and health care facilities and provide universal access, meeting Americans with Disabilities Act (ADA) stand ards at all stations. Be fully grade separated and constructed within existing MBTA railroad rightsof-way, which would enable light rail service to serve pedestrian-oriented centers with minimal disruption to the surrounding community and without significant property or neighborhood impacts. Maintain existing railroad operations while employing mitigation measures to reduce net noise and vibration impacts, resulting in residential and retail areas that would experience substantially reduced existing noise levels. Reduce daily Vehicle Miles Traveled (VMT) by 25,728 per day, improving air quality and providing zero-emission transportation capacity for anticipated growth. Transit improvements are needed along the Green Line Extension corridor as a result of poor transit access and mobility, limited transit capacity, poor regional air quality, and traffic congestion on local roads. Existing transit service within the project study area is currently offered by 15 MBTA bus routes with access to points within the study area as well as to Boston, Arlington, Woburn, and Winchester. However, existing bus routes operate within the urban street network and share the road with intense automobile traffic, which hinders bus service and causes inefficient and unreliable transit service in the project study area. Although MBTA commuter rail lines travel through the project study area, with impacts to the environment within the study area, there are no rail transit stops within the area communities to provide the off-setting benefit of transit access. These deficiencies and needs are more fully described in the following sections. The Green Line Extension is urgently needed to improve corridor mobility and livability, particularly in transit-dependent and environmental justice communities. The Green Line Extension enjoys strong community support from throughout the corridor, where residents and businesses are eager for better and expanded transportation access. The No-Build Alternative provides insufficient mobility improvements for project study area residents and fails to substantially improve environmental conditions and promote smart growth and economic development in the corridor Project Purpose and Predicted Outcomes The purpose of this project is to increase corridor mobility in high density, predominantly environmental justice communities and activity centers in the project study area. Project goals include boosting transit ridership, improv ing regional air quality, promoting equitable distribution of transit services, supporting Before and After Study Plan /23/2011

5 opportunities for smart growth initiatives and sustainable development, and maximizing transit system efficiencies. Transit improvements are needed along the Green Line Extension corridor as a result of poor transit access and mobility, limited transit capacity, poor local and regional air quality, and traffic congestion on local roads. These needs are detailed in previous chapters. The project s economic influence will be focused into existing urban villages and brownfield areas identified for mixed -use development. Regionally, the project relieves pressure to grow outward and supports compact, revitalized, low carbon footprint urban communities. The most dramatic d evelopment that relies on the project is NorthPoint in East Cambridge. NorthPoint s permitting requires Lechmere Station to be relocated on-site. NorthPoint is expected to add 2,700 housing units, 2.1 million square feet of non-residential space, nearly 5,280 parking spaces (of which 300 are replacement transit access parking spaces), and 392,000 square feet of open space. The project improves regional mobility by establishing a seamless light rail transit connection between the project study area, employment centers in Boston and Cambridge, and the regional transit network. The project improves regional light rail service by balancing the existing MBTA light rail system north and south of the Charles River, with the region s primary employment center at the midpoint. It improves light rail system efficiency by reducing non -revenue service miles. By the forecast year of 2030, 44,800 riders are expected to use the new Green Line Extension stations each day (inbound boardings plus outbound alightings) Responsibilities The project sponsor and key agencies and their responsibilities for the Green Line Extension project are discussed in this section. Internal The project sponsor for the Green Line Extension project through the planning and advanced conceptual design phases has been MassDOT. The MBTA, with support from MassDOT, is taking the management lead during the preliminary engineering phase for the Green Line Extension project, and the project is being managed by Mary R. Ainsley, MBTA Program Manager. The MBTA, in cooperation with MassDOT, will manage the development of preliminary design plans as well the final design and construction of the project. The Before and After Study will be the responsibility of the MBTA. Primary MBTA responsibilities related to the project include: Before and After Study Plan /23/2011

6 Manage the preliminary engineering and final design, preparation of designbuild contract documents, construction administration, and construction inspection; Provide oversight for project technical issues; Develop recommend ations for resolutions to unique problems arising out of unforeseen cond itions revealed during project planning, development, and implementation; and Develop responses to Project Management Oversight Consultant (PMOC) recommend ations and requests to prevent the deterioration of bud get and schedule. MBTA and MassDOT departments involved in development of the Green Line Extension project include Planning, Real Estate and Environment; Bud get; Operations; Legal; and Design and Construction. Metropolitan Area Planning Council (MAPC) The MAPC is the regional planning agency for the Boston region, representing 101 cities and towns in the metropolitan Boston area. As one of 14 members of the Boston Metropolitan Planning Organization (MPO), the MAPC has oversight responsibility for the region s federally-funded transportation program. The MAPC also is charged with developing the regional land use plan. Data on growth and development patterns were developed by the MAPC for use in forecasting project ridership. Central Transportation Planning Staff (CTPS) CTPS provides technical and policy analysis support to the Boston MPO and other members of the region s transportation community, including the MBTA and MassDOT. CTPS develops, maintains, and app lies the regional travel demand model set and has generated all forecasts for the Green Line Extension project. CTPS will provide documentation of these forecasts as needed. Federal Transit Administration (FTA) The FTA will review and approve the Before and After Study Plan. The FTA will also review project interim and final reports. Before and After Study Plan /23/2011

7 Project Management Oversight Consultant (PMOC) The PMOC designated by the FTA will assist in reviewing project data Scope of Work/Data Collection and Preservation Plan This section discusses the scope of work for the alternatives analysis, preliminary engineering and FFGA phases of the project, and how these forecasts are compared to the As-Built scenario after project opening. Task 1 Organization of Plans The following planning activities will be performed in preparation for the Before and After Study Plan: Assembly and review of project planning documents to date; Meeting of project participants; Preparation of draft work plan; and Preparation of final work plan. Task 2 Documentation of Forecasts The Green Line Extension ridership forecasts and capital and operating and maintenance (O&M) cost estimates will be reported to the FTA annually as part of the New Start submittal process. These key metrics are required to be reported annually by the FTA, both in its annual New Starts report and in the contractor performance report mandated by SAFETEA-LU. A. Project Scope and Capital Costs The project scope and capital cost estimation is being d eveloped and will be documented during the alternatives analysis, preliminary engineering and FFGA phases of the project in the following order: 1) Alternatives Analysis (AA): a) Collect project planning d ocuments All relevant documents related to the project scope and estimation of capital costs during the Green Line Extension alternatives analysis process beginning in 2008 were identified and documented. These documents are currently maintained in the document management system developed by the Green Line Extension project team, which also includes technical memoranda, drawings, and other relevant materials. Before and After Study Plan /23/2011

8 b) Document project scope A detailed project description has been developed. Major items (such as track alignment lengths, number of stations, and maintenance facility siting) will be refined and recorded. Other major cost items (such as signals, electrification, and vehicles, etc.) will be described and documented. The expected timing and duration of construction will be documented. Costs are assembled in the Stand ard Cost Categories (SCC) worksheet developed for this and previous New Starts submittals. 2) Preliminary Engineering (PE): a) Collect project planning documents All relevant documents related to the project scope and estimation of capital costs during the PE/ extended PE phase will be identified and assembled in the document management system. This will include not only the PE reports but all supporting technical memoranda, drawings, and similar materials, and other relevant materials (e.g., electronic spreadsheets used in cost estimation). b) Document project scope A detailed project description will be developed documenting the physical scope of the project as planned in PE. Major items (such as track alignment lengths, number of stations, and maintenance facility siting) will be record ed. Other major cost items (such as signals, electrification, vehicles, etc.) will be described and documented. The expected timing and duration of construction will be documented. Costs are assembled in the SCC worksheet developed for this and subsequent New Starts submittals. 3) Full Funding Grant Agreement (FFGA): a) Document projects as specified in FFGA A detailed project description will be developed documenting the physical scope of the project as specified for the FFGA. Major items (such as track alignment lengths, number of stations, and maintenance facility siting) will be recorded. Other major cost items (such as signals, electrification, vehicles, etc.) will be described and documented. The expected timing and duration of construction will be d ocumented. Costs will be assembled in the Stand ard Cost Categories (SCC) worksheet during final design. b) Document any changes in scope, capital costs, or sched ule from PE. Before and After Study Plan /23/2011

9 B. Operating and Maintenance Costs The operating and maintenance cost estimation will be developed and d ocumented during the alternatives analysis, preliminary engineering and FFGA phases of the project in the following ord er: 1) Green Line Extension Alternatives Analysis: a) Green Line Extension operating plan. Documentation included the following measures for the Green Line system as a whole: i) Routes. i iv) Headways (peak, off-peak, night, weekend). Run time by route. Vehicle miles traveled and revenue hours. b) Systemwide operating statistics: i) Number of routes by mode. Vehicle miles by mode. c) Operating and maintenance costs: i) Green Line Extension. Systemwide. 2) Preliminary Engineering/ Extended PE: a) Green Line Extension operating plan. Documentation will include the following measures for the Green Line system as a whole, and any changes from AA will be explained: i) Routes. i iv) Headways (peak, off-peak, night, weekend). Run time by route. Vehicle miles traveled and revenue hours. b) Systemwide operating statistics: i) Number of routes by mode. Vehicle miles by mode. c) Operating and maintenance costs: i) Green Line Extension. Systemwide. 3) Full Funding Grant Agreement (FFGA): Before and After Study Plan /23/2011

10 a) Green Line Extension operating plan. Documentation will include the following measures for the Green Line system as a whole, with any changes from PE explained: i) Routes. i iv) Headways (peak, off-peak, night, weekend). Run time by route. Vehicle miles traveled and revenue hours. b) Systemwide operating statistics: i) Number of routes by mode. Vehicle miles by mode. c) Operating and Maintenance Costs: i) Green Line Extension. Systemwide. C. Ridership The ridership forecasts will be collected and documented during the alternatives analysis and preliminary engineering phases of the project in the following order: 1) Green Line Extension Alternatives Analysis (AA): a) Document Methods The methods and procedures used in the Green Line Extension alternatives analysis to develop forecasts of project ridership were documented. This includes not just the description of the procedures or the functional relationships but also all of the underlying data that were used in developing the forecasts. Since the ridership forecasts were developed for MassDOT by CTPS, these materials were obtained from CTPS: i) Obtain and document electronic and hard copy of geographic analysis system (traffic analysis zones). i iv) Obtain and document electronic and hard copy of transportation networks. Obtain and document electronic and hard copy of travel forecasting functional relationships. Obtain and document electronic and hard copy of demographic and economic forecast d ata (e.g., population, employment, parking costs, transit fares, etc). b) Document Results: Before and After Study Plan /23/2011

11 i) Document electronic and hard copy of trip tables by mode and purpose. Document travel assignments. 2) Preliminary Engineering (PE): a) Document Methods The methods and procedures used in the PE phase of the project to develop forecasts of project ridership will be documented. This includes not just the description of the procedures or the functional relationships but also all of the underlying d ata that were used in developing the forecasts. Since the ridership forecasts were developed for MassDOT by CTPS, these materials will be obtained from CTPS: i) Obtain and document electronic and hard copy of geographic analysis system (traffic analysis zones). i iv) Obtain and document electronic and hard copy of transportation networks. Obtain and document electronic and hard copy of travel forecasting functional relationships. Obtain and document electronic and hard copy of demographic and economic forecast d ata (e.g., population, employment, parking costs, transit fares, etc.). v) Document changes from the AA/ EIR/ EA phase. vi) Changes in the projected system ridership as reported in the Green Line Extension AA will be documented. This will include not only changes in total ridership but also changes in ridership by station, by market segment, or by other meaningful grouping. Changes in the design of the project, in forecasts of population, economic activity, transportation systems, or in other factors that would have affected the ridership forecasts will be identified and documented. b) Document Results: i) Document electronic and hard copy of trip tables by mode and purpose. Document travel assignments, including boardings and mode of access by station. c) Document changes from the AA/ EIR/ EA phase. Before and After Study Plan /23/2011

12 Task 3 Documentation of Conditions Before Project Implementation Various performance measures including transit operations, ridership and capital and O&M costs will be documented for the Before Project Implementation conditions under this task. A. Project Scope 1) Document any refinements from the FFGA. 2) Document the timing and duration of construction (from the FFGA). B. Transit Service Levels 1) Area covered The service area for which data will be gathered will be described. 2) Measures to be documented are those shown in Task 2, B. 3) Data sources MBTA Operations. 4) Reporting method The sources of data on transit operations are the schedules, vehicle assignment sheets, run cuts, and d ata collection report prepared by the MBTA. C. Capital Costs Document costs from Construction documents, using the FTA Activity Line Item codes, noting and explaining any changes from the FFGA. D. Operating and Maintenance Costs Document revised operating and maintenance cost estimates, noting and explaining any changes from the FFGA. E. Ridership and Revenue On-board surveys and counts from existing Green Line service, in addition to d ata from the automatic fare collection system, will be used to establish the pre-implementation ridership and revenue. F. Other Factors Affecting Costs and/or Ridership 1) Construction cost index values The Engineering News Record construction cost index for Boston will be researched and recorded for the cost years used in estimation of project costs. Before and After Study Plan /23/2011

13 2) Consumer price index (CPI) The CPI for the Boston region will be documented for each year in which cost estimates were prepared and will be monitored and recorded during the construction period. 3) Cost of gasoline The average price of gasoline in the Boston metropolitan region will be obtained from the local American Automobile Association (AAA) office. This information will be documented and compared against operating cost per mile values used in the CTPS travel forecasting model. 4) Parking costs Data on downtown (and other) parking costs will be obtained from the City of Boston (and other sources), as they are updated. These costs will be documented and compared against parking costs during the planning and design phase of the project. 5) Planned development Updated information on planned development will be obtained from the Metropolitan Area Planning Council (MAPC), the Boston Redevelopment Authority, and other agencies as applicable. 6) Transit wage rates Average wage rates for MBTA light rail operators will be recorded for each year since the start of the Green Line Extension alternatives analysis process. This information will be obtained from MBTA records. Task 4 Documentation of Conditions After Project Opening Data will be collected during the first full fiscal year after project opening, currently anticipated in Since the MBTA s fiscal year runs from July 1 through June 30, the data will be collected or documented for the fiscal year beginning July 1, On-board surveys and on-off counts will be collected in spring Various performance measures including transit operations, ridership and capital and O&M costs will be d ocumented for the After Project Opening cond itions under this task. A. Physical Scope (As-Built) 1) A detailed project description will be developed d ocumenting the physical scope of the project as actually constructed. Major items such as project length and number of stations will be recorded. Other major cost items (e.g., electrification and communications, vehicles) will be d escribed and documented. Any changes from the EIR/ EA phase and/ or FFGA will be documented and explained. Finally, the actual length of the construction period will be documented. B. Transit Service Levels (as operated) 1) Area covered The service area for which data will be gathered will be described. Before and After Study Plan /23/2011

14 2) Measures to be documented are those shown in Task 2, B. 3) Data sources As operated from MBTA Operations. 4) Reporting method The sources of data on transit operations are the schedules, vehicle assignment sheets, run cuts, and d ata collection report prepared by the MBTA. Comparison of the as-operated levels to those anticipated in the EIR/ EA studies will be documented. C. Capital Costs 1) Sources of Information Project expend itures will be reported and summarized using the FTA Activity Line Item codes. These reports will be available monthly during the project construction period. While there will be some work continuing and likely some claims unresolved on opening day, the vast majority of capital costs should have been incurred and claims resolved by the end of the first full year of operation. MBTA records and PMOC reports will provide needed capital cost information. 2) Adjustments: a) For changes in physical scope Differences between the project As-Built and the project as planned and described in the FFGA will be documented. Estimates of the impacts of these changes on actual construction as compared to estimated costs will be prepared. b) As-Built costs will be expressed in year of expenditure dollars and compared to anticipated expenditures as detailed in the FFGA. All changes will be noted and explained. D. Operating and Maintenance Costs 1) Information Sources MBTA Budget. 2) Allocation method ologies As operating costs will focus on the incremental cost of the project service within the overall Green Line operating plan. E. Ridership On-board surveys and on-off counts will be used to collect information about the incremental ridership associated with the Green Line Extension. Task 5 Proposed Analyses Based on the information d ocumented in Tasks 2, 3 and 4, the following comparative analyses will be conducted against each performance measure: A. Project Scope 1) Planned versus As-Built: Before and After Study Plan /23/2011

15 a) Analyze and explain changes in project scope from Green Line Extension AA/ EIR/ EA through FFGA. b) Analyze and explain changes in project scope from FFGA to After Implementation, as described in Task 4. c) Analyze and explain changes in project scope from Before Implementation (Task 3) to After Implementation (Task 4). B. Transit Service Levels 1) Planned versus After Implementation: a) Maps will be prepared, illustrating the service plan in the project corridor as envisioned in the AA/ EIR/ EA phase of study and as actually operated. b) Charts will be prepared comparing the service measures as documented in Tasks 2 and 4. c) Explanation of any changes will be provided. 2) Before versus After Implementation: a) Maps will be prepared illustrating the service plan in the project corridor as envisioned in the AA/ EIR/ EA phase of study and as actually operated. b) Charts will be prepared comparing the service measures as documented in Tasks 3 and 4. c) Any changes will be analyzed and explained. C. Capital Costs 1) Estimated versus After Implementation: a) A chart will be prepared that compares costs as documented in Task 2 (Green Line Extension AA/ EIR/ EA, PE, and FFGA) with Task 4, after implementation costs. b) Analysis of estimated versus achieved costs will be conducted in year of expenditure dollars. A construction cost index and Consumer Price Index for the Boston region will be analyzed in relation to actual costs. The analysis of capital costs will seek to identify not only the differences between costs as estimated and as achieved, but also the project components that contributed to these differences. This will include an assessment of differences between estimated and achieved costs by component (e.g., viaducts and bridges, stations, right-of-way acquisition, vehicles, design, environmental mitigation, etc.) with special attention given to any Before and After Study Plan /23/2011

16 changes in project scope. Other documented changes that may have had a significant impact on achieved project costs, but which cannot be specifically identified by cost category, will be discussed. 2) Before and After Implementation: a) A chart will be prepared that compares costs as documented in Task 3 with final costs as d ocumented in Task 4. b) Any changes from Task 3 to Task 4 will be analyzed and explained. D. Operating and Maintenance Costs 1) Estimated versus After Implementation: a) A chart will be prepared that compares costs as documented in Task 2 (Green Line Extension AA/ EIR/ EA, PE, and FFGA) with Task 4, after implementation costs. b) Analysis of any changes from the FFGA to after implementation costs will be conducted and documented. The analysis will focus on differences due to changes in the number of units (e.g., vehicle hours of service, route lengths, etc.) and changes in the cost per unit. To the extent possible, the analysis will address costs by component including vehicle operations, maintenance, etc. Changes in the Consumer Price Index for the Boston region will be analyzed in relation to actual costs. 2) Before and After Implementation: E. Ridership a) A chart will be prepared that compares costs as documented in Task 3 with final costs as d ocumented in Task 4. b) Any changes from Task 3 to Task 4 will be analyzed and explained. 1) Ridership Estimates versus After Implementation: a) A chart will be developed that shows the changes in ridership between the Green Line Extension AA/ EIR/ EA and PE (Task 2) and after implementation (Task 4). This will include not only changes in system ridership, but also the total Green Line ridership, changes in ridership by station, by market segment, and other meaningful comparisons. b) An analysis will explain how changes in the design of the project, forecasts of population, economic activity, transportation systems, or other factors affected the ridership forecasts and actual outcomes. 2) Before versus After Implementation: Before and After Study Plan /23/2011

17 a) A chart will be prepared to show changes in ridership projections and ridership characteristics as documented in Tasks 3 and 4. b) An analysis will explain the impacts the project had on overall ridership and ridership characteristics for the Green Line Extension corridor, the overall Green Line service, and the system as a whole. Task 6 Findings and Recommendations Findings and recommend ations from the previous tasks will be summarized and the Before and After report will be prepared in the following order: 1) Summarize Findings A summary will be prepared highlighting the major findings of the analysis. The relationship between forecast and achieved values of capital cost, operating cost, and ridership will be documented. Major factors influencing the differences will be presented. 2) Summarize Recommend ations Based on the comparisons of forecast and achieved values, recommendations will be developed for improving the methods for developing forecasts, for presenting forecasts, or for other actions that would foster better use of data in making transit investment decisions. 3) Prepare Draft Report The Before and After draft report and the associated findings and recommendations will be prepared and submitted to the FTA. 4) Discuss Report with the FTA The Before and After d raft report will be reviewed with the FTA. 5) Revise Report Based on d iscussions with the FTA, the draft report will be revised. 6) Prepare Final Report The final version of the Before and After Report will be prepared and submitted to the FTA. Before and After Study Plan /23/2011

18 This Page Intentionally Left Blank Before and After Study Plan /23/2011

Green Line extension Project Fall 2009

Green Line extension Project Fall 2009 Introduction The Massachusetts Department of Transportation (MassDOT) is proposing to extend the Green Line to improve transit service, mobility, and regional access for residents and visitors of Cambridge,

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM. DATE January 21, 2010

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM. DATE January 21, 2010 BOSTON REGION METROPOLITAN PLANNING ORGANIZATION State Transportation Building Ten Park Plaza, Suite 2150 Boston, MA 02116-3968 Tel. (617) 973-7100 Fax (617) 973-8855 TTY (617) 973-7089 www.bostonmpo.org

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM BOSTON REGION METROPOLITAN PLANNING ORGANIZATION State Transportation Building Ten Park Plaza, Suite 2150 Boston, MA 02116-3968 Tel. (617) 973-7100 Fax (617) 973-8855 TTY (617) 973-7089 www.bostonmpo.org

More information

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY Purpose of tonight s meeting A Notice of Project Change (NPC) has been published for a possible extension of the Green Line from College Avenue to Mystic

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

CHAPTER 7. Illustrative Scenarios

CHAPTER 7. Illustrative Scenarios CHAPTER Illustrative Scenarios As mentioned in Chapter, this PMT presents and evaluates three scenarios state-of-good-repair (SGR), enhancement, and expansion that illustrate possible capital investment

More information

PERFORMANCE-BASED PLANNING AND PROGRAMMING

PERFORMANCE-BASED PLANNING AND PROGRAMMING February 2017 performance-based planning and programming Boston Region MPO PERFORMANCE-BASED PLANNING AND PROGRAMMING WHAT IS PERFORMANCE-BASED PLANNING AND PROGRAMMING? Performance-based planning and

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

View from Cabot Yard, South Boston. ACEC State Markets Conference April 2019

View from Cabot Yard, South Boston. ACEC State Markets Conference April 2019 View from Cabot Yard, South Boston. ACEC State Markets Conference April 2019 AGENDA MBTA By The Numbers FY 2020-2024 Capital Investment Overview and Programs FY 2019 Major Program Highlights Doing Business

More information

Travel Demand Forecasting User Guide

Travel Demand Forecasting User Guide Travel Demand Forecasting User Guide A Supplement to the Regional Transitway Guidelines Metropolitan Council February 2012 This document supplements the Project Development, Leadership, and Oversight discussion

More information

Columbia Pike Transit Initiative

Columbia Pike Transit Initiative The purpose of this project is to implement higher-quality and higher-capacity transit service in the corridor in order to: Provide more capacity; Enhance access within the corridor and provide connections

More information

PERFORMANCE-BASED PLANNING AND PROGRAMMING

PERFORMANCE-BASED PLANNING AND PROGRAMMING February 2017 performance-based planning and programming Boston Region MPO PERFORMANCE-BASED PLANNING AND PROGRAMMING WHAT IS PERFORMANCE-BASED PLANNING AND PROGRAMMING? Performance-based planning and

More information

APPENDIX TRAVEL DEMAND MODELING OVERVIEW MAJOR FEATURES OF THE MODEL

APPENDIX TRAVEL DEMAND MODELING OVERVIEW MAJOR FEATURES OF THE MODEL APPENDIX A TRAVEL DEMAND MODELING OVERVIEW The model set that the Central Transportation Planning Staff (CTPS), the Boston Region Metropolitan Planning Organization s (MPO) technical staff, uses for forecasting

More information

EVALUATION OF ALTERNATIVES CARRIED FORWARD

EVALUATION OF ALTERNATIVES CARRIED FORWARD 1 EVALUATION OF ALTERNATIVES CARRIED FORWARD This chapter presents a comparative evaluation of the alternatives carried forward in this Final Environmental Impact Statement (EIS). The intent of this evaluation

More information

Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation

Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation Table of Contents Acronyms and Abbreviations Secretary s Certificate on the EENF Executive Summary 1 Introduction and Background... 1-1 1.1 Introduction... 1-1 1.2 Project Summary... 1-2 1.3 Permits and

More information

11 Joint Development Regulatory Context and Methodology

11 Joint Development Regulatory Context and Methodology 11 Joint Development This chapter describes the long-term direct and potential indirect impacts, and short-term direct and potential indirect impacts, of the proposed METRO Blue Line Light Rail Transit

More information

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

SOUTHWEST LRT (METRO GREEN LINE EXTENSION) 8 Evaluation of Alternatives This chapter evaluates the effectiveness of the No Build Alternative and the Southwest Light Rail Transit (LRT) Project (the Project) based on the information contained in

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

Appendix B. Technical Memoranda and Reports

Appendix B. Technical Memoranda and Reports Cotton Belt Corridor Regional Rail Project Draft Environmental Impact Statement Appendix B Technical Memoranda and Reports Technical memoranda and reports were prepared as independent documents to support

More information

Chicago Transit Authority Orange Line Alternatives Analysis Study

Chicago Transit Authority Orange Line Alternatives Analysis Study Chicago Transit Authority July 10, 2009 Written questions and comments regarding the were submitted by a variety of individuals and groups from throughout the Chicago region at the study s Screen 2 Public

More information

A report produced by the Central Transportation Planning Staff for the Massachusetts Bay Transportation Authority

A report produced by the Central Transportation Planning Staff for the Massachusetts Bay Transportation Authority $ T F D A R Impact Analysis of a Potential MBTA Fare Increase in 2009 A report produced by the Central Transportation Planning Staff for the Massachusetts Bay Transportation Authority Impact Analysis

More information

Regional Performance Measures Annual Progress Report TPO Board - 2/4/2016 Presentation by: Chris Wichman, Senior Planner

Regional Performance Measures Annual Progress Report TPO Board - 2/4/2016 Presentation by: Chris Wichman, Senior Planner 2015 TPO Board - 2/4/2016 Presentation by: Chris Wichman, Senior Planner Overview History and definition of performance-based planning & programming Review of 2015 TPO Board Action Requested 2 History

More information

Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116

Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116 Comments on this Environmental Assessment (EA) and may be submitted in writing to: Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116 Comments must

More information

14-Dec-2016 Public Meeting Medford City Hall

14-Dec-2016 Public Meeting Medford City Hall 1 Agenda December 14, 2016 1. Update on GLX Status a. New Program Manager, John Dalton b. Work of the Interim Program Management Team 2. Design Build (DB) contractor selection process and timeline 3. Latest

More information

GLX Project AUGUST 2 4 FMCB MEETING

GLX Project AUGUST 2 4 FMCB MEETING GLX Project Green Line Extension Project AUGUST 2 4 FMCB MEETING Presentation Overview 1) Project Essentials 2) Funding the Green Line Extension Project 3) The Construction Manager/General Contractor Procurement

More information

Evaluation of Alternatives

Evaluation of Alternatives Chapter 9.0 Evaluation of Alternatives Chapter 9.0 provides a summary evaluation of the No Build Alternative and the Preferred Alternative. The evaluation contained within this chapter is an assessment

More information

Alternatives Analysis, New Starts

Alternatives Analysis, New Starts Alternatives Analysis, New Starts E. Beimborn, University of Wisconsin-Milwaukee 1 Outline Overview The process at the local level FTA new starts process Project justification Financial rating Forecasting

More information

South Florida East Coast Corridor (SFECC) Study

South Florida East Coast Corridor (SFECC) Study South Florida East Coast Corridor (SFECC) Study P r o j e c t U p d a t e J u l y 2 7, 2 0 11 FM Number: 417031-3-22-01 Re-introduce Passenger Rail Service on FEC Corridor (85 miles) Improve Freight Capacity

More information

ENVIRONMENTAL JUSTICE ASSESSMENT

ENVIRONMENTAL JUSTICE ASSESSMENT 14 ENVIRONMENTAL JUSTICE ASSESSMENT As part of its regional equity program (discussed in Chapter 9), the MPO performed a detailed, system-level analysis of transportation equity in the region, examining

More information

Locally Preferred Alternative. Work In Progress; Subject To Change Without Notice 1

Locally Preferred Alternative. Work In Progress; Subject To Change Without Notice 1 Locally Preferred Alternative 1 Riverview Corridor Study Area 12 mile study area between Saint Paul and Bloomington. Connects major destinations, neighborhoods and job concentrations. Serves growing and

More information

July 20, RE: XMBLY, MEPA #15595, Draft Environmental Impact Report. Dear Secretary Beaton:

July 20, RE: XMBLY, MEPA #15595, Draft Environmental Impact Report. Dear Secretary Beaton: July 20, 2018 Matthew A. Beaton, Secretary Executive Office of Energy & Environmental Affairs Attention: MEPA Office Page Czepiga, MEPA #15595 100 Cambridge Street, Suite 900 Boston, MA 02114 RE: XMBLY,

More information

Chapter 4. Recommendations

Chapter 4. Recommendations Chapter 4 Recommendations Project Rating Methodology 1.0 Introduction This chapter outlines the prioritization of potential investments that were identified during this MIS process. During this study there

More information

Nashville Southeast Corridor High-Performance Transit Alternatives Study. Final Report

Nashville Southeast Corridor High-Performance Transit Alternatives Study. Final Report Nashville Southeast Corridor High-Performance Transit Alternatives Study Final Report August 2007 - Nashville Southeast Corridor Executive Summary I. Introduction The southeast corridor is a 30 mile long

More information

Section 2: Transit Planning for Major Investments and New Starts

Section 2: Transit Planning for Major Investments and New Starts Section 2: Transit Planning for Major Investments and New Starts Introduction and Assignments New Starts/Alternatives Analysis/Major Investments New Starts/Alternatives Analysis/Major Investments power

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

Capital Cost Estimating Methodology Technical Memorandum

Capital Cost Estimating Methodology Technical Memorandum Memo Date: November 7, 2018 Project: To: From: DART Cotton Belt Regional Rail Project DFW International Airport to Shiloh Road Chad Edwards, DART Assistant Vice President Capital Planning John Hoppie,

More information

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend

More information

BUS RAPID TRANSIT CORRIDOR

BUS RAPID TRANSIT CORRIDOR DOWNTOWN UPTOWN OAKLAND EAST END BUS RAPID TRANSIT CORRIDOR Scoping Booklet for National Environmental Policy Act Review City of Pittsburgh Port Authority of Allegheny County Uptown/Downtown Scoping Meeting

More information

PERFORMANCE-BASED PLANNING AND PROGRAMMING

PERFORMANCE-BASED PLANNING AND PROGRAMMING September 2018 performance-based planning and programming Boston Region Metropolitan Planning Organization: PERFORMANCE-BASED PLANNING AND PROGRAMMING WHAT IS PERFORMANCE-BASED PLANNING AND PROGRAMMING?

More information

Category 3, BART Capacity, Access and Parking Improvements. Contra Costa Transportation Authority STAFF REPORT Page 2 of 5 The Authority directed staf

Category 3, BART Capacity, Access and Parking Improvements. Contra Costa Transportation Authority STAFF REPORT Page 2 of 5 The Authority directed staf Meeting Date: Subject Summary of Issues Recommendations Financial Implications Options Attachments Changes from Committee Development of a Potential Transportation Expenditure Plan (TEP) Review and Discussion

More information

Fairmount Line Feasibility Study

Fairmount Line Feasibility Study Executive Summary Wednesday October 16, 2002 Prepared for Massachusetts Bay Transportation Authority Planning Department Prepared by KKO and Associates, L.L.C. Two Dundee Park Andover, Massachusetts 01810

More information

VIA Long Range Plan Glossary

VIA Long Range Plan Glossary VIA Long Range Plan Glossary Accessibility. Accessibility is the ability to reach opportunities (economic, social, etc.) within a certain geographical area. Americans with Disabilities Act (ADA). Passed

More information

CHAPTER FIVE. Determination of Air Quality Conformity BACKGROUND. Timely Implementation of Transportation Control Measures

CHAPTER FIVE. Determination of Air Quality Conformity BACKGROUND. Timely Implementation of Transportation Control Measures 5 CHAPTER FIVE Determination of Air Quality Conformity BACKGROUND The Commonwealth of Massachusetts is classified as unclassifiable/attainment for the ozone standard with the exception of Dukes County.

More information

A Win/Win Strategy: Fixing Transportation and Reducing Greenhouse Gas Emissions in Massachusetts

A Win/Win Strategy: Fixing Transportation and Reducing Greenhouse Gas Emissions in Massachusetts Northeastern University Dukakis Center for Urban & Regional Policy A Win/Win Strategy: Fixing Transportation and Reducing Greenhouse Gas Emissions in Massachusetts E2/T4MA/NRDC EcoSalon Full Speed Ahead:

More information

09Scenario Evaluation

09Scenario Evaluation 09 Evaluation CHAPTER 9: Evaluation 73 74 2018 Draft Regional Transportation Plan/Sustainable Communities Strategy 9 SCENARIO EVALUATION Testing The four scenarios discussed in the previous chapter were

More information

S-09: Auburn Station Access Improvements

S-09: Auburn Station Access Improvements Project Number S-09 Subarea South King Primary Mode Commuter Rail Facility Type Infrastructure Improvements Length Version Number ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE

More information

The Transportation dividend

The Transportation dividend Prepared by AECOM Technical Appendices report February 2018 The Transportation dividend Transit investments and the Massachusetts economy Technical Appendix A economic Benefits Methodology and Results

More information

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11 Contents i Contents 1 A New Transportation Plan... 1 Why develop a new plan?... 1 What area does the LRTP focus on?... 2 Why is this LRTP important?... 3 Meeting Requirements for Transportation Planning...

More information

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services

More information

Identification and Evaluation of Alternatives Tier 1

Identification and Evaluation of Alternatives Tier 1 Vanasse Hangen Brustlin, Inc. DRAFT 4 Identification and Evaluation of Alternatives Tier This chapter describes the initial set of alternatives that were identified to address the Purpose and Need of the

More information

Wynn Everett Boston Presentation to MGC Staff

Wynn Everett Boston Presentation to MGC Staff Wynn Everett Boston Presentation to MGC Staff Presented by Keri Pyke, P.E., PTOE Howard/Stein-Hudson Associates, Inc. July 23, 2014 1 Keri Pyke, P.E., PTOE Summary of Qualifications B.S. in Civil Engineering,

More information

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015 ACTIVE TRANSPORTATION ADVISORY COMMITTEE Memphis MPO March 30, 2015 Agenda Welcome & Introductions Announcements and Briefings Livability 2040: Regional Transportation Plan Congestion Management Process

More information

09Scenario. Evaluation. CHAPTER 9: Scenario Evaluation 85. Modesto Junior College, Modesto, CA

09Scenario. Evaluation. CHAPTER 9: Scenario Evaluation 85. Modesto Junior College, Modesto, CA 09 Evaluation Modesto Junior College, Modesto, CA CHAPTER 9: Evaluation 85 86 2018 Regional Transportation Plan/Sustainable Communities Strategy Historic Downtown, Turlock, CA 9 SCENARIO EVALUATION Testing

More information

CHAPTER 2: Goals, Objectives & Standards

CHAPTER 2: Goals, Objectives & Standards CHAPTER 2: Goals, Objectives & Standards Report Prepared by: Contents 2 GOALS, OBJECTIVES AND STANDARDS... 2-1 2.1 Goals, Objectives, Performance Measures, and Targets... 2-1 2.2 Service Standards... 2-6

More information

What is the Transportation Policy Plan (TPP)?

What is the Transportation Policy Plan (TPP)? Summary What is the Transportation Policy Plan (TPP)? The region s long range transportation plan Includes all modes of transportation: highways, transit, airports, freight, biking, pedestrians Meets the

More information

Strategic Plan Progress Report Goal 2 Focus. November 2015 San Francisco, California

Strategic Plan Progress Report Goal 2 Focus. November 2015 San Francisco, California Strategic Plan Progress Report Goal 2 Focus November 2015 San Francisco, California 1 Goal 2 focus Make transit, walking, bicycling, taxi, ridesharing and carsharing the preferred means of travel Objective

More information

Improving Urban Mobility Through Urban Analytics Using Electronic Smart Card Data

Improving Urban Mobility Through Urban Analytics Using Electronic Smart Card Data Improving Urban Mobility Through Urban Analytics Using Electronic Smart Card Data Mayuree Binjolkar, Daniel Dylewsky, Andrew Ju, Wenonah Zhang, Mark Hallenbeck Data Science for Social Good-2017,University

More information

Overview of Alternatives Analysis

Overview of Alternatives Analysis Red Line/HealthLine Extension Major Transportation Improvement Analysis Greater Cleveland Regional Transit Authority Public Meeting: February 11, 2016 Final Report Overview of Alternatives Analysis Public

More information

COORDINATED TRANSPORTATION

COORDINATED TRANSPORTATION S T R A T E G Y T W E L V E EXPAND COORDINATED TRANSPORTATION Summary Adopted in 2008, MetroFuture is Greater Boston s thirty year (2010 to 2040) regional plan. The foundation of the plan is a well-defined

More information

Bonnie Doon Grade Separation

Bonnie Doon Grade Separation 6. 2 Bonnie Doon Grade Separation Recommendation: That the April 18, 2017, Integrated Infrastructure Services report CR_4461, be received for information. Report Summary This report provides information

More information

CHAPTER 21: COMMITMENT OF RESOURCES

CHAPTER 21: COMMITMENT OF RESOURCES CHAPTER 21: COMMITMENT OF RESOURCES 21.1 INTRODUCTION In accordance with the National Environmental Policy Act (NEPA) and the Council on Environmental Quality s implementing procedures under Title 40,

More information

MONITORING IMPLEMENTATION AND PERFORMANCE

MONITORING IMPLEMENTATION AND PERFORMANCE 12 MONITORING IMPLEMENTATION AND PERFORMANCE The FAST Act continues the legislation authorized under MAP-21, which created a data-driven, performance-based multimodal program to address the many challenges

More information

PUBLIC TRANSPORTATION PLAN

PUBLIC TRANSPORTATION PLAN PUBLIC TRANSPORTATION PLAN Introduction Public transportation is a vital element of the total transportation services provided within a metropolitan area. Not only does public transportation provide options

More information

Summary of transportation-related goals and objectives from existing regional plans

Summary of transportation-related goals and objectives from existing regional plans SMTC 2050 Long Range Transportation Plan Appendix A: Summary of transportation-related goals and objectives from existing regional plans SMTC 2050 Long Range Transportation Plan Summary of transportation-related

More information

2017 TRANSPORTATION POLICY STATEMENT

2017 TRANSPORTATION POLICY STATEMENT 0 TRANSPORTATION POLICY STATEMENT 1 1 1 1 1 1 0 1 0 1 0 1 Critical investments are needed to maintain and improve Virginia s transportation network. The structural imbalance between critical needs and

More information

NEW ORLEANS REGION TRANSIT COMPREHENSIVE OPERATIONS ANALYSIS SCOPE OF SERVICES. RPC Project LA90X361

NEW ORLEANS REGION TRANSIT COMPREHENSIVE OPERATIONS ANALYSIS SCOPE OF SERVICES. RPC Project LA90X361 NEW ORLEANS REGION TRANSIT COMPREHENSIVE OPERATIONS ANALYSIS SCOPE OF SERVICES RPC Project LA90X361 Overview Summary The purpose of the Comprehensive Operations Analysis (COA) is to provide detailed review

More information

Appendix A: Project Planning and Development A-1 White Paper on Transit and the Tappan Zee Hudson River Crossing Project

Appendix A: Project Planning and Development A-1 White Paper on Transit and the Tappan Zee Hudson River Crossing Project Appendix A: Project Planning and Development A-1 White Paper on Transit and the Tappan Zee Hudson River Crossing Project Purpose of White Paper White Paper on Transit and the Tappan Zee Hudson River Crossing

More information

TRANSIT SERVICE GUIDELINES

TRANSIT SERVICE GUIDELINES CHATHAM AREA TRANSIT AUTHORITY FEBRUARY 2014 Table of Contents 1. PURPOSE... 3 2. CAT SERVICE GUIDELINES... 3 3. TRAVEL MARKETS... 4 4. TRANSIT COVERAGE... 4 5. TRANSIT ACCESS... 4 6. BUS STOP SPACING

More information

CHAPTER HIGHLIGHTS GOALS AND GUIDING POLICIES 60 SEEKING PUBLIC INPUT TO REFINE SCENARIOS FOR OUR FUTURE 61

CHAPTER HIGHLIGHTS GOALS AND GUIDING POLICIES 60 SEEKING PUBLIC INPUT TO REFINE SCENARIOS FOR OUR FUTURE 61 04 CHAPTER HIGHLIGHTS GOALS AND GUIDING POLICIES 60 SEEKING PUBLIC INPUT TO REFINE SCENARIOS FOR OUR FUTURE 61 SCENARIOS FOR THE FUTURE: IT S OUR CHOICE 63 CREATING A PLAN FOR OUR FUTURE The RTP/SCS is

More information

REGION I. August 12, Re: Green Line Extension Project - Risk Assessment Review RepOli

REGION I. August 12, Re: Green Line Extension Project - Risk Assessment Review RepOli REGION I Volpe Cenler Connecticut, Maine, 55 Broadway Suile 904 Massachusetts, Cambridge, MA 02142-1093 U.S. Department of Transportation Federal Transit New Hampshire, 617-494-2055 Administration Rhode

More information

Chapter 3 - Goals, Objectives, & Strategies

Chapter 3 - Goals, Objectives, & Strategies Chapter 3 - This chapter presents goals, objectives, and strategies that have been developed as part of the Richmond Area MPO 2026 Long-Range Transportation Plan (LRTP) update. Strategies have been developed

More information

Chapter 4: Transportation and Land Use

Chapter 4: Transportation and Land Use Chapter 4: Transportation and Land Use Transportation and land use together make possible the wide range of destination opportunities in the region. Transportation provides the connections, and, in turn,

More information

MOBILITY 2045: A FOCUS ON TRANSPORTATION CHOICE:

MOBILITY 2045: A FOCUS ON TRANSPORTATION CHOICE: Mobility 2045: The Metropolitan Transportation Plan for North Central Texas is the defining vision for the multimodal transportation system in the Dallas- Fort Worth Metropolitan Planning Area. The plan,

More information

POLK COUNTY TPO Polk County 2060 Transportation Vision Plan Final Report. ADOPTED June 18, 2009

POLK COUNTY TPO Polk County 2060 Transportation Vision Plan Final Report. ADOPTED June 18, 2009 POLK COUNTY TPO Polk County 2060 Transportation Vision Plan Final Report ADOPTED June 18, 2009 TABLE OF CONTENTS CHAPTER 1 Introduction and Prior Planning Effort...Page 1-1 CHAPTER 2 Population and Employment

More information

BEFORE THE UNITED STATES DEPARTMENT OF TRANSPORTATION FEDERAL TRANSIT ADMINISTRATION ) ) ) ) ) ) ) ) ) ) )

BEFORE THE UNITED STATES DEPARTMENT OF TRANSPORTATION FEDERAL TRANSIT ADMINISTRATION ) ) ) ) ) ) ) ) ) ) ) BEFORE THE UNITED STATES DEPARTMENT OF TRANSPORTATION FEDERAL TRANSIT ADMINISTRATION THE CONSERVATION LAW FOUNDATION, ALTERNATIVES FOR COMMUNITY AND ENVIRONMENT and GREATER FOUR CORNERS ACTION COALITION

More information

Greenhouse Gas Reduction Strategy Alternatives: Cost-Effectiveness Analysis

Greenhouse Gas Reduction Strategy Alternatives: Cost-Effectiveness Analysis Greenhouse Gas Reduction Strategy Alternatives January 21, 2016 Greenhouse Gas Reduction Strategy Alternatives: Cost-Effectiveness Analysis Executive Summary Project Manager Anne McGahan Project Principal

More information

2016 Cape Cod Regional Transportation Plan Development

2016 Cape Cod Regional Transportation Plan Development 2016 Cape Cod Regional Transportation Plan Development APRIL 2015 PUBLIC MEETING PRESENTATION REGIONAL TRANSPORTATION P LAN ( RTP) + Long-range plan (2016-2040) + Includes all modes + Establishes the regional

More information

Updating Sound Transit s Long-Range Plan. ITE November 12, 2013

Updating Sound Transit s Long-Range Plan. ITE November 12, 2013 Updating Sound Transit s Long-Range Plan ITE November 12, 2013 The Sound Transit district Today s regional transit system Serving more riders each year Millions of annual Boardings Responding to the recession

More information

LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Volume I September 22, 2011 The Boston Region Metropolitan Planning Organization (MPO) is composed of: Massachusetts

More information

6 CHARTING PERFORMANCE

6 CHARTING PERFORMANCE DRAFT 6 CHARTING PERFORMANCE OVERVIEW OF PERFORMANCE BASED PLANNING Background of Performance Based Planning Increasingly, over the past two decades, transportation agencies have been utilizing performance

More information

Expanding the Use of Value Capture for Transportation and TOD in Massachusetts

Expanding the Use of Value Capture for Transportation and TOD in Massachusetts Expanding the Use of Value Capture for Transportation and TOD in Massachusetts EXECUTIVE SUMMARY January 20, 2017 Prepared for: Metropolitan Planning Area Council (MAPC) City of Somerville Barr Foundation

More information

June 30, Mr. Martin Suuberg Commissioner Department of Environmental Protection 1 Winter Street Boston, MA Dear Commissioner Suuberg:

June 30, Mr. Martin Suuberg Commissioner Department of Environmental Protection 1 Winter Street Boston, MA Dear Commissioner Suuberg: Charles D. Baker, Governor Karyn E. Polito, Lieutenant Governor Stephanie Pollack, MassDOT Secretary & CEO massdot Massachusetts Department of Transportation Mr. Martin Suuberg Commissioner Department

More information

CHAPTER 4 HIGHLIGHTS GOALS AND GUIDING POLICIES 64 SEEKING PUBLIC INPUT TO REFINE SCENARIOS FOR OUR FUTURE 66

CHAPTER 4 HIGHLIGHTS GOALS AND GUIDING POLICIES 64 SEEKING PUBLIC INPUT TO REFINE SCENARIOS FOR OUR FUTURE 66 04 CHAPTER 4 HIGHLIGHTS GOALS AND GUIDING POLICIES 64 SEEKING PUBLIC INPUT TO REFINE SCENARIOS FOR OUR FUTURE 66 SCENARIOS FOR THE FUTURE: IT S OUR CHOICE 68 CREATING A PLAN FOR OUR FUTURE The RTP/SCS

More information

3. STATION SPACING AND SITING GUIDELINES

3. STATION SPACING AND SITING GUIDELINES 3. STATION SPACING AND SITING GUIDELINES The station spacing and siting guidelines are summarized in Table 3-1. Table 3-1 also includes benchmark information for local transit service and express bus as

More information

Metrorail and Metrobus Fare Structure Model

Metrorail and Metrobus Fare Structure Model Finance & Administration Committee Information Item III-A October 13, 2011 Metrorail and Metrobus Fare Structure Model Page 3 of 41 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Staff Report. Allocation of Congestion Management and Air Quality Improvement Program Funding

Staff Report. Allocation of Congestion Management and Air Quality Improvement Program Funding ITEM 7F Staff Report Subject: Contact: Allocation of Congestion Management and Air Quality Improvement Program Funding Eric Cowle, Transportation Program Manager (ecowle@cvag.org) Recommendation: Authorize

More information

Honorable Mayor and Members of the City Council. Submitted by: Dan Marks, Director, Planning and Development

Honorable Mayor and Members of the City Council. Submitted by: Dan Marks, Director, Planning and Development Office of the City Manager To: From: Honorable Mayor and Members of the City Council Phil Kamlarz, City Manager Submitted by: Dan Marks, Director, Planning and Development Subject: EXECUTIVE SUMMARY Senate

More information

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012 2030 Transportation Policy Plan SUMMARY PRESENTATION Land Use Advisory Committee November 15, 2012 Today s Topics Transportation Policy Plan (TPP) Requirements and Background Current TPP Policies, Issues

More information

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS FINAL REPORT SEPTEMBER 2010 TABLE OF CONTENTS 1.0 INTRODUCTION 1 2.0 EXISTING TRAFFIC CONDITIONS 2 3.0 FUTURE TRAFFIC CONDITIONS 3 4.0 POTENTIAL IMPACTS

More information

Transit Service Guidelines

Transit Service Guidelines G R E AT E R VA N CO U V E R T R A N S P O RTAT I O N A U T H O R I T Y Transit Service Guidelines PUBLIC SUMMARY REPORT JUNE 2004 Greater Vancouver Transportation Authority TRANSIT SERVICE GUIDELINES

More information

CHAPTER IV REQUIREMENTS AND GUIDELINES FOR FIXED ROUTE TRANSIT PROVIDERS

CHAPTER IV REQUIREMENTS AND GUIDELINES FOR FIXED ROUTE TRANSIT PROVIDERS Chap. IV-1 CHAPTER IV REQUIREMENTS AND GUIDELINES FOR FIXED ROUTE TRANSIT PROVIDERS 1. INTRODUCTION. The requirements described in this chapter apply to all providers of fixed route public transportation

More information

PUBLIC TRANSIT SERVICE OBJECTIVES AND STANDARDS

PUBLIC TRANSIT SERVICE OBJECTIVES AND STANDARDS PUBLIC TRANSIT SERVICE OBJECTIVES AND STANDARDS 3 Credit: Ozaukee County 3.1 INTRODUCTION To allow a thorough evaluation of the existing transit services offered by Ozaukee County and any alternative transit

More information

Section 7 Environmental Constraints

Section 7 Environmental Constraints Section 7 Environmental Constraints i Yakima Valley Metropolitan and Regional Transportation Plan Public Comment DRAFT 1/27/2016 Environmental Constraints Analysis A programmatic-level review of potential

More information

Chapter 5 Transportation Draft

Chapter 5 Transportation Draft Chapter 5 Transportation Draft Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the

More information

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices DRFT ppendices MIS 8-05 - ppendices ppendices ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK] DRFT ppendix Tier Detailed Evaluation Tables MIS 8-05 - ppendix ppendix ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK]

More information

2040 Transportation Policy Plan Amendment #1

2040 Transportation Policy Plan Amendment #1 2040 Transportation Policy Plan Amendment #1 Overview Amendment Purpose This 2040 Transportation Policy Plan amendment adds the Riverview Modern Streetcar transitway project to the Current Revenue Scenario.

More information

AT L A N TA B E LT L I N E C I T Y O F AT L A N TA, F U LTO N C O U N T Y, G A

AT L A N TA B E LT L I N E C I T Y O F AT L A N TA, F U LTO N C O U N T Y, G A AT L A N TA B E LT L I N E C I T Y O F AT L A N TA, F U LTO N C O U N T Y, G A T I E R 1 F I N A L E N V I R O N M E N TA L I M PA C T S TAT E M E N T / S E C T I O N 4 ( F ) E VA LUAT I O N U.S. Department

More information

Executive Summary and Staff Recommendation

Executive Summary and Staff Recommendation Executive Summary and Staff Recommendation January 2017 Project Background In 2010, NFTA completed an update to our 2001 Strategic Assessment. This assessment identified four corridors for potential rail

More information

4.0 Coordination and Consultation 4.0 Coordination and Consultation

4.0 Coordination and Consultation 4.0 Coordination and Consultation 4.0 Coordination and Consultation 4.0 Coordination and Consultation DART RAIL TO ROWLETT Connecting Communities 4.0 COORDINATION AND CONSULTATION This Chapter provides an overview of the public involvement

More information