FEASIBILITY ANALYSIS ON THE INSTALLATION OF A WIND TURBINE IN SMALL ISLAND OF THAILAND

Size: px
Start display at page:

Download "FEASIBILITY ANALYSIS ON THE INSTALLATION OF A WIND TURBINE IN SMALL ISLAND OF THAILAND"

Transcription

1 FEASIBILITY ANALYSIS ON THE INSTALLATION OF A WIND TURBINE IN SMALL ISLAND OF THAILAND Mr.Watthana Limpananwadi System Development Division Provincial Electricity Authority 2 Ngam Wong Wan Rd., Chatuchak, Bangkok, Thailand, 19 Tel wlimpanan@pea.co.th Mr.Warich Khun-Aksorn System Development Division Provincial Electricity Authority 2 Ngam Wong Wan Rd., Chatuchak, Bangkok, Thailand, 19 Tel boypotter@yahoo.com Assoc. Prof. Dr. Worawit Tayati Department of Electrical Engineering Chiang Mai University, Chiang Mai, Thailand 52 worawit@eng.cmu.ac.th Abstract In Thailand, there are a number of small mountainous areas and islands far away from the distribution network, which are under the responsibility of the Provincial Electricity Authority (PEA). To meet the Royal Thai Government policy to supply electricity to these regions, the electricity generation using diesel generator is employed. At the moment, due to higher oil price and lower price of energy sale as compared to the energy production cost, PEA faces a huge loss on such electricity generation about hundreds million Baht per year. Therefore, to decrease such loss, the electricity generation using renewable energy is introduced in the site with potential resource. The paper presents a feasibility analysis on the installation of a wind turbine in a small island. A case study at Ko Tao supplied with a set of diesel generators is investigated. Site survey had been conducted and processed to select the suitable site for the wind turbine installation. Furthermore, the wind data obtained from the wind monitoring at the special site about one year were analyzed to ensure that the wind performance is reasonable. Moreover, the technical, financial and economic analysis was carried out and discussed in detail. Keywords: Wind Turbine, Renewable Energy, Diesel Generator, Distribution Network. 1. Introduction At the end of 22, there was a total wind turbine capacity of 31, MW installed to generate electricity power worldwide [1]. It was predicted that it would be 1,2 GW in 22. The development of wind energy technology is focused on rated power, rotor diameter, hub height, potential annual and energy yield. The rated power of wind turbine was upgraded from 3 kw to 5 MW in 198 and 25 respectively with bigger rotor diameter and higher hub height. There are many researches concerning technical and environmental issues of small wind turbine application. To improve a weak system, the wind turbines using synchronous generators are proposed with both woundfield and permanent magnet rotors, which they can control the output power factor [2]. However, the impacts of wind turbine on distribution system must be considered. The impact of induction wind turbine on voltage stability is mentioned in [3]. It shows that the voltage stability is affected by the capacity of wind turbine when connected to a weak network. Moreover, the power injected from a small wind turbine into a DC bus is presented in [4]. The concept is used for installing small windmills on their own properties to offset the load. Besides, the environmental issues of wind turbine are important when it located close to community [5]. In Thailand, the wind energy is applied typically for water pumping purposes in remote areas. In 1983, the wind energy application for electricity generation was experimented by the Electricity Generation Authority of Thailand (EGAT) in Phuket Province. Four small wind turbines: 18.5, 2, 1 and.83 kws respectively were installed in a pilot station at Prom Thep Cape [6]. The result achieved indicated that the wind energy generation worked reasonably well but there were some problems on procuring spare parts from abroad in certain cases and on broken parts of wind turbine such as wheel blade and ball bearings. After that, in the early 199s, the wind turbines were applied to connect to the grid system. For the PEA responsibility areas, a wind turbine is being applied to the remote areas. Basically, they are supplied by a set of diesel generators. Due to sudden increase in oil price and cheap energy sale price, it has made a huge loss on the energy sale. This paper presents a feasibility analysis on the installation of a small wind turbine in small island of Thailand. Due to high fuel oil price and fixed energy sale price controlled by the government, PEA is now operating at a loss. Therefore, a small wind turbine is applied to a remote island supplied by a set of diesel generators to decrease the loss and fuel oil consumption. The paper starts with the electricity generation for the remote area in Thailand. Then, the system descriptions of case study and wind performance monitoring are discussed. After that, the financial and economic of a small wind turbine installation is analyzed in detail. 2. Electricity Generation for Remote Area PEA is a government enterprise under the Ministry of Interior. The PEA's major task is to supply electricity to all regions in Thailand, accounting for 99 percents of the country with the exception of Bangkok, Nonthaburi and Samut Prakran Provinces, and serve a basic infrastructure of the country according to the government policy with the emphasis on the efficiency, stability and safety power [7]. To meet the above policy, the diesel generator is applied to the remote areas with difficulty in grid connection. Presently, PEA has a total of 12 remote small areas including island and mountainous area [8]. The energy

2 production during Jan to Sep 25 is nearly 13.3 million kwh. In accordance with the government policy, the energy sale price for all residential customers is currently fixed at roughly 3. Baht/kWh. However, the energy production cost of PEA s diesel generator is 1.5 Baht/kWh, derived from the PEA s average diesel generator consumption at.286 liter per kwh and diesel oil price including transportation at 3 Baht/liter. From the energy production mentioned earlier, it is about 1 million Baht worth of PEA s loss. As a result, it makes a loss of worth several hundreds of million Bath per year. Therefore, the hybrid system: diesel generator and electricity generation using renewable energy is taken into account. Ko Nangyuan 3 KVA 1 KVA 12 PIC 3. Research Methodologies The purpose of this study is to investigate the feasibility of the wind turbine installation in the small island to reduce the loss. Details of activities carried out in each stage are given below. Site survey; a field trip to the area had been conducted to obtain the site for wind monitoring and installation. Face to face interviews with local village headmen, Sub-District Administration Organization and villagers were performed to collect the key data on site selection. Wind performance monitoring; after obtaining the site, the wind data was recorded to investigate the wind performance by using data loggers. Wind performance analysis; the wind data was analyzed to evaluate the potential of the wind energy production. Technical, financial and economic analysis; the existing system performance was monitored and analyzed. Then, the analysis of financial and economic is assessed. 4. Case Study 4.1 System Descriptions Ko Tao is a small tropical island with incredible snorkeling and scuba diving, a rich jungle in the centre and surrounded by remarkably quiet, palm tree laced beaches. It is located about 75 km southeast of Chumphon Province with a famous tourist attraction and environmental issues. The 33 kv system is supplied by a set of 6 small diesel generators with a total capacity of approximately 3, kw operated by PEA. The system load is about 75 kw as of September 25. The demand growth is controlled by PEA with limit of meter size. The map and distribution system is shown in Fig.1. The island is fully mountainous area and tropical forest. There is no electrification in some areas since it is difficult to extent the grid and being of diesel generation limit. 4.2 Site Selection From the site survey, there are few sites suitable for wind turbine installation due to high land price. At the beginning, the sites were processed and selected using wind flow directions and available grid connection. At the sites the wind speed was also measured using a potable cup anemometer. Finally, the appropriate site was selected as given in Fig.1. It is located at the southern area of island and far away from distribution system nearly 1 km. 25 KVA 3 KVA Diesel Power Plant 5 PIC 5 PIC 3 KVA 5 PIC 5 KVA 5 PIC 3 KVA 5 PIC 5 PIC Wind Turbine Location 5 PIC 3 KVA 3 KVA 3 KVA Figure1 Map and Distribution System of Ko Tao 4.3 Wind Performance Monitoring In November 22, a wind assessment system was installed at the site to confirm that it is suitable for a wind turbine location. The system is consisted of a tilt-up tower with 4 meters in height, instrument, sensors and accessories. During Nov to Dec 22, the wind data was analyzed to ensure that the data achieved was accurate. Afterward, the wind data was recorded in 23. The wind performance data obtained are processed and analyzed using MicroSite program [9] as follows; Monthly Gust Speed, Monthly Average Wind Speed and Monthly Temperature The monthly gust speed, average wind speed and temperature observed are shown in Fig.2. The minimum and maximum gust wind speed is m/s in April and m/s in August respectively. Besides, it is found that the average of monthly wind speed is about 5.38 m/s. In addition, it is worth noting that the temperature in April is very high but the wind speed is very low. Annual Wind Speed To show the temporal distribution of wind speeds and the frequency of varying wind directions [9], a graph so-called wind rose is employed as demonstrated in Fig.3. From data obtained, the prevailing wind direction is NE and SW. Besides, it is evident that the wind speed and wind energy achieved at SW is more than at NE.

3 Wind Speed (m/s) Jan Feb Mar Apr May Jun Jul Aug Months Sep Oct Nov Dec Temperature ( C) Monthly Gust Speed Monthly Average Wind Speed Monthly Temperature Figure 2 Monthly Gust Speed, Average Wind Speed and Temperature Site Number: 5 Start Date: End Date: W NW.15 SW N Outer numbers are averaged TIs for that sector Inner circle = % Outer circle = 3% NE.2 SE S Figure 3Wind Rose for Annual Wind Direction Site Number: 5 Start Date: End Date: Diurnal Wind Speed Pattern E Percent of Total Time Percent of Total Wind Energy turbine and energy generation selected will be discussed in the next section Wind Speed Frequency Distribution (%) < >15 Wind Speed (m/s) Figure 5 Wind Speed Frequency Distribution (%) 4.4 Wind Size Selection The size consideration of wind turbine is dependent on the budget and wind performance data obtained. The project budget is supported from the government, which is available under the government s Energy Conservation Promotion Fund (ECON Fund) and PEA investment. To stimulate the wind energy market in Thailand, the large commercial size is preferred. Finally, one large unit of 1.2 MW wind turbine classified in [1], is selected to generate power for this site as the power curve provided by manufacturer shown in Fig.6. Besides, the wind turbine size is designed according to the system load. In theory, the wind power is proportional to the area of windmill being swept by the wind, the cube of the wind speed and air density, which varies with altitude [11] Cumulative Frequency Wind Speed in M/S Wind Speed (m/s) Hours Figure 4 Daily Wind Speed Pattern The average of daily wind speed in 23 is shown in Fig.4. It is important to note that the peak wind speed is occurred during hrs and hrs. Wind Speed Frequency Distribution (%) The most important wind data is the wind speed frequency distribution as given in Fig.5. It shows the frequency of wind speed occurred. At 6 m/s wind speed was happened with 16.3%. Besides, it is obvious that at cut-in speed, in general at 3 m/s, the wind energy can not be generated roughly 11%, see the cumulative frequency graph. From the wind performance mentioned, it is clear that the island can be supplied by a wind turbine. The size of wind Power Output (kw) Fig.6 Power Curve of Wind Turbine Applied From the power curve above, the wind performance is described as follows; Cut-in speed at 3m/s: is the lowest wind speed at which a wind turbine begins producing usable power. Rated power at 1,2 kw: is the maximum power output of wind turbine. Cut out speed at 25 m/s: is the highest wind speed at which a wind turbine stops producing power. 4.5 Wind Energy Assessment The wind energy gained from the wind speed frequency distribution in Fig.5 and power curve in Fig.6 is calculated from a summation of the hourly interval of wind speed

4 frequency distribution multiplied by power curve at that wind speed of wind turbine as given in (1). where: 15 E = S n xp n (1) n= 1 E = Wind energy production S = Hourly interval of wind speed frequency distribution P = Power of wind turbine power curve However, the wind speed used for hourly interval in (1) is transformed to (2) because the wind speed was recorded at 4 meters but the hub height of wind turbine preferred is about at 5 meters. Therefore, the wind speed can be estimated by: σ h( x 2) (2) V ( x2) = V ( x1) h( x1) where: V(x 2 ) = Speed transformed to at x 2 meter m/s V(x 1 ) = Speed Recorded at 4 meters m/s h(x 2 ) = Speed measured at x 2 meters in height m h(x 1 ) = Speed measured at 4 meters in height m σ = 1/7 = Therefore, from the wind energy production obtained, CF of the wind energy is 2.55% with total energy production 2,159,319 kwh per year. 5. Feasibility Analysis 5.1 Technical Feasibility To ensure the excellent system reliability and no power quality problems, the system power quality is monitored by using commercial PQ meter at diesel generator bus (23/4 V) within one week. There are two parameters: voltage and frequency investigated because the system is supplied by diesel generation, without harmonic (no electronic interface) according to PEA s power quality standard [6]. However, the harmonic should be analyzed after the wind turbine interconnected to the system if the electronic interface is in use. The voltage and frequency observed is shown in Fig.8 and Fig.9 respectively. From Fig.8, the voltage is in range of PEA s voltage limit ( pu). Similarly, the system frequency monitored is in limit (5 ±.5 Hz), except at the beginning of time, there is an over frequency due to car accident. At the beginning, it would be concluded that the system has a good power quality. The wind energy calculated from (1) and monthly average wind speed is illustrated in Fig.7, which is 12 months of the wind energy productions. It is clear that the wind energy is dependent on the wind speed. For example, in April, the energy is the lowest about 3,7 kwh because the wind speed is very low. On the other hand, the energy generation is the highest in Dec due to the highest wind speed. The capacity factor (CF) is the amount of energy that a facility generates in one year divided by the total amount it could generate if it ran at full capacity [12]. A capacity factor of one implies that the system ran at full capacity for the entire year; a typical wind farm will operate at.25 capacity factor, or 25% [12]. It is calculated form (3) as follow: Figure 8 System Three-Phase Voltage Monitored Within Limits Actual Annual Enery Output CF = Rated Power Output x Operating Time (3) Expected Wind Energy Production Monthly Average Wind Speed Energy (kwh) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Month Figure 7 Expected Wind Energy Wind Speed (m/s) Figure 9 System Frequency Monitored Within Limits 5.2 Financial & Economic Feasibility Nowadays, the annual system energy produced by diesel generators is around 4,464, kwh. As 1.2 MW wind turbine is supplied to the system, the annul energy generated from the wind turbine is about 2,16, kwh or 662, liters of diesel saving. Besides, it is well known that the rate of CO 2, SO x and NO x emission or air pollutions per kwh from stand-alone diesel generators can vary widely depending on generator type, size, and load

5 factors. The gas emission in case of stand-alone diesel generation and diesel generation including 1.2 MW wind turbine is given in Table 1. It is clear that after the wind turbine is interconnected, the gas emission is decreased dramatically. The annual reduction of CO 2, SO x and NO x is 1685., 97. and 1. ton respectively, which is estimated from the wind turbine generation (2,16, kwh). Because it is a pilot project, the typical value of gas emission from electricity generation is assumed as given below in the table 1, which are the typical value. Table 1 Gas Emissions Case A Case B Case Emission (Ton/Year) Reduction (Ton/Year) CO 2 3,482. 1,685. SO x NO x Remarks: Case A = Stand-alone diesel generation Case B = Diesel generation with 1.2 MW wind turbine where, the emission amount of electricity produced: CO 2 =.78 kg/kwh SO x =.5 kg/kwh NO x =.48 kg/kwh In addition, the assumptions of the financial and economic feasibility analysis are as follows: Discount rate: 11% Project duration: 2 years Three cases are analyzed: Case 1, Case 2 and Case 3, by varying the diesel oil price: 28, 3 and 32 Baht respectively. The key financial and economic data are given in Appendix A Financial Feasibility The financial feasibility analysis is focused on the investment cost and benefit achieved from the diesel saving as the 1.2 MW wind turbine connected to the system. The following investment cost factors of the wind turbine installation are considered: Wind turbine equipment and installation Distribution system upgraded Project management Operation and maintenance In a different way, the benefit of the wind turbine installation is only diesel fuel consumption saving. Moreover, the financial indicators employed to explain the project feasibility analysis are: Financial Internal Rate of Return: FIRR Financial Net Present Value: FNPV Benefit to Cost Ratio: B/C Breakeven Tariff Energy Cost The results of financial feasibility analysis are demonstrated in Table 2. It is seen that in Case3, in which the oil price is 32 Baht with the wind energy generation of 2,16, kwh, the project is feasible to implement. The FIRR and B/C is 11.6% and 1.3 respectively. The energy cost is 3.52 Baht per kwh, which is more than the energy price (3. Baht) controlled by the government. In Case1 and Case2, it is not practical to execute because of the terrible financial indicator. For example, the breakeven point of Case2 is -.11 Baht/kWh meaning that the project can be implemented if a subsidy with.11 Baht/kWh is offered. Table 2 Financial Feasibility Analysis Results Financial Indicators Results Case1 Case2 Case3 Annual Energy (kwh) 2,16, 2,16, 2,16, FIRR (%) FNPV (Baht) -14,47,688-4,578,666 5,25,356 B/C Breakeven tariff (Baht/kWh) Energy Cost / kwh (Baht) It can be concluded that the project can be implemented if the diesel oil price is more than 3 Baht Economic Feasibility Similarly, the economic feasibility is investigated by using the investment cost (excluding VAT and Tax) and benefit obtained from the wind turbine generation, which is the same as financial feasibility analysis. Therefore, the key economic indicators are: Economic Internal Rate of Return: EIRR Economic Net Present Value: FNPV Benefit to Cost Ratio: B/C The important indicators of economic feasibility evaluated are demonstrated in Table 2. It is clear that in this project all cases are feasible to be implemented because the indicators shown are reasonable. For example, the EIRR of case 1, case 2 and case 3 is 13.36, and respectively. They are higher than the discount rate. Besides, the ENPVs are positive value and the B/C ratios are more than 1.. Table 2 Economic Feasibility Study Results Economic Indicators Results Case1 Case2 Case3 Annual Energy (kwh) 2,16, 2,16, 2,16, EIRR (%) ENPV 19,169,314 28,998,336 38,827,358 B/C In these circumstances, it can be concluded that following the economic study of this project, it is feasible to install the wind turbine. 6. Conclusions The paper presents a feasibility study on the installation of a wind turbine in a small island of Thailand. Ko Tao is selected as a case study because it is an attractive place for tourists with environmentally friendly. Moreover, PEA makes a loss on the diesel power generation. The site visit had been conducted to choose the site for wind turbine

6 installation and wind performance monitoring. The results obtained indicated that, the wind energy performance is reasonable to install a wind turbine. After that, the results achieved from technical, financial and economic analysis show that the project is feasible to be implemented. Moreover, the impact of wind turbine on technical: stability, power quality etc. and environmental issues: sound, height, visibility, wildlife, public safety, land use and erosion or on the distribution network should be analyzed thoroughly after finished installation. 7. Acknowledgements This work was supported by the Provincial Electricity Authority (PEA). In addition, the village headmen, Sub- District Administration Organization and villagers at Ko Tao involved are appreciatively acknowledged. References [1] The World Wind Energy Association. 23. Status and Perspective of the Wind Industry: An International Overview. Retrieved January 23, 26 from w.pdf [2] Green, A.M.; Jenkins, N Connection of small wind-turbines in weak grids. IEE Colloquium on Small Wind Power Systems (Digest No. 1996/175). 23 Oct pp 3/1-3/3. [3] Jenkins, N. and Strbac, G Impact of embedded generation on distribution network voltage stability. IEE Colloquium on Voltage Collapse. pp. 9/1-9/4. [4] Turner, A.R.; Sathiakumar, S.; Lee, Y.S. 24. Injecting power from a small wind turbine into a DC bus. PowerCon 24, International Conference on Power System Technology, Vol. 2, Nov 24, pp [5] Driesen, J.; De Brabandere, K.; D'hulst, R.; Belmans, R. 25. Small wind turbines in the built environment: opportunities and grid-connection issues. IEEE Power Engineering Society General Meeting, June 12-16, 25, pp [6] Electricity Generating Authority of Thailand. 23. Green Power: Wind Power. Retrieved January 23, 26 from [7] Provincial Electricity Authority. 2. PEA s regulations for Service Quality. [8] Provincial Electricity Authority. 25. PEA s Diesel Power Generation Data. [9] NRG System, Inc MicroSite Version 2.7 Program. ( [1] Manwell J.F., McGowan. J.G. and Reogers A.L. 22. Wind Energy Explained. London: John Wiley& Sons, Ltd. [11] Intermediate Technology Development Group (ITDG). Wind Electricity Generation. Retrieved November 26, 25 from wind_electricity_generation.pdf [12] Neison, V. and Rohatgi, J.S Wind Characteristic: An Analysis for the Generation of Wind Power. Alternative Energy Institute, West Texas A&M University [13] TEXAS' Renewable Energy Resource. 26. Glossary. Retrieved January 23, 26 from Appendix A Financial and Economic Data Table A.1 Financial Data No. Project Specification &Assumption Factors MW wind turbine cost 56,, Baht 2 Import Taxes 1 % of Equipment 5,6, Baht 3 Wind turbine foundation 12,, Baht 4 Wind turbine transportation 14,, Baht 5 Wind turbine installation 14,, Baht 6 Vat (7%) 6,132, Baht 7 Underground HV. distribution system extension 4,, Baht 8 Overhead HV. distribution system extension 4,5, Baht 9 Transformer and installation 1,5, Baht 1 Distribution system upgraded 1,, Baht 11 Diesel generator efficiency 3.5 kwh/l 12 Fuel saving from excess electricity reduction 615,4 L 13 Project management - Year1 2,887,2 Baht 14 Project management - Year2 3,729,2 Baht 15 Project management - Year3 1,51,6 Baht 16 Annual Maintenance.4 Baht/kWh 17 Annual output from wind turbine 2,16, kwh 18 Annual output diesel generation 2,325,5 kwh 19 Annual maintenance cost increase 2.5 %

7 Table A.2 Economic Data No. Project Specific &Assumption Factors MW wind turbine cost 56,, Baht 2 Wind turbine foundation 12,, Baht 3 Wind turbine transportation 14,, Baht 4 Wind turbine installation 14,, Baht 5 Underground HV. distribution system extension 4,, Baht 6 Overhead HV. distribution system extension 4,5, Baht 7 Transformer and installation 1,5, Baht 8 Distribution system upgraded 1,, Baht 9 Annual Maintenance.4 Baht/kWh 1 Annual output from wind turbine 2,16, kwh 11 Annual output diesel generation 2,325,5 kwh 12 Diesel generator efficiency 3.5 kwh/l 13 CO2 Emission / kwh of Diesel Generation.78 kg/kwh 14 SOx Emission/kWh of Diesel Generation.5 kg/kwh 15 NOx Emission/kWh of Diesel Generation.48 kg/kwh 16 Ton of CO2 Reduction 1,684.8 Ton 17 Ton of SOx Reduction 97.2 Ton 18 Ton of NOx Reduction 1.37 Ton 19 Unit Cost of CO2 Reduction.63 Baht/kWh 2 Unit Cost of SOx Reduction.5 Baht/kWh 21 Unit Cost of Nox Reduction.14 Baht/kWh 22 Fuel saving from Excess electricity reduction 615,4 Liter 23 Project Management - Year1 2,887,2 Baht 24 Project Management - Year2 3,729,2 Baht 25 Project Management - Year3 1,51,6 Baht 26 Annual Maintenance Cost Increase 2.5 %

The Derivation of Efficiency Equation of the Prototype of Pico Wind Turbine Produces the Electricity

The Derivation of Efficiency Equation of the Prototype of Pico Wind Turbine Produces the Electricity Available online at www.sciencedirect.com Procedia Engineering 3 (0) 994 999 I-SEEC0 The Derivation of Efficiency Equation of the Prototype of Pico Wind Turbine Produces the Electricity S. Jugsujinda a*,

More information

Overcoming Barriers to Power Purchasing from Very Small Renewable Energy Producers

Overcoming Barriers to Power Purchasing from Very Small Renewable Energy Producers from Very Small Renewable Energy Producers W. *, W. Limpananwadi**, B. Kamonsin** and P. Sripattananon** * Department of Electrical Engineering, Chiang Mai University, Chiang Mai 50200 THAILAND Email:worawit@doe1.eng.cmu.ac.th

More information

Potential Impact of Biomass Burning on Urban Air Quality: Case-study of Chiang Mai

Potential Impact of Biomass Burning on Urban Air Quality: Case-study of Chiang Mai Potential Impact of Biomass Burning on Urban Air Quality: Case-study of Chiang Mai Sébastien Bonnet, Narongchai Suwanprik and Savitri Garivait The Joint Graduate School of Energy and Environment Chiang

More information

COST ANALYSIS OF RENEWABLE ENERGY FOR POWER SUPPLY FOR REMOTE AREA IN YEMEN : A CASE STUDY FOR SOCOTRA ISLAND

COST ANALYSIS OF RENEWABLE ENERGY FOR POWER SUPPLY FOR REMOTE AREA IN YEMEN : A CASE STUDY FOR SOCOTRA ISLAND COST ANALYSIS OF RENEWABLE ENERGY FOR POWER SUPPLY FOR REMOTE AREA IN YEMEN : A CASE STUDY FOR SOCOTRA ISLAND Saqqaf A. Alkaf, Mohammed A. Muqbel and Salem M. Bin Qadhi + Mechanical Engineering Department,

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org C5-1036 AORC Technical meeting 2014 Solar PV Rooftop System Connection to MEA s Distribution Network: Technic and Economic Aspects Tosak Thasananutariya Metropolitan Electricity

More information

Issarachai Ngamroo. King Mongkut s Institute of Technology Ladkrabang (KMITL) Bangkok, Thailand

Issarachai Ngamroo. King Mongkut s Institute of Technology Ladkrabang (KMITL) Bangkok, Thailand Issarachai Ngamroo King Mongkut s Institute of Technology Ladkrabang (KMITL) Bangkok, Thailand knissara@kmitl.ac.th Vancouver 2010 Microgrid Symposium on Microgrid Vancouver, BC, Canada July 21-22, 2010

More information

DETERMINATION OF POWER GENERATION CAPACITY OF WIND TURBINE

DETERMINATION OF POWER GENERATION CAPACITY OF WIND TURBINE DETERMINATION OF POWER GENERATION CAPACITY OF WIND TURBINE HARMON EBI OKILO AND ONITA CHUKWUKA LOVEDAY Department of Electrical Engineering, Federal Polytechnic, Ekowe, Bayelsa State, Nigeria. Abstract

More information

A. Behaviour of the Wind

A. Behaviour of the Wind Preliminary Assessment of the Potential for Wind Farm Development in Southern Sri Lanka Supervised by: Nishantha Nanayakkara, Yushan De silva, Amila Fernando, Chamila Fernando, Nawoda Gunawardhana, Sandika

More information

Planning of Sustainable Renewable Energy System for Remote Village Electrification

Planning of Sustainable Renewable Energy System for Remote Village Electrification for Remote Village Electrification *N., **D. Tayati, ** W. Pruksikanun, **P. Kanchanakaroon, **T. Komolmit, ** Y. Srisiriuthaiwong and **W.Tayati * Provincial Electricity Authority, 200 Ngam Wong Wan Road,

More information

Analysis of Wind Speed Data in East of Libya

Analysis of Wind Speed Data in East of Libya Analysis of Wind Speed Data in East of Libya Abdelkarim A. S, D. Danardono, D. A. Himawanto, Hasan M. S. Atia Mechanical Engineering Department, SebelasMaret University, Jl. Ir. Sutami 36ASurakarta Indonesia

More information

Evaluation of Solar PV and Wind Alternatives for Self Renewable Energy Supply: Case Study of Shrimp Cultivation

Evaluation of Solar PV and Wind Alternatives for Self Renewable Energy Supply: Case Study of Shrimp Cultivation Available online at www.sciencedirect.com ScienceDirect Energy Procedia 88 (2016 ) 462 469 CUE2015-Applied Energy Symposium and Summit 2015: Low carbon cities and urban energy systems Evaluation of Solar

More information

Thailand Power Development Plan ( ) TANONGSAK WONGLA

Thailand Power Development Plan ( ) TANONGSAK WONGLA Thailand Power Development Plan (2010-2030) TANONGSAK WONGLA August 2013 GOV. POLICY Structure of Thailand Power Sector Regulators EGAT (44%) IPPs (38%) Imports (7%) SPPs (10%) VSPPs (

More information

ASHENDEN WIND TURBINE TRIAL: PHASE I RESULTS

ASHENDEN WIND TURBINE TRIAL: PHASE I RESULTS ASHENDEN WIND TURBINE TRIAL: PHASE I RESULTS PROJECT TEAM London Borough of Southwark: Tony Moseley, Sustainable Development and Infrastructure Manager; Client; data dissemination. Brian Dunlop Associates

More information

AN AC COUPLED PV/WIND/DIESEL MICROGRID SYSTEM IMPLEMENTED IN A REMOTE ISLAND IN THE REPUBLIC OF MALDIVES

AN AC COUPLED PV/WIND/DIESEL MICROGRID SYSTEM IMPLEMENTED IN A REMOTE ISLAND IN THE REPUBLIC OF MALDIVES AN AC COUPLED PV/WIND/DIESEL MICROGRID SYSTEM IMPLEMENTED IN A REMOTE ISLAND IN THE REPUBLIC OF MALDIVES 1 The President inaugurates the Hybrid Renewable Energy Pilot Project implemented at North Thiladhunmathi

More information

PERFORMANCE EVALUATION OF PS-600 kw WIND TURBINE

PERFORMANCE EVALUATION OF PS-600 kw WIND TURBINE Proceedings of the IASTED International Conference Power and Energy Systems (AsiaPES 2013) April 10-12, 2013 Phuket, Thailand PERFORMANCE EVALUATION OF PS-600 kw WIND TURBINE Jyoti D. Nimbal SGI, Electrical

More information

Ashenden House Wind Turbine Trial. CIBSE ASHRAE Seminar May 2009

Ashenden House Wind Turbine Trial. CIBSE ASHRAE Seminar May 2009 Ashenden House Wind Turbine Trial CIBSE ASHRAE Seminar May 2009 PROJECT TEAM London Borough of Southwark: Tony Moseley, Sustainable Development and Infrastructure Manager; Client; data dissemination. Brian

More information

Electric Forward Market Report

Electric Forward Market Report Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08

More information

Ultra high wind penetration in simple wind-diesel power systems in Cape Verde

Ultra high wind penetration in simple wind-diesel power systems in Cape Verde Ultra high wind penetration in simple wind-diesel power systems in Cape Verde Per Nørgård Risø DTU, Technical University of Denmark pern@risoe.dtu.dk João Fonseca Electra, Cabo Verde j.fonseca@electra.cv

More information

Modeling and Simulation of Wind Turbine under the Condition Prevailing in and around Jodhpur District

Modeling and Simulation of Wind Turbine under the Condition Prevailing in and around Jodhpur District Modeling and Simulation of Wind Turbine under the Condition Prevailing in and around Jodhpur District Harish Kumar Khyani Associate Professor Piyush Rai Pankaj Vaishnav Praful Bohra ABSTRACT Wind energy

More information

USAP, AntNZ, Meridian Energy, Powercorp, RPSC, DOE-NSF Collaboration & The Ross Island Wind Project

USAP, AntNZ, Meridian Energy, Powercorp, RPSC, DOE-NSF Collaboration & The Ross Island Wind Project USAP, AntNZ, Meridian Energy, Powercorp, RPSC, DOE-NSF Collaboration & The Ross Island Wind Project Owen Roberts 2012 Polar Technology Conference with thanks to Scott Bennett, Meridian Power; Ian Miller

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

Updates on the feed-in Tariff scheme in Thailand

Updates on the feed-in Tariff scheme in Thailand Updates on the feed-in Tariff scheme in Thailand Monday 29 April, 2013 Bangkok Convention Centre at Central World Bangkok, THAILAND Prof. Emeritus Dr. Direk Lavansiri Chairman of the Energy Regulatory

More information

THE BUSINESS CASE FOR WIND TURBINES

THE BUSINESS CASE FOR WIND TURBINES 20 THE BUSINESS CASE FOR WIND TURBINES TECHNOLOGY OVERVIEW Wind turbines convert the kinetic energy generated by the wind into rotational mechanical energy to generate electricity. The power available

More information

CO2, SO2 and NOX Emission Rates. March 15, 2018

CO2, SO2 and NOX Emission Rates. March 15, 2018 March 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com 1 P age Introduction To support the efforts of regulators, stakeholders, and other interested parties as they work towards achieving

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org C4-1059 AORC Technical meeting 2014 Case Study of Micro Power Grid Applications in Remote Rural Area of Thailand SUMMARY Payon Punjad, Pongsakorn Yuthagovit, Saranyphong Atchvsunthon

More information

Urban Wind Turbines: A Feasibility Study

Urban Wind Turbines: A Feasibility Study Urban Wind Turbines: A Feasibility Study Ben Dymock And Stephen Dance Urbines Urbines: The Issues Urban Wind Turbines Urbines Rooftop installation for energy generation Uncertainty of wind flow and knock

More information

SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM

SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM (Thailand, July 2013) The Thai government has recently introduced a generous subsidy scheme involving Feed in Tariffs. This means that you get paid a premium rate

More information

Small Wind Systems for Village Power: An Update

Small Wind Systems for Village Power: An Update Small Wind Systems for Village Power: An Update Village Power 98 Washington, DC Oct. 6-8, 1998 Michael Bergey Bergey Windpower Co. < mbergey@bergey.com > Modern Small Wind Turbines: High Tech, High Reliability,

More information

Peter Randall Solar Kingdom Ltd

Peter Randall Solar Kingdom Ltd Peter Randall Solar Kingdom Ltd How is Solar Doing? How is Solar Doing? Now an Established Industry How is Solar Doing? Now an Established Industry UK a Major Market Estimated Total installed capacity

More information

Viability of Micro Wind Turbines in the Urban Environment

Viability of Micro Wind Turbines in the Urban Environment Viability of Micro Wind Turbines in the Urban Environment World Renewable Energy Forum WREF/WREN May 13-17, 2012, Denver, Colorado Ghanim Putrus Reader in Electrical Power Engineering Power and Wind Energy

More information

Wild Horse Solar Photovoltaic Project

Wild Horse Solar Photovoltaic Project Wild Horse Solar Photovoltaic Project Steven J. St.Clair Manager Renewable Assets Phone: 425-462-3057 Email: steven.stclair@pse.com November 19, 2009 Agenda Introduction PSE Renewable Energy Facilities

More information

Carbon Free Islands in South Korea

Carbon Free Islands in South Korea Carbon Free Islands in South Korea Dong Wook(Dylan) Kim Senior Manager LG CNS 17 th Oct. 2015 I. Activities and Policies in Korea II. Case Studies 1) Jeju Island 2) Ulleung Island 3) Jo & Geomun Islands

More information

INSTITUTE FOR SUSTAINABLE FUTURES PARKES SHIRE COUNCIL: SMALL WIND SITE ASSESSMENT

INSTITUTE FOR SUSTAINABLE FUTURES PARKES SHIRE COUNCIL: SMALL WIND SITE ASSESSMENT INSTITUTE FOR SUSTAINABLE FUTURES PARKES SHIRE COUNCIL: SMALL WIND SITE ASSESSMENT 2012 ABOUT THE AUTHORS The Institute for Sustainable Futures (ISF) was established by the University of Technology, Sydney

More information

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends

More information

Leading Insights into Solar

Leading Insights into Solar Leading Insights into Solar Fong Wan Senior Vice President, Energy Procurement Pacific Gas and Electric Company CalSEIA - SolarTech Summit May 7, 2009 Agenda California s Clean Energy History Renewable

More information

Feasibility of Wind Power Technology Schemes in St. Martin s Island of Bangladesh

Feasibility of Wind Power Technology Schemes in St. Martin s Island of Bangladesh Paper ID: ET-P19 Feasibility of Wind Power Technology Schemes in St. Martin s Island of Bangladesh Rasedul Hasan 1, Md. Abu Saaklayen 2, Farjana Nasim 3, Md. Tajul Islam 4, Md. Abu Shahab Mollah 5 1,2,3

More information

Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang

Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang Renewable curtailment in China All ready to generate but no place to go RE curtailment in China TWh 100 90 80 70 60

More information

Reducing the Carbon Footprint of the Hyannis WPCF:

Reducing the Carbon Footprint of the Hyannis WPCF: Reducing the Carbon Footprint of the Hyannis WPCF: Through Renewable Energy Production and Energy Efficiency Measures Rip Copithorn PE, BCEE Water Technology Leader Marc Drainville PE, BCEE, LEED AP Senior

More information

Pumped hydro Storage Plants

Pumped hydro Storage Plants Pumped hydro Storage Plants Olivier Teller, Product Director PSP 15 Nov 2012 PSP >130 GW (99% world electricity storage) Market: 6 GW/year Europe: ~1.5GW/year 100 years / illimited cycle numbers ~1000

More information

WIND ENERGY RESOURCE ASSESSMENT: A CASE STUDY

WIND ENERGY RESOURCE ASSESSMENT: A CASE STUDY WIND ENERGY RESOURCE ASSESSMENT: A CASE STUDY Norman Maphosa. National university of Science and Technology, Department of Technical Teacher Education, NUST, Box AC 939, Ascot, Bulawayo, Zimbabwe. Tel:

More information

THE SIMULATION OF PHOTOVOLTAIC POWER GENERATION AND WIND POWER GENERATION ON THE HYDRID ELECTRICITY SUPPLY SYSTEM OF A BUILDING

THE SIMULATION OF PHOTOVOLTAIC POWER GENERATION AND WIND POWER GENERATION ON THE HYDRID ELECTRICITY SUPPLY SYSTEM OF A BUILDING THE SIMULATION OF PHOTOVOLTAIC POWER GENERATION AND WIND POWER GENERATION ON THE HYDRID ELECTRICITY SUPPLY SYSTEM OF A BUILDING Masafumi Terawaki and Isamu Suzuki Sanki Engineering Co.,Ltd. 1742-7,Simoturuma,Yamato-City,Kanagawa,242-1,Japan

More information

Woking. q business confidence report

Woking. q business confidence report Woking q1 business confidence report Woking q1 report headlines saw a new record in company registrations in Woking when compared to any previous. was a record quarter for company registrations in Woking

More information

ONTARIO ENERGY REPORT Q2 2018

ONTARIO ENERGY REPORT Q2 2018 ONTARIO ENERGY REPORT Q APRIL JUNE OIL AND NATURAL GAS Regular Gasoline and Diesel Provincial Retail Prices ($/L) Regular Gasoline $1.3 Diesel $1.7 Source: Ministry of Energy, Northern Development and

More information

Impact of Wind Energy System Integration on the Al-Zawiya Refinery Electric Grid in Libya

Impact of Wind Energy System Integration on the Al-Zawiya Refinery Electric Grid in Libya Journal of Power and Energy Engineering, 26, 4, -2 http://www.scirp.org/journal/jpee ISSN Online: 2327-59 ISSN Print: 2327-588X Impact of Wind Energy System Integration on the Al-Zawiya Refinery Electric

More information

ONTARIO ENERGY REPORT Q1 2018

ONTARIO ENERGY REPORT Q1 2018 ONTARIO ENERGY REPORT Q1 018 JANUARY MARCH 018 OIL AND NATURAL GAS Regular Gasoline and Diesel Provincial Retail Prices ($/L) Regular Gasoline $1.3 Diesel $1.3 Source: Ministry of Energy Fuel Prices Natural

More information

Optimizing and Economical Assessment of the Utilization of Photovoltaic Systems in Residential Buildings: The Case of Sari Station, Northern of Iran

Optimizing and Economical Assessment of the Utilization of Photovoltaic Systems in Residential Buildings: The Case of Sari Station, Northern of Iran Australian Journal of Basic and Applied Sciences, 6(8): 133-138, 2012 ISSN 1991-8178 Optimizing and Economical Assessment of the Utilization of Photovoltaic Systems in Residential Buildings: The Case of

More information

A New Type of Hybrid Groundwater Energy System

A New Type of Hybrid Groundwater Energy System This case-history is about: A New Type of Hybrid Groundwater Energy System by Todd Giddings, Ph.D., P.G. My 10,000 square foot office building Located in State College, PA (5,600 hdd s) Constructed in

More information

Techno-economic feasibility study of solar and wind based Irrigation Systems in Northern Colombia

Techno-economic feasibility study of solar and wind based Irrigation Systems in Northern Colombia Techno-economic feasibility study of solar and wind based Irrigation Systems in Northern Colombia by Javier Cuellar September 2014 1 Table of Content Introduction Background The case study area Methods

More information

ENERGY SELF SUFFICIENCY WITH RENEWABLE SOURCES BIOMASS AND WIND IN THE REHABILITATION PROJECTOF AN OLD RURAL BUILDING COMPLEX IN SICILY (ITALY)

ENERGY SELF SUFFICIENCY WITH RENEWABLE SOURCES BIOMASS AND WIND IN THE REHABILITATION PROJECTOF AN OLD RURAL BUILDING COMPLEX IN SICILY (ITALY) ENERGY SELF SUFFICIENCY WITH RENEWABLE SOURCES BIOMASS AND WIND IN THE REHABILITATION PROJECTOF AN OLD RURAL BUILDING COMPLEX IN SICILY (ITALY) Paola Caputo paola.caputo@polimi.it Politecnico di Milano,

More information

CO2, SO2 and NOX Emission Rates. August 21, 2015

CO2, SO2 and NOX Emission Rates. August 21, 2015 August 21, 2015 This page is intentionally left blank. PJM 2015 www.pjm.com 1 P age Introduction In recent years, federal and state environmental regulations have applied or will apply more stringent restrictions

More information

Microturbine CHP for Microgrids Microgrid2017

Microturbine CHP for Microgrids Microgrid2017 Microturbine CHP for Microgrids Microgrid2017 Why Microturbines for Microgrids? Proven: Over 3,000 sites operating in Stand Alone and Dual Mode One Moving Part; Air Bearings Invertor Based Power Electronics

More information

TECHO-ECONOMIC SIMULATION AND OPTIMIZATION OF 4.5KW WIND/SOLAR MICRO-GENERATION SYSTEM FOR VICTORIAN CLIMATE

TECHO-ECONOMIC SIMULATION AND OPTIMIZATION OF 4.5KW WIND/SOLAR MICRO-GENERATION SYSTEM FOR VICTORIAN CLIMATE TECHO-ECONOMIC SIMULATION AND OPTIMIZATION OF 4.5KW WIND/SOLAR MICRO-GENERATION SYSTEM FOR VICTORIAN CLIMATE Kannan Jegathala Krishnan #1 Velumani Rajan *2 Balasubramani Mohan *3 Akhtar Kalam *4 Aladin

More information

Using Wind Energy to Offset Irrigation Costs: A Systems-Modeling Case Study

Using Wind Energy to Offset Irrigation Costs: A Systems-Modeling Case Study 47th AIAA Aerospace Sciences Meeting Including The New Horizons Forum and Aerospace Exposition 5-8 January 9, Orlando, Florida AIAA 9-549 Using Wind Energy to Offset Irrigation Costs: A Systems-Modeling

More information

NATIONAL PRESENTATION LIBERIA

NATIONAL PRESENTATION LIBERIA Regional Forum on ECOWAS Solar Energy Initiative (ESEI) Dakar, Senegal, 18 21 October 2010 NATIONAL PRESENTATION LIBERIA Augustus V. Goanue Rural & Renewable Energy Agency (Liberia) +231-655-9266 gusgoanue@yaho.com

More information

GIS-maps for identification of miniwind potential in southeast Sweden

GIS-maps for identification of miniwind potential in southeast Sweden IEE/07/797/S12.499715 acronym RURAL-RES Report: GIS-maps for identification of miniwind potential in southeast 2010-09-01 Energy Agency for Southeast Lennart Tyrberg co/ Project manager and wind power

More information

Expanding visibility and controllability requirements: The solar PV case. IEA: Task 14 Lisboa - May 11 th 2011

Expanding visibility and controllability requirements: The solar PV case. IEA: Task 14 Lisboa - May 11 th 2011 Expanding visibility and controllability requirements: The solar PV case IEA: Task 14 Lisboa - May 11 th 2011 Solar generation in Spain today Influence of solar technologies in system operation The new

More information

A Bulk Energy Storage Resource Case Study with 40% RPS in 2024

A Bulk Energy Storage Resource Case Study with 40% RPS in 2024 A Bulk Energy Storage Resource Case Study with 40% RPS in 2024 Shucheng Liu Principal, Market Development 2015-2016 Transmission Planning Process Stakeholder Meeting February 18, 2016 California ISO Public

More information

Hydrogen Applications for Small Islands

Hydrogen Applications for Small Islands Hydrogen Applications for Small Islands Dr. Ε. Ι. Ζoulias Head of RES & H2 Technologies Section Centre for Renewable Energy Sources & Saving Is Hydrogen a Hype? Reasons: Availability of fossil fuels Decrease

More information

Solar Powered Integrated Farming System: Irrigation, Rice Husking and Fishing

Solar Powered Integrated Farming System: Irrigation, Rice Husking and Fishing Solar Powered Integrated Farming System: Irrigation, Rice Husking and Fishing Mohammad Rejwan Uddin Research Assistant, Department of EEE, IUB SESSION 20 PARALLEL: RENEWABLE ENERGY DAY 3, TUESDAY, 10 JANUARY

More information

Hybrid Energy on St. Helena Island

Hybrid Energy on St. Helena Island Hybrid Energy on St. Helena Island *** Results and Lessons Learned *** The location and situation Saint Helena is a remote island in the middle of the South Atlantic Ocean and is part of the British Overseas

More information

Availability of decentralized inverter concept of PV power system in Ubon Ratchathani, Thailand

Availability of decentralized inverter concept of PV power system in Ubon Ratchathani, Thailand Availability of decentralized inverter concept of PV power system in Ubon Ratchathani, Thailand Panu Tanomvorasin and Prapita Thanarak School of Renewable Energy Technology (SERT), Naresuan University,

More information

Energy Savings Analysis Generated by a Real Time Energy Management System for Water Distribution

Energy Savings Analysis Generated by a Real Time Energy Management System for Water Distribution Energy Savings Analysis Generated by a Real Time Energy Management System for Water Distribution Sarah Thorstensen Derceto Ltd, Auckland, New Zealand sthorstensen@derceto.com Abstract Washington Suburban

More information

Union College Combined Cooling, Heat and Power Project

Union College Combined Cooling, Heat and Power Project Union College Combined Cooling, Heat and Power Project Presented by: Mark Donovan, PE Union College, Assistant Director of Utilities Aaron Bolhous, PEng CHA, Project Engineer Agenda Introduction to Union

More information

Powergen International 2003 IMTE AG

Powergen International 2003 IMTE AG Las Vegas, USA 9. 11. December 2003 Advantages of Combined Wind-Biogas Energy Utilization for Distributed Power Generation Presented by Co-authors Miro R. Susta Kurt Stangl Peter Luby IMTE AG Switzerland

More information

Feed-in Tariff Structure Development for the Kingdom of Bahrain for PV Electricity

Feed-in Tariff Structure Development for the Kingdom of Bahrain for PV Electricity Feed-in Tariff Structure Development for the Kingdom of Bahrain for PV Electricity Shaker Haji *, Amal Durazi, and Yaser Al-Alawi * Dr. Shaker Haji, Associate Professor Department of Chemical Engineering,

More information

Presentation by: Victor Austin Midwest Renewable Energy Corporation

Presentation by: Victor Austin Midwest Renewable Energy Corporation Wind Power Presentation by: Victor Austin Midwest Renewable Energy Corporation Outline The Wind Resource Turbine Design US Wind Industry Wind Farm Development The Future The Wind Resource Opportunity

More information

UTILIZATION OF WIND ENERGY

UTILIZATION OF WIND ENERGY 1 UTILIZATION OF WIND ENERGY The Case Study on Analyzing Hourly Wind Data at the City of Makassar and its Surroundings Syukri Himran Fakultas Teknik, Universitas Hasanuddin Makassar, 90245, Indonesia Email:

More information

NJ Solar Market Update

NJ Solar Market Update NJ Solar Market Update March 10, 2015 Renewable Energy Committee Meeting Trenton, NJ Prepared by Charlie Garrison Solar Installed Capacity Data The preliminary installed solar capacity as of 2/28/15 is

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Andhra Pradesh Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports

More information

The Future of Electricity: A Market with Costs of Zero? Marginal

The Future of Electricity: A Market with Costs of Zero? Marginal The Future of Electricity: A Market with Costs of Zero? Marginal Richard Green, IAEE European Conference, 217 1 Supply /MWh Marginal Cost Nuclear CCGT OCGT GW 2 Demand and Supply Prices reflect Marginal

More information

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity Energy Accounting & Education Energy Managers Kermit King School District of La Crosse John Daily School District of Holmen 1 Topics (Electricity) Creating electricity Defining degree days Customer charges

More information

FEASIBILITY STUDY OF THE COST EFFECTIVE HYBRID POWER SYSTEM FOR CUET IN BANGLADESH

FEASIBILITY STUDY OF THE COST EFFECTIVE HYBRID POWER SYSTEM FOR CUET IN BANGLADESH Proceedings of the International Conference on Mechanical Engineering and Renewable Energy 2015 (ICMERE2015) 26 29 November, 2015, Chittagong, Bangladesh ICMERE2015-PI-057 FEASIBILITY STUDY OF THE COST

More information

Technical Talk on HK s Largest Solar Power System at Lamma Power Station

Technical Talk on HK s Largest Solar Power System at Lamma Power Station 15 June 2011 Technical Talk on HK s Largest Solar Power System at Lamma Power Station for HKIE EV Division by C.K. Lau Agenda Fundamentals of PV Project Background Feasibility Study and Site Selection

More information

Understanding the Trade-off: Environmental Costs and Benefits of Industrial Wind Energy Development (with Focus on Eastern US)

Understanding the Trade-off: Environmental Costs and Benefits of Industrial Wind Energy Development (with Focus on Eastern US) Understanding the Trade-off: Environmental Costs and Benefits of Industrial Wind Energy Development (with Focus on Eastern US) Dan Boone & Rick Webb Virginia Wind www.vawind.org Special Session on Bats

More information

FP_C.3_EGAT_ Thai-Laos Cross Border Energy and Environment: Case study on Hong Sa Lignite Power Plants in Lao PDR.

FP_C.3_EGAT_ Thai-Laos Cross Border Energy and Environment: Case study on Hong Sa Lignite Power Plants in Lao PDR. FP_C.3_EGAT_ Thai-Laos Cross Border Energy and Environment: Case study on Hong Sa Lignite Power Plants in Lao PDR. Cherid Kalayanamitr, Project Environment Division Electricity Generating Authority of

More information

RENEWABLE ENERGY SYSTEMS WIND ENERGY (1) Prof. Ibrahim El-mohr Prof. Ahmed Anas. Lec. 5

RENEWABLE ENERGY SYSTEMS WIND ENERGY (1) Prof. Ibrahim El-mohr Prof. Ahmed Anas. Lec. 5 RENEWABLE ENERGY SYSTEMS WIND ENERGY (1) Prof. Ibrahim El-mohr Prof. Ahmed Anas Lec. 5 Outline 2 Wind Energy Outlook Introduction to Wind Energy Conversion History of Wind Turbines Classifications of Wind

More information

AEC + BIMSTEC EC : ASEAN Economic Community + Bay of Bengal Initiative for Multi-sectoral Technical and Economic Cooperation

AEC + BIMSTEC EC : ASEAN Economic Community + Bay of Bengal Initiative for Multi-sectoral Technical and Economic Cooperation AEC + BIMSTEC EC : ASEAN Economic Community + Bay of Bengal Initiative for Multi-sectoral Technical and Economic Cooperation 11 2556 2 (GDP) 3 - - 7 - - 4 Low Carbon Economy: 450 ppm scenario 5 2,000 1,800

More information

Wind Energy Basics & Project Cycle

Wind Energy Basics & Project Cycle Wind Energy Basics & Project Cycle Wind Energy Basics & Project Cycle 1.800.580.3765 WWW.TTECI.COM Pramod Jain, Ph.D. Presented to: DFCC Bank and RERED Consortia Members January 26 27, 2011 Colombo, Sri

More information

VALIDATION OF GH ENERGY AND UNCERTAINTY PREDICTIONS BY COMPARISON TO ACTUAL PRODUCTION

VALIDATION OF GH ENERGY AND UNCERTAINTY PREDICTIONS BY COMPARISON TO ACTUAL PRODUCTION VALIDATION OF GH ENERGY AND UNCERTAINTY PREDICTIONS BY COMPARISON TO ACTUAL PRODUCTION Andrew Tindal, Keir Harman, Clint Johnson, Adam Schwarz, Andrew Garrad, Garrad Hassan 1 INTRODUCTION Garrad Hassan

More information

Ratchaburi Electricity Generating. Asean & India Conference

Ratchaburi Electricity Generating. Asean & India Conference Ratchaburi Electricity Generating Holding PCL. Asean & India Conference 1-3 September 2010 Table of Contents o RATCH Overview o RATCH Highlights o RATCH Growth Strategies Appendix RATCH Overview Company

More information

Dharam V. Punwani Avalon Consulting, Inc. Tom L. Pierson Turbine Air Systems, Ltd.

Dharam V. Punwani Avalon Consulting, Inc. Tom L. Pierson Turbine Air Systems, Ltd. Turbine Inlet Air Cooling: A Great Strategy for Maximizing the Potential of Combustion Turbines and Addressing the Needs of Restructuring Energy Market Dharam V. Punwani Avalon Consulting, Inc. Tom L.

More information

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm SYNOPSIS OF THE THESIS Enhanced Power Quality Management of Grid Connected Wind Farm INTRODUCTION OF THE THESIS Faster depletion of fossil fuels and environmental damage has resulted into increased use

More information

August 22, 2014 FIRE ISLAND WIND

August 22, 2014 FIRE ISLAND WIND August 22, 2014 FIRE ISLAND WIND Phase 1 Summary: Performance Project Performance: Benefits realized: 93,500 MWh LTD >875,000 MCF of NG burn avoided ~$6.5 MM in NG purchases avoided 55,000 tons of CO2

More information

Renewables. The World s Most Robust Small Scale Wind Turbines

Renewables. The World s Most Robust Small Scale Wind Turbines Renewables The World s Most Robust Small Scale Wind Turbines Kingspan Renewables introduces the latest addition to the renewables portfolio Small Scale Wind Turbines. Climate Change is now a generally

More information

Wind Energy Basics & Project Cycle

Wind Energy Basics & Project Cycle Wind Energy Basics & Project Cycle WIND POWER PROJECT DEVELOPMENT PRACTICAL APPROACHES TO LAUNCHING SUSTAINABLE WIND PROJECTS October 18-19, 2011 1.800.580.3765 WWW.TTECI.COM Pramod Jain, Ph.D. Presented

More information

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009 The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009 Growth of Wind Generation in ERCOT MW 12,000 10,000 8,000

More information

ELG4126 Distributed Generation and Renewables

ELG4126 Distributed Generation and Renewables ELG4126 Distributed Generation and Renewables Case Study of Renewable Energy and Smart Grid of Three Phases Phase One: Wind Farm Conduct a feasibility study for initiating a profitable wind energy farm

More information

Solar Power Realities

Solar Power Realities Solar Power Realities Supply-Demand Characteristics, Storage and Capital Costs by Peter Lang Abstract This paper provides a simple analysis of the capital cost of solar power and energy storage sufficient

More information

Design Installation and Testing of 1.6 kwp GPV System

Design Installation and Testing of 1.6 kwp GPV System Design Installation and Testing of 1.6 kwp GPV System Napat Watjanatepin Rajamangala University of Technology Suvarnabhumi Nonthaburi Campus THAILAND Phone:+66-2969-1521, Fax:+66-2525-2682 Email:watjanatepin@yahoo.com

More information

Wind Power Update. Larry Flowers NREL. January 15, 2002

Wind Power Update. Larry Flowers NREL. January 15, 2002 Wind Power Update Larry Flowers NREL January 15, 2002 Sizes and Applications Small ( 10 kw) Homes Farms Remote Applications (e.g. water pumping, telecom sites, icemaking) Intermediate (10-250 kw) Village

More information

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response

More information

AN ASSESSMENT OF HYBRID DISTRIBUTED GENERATION SYSTEMS IN RURAL ALASKA

AN ASSESSMENT OF HYBRID DISTRIBUTED GENERATION SYSTEMS IN RURAL ALASKA AN ASSESSMENT OF HYBRID DISTRIBUTED GENERATION SYSTEMS IN RURAL ALASKA Lindsay Willman Environmental Engineering, University of Colorado at Boulder, 428 UCB, Boulder, CO 80309-0428, USA Moncef Krarti,

More information

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704)

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704) 2 nd Annual California Biomass Collaborative Forum Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704) Tony Gonçalves Program Lead Existing Renewable Facilities

More information

Storage as a Transmission Asset:

Storage as a Transmission Asset: Storage as a Transmission Asset: Enabling storage assets providing regulated cost-ofservice-based transmission service to access market revenues Working Group Meeting Karl Meeusen, Ph.D. Stakeholder Meeting

More information

The Future of Electricity: A Market with Costs of Zero? Marginal

The Future of Electricity: A Market with Costs of Zero? Marginal The Future of Electricity: A Market with Costs of Zero? Marginal Imperial College Business School Richard Green, IAEE European Conference, 217 1 Running your mouse over the bubble in the top left corner

More information

Prospects and Viability of Solar Energy in Khyber Pakhtunkhwa Pakistan

Prospects and Viability of Solar Energy in Khyber Pakhtunkhwa Pakistan Prospects and Viability of Solar Energy in Khyber Pakhtunkhwa Pakistan Muhammad Riaz 1, Amjad Ullah 2, Khadim Ullah Jan 3 1,2 Department of Electrical Engineering, University of Engineering and Technology

More information

Pre-Feasibility Study of Cogeneration in a Paper Recycling Mill in Bangladesh

Pre-Feasibility Study of Cogeneration in a Paper Recycling Mill in Bangladesh CMU. Journal (2003) Vol. 2(1) 27 Pre-Feasibility Study of Cogeneration in a Paper Recycling Mill in Bangladesh Md. Ehsan, M.A.R. Sarkar*, Md. Obaidullah and M. A. Islam Bangladesh University of Engineering

More information

Energy Uplift (Operating Reserves)

Energy Uplift (Operating Reserves) Section 4 Energy Uplift Energy Uplift (Operating Reserves) Energy uplift is paid to market participants under specified conditions in order to ensure that resources are not required to operate for the

More information

A Study of Local Identity and Local Environment Factors Influenced Architectural Design

A Study of Local Identity and Local Environment Factors Influenced Architectural Design International Journal of Renewable Energy, Vol. 7, No. 1, January - June 2012 A Study of Local Identity and Local Environment Factors Influenced Architectural Design Usanee Mingvimol Faculty of Architecture,

More information

THAYER CREEK HYDROPOWER PROJECT ANGOON, AK

THAYER CREEK HYDROPOWER PROJECT ANGOON, AK THAYER CREEK HYDROPOWER PROJECT ANGOON, AK THE CHALLENGES OF DESIGNING AND BUILDING A NEW DAM AND HYDROPOWER FACILITY IN SOUTHEAST ALASKA DEL SHANNON, PE ANGOON, ALASKA KOOTZNOOWOO, INC. ANGOON, AK, ADMIRALTY

More information