1 2016 Expansion of POL Terminal In Magalia, Indore, Madhya Pradesh PRE FEASIBILITY REPORT 1 P a g e

2 Prefeasibility Report 1 EXECUTIVE SUMMARY INDUSTRIAL AREA (PROCESSING AREA) RESIDENTIAL AREA (NON-PROCESSING AREA) GREEN BELT DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER) SEWAGE SYSTEM INDUSTRIAL WASTE MANAGEMENT POWER REQUIREMENT & SUPPLY/ SOURCE INTRODUCTION BRIEF DESCRIPTION OF THE PROJECT NEED FOR THE PROJECT AND ITS IMPORTANCE TO REGION EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT PROJECT DESCRIPTION TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS, IF ANY LOCATION (SPECIFIC LOCATION AND PROJECT BOUNDARY & PROJECT LAY OUT) WITH COORDINATES DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL CONSIDERATIONS GONE INTO SHOULD BE HIGHLIGHTED SIZE OR MAGNITUDE OF OPERATION TECHNOLOGY AND PROCESS DESCRIPTION RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY SOURCE, MARKETING AREA OF FINAL PRODUCTS, MODE OF TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT RESOURCE OPTIMIZATION/RECYCLING AND REUSE ENVISAGED IN THE PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED TRANSPORTATION DETAILS OF RAW MATERIALS AVAILABILITY OF WATER ITS SOURCE, ENERGY/POWER REQUIREMENT AND SOURCE SHOULD BE GIVEN Water Source Electricity & Fuel Requirements QUANTITY OF WASTE TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT /DISPOSAL Waste Water generation & Management plan Solid & Hazardous waste generation & Management plan SITE ANALYSIS CONNECTIVITY LAND FORM, LAND USE AND LAND OWNERSHIP TOPOGRAPHY (ALONG WITH MAP) EXISTING LAND USE PATTERN EXISTING INFRASTRUCTURE SOIL CLASSIFICATION SOIL INVESTIGATION WILL BE DONE DURING CONSTRUCTION OF POL STORAGE TERMINAL CLIMATIC DATA FROM SECONDARY SOURCES PLANNING BRIEF P a g e

3 5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, TRANSPORTATION ETC) TOWN AND COUNTRY PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION POPULATION PROJECTION ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) AMENITIES/FACILITIES PROPOSED INFRASTRUCTURE INDUSTRIAL AREA (PROCESSING AREA) RESIDENTIAL AREA (NON-PROCESSING AREA) GREEN BELT DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER) SEWAGE SYSTEM INDUSTRIAL WASTE MANAGEMENT POWER REQUIREMENT & SUPPLY/ SOURCE REHABILITATION AND RESETTLEMENTS (R& R) PLAN POLICY TO BE ADOPTED (CENTRAL/STATE) IN RESPECT OF THE PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND LANDLESS LABOURERS (A BRIEF OUTLINE TO BE GIVEN) PROJECT SCHEDULE AND COST ESTIMATE LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATA OF COMPLETION (TIME SCHEDULE FOR THE PROJECT TO BE GIVEN) ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE PROJECT ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE BENEFIT TO BE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN THE AREA List of Annexure ANNEXURE- I- LETTER AND MOM OF MINISTER OF STATE (IC) P&NG ANNEXURE-II- LAND ALLOTMENT LETTER WITH NOTIFICATION ANNEXURE-III- AUTHORIZATION LETTER FOR HAZARDOUS WASTE ANNEXURE-IV- COPY OF CONSENT LETTER ANNEXURE V: TOPOMAP OF PROJECT SITE ANNEXURE VI- P&ID 3 P a g e

4 1 EXECUTIVE SUMMARY Oil marketing companies have projected an increase in demand of POL product in future due to increase in its domestic, Transportation and industrial use. The demand is likely to increase substantially over the years to come. Oil PSUs have planned enrollment of new customers to saturate the demand potential as per directive of the Ministry of Petroleum and Natural Gas, Government of India. In this regard, the meeting held on 6 th October 2016 with Hon ble Minister of state (IC) (P&NG) and PSUs (IOCL/HPCL/BPCL). The minutes of Meeting vid letter No-P20019/41/2014-LPG issued on 24 th December Now HPCL is planning to increase the plant capacity, by reducing the no of tanks (the existing plant was commissioned before 1994, all the design as per last standard. Now as per PESO/OISD standard the inter tanager distance is reduced. So, by increasing the ground covering, the size and storage quantity of all tankages will be revised) at existing plant at Manglia, Indore, and Madhya Pradesh. The existing capacity of the plant is 20,450 KL (18,450 KL Product & 2,000 KL Water) with 23 Tanks, which will be dismantle and proposing 51,600 KL (43600 KL Product & 8000 Water) with the 19 No of tanks. The project is targeted to be mechanically completed within 30 months from the date of handing over the land or statutory MOEF approval. The surmised point of this project mention below. Existing Facilities at Indore IRD Installation: Existing Capacity of Plant-18,450 KL Product & 2,000 KL Water 12 Nos of above ground Storage Tanks 8 Nos U/G Tanks for MS, HSD, SKO, ATF & ethanol, 2 Nos A/G Horizontal tanks 1x8 Bays + 1x2 bays T/T Gantry Pump Houses, Admin building and other allied facilities. Proposed Facilities: Proposed Capacity KL Product & 8000 Water. Dismantling of all tanks, Gantry, Pipeline, Pump house. New facilities proposed:. Tanks-19of varying capacity ( refer Table 1), TT Gantry (two rows of 8 bay ), pump house, and Fire fighting lines/facilities other support facilities and infrastructure facilities like approach roads, Pump Houses, Admin building, and vehicles parking areas. ( details given in the following section) 4 P a g e

5 Table 1: Existing Tanks with Quantity Sl.No Class Material No of Tank Quantity (KL) 1 C FO/LDO A Hexane/MS ULP 8 4, B HSD/SKO/ATF 8 13, TOTAL 21 18, NA Water (Fire Fighting) 2 2, ToTal 23 20,450 Table 2: Proposed Tanks with Quantity Sl.No Class Material No of Tank Quantity (KL) 1 C Bio Diesel 2 3, A Hexane/MS Ethanol 7 11, B HSD/SKO/ATF BIO Diesel 7 28, TOTAL 16 43, NA Water (Fire Fighting) 3 8, ToTal 19 51, Industrial Area (processing area) The proposed project falls under the industrial area and there is no processing involve in this project. The transportation of material for storage purpose thru railway siding and also depend on existing pipeline form BPCL terminal. Mangliya industrial area is situated beside A.B. Road near mangliya village 13 km away from Indore. In this area mainly medium major scale industries are established like dairy plant, solvent extraction, vegetable oil refinery, vanaspati plant and Storage of petroleum product. Total No. of industries registered in the board are 13 out of which red category units are 11 and green are Residential Area (non-processing area) No residential area proposed in upcoming project. 1.3 Green belt 6.5 Acres Green belt is already in existing plant. 1.4 Drinking water management (source & supply of water) No additional manpower will be added in proposed project. Existing drinking water management system is sufficient for proposed project. 5 P a g e

6 1.5 Sewage system Existing Sewage system is sufficient for proposed project. No additional facility will be required. 1.6 Industrial waste management There is no industrial waste will be generated by this project. Pleasantly 10 KL oil sludge is generated in once in 5 year from existing facility and it will be increase by 15 KL. The agreement is already signed with approved vender for dispose/recycle the waste. 1.7 Power requirement & supply/ source 400 kv electricity supplied by local electricity board and this is also sufficient for proposed project. No additional facility will be required. For the power backup 100 and 200 KW already existing in plant and it will be sufficient. 6 P a g e

7 2 INTRODUCTION Hindustan Petroleum Corporation Ltd is a Government of India Enterprise with a Navratna Status, and a Forbes 2000 and Global Fortune 500 company, is a leading public sector undertaking (PSU) engaged in refining, transportation and marketing of petroleum products across the country. HPCL has the second largest share of product pipelines in India with a pipeline network of more than 2,500 kms for transportation of petroleum products and a vast marketing network consisting of 13 Zonal offices in major cities and 101 Regional Offices facilitated by a Supply & Distribution infrastructure comprising Terminals, Pipeline networks, Aviation Service Stations, LPG Bottling Plants, Inland Relay Depots & Retail Outlets, Lube and LPG Distributorships. As an integrated oil company with refineries, marketing terminals/depots and retail outlets, HPCL is playing a significant role in the nation s economic development and growth. The proposed terminal is to cater the demand of POL products in western India from Manglia terminal. 2.1 Brief Description of the Project Oil marketing companies have projected an increase in demand of POL product in future due to increase in its domestic, Transportation and industrial use. The demand is likely to increase substantially over the years to come. Oil PSUs have planned enrollment of new customers to saturate the demand potential as per directive of the Ministry of Petroleum and Natural Gas, Government of India. In this regard, the meeting held on 6 th October 2016 with Hon ble Minister of state (IC) (P&NG) and PSUs (IOCL/HPCL/BPCL). The minutes of Meeting vid letter No-P20019/41/2014-LPG issued on 24 th December The MoM letter enclosed as an Annexure-I. Now HPCL is planning to increase the plant capacity, by reducing the no of tanks (the existing plant was commissioned before 1994, all the design as per last standard. Now as per PESO/OISD standard the inter tanager distance is reduced. So, by increasing the ground covering, the size and storage quantity of all tankages will be revised) at existing plant at Manglia, Indore, and Madhya Pradesh. The existing capacity of the plant is 20,450 KL (18,450 KL Product & 2,000 KL Water) with 23 Tanks, which will be dismantle and proposing 51,600 KL (43600 KL Product & 8000 Water) with the 19 No of tanks. 2.2 Employment Generation (Direct and Indirect) due to the project Currently 30 employee on HPCL pay roll, 25 No security staff and 14 contractor. For proposed project approx 95 people (Employee/security/Contractor) will work. 7 P a g e

8 Figure 1: Plant Lay Out 8 P a g e

9 3 PROJECT DESCRIPTION In proposed project, there is no process involved, only the storage of finished product (MS, HSD, SKO, ATF, HEXANE, FO & LDO) at terminal. All these materials will receive by existing pipeline and through rail wagons. The products are pumped through dedicated pipelines laid from POL siding to the respective product tanks. The terminal is provided with a total proposed storage capacity of 51, 600 KL of Tankage (MS, Ethanol, HSD, SKO, ATF, LDO & FO and water) and allied facilities. Details of storage tanks are provided in Table. All tanks are enclosed in dyke wall, capable of enclosing the volume of largest tank among others within the dyke in case of failure. New hydrant system and foam pourers will be provided to meet the Oil Industry and Safety Directorate (OISD) std Distribution/Dispatched of POL Product POL Products are dispatched through road tanks through closed dealer network system. Two number of TT gantry with 8 bay will be construct and addition space for 8 bay gantry will be leave free for future expansion. In addition to all Ethanol blending and additives blue dye dosing facility will be provided. Existing Facilities at Indore IRD Installation: Existing Capacity of Plant-18,450 KL Product & 2,000 KL Water 12 Nos of above ground Storage Tanks 8 Nos U/G Tanks for MS, HSD, SKO, ATF & ethanol, 2 Nos A/G Horizontal tanks 1x8 Bays + 1x2 bays T/T Gantry Pump Houses, Admin building and other allied facilities. Proposed Facilities: Proposed Capacity KL Product & 8000 Water. Dismantling of all tanks, Gantry, Pipeline, Pump house. New facilities proposed:. Tanks-19of varying capacity, TT Gantry (two rows of 8 bay ), pump house, and Fire fighting lines/facilities other support facilities and infrastructure facilities like approach roads, Pump Houses, Admin building, and vehicles parking areas. Detailed Process flow is given in Annexure VI. Table 3: Existing Tanks with Quantity Sl.No Class Material No of Tank Quantity (KL) 1 C FO/LDO A Hexane/MS ULP 8 4, B HSD/SKO/ATF 8 13, TOTAL 21 18, NA Water (Fire Fighting) 2 2, G.TOTAL 23 20,450 Table 2: Proposed Tanks with Quantity Sl.No Class Material No of Tank Quantity (KL) 9 P a g e

10 1 C Bio Diesel 2 3, A Hexane/MS Ethanol 7 11, B HSD/SKO/ATF BIO Diesel 7 28, TOTAL 16 43, NA Water (Fire Fighting) 3 8, G.TOTAL 19 51, Table 5: Existing Facility/Structure S. No. Structures AREA (SQ.M) 1 SECURITY CABIN 12 2 CHECKING PLATFORM CAR / CYCLE PARKING OFFICE BUILDING WORKER'S REST ROOM 48 6 DG / CONTROL ROOM-I BAY T/T GANTRY CALIBRATION SHED 64 9 LUBE DRUM YARD FIRE PUMP HOUSE AND EXTENSION TLF PUMP HOUSE TWD PUMP HOUSE TRANSFORMER YARD PLANT TOILET FLOOD LIGHT TOWER BLACK OIL GANTRY PLATFORM SEALING PLATFORM (PROPOSED) (RESIZE) OIL WATER SEPARATOR 9 20 TT LOCKING SHED LUBE WARE HOUSE NEW CONTROL ROOM LABORATARY LAB BUILDING CONTROL ROOM AUTOMATION BLUE DYE SHED (RESITEMENT) LAB BUILDING EXTENSION SECURITY CABIN(EXTENSION) POLE TYPE HIGH MAST WEIGH BRIDGE ADDITIVE SHED AIR COMPRESSOR SHED PLANING AND LOCKING ROOM ATF PUMP HOUSE 10 P a g e

11 35 ATF LOADING/ UNLOADING POINT Total 3860 Table 6: Proposed Facility/Structure SL.NO STRUCTURE AREA (SQ.M) 1 PLANNING ROOM 50 2 SECURITY CABIN/TT CHECKING 85 2A SEALING PLATFORM 50 3 SECURITY CABIN/TT CHECKING 28 4 OFFICE BUILDING CONTROL ROOM 300 5A LAB BUILDING T.T. PARKING AREA A 8X2 NO BAYS TT GANTRY 7 TLF PRODUCT PUMP HOUSE FIRE WATER PUMP HOUSE FIRE WATER PUMP HOUSE 10 CALIBRATION FACLILITY ENGG WARE HOUSE DU WARE HOUSE A DU SHED ETP TWO PUMP HOUSE IBACKS ROOM TRANSFORMER SUB SATTAION/MCC/DG ROOM VAPOUR REC SCRAP YARD SAMPLE ROOM DRIVER REST ROOM WATCH TOWER 23 DOSING SHADE (3 NO.) 12 TOTAL Type of Project including interlinked and interdependent projects, if any This is isolated storage project, as per EIA notification, project comes under the 6 B category. There is no interlined with this project. 3.2 Location (specific location and project boundary & project lay out) with coordinates The latitude and longitude of proposed site is N and E. 11 P a g e

12 Figure. Study Area Map 12 P a g e

13 3.3 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted Alternative sites have not been considered for proposed project because the proposed project is coming in existing plant area. Major Factor involved in the selection of site are listed below The project site is in industrial area Site is connected with state highway for easy transport of POL product. Site is near to railway station and connected by railway line for import of POL product. Power, water and manpower is available near the project site. There is no forest or eco sensitive area within the 10km of project site 3.4 Size or Magnitude of Operation This is an expansion of existing project to construct POL storage Terminal. Class A, B, and C product will store and dispatched according to demand of market. Total storage capacity of POL storage will 51,600 KL future tanks. All facilities including admin building and other important structure will be constructed in acres of land and 33% (6.5 Acres) of total land will be used for green belt development. 3.5 Technology and Process Description POL products (MS, HSD, SKO, ATF, FO & LDO) will received through existing pipeline and rail wagons and stored in Tanks, further distributed thru tankers. 3.6 Raw material required along with estimated quantity, likely source, marketing area of final products, mode of transport of raw material and finished product. Construction material will be required during construction phase for building and utility quantity will be finalized during construction. POL product will be imported through Tank Wagon and store in respective tank 3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be briefly outlined. The sources of waste water from the proposed terminal are from canteen facilities and office building. The waste water is treated in sewage treatment plant and is reused for gardening and other activities like toilet flushing and cleaning purposes. Zero discharge is proposed for the terminal project. There is no process effluents generated. Hence impact on water quality from the proposed project is insignificant. 3.8 Transportation details of Raw Materials The raw material will be transported thru Railway Wagon and pipeline of BPCL Magaliya Terminal also. 13 P a g e

14 3.9 Availability of water its source, energy/power requirement and source should be given Water Source No additional water will be required for proposed project. Presently 12 KLD water requirement for Existing project. The source of water for the proposed project is meeting through Bore wells. Sewage will be treated in proposed STP. No trade effluent generates from the operation Electricity & Fuel Requirements For the Existing project, 250KV supply provided by Madhya Pradesh State Electricity Distribution Company Limited but future demand will be increase by 400kvA. Also for Power backup, HSD used as a fuel for D.G sets (100 & 200 kv) and it will be sufficient for proposed project also Quantity of waste to be generated (liquid and solid) and scheme for their management /disposal Waste Water generation & Management plan There is no manufacturing process as it is only storage and filling plant hence there will be no generation of Effluent. Sewage will be treated through septic tanks and soak pits Solid & Hazardous waste generation & Management plan The hazardous wastes generated is petroleum tank bottom sludge, Petroleum tanks are cleaned once in five year, The type and quantities of Hazardous waste generated from various processes are Approx.10 KL and it will be increase by 15 KL. The tank bottom sludge is sold out at third party to authorized vendor. The proponent is having authorization of 3.0 MT (15.0 MT/Year) in waste stream 3.1 for cleaning of petroleum oil storage tank sludge contacting oil and 0.04 MT (Yearly) in waste stream 5.1 used oil. The Authorization Letter enclosed as an Annexure II. The impact of solid waste on the environment will be insignificant. The Management of Hazardous waste will be done as per Hazardous Waste Management Rules P a g e

15 4 SITE ANALYSIS 4.1 Connectivity Mangliya industrial area is a industrial area, situated beside A.B. Road near mangliya village 13 km away from Indore. In this area mainly medium major industries are established like dairy plant, solvent extraction, vegetable oil refinery, vanaspati plant and Storage of petroleum product. Nearest railway station : Mangliya Gaon Railway Station (0.20 KM, NW )Indore Railway station (15 KM, SW) Nearest highway: Agra-Bombay Road,(0.380 km, E), NH-3,(1.59 km, E) Nearest Airport: Devi Ahilyabai Holkar Airport, Indore (25 KM, SW) Figure 2: Connectivity of Proposed plant 4.2 Land Form, Land Use and Land Ownership The existing plant is laying in Mangaliya industrial area, the copy of land allotment letter and copy of notification enclosed as an Annexure III. The existing plant area is about Acres and upcoming proposed facility coming in same premises. There is no additional land is required for POL Terminal. 4.3 Topography (along with map). The topography of the site is plain. Refer Annexure V. 15 P a g e

16 Figure 2: Plant Boundary of Proposed plant 4.4 Existing land use pattern The project area is laying Industrial area; there is no national park, wild life sanctuary, eco sensitive areas within 10 Km from the proposed project boundary. 4.5 Existing Infrastructure Adjacent BPCL/IOCL POL Terminal and well connected to rail facility. 4.6 Soil Classification Soil investigation will be done during construction of POL Storage Terminal. The district is covered by medium black soils. These soils are 0.46 to 0.9 meters thick and are rich in lime and lime nodules. The sub-soil and the partially disintegrated rock below allow easy drainage and hence these medium black soils can be freely irrigated. 16 P a g e

17 4.7 Climatic data from secondary sources The climate of Indore district is characterized by hot summer and well distributed rainfall during the southwest monsoon season. Monsoon arrives generally in the middle of June and the weather becomes pleasant. January is generally the coolest month. Sometimes in December, the minimum temperature. Normal annual rainfall of the district is mm. The district receives maximum rainfall during the south west monsoon period. Thus about 91.2 % of the total annual rainfall takes place during the south west monsoon period (June to September) alone. The maximum monthly rainfall takes place during the month of July. 17 P a g e

18 5 PLANNING BRIEF 5.1 Planning Concept (type of industries, facilities, transportation etc) Town and Country Planning/Development authority classification. Type of Industry: Construction of POL Storage Terminal 5.2 Population Projection Due to proposed project, there will be no impact on population inside and outside the plant. 5.3 Assessment of Infrastructure Demand (Physical & Social) On the basis of the preliminary site visit, the infrastructure demand in the villages was assessed on the basis of need and priority. Employment would be as per prevailing norms of state government for skilled and unskilled people for the proposed project activity. 5.4 Amenities/Facilities Proper site services such as First Aid, Canteen, Drinking Water, etc. will be provided to the workers. 18 P a g e

19 6 PROPOSED INFRASTRUCTURE 6.1 Industrial Area (processing area) The proposed project fall under the existing premises of HPCL, which is located in Mangliya industrial area. Mangliya industrial area is situated beside A.B. Road near mangliya village 13 km away from Indore. In this area mainly medium major scale industries are established like dairy plant, solvent extraction, vegetable oil refinery, vanaspati plant and Storage of petroleum product. Total No. of industries registered in the board are 13 out of which red category units are 11 and green are Residential Area (non-processing area) No residential area proposed in upcoming project 6.3 Green belt 6.5 Acres Green belt is already in existing plant. No additional green belt will be required. 6.4 Drinking water management (source & supply of water) There is no addition manpower will be added. So, existing drinking water management system is sufficient for proposed project. 6.5 Sewage system ETP facility is proposed for project. There is no addition manpower will be added. So, existing Sewage system is sufficient for proposed project. 6.6 Industrial waste management Approx 10 KL oil sludge is generated in 5 year form existing facility and it will be increase by 15 KL. The agreement is already signed with approved vender for dispose/recycle the waste. 6.7 Power requirement & supply/ source 250 kv electricity supplied by local electricity board and this is also sufficient for proposed project. No additional facility will be required. For the power backup 100 and 200 KW already existing in plant and it will be sufficient. 19 P a g e

20 7 REHABILITATION AND RESETTLEMENTS (R& R) PLAN 7.1 Policy to be adopted (central/state) in respect of the project affected persons including home oustees, land oustees and landless labourers (a brief outline to be given) Not applicable because the proposed project is located in Existing plant of HPCL. 20 P a g e

21 8 PROJECT SCHEDULE AND COST ESTIMATE 8.1 Likely date of start of construction and likely data of completion (time schedule for the project to be given) The time schedule for completion of project is 30 months after getting the all the statuary clearances. 8.2 Estimated project cost along with analysis in terms of economic viability of the project. Total cost for proposed project activity is Rs.150 Cr. 21 P a g e

22 9 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) 9.1 Financial and social benefits with special emphasis on the benefit to be local people including tribal population, if any, in the area. The project will be beneficial to people as the company progress and expands its activity gradually. Through CSR activity company management will be committed to improve infrastructural facilities for the local people in fields of Environmental, Medical, and Transportation etc. The local people especially tribal population will be benefited by way of indirect employment opportunities which will improve the socioeconomic environment of the area. 22 P a g e

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For PRIOR ENVIRONMENTAL CLEARANCE STORAGE CAPACITY ENHANCEMENT OF HPCL, LPG BOTTLING PLANT Capacity: 3 X 500 MT At Plot No.499 Kota-Jhalawar Road (NH-12) Village- Mandana, Tehsil-

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report 1. Executive Summary Residential, Commercial, Retail and Hotel projects and an IT/ITES. The Project has already obtained an Environmental Clearance from Ministry of Environment &

More information

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal ANNEXURE Annexure 1: Production Details Annexure 2: Site Location Map Annexure 3: Site Layout Map & Area breakup for Terminal Annexure 4: Operation Philosophy Annexure 5: Copy of Consent to Operate Annexure

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR DYES, PIGMENTS AND DYE INTERMEDIATES MANUFACTURING PLANT IN GIDC, DAHEJ-II Of M/s. SHREEJI INDUSTRIES Plot No. D2/CH/24, Dahej-II, GIDC Industrial Estate,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For PROPOSED EXPANSION OF BAKELITE POWDER MANUFACTURING UNIT of M/S. HINDUSTAN BAKELITE COMPANY PLOT NO. J-3436, GIDC ESTATE, ANKLESHWAR, DISTRICT: BHARUCH-393002, GUJARAT 0 CONTENTS

More information

Pre-Feasibility Report for Construction of Additional Tankage at POL Terminal Partapur, Meerut, M/s IOCL PRE-FEASIBILITY REPORT

Pre-Feasibility Report for Construction of Additional Tankage at POL Terminal Partapur, Meerut, M/s IOCL PRE-FEASIBILITY REPORT PREAMBLE Pre-Feasibility Report for Construction of Additional PRE-FEASIBILITY REPORT Indian Oil Corporation Limited (IOCL) is India's largest commercial enterprise, with a sales turnover of Rs. 4,38,710

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY M/s Arti Chemical Industries is a project located at Plot No. E-22, Vilayat G.I.D.C. Tal: Vagra area of Bharuch district in Gujarat. M/s Arti Chemical Industries

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 0.0 EXECUTIVE SUMMARY Shri Ashok Patel Partner of M/s. Patel Polymers is planning to manufacture organic chemical Different Types of Resins, for proposed expansion project at Plot

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT FOR Conversion of Existing Product Storage Tanks TK-16(HSD) of 6000 KL to MS and TK-6(MS) of 1000 KL to Ethanol AT HPCL Bulk POL Depot, Mansa Road, Phoos Mandi, Bhatinda-151001.

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANICCHEMICALS (RESINS) (5 f B IND II) By M/s M R INDUSTRIES SURVEY NO. 58/1 & 58/3 OPPOSITE WHOLESOME FOOD PVT. LTD.,

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT For EC FOR INCREASING STORAGE CAPACITY OF ETHANOL BY 6000 KL At Indian Oil Corporation Limited (IOCL), Panipat marketing Complex, Village-Baholi, P.O.-Panipat Refinery, Tehsil Panipat,

More information

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal

ANNEXURE. Annexure 1: Production Details. Annexure 2: Site Location Map. Annexure 3: Site Layout Map & Area breakup for Terminal ANNEXURE Annexure 1: Production Details Annexure 2: Site Location Map Annexure 3: Site Layout Map & Area breakup for Terminal Annexure 4: Operation Philosophy Annexure 5: Copy of Consent to Operate Annexure

More information

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF (B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF Makwana Dineshbhai Khimjibhai AT VILLAGE:- Tithava, TALUKA:- Wankaner, DIST.:- Morbi 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXCUTIVE SUMMARY

More information

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3 N to 20 44' 20.7N Longitude  E to 85 35'27.5 E EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at

More information

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT PRE - FEASIBILITY REPORT For PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT Of M/s. SHREE RAM INDUSTRIES PLOT NO.5117, GIDC-ANKLESHWAR, PIN-393002 TAL: ANKLESHWAR, DIST: BHARUCH, GUJARAT

More information

M/S. Dain Colour Chem

M/S. Dain Colour Chem PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of M/S. Dain Colour Chem Plot No.: 5, Nilkanth Estate, Village: Dhanot, Ta.: Kalol, Dist.: Gandhinagar-382729, Gujarat 1 CONTENTS

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

PROJECT REPORT FOR AMMENDMENT IN ENVIRONMENT CLEARANCE

PROJECT REPORT FOR AMMENDMENT IN ENVIRONMENT CLEARANCE 1.1 TYPE OF PROJECT The project of IOTL is a green field POL terminal with storage capacity 1,90,570 KL. 1.2 NEED FOR THE PROJECT Chhattisgarh was carved out of Madhya Pradesh on the 1 st November, 2000.

More information

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha)

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Pre Feasibility Report On STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Submitted to MINISTRY OF ENVIRONMENT & FOREST STATE LEVEL ENVIRONMENTAL

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For DEVELOPMENT OF LPG BOTTLING PLANT AT RASAYANI, DISTRICT-RAIGAD, MAHARASTRA Proposed By M/s. BHARAT PETROLEUM CORPORATION LTD. ******************************************** Prepared

More information

PRE FEASIBILTY REPORT

PRE FEASIBILTY REPORT PRE FEASIBILTY REPORT FOR ENVIRONMENT CLEARANCE OF PROPOSED NEW PROJECT S. O. CHEMICALS (5 f Category) Proposed By: COREL PHARMA CHEM PVT. LTD. SURVEY NO. 473 & 481, BORISANA, KADI THOL ROAD, KADI, DIST

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For EXPANSION IN EXISTING MANUFACTURING PLANT Of M/s. SHIVA DYE STUFF PVT. LTD Plot no. A2-11/6104,G.I.D.C. Industrial Estate, Ankleshwar-393002, Gujarat. 1 CONTENTS Sr. No. Description

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT (B) PREFEASIBILITY REPORT OF EXISTING SAND MINING PROJECT OF RAJESHBHAI BHAGUBHAI PATEL AT VILLAGE:- Panchlai, TALUKA:- Pardi, DIST.:-Valdad. 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT For ToR Application of Expansion Project For MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS (Dyes Intermediates) Proposed By: M/s. Plot No. C/1/B-145-3 Phase-II, GIDC Estate, Naroda,

More information

EXISTING PROJECT FOR ORDINARY SAND MINING

EXISTING PROJECT FOR ORDINARY SAND MINING (C) PROJECT REPORT OF EXISTING PROJECT FOR ORDINARY SAND MINING OF JASHUBEN CHHAGANBHAI OAD AT VILLAGE:-TIMBA, TALUKA:- KAMREJ, DIST.:- SURAT 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others 1. EXECUTIVE SUMMARY 1.1 Introduction The Road Metal Quarries was granted in Guntur District, Andhra Pradesh has been allotted to M/s. Viswanadha Stone Crusher & 16 others by Assistant Director of Mines

More information

A. INTRODUCTION PREFEASIBILITY REPORT

A. INTRODUCTION PREFEASIBILITY REPORT A. INTRODUCTION a. BRIEF DESCRIPTION OF PROJECT M/s Bharat Petroleum Corporation Limited has set up the Haldia Coastal Installation at HAL-733, Patikhali, Durgachak, Haldia 721602, West Bengal. The Depot

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For NEW PROJECT (PIGMENT MANUFACTURING PLANT) Of M/s. SHREY INDUSTRIES Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat) CONTENTS Sr.

More information

PRE-FEASIBILITY REPORT FOR ORDINARY SAND

PRE-FEASIBILITY REPORT FOR ORDINARY SAND PRE-FEASIBILITY REPORT FOR ORDINARY SAND Proponent NISANT TRADERS At- Opp. Survey No.- 3 Panam River Area-2.50.00 Hectare Village-Ramji-ni-Nal, Taluka- Shahera Dist.- Panchmahal Mob.- +91924040782 CONTENTS

More information

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad Annexure Prefeasibility Report (PFR) File PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of Shri Hari Dyes & Chemicals Work & Regd. Office: CONTENTS Sr. No. Description 1.

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS OF M/s. MAYUR COLOUR AND CHEMICALS LOCATED AT Plot No. 5148, GIDC Industrial Estate, Ankleshwar

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project Of MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS of 850 MT/Month By PASHUPATI INDUSTRIES 169/1/A2, Phase 1, Opposite Telephone Exchange, GIDC Naroda, Ahmedabad-382330

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT M/S. VANAS INFRA PROJECTS PVT. LTD SURVEY NO. 598, CHINTALAPALLY VILLAGE, KOLLAPUR MANDAL, NAGARKURNOOL DISTRICT, TELANGANA PRE-FEASIBILITY REPORT SUBMITTED BY M/s. Sri Soma Jitendra H. No. 7-1-397/150,

More information

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant PRE FEASIBILITY REPORT FOR Silica Sand Beneficiation Plant BY Shree Silicaam Minerals LLP VILLAGE : CHOKI TALUKA : JAGADIA DIST : BHARUCH GUJARAT (INDIA) PRE-FEASIBILITY REPORT: SILICA SAND BENIFICIATION

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT Of Shri Upendra Suryawanshi At Khasra No. 413/1, 413/3 Vill.-Ambada, Tehsil-Amla, District-Betul (M.P.) Production Capacity: Max 6,320 Cu.mt/year Area 1.00Hectare Proponent Name

More information

PRE-FEASIBILITY REPORT OF SAND QUARRY

PRE-FEASIBILITY REPORT OF SAND QUARRY PRE-FEASIBILITY REPORT OF SAND QUARRY Survey No Village Taluka District Lease area : 1 Paiki : Marigana : Anjar, : Kutch, Gujarat, : 2.00 Ha. Submitted to MINISTRY OF ENVIRONMENT & FORESTS STATE LEVEL

More information

1.1 SALIENT FEATURES OF THE PROJECT Pipeline extension from VVSPL Vijayawada to the proposed Dharmapuri Storage Terminal

1.1 SALIENT FEATURES OF THE PROJECT Pipeline extension from VVSPL Vijayawada to the proposed Dharmapuri Storage Terminal 1.0 EXECUTIVE SUMMARY Hindustan Petroleum Corporation Limited (HPCL) is one of the major Public Sector Navratna Oil Company engaged in refining, marketing and distribution of Petroleum Products in India.

More information

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR AT VILLAGE:- BRAHMPURI, TALUKA:- Sayla, DIST.:-Surendranagar 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri Door No. 39/49/39,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT OCTOBER 2017 Page 1 of 29 INDEX 1.1 EXECUTIVE SUMMARY...5 1.2 SALIENT FEATURES OF THE PROJECT...6 1.3 PROPOSED PLANNING...8 2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION...8

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT Page1 PRE FEASIBILITY REPORT KALDA FLAG STONE QUARRY AREA OF -1.55 HACTARE STRICTLY AS PER MOEF GUIDELINE DATE 30/12/2006 IN TERMS OF PROVISIONS OF EIA NOTIFICATION 2006 VILLAGE KALDA TEHSIL PAWAI DISTRICT

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

Environment Consultant:

Environment Consultant: MODERNIZATION CUM EXPANSION OF INDUCTION FURNACE PRODUCTION(2,05,000 TPA TO 6,00,000 TPA) AND ROLLING MILL PRODUCTION (3, 69,000 TPA TO 6,00,000 TPA) at Sy. No. 158 (part) 159 (part), 166 170, village

More information

Pre- Feasibility RepoRt

Pre- Feasibility RepoRt Pre- Feasibility RepoRt AREA- 59.28 ACRE (24.0 HA) FOR KEN RIVER SAND/MORRUM MINING AT BLOCK NO-09 KHAND NO-03 GATA NO-337 VILLAGE- KANWARA TEHSIL-BANDA, DISTRICT- BANDA(U.P) SHRI RAVINDRA NATH SINGH JULY

More information

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location 1. SUMMARY PRE-FEASIBILITY REPORT Project Stone Quarry Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location Village Taluka District State Rupapali Basna Mahasamund Chhattisgarh 1 Mining Lease

More information

Plot No. 2-D1, Obadenahalli, 3 rd Phase KIADB Industrial Area, Doddaballapur taluk, Bangalore Rural District , Karnataka State.

Plot No. 2-D1, Obadenahalli, 3 rd Phase KIADB Industrial Area, Doddaballapur taluk, Bangalore Rural District , Karnataka State. ON Plot No. 2-D1, Obadenahalli, 3 rd Phase KIADB Industrial Area, Doddaballapur taluk, Bangalore Rural District 561 205, Karnataka State. Table of Contents 1. EXECUTIVE SUMMARY 2. INTRODUCTION OF THE PROJECT/

More information

PRE-FEASIBILITY REPORT OF JAIPUR-PANIPAT NAPHTHA PIPELINE PROJECT PROPONENT M/S. INDIAN OIL CORPORATION LTD., PIPELINE DIVISION NOIDA

PRE-FEASIBILITY REPORT OF JAIPUR-PANIPAT NAPHTHA PIPELINE PROJECT PROPONENT M/S. INDIAN OIL CORPORATION LTD., PIPELINE DIVISION NOIDA PRE-FEASIBILITY REPORT OF JAIPUR-PANIPAT NAPHTHA PIPELINE PROJECT PROPONENT M/S. INDIAN OIL CORPORATION LTD., PIPELINE DIVISION NOIDA-201301 M.2015/ Nov, 2015 Prepared By MANTEC CONSULTANTS PVT. LTD. QCI/NABET

More information

PRE-FEASIBILITY REPORT OF AUGMENTATION OF KOYALI-SANGANER PIPELINE PROJECT PROPONENT M/S. INDIAN OIL CORPORATION LTD., PIPELINE DIVISION NOIDA

PRE-FEASIBILITY REPORT OF AUGMENTATION OF KOYALI-SANGANER PIPELINE PROJECT PROPONENT M/S. INDIAN OIL CORPORATION LTD., PIPELINE DIVISION NOIDA PRE-FEASIBILITY REPORT OF AUGMENTATION OF KOYALI-SANGANER PROJECT PROPONENT M/S. INDIAN OIL CORPORATION LTD., DIVISION NOIDA-201301 M.2015/ Dec, 2015 Prepared By MANTEC CONSULTANTS PVT. LTD. QCI/NABET

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For Excavation of Brick Earth (Total Mining Area 1.112Ha.) (For Manufacturing of Bricks) Submitted By M/s New Kaptan Brick Field Shri Krishna Kr. Singh S/o Shri Brahma DevSingh Pure

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of KATIKELA RIVER SAND BED OVER 15.00 ACRES OR 6.070 HA IN VILLAGE KATIKELA, JHARSUGUDA TAHASIL OF JHARSUGUDA DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20)

More information

PRE-FEASIBILITY REPORT. 1. SUMMARY Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2

PRE-FEASIBILITY REPORT. 1. SUMMARY Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2 PRE-FEASIBILITY REPORT 1. SUMMARY Project Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2 Village Kudeli Taluka Baikunthpur District Koriya

More information

PREFEASIBILITY REPORT FOR BRICK EARTH MINE

PREFEASIBILITY REPORT FOR BRICK EARTH MINE Page 1 PREFEASIBILITY REPORT FOR BRICK EARTH MINE Developed By- Village-Chandauhan, Tehsil-Phulpur, District-Allhabaad, Uttar Pradesh. RAI ENVIROMENTAL SERVICES PVT. LTD. Website: www.raienviro.com Email

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1. Introduction 1. Identification of project and project proponent The Pahanbarri Sand Quarry area is located in the Tawa River at Village- Pahanbarri, Tehsil- Itarsi & District-

More information

Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report

Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report Limestone Mining Project (Area: 16.18 ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For MINING ACTIVITY CATEGORY B2 UNDER

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For Polyurethane Foam Manufacturing Facility Of M/s. KRISHNA MARUTI LTD. At Plot No-13, SMG JV Park, Block No- 334,335 Vill- Hansalpur, Tal - Mandal Dist.: Ahmedabad, Gujarat INDEX

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For PROPOSED EXPANSION OF CARBON BLACK (10950 TPM TO 15750 TPM ) AND CO-GENERATION POWER PLANT (22 MW TO 32 MW) IN EXISTING PREMISES of M/s. PHILLIPS CARBON BLACK LTD. Survey No.

More information

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED 1. SUMMARY Kacari Silica Sand,Khanda,Geeti And Moram Project at Khasra No.-10,11,12,13,101, 102,122, 126, 127,128,129,130,131, 167,568,570,571,572,

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

Pre-Feasibility Report. for. Educational Institute Allen Career Institute-Supath

Pre-Feasibility Report. for. Educational Institute Allen Career Institute-Supath Pre-Feasibility Report for Educational Institute Allen Career Institute-Supath at Plot No. 1, Educational Scheme, Naya Nohra & Hanuwantkhera, Kota, Rajasthan-324001 By M/s. Allen Career Institute Registered

More information

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED 1. SUMMARY Kacari Silica Sand,Khanda,Stone And Moram Project at Khsara No.-144,145,146,147, 148,150, 309, 310, 311,312,313,314,315,316,317,318,320,399,403,404,405,

More information

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND EXECUTIVE SUMMARY Kumhari Stone Mine is situated in Village - Kumhari, P.O. Basia, P.S. - Basia, District : Gumla, Jharkhand over an area of 2.02 Hectares or 5.00 Acres [ Plot no. 2085(P)]. Kumhari Stone

More information

Brief Summary of Project

Brief Summary of Project Brief Summary of Project Project Name: 1) Acrylics/Oxo Alcohol Project at Dumad near Gujarat Refinery. 2) Creation of necessary facility for origination of Koyali-Ahmednagar-Sholapur Pipeline (KAhPL) &

More information

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT LG Polymers India Pvt. Ltd. Sy. No.s

More information

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha 1. EXECUTIVE SUMMARY 1.1 Introduction The Eknampuram Quartz mine of 89.80 Acres/ 36.34 ha is located in Sy. No. 60, Eknampuram Village, C.S. Puram Mandal, Prakasam District, Andhra Pradesh has been allotted

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT BANDOL CRUSHER STONE QUARRY OF SHRI TULSIRAM SAHU AT Khasra No. 15/2,23/2 Village Bandol Tehsil District State Madhya Pradesh Production Capacity 45030 M3/Year Area 3.150 Hectare

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

Kadam Environmental Consultants

Kadam Environmental Consultants M/s. PERSTORP INDUSTRIES INDIA PRIVATE Prefeasibility Report for Proposed Pentaerythritols Manufacturing Plant at Plot No. T 49 to T 54, Saykha Industrial Estate, Vagra Taluka, Bharuch District MARCH 2018

More information

UNSATURATED POLYESTER RESIN

UNSATURATED POLYESTER RESIN PROJECT REPORT ON UNSATURATED POLYESTER RESIN BY AQUA CHEM INDUSTRIES Survey No. 50/2, Jodhpar (Nadi), Morbi - 363641, Gujarat. I N D E X Sr. No. Contents Page No. 1 Introduction 3 2 Project Description

More information

PRE-FEASIBILTY REPORT

PRE-FEASIBILTY REPORT Aug 2018 PRE-FEASIBILTY REPORT OF M/S. J.M.R.MINES (MINING OF FELDSPAR, QUARTZ & MICA MINE) Lease Area : 5.78 Hectares(14.29 Acres) Sy.No.941,942,943 &947 Giddalur (V), Sydapuram (M), SPSR Nellore District

More information

DEVELOPMENT of. LPG Storage & Bottling Plant. Haldia. Project Feasibility Report

DEVELOPMENT of. LPG Storage & Bottling Plant. Haldia. Project Feasibility Report Hindustan Aegis LPG Limited DEVELOPMENT of LPG Storage & Bottling Plant Haldia Project Feasibility Report August 2017 1 Amendment Record: Amendment Inserted by (Name printed) Date Signature Remarks 2 Table

More information

KL) Proposed capacity of the. No change similar as existing i.e KL (MS KL, HSD KL & SKO KL) Terminal

KL) Proposed capacity of the. No change similar as existing i.e KL (MS KL, HSD KL & SKO KL) Terminal 1.0 EXECUTIVE SUMMARY Hindustan Petroleum Corporation Limited (HPCL) is one of the major Public Sector Navratna Oil Company engaged in refining, marketing and distribution of Petroleum Products in India.

More information

M/s. Lakeland Chemicals (India) Ltd.

M/s. Lakeland Chemicals (India) Ltd. FOR THE PROPOSED EXPANSION PROJECT FOR MANUFACTURING OF SPECALITY CHEMICALS Category: 5(f) A OF Located at: Plot no 63,6A,6B, Rasayani Road, Vill. Madap, Tq. Khalapur, Dist. Raigad.( Maharashtra) 1 Project

More information

MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.

MODIFIED QUARRYING PLAN FOR SHINGATALOOR SAND MINING BLOCK-2 EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY. MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT -12.00 Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.NO - 129 & 131OF SHINGATALOOR - VILLAGE MUNDARGI - TALUK GADAG - DISTRICT

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary Sri D. Ujjinappa has applied for quarry lease for extracting of Building stone in Sy No. 19/2, Chatnihalli Village, Harpanahalli Taluk, Davangere District,

More information

PRE-FEASIBILIY REPORT

PRE-FEASIBILIY REPORT BENDRI LIMESTONE QUARRY NO. - 4 3 (Quarry No. 1) (Quarry No. 1)MINERALS - DOLOMITE (LEASE PERIOD 20.05.2002 TO 19. 05.2022) LEASE AREA - 42.754 HECTARES MINING PROJECT - CATEGORY- B PRE-FEASIBILIY REPORT

More information

PROPOSED TERMS OF REFERENCE FOR THE FOR EIA STUDIES

PROPOSED TERMS OF REFERENCE FOR THE FOR EIA STUDIES Project Category Project Proponent Location Expansion of Lucknow Airport in Respect of Construction of New Integrated Terminal Building at Amausi, Lucknow, Uttar Pradesh. A [7 (a): Development of an Airport]

More information

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS Annexure No - 13 SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS File No : Name of the Project: Proposed Commercial project called Bagmane Tech Park RIO Campus of M/s. Bagmane Developers

More information

PRE-FEASIBILITY REPORT GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS)

PRE-FEASIBILITY REPORT GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS) 20 PRE-FEASIBILITY REPORT OF GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS) 1. EXECUTIVE SUMMARY: The project is for mining of Ghodach soapstone & Dolomite Mine M.L. No. 69/2010 Near

More information

Check list for construction Project of EC [Category 8(a)]:

Check list for construction Project of EC [Category 8(a)]: Check list for construction Project of EC [Category 8(a)]: Provide authenticated (with stamp & Signature) hard copy of this check-list during submission of hard copy of ToR application. Sr. no. Checklist

More information

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh.

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh. 1.0 EXECUTIVE SUMMARY 1.1 Introduction Road Metal of M/s. Lakshmi Stone Crusher covering an extent of 2.10 Ac is located at Sy. No. 379/1 of Perecherla Village, Medikonduru Mandal, Guntur District, Andhra

More information

Development of Smart Industrial Park Near Padora Village, Shivpuri, Madhya Pradesh. Project Area: hectares

Development of Smart Industrial Park Near Padora Village, Shivpuri, Madhya Pradesh. Project Area: hectares 2017 PRE FEASIBILITY REPORT Development of Smart Industrial Park Near Padora Village, Shivpuri, Madhya Pradesh. Project Area: 881.69 hectares Developed By IDC Plaza, 39-City Center, Gwalior-474011 (M.P.)

More information

PRE FEASIBILITY REPORT OF KANIYAKULAM EARTH QUARRY

PRE FEASIBILITY REPORT OF KANIYAKULAM EARTH QUARRY PRE FEASIBILITY REPORT OF AZHAGAPPAPURAM EARTH FOR OVER AN EXTENT OF 0.61.0HA IN AZHAGAPPAPURAM VILLAGE, AGASTEESWARAM TALUK, KANNIYAKUMARI DISTRICT, TAMIL NADU OF, (Under the Guidelines of Ministry of

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT ASTRICA LABORATORIES PRIVATE LIMITED SY. NO. Part of 46,50,51,52,53, 54,55&56, ANANTHSAGAR VILLAGE, CHEGUNTA MANDAL, MEDAK DISTRICT, TELANGANA PRE FEASIBILITY REPORT ASTRICA LABORATORIES PRIVATE LIMITED

More information

PRE FEASIBILTY REPORT MANUFACTURING OF ORGANIC PIGMENT M/S PRINCE CHEMICALS

PRE FEASIBILTY REPORT MANUFACTURING OF ORGANIC PIGMENT M/S PRINCE CHEMICALS PRE FEASIBILTY REPORT ON PROPOSED PROJECT FOR MANUFACTURING OF ORGANIC PIGMENT OF M/S PRINCE CHEMICALS AT PLOT NO: 9111/3,9111/2/1 GIDC ESTATE, ANKLESHWAR, DIST: BHARUCH, STATE: GUJARAT 1 Index Sr no.

More information

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative) Six Monthly Progress Report reg. Construction of Group Housing Colony at village Sarai Aurangabad in Sector 3-A, Bahadurgarh (Distt. Jhajjar), Haryana by M/s Prabhu Shanti Real Estate Pvt. Ltd., due in

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT PREPARED FOR SHIV SHANTHI CEMENT PRIVATE LIMITED Sy. Nos. 92, 93 & 94, Tatiguda Village, Garividi Mandal, Vizianagaram District, Andhra Pradesh. PREPARED BY ISO 9001: 2008 Certified

More information

CHAPTER REHABILITATION AND RESETTLEMENT (R&R) PLAN (I) POLICY TO BE ADOPTED (CENTRAL / STATE)... 32

CHAPTER REHABILITATION AND RESETTLEMENT (R&R) PLAN (I) POLICY TO BE ADOPTED (CENTRAL / STATE)... 32 CONTENTS CHAPTER 1... 1 1.0 PROJECT SUMMARY... 1 CHAPTER 2... 2 2.0 INTRODUCTION... 2 (I) IDENTIFICATION OF PROJECT AND PROJECT PROPONENT... 2 (II) BRIEF DESCRIPTION OF NATURE OF THE PROJECT... 2 (III)

More information

BALAJI AMINES LIMITED

BALAJI AMINES LIMITED FOR EXPANSION OF EXISTING SYNTHETIC ORGANIC CHEMICALS MANUFACTURING UNIT BALAJI AMINES LIMITED At Plot No: 4 & 5, Beside Sub-Station-II, I.D.A, Bollaram, Jinnaram (M), Medak District, Telangana State -

More information

M/s. NGL Fine-Chem Limited Plot no. S 18/3, Tarapur MIDC, Boisar, District Palghar, Maharashtra. PIN:

M/s. NGL Fine-Chem Limited Plot no. S 18/3, Tarapur MIDC, Boisar, District Palghar, Maharashtra. PIN: Pre-feasibility Study Report For M/s. NGL Fine-Chem Limited Plot no. S 18/3, Tarapur MIDC, Boisar, District Palghar, Maharashtra. PIN: 401506 Prepared By: M/s SADEKAR ENVIRO ENGINEERS PVT. LTD. Accredited

More information

PRE-FEASIBILTY REPORT SUNATHAR STONE QUARRY. VILLAGE: Sunathar. TAHASIL: Purushottampur. DIST: Ganjam LESSEE SRI KAPILA CHANDRA SAHU

PRE-FEASIBILTY REPORT SUNATHAR STONE QUARRY. VILLAGE: Sunathar. TAHASIL: Purushottampur. DIST: Ganjam LESSEE SRI KAPILA CHANDRA SAHU PRE-FEASIBILTY REPORT OF SUNATHAR STONE QUARRY VILLAGE: Sunathar TAHASIL: Purushottampur DIST: Ganjam LESSEE SRI KAPILA CHANDRA SAHU Vill/Po- Gandala, P.S.- Hinjili, Dist.-Ganjam Odisha. CONTENTS CHAPTER

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary Smt. J N Rukmini, has applied for extracting of Building stone in Sy No. 40, Kuroda Bore Kavala village, Hassan Taluk & District, Karnataka over an extent

More information

Kadam Environmental Consultants w w w. k a d a m e n v i r o. c o m

Kadam Environmental Consultants w w w. k a d a m e n v i r o. c o m AHIR SALT AND ALLIED PRODUCTS PVT. LTD. Pre-feasibility report for Revival of Existing Jetty with Liquid Storage Terminal, Pipeline, road connectivity, Railway line and sidings at Mithirohar near (Kandla),

More information

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) 1) Executive Summary Project Name of Company / Mine Owner Location Village Taluka District State Girgita Limestone Mine M/s KJS

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For NEW MANUFCTURING PLANT Of BHIMANI DYE CHEM INDUSTRIES Plot No. 2, Survey No. 316, At: Dhanot, Ta: Kalol, Dist: Gandhinagar, Gujarat. CONTENTS Sr.No. Description 1. Executive

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT EXECUTIVE SUMMARY 1.0 Executive Summary The Mining lease was granted in favour of Shri Mukesh Kumar S/o Shri Harish Chandra, R/o Tatol vaya Bagra, Tehsil - Bhinmal, Dist.-Jalore

More information