1 MCA Michael Calafati Architect, LLC 510 Bank Street, P.O.Box 2363, Cape May, NJ T F Addendum No. 1 Date: Friday, August 10, 2018 To: Re: From: Copy: Length: Via: All Bidders of Record Bayside Center Improvements - Phase 3A Project 520 Bay Avenue Ocean City, New Jersey Block 508 / Lot 10 City Contract #18-37 Michael Calafati, AIA Joseph S. Clark, Purchasing Manager, City of Ocean City Darleen H. Korup, Purchasing Assistant, City of Ocean City Christine D. Gundersen, Manager of Capital Planning, City of Ocean City Roger Rinck, Manager Engineering and Construction, City of Ocean City 5 pages total (3 cover pages + 1 pg. Agenda + 1 pg. Sign-In Sheet) ed as a PDF file attachment only and/or faxed to all Bidders of Record YOU ARE DIRECTED TO MAKE THE FOLLOWING changes and/or accommodate the following clarifications to the Bid Documents. Acknowledge the receipt of this addendum with the bid proposal submitted. 1.1 Pre-Bid Meeting. Attached please find an agenda and a list of attendees for the (nonmandatory) Pre-Bid Meeting that was held at the site on Tuesday, July 17, Federal CBDG/HUD Requirements. The specific requirements of this project were highlighted at the Pre-Bid Meeting, as the source of the project funding is federal. [Note: The General Instructions to Bidders portion of the Project Manual is lengthier than most other City projects. Bidders should pay special attention to minority participation, governing wage rates and all other federal requirements (e.g. the note on the bottom of page 61 of 103).] 1.3 Bond Obligee. Clarification - While the Property Owner is the County of Cape May, the Client and Owner for the purposes of this contract is the City of Ocean City. Therefore, it is the City of Ocean City who should be listed as the Obligee on the bond(s) as the City of Ocean City will be the contracting entity. 1.4 Bid Proposal Form. Regarding the Bid Proposal Form (5 pages in the Project Manual), please note the following: a. Alternate #1 must be clearly indicated as either a positive or negative amount. Insert a plus ( + ) or a minus ( - ) symbol before the dollar figure. Alternately, you may clearly circle the + or symbol below the dollar figure. b. Insert 0 (zero) on the line for Base Subitem #4 for the Pavilion, as all work on

2 Addendum #1: Bayside Center Improvements - Phase 3A Project August 10, 2018 Page 2 of 3 this particular structure has been deleted from the project (see further discussion below). 1.5 Facilities. The successful bidder may use the Owner s water and electric. The successful bidder must provide a portable toilet for use by the construction staff. 1.6 Hazardous Materials. Given the age and type of existing exterior wall siding, there is a possibility that the materials are ACMs (asbestos-containing materials). Take all necessary precautions not to disturb these surfaces during construction. 1.7 Pavilion. The work requirements at the Pavilion are deleted from the Project Scope. Accordingly, drawing A300 and the description on pages and of the Project Manual (as they pertain to the Pavilion) do not apply. Similarly, references to Division 05 may be ignored. 1.8 Selective Demolition. Regarding Division 02 Site Work (and Base Bid Subitem #2), in addition to the removal and disposal of layers of existing roof shingles at the Main House, Pool House and Garage, include the removal and proper disposal of the existing gutters and leaders at the Pool House and Garage. 1.9 Masonry. Regarding Division 04 Masonry (and Base Bid Subitem #3), no corresponding section is provided in the Project Manual. However, the existing brick chimneystack is to be raked and repointed (100%) above the roofline as part of this project. Provide a $4,000 allowance for this aspect to cover the cost of materials and labor. The cost for access and staging to accomplish the masonry work, however, is to be included in Base Bid Subitem # Rough Carpentry. Regarding Division 06 Wood and Plastics (and Base Bid Subitem #5), no corresponding section is provided in the Project Manual. Therefore: a. Assume that up to 10% of the existing wood sheathing will require replacement due to deterioration. Use minimum ½ thick 4-ply plywood suitable for roof sheathing or Architect-approved equal. Shim rafters as (if) required in order to maintain uniformly flat sheathing Old and new). Applies to Main House, Pool House and Garage only. b. Provide a $4,000 allowance for additional (unforeseen) rough carpentry repairs other than wood sheathing replacement noted immediately above Finished Carpentry. Regarding Division 06 Wood and Plastics (and Base Bid Subitem #6), no corresponding section is provided in the Project Manual. Therefore: a. Provide a $4,000 allowance for in-kind finished carpentry repairs, such as roof fascias, running trim, overhangs, exposed rafter tails, and soffits (undersides of eaves). Applies to Main House, Pool House and Garage only Roofing. Regarding Division 07 Thermal and Moisture Protection (and Base Bid Subitem #7), please note:

3 Addendum #1: Bayside Center Improvements - Phase 3A Project August 10, 2018 Page 3 of 3 a. Provide a $4,000 allowance for new straight sections of new half-round aluminum gutters and leaders in white to be installed on the north elevation of the Main House and the west elevation of the Pool House Paintings and Coatings. Regarding Division 09 Painting (and Base Bid Subitem #8), no corresponding section is provided in the Project Manual. Therefore: a. Dry-scrape all blistered and detached existing paint at wood surfaces of roof fascias, running trim, overhangs, exposed rafter tails, and soffits (undersides of eaves) directly related to the roofs of the Main House, Pool House and Garage (Pavilion not included). Use Lead-Safe Practices, including proper personnel protection, the collection of all loosened paint chips and their proper disposal. b. Clean all surfaces to assure proper adhesion of new paint. In order to insure that the wood surfaces do not become saturated with moisture, do not power wash without reviewing the procedure for doing so without the prior approval of the Architect. In addition, allow for proper drying time. c. Preparation shall include the patching of surface irregularities (openings, holes and other imperfections) with a filler where gutters, leaders and extraneous items have been removed. Use a 2-part epoxy or Architect-approved equal. d. Spot prime where wood is exposed or remaining paint is thin. Use Sherwin- Williams Exterior Oil-Based Wood Primer or Architect-approved equal. e. Apply two finished coats. Use Sherwin Williams Emerald Exterior Acrylic Latex Paint in White (Semi-Gloss) or Architect-approved equal. f. Provide 2-gallons of addition paint as attic stock Allowances. Allowances include, but not necessary limited to, the following: a. $4,000 for masonry as described above (Base Bid Subitem #3). b. $4,000 for additional rough carpentry repairs (Base Bid Subitem #5). c. $4,000 for in-kind finished carpentry repairs (Base Bid Subitem #6). d. $4,000 for new gutters and leaders as described above (Base Bid Subitem #7). In all cases the allowances are to be incorporated into (part of) the corresponding line items submitted on the Bid Proposal Form Receipt of Bid Proposals. The date, time and location for the receipt of Bid Proposals remain unchanged (by 2:00 PM on 08/21/18, as previously noticed). End of Addendum No. 1

4 MCA Michael Calafati Architect, LLC 510 Bank Street, P.O.Box 2363, Cape May, NJ T F Bayside Center Improvements - Phase 3A Project City Contract No Bay Avenue, Ocean City, New Jersey :30 a.m., Tuesday, July 17, 2018 Pre-Bid Meeting Agenda I. Introduction: A. Owner The County of Cape May B. Client The City of Ocean City C. Architect - Michael Calafati Architect, LLC, Michael Calafati, AIA, Principal D. Project Funding The City of Ocean City and a Community Development Block Grant (CDBG) from the U.S. Department of Housing and Urban Development. II. Bid Documents in multiple parts: A. Project Manual (Part I) - Owner s Requirements, including CDBG requirements. B. Project Manual (Part II) - Technical Specifications. C. Drawings (Part III) - 18 x 24 format for Architectural Drawings. D. Addenda to be issued during the bid period. Note: Documents are available only as PDF files sent as an attachment from the Architect at no cost or for purchase from the City of Ocean City s Purchasing Department. III. Scope of Work: A. Base Bid: The project entails roof replacement and related repairs at the Main House, Pavilion, Pool House and Garage. B. Line-Item Breakdowns, Add Alternates, Unit Prices and Allowances: Refer to the Bid Proposal Form. IV. Timetable: A. Bid Documents Release Date Wednesday, July 11 th B. Pre-Bid Walk Thru Meeting at Site Tuesday, July 17 at 10:30 a.m. C. Last Day for Bidders Questions/RFIs Friday, August 3 rd by 4:00 p.m. D. Last Day for the issuance of Addenda Friday, August 10 th E. Receipt of Bids at City Hall Tuesday, August 21 st at 2:00 p.m. F. Contract Authorization by City Council Thursday, September 13 th * Questions and RFIs must be submitted in writing via to michael@calafati.com. V. Follow-Up Site Visitation: A. Return site visits are possible M-F with advance arrangement. Contact Wendy Moyle, Manager of Recreation Programs, two days in advance (suggested minimum) at

5

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building.

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building. ADDENDUM #1 EXTERIOR REPAIRS YOUTH SERVICES BUREAU 63 LINDEN STREET MANCHESTER, CT 06040 BID #15/16-68 S/P+A PROJECT NO. 15.207 DATE: March 15, 2016 The following changes to the Drawings and Project Specifications

More information

REQUEST FOR BIDDER QUALIFICATIONS

REQUEST FOR BIDDER QUALIFICATIONS CITY OF OCEAN CITY CAPE MAY COUNTY, NEW JERSEY 08226 REQUEST FOR BIDDER QUALIFICATIONS Phase II Improvements at the Ocean City Life Saving Station 801 4 th Street, Ocean City, NJ 08226 Pursuant to N.J.S.A.

More information

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732)

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732) THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ 08904 PHONE (732)572-4420 February 10, 2017 Window Replacements at Samuel J Kronman Building and Park Terrace

More information

CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO

CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO. 16-01 RESTORATION OF THE HISTORIC TRANSPORTATION CENTER PHASE III BID RECEIPT: o Sealed bids shall be received

More information

FOR IFB #PC436 Exterior Improvements at Colton Public Housing Complex

FOR IFB #PC436 Exterior Improvements at Colton Public Housing Complex HOUSING AUTHORITY OF THE COUNTY OF SAN BERNARDINO PROCUREMENT AND CONTRACTS DEPARTMENT 715 E. BRIER DRIVE, SAN BERNARDINO, CA 92408 (909) 890-0644 FAX (909) 890-2349 http://www.hacsb.com/procurement.htm

More information

Addendum 1 Residential Reroofing at Multiple Public Housing Developments. Town of Chapel Hill, NC ZAKIA ALAM, PURCHASING & CONTRACTS MANAGER

Addendum 1 Residential Reroofing at Multiple Public Housing Developments. Town of Chapel Hill, NC ZAKIA ALAM, PURCHASING & CONTRACTS MANAGER Addendum I For Residential Reroofing at Multiple Public Housing Developments Town of Chapel Hill, NC BID: Q18-141 TO: FROM: SUBJECT: ALL PROSPECTIVE BIDDERS ZAKIA ALAM, PURCHASING & CONTRACTS MANAGER DATE:

More information

TELEPHONE: (215) ADDENDUM No. 1

TELEPHONE: (215) ADDENDUM No. 1 THE SCHOOL DISTRICT OF PHILADLPHIA SCHOOL REFORM COMMISSION Office of Capital Programs 440 North Broad Street, 3 rd Floor Suite 371 Philadelphia, PA 19130 TELEPHONE: (215) 400-4730 ADDENDUM No. 1 Subject:

More information

STUDIO 2LR ARCHITECTURE + INTERIORS

STUDIO 2LR ARCHITECTURE + INTERIORS STUDIO 2LR ARCHITECTURE + INTERIORS University of South Carolina Longstreet Theatre Shutter Replacement 1300 Greene Street, Columbia, South Carolina State Project Number: H27-6100-F February 18, 2015 ADDENDUM

More information

LSCC MISC. PROJECTS (PACKAGE D) MILLSAP BUILDING ROOF REPLACEMENT Addendum 3

LSCC MISC. PROJECTS (PACKAGE D) MILLSAP BUILDING ROOF REPLACEMENT Addendum 3 LSCC MISC. PROJECTS (PACKAGE D) MILLSAP BUILDING ROOF REPLACEMENT Addendum 3 PART 1 - GENERAL Project: Open-End Agreement for Misc. Projects Package D Millsap Building [B.C. # 2018332] Owner: Lawson State

More information

A. Remove Table of Contents and insert new attached Table of Contents.

A. Remove Table of Contents and insert new attached Table of Contents. ADDENDUM NO. 01 PROJECT Colby Glass E.S. Window Upgrades and ADA Work PROJECT NO. 16043 DATE February 07, 2018 TO: All Prime Contract Bidders and all others to whom Drawings and Specifications have been

More information

ENGINEERING BUILDING ROOF REPLACEMENT

ENGINEERING BUILDING ROOF REPLACEMENT ENGINEERING BUILDING ROOF REPLACEMENT SOLICITATION NO. 2017-06 March 13, 2017 St. Clair County, Illinois, through the Public Building Commission (herein after referred to as OWNER ), hereby gives notice

More information

ALL BIDDERS OF RECORD, CONSULTANTS, OWNER:

ALL BIDDERS OF RECORD, CONSULTANTS, OWNER: ADDENDUM NUMBER ONE for Project No.: U-787-14-1 State Permanent Improvement Project No.: H27-Z167 COLUMBIA, SOUTH CAROLINA PREPARED BY: The Boudreaux Group 1330 Lady Street, Columbia, SC 29201 DATE OF

More information

DAYTONA BEACH PIER BUILDING RESTORATION 06/10

DAYTONA BEACH PIER BUILDING RESTORATION 06/10 SECTION 099113 - EXTERIOR PAINTING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes surface preparation and the application of paint systems on the following exterior substrates: 1. Steel. 2. Galvanized

More information

ADDENDUM #1 NWIT Exterior Repainting Various Locations, New Westminster, BC

ADDENDUM #1 NWIT Exterior Repainting Various Locations, New Westminster, BC August 3, 2016 ADDENDUM #1 NWIT-16-28 Exterior Repainting Various Locations, New Westminster, BC This addendum modifies the Invitation to Tender only as noted: BID FORM Section 6.0 Separate Prices revise

More information

Hillsborough City School District Window Covering Projects At 6 District Sites. Bid #19-01 ADDENDUM NO. 1

Hillsborough City School District Window Covering Projects At 6 District Sites. Bid #19-01 ADDENDUM NO. 1 Window Covering Projects At 6 District Sites Bid #19-01 ADDENDUM NO. 1 February 13, 2019 Owner: Project Manager: 300 El Cerrito Avenue Hillsborough, CA 94010 Capital Program Management, Inc. 1851 Heritage

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 09 - FINISHES

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 09 - FINISHES SECTION 099113 - EXTERIOR PAINTING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes surface preparation and the application of paint systems on the following exterior substrates: 1. Concrete. 2. Concrete

More information

TRIAD ENGINEERING CONSULTANTS, INC.

TRIAD ENGINEERING CONSULTANTS, INC. TRIAD ENGINEERING CONSULTANTS, INC. 2638 Willard Dairy Rd Providing High Point, NC Suite 100 Plumbing, Mechanical and 27265 (336) 454-0225 Electrical Engineering Services Since 1984 admin@triadengmep.com

More information

RIVERSIDE CHURCH OF CHRIST. Lafayette, LA

RIVERSIDE CHURCH OF CHRIST. Lafayette, LA SECTION 000010 INVITATION FOR BIDS Bids for will be received in the office of Church Development Construction Services, 708 S. Rosemont Road, Suite #101,, until 12:00 noon Local Prevailing Time on Friday,

More information

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT 06045-0191 138 MCKEE STREET MANCHESTER, CT BID NO. 16/17-5 ADDENDUM NO. 1 1. The bid opening has been

More information

BID ADDENDUM. 1 of 1. State Project No: H27-Z381 ADDENDUM NO.: PROJECT NAME: 1600 Hampton St. Building Roof Replacement

BID ADDENDUM. 1 of 1. State Project No: H27-Z381 ADDENDUM NO.: PROJECT NAME: 1600 Hampton St. Building Roof Replacement BID ADDENDUM State Project No: H27-Z381 PROJECT NAME: 1600 Hampton St. Building Roof Replacement ADDENDUM NO.: One ADDENDUM ISSUE DATE: January 24, 2019 TO ALL BIDDERS: This addendum is issued for the

More information

Town of Atkinson, New Hampshire INVITATION TO BID. Town Garage Roof Replacement Issued: June 30, 2015

Town of Atkinson, New Hampshire INVITATION TO BID. Town Garage Roof Replacement Issued: June 30, 2015 Town of Atkinson, New Hampshire INVITATION TO BID Town Garage Roof Replacement Issued: June 30, 2015 The Town of Atkinson invites qualified contractors to bid on the replacement of the roof of the Town

More information

Wesleyan University 1.1 RELATED INFORMATION, DOCUMENTS AND REQUIREMENTS

Wesleyan University 1.1 RELATED INFORMATION, DOCUMENTS AND REQUIREMENTS Wesleyan University SCOPE OF WORK 346 WASHINGTON STREET ASPHALT ROOF REPLACEMENT PROJECT 23AB VINE STREET ASPHALT ROOF REPLACEMENT PROJECT 72 HOME NORTH SIDE ROOF REPLACEMENT 64 FOUNTAIN AVE ROOF REPAIR

More information

2. Clarification: The building address is 801 Henderson Street.

2. Clarification: The building address is 801 Henderson Street. East Energy Structural Steel Painting University of South Carolina Project Number H27-Z037 Addendum One October 19, 2015 NOTE: The following amendments, additions, and deletions shall be made to the Construction

More information

DOCUMENT BID FORM - STIPULATED SUM (MULTIPLE-PRIME CONTRACTS) Bidder:.

DOCUMENT BID FORM - STIPULATED SUM (MULTIPLE-PRIME CONTRACTS) Bidder:. DOCUMENT 004120 - BID FORM - STIPULATED SUM (MULTIPLE-PRIME CONTRACTS) BID INFORMATION Bidder:. Project Name: Remodeling for Urban Style Apartments 409 N. Broadway Green Bay, WI 54303 Owner: Architect:

More information

To All Interested Parties of the following Project: Project # Scattered Sites Roof Replacement, Gutters and Fascia

To All Interested Parties of the following Project: Project # Scattered Sites Roof Replacement, Gutters and Fascia To All Interested Parties of the following Project: Project # 2017-04 Scattered Sites Roof Replacement, Gutters and Fascia Addendum #3 Dated: February 1, 2017 BID DUE DATE REMAINS UNCHANGED Date: February

More information

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab.

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab. Willow Glen Housing Repairs Project #9-59 Addendum Item. Change to bid date The bid date will be extended to March 8, 09, :00pm at the Housing Authority of Columbus Central Office,000 Wynnton Road Columbus,

More information

SCOPE OF WORK BID TAB

SCOPE OF WORK BID TAB Housing and Neighborhood Services of Rock Hill SCOPE OF WORK BID TAB Job # BID-CDBG #23 Bid is to be turn-key, including all applicable code requirements, materials, labor, City Business License permits,

More information

revisions to project manual Bid Form: Added deduct alternate 07. Refer to written responses below for explanation.

revisions to project manual Bid Form: Added deduct alternate 07. Refer to written responses below for explanation. a r c h i t e c t u r e d e s i g n p l a n n i n g m a n a g e m e n t 27 March 2019 27 March 2019 Addendum 01 Sumner County Administration Building Reroof To All Holders of the Contract Documents: The

More information

Purchasing and Property Services AOC East Fowler Avenue Tampa, Florida (813)

Purchasing and Property Services AOC East Fowler Avenue Tampa, Florida (813) Purchasing and Property Services AOC 200 4202 East Fowler Avenue Tampa, Florida 33620 (813) 974-2481 Web Address: http://usfweb2.usf.edu/purchasing/purch2.htm April 23, 2015 Invitation to Bid No. Entitled:

More information

TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS OFFICE OF COLONIA INITIATIVES TEXAS BOOTSTRAP LOAN PROGRAM. Form 15 Work Write-Up

TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS OFFICE OF COLONIA INITIATIVES TEXAS BOOTSTRAP LOAN PROGRAM. Form 15 Work Write-Up TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS OFFICE OF COLONIA INITIATIVES TEXAS BOOTSTRAP LOAN PROGRAM Form 15 Work Write-Up Owner-Builder Applicant Owner-Builder Co-Applicant Physical Address: City,

More information

ADDENDUM NO. 1 DES MOINES PUBLIC SCHOOLS WINDSOR ELEMENTARY SCHOOL EXTERIOR MASONRY RESTORATION PROJECT 5912 UNIVERSITY AVENUE DES MOINES, IOWA 50311

ADDENDUM NO. 1 DES MOINES PUBLIC SCHOOLS WINDSOR ELEMENTARY SCHOOL EXTERIOR MASONRY RESTORATION PROJECT 5912 UNIVERSITY AVENUE DES MOINES, IOWA 50311 ADDENDUM #1 WINDSOR ELEMENTARY SCHOOL EXTERIOR MASONRY RESTORATION ANGELO JOB NO. 1213 Page 1 of 2 Total ANGELO ARCHITECTURAL ASSOCIATES 12314 Ridgeview Drive Urbandale, IA 50323 Ph: 515-250-6950 Fax:

More information

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320 REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE 2015 2016 ROOF AND HVAC REPLACEMENT PROJECT PW1320 Issued by: City of Stockton Public Works Department 22 E. Weber Avenue, Room 301 Stockton, CA 95202

More information

PROJECT # University of South Carolina, Aiken USCA Convocation Center Shed Aiken, South Carolina ADDENDUM NUMBER

PROJECT # University of South Carolina, Aiken USCA Convocation Center Shed Aiken, South Carolina ADDENDUM NUMBER University of South Carolina, Aiken PROJECT #10010.01 SECTION 00911 - ADDENDUM NUMBER 2 PARTICULARS 1.01 DATE: April 10, 2012 1.02 PROJECT: USC AIKEN CONVOCATION CENTER SHED 1.03 STATE PROJECT NUMBER:

More information

Farmington Public Schools 2015 Bond Issue Bid Package 9- Beechview & Kenbrook Elementary School Remodeling Project Wednesday, January 24, 2018

Farmington Public Schools 2015 Bond Issue Bid Package 9- Beechview & Kenbrook Elementary School Remodeling Project Wednesday, January 24, 2018 Farmington Public Schools 2015 Bond Issue Bid Package 9- Beechview & Kenbrook Elementary School Remodeling Project Wednesday, January 24, 2018 POST-BID ADDENDUM 1 CONSTRUCTION MANAGEMENT PACKAGE - Bidding

More information

4615 E. State Street Suite 206 Rockford Illinois /

4615 E. State Street Suite 206 Rockford Illinois / ADDENDUM NO. 2 Date: April 29th 2015 4615 E. State Street Suite 206 Rockford Illinois 61108 815 / 397-3330 Project: Whiteside County Health Department New Facility and Interior Renovation Project Number:

More information

Moonlight Architecture, Inc. Architecture Interior Design Site Planning

Moonlight Architecture, Inc. Architecture Interior Design Site Planning Moonlight Architecture, Inc. Architecture Interior Design Site Planning 22 May 2018 18057 Mr. Michael J. Petit de Mange, County Administrator Kent County Levy Court 555 Bay Road Dover, DE 19901 RE: Facilities

More information

Butte County Fire Department Fire Prevention Bureau 176 Nelson Avenue Oroville, CA Office (530)

Butte County Fire Department Fire Prevention Bureau 176 Nelson Avenue Oroville, CA Office (530) 2016 CBC Chapter 7A and CRC Section R337 (The use of paints, coatings, stains, or other surface treatments are not an approved method of protection as required in this chapter.) The Wildland Urban Interface

More information

WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES

WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES 1. Introduction WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES The Town of West Yellowstone (Town) is seeking a qualified

More information

ADDENDUM # 2 LOUISA COUNTY PUBLIC LIBRARY ROOF REPLACEMENT PROJECT IFB# GS-18-02

ADDENDUM # 2 LOUISA COUNTY PUBLIC LIBRARY ROOF REPLACEMENT PROJECT IFB# GS-18-02 August 25, 2017 To: From: Prospective Bidders, and Plan Holders County of Louisa, Dewberry and HDH Associates ADDENDUM # 2 LOUISA COUNTY PUBLIC LIBRARY ROOF REPLACEMENT PROJECT IFB# GS-18-02 CHANGES AND

More information

SECTION COMMERCIAL CURB-MOUNT ACRYLIC DOUBLE DOME SKYLIGHTS

SECTION COMMERCIAL CURB-MOUNT ACRYLIC DOUBLE DOME SKYLIGHTS SECTION 08620 COMMERCIAL CURB-MOUNT ACRYLIC DOUBLE DOME SKYLIGHTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

MAKE THE FOLLOWING ADDITIONS, MODIFICATIONS OR DELETIONS TO THE DRAWINGS AND SPECIFICATIONS:

MAKE THE FOLLOWING ADDITIONS, MODIFICATIONS OR DELETIONS TO THE DRAWINGS AND SPECIFICATIONS: ADDENDUM NO. 1 CITY OF PORT ARANSAS ELLIS MEMORIAL EXISTING LIBRARY RENOVATIONS AND REPAIRS CSP #2016-22 700 W. AVE A PORT ARANSAS, TX 78373 Issue Date: 01/07/2019 The following additions, deletions, modifications,

More information

All bidders shall indicate in their bid/proposal that this Addendum has been received and considered in their bid proposal.

All bidders shall indicate in their bid/proposal that this Addendum has been received and considered in their bid proposal. Addendum #1 Window Replacements at [4] Buildings Desoto Bass Court, OH5-2A, AMP 7 IFB #13-02 May 6, 2013 Greater Dayton Premier Management 400 Wayne Ave. Dayton, Ohio 45410 This Addendum modifies and shall

More information

PAWLEYS ISLAND TOWN HALL

PAWLEYS ISLAND TOWN HALL DOCUMENT 001116 - INVITATION TO RE-BID 1.1 PROJECT INFORMATION A. Notice to Bidders: Prequalified bidders are invited to submit bids for Project as described in this Document according to the Instructions

More information

REROOFING THE CAREER TECHNICAL SCHOOL FOR THE CLEBURNE COUNTY BOARD OF EDUCATION HEFLIN, ALABAMA

REROOFING THE CAREER TECHNICAL SCHOOL FOR THE CLEBURNE COUNTY BOARD OF EDUCATION HEFLIN, ALABAMA McKee and Associates Architecture and Interior Design Addendum No. FOUR Date: 07.17.17 Project: REROOFING THE CAREER TECHNICAL SCHOOL FOR THE CLEBURNE COUNTY BOARD OF EDUCATION HEFLIN, ALABAMA A4.1 GENERAL

More information

A. Section includes surface preparation and the application of high-performance coating systems on the following substrates:

A. Section includes surface preparation and the application of high-performance coating systems on the following substrates: ILLINOIS STATE UNIVERSITY CORDOGAN, CLARK & ASSOCIATES, INC. WATTERSON DINING EXPANSION PROJECT 960 RIDGEWAY AVENUE NORMAL, ILLINOIS AURORA, ILLINOIS CCA PROJECT NUMBER: 14362 630-896-4678 BID SET JULY

More information

TITLE PAGE SCOPE OF WORK MAP / FLOOR PLAN; AS424 MAP / FLOOR PLAN; RR50 MAP / FLOOR PLAN; DD3, DD4, DD5, DD6, DD36, DD37 RR50

TITLE PAGE SCOPE OF WORK MAP / FLOOR PLAN; AS424 MAP / FLOOR PLAN; RR50 MAP / FLOOR PLAN; DD3, DD4, DD5, DD6, DD36, DD37 RR50 8/5/05 NEW RIVER AIR STATION AS CAMP LEJEUNE DD3, DD, DD5, DD6, DD36, DD37 T A A A3 A TITLE PAGE SCOPE OF WORK MAP / FLOOR PLAN; AS MAP / FLOOR PLAN; RR50 MAP / FLOOR PLAN; DD3, DD, DD5, DD6, DD36, DD37

More information

MECHANICAL SYSTEM REPLACEMENT BROWN COUNTY COURTHOUSE 200 EAST COURT STREET MOUNT STERLING, ILLINOIS 62353

MECHANICAL SYSTEM REPLACEMENT BROWN COUNTY COURTHOUSE 200 EAST COURT STREET MOUNT STERLING, ILLINOIS 62353 ARCHITECHNICS, INC. 510 MAINE STREET QUINCY, ILLINOIS 62301 PROJECT NO. : 5661A ADDENDUM NO.: 1 ISSUED: 12/4/2017 Project: MECHANICAL SYSTEM REPLACEMENT BROWN COUNTY COURTHOUSE 200 EAST COURT STREET MOUNT

More information

NFL Building Sloped Roof Replacement

NFL Building Sloped Roof Replacement NFL Building Sloped Roof Replacement Summary of Scope of Work The NFL Building has sloped asphalt shingle roofs and flat roofs, this project includes the replacement of the sloped main roofs and small

More information

Exterior Trellis Painting Horticulture 5000 & 5100

Exterior Trellis Painting Horticulture 5000 & 5100 Exterior Trellis Painting Horticulture 000 & 00 600 Soquel Dr, Aptos, CA 900 Exterior Painting of Building 000 SCOPE OF SERVICES BASE RESPONSIBILITIES: Paint the exterior of Horticulture Building 000 all

More information

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding

More information

SECTION TEMPORARY ROOFING MEMBRANE INSTALLATION. A. Areas of the roof deck for asbestos abatement.

SECTION TEMPORARY ROOFING MEMBRANE INSTALLATION. A. Areas of the roof deck for asbestos abatement. PART 1 GENERAL 1.01 APPLICATIONS SECTION 07500 TEMPORARY ROOFING MEMBRANE INSTALLATION A. Areas of the roof deck for asbestos abatement. B. Areas of the roof deck exposed to the structural roof deck substrate.

More information

F. EXTERIOR SIDINGS, FINISHES, FACINGS and MATERIALS

F. EXTERIOR SIDINGS, FINISHES, FACINGS and MATERIALS F. EXTERIOR SIDINGS, FINISHES, FACINGS and MATERIALS In order to preserve the historic features found within Ocean Grove, the HPC strongly discourages the removal, replacement, layering or covering of

More information

Historic Structure Treatment Record

Historic Structure Treatment Record Historic Structure Treatment Record Stephen T. Mather Training Center For the Stephen T. Mather Training Center PMIS #161111 Historic Preservation Training Center National Park Service Frederick, MD December

More information

ADDENDUM NUMBER TWO. for SWIM TEAM LOCKER ROOM RENOVATIONS REBID UNIVERSITY OF SOUTH CAROLINA COLUMBIA, SOUTH CAROLINA. DATE OF ISSUE: June 19, 2014

ADDENDUM NUMBER TWO. for SWIM TEAM LOCKER ROOM RENOVATIONS REBID UNIVERSITY OF SOUTH CAROLINA COLUMBIA, SOUTH CAROLINA. DATE OF ISSUE: June 19, 2014 ADDENDUM NUMBER TWO for SWIM TEAM LOCKER ROOM RENOVATIONS REBID UNIVERSITY OF SOUTH CAROLINA COLUMBIA, SOUTH CAROLINA DATE OF ISSUE: June 19, 2014 TO: ALL BIDDERS OF RECORD This Addendum is issued pursuant

More information

SECTION PANEL SIGNAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION PANEL SIGNAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 101423 - PANEL SIGNAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SSL-175. Specifications

SSL-175. Specifications SSL-175 Specifications Everlast Metals 10 Enterprise Court Lebanon, PA 17042 Phone: (717) 270-6554 Fax: (717) 270-6569 www.everlastmetals.com 7410 Preformed Metal Roofing PART 1: GENERAL 1.01 SECTION INCLUDES

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: OWNER: Shell and Core Improvements-1235 Mission Scope 1: Stairs DATE: December 29, 2017 1235 Mission Street San Francisco, California SFUSD Project

More information

Hays CISD IH 35 Kyle, Texas ext August 2018

Hays CISD IH 35 Kyle, Texas ext August 2018 Hays CISD 21003 IH 35 Kyle, Texas 78640 512-268-2141 ext. 45092 Email: valerie.littrell@hayscisd.net 13 August 2018 Date: August 14, 2018 ADDENDUM 1 Bid#: 18-071802VL Lehman HS Roof Replacements Opening

More information

Addendum # 6. Date: March 16, 2017 RFT Construction of New Building Addition to the Town of Caledon Yard 1 Garage Building

Addendum # 6. Date: March 16, 2017 RFT Construction of New Building Addition to the Town of Caledon Yard 1 Garage Building Addendum # 6 Date: March 16, 2017 RFT 2017-08 Construction of New Building Addition to the Town of Caledon Yard 1 Garage Building Closing Date: Friday, March 17, 2017 2:00 PM This addendum refers to additions,

More information

Façade Improvement Specifications: 221 S. Lafayette, Greenville, MI. General Section:

Façade Improvement Specifications: 221 S. Lafayette, Greenville, MI. General Section: Façade Improvement Specifications:, Greenville, MI SEE ARCHITECTUAL RENDERINGS ATTACHED TO PROVIDE ADDITIONAL DETAIL: General Section: $ General Building Permit: Permit for working on project. Contact

More information

This Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect.

This Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect. GADSDEN STATE COMMUNITY COLLEGE OPEN-END AGREEMENT FOR MISC. PROJECTS, PKG. H RENOVATION OF THE VALLEY STREET STUDENT CENTER FOR DENTAL HYGIENE ADDENDUM #1 PART 1 - GENERAL Project: Open-End Agreement

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 FACILITIES, DESIGN AND CONSTRUCTION ADDENDUM NO. 1 PROJECT: OWNER: Shell and Core Improvements-1235 Mission Scope 2: Roof 2 DATE: December 29, 2017 1235 Mission Street San Francisco, California SFUSD Project

More information

Maintaining Materials Within the District

Maintaining Materials Within the District Maintaining Materials Within the District The prevalent styles found within the district utilize various common building materials of the Tampa Bay area. Wood siding and brick flourish as the dominant

More information

ADDENDUM NUMBER 1: Portsmouth City Boiler Plant Improvements Project Bid Proposal # Issued: May 23, 2011

ADDENDUM NUMBER 1: Portsmouth City Boiler Plant Improvements Project Bid Proposal # Issued: May 23, 2011 ADDENDUM NUMBER 1: Portsmouth City Boiler Plant Improvements Project Bid Proposal #43-11 Issued: May 23, 2011 This Addendum forms part of the original document marked: Portsmouth City Hall Boiler Plant

More information

ROME ART AND COMMUNITY CENTER

ROME ART AND COMMUNITY CENTER ROME ART AND COMMUNITY CENTER 308 W. Bloomfield St. Rome, NY 13440 INSULATION AND SLATE ROOFING REPAIRS SCOPE OF WORK: A. SPRAY FOAM INSULATE ATTIC AREA B. FRONT ROOF REPAIR C. REAR ROOF REPAIRS D. INTERIOR

More information

Introduction Observations

Introduction Observations Architecture Roof Consulting Construction Technology AA C000932 601 North Fern Creek Avenue Suite 100 Orlando, Florida 32803-4899 (407) 896-7875 FAX (407) 898-6043 October 12, 2013 Mr. David Martin, Project

More information

ADDENDUM NO. 2 Consisting of 3 pages and Attachments

ADDENDUM NO. 2 Consisting of 3 pages and Attachments 10404-125 Street, Edmonton, AB. T5N 1T2 Tel: 780.455.5975 Fax: 780.454.2397 info@cdyarchitect.com ADDENDUM NO. 2 Consisting of 3 pages and Attachments PROJECT: Maina Centre Ville Phase II, Beaumont, Alberta

More information

Distances are not shown to scale. Existing porch. Community. Building. Distances are not shown to scale

Distances are not shown to scale. Existing porch. Community. Building. Distances are not shown to scale patio and deck 00 Building Two story Four-plex Entrance 0 0 00 Building Single Story Duplex 0 patio Contact Information: Owner: Housing Authority of Yamhill County, NE Dunn Place, McMinnville, OR 9. Contact:

More information

ADDENDUM NO. 1 February 6, Bidders are hereby informed that the construction plans and/or specifications are modified as follows:

ADDENDUM NO. 1 February 6, Bidders are hereby informed that the construction plans and/or specifications are modified as follows: ADDENDUM NO. 1 February 6, 2013 TO: PLANS and SPECIFICATIONS for BUILDING IMPROVEMENTS MARCELINE NUTRITION CENTER 229 WEST HAUSER STREET MARCELINE, MISSOURI The Architects Alliance, Inc. 631 West Main

More information

Request for Proposal. February 6, 2017

Request for Proposal. February 6, 2017 Request for Proposal Holy Redeemer Medical Office Building 1648-1650 Huntingdon Pike Huntingdon Valley, PA 19046 MANDATORY CONTRACTOR WALK-THRU: Wednesday, February 8, 2017 at 8:30 AM BIDS DUE: Monday,

More information

SECTION ADDENDA

SECTION ADDENDA SECTION 00 91 03 ADDENDA ADDENDUM NO. 2 June 14, 2017 RE: Cana Island Light Station Phase 2 Baileys Harbor, WI RA 1372.A FROM: TO: River Architects, Inc. 740 7 th Street North La Crosse, Wisconsin 54601

More information

1.1 This Section includes surface preparation and the application of base coats, intermediate and topcoats.

1.1 This Section includes surface preparation and the application of base coats, intermediate and topcoats. PAINTING GENERAL INFORMATION 1.1 This Section includes surface preparation and the application of base coats, intermediate and topcoats. DESIGN REQUIREMENTS 2.1 Material Compatibility: a. Provide materials

More information

Town of York, Maine Request for Qualifications

Town of York, Maine Request for Qualifications Town of York, Maine Request for Qualifications Historic Restoration Contractor The Town of York is accepting Statement of Qualifications from General contractors experienced in historic restoration, for

More information

Addendum No. 2 May 13, 2017

Addendum No. 2 May 13, 2017 Addendum No. 2 May 13, 2017 Project: St. Joseph s Health Center Chamberlain, South Dakota Project No. 2617 Architect: Architecture Incorporated Opening: Thursday, May 19, 2016 2:00 p.m. CT Barger Room,

More information

ADDENDUM #1. A non-mandatory site visit has been scheduled for Thursday, January 5, 2017 at 1:30 p.m.

ADDENDUM #1. A non-mandatory site visit has been scheduled for Thursday, January 5, 2017 at 1:30 p.m. Steven V. Stenger County Executive Pamela J. Reitz, CPFO Director of Administration Rick Schaeffer Director of Procurement December 27, 2016 ADDENDUM #1 To: From: Subject: All Potential Proposers St. Louis

More information

ZONE 7 WATER AGENCY CWS 5 TURNOUT REPLACEMENT PROJECT # ADDENDUM NO. 3 April 02, 2019

ZONE 7 WATER AGENCY CWS 5 TURNOUT REPLACEMENT PROJECT # ADDENDUM NO. 3 April 02, 2019 ZONE 7 WATER AGENCY CWS 5 TURNOUT REPLACEMENT PROJECT # 275-18 ADDENDUM NO. 3 April 02, 2019 This Addendum No. 3 ( Addendum ) is dated the date set forth above and modifies certain Bidding Documents issued

More information

Margaret Greene Park Washroom Building 80 Westwood Road, Guelph, Ontario. Structural and Maintenance Remedial Work

Margaret Greene Park Washroom Building 80 Westwood Road, Guelph, Ontario. Structural and Maintenance Remedial Work SCOPE OF WORK Margaret Greene Park Washroom Building 80 Westwood Road, Guelph, Ontario Structural and Maintenance Remedial Work Prepared For City of Guelph City Hall, 1 Carden Street, Guelph, ON N1H 3A1

More information

Specifications for FL-100 Soffit Panel

Specifications for FL-100 Soffit Panel Union Corrugating Company Specifications for FL-100 Soffit Panel SECTION 07410 METAL SOFFIT PANELS PART 1 GENERAL 1.1 DESCRIPTON A. Section Includes: 1. Preformed metal soffit panel system 2. Associated

More information

RESPONSES TO QUESTIONS and/or RFI s Date: 26 January 2017

RESPONSES TO QUESTIONS and/or RFI s Date: 26 January 2017 MPA Project No. M574-C1 Project Title: Black Falcon Cruise Terminal Façade Repairs and Coating Location: Black Falcon Cruise Terminal, South Boston, MA RESPONSES TO QUESTIONS and/or RFI s Date: 26 January

More information

DL-200. Specifications

DL-200. Specifications DL-200 Specifications Everlast Metals 10 Enterprise Court Lebanon, PA 17042 Phone: (717) 270-6554 Fax: (717) 270-6569 www.everlastmetals.com 7410 Structural Preformed Metal Roofing PART 1: GENERAL 1.01

More information

ADDENDUM NO. 1 January 13, 2012

ADDENDUM NO. 1 January 13, 2012 ADDENDUM NO. 1 January 13, 2012 TO: PLANS and SPECIFICATIONS for REPAIRS AND REPLACEMENTS MARTIN LUTHER KING HALL LINCOLN UNIVERSITY 812 EAST DUNKLIN STREET JEFFERSON CITY, MISSOURI The Architects Alliance,

More information

The Housing Authority of the County of Marin ( MHA ) 4020 Civic Center Drive. San Rafael, CA Addendum #1. Released October 3, 2016

The Housing Authority of the County of Marin ( MHA ) 4020 Civic Center Drive. San Rafael, CA Addendum #1. Released October 3, 2016 The Housing Authority of the County of Marin ( MHA ) 4020 Civic Center Drive San Rafael, CA 94903 Addendum #1 Released October 3, 2016 Addendum #1 to IFB MHA-010-2016 Re-Roofing, HVAC Unit Replacements

More information

TABLE OF CONTENTS Structural Library

TABLE OF CONTENTS Structural Library Title Description DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 Project Title Page Project Manual title page. 000107 Seals Page For seals of design professionals on Project Manual. 000115

More information

COUNTY OF SAN JOAQUIN

COUNTY OF SAN JOAQUIN June 4, 2012 COUNTY OF SAN JOAQUIN General Services Department 44 North San Joaquin Street, Suite 590 Stockton, California 95202-2778 (209) 468-3357, Fax (209) 468-2186 GABRIEL E. KARAM Director Capital

More information

ADDENDUM #3. GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4

ADDENDUM #3. GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4 ADDENDUM #3 GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4 Please address inquiries to: Aaron R. Nickerson GRW, Inc. anickerson@grwinc.com TO ALL PROSPECTIVE BIDDERS:

More information

SECTION ALTERATION PROJECT PROCEDURES

SECTION ALTERATION PROJECT PROCEDURES SECTION 013516 ALTERATION PROJECT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for protection of existing facilities during construction operations. 2. Demolition and removals

More information

PURCHASING DEPARTMENT

PURCHASING DEPARTMENT PURCHASING DEPARTMENT The bid listed below has had addenda issued. Documents are available over the Internet at http://www.norwalkct.org Adobe Acrobat reader is required to view this document. If you do

More information

AMENDMENT TO SPECIFICATIONS

AMENDMENT TO SPECIFICATIONS AMENDMENT TO SPECIFICATIONS SECTION 01 10 00, Paragraph 1.01: Revise subparagraphs A, B, and C as follows: A. BASE WORK 1) Temporarily remove and store items mounted on the building exterior for reinstallation

More information

Addendum Number 1. August 31, Colcock Hall Windows. Owner Project Number: Prepared by:

Addendum Number 1. August 31, Colcock Hall Windows. Owner Project Number: Prepared by: Addendum Number 1 Colcock Hall Windows Owner Project Number: 50059 Prepared by: ADC Engineering, Inc. 1226 Yeamans Hall Road Hanahan, South Carolina 29410 To Bidders: This Addendum forms a part of the

More information

Spring Lake Public Schools. Spring Lake, MI. March RE: High School Storage Buildings

Spring Lake Public Schools. Spring Lake, MI. March RE: High School Storage Buildings Spring Lake Public Schools Spring Lake, MI March 2018 RE: High School Storage Buildings Advertisement for bids Bid Proposal Sealed bids for Spring Lake Public Schools-High School Storage Buildings will

More information

ST. GABRIEL OF THE SORROWFUL MOTHER CHURCH

ST. GABRIEL OF THE SORROWFUL MOTHER CHURCH ADDENDUM NO. 1 TO CONTRACT DOCUMENTS DATED FEBRUARY 12, 2015 FOR ADDITION TO ST. GABRIEL OF THE SORROWFUL MOTHER CHURCH Located at 8910 Gap Newport Pike Avondale, PA 19311 ARCHITECT 270 South Main Street,

More information

FYPON, LLC. February 2014

FYPON, LLC. February 2014 Section 06 66 30 EXTERIOR PVC RAILINGS AND GUARDS PART 1 - GENERAL 1.1 RELATED SECTIONS: A. All contract documents apply to work of this section; this includes but is not limited to: Agreement; Drawings;

More information

HERITAGE PERMIT APPLICATION SUBMISSION GUIDELINES

HERITAGE PERMIT APPLICATION SUBMISSION GUIDELINES HERITAGE PERMIT APPLICATION SUBMISSION GUIDELINES WHAT IS A DESIGNATED HERITAGE PROPERTY? A designated heritage property is a property that has been identified as historically or architecturally significant

More information

SEND ALL PROPOSALS DIRECTLY TO THE ADDRESS SHOWN BELOW.

SEND ALL PROPOSALS DIRECTLY TO THE ADDRESS SHOWN BELOW. REQUEST FOR PROPOSALS RFP# 2018-02 TITLE: PAINTING SERVICES ISSUSING AGENCY: TOWN OF WALLACE 316 East Murray Street Wallace, North Carolina 28466 ISSUE DATE: January 11, 2019 IMPORTANT NOTE: Indicate firm

More information

MMI PREPARATORY SCHOOL LIBRARY FREELAND, PA BID CLARIFICATION NO. 3 JULY 19, 2011

MMI PREPARATORY SCHOOL LIBRARY FREELAND, PA BID CLARIFICATION NO. 3 JULY 19, 2011 MMI PREPARATORY SCHOOL LIBRARY FREELAND, PA BID CLARIFICATION NO. 3 JULY 19, 2011 This Bid Clarification forms a part of the Contract Documents and modifies the original bidding documents. Please acknowledge

More information

Project Name: Window and Roofing Replacement at Blanton-Nason-Brewer (BNB) Hall.

Project Name: Window and Roofing Replacement at Blanton-Nason-Brewer (BNB) Hall. DOCUMENT 0091101 ADDENDUM NO. 1 1 PROJECT INFORMATION Project Name: Window and Roofing Replacement at Blanton-Nason-Brewer (BNB) Hall. Project Location: Truman State University Campus. Owner: Truman State

More information

SECTION METAL ROOF AND SOFFIT PANELS

SECTION METAL ROOF AND SOFFIT PANELS Metal Panel Systems, Inc. 11506 Reading Road Cincinnati, Ohio 45241-2512 Telephone: 800-554-6126 or 513-554-6120 Fax: 513-554-6121 www.metalpanelsystems.com info@metalpanelsystems.com Specifications for

More information

MPA Project No. LP1703-C1 Project Title: Tanks Coating Upgrade Location: Logan International Airport

MPA Project No. LP1703-C1 Project Title: Tanks Coating Upgrade Location: Logan International Airport MPA Project No. LP1703-C1 Project Title: Tanks Coating Upgrade Location: Logan International Airport RESPONSES TO QUESTIONS and/or RFI s Date: June 16, 2016 The attention of Contractors submitting General

More information

SECTION SELF-ADHERED WATER-RESISTIVE ROOF UNDERLAYMENT

SECTION SELF-ADHERED WATER-RESISTIVE ROOF UNDERLAYMENT SECTION 07 30 05.01 SELF-ADHERED WATER-RESISTIVE ROOF UNDERLAYMENT SPEC WRITERS NOTE: This specification includes materials and installation procedures for SlopeShield SA Self-Adhered Water-Resistive Vapor

More information

ARCHITECTURE, PLANNING AND HISTORIC PRESERVATION, INC. ADDENDUM NO. 1. September 9, to the BIDDING DOCUMENTS for

ARCHITECTURE, PLANNING AND HISTORIC PRESERVATION, INC. ADDENDUM NO. 1. September 9, to the BIDDING DOCUMENTS for AUSTIN ARCHITEXAS DALLAS ARCHITECTURE, PLANNING AND HISTORIC PRESERVATION, INC. ADDENDUM NO. 1 September 9, 2014 to the BIDDING DOCUMENTS for ELLIS COUNTY COMPLEX Records Storage Building Waxahachie, Texas