1 Annex III - Bill of Quantity PREAMBLE TO BILL OF QUANTITIES BILL OF QUANTITIES DAY WORKS RATES

2 Table of Contents PREAMBLE TO BILL OF QUANTITIES TABLE OF CONTENTS Page Nr. PREAMBLE TO BILLS OF QUANTITIES SECTION 1 - GENERAL Complementary Documents Method of Measurement Units and Extension of Bill of Quantities Extent of Works Additional Work 3 SECTION 2 RATES AND PRICES Rates and Sums Taxes and Duties Provisional Sum Provisional Quantity Provisional Item Lump Sum Item Payment of Items in a Monthly Basis Mobilization Protection of Completed Work and Clearing upon Completion Rate Analysis 5 SECTION 3 - PIPEWORKS General Pipe Laying Pipe Specials and Fittings Yard Piping and Connections in Structures Section Valves Washout Valves Air Valves Bulk Water Meters Fire Hydrants Valve Chambers, Manhole Cover and Surface Boxes Pipe Bedding Concrete Encasement to Pipes Hydraulic Pressure and Leakage Tests, Disinfection and Cleaning Connections to Existing Pipe work 8 SECTION 6 MISCELLANEOUS WORKS Access Facilities Existing Services and Structures Painting & Protective Coatings Steel Flooring Amendments to Designs Marker Posts As Built Drawings 9 UNOPS SDOC TOC-A-1

3 PREAMBLE TO BILLS OF QUANTITIES SECTION 1 - GENERAL 1.1 Complementary Documents The attention of the bidder is explicitly directed to the Conditions of Contract, Technical Specifications, Scope and Description of Works and Tender Drawings that are to be read in conjunction with the Bills of Quantities and its Preamble. The bidder shall specify the currency of his bid in each page of BOQ in the cell marked as currency. The Bidder shall neither insert additional items in to the Bill of Quantities nor made any alterations to the item descriptions and quantities described in it. The modification of BOQ, in any form by the bidder, will result in immediate rejection of the bid. 1.2 Method of Measurement The Works as executed shall be measured for payment in accordance with the method adopted in the Bills of Quantities and under the item as therein set forth. The contractor s rate shall include for the complete execution of the works as depicted in the drawings and as specified in Technical Specifications. The net measurement or weight of the finished work in place shall always be taken and except where otherwise stated or where separate items are provided. No allowance shall be made for cutting, waste, laps, circular work, etc. and no deductions shall be made for grout nicks, joggle holes, rounded arises or for linkages for fitting ironwork and the like. Payment shall be effected only for those materials that are incorporated in the Permanent Works and taken over the stocks as stipulated in the specifications to the approval of the Engineer. Any surplus materials delivered to the site shall become the property of the Contractor unless otherwise directed by the Engineer and the Contractor shall reimburse any money that was paid by the Employer on account of such materials. Unless specific items have been provided for in the Bill of Quantities, no separate measurement shall be made in respect of items whether specified or not requiring mortar/sealant, assembling, building-in or fixing to concrete, block works, metal work or timber, painting and protective treatment, welding, drilling, bolting inclusive of bolts, nuts and washers, screws, nails and plugs, jointing and joint materials, box out and filling thereof, grouting, packing, bedding, insulation between different metals, making good, conduits and fittings, cutting, waste, labour materials and all incidental work to the items concerned and their surroundings. 1.3 Units and Extension of Bill of Quantities All sizes and quantities provided in the Bill of Quantities have been in metric units, figures involving decimals including sums of money are written in the British tradition, namely with a full stop in the decimal position and commas between each successive group of three digits to the left of the decimal position. 1.4 Extent of Works UNOPS SDOC An III-1

4 Notwithstanding any limits that may be implied by the wording of the individual items and /or explanation provided in this preamble, it is to be clearly understood by the contractor that the rates and sums that are entered in the Bills of Quantities shall be for the work finished complete in every respect. The bidder shall be deemed to have taken full account of all requirements and obligations whether expressed or implied, covered by all parts of this Contract and to have priced the items herein accordingly. The rates and sum shall therefore be included for all incidental and contingent expenses and risks of every kind necessary to construct, complete and maintain the whole of works in accordance with the Contract. Full allowance shall be made in the rates and/or sums inter-alias that are referred to and/or specified herein. Site investigations that may be necessary for proper and complete execution All setting out and survey works Provision of project insurance certificates Provision of contractual bonds and guarantees Provision of temporary services such as water supply, electricity, fencing, watching, lighting; etc. Paying fees and giving notice to authorities, public etc. Payment of all patent rights and royalties Reinstatement of the site on completion of works to the satisfaction of the Engineer Safety precautions and all measures to prevent and suppress fire and other hazards during implementation Material testing and quality control test reports Interference to the works by persons, vehicles, vessels and the like using the existing land and water facilities Maintenance of traffic flows and access to the existing roads in a motor-able status and waterways during the period of construction Works in connection with the protection and safety of adjacent structures Supplying, maintaining and removing on completion contractor s own temporary installations such as accommodation, offices, stores, workshops, transport, welfare services and all charge in connection therewith unless otherwise directed by the Engineer Working in dry conditions including dewatering if required except where otherwise permitted by the specification Maintaining public roads and footpaths, and maintaining access upon existing roads or recognized routes Supply, inspection, sampling and testing of materials and of the Works under construction including the provision and use of equipment. Except where separate items are provided for bringing plant to the site and removing on completion, for providing transporting to site, setting to work operating (including all fuel and consumable stores), maintaining and removing from the site upon completion all construction plant and equipment necessary for the execution of the work including the cost of all tests and other requirements in respect to such plant and equipment Recruitment, bringing to and repatriate from the site, accommodating and feeding and all other incidental costs and expenses involved in the provision of all necessary skilled and unskilled labour and supervision Supporting faces of excavation temporary or permanent shoring, shuttering and scaffolding etc. Cost of design based on tender drawings, preparation of working drawings and related data for materials, pipe work and equipment All ancillary parts, minor fittings, bolts, nuts, gaskets, washers, fixing, etc., joining materials, protective coatings and sleevings and other relevant items not specifically listed but necessary for proper installation of the materials, pipe works and equipment (applicable to materials supplied by the contractor) UNOPS SDOC AN- III -2

5 Costs of packing, protection, storage, insurance and related documentation for shipment to Sudan for materials, pipes, fittings, equipment, etc. Cost of unloading at port, road transport to site, offloading, stacking and storage in suitable sheds, double handling as needed at site for materials, pipes, fittings, equipment, etc. No claim shall be considered for further payment in respect of any work or method of execution, which may be described in the Contract or is inherent in the construction of the work and detailed in the drawings on account of: items that have been omitted from the Bill of Quantities, but depicted on the drawings any omission from the wording of the items or from a clause in the Preamble or no mention of such work or method of execution having been in the Preamble Items against which no rates or sum is entered by the contractor whether quantities are stated or not shall not be paid for when executed, but will be regarded as covered by other rates in the Bill of Quantities. The quantities set out in the Bill of Quantities are the estimated quantities of the work and they shall not be taken as the actual and correct magnitude of the works to be executed by the contractor in fulfillment of his obligation under the Contract. The contractor shall be deemed to have taken into account all of the following in his tender prices and his construction programme. all recognized holidays, festivals, religious and other local customs any stoppage of work or delays due to adverse weather conditions 1.5 Additional Work The relevant Clauses of this Preamble shall deem to apply equally to any work subsequently ordered for execution by the Contractor either under Provisional Sum or Variation Orders, except where specifically varied therein. UNOPS SDOC AN- III -3

6 SECTION 2 RATES AND PRICES 2.1 Rates and Sums The rates and sums entered by the contractor against all items in the Bill of Quantities shall bear a proper relationship to the cost of carrying out the work described in the Contract. All on costs and similar charges that are applicable to the Contract as a whole shall be spread over all items in the Bill of Quantities whilst those that are applicable only to particular sections of the Contract shall only to be spread over the relevant items in that particular section. 2.2 Taxes and Duties As per the section I, Bid Particulars of the invitation to Bid. The bidder shall submit a comprehensive material list containing the items to be imported from overseas with full details such as quantity, cost, country of origin, source, etc. with his tender. 2.4 Provisional Sum Provisional sum items in general shall be dealt with as provided for in the Conditions of Contract. Provisional Sums are represented by the words Provisional Sum (PS) entered under the description. The Works identified as provisional sums shall be carried out by the contractor only with a written instruction from the Engineer. The contractor shall be entitled for an amount of 15% of the actual cost of services provided to cover all his financial and administrative charges including cost of liaison with external agencies, profits, overheads and any other costs for performing the work under Provisional Sum item. This percentage will be the basis of assessing the actual amount payable to the contractor. This additional amount of 15% shall not be paid to the Contractor in the event when no work is performed under a particular provisional sum item or carried out by others without any significant input from the Contractor. 2.5 Provisional Quantity Certain items in the Bill of Quantities are designated as Provisional Quantity in the description column to indicate that the quantities for the work covered by such items are the best possible estimates that can be made in advance of the execution of the work or that the provision of such facilities as are described in the items may not in the event be required under the contract. All items so designated shall be used only at the direction and discretion of the Engineer and in the event of not utilizing either wholly or in part shall as to the amount not used, be deducted from the Contract Price. 2.6 Provisional Item Any item that is designated as Provisional Item in the description column of the Bill of Quantity is to indicate that the provision of such facilities of work is uncertain at the time of document preparation. All items so designated shall be used only at the direction and discretion of the Engineer. The unit rate if any quoted by the contractor shall be applicable for the amount of work executed under such items. 2.7 Lump Sum Item UNOPS SDOC AN- III -4

7 Certain items in the Bill of Quantities are designated as Lump Sum (LS) in the unit column to indicate that the payment will be effected as a sum on satisfactory completion of that particular work. Lump sum items stipulated in Bill of Quantities that are related to a specific work shall be paid on the basis of the proportion of actual work done to the total work of that specific item as assessed by the Engineer. Items with quantities and units shall be paid against number of units used and/or incorporated in the works. 2.8 Payment of Items in a Monthly Basis Payment under items that are measured on a monthly basis shall not be commenced until the full facilities described in the items and the specifications have been provided to the satisfaction of the Engineer. Payment shall continue until such time that the Engineer signifies that such facilities are no longer required. 2.9 Mobilization The mobilization to site, including provision of contractor s temporary arrangements and demobilization on completion shall be certified to the contractor at described in the instruction to bidders. In no case, shall the amount entered against the Mobilization exceed 10% of Permanent Works of the Contract Protection of Completed Work and Clearing upon Completion The Contractor shall allow in his rates for protecting completed work from subsequent operations, making good of all damage to completed work, clearing away all rubbish as it accumulates and leaving the site in a tidy condition to the satisfaction of the Engineer Rate Analysis The contractor on demand by the Engineer shall provide a detailed breakdown of tendered rates and lump sum items for all or part of the Bill of Quantity items within 48 hours of being so requested. The detailed breakdown of rates shall include the actual calculations of the labour, materials, plant/equipment costs for works, the build up of measured rates with profit, overheads and other allowances used to arrive at the tender price. SECTION 3 - PIPEWORKS UNOPS SDOC AN- III -5

8 3.1 General The items provided in the Bill of Quantities for earth works, pipe laying and installation shall cover all necessary works including digging and reinstatement of trial pits required or as directed by the Engineer together with obtaining permission from the relevant Road Authorities for the making of the trial holes, excavation of trench, rock blasting, importation of materials and to install or lay and test the completed pipeline without limitation including storing, transporting, handling, site clearance, dewatering, bedding, laying, cutting, jointing, incorporation of all required pipe specials and fittings, connections to existing mains, painting where specified, backfilling, compacting and testing thereof, protection, security, removal and proper disposal of unsuitable and surplus excavated material all as specified, temporary, permanent and all other things necessary for pipeline installation not measured separately under other items in the Bill of Quantities. 3.2 Pipe Laying The Quantities for laying of pipes shall be measured by effective length of pipeline along its centerline without deducting for valves, specials and fittings. The measurement shall be carried out separately according to type, diameter and given depth ranges. The laying length of each depth range shall be paid separately as provided in the BOQ (depth means ground level to invert level of pipes). Where in Bill of Quantities, items described as plain-ended pipe piece, the pipe piece end shall be spigot type for joining with socket end pipes or specials. Excavation in rock in all cases shall be measured as extra over to excavation in normal materials by volume from the level at which rock is encountered. The volume of rock measured for trench excavation shall be to the maximum bottom width of trench permitted under the Specification or actual width, whichever is less and to the depth of bedding bottom level or as authorized by the Engineer. An isolated localized quantity of rock or other hard materials such as concrete encountered within the excavation of normal materials shall not be measured separately for payment unless its volume exceeds 1 cum except where the minimum volume shall be limited to 0.25 cum when the extent of net width of excavation is less than 2.5m. The excavation in all other materials shall not be measured separately but shall be deemed to be included in the unit rates of other relevant items, except where specific items are provided in the bill of quantities. 3.3 Pipe Specials and Fittings Laying of Pipe Specials and Fittings shall be measured as the number of each item installed in accordance with the Drawings and the Engineer's instructions but separately according to type and diameter. The installation rates for fittings and specials shall be extra over to the laying of pipes and shall include all connected works but in any way not limited to installation alone. Separate item has been provided in the Bill of Quantity for concrete thrust block and anchor blocks as depicted on drawings and for pressure testing. But no separate item is provided for projection of joint and for protection of berried GI parts of pipe work and cost for such work shall be included in the unit rates. 3.4 Yard Piping and Connections in Structures All HDPE pipes works specials and fittings shall be measured as same as the transmission main together with them. Supply and installation of GI pipe works shall be paid under relevant items in the BOQ. Only for the connection between HDPE pipeline and the existing sedimentation tanks pipe shall be measured UNOPS SDOC AN- III -6

9 in metres including bends and number of flanges shall be counted separately include but not limiting for gaskets and other jointing materials, protection paste and tapes. 3.5 Section Valves Rates and prices for the installation of section valves shall be measured as the number of each item installed in accordance with the drawing and shall include for extended spindles,, key heads. Surface box assembly with the protection pipe as depicted in drawings shall be paid separately. 3.6 Washout Valves Rates and prices for installation of washouts shall include for extended spindles, key heads, etc. as required, and discharge PE pipes (average length not exceeding 6.0m) within the limit of installation as shown on the drawing including the overflow chamber, head wall, drain as relevant. If the average length of pipes within the limit of installation measured along the centerline of pipe exceeds 6.0 m, the extra length of pipe shall be measured separately. The installation of suitable invert level Tee on the main pipeline shall be paid separately. 3.7 Air Valves Rates and prices for installation of air relief valve beyond Tee on the main pipeline shall include installation of isolation valves (sluice valve, GI flange spigot pipe, flange adapter and GI support with concrete base. The rate shall include supply of GI flange spigot pipe, GI support, and GR20 concrete for the base. A separate item has been provided in the BOQ for the installation of Tee or clamping saddle on the main pipeline as appropriate in the Bill of Quantity. 3.8 Bulk Water Meters Rates and prices for installation shall include for all associated fittings and support blocks as shown in drawings. The cost of supply of GI double flange pipes shall also included to the rate. 3.9 Fire Hydrants Rates and prices for installation shall include for all the fittings, beyond the Tee of the main pipeline, valves, surface boxes, chambers within the limit of installation and pipes (length not exceeding 5.0m measured along the centerline). If the length of pipes within the limit of installation measured along the centerline exceeds 5.0 m, the extra length of pipe shall be measured separately Valve Chambers, Manhole Cover and Surface Boxes Provision of valve chambers with manhole covers and surface boxes shall be measured separately under relevant items incorporated in the bill of quantities. Thus, the rate shall include for all Contractor's obligations necessary to complete the chambers in accordance with the Drawings including, but not limited to excavation, concreting, Blockwork, associated pipe work manhole covers, drain pipes etc Pipe Bedding UNOPS SDOC AN- III -7

10 The special bedding types shall be measured in length of pipe trench but separately according to diameter of pipe as depicted in the drawing. The Type A bedding is depicted in the standard drawing is for normal pipe laying where the Contractor is required to scarify the bottom of pipe trench to a depth of 100mm below designed level to loosen the naturally occurring material to provide soft bedding for the pipes. Loosing of last 100mm of material for normal pipe laying as indicated in the drawings shall not be paid separately. The excavation rates shall include for the removal of unsuitable materials from trench bottom and disposal of such materials off the site. The rates shall also include for backfilling with clean river sand from the specified bedding up to 300 mm from the crown of the pipe. Separate items have been provided for supply and placing of granular material as specified in drawing and geo-textile where relevant including preparation of bedding as required. The Contractor shall lay the geo-textile material along the two vertical sides, the bottom and the top of the trench in one piece as shown in the drawings. However, overlaps of 500 mm shall be allowed at joints but not measured separately for payment Concrete Encasement to Pipes Grade 20 concrete encasements to pipes shall be measured in effective length or in cubic metre as provided in the bill of quantity Hydraulic Pressure and Leakage Tests, Disinfection and Cleaning Rates for pressure and leakage test and disinfection and cleaning shall cover costs of all materials including water, labour, tools and equipment, and incidentals necessary to complete the required work, disconnecting and reconnecting any pipes and specials together with any excavation and backfilling involved. The measurement shall be by length according to the type and diameter of the pipe and shall be along the centre of the pipeline including all the bends, valves, fittings and appurtenances. The amount payable to the Contractor for these items shall only become due when the Engineer approves the successful test results Connections to Existing Pipe work Rates and prices for connecting to or capping off existing pipe work shall include but not by way of limitation for: all work as defined in the relevant Clauses of this preamble coordinating the work with the relevant authority as specified any work necessary outside normal working hours or days ascertaining the precise outside diameters of existing pipes arranging for the location, isolating and drainage of the existing main re-commissioning including testing and disinfection UNOPS SDOC AN- III -8

11 SECTION 6 MISCELLANEOUS WORKS 6.1 Access Facilities The Contractor shall provide adequate access facilities to various sites within the project area to facilitate construction activities at no extra cost to the Employer. These new facilities provided by the Contractor shall be extended to other contractors executing works for the project or other agencies free of charge. 6.2 Existing Services and Structures The Contractor's attention is specifically drawn to connections to and protecting of existing services and installations. The Contractor shall be deemed to have included in his tender rates and prices adequate provision to comply with all such requirements. 6.3 Painting & Protective Coatings The rate for painting and protective coatings whether measured separately or included in other items are to include for all temporary staging ladders and the like, covering the adjacent works to prevent splashing providing adequate protection to the work being painted or coated against dust, spray and other foreign matter, for all preparation and priming, carrying out the work in materials and colours to the requirements of the Engineer, curling in edges, washing off stains, and leaving the whole of the work perfect on completion. The rates for painting are to allow the applying of the final coat of paint immediately prior to handing over any section of the work. 6.4 Steel Flooring Rates and prices for open steel flooring, steel checker plate flooring and steel chamber covers shall include for all curbing, all necessary steel support members and all trimmed cutouts for valves, keys, pipe work, etc. together with the forming of all rebates in concrete, the grouting in and fixing of curbing to same and painting. 6.5 Amendments to Designs Where amendments are required to the civil designs due to prevailing ground conditions, the amended designs shall be produced by the Contractor and approved by the Engineer. No extra payment shall be made for design work to the Contractor. 6.6 Marker Posts Marker posts shall be provided for all valves such as section valves, washout valves, air vales and fire hydrants. Rate for installation of all such valves shall include the supply and erection of marker posts provided no separate item incorporated in the Bill of Quantities for such work. 6.7 As Built Drawings Rate shall include the provision of originals and copies of approved As Built drawings as specified in Clause of Section I of the Technical Specifications.Payment under item for As Built Drawings in the BOQ shall be made as follows: 25% of BOQ item on submission of acceptable draft As Built Drawings 75% of BOQ item on submission of approved As Built Drawing UNOPS SDOC AN- III -9

12 ITB Ref. 2011/UWS-76613/ITB-006/WORKS/SDOC-086- Supply of material & construction of water transmission pipeline from Konduwa borehole field to Majok Tank PLEASE INDICATE THE CURRENCY OF THE QUOTATION Item No. Cost Item Description Unit Quantity Unit Rate 1.0 Mobilization & Demobilization 1.1 Mobilization of Contractor's resources to the work site sum Demobilization of Contractor's resources at the end of substantial sum 1 completion of the works Currency ( _) 1-ST Subtotal of Mobilization & Demobilization (sum of items 1.1 & 1.2) 2 Supply of material 2.1 Supply of HDPE materials-all Polyethylene material shall be PE 100,PN 6 SDR 26 ( unless otherwise stated ) suitable for butt fusion jointing and the rate shall include for supply and delivery to the work site of all pipes, fittings & specials including all other associated accessories such as gaskets, backing rings (to suite PN 16 flange), bolts and nuts, etc. required for complete installation. Amount Currency ( _) HDPE Pipes OD 250,PN 10,SDR 26 pipes m OD 110,PN 6 SDR 26 pipes m 480 HDPE Stub flanges OD 250 stub flange complete with DN 250 backing ring, nuts and bolts OD 110 stub flange complete with DN 100 backing ring, nuts and bolts HDPE Bends OD 110 mm,45,with two stub flanges in either ends complete with DN 100 backing rings, nuts and bolts for wash outs Nr 2 Nr 5 Nr 1 HDPE Tees equal tee Nr x110 tee with a stub flange branch complete with DN 100 backing ring, nuts and bolts for washout. Nr 1 HDPE Reducers x110 Nr Supply of DI materials- Supply and delivery at site all DI pipes, fittings, specials & valves including rubber rings, lubricant, gaskets, bolts and nuts, denso or equivalent primer, paste, protection tape and all other associated material required for complete installation. Double flange Valves DN 250 sluice valve Nr DN 100 sluice valve for washouts Nr 1 Flange Adapters DN 250 Nr 1 UNOPS SDOC AN- III -10

13 2.2.4 DN 100 for wash out valve installation Nr 1 Couplings Axially restrained coupling for OD 250 PE (provisional quantity) Nr 2 Lockable Surface boxes x 150 for valve installation Nr 2 2-ST 3 Construction & Installations 3.1 Earth Works & Pipe Laying - Earth work rate shall include for back filling, shoring, compaction as per the specifications and disposal of surplus excavated material elsewhere as directed by the Engineer. Pipe laying rate shall include for local transportation within the site, handling, welding, and all other associated works required for complete installation. Sub total of Supply of material Excavation for pipe trenches in any material other than rock with a depth not exceeding 1.5m. m Ditto, for depth of excavation between 1.5m and 2.5m m Ditto, for depth of excavation exceeding 2.5m m Extra over for item Nrs and for excavation in rock (Provisional Quantity) Selected material for back filling & compaction of pipe trench as directed by the Engineer (Provisional Quantity) Laying and Jointing or Fixing in Open Trench HDPE pipes (OD 250mm) with Butt Fusion Welded Joints - in all depth with Type "A" bedding as depicted in drawings. m 3 15 m m Ditto, for Type" B"bedding (Provisional Quantity). m Ditto, for Type" C"bedding (Provisional Quantity). m Ditto, for Type" D"bedding (Provisional Quantity). m Laying and Jointing or Fixing above ground HDPE pipes (OD 250mm) with Butt Fusion Welded Joints through culverts and protective GI pipes Extra over to item supply and installation of light duty GI protective pipes and straps as shown in drawings. m 78 m Laying and Jointing or Fixing in Open Trench HDPE pipes (OD m mm) with Butt Fusion Welded Joints - in all depth with Type "A" bedding as depicted in drawings Ditto, for Type" B"bedding (Provisional Quantity). m Ditto, for Type" C"bedding (Provisional Quantity). m Ditto, for Type" D"bedding (Provisional Quantity). m Installation of HDPE Fittings, The rate shall include for additional excavation, shoring, dewatering, etc. necessary for the complete installation Installation of OD 250 stub flange complete with DN 250 backing ring, nuts and bolts in main line Installation of OD 110 stub flange complete with DN 100 backing ring, nuts and bolts in branch line in WTP yard Nr 2 Nr 5 UNOPS SDOC AN- III -11

14 3.2.3 Installation of OD 250 equal tee complete main PE pipe line within the yard Installation of OD 250 x 110 stub flanged branch PE tee complete with joint rings, gaskets, washers, bolts and nuts, etc. for washout branch from main PE pipe as depicted in drawings or directed by the Engineer. Nr 1 Nr Installation of OD 250 x 110 reducer in main PE pipe line Nr Installation of Valves including supply and installation of GI pipe works Installation of 250 mm dia control Sluice Valve on the branch line line as depicted in drawings or directed by the Engineer. Nr Installation of 80 mm dia double flanged sluice valve for wash out complete with PE 45 0 Bend with flanges,di Flange Adaptor, OD 90 mm HDPE Plain pipes upto the wash out chamber as depicted in the drawing. (Total length not to exceed 6m.) Nr Supply and installation of 250mm GI pipe work (pipes and bends) within the Majok reservoir yard including making connection to the HDPE OD 250 pipes as depicted in drawings or directed by the Engineer Extra over for item Nr , supply and installation of galvanized DN 250 steel flanges as shown the drawings & specification. m 13 Nr Extra over for item Nr , supply and installation of galvanized steel supports and brackets for the pipe work as depicted in sum 1 drawings Supply and installation of 250mm MS blank flange to the branch end of the pipeline as depicted in drawings Nr Chamber construction and concrete works 3.41 Construction of washout (outlet) chamber as depicted in drawings. Rate shall be included supply and installation of galvanized chequered plate cover with locking arrangement. Nr Installation of 150 surface box with Grade 25 concrete for sluice valves on main or branch lines as depicted in the drawing. Rate shall include for supplying and fixing 150mm heavy duty GI protective pipe and concrete for the valve support. Nr Mass concrete Grade 20 for the construction of thrust and anchor blocks, concrete surround pipes, etc. m Mass concrete (Grade 20) pipe supports for above ground pipe work as shown in the drawings. m Reinforced concrete block at the connection between HDPE and GI with Grade 25 as depicted in drawings. (including supply and erection of reinforcements) m ST Subtotal of Construction & Installations 4 Testing & Commissioning hand-over 4.1 Hydraulic pressure testing of OD 250mm dia. PE pipeline. The rate shall include for supply of water and provision of necessary equipment to complete the hydraulic pressure testing in the presence of Urban Water Corporation representative & the preparation of hydraulic pressure testing report LS 1 UNOPS SDOC AN- III -12

15 4.2 Disinfection of pressure tested & completed pipeline. The rate shall include for labour, materials, supervision, and equipment including pump(s) and power unit, and chemicals, as necessary for disinfecting the pipelines in accordance with the specification. LS provision of originals and copies of approved As Built drawings as specified in Clause of Section I of the Technical Specifications. 4-ST TOTAL COST (sum of Sub totals 1-ST, 2-ST,3-ST & 4-ST) LS Subtotal of Testing & commissioning hand-over 1 SCHEDULE OF DAYWORKS RATE TABLE OF CONTENTS DAYWORK SCHEDULE General Labour Materials Constructional Plant 16 UNOPS SDOC AN- III -13

16 UNICEF Assisted Water Supply Project Thirukkovil WSS Preamble to Bills of Quantities DAYWORK SCHEDULE 1.1 General This Section refers to the provision incorporated in Clause 52.4 of General Conditions of Contract and the work shall not be executed on a work basis except by written order of the Engineer. Contractor shall be entitled to payment in respect of labour, material and plant used for dayworks at the rates given in the schedules of Works presented below. The works rates inserted in this section by the Contractor shall cover all expenses relating to administration, financial cost, overhead and profit, cost of liaison with external agencies and all other costs related to Works. 1.2 Labour The time engaged by the category of labour directly performing work ordered by the Engineer and for which they are competent to perform shall be measured. The time of gangers (charge hands) actually doing the work with the gangs shall also be measured but not the time of foremen or other supervisory personnel. The given rate shall cover all direct costs to the Contractor including the amount of wages paid to such labour, transportation time, overtime, subsistence, allowances, and any sums paid to or on behalf of such labour for social benefits in accordance with the Sudan Law. SCHEDULE OF DAYWORK RATES LABOUR Nr. Trade Description Unit Rate (Currency) Ganger Unskilled Labourer Operator for Crawler Mounted Machine Operator for Wheel Mounted Machine Operator for Pneumatic tools Driver for Trucks / Bowser / Tractor/ Lorry / Trailer etc. Mechanic Electrician Painter Welder Bar Bender/Reinforcement Worker Mason/Concrete Worker Carpenter/Form Worker Pipe Layer / Fitter / Plumber Light Vehicle Driver Skilled Labour (other categories) UNOPS SDOC AN- III -14

17 Annex III- Bill of Quantities 1.3 Materials The given rates shall cover the price, freight, insurance, handling, expenses, damage, losses, etc, and shall provide for delivery to store for stock piling at the site; and The cost of any materials supplied by Employer for use on works shall not be taken into account and additional percentage quoted also not applicable. The Contractor must submit his receipts/bills to the Engineer in support of all works materials payment claims. SCHEDULE OF DAYWORK RATES MATERIALS Nr. Material Description Unit Rate (Currency) 1 a) Ready mix concrete up to Gr.20 from Gr. 20 up to Gr. 35 A Cum Cum 2 Cement Ordinary Portland or Equivalent in Bags (50 Kg) Bag 3 Ribbed TOR Steel reinforcing Bar Tonne 4 Fine aggregate for concrete as specified Cum 5 Coarse aggregate for concrete as Specified Cum 6 a) Timber (Class 1) b) Plywood Sheets (½ inch) Cum Sqm 7 Bricks/Masonry Blocks a) Masonry Blocks (400 x 200 x 400) b) Rubble 225 x 150 mm Nr Nr Cum 8 9 Fuel a) Petrol b) Diesel Litre Litre River Sand Cum UNOPS SDOC AN- III - 15

18 Annex III- Bill of Quantities 1.4 Constructional Plant In calculating the payment due to the Contractor for Constructional Plant employed on daywork, only the actual number of working hours will be eligible for payment, except that where applicable and agreed with the Engineer, the travelling time from the part of the Site where the Construction Plant was located when ordered by the Engineer to be employed on daywork and the time for return journey thereto shall be included for payment. The cost of drivers and operators will be paid separately as described under the section on work Labour. The given rate shall cover; due and complete allowances for depreciation, interest, indemnity and insurance, repairs, maintenance, supplies, fuel, lubricants, and other consumables, and all overhead profit and administrative costs related to the use of such equipment; SCHEDULE OF DAYWORK RATES CONSTRUCTIONAL PLANT Nr. Plant Description Minimum Capacity Unit Rate (Currency) 1 a) Excavator - Crawler mounted c) - Ditto Cu.m 0.7 Cu.m 1.2 Cu.m 2 a) Bull-Dozer with Ripper- Crawler Mounted 90 HP 200 HP 3 a) Back-Hoe Excavator - Wheel mounted with bucket width 0.3,0.45 and 0.6 m 70 HP 85 HP 4 a) Front End Loader - Wheel mounted c) - Ditto Cu.m 2.3 Cu.m 3.2 Cu.m 5 Motor Grader - Wheel mounted 90 HP 6 a) Mobile Crane 2 Tonne 5 Tonne 7 a) Concrete pump cart 55 Cu.m/Hr 95 Cu.m/Hr 8 Boom Truck 15 Tonne 9 a) Dump Truck c) - Ditto - 4 Tonne 8 Tonne 11Tonne 10 a) Trailer Truck for Pipe Transport without load 17 Tonne Km Km 11 a) Low bed Trailer with prime mover for Machine / Pipe Transport with load without load 17 Tonne Km Km 12 a) Agitator Car/Concrete Transport Truck 3 Cum. 6 Cum. 13 a) Water Bowser 1000 Lit 4000 Lit UNOPS SDOC AN- III - 16

19 Annex III- Bill of Quantities Nr. Plant Description Minimum Capacity Unit Rate (Currency) 14 Tractor with Trailer 2 Cu.m. 15 a) Lorry / Pickup / Truck b) Lorry 1.5 Tonne 10 Tonne 16 a) Concrete mixer Truck (with self loading Facilities) 1.4 Cum. 3.2 Cum. 17 Plate compactor/vibrator 2 Tonne 18 Rammer Compactor / Vibrator 80 Kg. 19 a) Roller compactor / Vibrator 4 Tonne 10 Tonne 20 Form Vibrator 0.4 Kw 21 Poker Vibrator Plant including 25, 32, 50 mm poker 0.4 Kw a) Diesel Generator c) - Ditto - d) - Ditto - a) Portable Air Compressor including rock Breakers & Hammers a) Submersible Pump c) - Ditto - a) Portable self priming engine driven Centrifugal diesel pump c) - Ditto - Spray painting Equipment a) Portable Welding Plant including Welding rods 500 A b) Oxy-Acetylene Welding Set including welding rods 1 kva 5 kva 25 kva 60 kva 175 cfm 300 cfm 1 HP 3 HP 7 HP 50 mm 60 mm 75 mm Bar Cutting / Bending Machine a) Concrete Mixer Asphalt Cutter with diamond disc Pipe Cutter / Grinder including Cutting Wheels Butt fusion PE pipe welding plant Electro fusion PE welding plant 0.3 Cum. 1.4 Cum. UNOPS SDOC AN- III - 17

Improvements to the Distribution Pipe Lines in Zalengi, Central Darfur Please insert the currency Item Description

Improvements to the Distribution Pipe Lines in Zalengi, Central Darfur Please insert the currency Item Description RETURNABLE BID SCHEDULE 4 BILL OF QUANTITIES Case No. SDPC/76613/WORKS/ITB056 Improvements to the Distribution Pipe Lines in Zalengi, Central Darfur Please insert the currency 1 General 1 Mobilization

More information

ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE...

ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE... ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL... 3 2. DESCRIPTION OF ITEMS... 5 3. PRICES TO BE FULLY INCLUSIVE... 5 4. COVERAGE... 6 5. BIDDER TO PRICE EACH ITEM... 6 6.

More information

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. Beit Hanoun Emergency Water Supply Project "Beit Hanoun Emergency Water Supply Project" " Rehabilitation and Construction of Beit Hanoun Water Network " BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE Bill of Quantities PREAMBLE TO

More information

Price Schedule 1 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE COVERAGE BIDDER TO PRICE EACH ITEM...

Price Schedule 1 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE COVERAGE BIDDER TO PRICE EACH ITEM... Price Schedule 1 1. GENERAL... 3 2. DESCRIPTION OF ITEMS... 5 3. PRICES TO BE FULLY INCLUSIVE... 5 4. COVERAGE... 6 5. BIDDER TO PRICE EACH ITEM... 6 6. DESCRIPANCIES BETWEEN RATES... 6 7. MEASUREMENT...

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) PAL 10-92895 - Emergency Removal and Crushing of Rubble and Debris Management Lot # 10: Site Preparation and Crushing of Concrete Rubble Bill of Quantity (BOQ) Bill of Quantity (BOQ) ITB 2015-039 PREAMBLE

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Item No. Description Unit Quantity Rate (EUR) Amount (EUR) No 2

Item No. Description Unit Quantity Rate (EUR) Amount (EUR) No 2 BILL NO.1 : PRELIMINARY AND SUPERVISORY SERVICES 1.01 Allow a prime cost sum for material testing to be spent in whole or part as directed by the Resident Engineer. PC Sum 1 1,351.35 1,351.35 1.02 Contractor's

More information

CONSTRUCTION SPECIFICATION FOR TUNNELLING

CONSTRUCTION SPECIFICATION FOR TUNNELLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 415 FEBRUARY 1990 CONSTRUCTION SPECIFICATION FOR TUNNELLING 415.01 SCOPE 415.02 REFERENCES 415.03 DEFINITIONS TABLE OF CONTENTS 415.04 SUBMISSION AND

More information

Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA TMWA Capital Project No.: October 3, 2018

Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA TMWA Capital Project No.: October 3, 2018 Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA-2019-004 TMWA Capital Project No.: 10-0001.053 October 3, 2018 The following information, clarifications, changes and modifications are by reference

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

General Maintenance (Contract Name) Transit Contract No.(Number)

General Maintenance (Contract Name) Transit Contract No.(Number) General Maintenance (Contract Name) Transit Contract No.(Number) Contract Number & Name Page SP 1 SM032 App B2 Issue 4: 1 March 2005 Schedule of Prices Schedule of Prices Item Description Quantity Unit

More information

Bill No.1: Preliminaries

Bill No.1: Preliminaries Bill No.1: Preliminaries Item No. Description of Works Qty. 1 Mobilization 1.1 This item should include site office for the use of the Engineer's and Employer's staffs with the necessary facilities, furniture,

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Programme of Assistance to the Palestinian People UXOs and Rubble Removal from Gaza Strip Removal of Residential and public Debris from North Governorate (Package 7)

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) Emergency Removal and Crushing of Rubble and Debris Management PAL 10-92895 Lot # 13: Rubble Removal from Different Locations of Gaza Governorates Bill of Quantity (BOQ) Bill of Quantity (BOQ) PREAMBLE

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY D DEMOLITION & SITE CLEARANCE D1 GENERAL CLEARANCE 6-D152 Open bush and thicket in and around ha 0.02 the ponds. Locally disposed. D2 REMOVAL OF TREES AND STUMPS 6-D212 Trees of girth: 150 mm - 500 mm

More information

January 2008 No. 700

January 2008 No. 700 January 2008 No. 700 INDEX FOR SPECIFICATIONS FOR GRANULAR BASE COURSE Page 700. 1 SCOPE...1 1.1 Pre-Construction Meeting...1 1.2 Mobilization of Equipment...1 700. 3 MATERIALS 3.1 Granular Base Course

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES

More information

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract

More information

July Bill No.1: Preliminaries

July Bill No.1: Preliminaries Bill No.1: Preliminaries 1 Mobilization 1.1 This item should include site office for the use of the Engineer's and Employer's staffs with the necessary facilities, furniture, computers, printers, photocopier,

More information

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.

More information

CONSTRUCTION AND REHABILITATION OF FENCE AT GPL'S VERSAILLES COMPOUND

CONSTRUCTION AND REHABILITATION OF FENCE AT GPL'S VERSAILLES COMPOUND BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg, Georgetown. 1.2 Engineer The Engineer

More information

Estimate FOR THE SEPTIC TANK

Estimate FOR THE SEPTIC TANK Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Construction Salah El Deen Road Median From Al Zawaida entrance to Al Maghazi Northern entrance PAL 10-00071488 Bill of Quantity (BOQ) PREAMBLE TO BILL OF QUANTITY (BOQ)

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES

More information

CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS

CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS October 1990 CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS 1. GENERAL CONDITIONS...1 3. DESCRIPTION...1 5. MATERIALS...1 5.1 General...1 5.2 Testing and Approval...1 5.3 Irrigation Pipe and Fittings...1

More information

SECTION WATER DISTRIBUTION SYSTEM

SECTION WATER DISTRIBUTION SYSTEM Conditions of Use/ Responsibility of Data Montgomery County Public Schools Facilities Guide DIVISION 2 - SITE WORK These guideline specifications are to be used by the A/E as a base document in the development

More information

DEVELOPMENT OF MANGROL FISHERY HARBOUR -PHASE-III Part-A

DEVELOPMENT OF MANGROL FISHERY HARBOUR -PHASE-III Part-A 1 DEVELOPMENT OF MANGROL FISHERY HARBOUR -PHASE-III Part-A VOLUME-II PRICE BID Downloading of tender documents (Start Date): Dt 30/05/2017 from 11.00 hrs. On line submission of tender (End Date): Dt. 01/07/2017

More information

REPUBLIC OF LEBANON MINISTRY OF ENERGY AND WATER UNITED NATIONS DEVELOPMENT

REPUBLIC OF LEBANON MINISTRY OF ENERGY AND WATER UNITED NATIONS DEVELOPMENT REPUBLIC OF LEBANON MINISTRY OF ENERGY AND WATER UNITED NATIONS DEVELOPMENT PROGRAMME FEASIBILITY ASSESSMENT AND DESIGN OF A WASTEWATER MANAGEMENT SYSTEM IN AL AMAYER-WADI KHALED (KNAISSE VILLAGE) VOLUME

More information

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2 Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2 PARTICULAR SPECIFICATIONS FOR THE CONSTRUCITON OF STORM WATER DRAINAGE NETWORK March 2018 BUREAU TECHNIQUE POUR LE DEVELOPPEMENT P.O.B

More information

TABLE OF CONTENTS. Chapter 3 - WATER MAIN, VALVES, HYDRANTS AND APPURTENANCES. Chapter 4 - SANITARY SEWER. Chapter 5 - STORM SEWER

TABLE OF CONTENTS. Chapter 3 - WATER MAIN, VALVES, HYDRANTS AND APPURTENANCES. Chapter 4 - SANITARY SEWER. Chapter 5 - STORM SEWER Chapter 3 - WATER MAIN, VALVES, HYDRANTS AND APPURTENANCES Chapter 4 - SANITARY SEWER Chapter 5 - STORM SEWER Chapter 6 - EXCAVATION, TRENCING, BACKFILLING, AND BEDDING Chapter 11 - CONCRETE CURBS, CURB

More information

Description Unit Quantity Rate Kshs. Amount Kshs.

Description Unit Quantity Rate Kshs. Amount Kshs. BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Rehabilitation of Tunis & Omer Bin Abdel Aziz Sidewalks PAL 10-71488 : UXOs and Rubble Removal From Gaza Strip Bill of Quantity (BOQ) PREAMBLE TO BILL OF QUANTITY (BOQ)

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS UTILITY LINE INSTALLATION REQUIREMENTS Index 26.01 JACK AND BORE OPERATIONS 26.02 PRESSURE PIPE RESTRAINT 26.03 PRESSURE CONNECTION BACK TO TABLE OF CONTENTS Section 26.01 JACK AND BORE OPERATIONS 26.01.01

More information

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices. SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section

More information

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO.

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. 2017-1 43 SOUTH GRANVILLE WATER AND SEWER AUTHORITY H STREET BY-PASS

More information

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 PART 1 - GENERAL... 2 1.1 Work Included... 2 1.2 Related Sections... 2 1.3 Reference Standards... 2 1.4 Shop Drawings... 3 1.5 Certificates...

More information

Contract Identification No. and Package 1. SUHEP-067/68-Lot No.1-AR: Package B 2. SUHEP-067/68-Lot No.1-AR: Package C

Contract Identification No. and Package 1. SUHEP-067/68-Lot No.1-AR: Package B 2. SUHEP-067/68-Lot No.1-AR: Package C Notice of Amendment No.1 Addendum No.1 to the following Contract Packages has been made in the Bids, for which the first date notice was published in the Gorkhapatra daily on December 14, 2010 by Sanjen

More information

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 7

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 7 September 2013 Page 1 of 7 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of a wetwell as shown on the Plans and in accordance with Section 01001,

More information

Section 3 Tender Submission Package Pricing Form Tender Call No Contract No.18SC-120TE Emergency Repairs

Section 3 Tender Submission Package Pricing Form Tender Call No Contract No.18SC-120TE Emergency Repairs 1 of 8 The Bidder must provide the rate and the amount for each tender item, the total for each part / subsection, the grand total, HST amount and the total amount of tender on the forms in the ensuing

More information

Each Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal.

Each Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal. ACKNOWLEDGEMENT BY RESPONDENT Each Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal. This undersigned acknowledges receipt of this Addendum No. 1

More information

***************************************************************************************************************

*************************************************************************************************************** 02732 SANITARY FORCE MAIN *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 34 00. ***************************************************************************************************************

More information

1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service connections.

1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service connections. Issued 2005/06/01 Section 02511 Water Mains Page 1 of 10 PART 1 GENERAL 1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document

More information

DUCTILE IRON PIPES AND FITTINGS DETAILED PRODUCTS SPECIFICATIONS

DUCTILE IRON PIPES AND FITTINGS DETAILED PRODUCTS SPECIFICATIONS DUCTILE IRON PIPES AND FITTINGS DETAILED PRODUCTS SPECIFICATIONS General All Materials shall be EN, ISO or equivalent standard and shall be supplied from approved manufacturers. According to the International

More information

CONSTRUCTION SPECIFICATION FOR NEW MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION

CONSTRUCTION SPECIFICATION FOR NEW MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 407 NOVEMBER 2015 CONSTRUCTION SPECIFICATION FOR NEW MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION TABLE OF CONTENTS 407.01

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Engineer. 812.2 MATERIALS: The

More information

FORM OF TENDER RITHET RESERVOIR DRAIN PROJECT ( TITLE OF CONTRACT ) T 34/16 ( OWNER S CONTRACT REFERENCE NO. )

FORM OF TENDER RITHET RESERVOIR DRAIN PROJECT ( TITLE OF CONTRACT ) T 34/16 ( OWNER S CONTRACT REFERENCE NO. ) PAGE 1 OF 6 FOR USE WHEN UNIT S FORM THE BASIS OF PAYMENT - TO BE USED ONLY WITH THE GENERAL CONDITIONS AND OTHER STANDARD DOCUMENTS OF THE UNIT MASTER MUNICIPAL CONSTRUCTION DOCUMENTS. Owner: Contract:

More information

Construction Price Survey Form

Construction Price Survey Form International Comparison Program [04.05] Construction Price Survey Form 3 rd Regional Coordinators Meeting October 21-22, 2010 Washington DC Table of Contents 1. Form... 3 2. Purpose of the survey... 3

More information

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section 02540-1 of 10 SECTION 02540 STORM DRAIN REHABILITATION 02540.01 GENERAL A. Description Storm drain rehabilitation shall include, but not necessarily be limited to, pipe joint sealing, inlet and manhole

More information

REHABILITATION OF DRIVEWAY AND GROUND FLOOR OF THE SECOND BUILDING AT MIDDLE STREET OFFICE

REHABILITATION OF DRIVEWAY AND GROUND FLOOR OF THE SECOND BUILDING AT MIDDLE STREET OFFICE BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg, Georgetown. 1.2 Engineer The Engineer

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

Special Provision No. 421F01 April 2006

Special Provision No. 421F01 April 2006 RIGID PIPE CULVERTS Item No. FLEXIBLE PIPE CULVERTS Item No. CSP ARCH CULVERTS Item No. STRUCTURAL PLATE CSP Item No. CORRUGATED STEEL PIPE EXTENSIONS Item No. ROCK EXCAVATION FOR CULVERTS Item No. CLAY

More information

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer

More information

ITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219.

ITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219. ITEM 461 STRUCTURAL PLATE STRUCTURES 461.1. Description. This Item shall govern for the furnishing and installing of structural plate pipes, pipe arches, arches, underpasses, box culverts and special shapes

More information

Polysewer Gravity Sewer System SPECIFICATION

Polysewer Gravity Sewer System SPECIFICATION Polysewer Gravity Sewer System SPECIFICATION July 2014 SCOPE OF WORKS To meet the specific performance criteria detailed within this specification and accompanying drawings. The completed drainage systems

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 012000 Applies only to Collier County Public Utilities Projects or Works and Utilities Portions of Collier County Transportation Projects, but not to Private Developments PART 1 GENERAL 1.1 SECTION

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 616 APRIL 2018 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03 DEFINITIONS

More information

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete. SECTION 02720 STORM DRAINAGE SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02221 - Excavating, Backfilling, and Compaction for Utilities. 2. 03300 - Cast-in-place Concrete. 1.02 REFERENCES

More information

CONSTRUCTION SPECIFICATION FOR POLE ERECTION

CONSTRUCTION SPECIFICATION FOR POLE ERECTION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 615 SEPTEMBER 1993 CONSTRUCTION SPECIFICATION FOR POLE ERECTION 615.01 SCOPE 615.02 REFERENCES 615.05 MATERIALS TABLE OF CONTENTS 615.05.01 Concrete.02

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 616 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03

More information

SCHEDULE OF RATES. WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT

SCHEDULE OF RATES. WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT WORK : External Waterproofing for Basement at Dena Bank, Kandivali Branch SCHEDULE OF RATES SR NO PARTICULARS UNIT QUANTITY RATE AMOUNT 1 Excavation for foundation in earth all types of soils like clay,

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

Amendment -1. Date: NIT No. RECPDCL/CSR/CWC/ /3368 dt:

Amendment -1. Date: NIT No. RECPDCL/CSR/CWC/ /3368 dt: Amendment -1 Date: 17.02.2017 NIT No. RECPDCL/CSR/CWC/2016-17/3368 dt: 20.01.2017 Notice Inviting Tender (Bid Invited through e Tendering mode only) From Implementing Agencies for Turnkey execution of

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 21 11 10 PART 1. GENERAL 1.1 SUMMARY: A. Work consists of furnishing and installing new fire hydrants, (boot with ductile iron retainer gland, standpipe and hydrant complete) plus constructing

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the

More information

APPENDIX A MEASUREMENT AND PAYMENT

APPENDIX A MEASUREMENT AND PAYMENT P-150 DEMOLITION 4.01 Removal of pavement shall be measured per square yard based on the area shown on the plans. Any pavement removed outside the designed limits of removal because the pavement was damaged

More information

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items: ITEM 431 PNEUMATICALLY PLACED CONCRETE 431.1. Description. This Item shall govern for furnishing and placing of "Pneumatically Placed Concrete" for encasement of designated structural steel members, the

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

ITEM No. D E S C R I P T I O N UNIT QTY. 5-E343.2 In class III material m³ 1,260 - Max. Depth: m For disposal

ITEM No. D E S C R I P T I O N UNIT QTY. 5-E343.2 In class III material m³ 1,260 - Max. Depth: m For disposal EARTHWORKS Excavation for foundations 5E343.2 In class III material m³ 1,260 Max. Depth: 0.50 1 m For disposal 5E334.2 In class III material m³ 720 Max. Depth: 1 2 m For disposal Filling Ancillaries 5E723.0

More information

FABRICATION OF A NEW INDUCED DRAUGHT FAN DUCTING KILN 2

FABRICATION OF A NEW INDUCED DRAUGHT FAN DUCTING KILN 2 FABRICATION OF A NEW INDUCED DRAUGHT FAN DUCTING KILN 2 SITE INFORMATION The tenderer should, in his own interest, visit the site and familiarize with the site conditions before tendering. For any clarification,

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

CONSTRUCTION SPECIFICATION FOR CEMENT MORTAR LINING OF WATERMAINS

CONSTRUCTION SPECIFICATION FOR CEMENT MORTAR LINING OF WATERMAINS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 462 NOVEMBER 2009 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR CEMENT MORTAR LINING OF WATERMAINS TABLE OF CONTENTS 462.01 SCOPE 462.02

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS)

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) 00950 - Measurement & Payment Page 00950-1 00950 - MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) (Last revised 5/20/10) SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Base Course & Paving Curb & Gutter,

More information

CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES

CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 615 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES TABLE OF CONTENTS 615.01 SCOPE 615.02 REFERENCES 615.03 DEFINITIONS - Not Used 615.04

More information

CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES

CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 615 NOVEMBER 2008 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES TABLE OF CONTENTS 615.01 SCOPE 615.02 REFERENCES 615.03

More information

SOR FOR PILE FOUNDATION WORKS FOR TANKAGE & ENGINEERING STORE

SOR FOR PILE FOUNDATION WORKS FOR TANKAGE & ENGINEERING STORE SOR FOR PILE FOUNDATION WORKS FOR TANKAGE & ENGINEERING STORE S.NO Description Unit Total Qty EARTH WORK EXCAVATION : Earthwork in excavation at all depths for foundation, pile cap,drain, ramp,pits, etc.,

More information

1 Revised: 2019 Edition

1 Revised: 2019 Edition STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with

More information

Name of work Estimated cost Time allowed for completion of work 1. Construction of PVC coated Chain Link fencing at Megapode Resort. Sl. No.

Name of work Estimated cost Time allowed for completion of work 1. Construction of PVC coated Chain Link fencing at Megapode Resort. Sl. No. The Andaman & Nicobar Islands Integrated Development Corporation Ltd, Vikas Bhawan, Post Box. No.180, Port Blair 744 101 Phone: 232098 Fax 03192-240615 F.No. 7-37/ANIIDCO/95/1231/2018 Dated the 16 th April

More information

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS TABLE OF CONTENTS 11.01 SCOPE OF WORK... 1 11.02 REFERENCES... 1 11.03 MATERIALS... 2 11.04 GRANULAR & NATIVE BACKFILL... 2 11.05 CONSTRUCTION... 2 11.06 MEASUREMENT FOR PAYMENT... 5 11.07 BASIS OF PAYMENT...

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

Item 460 Corrugated Metal Pipe

Item 460 Corrugated Metal Pipe Item 460 Corrugated Metal Pipe 1. DESCRIPTION 2. MATERIALS Furnish and install corrugated metal pipes, materials for constructing corrugated metal pipe culverts, or corrugated metal storm drain mains,

More information

SECTION STORM DRAIN

SECTION STORM DRAIN PART 1 - GENERAL 1-01 SECTION INCLUDED A. Furnishing and installing storm drainage facilities, including pipe, cleanout, manhole structures and inlet structures. 1-02 RELATED SECTIONS A. Division 00 Contract

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information